rotating machines erection guidelines

Upload: sbmmla

Post on 17-Oct-2015

117 views

Category:

Documents


17 download

DESCRIPTION

erection procedure of rotating machineries

TRANSCRIPT

  • Originator ALSTOM POWER SYSTEMS S.A..

    Alstom Identification number TJN/40/M/----- -----/EG/013

    Rev. A

    Date 04.04.2013

    Lang. En

    Sheet 2/18

    Owners dwg number T4-APD-B0-A-40104

    Rev A

    ALSTOM 2013. All rights reserved.

    Table of Contents:

    1. Objective ........................................................................................................................................................... 4 2. General requirements ..................................................................................................................................... 4

    2.1. Logic diagram of operations .............................................................................................................................. 4 2.2. Reference documents ....................................................................................................................................... 6 2.3. General requirements concerning works ......................................................................................................... 6

    3. Basement level preparation ........................................................................................................................... 6 3.1. Basement level inspection for erection purposes ............................................................................................ 6 3.2. Concrete basement level preparation .............................................................................................................. 6 3.3. Metal basement level preparation .................................................................................................................... 7

    4. Installation ........................................................................................................................................................ 7 4.1. General ............................................................................................................................................................... 7 4.2. Installation tolerances ........................................................................................................................................ 7

    5. Wedging ............................................................................................................................................................ 7 6. Alignment .......................................................................................................................................................... 8

    6.1. Alignment chronology ........................................................................................................................................ 8 6.2. Execution of alignment ...................................................................................................................................... 8 6.3. Allowable alignment tolerances ........................................................................................................................ 8

    7. Tightening of anchor pieces .......................................................................................................................... 9 8. Piping connection ......................................................................................................................................... 10

    8.1. Erection of pipes .............................................................................................................................................. 10 8.2. Jointing ............................................................................................................................................................. 10 8.3. Connection of the main pipes ......................................................................................................................... 10

    9. Inspections ..................................................................................................................................................... 11 9.1. Inspections of the basement level "for erection" ............................................................................................ 11 9.2. Equipment installation inspection ................................................................................................................... 11 9.3. Alignment checking before jointing of pipes ................................................................................................... 12 9.4. Checking of main pipes jointing ...................................................................................................................... 12 9.5. Alignment checking after piping connection................................................................................................... 12 9.6. Alignment checking after final setting of pipe elastic supports ...................................................................... 12 9.7. Checking of auxiliary mechanical equipment erection .................................................................................. 12 9.8. Checking of instrumentation and control installation ..................................................................................... 12 9.9. Miscellaneous .................................................................................................................................................. 12

    10. Attachment 1: Alignment of rotating machines ........................................................................................ 12 10.1. Measuring instruments .................................................................................................................................... 12 10.2. Alignment procedures ..................................................................................................................................... 13 10.3. Marking of the reference points ...................................................................................................................... 13 10.4. Adjustment of the distance between shaft ends ............................................................................................ 14 10.5. Adjustment of parallelism ................................................................................................................................ 14 10.6. Adjustment of concentricity ............................................................................................................................. 16

  • Originator ALSTOM POWER SYSTEMS S.A..

    Alstom Identification number TJN/40/M/----- -----/EG/013

    Rev. A

    Date 04.04.2013

    Lang. En

    Sheet 3/18

    Owners dwg number T4-APD-B0-A-40104

    Rev A

    ALSTOM 2013. All rights reserved.

    11. Attachment 2: Calculation of tolerances for semi-flexible coupling ..................................................... 18 11.1. Calculation of speed factor (Fv) values .......................................................................................................... 18

  • Originator ALSTOM POWER SYSTEMS S.A..

    Alstom Identification number TJN/40/M/----- -----/EG/013

    Rev. A

    Date 04.04.2013

    Lang. En

    Sheet 4/18

    Owners dwg number T4-APD-B0-A-40104

    Rev A

    ALSTOM 2013. All rights reserved.

    1. OBJECTIVE

    The present document collects the general recommendations and/or requirements concerning the erection of rotating machines and particularly:

    motor-driven feedwater pumps miscellaneous motor-driven pumps Given the wide range and diverse nature of the equipment concerned and especially the particular requirements relating to some major components (such as feedwater pumps) the present document can be amended or completed by specific rules mentioned in the Erection Instructions (EI) and/or Erection Quality Control Plan (EQ).

    2. GENERAL REQUIREMENTS

    2.1. Logic diagram of operations

    The extent of the works and inspections to be performed for erection of rotating machines is shown by the following logic principle diagram:

  • Originator ALSTOM POWER SYSTEMS S.A..

    Alstom Identification number TJN/40/M/----- -----/EG/013

    Rev. A

    Date 04.04.2013

    Lang. En

    Sheet 5/18

    Owners dwg number T4-APD-B0-A-40104

    Rev A

    ALSTOM 2013. All rights reserved.

    Miscellaneous mechanical

    Inspection of basement

    Placing of equipment

    level for erectionPreparation of basement level

    machines not arranged on a

    Alignment checking after main

    (coolers, pipes, ...)

    Prealignment of the rotating

    Main piping connections

    Installation of instrumentation

    common frame

    "Equipment location" inspection

    Alignment with anchor boltstightened to their rated torque

    jointing

    Jointing of main piping

    Alignment checking after final adjustment of the elastic

    Installation of auxiliarymechanical equipment

    Alignment checking prior to pipe

    Checking of main piping jointing

    piping connection

    Final adjustment of the elasticsupports of the main piping

    equipment erection checking

    and control equipmentInstrumentation and controlequipment erection checking

    supports of main piping

    X

    X

    Grouting

  • Originator ALSTOM POWER SYSTEMS S.A..

    Alstom Identification number TJN/40/M/----- -----/EG/013

    Rev. A

    Date 04.04.2013

    Lang. En

    Sheet 6/18

    Owners dwg number T4-APD-B0-A-40104

    Rev A

    ALSTOM 2013. All rights reserved.

    2.2. Reference documents

    The basic documents at the Erection Subcontractor's disposal are:

    The civil works conformance report relating to basement level. The tolerances allowed for civil works execution (Erection Standard: EG 101) The equipment manufacturing drawing. The general arrangement drawing (GA) or the piping arrangement drawing (PA). The list of equipment and accessories for the equipment concerned and the corresponding

    warehouse issue slip.

    The erection instruction (EI) with erection drawings and documents. The erection quality control plan (EQ).

    2.3. General requirements concerning works

    The access and erection areas must be kept tidy and clean.

    During erection, all necessary steps shall be taken to protect the surrounding equipment and the equipment waiting for erection.

    3. BASEMENT LEVEL PREPARATION

    3.1. Basement level inspection for erection purposes

    The Erection Subcontractor performs the following operations:

    Materialization on the basement level: - of the theoretical equipment installation axes - of a reference level.

    Checking of: - location with regard to the theoretical axes - basement level geometry - surface conditions of basement level and anchor holes - location of anchor bars in anchor holes - visuel examination of foundations to search for apparent construction and erection defects

    and faults (cracks, deformations, assembly of metal foundations, ...).

    Once these inspections have been performed, the Erection Subcontractor:

    gives his inspection report stamped "issued for erection" or transmits his observations with request for bringing the basement level to its final form (civil

    works basement or metal support)

    or proposes a new installation. 3.2. Concrete basement level preparation

    Careful concrete surfacing at the shims

    Checking of dimensions, flatness and horizontality of the supports thus arranged.

  • Originator ALSTOM POWER SYSTEMS S.A..

    Alstom Identification number TJN/40/M/----- -----/EG/013

    Rev. A

    Date 04.04.2013

    Lang. En

    Sheet 7/18

    Owners dwg number T4-APD-B0-A-40104

    Rev A

    ALSTOM 2013. All rights reserved.

    3.3. Metal basement level preparation

    Cleaning of basement levels

    Elimination of the defects caused by any possible damage (shocks for instance).

    4. INSTALLATION

    4.1. General

    Rotating machines can be delivered:

    on rigid frames, mounted and set in workshop in separate elements with shaft line to be assembled on Site. Refer to the relevant Erection Instruction (EI) for:

    location and orientation special instructions Equipment must be installed with respect to the theoretical reference axes of the installation building or area.

    4.2. Installation tolerances

    Tolerances to be adopted unless stated otherwise in the Erection Instruction (EI) concerned:

    Installation with respect to the theoretical reference axes: - arrangement : 5 mm - level : 5 mm

    Verticality (perpendicularity deviation) = 0.3 mm per meter Horizontality = 0.3 mm per meter

    5. WEDGING

    Arranged on each side of each anchor bolt, and as close as possible to the anchor holes (or bolts in case of metal foundations)

    Wedging height on concrete foundations: above 30 mm

    Reduce to the minimum the number of wedges to be stacked while respecting the stipulated height

    The wedges shall be dimensioned (length x width) as specified on the documents attached to the construction package cleaned and burred.

    The temporary wedges (screws jacks for instance) provided to make final wedging easier, must imperatively be removed before the anchor bolts are tightened to their rated torque.

    The jacks-wedges definitely embedded in grouting mortar shall be blocked by tack-welds after the last alignment checking and before the grouting mortar is poured.

  • Originator ALSTOM POWER SYSTEMS S.A..

    Alstom Identification number TJN/40/M/----- -----/EG/013

    Rev. A

    Date 04.04.2013

    Lang. En

    Sheet 8/18

    Owners dwg number T4-APD-B0-A-40104

    Rev A

    ALSTOM 2013. All rights reserved.

    6. ALIGNMENT

    6.1. Alignment chronology

    Considering the type of the machine, all or some of the following alignments must be carried out.

    Prealignment: only for the machines not installed on a common frame. Alignment prior to pipe jointing:

    - before pouring the grouting and wedging mortars - after tightening of the anchor bolts to their rated torque.

    Alignment after pipe connection Alignment after final adjustment of the elastic supports of the main pipes.

    6.2. Execution of alignment

    Alignment comprises 3 types of operation:

    adjustment of the distance between shaft ends or coupling plates, axial positioning of axes, radial positioning of axes. Appendix 1 details a method for aligning 2 axes.

    Alignment is performed with "cold machines"

    The cold position of shafts is defined in the relevant Erection Instructions (EI), when the shaft deformations and displacements affect the alignment.

    NOTE: For spring mounted foundations ; shaft alignment is not affected by loading and adjustment of spring supports. Nevertheless it is recommended that the couplings stay open during these operations for control measurement.

    6.3. Allowable alignment tolerances

    Unless stated otherwise in the Manufacturer's drawing or Erection Instructions (EI), the tolerances are as follows:

    Semi-flexible couplings with rubber inserts

    For the same coupling, the allowable tolerances vary with the rotation speed.

    The alignment is satisfactory if the 3 following conditions are met:

    Parallelism: maxi angle difference (EA) = 16 Fv Od/10000 Concentricity: maxi radius difference (ER) = 16 Fv Od/10000 Maxi (EA + ER) = 16 Fv Od/10000 Where Fv is the speed factor calculated by means of the abacus of Appendix 2, Od is the outside diameter of the half coupling.

    Rigid couplings

  • Originator ALSTOM POWER SYSTEMS S.A..

    Alstom Identification number TJN/40/M/----- -----/EG/013

    Rev. A

    Date 04.04.2013

    Lang. En

    Sheet 9/18

    Owners dwg number T4-APD-B0-A-40104

    Rev A

    ALSTOM 2013. All rights reserved.

    Parallelism : 0.01 mm max. on a diameter of 100 mm (i.e 1/10000) Concentricity : 0.02 mm max. Flexible couplings

    Parallelism : 0.05 mm max on a diameter of 100 mm (i.e 5/10000) Concentricity : 0.20 mm Tooth couplings

    Parallelism - Max.: 0.025 mm for n = 1 800 rpm max. on a diameter of 100 mm (i.e 2.5/10000) - Min. : 0.015 mm for n > 1 800 rpm on a diameter of 100 mm (i.e 1.5/10000)

    where n = number of revolutions per minute.

    Concentricity (tolerance in event of misalignment): - Max.: 0.05 mm for n = 1 800 rpm max. - Min.: 0.03 mm for n > 1 800 rpm.

    Clearance between the coupling hubs: 0.5 mm

    NOTE: Before measuring the clearance between hubs, make sure that:

    The possible axial rotor locking device has in fact been removed, The free rotor of an electric motor is in the correct position with a 0.3 mm tolerance.

    7. TIGHTENING OF ANCHOR PIECES

    Nuts: mounted lubricated

    Tightening torque to be adopted tolerances 5 % if the erection instruction (EI) or its appendices specify no special value.

    bolt mm 14 16 18 20 22 24 27 30 33 36

    Torque value m daN 3,5 5,5 7,5 10,5 14 18,5 27 33,5 50 64

    Tighten all anchor bolts progressively.

  • Originator ALSTOM POWER SYSTEMS S.A..

    Alstom Identification number TJN/40/M/----- -----/EG/013

    Rev. A

    Date 04.04.2013

    Lang. En

    Sheet 10/18

    Owners dwg number T4-APD-B0-A-40104

    Rev A

    ALSTOM 2013. All rights reserved.

    8. PIPING CONNECTION

    8.1. Erection of pipes

    The pipes absolutely must be erected by starting from the fixed point of the piping so as to end in the machine pipe. In no case shall erection be started by fixing the piping onto the machine.

    When designing the piping execution and prefabrication, extra-lengths are to be provided so as to adjust the pipe sections arranged as close as possible to the machine in the 3 planes.

    8.2. Jointing

    Before beginning any jointing operation, check that the protecting covers have in fact been placed on the machine pipes to prevent any foreign matter from entering the machine.

    Jointing is satisfactory only if:

    All the welds on the piping jointed to the machine are made (up to the first fixed point support, at least)

    All hangers between the fixed point and the machine are free and set on "cold piping" position, in conformity with the instructions shown on the supports drawings

    The flange facings are parallel and centered, taking account of the tolerances given hereafter. The clearance between the flange facings complies with the type of connection to be made

    (flanges or welds)

    Flange-type jointing

    During the checking of the jointing, the flange/pipe weld must be totally carried out and checked. Unless specified otherwise in the erection instruction (EI), the preliminary connection tolerances

    to be complied with are the following: - Parallelism : < 0.1 mm for pipe < 12"

    < 0.3 mm for pipe 12" < < 24" < 0.5 mm for pipe > 24"

    - Concentricity : The flange fixing bolts must be put into place manually without forcing and particularly without applying any load or thrust on the pipe whatsoever.

    Weld-type

    The preliminary connection tolerances are those applying to butt-welding and specified in the Piping Welding Standards or in the relevant Erection Instructions (EI).

    8.3. Connection of the main pipes

    Before connection check that the piping preliminary connection complies with the instructions specified in item 82,

    To prevent any risk of electric striking between the various machine internals during the welding operations, make sure that:

    The grounding terminal is well connected to the general grounding circuit of the Power Plant The grounding connector is well fastened to the machine frame. Welds are made in conformity with the Piping Welding Rules. The machine-to-pipe heterogeneous welding processes shall be specified in the Erection Instructions (EI).

  • Originator ALSTOM POWER SYSTEMS S.A..

    Alstom Identification number TJN/40/M/----- -----/EG/013

    Rev. A

    Date 04.04.2013

    Lang. En

    Sheet 11/18

    Owners dwg number T4-APD-B0-A-40104

    Rev A

    ALSTOM 2013. All rights reserved.

    For connections by welded joints:

    Realize only one joint at a time on the same shaft line Check the alignment before proceeding to any welded connection of main pipes Take all necessary arrangements to prevent any deformations of the machine, e.g. realize the

    weld according to the method of the "Quarters opposite" to 2 welders

    Make sure that the machine has not undergone any deformation during welding, so that the adequate measures can be taken as soon as a deformation is detected.

    The inspection points specific to the machine are defined in the erection instruction (EI). The corrective actions selected shall receive the approval of the erection supervision department.

    9. INSPECTIONS

    The following list is not exhaustive. It defines the minimum inspection to be performed by the Erection Subcontractor. In addition to these inspections, the Erection Subcontractor must take all the necessary steps to ensure erection quality.

    The inspections specified hereafter shall be detailed in the Erection Quality Control Plan (EQ) which may be completed or amended by the Erection Instructions (EI).

    9.1. Inspections of the basement level "for erection"

    Visual examination to detect the visible defects

    Layout and materialization of the theoretical equipment axes

    Basement level altitude

    Horizontality of the basement upper part

    Dimensions of the basement(s) (geometry)

    Installation of the basement(s) with respect to the theoretical equipment axes

    Anchoring or fixing holes (number, location, dimensions, installation and location of the anchor bars)

    Chipping of the basement surface.

    9.2. Equipment installation inspection

    Surface conditions, dimensions, flatness, horizontality of base levels for metal wedges

    Position of the theoretical axes of the equipment or of a set of elements connected one to another

    Horizontality and verticality

    Orientation of equipment with respect to the reference axes of the building

    relative position of the machines

    preliminary alignment of the independant machines.

  • Originator ALSTOM POWER SYSTEMS S.A..

    Alstom Identification number TJN/40/M/----- -----/EG/013

    Rev. A

    Date 04.04.2013

    Lang. En

    Sheet 12/18

    Owners dwg number T4-APD-B0-A-40104

    Rev A

    ALSTOM 2013. All rights reserved.

    9.3. Alignment checking before jointing of pipes

    Torque load of anchor bolts

    Alignment.

    9.4. Checking of main pipes jointing

    Erection of pipes up to the first fixed point with setting of supports

    Characteristics of each jointing and in particular:

    Parallelism of flanges Centering of the pipe on the nozzle Clearance between the sides to be assembled.

    9.5. Alignment checking after piping connection

    Checking of connecting welds on machines

    Alignment.

    9.6. Alignment checking after final setting of pipe elastic supports

    Filling of the pipes conveying water

    Complete thermal insulation of pipes

    Unlocking of elastic supports

    Alignment.

    9.7. Checking of auxiliary mechanical equipment erection

    Refer to the Erection Standards relative to the corresponding equipment (fabricated components, piping, ...).

    9.8. Checking of instrumentation and control installation

    Refer to the Construction Data Package for Instrumentation.

    9.9. Miscellaneous

    Protection of the equipment being erected and of the surrounding equipment as well.

    Inner and outer cleanliness of equipment after erection

    10. ATTACHMENT 1: ALIGNMENT OF ROTATING MACHINES

    10.1. Measuring instruments

    Miscellaneous measuring instruments can be used for the alignment operations and, in particular:

    For alignment truing (preliminary alignment): - fitter setting gauge

  • Originator ALSTOM POWER SYSTEMS S.A..

    Alstom Identification number TJN/40/M/----- -----/EG/013

    Rev. A

    Date 04.04.2013

    Lang. En

    Sheet 13/18

    Owners dwg number T4-APD-B0-A-40104

    Rev A

    ALSTOM 2013. All rights reserved.

    - set of adjusting shims

    For alignment: - comparators - set of shims (normal or oblique)

    These instruments are supplied by the Subcontractor charged with realizing or checking the alignment.

    10.2. Alignment procedures

    Alignment is to be ensured by a qualified fitter perfectly familiarized with the usual procedures associated with this king of work.

    Alignment and prealignment include 3 checkings of:

    distance between both shaft ends parallelism concentricity When defining the concentricity corrections, do not forget to take account of the possible shaft line shifting defined in an Appendix to the relevant Erection Instructions (EI).

    Before performing the various alignment measurements, make the machines provided with journal bearings rotate a few turns so as to get an oil film

    The various alignment measurements require the simultaneous rotation of both shafts as if they were connected.

    10.3. Marking of the reference points

    4 fixed points to be marked on the body of one of the machines (12 o'clock,

    3 o'clock, 6 o'clock and 9 o'clock) according to 2 perpendicular axes (one vertical axis and one horizontal axis - see fig. 1 hereafter).

    2 diametrally opposed A and B generatrices to be marked on both half-coupling sleeves (see figure 1 hereafter).

  • Originator ALSTOM POWER SYSTEMS S.A..

    Alstom Identification number TJN/40/M/----- -----/EG/013

    Rev. A

    Date 04.04.2013

    Lang. En

    Sheet 14/18

    Owners dwg number T4-APD-B0-A-40104

    Rev A

    ALSTOM 2013. All rights reserved.

    FIGURE 1

    10.4. Adjustment of the distance between shaft ends

    The distance between the coupling hubs must be adjusted according to the Manufacturer's drawing so as to respect the functional axial clearances.

    Distances shall be checked only after adjustment of the rotors within their respective axial clearances.

    10.5. Adjustment of parallelism

    Use one or two comparators (normal mounting or mounting with return level). If the measurement cannot be made by means of a comparator, sets of shims may, exceptionally, be used.

    Make both machines rotate simultaneously and after each quarter-turn, read the "a" and "b" values at the vertical marks 12 o'clock and 6 o'clock or at the horizontal marks 3 o'clock and 9 o'clock.

    See figures 2, 3 and 4 hereafter, for information.

    FIGURE 2 FIGURE 3 FIGURE 4

  • Originator ALSTOM POWER SYSTEMS S.A..

    Alstom Identification number TJN/40/M/----- -----/EG/013

    Rev. A

    Date 04.04.2013

    Lang. En

    Sheet 15/18

    Owners dwg number T4-APD-B0-A-40104

    Rev A

    ALSTOM 2013. All rights reserved.

    Driven rotor Driving rotor

    D

    Driven rotor Driving rotor

    D

    12 o'clock

    9 o'clock 3 o'clock

    6 o'clock

    a

    b

    Calculate the average of the "a" and "b" values at the 12 o'clock, 3 o'clock, 6 o'clock and 9 o'clock points.

    See figure 5 hereafter, for information.

    FIGURE 5

    12 o'clock a = 5.00b = 8.00 Average = 6.5 mm

    9 o'clock 3 o'clock

    6 o'clock

    a = 6.75a = 6.25

    a = 7.00

    b = 7.25 b = 3.75

    b = 6.00

    Average = 6.75 mm Average = 5.25 mm

    Average = 6.5 mm

    This example points out that the "a" and "b" measurements made at the same place are not identical. This is of minor importance for the measurement interpretation as an average of both these values is made.

    Interpret these averages. The difference between both averages of points facing one another (either vertically or horizontally) gives the parallelism differences.

    See figures 6 and 7 hereafter, for information.

    FIGURE 6 FIGURE 7

    12 o'clock

    6 o'clock Difference : 0

    Difference : 0

    9 o'clock 3 o'clock

    Difference : + 0.5 mm Difference : 0

    In this example, it will be observed that:

  • Originator ALSTOM POWER SYSTEMS S.A..

    Alstom Identification number TJN/40/M/----- -----/EG/013

    Rev. A

    Date 04.04.2013

    Lang. En

    Sheet 16/18

    Owners dwg number T4-APD-B0-A-40104

    Rev A

    ALSTOM 2013. All rights reserved.

    Parallelism is correct in the vertical plane Parallelism is defective (0.5 mm clearance on 9 o'clock side) in the horizontal plane. The parallelism differences must be less than those allowed for this machine.

    Otherwise, corrections shall be made util acceptable values are reached.

    In the example mentioned above, one of the machines is to be moved in the horizontal plane for:

    Decreasing the 0.5 mm measure at 9 o'clock Increasing the 0.5 mm measure at 3 o'clock.

    10.6. Adjustment of concentricity

    The comparator is to be arranged on the generatrix marked A.

    Make the machines rotate simultaneously and after each quarter-turn, read the "c" value at the 12 o'clock and 6 o'clock vertical marks and at the 3 o'clock and 9 o'clock horizontal marks.

    See figures 8, 9 and 10 hereafter for information.

    FIGURE 8 FIGURE 9 FIGURE 10

    C

    C

    12 o'clock

    9 o'clock 3 o'clock

    6 o'clock

  • Originator ALSTOM POWER SYSTEMS S.A..

    Alstom Identification number TJN/40/M/----- -----/EG/013

    Rev. A

    Date 04.04.2013

    Lang. En

    Sheet 17/18

    Owners dwg number T4-APD-B0-A-40104

    Rev A

    ALSTOM 2013. All rights reserved.

    Interpret these measurements

    See figures 11, 12 and 13 hereafter, for information.

    FIGURE 11 FIGURE 12 Measurement readings Vertical distance and correction

    12 o'clock

    9 o'clock 3 o'clock

    6 o'clock

    2c = 4.85 mm

    2c = 5.00 mm

    2c = 5.60 mm

    2c = 5.75 mm

    12 o'clock

    Correction : 0.30 mim.

    6 o'clock

    Distance : 0

    Distance : + 0.60 mm

    towards 12 o'clock

    FIGURE 13

    Horizontal distance and correction

    9 o'clock 3 o'clock

    Distance : 0

    Correction : 0.45 mm towards 9 o'clock

    Distance :- 0.9 0 mm

    The concentricity differences must be less than those allowed for this machine.

    Otherwise, corrections shall be made on the machine on comparator needle side until acceptable values are reached.

    In the example mentioned above, the rotor axis is to be moved even if the relevant Erection Instructions (EI) does not specify any shaft line difference between "cold" and "hot" positions.

    0.30 mm (vertically) from 6 o'clock to 12 o'clock 0.45 mm (horizontally) from 3 o'clock to 9 o'clock.

  • Originator ALSTOM POWER SYSTEMS S.A..

    Alstom Identification number TJN/40/M/----- -----/EG/013

    Rev. A

    Date 04.04.2013

    Lang. En

    Sheet 18/18

    Owners dwg number T4-APD-B0-A-40104

    Rev A

    ALSTOM 2013. All rights reserved.

    11. ATTACHMENT 2: CALCULATION OF TOLERANCES FOR SEMI-FLEXIBLE COUPLING

    11.1. Calculation of speed factor (Fv) values

    Example:

    For a coupling with an outside diameter of 300 mm, with spacer, rotation speed of 3000 rpm:

    Fv = 0.53

    whence the following alignment tolerances:

    EA max. =

    16 0 53 30010000x x,

    : 0.25 mm at the outside diameter of the half couplings.

    ER max. = 0.25 mm

    (EA + ER) max. = 0.25 mm