route 55: lauer rd –tsp & access management. agenda welcome and introductions workshop...
TRANSCRIPT
Route 55: Lauer Rd –TSP & Access Management
Agenda
Welcome and Introductions Workshop Purpose Project Introduction & Background Citizen Advisory Committee Report Introduce Preliminary Design Alternatives Question & Answer Period Break Out Session Report Back Next Steps
Workshop Purpose Report Back to Community on Public
Workshop I & the Citizen Advisory Committee
Introduce the Preliminary Design Alternatives to Community
Gain community feedback
Introduction & Background
NYSDOT Project Objectives:Reduce AccidentsReduce Traffic DelaysSupport Future needs of the corridor and
the community
Project Overview Feb 2008
Initiated to address safety and operational concerns along the corridor
Oct 2010 Public Officials Meeting
February 2011 Public Workshop 1
April – July 2011 CAC meetings
August 2011 Public Workshop 2
Public Workshop 1
Summary of Things That Work
Access to TSP/Poughkeepsie Current Assets/Setup Access to Businesses Small Town Feel Existing Turn Lanes Zoning Town Maintenance
Summary of Needs Improve Intersection Operations at
Stringham Rd. & Arlington High School (AHS)
Address heavy traffic along Route 55
Improve safety for pedestrians and bicyclists
Improve right turn movement onto Freedom Rd.
Improve ability to make left turns throughout the corridor
Improve traffic flow and signal timing throughout Route 55 corridor
Improve access to the many driveways along Route 55
Improve access to Post Office
Improve operations at Mobil Station near Freedom Rd.
Add left turn access at Lexington Park exit
Improve vehicle & pedestrian access on Dr. Fink Rd.
Improve site distance at TSP ramps and Route 55
Address flooding problems along Route 55 near Kelly’s
Address inconsistent vehicle speed through corridor
Maintain consistency of roadway corridor along Route 55
Citizens Advisory Committee Committee Make-up
Represent different facets of community Community voice
FocusCommunity Priorities
Schedule Monthly Meetings
CAC Focus
Priority NeedsImprove Intersection OperationsAddress Heavy Traffic on Route 55Improve Business AccessImprove Bike/Pedestrian Access and Safety
Conceptual Layouts
Concept 1
Concept 2
Concept 3
Concept 4
Concept 5
From Layout to Alternative
• Modern Roundabout • Yield Approach• No Turn Lanes• Raised Median• Permitted Pedestrian
• Modern Roundabout • Yield Approach• No Turn Lanes• Raised Median• Permitted Pedestrian
• Standard Traffic Signal• Protected Approach• Designated Turn Lanes• Flush Median• Protected Pedestrian
• Standard Traffic Signal• Protected Approach• Designated Turn Lanes• Flush Median• Protected Pedestrian
• Modern Roundabout • Yield Approach• No Turn Lanes• Raised Median• Permitted Pedestrian
• Modern Roundabout • Yield Approach• No Turn Lanes• Raised Median• Permitted Pedestrian
• Standard Traffic Signal• Protected Approach• Designated Turn Lanes• Flush Median• Protected Pedestrian
• Standard Traffic Signal• Protected Approach• Designated Turn Lanes• Flush Median• Protected Pedestrian
• Modern Roundabout • Yield Approach• No Turn Lanes• Raised Median• Permitted Pedestrian
• Modern Roundabout • Yield Approach• No Turn Lanes• Raised Median• Permitted Pedestrian
• Standard Traffic Signal• Protected Movements• Designated Turn Lanes• WB Right Turn By-Pass• Flush Median
• Standard Traffic Signal• Protected Movements• Designated Turn Lanes• WB Right Turn By-Pass• Flush Median
1 2-Way Dr. Fink Connection2 Access to Business3 Access to School4 Pedestrian Connection5 Right’s In / Out
1 2-Way Dr. Fink Connection2 Access to Business3 Access to School4 Pedestrian Connection5 Right’s In / Out
Comparison of AlternativesWeighting Criteria
Signalized Alternative(w/ flush median & turn lanes)
Roundabout Alternative(w/ Raised Median Section)
Safety High Speed on Green28 conflict pointsProtected Pedestrian Phase
Low Speed Operation8 conflict pointsYield Control
Access Turning Movement FrictionNo Left at Peak Hours
Rights in / Rights out Utilize Roundabout To make left
Operation Restricted Lefts Red pedestrian phase
Raised MedianRights in / out
Environment More PavementMore Signs / Stripes
Less PavementMore Green Space
Const. Cost 4.8 M 5.2 M
Safety Considerations32 32
Vehicle to Vehicle to Vehicle Vehicle Conflict Conflict PointsPoints
24 Ped. to 24 Ped. to Vehicle Vehicle Conflict Conflict PointsPoints
8 Vehicle 8 Vehicle to Vehicle to Vehicle Conflict Conflict PointsPoints
8 Ped. to 8 Ped. to Vehicle Vehicle Conflict Conflict PointsPoints
Q & A
Break Out Session Choose a Recorder and a Reporter Using the worksheets provided Discuss
How Well The Alternatives Meet The Project Objectives and Community Needs.
Please write down your comments on the worksheet- Be specific. This is our record of what happened at this meeting.
In 30 minutes or so we’ll ask the reporter at each table to present TWO items that your group identified (positive/negative).
Next Steps
Review comments; additional meetings with the CAC; refine alternatives; use specific design criteria; design report etc.
Workshop III – Present Preferred
Alternative
Please Fill Out Your Surveys And Drop Them By The Door Before You Leave