Route Plans are generally published on an annual basis including the most up-to-date position at that point in time. In 2011 we will be publishing information on a route basis as part of our Initial Industry Plan in the Autumn covering CP5 and beyond.
In the meantime we have retained the 2010 Route Plans, updated where appropriate with current information including our plans to the end of CP4. This document, therefore, should be read in conjunction with the equivalent 2010 Route Plan.
Should you require any further information, please contact the Route Plan 2011 mailbox at [email protected].
Appendix A: Updated Route Map
Appendix B: Updated list of CP4 enhancements
Appendix C: Constraints and issues on the route
]
Summary of alterations
Reference Data Location in
Route Plan
Change
Page 3 Route Map Page 3 Labels updated to match Appendix B.
Figure 11 Forecast end of
year PPM
Page 12 First Great Western 90.1%
CrossCountry 88.3%
Stagecoach South West Trains 93.9%
Arriva Trains Wales 94.1%
The above is based on 2010/2011 Period 11 data.
2
Network Rail 2011 Route Plans Update – Route K
Appendix A: Updated Route Map
Key to diagrams
KeyPrimarySecondaryRuralFreight only
The line shading indicatesstrategic route sectionswhich are numbered on the map
Route K West of England
Treviscoe branch
ParHarbour branch
Heathfield branch
Meldon Quarry
Moorswater branch
St BlazeyJnPar Loop Jn
Coombe Jn
St BudeauxJn
Newton AbbotWest Jn
Newton Abbot East Jn
Cowley Bridge Jn
Cogload Jn
Exeter St Davids JnExmouth Jn
PenwithersJn
Burngullow Jn
St Erth Jn
FoweyHarbour branch
Cattewaterbranch
NEWQUAY
LISKEARD EXMOUTH
PAIGNTON
PENZANCE
GUNNISLAKE
Bere Alston
ST IVES
FALMOUTH DOCKSLOOE
NEWTON ABBOT
EXETER ST DAVIDS
TAUNTON
BARNSTAPLE
PLYMOUTH
St ErthHayle
Lostwithiel
Camborne Truro St AustellRedruth
Perranwell
St Budeaux Victoria Road Ivybridge
Totnes
TeignmouthDawlish
Dawlish WarrenStarcross
Exeter St Thomas
Newton St Cyres Tiverton ParkwayCrediton
YeofordCopplestone
Morchard RoadLapford
EggesfordKings Nympton
Portsmouth ArmsUmberleigh
Chapelton
Bere Ferrers
Calstock
Carbis BayLelant
Lelant SaltingsPenryn
PenmereFalmouth Town
Keyham
St Budeaux Ferry Road
Dockyard
DevonportMenheniot
Coombe
Sandplace
Causeland
St Keyne
St Germans
Saltash
Par
BodminParkway
Exeter Central
St JamesPark
Polsloe Bridge
Digby & Sowton
Topsham
Exton
Lympstone Commando
Lympstone Village
Torre
Torquay
St Columb RoadRoche
Bugle
Luxulyan
Quintrel Downs
Route J
Dr. Days Jn
PORTBURY DOCK BRANCH
Feeder Bridge Jn
Thingley Jn
Bristol East Jn
Uphill Jn
Worle Jn
Route M
Stoke Works Jn
Route M
Route L
Route L
Tytherington branch
Sharpness branch
Horton Road JnBarnwood Jn
Abbotswood Jn
GloucesterYard Jn
StokeGiffordJn
Filton Jn Westerleigh
Yard
WesterleighJn
Wootton Bassett Jn
AVONMOUTHDOCKS
Yate JnsPatchway
Jn
BIRMINGHAM NEW STREET
DROITWICH SPA
WORCESTER FOREGATE STREET
WORCESTER SHRUB HILLHEREFORD
BRISTOL PARKWAY
NEWPORT
SWINDON
GLOUCESTER
CHELTENHAM SPA
BRISTOL TEMPLE MEADS
SEVERNBEACH
WESTON-SUPER-MARE
BATH SPA
St Andrews RoadAvonmouth
ShirehamptonSea Mills Redland
Montpelier
Keynsham Oldfield Park
CliftonDown
Parson Street
Bedminster
Nailsea & BackwellYatton
Worle
Highbridge & Burnham
Bridgwater
Weston Milton
Yate
Cam & Dursley
Ashchurch
Filton Abbey Wood
Stapleton RoadLawrence Hill
Chippenham
MORETON-IN-MARSH
CASTLE CARY
WESTBURY
WEYMOUTH
Dorchester Jn
Wilton Jn
Castle Cary Jn
Westbury South Jn
Westbury North Jn
Hawkeridge Jn
Bradford Jn
Bathampton Jn
Pen Mill Jn
Westbury East Loop
Route C
Route C
Route C
Route C
DORCHESTER WEST
Yeovil Pen Mill
Thornford
Yetminster
Chetnole
Maiden Newton
Warminster
Dilton Marsh
FreshfordAvoncliff
Bradford-on-Avon
Trowbridge
Melksham
NEWPORT
Narroways Hill Jn
Standish Jn
Route J
SALISBURY
Route J
Route J
Route L
YEOVIL JUNCTION
Bristol West Jn
Route J
99
01
02
03
06
07
08
09
10
11
12
13
14
99
99
99
99
99
99 99
18
98
98
98
99
04
05
99
16
17
15
A
B
C
D
E
F
G
1
2
3
A
A
B
BD
F
G
G
I
J
3
Netw
ork Rail 2011 R
oute Plans U
pdate –R
oute K
Appendix B: Infrastructure investment in CP4
Figure 15 Infrastructure investment in CP4 (formerly Proposed enhancements in CP4)
Implementation date Project Project description Output change Funding GRIP stage
2011/12 A Earthworks renewals Embankments renewals at Dauntsey Bowds Farm and Eckington
Renewal Network Rail Various
2011/12 B Telecoms renewals CIS, PA and CCTV renewals at Exeter St Davids and Plymouth
Renewal Network Rail 5
2010/11 Track renewals Project complete
2010 – 13 D Structures renewal Structures renewal at Royal Albert Bridge Renewal Network Rail 6
2011/12 Earthworks renewals Project deferred
2011/12 F Telecoms renewals CIS, PA and CCTV renewals at Bristol Temple Meads
Renewal Network Rail 5
2011/12 G Track renewals Track renewals at Dr Days Junction and Barnwood Junction
Renewal Network Rail Various
2012/13 Track renewals Project deferred
2013/14 I Westerleigh Junction – Barnt Green line upgrade
Options for linespeed increases up to 100mph Improved reliability and additional capacity and journey time savings between Bristol and Birmingham
Periodic Review 2008 4 – 6
2011/12 Signalling renewals Bristol TDM renewals Renewal Network Rail 5/6
2012/13 Plant renewals Renewal of signalling power distribution cables in the Gloucester area
Renewal Network Rail 5
2013/14 Track renewals Track renewals at Patchway Junction Renewal Network Rail 3
On-going until
2015/16
Signalling renewals Signalling renewal of the Bristol Signalling Centre area
Renewal Network Rail 3
On-going until
2017
Great Western Main Line
electrification
Electrification from London Paddington to Bristol
and Cardiff
Electrified network Department for
Transport
3
Netw
ork Rail 2011 R
oute Plans U
pdate – Route K
4
NRDF candidate schemes in CP4
Figure 16 Candidate NRDF schemes in CP4
Implementation date Project Project description Output change Funding GRIP stage
2011/12 J Bath Spa capacity enhancement
Repositioning of signals Improved reliability, additional capacity and reduced platform reoccupation times. Facilitates enhanced cross-Bristol service
Network Rail Discretionary Fund
6
GRIP stages: 1 Output definition, 2 Pre-feasibility, 3 Option selection, 4 Single option selection, 5 Detailed design, 6 Construction, test and commission, 7 Scheme hand back, 8 Project close out
5
Network Rail 2011 Route Plans Update – Route K
Appendix C Constraints and issues on the route
Capacity and operational constraints
A Westerleigh Junction – Bristol Parkway: two track section on highly utilised converging route B 5 AHB level crossings north of Cheltenham restrict linespeed to 100mph C Weston-super-Mare loop: single line restricts capacity and flexibility D Dorchester West – Castle Cary: single line sections prevent significant increases in train service frequency E Signalling headways between Newton Abbot and Plymouth F Royal Albert Bridge: single line section linking Devon and Cornwall G St Pinnock and East Largin viaducts: single line sections
Other Issues on Route
1 Somerset Levels – flooding
2 Flood plain to the north of Exeter requires constant monitoring
3 Dawlish Sea Wall defences require constant monitoring and enhanced maintenance