Roy Estrada Chavarriaga (57)3208335083 Bogota D.C Calle 94 No 16 – 09 ofic. 504 Telefax (57) (1) 6108097 / 7592489 COLOMBIA - SUR AMERICA Nit. 810.005.338-5 mail: [email protected]. Global Description of the Project (VISION). Reactivate cargo transport on the Magdalena River - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Roy Estrada Chavarriaga   (57)3208335083

SOCIEDAD PORTUARIADE LA DORADA S.A.

Roy Estrada Chavarriaga (57)3208335083Bogota D.C Calle 94 No 16 – 09 ofic. 504 Telefax (57) (1) 6108097 / 7592489

COLOMBIA - SUR AMERICANit. 810.005.338-5 mail: [email protected]

Page 2: Roy Estrada Chavarriaga   (57)3208335083

Global Description of the Project (VISION)

• Reactivate cargo transport on the Magdalena River• It has two phases:

– Phase 1: small dock in the city that can move oil and small-scale containers (oil storage capacity: 5,200 barrels, containers per week: 400).

– Phase 2: high capacity dock Gibraltar lot (128.000m2 lot owned by SPD with) to move oil and large-scale containers. The lot has excellent geographical location, appropriate land and meets the requirements for proper port functioning. The lot is included in the POT (Land Use Plan) of the municipality of La Dorada for port development.

Page 3: Roy Estrada Chavarriaga   (57)3208335083

Project Location and its Importance

• The port is located at the municipality of La Dorada – Caldas, key point for cargo transport specially the one that moves between Cartagena/Barranquilla and the rest of the country.

• Terminal is strategically located in the main logistics center of the country and only place where the loads are balanced within the design of its operation.

Page 4: Roy Estrada Chavarriaga   (57)3208335083

Social and Environmental Responsability

• The project has an Environmental Management Plan (PMA) for Phase 1 to ensure environmental and social management. PMA is being adopted by CORPOCALDAS (corporate environmental agency).

• Actions indicated in the terms of reference issued by CORPOCALDAS are being developed to mitigate the social and environmental impact.

• Along with employment generation (operation of the port) SPD wants to improve the quality of life of La Dorada with health and education projects.

Page 5: Roy Estrada Chavarriaga   (57)3208335083

Benefits of River Transport VS other Means of Transport

• Global studiesCargo transport cost Average number of accidentes

Power consumption Pollutant emissions

Page 6: Roy Estrada Chavarriaga   (57)3208335083

Comparative chart between land and river transport for 80TEUs of 20 feet

80 TEUs 40 trucks

HP 14.000

Contamination 7.00

Energy consumption 16.4

80 TEUs 1 self-propelled boat

HP 1.400

Contamination 1.00

Energy consumption 1.0

Benefits of River Transport VS other Means of Transport

Page 7: Roy Estrada Chavarriaga   (57)3208335083

Economic Benefits

• Studies indicate that the port of La Dorada generates savings in the transport of oil of 40% compared with land transport

• Benefits to the region for additional income• Increased Gross Domestic Product (GDP)

Page 8: Roy Estrada Chavarriaga   (57)3208335083

Environmental Benefits

• Decrease in air pollution over the pollution emitted by road transport for the same amount of charge

• Less energy consumption with respect to land transport

• Proper management of the river which could prevent overflow and flooding in some places

Page 9: Roy Estrada Chavarriaga   (57)3208335083

Social Benefits

• Direct and indirect employment generation (aprox. 6,000 and 15,000 respectively) in a municipality with high unemployment and poverty. This depends greatly on the response capacity of the population.

• Lower cost of transportation would help the small and medium farmers / industrial.

• Most unskilled workmanship will be generated by the municipality of La Dorada.

• Increased quality of life.Appropriation of the river which would be reflected in its care.

Page 10: Roy Estrada Chavarriaga   (57)3208335083

What do we have now?

• La Doradas Port:– SPD has a small dock with some adjustment already

made, a few are pending. With minimum works the dock will be operating within months.

– Operating license for the development of port operations has been issued. Resolution 000 343 of December 1, 2007.

• Gibraltar Port:– The lot is owned by SPD and is stablished on the

POT for port development

Page 11: Roy Estrada Chavarriaga   (57)3208335083

Requirements to achieve full implementation of the project

• La Doradas Port:– Finish the adequacy of

the container yard.– Purchase / lease of

machinery.– There will be needed

approximately 2.400.000 USD to complete this port.

Tanks repared by SPD

Simulation with works completed and ready for operation

Page 12: Roy Estrada Chavarriaga   (57)3208335083

• Gibraltar Port:This Port will be constructed in 3 modules.There will be needed approximately 19.000.000 USD to complete the first phase.The other 2 phases can be built in 5 years using part of the profits from the first phase.

Gibraltar´s lot entrance

Gibraltar´s lot

Requirements to achieve full implementation of the project

Gibraltar´s lot

Page 13: Roy Estrada Chavarriaga   (57)3208335083

Historical Overview

• The municipality of La Dorada was a strategic point for cargo handling.

• Phase 1: was operational until the 1990's.

• Phase 2: Gibraltar was the place that the Spanish used to transport cargo.