run at rate (r@r)
TRANSCRIPT
Run at Rate (R@R)
Polaris Supply Chain – Supplier Training
Revised: June 6, 2016
Revision Number: 1Polaris CONFIDENTIAL
2
Welcome
Add the slide take-away here!Polaris CONFIDENTIAL
Welcome to the Run@Rate Training Module
3
Agenda
Name of Training Topic: Run@Rate Training Module
Learning Objectives
Why the Training Topic is Important? When?
Define Training Topic – What is It?
Training Content
Tools and References
Demo / Example
Learning Objectives Recap
Thank you!
Polaris CONFIDENTIAL
4
Learning Objectives
Effective R@R Audit
At the end of this training, participants will be able to:
• Understand importance of the R@R
• Know when to schedule a R@R
• Know how to perform a R@R
Polaris CONFIDENTIAL
5
Why is a R@R Important?
R@R Audits Determine State Of Production ReadinessPolaris CONFIDENTIAL
A R@R audit is used to:
Validate the readiness of your manufacturing process.Comprehensive process review: receipt to shipment.
Demonstrates capability over multiple shifts and production set ups.
Evaluate the process controls with regards to production readiness.
Evaluate capability.True capacity.
Equipment effectiveness.
Quality systems management.
Expose process variation prior to SOP.Drive production like requirements
Evaluate sub-tier supplier management.Review formal selection process.
Review PPAP completion of sub-tier suppliers.
Uncover and address quality risks before SOP.
The Quality Lifecycle Management process is a
process to ensure product quality assurance.
Process Usage: Run@Rate
Supplier selected for
R@R
R@R schedule
R@R requirements
Pre-R@R meeting(s)
held
Perform on site R@R
Close our action
register items
Follow up R@R if needed
6
Process Overview
R@R Audits Are Key Part Of PDP And APQPPolaris CONFIDENTIAL
P
P
A
P
Supplier
QualificationPDP
EOL
Safe Launch
Supplier Performance
Product
Assurance
ControlMonitoring Improvement
APQPQuality Event
Resolution
Supplier On-
Boarding
………….Serial
Production…….………MaturityVolume Ramp….SOP PPAP…..APQP……
SupplierSelection
All suppliers selected for APQP will require R@R audit.
Detail of APQP selection process can be found in this link.
SQE can conduct R@R audit as risk mitigation on any supplier.
Examples:
Validation of process change: sub-tier change, new equipment, etc.
In response to a design change.
Verify process due to seasonal manufacturing schedule.
7
R@R Selection
Suppliers Selected From APQP Process or as Risk MitigationPolaris CONFIDENTIAL
Supplier selected for
R@R
R@R schedule
R@R requirements
Pre-R@R meeting(s)
held
Perform on site R@R
Close out action
register items
Follow up R@R if needed
The R@R should be scheduled with PV parts production.
Higher risk parts/suppliers should have pre-audit visits.
Recommended at PI so that suggestions can be given before tooling has been completed.
8
R@R Timing
Schedule R@R Based on Project TimelinePolaris CONFIDENTIAL
Supplier selected for
R@R
R@R schedule
R@R requirements
Pre-R@R meeting(s)
held
Perform on site R@R
Close our action
register items
Follow up R@R if needed
Use PV or Pulse to Drive Requirements9
Audit to be performed at production of PV parts.Timing driven by PV timing.
High risk parts/suppliers will require earlier audit.
Quantities driven by PV volume.
If PV volume too low then use pulse process.
Significant production run(s) should be performed before R@R as well.
Production should be off tool, off process.Any changes to process after R@R will require PCR.
Should be at planned production volume.
Frozen design must be achieved.
R@R Requirements
Supplier selected for
R@R
R@R schedule
R@R requirements
Pre-R@R meeting(s)
held
Perform on site R@R
Close ouaction
register items
Follow up R@R if needed
Preparation is Key to Successful R@R10
Your preparedness is critical for success.
Steps to ensure you are prepared:Participate in the pre-audit meetings to set expectations.
• Go through the audit form with the SQE.• Perform the self assessment and send results back to SQE prior to formal audit.• Complete capacity tab and send back to SQE before the audit.
Audit is from receipt – shipment. Prepare all processes!
Conduct a significant production run before audit.
Review the agenda before audit.
Off tool, off process.Also means operators run the process not engineers.
Make sure the right representatives are present!• Senior Management (kickoff and wrap up).• Quality.• Engineering.• Manufacturing.
If your schedule changes let SQE know before arriving at audit.
This is meant to help your process be successful.
R@R Preparation
Supplier selected for
R@R
R@R schedule
R@R requirements
R@R preparation
Perform on site R@R
Close out action
register items
Follow up R@R if needed
Poor planning will result in a poor
audit!
It’s time for the R@R! How are we successful?
Review the agenda.
Have copies of print, control plan, and process flow available.
Make sure production operators are running the processes.
The SQE will Review the entire process
• Receiving – Shipment
• Poke yokes
• Labeling/barcoding
• Doc control
• Rework procedure
Review multiple shifts.
If not enough time to see entire process make sure critical processes are running for audit.
Stage any other processes for general review.
Have a closing meeting.
Work with SQE to complete action register.
11
Performing the R@R
Production Readiness & Risk Should be Fully UnderstoodPolaris CONFIDENTIAL
Supplier selected for
R@R
R@R schedule
R@R requirement
Pre-R@R meeting(s)
held
Perform on site R@R
Close out action
register items
Follow up R@R if needed
12
Action Register
Action Register Drives Required ImprovementPolaris CONFIDENTIAL
Use the action register tab to:
List any non-conformance items.
Assign responsible person for each item.
Assign due date for each item.
Drive process improvements for production.
Be prepared for all follow up meetings with updates.
As with the audit itself make sure the correct people participate in each meeting.
Complete all tasks on the action register!
Supplier selected for
R@R
R@R schedule
R@R requirement
Pre-R@R meeting(s)
held
Perform on site R@R
Close out action
register items
Follow up R@R if needed
Preparation Prevents Repeat Audits & Follow-up13
A follow up R@R will be required if:
The process was not ready when the SQE was present for the first R@R.
• Fixtures
• Machines
Late design change requires process changes.
The process was not able to complete enough parts for a full production run.
• Not enough raw material
• Equipment failure
High risk suppliers/parts as part of safe launch.
Validate any PCRs after R@R.
Follow Up
Supplier selected for
R@R
R@R schedule
R@R requirement
Pre-R@R meeting(s)
held
Perform on site R@R
Close out action
register items
Follow up R@R if needed
Standard Work; Use of Form is Required 14
R@R form can be accessed via the SQAM.
Tools / Other References
Polaris CONFIDENTIAL
Snap Shot Of Blank To Completed Audit Tab15
Example – Audit Tab
Complete All Fields16
Example – Audit Tab
First fill out the top section of the audit tab. Supplier
fills out top portion, SQE fills out bottom portion. All
orange sections must be completed.
Use Criteria as the Guideline to Score Audit17
Example – Audit Tab
Now it is time to work through the audit process.
Each item is graded on a 0-3 scale. If the item is not
applicable then it can be marked “NA.” The grading
criteria is provided as a guideline for each line. Take
all time required to review each line.
Utilize Objective Evidence to Justify18
Example – Audit Tab
The objective evidence is the section to insert the
detail justifying the rating given for each item. The
criteria gives the guideline for rating but the SQE is
still responsible for giving further detail when
necessary.
Tip: While objective evidence is important for all line items it is especially
important when the supplier and Polaris ratings are different and when giving a 0
or 3.
Use The AR Tab To Capture Improvement Plan19
Example – Action RegisterThere will be some improvement
items with each audit. The AR tab
is the place to capture the CA plan.
Quick Assessment to Prioritize Improvement Area(s)20
Example – Scoring SummaryOnce the scoring has been completed
on the audit tab use this summary to
show where most improvement is
needed.
Ensure Your Supplier Is Prepared!21
Example – Pre-Run@Rate AR
Prior to each audit the pre-run@rate AR must be completed. This is your checklist
to ensure the supplier is prepared for the audit.
Important to Verify Actual Capacity22
Example – Capacity
Line capacity is also a crucial part of the success for a supplier’s process. Before
arriving for the run@rate the supplier should have the capacity tab filled out. Make
sure to pay attention to the bottle neck(s) in the process. These should be attacked
for future improvements.
Complete Summary for Concise Reporting23
Example – Summary
The summary page is important for giving quick feedback in meetings where the full
detail is not needed. This should give a snapshot of the audit results.
24
You should understand:
Understand importance of the R@R
Know when to schedule a R@R
Know how to perform a R@R
Learning Objectives Recap
What you learned from this trainingPolaris CONFIDENTIAL
25
Thank you!
Thank you for attending!Polaris CONFIDENTIAL
Thank you for taking the time to complete the Polaris R@R Training Module.
• Please make sure to take the Quiz and provide training feedback.
• Taking the Quiz gives visibility to us that you have read and understand this
training!
Questions? Please contact your Supplier Quality Engineer or Buyer.