rural transportation summit – adot environmental in project development january 19, 201 4
TRANSCRIPT
5-YEAR PROGRAM Program Delivery Assistant
Lisa Pounds
DESIGNDeputy State Engineer
Steve Boschen
CONTRACTS & CLEARANCES Deputy State Engineer
Barry Crockett
STATEWIDE PROJECT MGMTGroup Manager
Vince Li
LOCAL PUBLIC AGENCIES Program ManagerBahram Dariush
State EngineerJennifer Toth
Sr. Deputy State Engineer Dallas Hammit
Executive Staff Asst.Peggy Harding
Right of Way Paula Gibson
Joint Project Agreements Lillian Marks
Engineering Consultant ServicesMichael Denbleyker
Utilities & Railroads Vicki Bever
Contracts & Specifications
Steve Hull
Environmental Planning
Paul O’Brien
Roadway Engineering
Annette Riley
Traffic Engineering Maysa Hanna
Bridge Group Shafi Hasan
Materials Group Bill Hurguy
Engineering SurveyChong-Tai Chyan
ADOT – Intermodal Transportation Division
Why do we have an Environmental process?
• Assure that there is a project purpose and need for the transportation project
• Assure that environmental impacts are considered in developing alternatives
• Assure that projects Avoid, Minimize, and Mitigate adverse effects
• Assure that projects meet all legal requirements
The National Environmental Policy Act (NEPA) of 1969
NEPA requires the Federal government to consider the environment in major Federal actions
• So why ADOT and LPA projects?– ADOT’s highway program, including LPA projects, is
largely a Federal-Aid Program (i.e. the Federal Gas Tax)
The National Environmental Policy Act (NEPA) of 1969
What requires NEPA?• Federal ‘Actions’– Federal Funds for Design, ROW and Construction– Other Federal actions (regardless of project funding): • US Army Corps. 404 permits• Action by land management agencies (FS, BLM, BIA, etc.)• Design Exceptions on the National Highway System (NHS)• ‘Change in Access’ on the Interstate System
The National Environmental Policy Act (NEPA) of 1969
What Brought about NEPA?• The Sixties– Reaction to the Interstate building of the 50’s into
the 60’s (the Freeway Revolt)– The book Silent Spring– Vietnam War protests – The Counter-Culture– Other significant events
Why are these Environmental laws in place?
1956 – Federal-Aid Highway Act started the Interstate Highway construction program
Why are these Environmental laws in place?
1956 – Federal-Aid Highway Act Interstate Highway construction mandate
Why are these Environmental laws in place?
The highway program is “being operated by barbarians. We ought to have some civilized understanding of just what we do to spots of
historic interest and great beauty by building eight-lane highways through the middle of our cities.”
Senator Joseph Sill Clark – PA, 1966Source: “Divided Highways” (Tom Lewis)
Why are these Environmental laws in place?
Planned freeway through Overton Park – 1971 the US Supreme Court “protection of parkland was to be given paramount importance.”
Why are these Environmental laws in place?
1969 Cuyahoga River Fire, Cleveland
Santa Barbara Oil Spill
NEPA signed into law on January 1, 1970
NEPA Decision Making FrameworkNEPA involves…
Consideration of environmental factors in decision-making (in addition to economic and technical)
Consideration of alternatives to actions with significant impacts
Evaluation of environmental impacts
Project documentation (NEPA documents)
Public involvement and interagency coordination
Regulatory and Guidance Hierarchy
Regulati on and Guidance
United States Code (USC) [Law]• 23 (Highways) and 42 (Public Health) USC
Council of Environmental Quality (CEQ) Regulations • 40 CFR 1500
FHWA NEPA Regulations • 23 CFR 771
FHWA HQ Guidance • Technical Advisory T6640.8A for NEPA Documents
• 4(f) Policy Paper
FHWA AZ Division Guidance and ADOT EPG Guidance
The NEPA Umbrella
• The NEPA process provides a framework for compliance with other Federal, State, and local environmental statutory requirements (hence the term “NEPA umbrella”)
• Procedural law – Follow the process– Defines process, not decisions
The NEPA Umbrella
Title VI of Civil Rights Act of 1964
Executive Order 12898 (Environmental Justice)
Civil Rights Act
Clean Water Act (CWA)
Clean Air Act (CAA)
Safe Water Drinking Act (SDWA)
Endangered Species Act (ESA)
Solid Waste Disposal Act (SWDA)
Resource Conservation and Recovery Act of 1976 (RCRA)
49 USC 303 – 4(f)
Emergency Planning and Community Right to Know Act of 1986 (EPCRA)
National Historic Preservation Act (NHPA)
Public Hearing Requirements
Archaeological and Historic Preservation Act (AHPA)
Farmland Protection Act
23 USC 109(h) – Highways Environmental Effects
“What if they just repealed NEPA?”
The NEPA Umbrella
Title VI of Civil Rights Act of 1964
Executive Order 12898 (Environmental Justice)
Coastal Zone Management Act
Clean Water Act (CWA)
Clean Air Act (CAA)
Safe Water Drinking Act (SDWA)
Endangered Species Act (ESA)
Solid Waste Disposal Act (SWDA)
Resource Conservation and Recovery Act of 1976 (RCRA)
Comprehensive Environmental Response, Compensation and Liability Act (CERLA)
Emergency Planning and Community Right to Know Act of 1986 (EPCRA)
National Historic Preservation Act (NHPA)
Public Hearing Requirements
Archaeological and Historic Preservation Act (AHPA)
AND MORE…
NEPA Approval & ADOT Environmental Clearance
NEPA approval– Approval date of the Environmental Document
(CE, EA or EIS)– Allows for Federal Authorizations for Final Design and all
ROW actions
ADOT Environmental Clearance– Final clearance from EPG to Contract and Specifications
to certify that the project is ready for bid advertisement in terms of environmental requirements
NEPA Classes of ActionNEPA Document:• Class I - Environmental Impact Statement (EIS)o Impacts significant
• Class II – Categorical Exclusion (CE)o Impacts not significant
• Class III – Environmental Assessment (EA)o Significance of impacts are not clearly known
• Re-Evaluation o Revisit after NEPA approval (time or changes)
NEPA Class of ActionCategorical Exclusion (CE)
Traffic Guide Sign – minor impacts with limited ground disturbance
NEPA Class of ActionCategorical Exclusion (CE)
Pavement Preservation Project- including work off the roadway such as culvert extensions and slope flattening
How Long Does It Take?
Schedule dictated by…
• Complexity of project• Timelines and quality of
technical reports• Responses from other
agencies/SHPO/Tribes• Changes in project scope • Timeliness of additional
funds needed
Project Development Timeframes• Group One (CE) – Up to 2 months– May still require some due-diligence
• Group Two (CE)
– 6 to 12* months* Biology, cultural resources, 404 Individual Permit
• Environmental Assessment – 1 to 3 years
• Environmental Impact Statement – 3 to 5+ years
Purpose and Need
Public and Agency Scoping (NEPA)
Section 106 Consultation (Historic Preservation Act)
Biological Evaluation (Endangered Species and more)
Hazardous Materials report
4(f) Evaluation
Environmental Process Highlights
Air and Noise
Mitigation measures
404 Permits (Clean Water Act)
Environmental in Project DevelopmentIntegration of
environmental and design – One Process
The Scope of the project and changes in design greatly influence the environmental schedule/project schedule
Environmental in Project Development
• Project scoping process and Environmental Field Review Form are important to identify environmental scope early
• Ideally we’ll have a 100% footprint for environmental & ROW at 60% Design. Try to avoid late changes as they can impact schedule.
• Identify Temporary Construction Easements (TCEs) early in Design
• Identify and include staging and stockpiling areas at Field Review if possible. May require TCEs
• Identify scope such as geotechnical work early. Do we need a separate clearance or can it be part of the project clearance
– Get environmental technical work/consultations going early before boring plan is finalized
Environmental in Project Development
• Communicate any scope changes to the EPG Planner as soon as they happen
• If the EPG Planner has requested information then supply it as soon as possible.
• The environmental process, through consultation and coordination with stakeholders and outside agencies, may bring about additional scope being added to the project
– EPG is never looking to increase scope but sometimes it happens
• Get funding in place quickly for addition work added to the project scope
– Examples; 404 permit, biological survey or cultural data recovery work added to the project
Environmental in Project Development Project Scoping/Preliminary Design
• Comprehensive and un-changing (ideal world)– Delay in defining or changing a project scope can
delay the environmental process– Define drainage improvements, culvert extensions,
geometric improvements, scour countermeasures, etc. Scope added later in the design process can add time to the environmental process and impact the project schedule
– Define project footprint with preliminary design
Environmental in Project Development
Define JDs early
Factor JDs and wetlands in the design; drainage, bridge, scour
Avoid, minimize and mitigate
Least Environmentally Damaging Practicable Alternative – required by Corps.
404 PERMITS
Environmental in Project Development404 PERMITS
Preliminary design impacted a wetland
404 Individual Permit required
Alternatives analysis required
Environmental in Project Development404 PERMITS
Design changed to avoid impact to wetland
404 Individual Permit avoided
Nationwide only for temporary construction impacts
Environmental in Project Development
Historic Buildings and Districts
Built Environment surveys are necessary
Cultural resource concerns may impact the design
CULTURAL RESOURCES
Environmental in Project DevelopmentCULTURAL RESOURCES
Historic Roads
We try to avoid ‘adverse effect’ through Section 106 Consultation
HPT has procedures for treating historic roads
Data recovery is expensive and time consuming
Environmental in Project Development
Data recovery is undertaken to recover data (information)
Data recovery may require a task order or contract (consider timing and funding)
Constructability in relation to avoidance areas
CULTURAL RESOURCES
Environmental in Project Development
SECTION 4(f)• Provides protection to parks and recreational
lands, wildlife and waterfowl refuges, and historic sites. No “use” unless:– No feasible and prudent alternative– All possible planning to minimize harm to the
property resulting from use
Environmental in Project Development SECTION 4(f)How to address: • First, can we avoid! – Study alternatives • Types of treatment – De minimis– Programmatic• Bridges, Minor Use of Historic Sites
– Individual
De minimis taking
Minimize impact
Negotiate compensation/ improvements
Agreement of local authority of no adverse effect
Inform the public
Environmental in Project DevelopmentSECTION 4(f)
Historic Bridge; Section 106 and Section 4(f)
Rehabilitation – De minimis
Replacement - Programmatic 4(f) Evaluation (one of five FHWA programmatic procedures for 4(f))
Environmental in Project DevelopmentSECTION 4(f)
Air, Noise and Hazmat. Project context driven.• Air Quality– Urban areas (Non-
attainment/Hot Spot Analysis for CAA)• Noise – Sensitive Receptors (houses)• Hazmat – History of land (old gas stations)
Environmental in Project Development
Avoid, Minimize, Mitigate – Required by regulation to be integral with the project development. Integral does not mean exclusive (for example at the expense of safety).
• Avoid – Historic Sites – Jurisdictional Waters– Biological Sensitive Species
• Minimize – Project impacts
• Mitigate – Compensation for unavoidable impacts– Can be included in the project cost (Federal-Aid eligible)
Environmental in Project Development
MAP-21 – Right-of-Way
Changes related to the Environmental process and ROW – MAP-21 Section 1302:• Changed 23 USC § 108 for Early Acquisition– (b) Many conditions including State Comprehensive
land use planning process and Governor Certification.
– (c) acquired without threat of condemnation. • Talk to FHWA if considering early acquisition of
ROW
MAP-21 - Environmental
• Categorical Exclusions – CEs – Two Types of CE defined in 23 CFR 771.117 under
sections (c) and (d). Both sections have lists of qualifying categories of projects
– The two types defined in 23 CFR 771 and the ADOT/FHWA Operating Agreement• (c) – Undocumented CEs
» Called Group One in Arizona
• (d) – Documented CEs (Checklist). » Called Group Two in Arizona
MAP-21 - Environmental Section 1316
• New Categorical Exclusions for projects within the right-of-way– Amends 771.117(c) by adding paragraph (22) – Makes projects within the ‘operational right-of-way’
of a transportation facility CEs (i.e. Group 1)– Operational ROW defined as areas “disturbed” and
“maintained” within the ROW (footprint)
MAP-21 – Environmental Section 1317
• New Categorical Exclusions for projects with limited Federal assistance– Amends 771.117(c) by adding paragraph (23) – Makes projects with limited Federal funds CEs (i.e.
Group 1) under (c)– $5 million or less total project cost with all Federal funds– $30 million or less total project cost with no more than
15% Federal funds contribution
MAP-21 – Environmental Section 1318
• New Categorical Exclusions added to the list of CE projects in 23 CFR 771– Adds new CEs requested by State DOTs, MPOs and LPAs– Also, reclassifies three categories of actions currently
under (d) to being listed under (c) (i.e. from Group 2 to Group 1) – Modernization including shoulders and auxiliary lanes– Highway safety & traffic operational– Bridge reconstruction, rehabilitation & replacement and RR
grade separations
MAP-21 – Environmental Sections 1316 - 1318
• Didn’t all these new CEs become effective when MAP-21 was signed into law? – No. Map-21 required the Secretary of Transportation to
propose Federal Rulemaking (currently in process)
• Federal rulemaking must occur before CE designations pursuant to sections 1316, 1317 and 1318 become effective. This includes the publication of a proposed rule and the publication of a final rule after consideration of public comments on the proposed rule. The final rule will establish the date when the new CEs become effective.