S. No RFP Ref Page
no
RFP Clause no Existing clause Details Change Sought Bank's Response
1 75/110 Annexure -13 A General: 5. Powering Off, dismantling the Servers,
Storage & Network devices from respective racks at BKC
and installing the devices in racks, Powering ON at
proposed location will be done by Bank’s ITSP team in
consultation with Bank and OEM / AMC vendors.
We understand this is bank's ITSP team scope and
not the part of Data Center Service provider, please
confirm.
No change in RFP terms.
Bidder's understanding is correct.
Bank's ITSP team in coordination
with respective OEM's shall jointly
do the activity
2 75/110 Annexure -13 The Bank may in future require additional space at the
Near DR site. The bidder will provide the additional
space to the Bank within the same Near DR site / floor
or building.
Request IDBI to share the road map for further
expansion.
No change in RFP terms.
Bank shall share the additional
requirements as and when it
evolves
3 76/110 Annexure -13 B. Server Room Area - Bank envisages requirement of a
dedicated clear space to accommodate 8 Racks (42U).
This information doesn’t match with Annexure-23
where max. Rack heights is 45U. Also 2 nos. Racks
dimensions are missing
The rack specification is 42U as
mentioned in RFP Annexure 13,
Clause B.2
Rack height of 45U mentioned in
Annexure 23 includes height of the
castor attached to the rack.
Rack dimension is 800 mm X 1000
mm. Please refer the corrigendum
Out of 8 racks, 2 are spare
4 76/110 Annexure -13 B. Server Room Area - 3. The specification for the 8 no.
of Racks to be shifted are mentioned below,
i. 2 no. of network Racks would require 2x16A/1P &
4x32A/1P sockets per rack
ii. 1 no. of Netapp Rack would require 4x32A/1P sockets
iii. 1 no. of IBM Rack would require 4x32A/3P sockets
iv. 4 no. of Racks would require 2x16A sockets per rack.
We understand the 2x16A/1P sockets will be
provisioned thru rack PDU thru C13/C19 connections
and 4x32 Amp/1P circuits will be terminating directly
in the Banks switch. Please confirm.
No change in RFP terms.
2x16A/1P sockets will be
provisioned through rack PDU and
4x32 Amp/1P circuits will be
terminating directly in the Banks
switch.
However necessary power sockets
should be provided for connecting
the equipment.5 76/110 Annexure -13 B. Server Room Area - 6. Bidder should provide two
factor authentications to the caged area for entry and
exit (Combination of any two- Card and Pin or
Biometric)
We shall provide Biometric+PINPAD reader for
server area 'Entry' and Proximity Card Reader for
'Exit'.
Please refer corrigendum
Bank's Respone to Prebid Queries to RFP for Engagement of Service Provider for Relocation of Near Disaster Recovery Site (NDR) Under Hosting Model
REF No: IDBIBank/ITD/VMG/RFP/2020-21/22, September 08, 2020
Page 1 of 35
S. No RFP Ref Page
no
RFP Clause no Existing clause Details Change Sought Bank's Response
Bank's Respone to Prebid Queries to RFP for Engagement of Service Provider for Relocation of Near Disaster Recovery Site (NDR) Under Hosting Model
REF No: IDBIBank/ITD/VMG/RFP/2020-21/22, September 08, 2020
6 76/110 Annexure -13 B. Server Room Area - 7. The Server room should have
precision air conditioning with redundancy. The
temperature in the server hall (caged area) should be
maintained at 20 +/- 4deg C, i.e. the temperature
should be in the range of 16 to 24deg C. The humidity in
the server room (caged area) should be maintained at
50 % +/- 10% RH and monitored periodically and
maintain logs of the same for Bank’s internal / external
/ statutory audit purposes.
Request Bank to accept ASHRAE TC9.9 guidelines of
24+/2 deg Celcius.
No change in RFP terms
7 76/110 Annexure -13 B. Server Room Area - 10. Bidder needs to provide inter-
rack Ethernet copper cabling (supporting 1/10 Gbps)
and fibre cabling at the proposed location for LAN
connections. Only the fibre cables for SAN cabling can
be shifted from the current BKC site. Bidder needs to
ensure that the cables are laid properly as per
structured cabling guidelines and standards.
A. We understand inter-rack cabling will be CAT-6
and fiber cabling will be Multi mode.please confirm.
B. As we understand existings SAN interrack Fiber
cabling can be used Please confirm.
No Change in RFP terms
A. Inter rack cabling will be CAT-6A
and fibre cabling will be multi mode
as mentioned in the RFP Annexure-
13 clause no. G.3 and Annexure -24
clause no 5.2
B. Existing SAN inter rack fibre cable
can be used as mentioned in RFP
Annexure 13 clause no. B.10
8 77/110 Annexure -13 B. Server Room Area - 11. The service provider will be
responsible for terminating the network links at DC and
Near Site premises
CtrlS is a carrier neutral DC, with all the ISP present
in our DC. Bank will have choice to select any
number of ISP directly from Banks side. CtrlS ( SP)
take care of all will be responsible for providing
cross connect between MMR/telecom room - BANK
cage area & Seating area.
No change in RFP terms
9 77/110 Annexure -13 C. Seating Area: 4. The SP shall provide adequate power
points in the Seating area.
Powerpoints shall be provided as per out standard
offering for required no. of seats
No change in RFP terms
10 77/110 Annexure -13 The access logs to the bank specific cage area, seating
area and the server room area need to be maintained
for the period of the contract. The log reports of bank’s
specific server cage area and seating area are to be
provided on a monthly basis.
Log reports shall be maintained for 90 days and
against request from Bank it will be made available
to Bank on Qtrly basis.Bank to provide the storage
media and maintain the same.
Please refer corrigendum
Page 2 of 35
S. No RFP Ref Page
no
RFP Clause no Existing clause Details Change Sought Bank's Response
Bank's Respone to Prebid Queries to RFP for Engagement of Service Provider for Relocation of Near Disaster Recovery Site (NDR) Under Hosting Model
REF No: IDBIBank/ITD/VMG/RFP/2020-21/22, September 08, 2020
11 77/110 Annexure -13 E. Building Management Systems (BMS): 4. There
should be CCTV monitoring for surveillance of the
server hall area. The CCTV surveillance should cover
Bank's Server area and other critical areas where Bank's
components are placed. Activities to be recorded and
kept for at-least 90 days. Bidder should provide Remote
Monitoring Facility of CCTV recordings for Bank’s Server
area where Bank's components are placed.
SP to share the live remote sharing of CCTV of the
Bank cage area remotely to Bank. SP to share the
remote feed within Bank cage area and bank shall be
resposnible for transferring the data further.
No change in RFP terms
12 78/110 Annexure -13 E. Building Management Systems (BMS): 6. The SP shall
provide Fire detection & suppression system exclusively
for the server room which will cover Bank caged area.
Fire detection and suppression can be common
however the areas allocated to the Bank should be well
within the coverage of fire detection and suppression.
No change in RFP terms
13 78/110 Annexure -13 E. Building Management Systems (BMS): 7. The facility
areas proposed for the Bank should be well within the
coverage of water leak detection system.
No change in RFP terms
14 78/110 Annexure -13 F. Miscellaneous: 5.The service provider must ensure all
the necessary support and permissions in this regard
for laying such cables beneath the false flooring is
provided to the system integrator. The system
integrator chosen by the bank will do this cabling
activity in consultation with the service provider.
Bank will appoint its own Structural cabling vendor,
please confir.
a) All Data Cable will run from Top over the shared
Data cable trays of cabofil and DC SP will additionally
only provide permission and approvals to the Bank
appointed Structural cabling vendor.
Please refer Corrigendum
15 78/110 Annexure -13 F. Miscellaneous: 6. Bank cannot provide any time
frame to inform SP for taking up additional space. The
additional seating space if required should be in the
same building
Additional space shall be provided based on the
availability, however bank will receive first right of
refusal
No change in RFP terms
16 81/110 Annexure -13 F. Miscellaneous:11. The service provider is required to
make provision for power meter / dedicated measuring
equipment / dedicated PDU to measure power
consumption by the Bank. Payments will be made by
the bank only on the basis of consumed power. The
Bidder shall provide power readings
Bank to advice on the requirement of dedicated PDU
since all the Mechnaical and electrical equipments
are generally shared resources offered by SP.We
also assume that power consumption shall be
metered at PDU level by using BCPM software for
rackwise power consumption. Bank to confirm.
No change in RFP terms
Bidder has to provide power meter
/ dedicated measuring equipment /
dedicated PDU's for Bank's cage
area / racks.
Page 3 of 35
S. No RFP Ref Page
no
RFP Clause no Existing clause Details Change Sought Bank's Response
Bank's Respone to Prebid Queries to RFP for Engagement of Service Provider for Relocation of Near Disaster Recovery Site (NDR) Under Hosting Model
REF No: IDBIBank/ITD/VMG/RFP/2020-21/22, September 08, 2020
17 81/110 Annexure -13 F. Miscellaneous: 12. The Bank requires a dedicated
power meter that can measure the actual power
consumption by the Bank’s equipment. This power
usage will be ONLY for the racks that are setup for Bank
and not any other environmental devices such as
precision air conditioners etc. The factor considered for
conversion from KV to KW is (0.9).
Request Bank to accept Power metering from PDU
BCPM( Branch Circuit Power Monitoring ). Please
Confirm.
No change in RFP terms
Bidder has to provide power meter
/ dedicated measuring equipment /
dedicated PDU's for Bank's cage
area / racks.
18 108/110 Annexure -23 Inventory to be shifted from NDR BKC to Proposed site. A. Only 6 racks details are available, requesting IDBI
to provide the details of remaining 2 nos. of racks
B. Is rack supply part of bidder's scope, please clarify
No change in RFP terms
A. Out of 8 racks, 2 are spare
B. Existing Racks to be shifted from
the current NDR site to the
proposed site by the Bidder.
19 108/110 Annexure -23 Row 1 Rack no 4 Storage rack, 32 A/1P/4S for 22kW rack
SAN storage.
32A, single phase 4 sockets (2+2) are not sufficient
to cater 22kW. Please clarify and confirm the rating.
No change in RFP terms.
In the existing setup four single
phase sockets are available.
Bidder may visit the exisiting NDR
site for obtaining more clarity as
mentioned in the RFP Annexure 13,
clause A.6
20 108/110 Annexure -23 Row 1 Rack no 4 Storage rack. Rack 1 Row no. 1 - 32A/1P/4S switch is mentioned.
We understand that here we have to provide 4
circuits of 32A, please confirm.
No change in RFP terms.
In the existing setup four single
phase sockets are available.
Bidder may visit the exisiting NDR
site for obtaining more clarity as
mentioned in the RFP Annexure 13,
clause A.6
21 27/110 Section 2 1. Payment Terms Please provide Bank's preferred payment terms. No change in RFP terms.
Page 4 of 35
S. No RFP Ref Page
no
RFP Clause no Existing clause Details Change Sought Bank's Response
Bank's Respone to Prebid Queries to RFP for Engagement of Service Provider for Relocation of Near Disaster Recovery Site (NDR) Under Hosting Model
REF No: IDBIBank/ITD/VMG/RFP/2020-21/22, September 08, 2020
22 10/110 Security Deposit/PBG Successful Bidder/s will have to give Security Deposit of
10% of 1st year cost (One Time Cost+ Annual Recurring
Cost) in the form of Performance Bank Guarantee (PBG)
Issued by a scheduled commercial bank (other than IDBI
Bank Ltd) with a validity of 72 months (60 months
contract period + 12 months claim period) from the
date of issue of PBG and directly forwarded to the Bank.
The PBG will have to be renewed / resubmitted with
fresh validity of Six months (includes Six months
Supplementary Contract Period and a claim period of 12
months (total 18 months) at the end of five year of
original contract period in case of extension of the
contract.
The PBG will be issued for a period of one year and
will be renewed every year subsequently, request
Bank to accept the same.
Please refer corrigendum
24 27/110 Section 2 - 1. Payment
Terms
1.4. Cost of the One Time charges and transit insurance
at actuals would be payable on successful
commissioning and completion of the acceptance test
exercise by the Bank from the new site for all the
activities/ services deemed to be one time installations
in this RFP document. The transit insurance (original
policy to be purchased in the name of the Bank) will be
reimbursed at actuals after commissioning the Near DR
and full acceptance by the Bank
Request Bank to accept advance for the OTC
charges.
No change in RFP terms
25 27/110 Section 2 - 1. Payment
Terms
1.5. The payment for hosting of the NDR Centre
including network link charges will be divided into four
equal installments for the year and paid quarterly in
arrears post the successful commissioning of the
cohosting site, acceptance of all the relevant
requirements under this tender and delivery of services
as per the RFP
Request Bank to accept quarterly in advance for the
recurring charges. And Power charges to be paid in
Monthly in arrears.
No change in RFP terms
26 29/110 5. DELIVERY AND TIME
LIMIT FOR
COMMENCEMENT OF
WORK: PERIOD &
LOCATION
5.1. The Delivery and time limit for commencement of
work shall be done at the specified locations (NDRBKC
to proposed Data Center site) within 6 Weeks from the
issuance of Purchase Order. The Bidder should deliver
services to the Bank as per the requirement of this RFP
as per below mentioned timelines:
Request Bank to accept delivery and time limit
within 6-8 weeks from the issuance of Purchase
order.
No change in RFP terms
Page 5 of 35
S. No RFP Ref Page
no
RFP Clause no Existing clause Details Change Sought Bank's Response
Bank's Respone to Prebid Queries to RFP for Engagement of Service Provider for Relocation of Near Disaster Recovery Site (NDR) Under Hosting Model
REF No: IDBIBank/ITD/VMG/RFP/2020-21/22, September 08, 2020
27 The bidder must have
provided co-hosting space for
at least 10 rack space area per
customer in
Tier III Data Centre colocation
facility at the
PROPOSED SITE for the bank
in India (Banks of Indian origin).
Marks shall be given as detailed below
based on the project
Credentials submitted.
Bidder will have to submit copy of PO
and reference contact details as per
Annexure-22.
Kindly ammedn this clause as:-
The bidder must have
provided co-hosting space for
at least 10 rack space area per
customer in
Tier III Data Centre colocation
facility at the
PROPOSED SITE for the bank
in India (Banks of Indian origin).
Marks shall be given as detailed below
based on the project
Credentials submitted.
Bidder will have to submit copy of PO
and reference contact details as per
Annexure-22.
No change in RFP terms
28 One customer with at least 10 racks - 5 Mark One customer with at least 10 racks - 20 Marks No change in RFP terms
29 Two customer with at least 10 racks - 10 Mark One customer with at least 08 racks - 15 Marks No change in RFP terms
30 Three customer with atleast10 racks - 15 mark One customer with at least 05 Racks - 10 Marks No change in RFP terms
31 More than three customer with at least 10 racks - 20
Mark
One customer with at least 02 Racks- 05 Marks No change in RFP terms
32 29 5. DELIVERY AND TIME
LIMIT FOR
COMMENCEMENT OF
WORK: PERIOD &
LOCATION
1. Making the server area ready and available for
installation of the Bank’s IT infrastructure (Site should
be ready with electrical and network cabling and other
facilities like CCTV, access control system etc. as
mentioned in SoW)
3 weeks from the date of issuing the purchase order to
the SP
Kindly Ammend the Clause as:-
Making the server area ready and available for
installation of the Bank’s IT infrastructure (Site
should be ready with electrical and network cabling
and other facilities like CCTV, access control system
etc. as mentioned in SoW)
4 weeks from the date of issuing the purchase order
to the SP
No change in RFP terms
33 29 5. DELIVERY AND TIME
LIMIT FOR
COMMENCEMENT OF
WORK: PERIOD &
LOCATION
2. Shifting of empty server racks & spare switches and
installation of same in the proposed server area.
4 weeks from the date of issuing the purchase order to
the SP
Kindly Ammend the Clause as:-
Shifting of empty server racks & spare switches and
installation of same in the proposed server area.
6 weeks from the date of issuing the purchase order
to the SP
No change in RFP terms
22 B. Bidders Past Experience
Page 6 of 35
S. No RFP Ref Page
no
RFP Clause no Existing clause Details Change Sought Bank's Response
Bank's Respone to Prebid Queries to RFP for Engagement of Service Provider for Relocation of Near Disaster Recovery Site (NDR) Under Hosting Model
REF No: IDBIBank/ITD/VMG/RFP/2020-21/22, September 08, 2020
34 29 5. DELIVERY AND TIME
LIMIT FOR
COMMENCEMENT OF
WORK: PERIOD &
LOCATION
3. NW links commissioning between DC and Near DR,
DR and Near DR
5 weeks from the date of issuing the purchase order to
the SP
Kindly Ammend the Clause as:-
NW links commissioning between DC and Near DR,
DR and Near DR
8 weeks from the date of issuing the purchase order
to the SP
No change in RFP terms
35 29 5. DELIVERY AND TIME
LIMIT FOR
COMMENCEMENT OF
WORK: PERIOD &
LOCATION
4. Shifting of all IT related equipment from BKC to
proposed Data Center site.
6 weeks from the date of issuing the purchase order to
the SP
Kindly Ammend the Clause as:-
Shifting of all IT related equipment from BKC to
proposed
Data Center site.
10 weeks from the date of issuing the purchase
order to the SP
No change in RFP terms
36 29 5. DELIVERY AND TIME
LIMIT FOR
COMMENCEMENT OF
WORK: PERIOD &
LOCATION
Actual Switch off the devices from BKC and switch on at
the proposed Hosting Site & activation of Data
connectivity Links
The proposed Near DR to be up and functional within
48 hours from switch off at BKC.
Kindly Ammend the Clause as:-
Actual Switch off the devices from BKC and switch
on at the proposed Hosting Site & activation of Data
connectivity Links
The proposed Near DR to be up and functional
within 1 week from switch off at BKC.
No change in RFP terms
37 30 5. DELIVERY AND TIME
LIMIT FOR
COMMENCEMENT OF
WORK: PERIOD &
LOCATION
5. Hosting & power-on will be effective only after
shifting of IT related equipment inside server room of
proposed Data Center site
6 weeks from the date of issuing the purchase order to
the SP. (Site readiness in all aspects including NW links
commissioning between DC and Near DR, DR and Near
DR)
KIndly Ammend the Clause As:-
Hosting & power-on will be effective only after
shifting of IT related equipment inside server room
of proposed Data Center site
10 weeks from the date of issuing the purchase
order to the SP. (Site readiness in all aspects
including NW links commissioning between DC and
Near DR, DR and Near DR)
No change in RFP terms
38 30 5. DELIVERY AND TIME
LIMIT FOR
COMMENCEMENT OF
WORK: PERIOD &
LOCATION
6. Project Commissioning Timeline
6 Weeks from the date of issuing the purchase order to
the SP
Kindly Ammend the Clause As:-
Project Commissioning Timeline
10 Weeks from the date of issuing the purchase
order to the SP
No change in RFP terms
Page 7 of 35
S. No RFP Ref Page
no
RFP Clause no Existing clause Details Change Sought Bank's Response
Bank's Respone to Prebid Queries to RFP for Engagement of Service Provider for Relocation of Near Disaster Recovery Site (NDR) Under Hosting Model
REF No: IDBIBank/ITD/VMG/RFP/2020-21/22, September 08, 2020
39 76 A. General 11. 99.982% Uptime is required for the Near DR
Environmental Infrastructure and services. 99.99%
Uptime is required
for the network availability.
As per the RFP Tier III compliance the required
infrastructure should be 99.982%, Request you to
kindly considred the same.
No change in RFP terms
40 76 B. Server Room Area Bank envisages requirement of a dedicated clear space
to accommodate 8 Racks (42U).In case the racks are
arranged in two rows, the distance of 3 ft. should be
maintained between the rows of the racks. Also there
should
be at least 3 ft. gap kept between Racks and caged area
in front and back side. However, if there is requirement
of
additional space in the future the SP should be able to
provide the same (within the same facility) as per the
agreed rate contract.
Kindly confirm the additional total no. of racks which
is required for future expansion.
No change in RFP terms.
Bank shall share the additional
requirements as and when it
evolves
41 85 14. (SERVICE LEVEL
EXPETATIONS AND
PENALTY - ANNEXURE
14)
Level
I. Critical
Type of Infrastructure
Environmental
Infrastructure
Function Technology
a. Access controls
b. UPS supply
c. Precision Air
conditioning
d. Fire Detection System
e. Water detection
systems
f. Humidity Controllers
g. Gen-sets
h. Building Management
Systems
i. LAN cabling
j. Power
Expected Response Time
Immediate
Resolution
Within 10
minutes
It seems it is very less time to react to the
mentioned scenario for the critical infrastructure, so
kindly changes the satement from 10 minutes to 30
minutes
Please refer the corrigendum
Page 8 of 35
S. No RFP Ref Page
no
RFP Clause no Existing clause Details Change Sought Bank's Response
Bank's Respone to Prebid Queries to RFP for Engagement of Service Provider for Relocation of Near Disaster Recovery Site (NDR) Under Hosting Model
REF No: IDBIBank/ITD/VMG/RFP/2020-21/22, September 08, 2020
42 86 14. (SERVICE LEVEL
EXPETATIONS AND
PENALTY - ANNEXURE
14)
Level
II. Key
Type of Infrastructure
Environmental
Infrastructure
Function Technology
All other environmental
infrastructure being a
part of SP solution and
not considered as
critical.
Expected Response Time
Minimum 30 Minutes
Resolution
Within 10
minutes
It seems it is very less time to react for the
mentioned scenarion i.e Key enviornmental
infrastructure, so kindly changes the satement from
30 Minutes to 1 Hour.
Please refer corrigendum
43 88 B. Service level
definitions for
Network Bandwidth
Level
II. Critical
Type of Infrastructure
(Network Bandwidth Fibre)
Function Technology
a. Links between DC & Near
DR
b. Links between DR and
Near DR
c. Links between DC,
Belapur to Hosting
location for Monitoring
purpose
Expected Response Time
within 10 Minutes
It seems it is very less time to react to the
mentioned scenario for the critical infrastructure, so
kindly changes the satement from 10 minutes to 30
minutes
Please refer corrigendum
44 General Queries General Queries Kindly Provide the Commercial Format Details as it is
not mentioned in the RFP.
No change in RFP terms
Page 9 of 35
S. No RFP Ref Page
no
RFP Clause no Existing clause Details Change Sought Bank's Response
Bank's Respone to Prebid Queries to RFP for Engagement of Service Provider for Relocation of Near Disaster Recovery Site (NDR) Under Hosting Model
REF No: IDBIBank/ITD/VMG/RFP/2020-21/22, September 08, 2020
45 21 5. TECHNICAL BID EVALUATION (SECOND STAGE)2. Bidders Past Experience – detailed below in 5.11.B-
20 Marks
The bidder must have provided co-hosting space for at
least 10 rack space area per customer in
Tier III Data Centre colocation facility at the
PROPOSED SITE for the bank in India (Banks of Indian
origin).
Marks shall be given as detailed below based on the
project Credentials submitted.
a. One customer with at least 10 racks- 5 Marks
b.Two customer with at least 10 racks-10 marks
c. |Three customer with atleast 10 racks-15 Marks
d. More than three customer with at least 10 racks- 20
Marks
We request the Bank to modify the clause as " The
bidder must have provided co-hosting space for at
least 10 rack space area per customer in
Tier III Data Centre colocation facility at any of the
Bidder's Datacenter in India for BFSI/Banking
Customers.
Marks shall be given as detailed below based on the
project Credentials submitted.
a. One customer with at least 10 racks- 5 Marks
b.Two customer with at least 10 racks-10 marks
c. |Three customer with atleast 10 racks-15 Marks
d. More than three customer with at least 10 racks-
20 Marks "
Please refer corrigendum
46 21 5. TECHNICAL BID EVALUATION (SECOND STAGE)5. If the proposed data center is Tier IV standard-
5 marks
We request the Bank to change this to Tier III
standard .
No change in RFP terms
47 29 5. DELIVERY AND TIME
LIMIT FOR
COMMENCEMENT OF
WORK: PERIOD &
LOCATION
The Delivery and time limit for commencement of work
shall be done at the specified locations (NDR-
BKC to proposed Data Center site) within 6 Weeks from
the issuance of Purchase Order
We request the Bank to modify the clause as " The
Delivery and time limit for commencement of work
shall be done at the specified locations (NDR-
BKC to proposed Data Center site) within 8 Weeks
from the issuance of Purchase Order "
No change in RFP terms
48 57 4. UNCONDITIONAL
ACCEPTANCE OF
TERMS & CONDITIONS
OF THE RFP
(ANNEXURE – 4)
This is to confirm that we absolutely & unconditionally
accept all the terms and conditions (including scope of
work) as mentioned
We request Bank to allow the bidders to propose
some deviations in the terms and conditions (
including scope of work) , which can be mutually
discussed and agreed at the time of contract
finalization
No change in RFP terms
49 75 13. PROJECT SCOPE
AND TECHNICAL
CAPABILITIES
(ANNEXURE – 13)
A. General
1. The proposed Near DR site should be located within
25 km radius from Banks Data Centre in CBD BELAPUR,
Navi Mumbai.
We are one of the leading Datacenter Services
Providers and our proposed Datacenter is located in
MMR region . We request the Bank to modify the
clause as " The proposed Near DR site should be
located within 50 km radius from Banks Data Centre
in CBD BELAPUR, Navi Mumbai." This would allow
more Datacenter Services Providers to participate in
the RFP.
No change in RFP terms
Page 10 of 35
S. No RFP Ref Page
no
RFP Clause no Existing clause Details Change Sought Bank's Response
Bank's Respone to Prebid Queries to RFP for Engagement of Service Provider for Relocation of Near Disaster Recovery Site (NDR) Under Hosting Model
REF No: IDBIBank/ITD/VMG/RFP/2020-21/22, September 08, 2020
50 94 17. ELIGIBILITY
CRITERIA COMPLAINCE
SHEET (ANNEXURE –
17)
The Bidder to provide an undertaking on his letter head
that all the technical requirements highlighted as part
of Technical Scope are covered in totality in the
proposal submitted by the bidder.
We request the Bank to allow the Bidder to propose
few deviations, which and be mutually discussed
and agreed at the time of contract finalization
No change in RFP terms
51 94 17. ELIGIBILITY
CRITERIA COMPLAINCE
SHEET (ANNEXURE –
17)
The Bidder should comply with all the
mandatory technical requirement as
mentioned in Annexure 13
We request the Bank to allow the Bidder to propose
few deviations, which and be mutually discussed
and agreed at the time of contract finalization
No change in RFP terms
52 94 17. ELIGIBILITY
CRITERIA COMPLAINCE
SHEET (ANNEXURE –
17)
Self-declaration regarding compliance of
RBI /Govt. guidelines
Request Bank to share the RBI guidelines that the
bidders are required to adhere to.
No change in RFP terms
53 96 17. ELIGIBILITY
CRITERIA COMPLAINCE
SHEET (ANNEXURE –
17)
The SP should have at least three of the
below certifications / compliance document:
a) ISO 27001 or BS 7799–3 Certified (Compulsory)
b) NFPA 70 & 75
c) IS 1893:1984 Seismic Compliance
d) TIA 942 compliance (for at least two of
the following – Architectural, Electrical,
cooling and network
The Proposed Datacenter has recently gone live. The
proposed Datacenter is an extension of our existing
Datacenetrs at our Chandivali Datacenter Campus .
We have all these certifications for our Other
Datacenters located in the same campus. . We will
extend the same certifications to the proposed
Datacenter as well. We request the Bank to allow us
to submit the certifications in next 2-3 months.
No change in RFP terms
54 96 17. ELIGIBILITY
CRITERIA COMPLAINCE
SHEET (ANNEXURE –
17)
The Service Provider's proposed site should
be within a maximum of 25 km radius from
our Data Centre in CBD Belapur, Navi
Mumbai
We are one of the leading Datacenter Services
Providers and our proposed Datacenter is located in
MMR region . We request the Bank to modify the
clause as " The proposed Near DR site should be
located within 50 km radius from Banks Data Centre
in CBD BELAPUR, Navi Mumbai." This would allow
more Datacenter Services Providers to participate in
the RFP.
No change in RFP terms
Page 11 of 35
S. No RFP Ref Page
no
RFP Clause no Existing clause Details Change Sought Bank's Response
Bank's Respone to Prebid Queries to RFP for Engagement of Service Provider for Relocation of Near Disaster Recovery Site (NDR) Under Hosting Model
REF No: IDBIBank/ITD/VMG/RFP/2020-21/22, September 08, 2020
55 17. ELIGIBILITY
CRITERIA COMPLAINCE
SHEET (ANNEXURE –
17)
a) Bidder must have provided DC or DRC or
Near DR / DC co-hosting facility to at least
10 Companies co-hosting sites in India,
b) Out of which there should be at least 1
credentials of Schedule Commercial Banks
and 1 BFSI in India who have co–hosted
their data center or disaster recovery site or
Near DR site with the service provider at
proposed Near DR.
c) Minimum of 4 Racks or 200 sqft. area for
each of these 2 sites referred in point (b)
above and should have been co-hosted as
on RFP date. It should have been hosted for
at least for 1 year).
We request the Bank to modify the clause as
" a) Bidder must have provided DC or DRC or
Near DR / DC co-hosting facility to at least
10 Companies at any of the Bidder's co-hosting sites
in India,
b) Out of which there should be at least 1
credentials of Schedule Commercial Banks
and 1 BFSI in India who have co–hosted
their data center or disaster recovery site or
Near DR site with the service provider at any of the
Bidder's Datacenter in India .
c) Minimum of 4 Racks or 200 sqft. area for
each of these 2 sites referred in point (b)
above and should have been co-hosted as
on RFP date. It should have been hosted for
at least for 1 year).
No change in RFP terms
56 75 Annex 13: A.4 The Bank may in future require additional space at the
Near DR site.
Can bank suggest the indicative sizing for this
expansion requirement?
No change in RFP terms.
Bank shall share the additional
requirements as and when it
evolves
57 76 Annex 13: B.3 The specification for the 8 no. of Racks…. Client to share details:
1. What are the physical dimensions (WxDxH) of the
racks?
2. Who provides the physical racks and rPDUs?
3. What is the indicative consumed IT load per rack?
1. Rack dimension is 800 mm X 1000
mm. Please refer the corrigendum.
2. The Bank will provide the racks
as mentioned in the RFP Annexure
13 clause no. A.4. Please refer the
corrigendum for more clarity
3. No change in RFP terms. Please
refer the RFP Annexure 23.
Page 12 of 35
S. No RFP Ref Page
no
RFP Clause no Existing clause Details Change Sought Bank's Response
Bank's Respone to Prebid Queries to RFP for Engagement of Service Provider for Relocation of Near Disaster Recovery Site (NDR) Under Hosting Model
REF No: IDBIBank/ITD/VMG/RFP/2020-21/22, September 08, 2020
58 76 Annex 13: B.7 The temperature in the server hall (caged area) should
be maintained at 20 +/- 4deg C, i.e. the temperature
should be in the range of 16 to 24deg C.
Request client to consider 22 to 26C (i.e. 22 +/- 2C)
temperature range
No change in RFP terms
59 76 Annex 13: B.10 ….inter-rack Ethernet copper cabling (supporting 1/10
Gbps) and fibre cabling…..
Client to share details:
1. Which rack to which racks how many cables of
each type (CAT6/CAT6A/SMF/MMF)?
2. Is it a top of rack switch/patch panel
arrangement?
3. Any specific arrangement of rack placement?
No change in RFP terms.
1. Rack to rack details & Cable type
(CAT 6A & Multi Mode Fiber) are
already mentioned in the RFP
Annexure 13 clause no G.3
2. Bidder to decide as the patch
panel is in bidders scope.
3. Please refer Annexure 13 clause
1.10 page no. 82
60 77 Annex 13: D.2 The link extension from the DC/DR service provider’s
communication, MUX room to the server cage area at
Near DR Site shall be done by the Near DR Site service
provider without involving any commercials.
As a standard practice, there is a monthly recurring
charge (MRC) fee applicable for cross-connect
services.
No change in RFP terms.
Please refer the Indicative
commercial bid- Bill of material
format. Bidder to include this cost
in commercials as per the RFP terms
61 77 Annex 13: E.4 Bidder should provide Remote Monitoring Facility of
CCTV recordings for Bank’s Server area where Bank's
components are placed.
Request bank to remove this sentence as remote
monitoring/ video sharing is a potential security risk.
All videos are available for audits/ security screening
on site at the facility premises
No change in RFP terms
62 78 Annex 13: F.5 The cabling within / between the racks will be done by
the system integrator chosen the Bank.
This is contradicting para B.10 of Annex 13. Please
suggest.
Please refer Corrigendum
63 80 Annex 13: H.10 The power protection devices maybe capable of SNMP
communications and with the facility to issue alarms via
text SMS and emails.
Alarms are monitored locally by the facility
operations staff and actioned upon as required.
These alarms are not extended to clients. Request to
please remove this sentence.
No change in RFP terms
power protection devices should
issue alarms via text SMS and emails
to the facility operations staff
posted at the DC
Page 13 of 35
S. No RFP Ref Page
no
RFP Clause no Existing clause Details Change Sought Bank's Response
Bank's Respone to Prebid Queries to RFP for Engagement of Service Provider for Relocation of Near Disaster Recovery Site (NDR) Under Hosting Model
REF No: IDBIBank/ITD/VMG/RFP/2020-21/22, September 08, 2020
64 80 Annex 13: H.11 The service provider is required to make provision for
power meter / dedicated measuring equipment /
dedicated PDU to measure power consumption by the
Bank.
Power consumption is monitored at BMS level using
BCPM enabled PDUs; and hence dedicated PDUs/
Meters is not required.
Please share concurrence.
No change in RFP terms
Bidder has to provide power meter
/ dedicated measuring equipment /
dedicated PDU's for Bank's cage
area / racks.
65 Annex 14: 4 The SLA charges will be subject to an overall cap of 10%
of the Annual Recurring Charges (ARC) then the Bank
will have the right to cancel the contract.
This is very steep as it means a single outage
resulting in uptime <=97%, can result in contract
termination.
Termination should be considered an option only for
3 such incidents in a 6 months rolling period.
In case of one or two incidents (instead of
termination), alongside penalty,and EGM
(emergency general meeting) of senior personnel
from both parties should try to discuss and resolve
the persistent issue
Request bank to reconsider.
No changes in RFP terms.
The SLA charges will be subject to
an overall cap of 10% of the Annual
Recurring Charges (ARC), after
which the Bank will have the right
to cancel the contract.
66 11 3.1 Consortium Any type of formation of consortium, sub-contracting
and joint assignments will not be allowed/ considered
for the submission of the proposal. Such proposals will
be disqualified.
We request the Bank to allow subcontracting. No change in RFP terms
67 25 13.1. Signing of
Contract
After the Bank notifies the Successful Bidder that its bid
has been accepted; the Bidder should sign the Contract
and complete the execution of all other documents to
the satisfaction of the Bank.
Terms of proposed contract should be mutually
discussed and agreed upon between the Parties. The
Bidder shall not be compelled to execute a contract
containing unilateral terms. Failure/ dealy in
executing such contract containing unilateral terms
shall not be deemed to be a failure on behalf of the
Bidder.
No change in RFP terms
68 27 1. Payment Terms Suggest to add:
In case of any delay/ non payment of fees by the
Bank, the Bidder shall be entitled to suspend the
services or terminate the agreement by issuing a
written notice of 5 days.
No change in RFP terms
Page 14 of 35
S. No RFP Ref Page
no
RFP Clause no Existing clause Details Change Sought Bank's Response
Bank's Respone to Prebid Queries to RFP for Engagement of Service Provider for Relocation of Near Disaster Recovery Site (NDR) Under Hosting Model
REF No: IDBIBank/ITD/VMG/RFP/2020-21/22, September 08, 2020
69 33 7.1 Indemnity The Bidder shall execute and furnish to the
Bank/Purchaser, a deed of indemnity in favor of the
Purchaser in a form and manner, as given in Annexure
10, indemnifying the Purchaser its directors, employees,
agents and representatives from and against any costs,
loss, damages, expense, claims, litigations, suits,
actions, judgments, and or otherwise including but not
limited to those from third parties or liabilities of any
kind howsoever suffered, arising out of or incurred inter
alia during and after the Contract period including but
not limited to third-party claims due to infringement of
Intellectual Property Rights including but not limited to
patent, trademark, logo, copy-rights or industrial
drawings and designs arising from use of the Services or
any part thereof and/or otherwise. . The Bidder has to
execute the indemnity in the format prescribed by the
Bank and provide in Annexure - 10 of this RFP.
We suggest to modify indemnity clause with a view
that either party to indemnify each other for the
following:
1. For third party IPR infringement claims
2. For Wilful misconduct or gross negligence, causing
loss or damages to a person resulting into personal
injury or death.
3. Third party claims if arises due to the intentional
wrongs committed by either party.
Provided that the indemnification obligations shall
be subject to following :-
a) Immediate notice to be sent by the Indemnified
party.
b) Control of the defence of the claim by the
indemnifying party.
c) Assistance by the indemnified party in the defence
at the expense of the indemnifying party.
No change in RFP terms
70 34 8.1 Intellectual
Property Rights
The Bank/ Purchaser shall own and have a right in
perpetuity to use all Intellectual Property Rights which
have arisen out of or in connection with the
implementation of this Contract, including all processes
and products which have been developed by the Bidder
during the performance of Services and for the
purposes of inter-alia use or sub-license of such
Services under this Contract.
The Bidder shall retain all rights and title to the
intellectual property belonging or introduced by the
Bidder. Execution of this agreement does not
envisage any transfer of IP rights from the Bidder to
the Bank.
No change in RFP terms
71 34 8.4 Intellectual
Property Rights
If the Successful Bidder fails to comply and the Bank is
required to pay compensation to a third party resulting
from such infringement, the Successful Bidder shall be
responsible for the compensation including all
expenses, court costs and lawyer fees. The Bank will
give notice to the Successful Bidder of such claim, if it is
made, without delay
The Bidder shall not be liable to pay any
compensation in case the Bank itself has contributed
to the breach of IP rights. In such a case, the Bank
shall be liable to indemnnify the Bidder for the claim
amount made on the Bidder including but not
limited to all expenses, court costs and lawyers fees.
No change in RFP terms
Page 15 of 35
S. No RFP Ref Page
no
RFP Clause no Existing clause Details Change Sought Bank's Response
Bank's Respone to Prebid Queries to RFP for Engagement of Service Provider for Relocation of Near Disaster Recovery Site (NDR) Under Hosting Model
REF No: IDBIBank/ITD/VMG/RFP/2020-21/22, September 08, 2020
72 36 15.1 Liquidated
damages
If the Vendor fails to deliver any or all of the Service(s) /
Systems or perform the Services within the time
period(s) specified in the Contract / Agreement / fails to
meet the Service Level Requirements, the Bank /
Purchaser shall, without prejudice to its other rights
and remedies under and in accordance with the
Contract / Agreement, deduct from the Contract price,
as liquidated damages, a sum equivalent to 1% per
week or part thereof of 1st year cost (One Time Cost+
Annual Recurring Cost) subject to maximum deduction
of 5% of ‘of 1st year cost (One Time Cost+ Annual
Recurring Cost)’ of the delayed Service(s) or
unperformed Service(s). However, Bank reserves the
right to terminate the contract at any time, if the
project is not delivered as per scheduled timelines.
We suggest to remove the liquidated damages
clause. Anyways Bank is proposing to terminate the
contract in case project is not delivered as per
scheduled timelines.
No change in RFP terms
73 36 15.1.2 Liquidated
damages
The Bank / IDBI / the Purchaser may without prejudice
to its right to effect recovery by any other method,
deduct the amount of liquidated damages from any
money belonging to the Vendor in its hands (which
includes IDBI's/ the Purchaser’s right to claim such
amount against Vendor's Bank Guarantee) or which
may become due to the Vendor. Any such recovery or
liquidated damages shall not in any way relieve the
Vendor from any of its obligations to complete the
works / service(s) or from any other obligations and
liabilities under the Contract / Agreement.
We suggest that the Bank shall not unilaterally
adjust and/ or deduct any amount from the amount
belonging to Vendor. Any such adjustment or
deduction shall be only after discussing and mutually
agreeing with the Bidder.
No change in RFP terms
74 39 21.1. Successful Bidder
Obligation
The Successful Bidder will abide by the job safety
measures prevalent in India and will free / indemnify
Purchaser from all demands or responsibilities arising
from accidents or loss of life, the cause of which is the
Bidder’s negligence.
Generic job safety measures will be carried out.
However in case there are any specific measures to
be taken then the Bank to intimate the same to the
Bidder prior hand in writing, failing which the Bank
shall be liable for any incident.
No change in RFP terms
75 39 22.1 Subcontracting Any type of formation of consortium, sub-contracting
and joint assignments will not be allowed/ considered
for the submission of the proposal. Such proposals will
be disqualified
We request the Bank to allow subcontracting. No change in RFP terms
Page 16 of 35
S. No RFP Ref Page
no
RFP Clause no Existing clause Details Change Sought Bank's Response
Bank's Respone to Prebid Queries to RFP for Engagement of Service Provider for Relocation of Near Disaster Recovery Site (NDR) Under Hosting Model
REF No: IDBIBank/ITD/VMG/RFP/2020-21/22, September 08, 2020
76 40 24.3 No set off,
Counter claims, cross
claims
However, IDBI Bank shall have such rights against the
successful Bidder up to maximum of 100% of the
contact value.
Bank shall not unilaterally set off or deduct any
amount. This shall be discussed and mutually agreed
with the Bidder.
No change in RFP terms
77 40 25.1 Tri partite
Agreement
The Bidder shall enter into relevant agreement covering
all related Parties at a later date, if required,
incorporating the requisite terms and conditions herein
in the form and manner and to the satisfaction of
Purchaser
Need clarity on this requirement. Which related
parties are referred here?
No change in RFP terms
78 40 27.1 Statutory
requirements
During the tenure of this Contract nothing shall be done
by the Bidder in contravention of any law, act and/ or
rules/regulations, there under or any amendment
thereof governing inter-alia customs, foreign exchange,
etc., and shall keep Purchaser indemnified in this
regard.
We suggest that this should be a mutual clause. No change in RFP terms
79 40 27. 2 Statutory
requirements
Successful Bidder undertakes to promptly produce all
records and information relating to the Contract/this
RFP for the purpose of inspection and audit of IDBI
Bank. Successful Bidder shall provide access, to officers
/ employees / representatives / agents or auditors of
the Bank to the premises / places where such records
are kept / maintained. The Bank shall not be duty
bound to give any prior notice to Successful Bidder
before carrying out the said inspection or audit
1. Information only w.r.t. this project will be
provided to the Bank.
2. Books of accounts will not be provided to the
Bank;
3. Bank shall provide a prior notice of at least 7 days
before any inspection.
4. Person conducting inspection shall be governed
by confidentiality obligations which shall not be less
stringent then the terms contained herein.
No change in RFP terms
80 41 28.1 Purchasers right
of inspection and
periodic audit
The Purchaser reserves the right to inspect and
monitor/assess the progress of the project at any time
during the course of the Contract. The Purchaser may
demand and upon such demand being made, the
Purchaser shall be provided with any document, data,
material or any other information, which it may require,
to enable it to assess the progress of the project.
1. Information only w.r.t. this project will be
provided to the Bank.
2. Books of accounts will not be provided to the
Bank;
3. Bank shall provide a prior notice of at least 7 days
before any inspection.
4. Person conducting inspection shall be governed
by confidentiality obligations which shall not be less
stringent then the terms contained herein.
No change in RFP terms
Page 17 of 35
S. No RFP Ref Page
no
RFP Clause no Existing clause Details Change Sought Bank's Response
Bank's Respone to Prebid Queries to RFP for Engagement of Service Provider for Relocation of Near Disaster Recovery Site (NDR) Under Hosting Model
REF No: IDBIBank/ITD/VMG/RFP/2020-21/22, September 08, 2020
81 41 29.3 Contract Price The Bank reserves the right to re-negotiate the prices in
the event of change in the international market prices
of both the hardware and software.
Even the Bidder should be entitled to revise the
prices due to changes in foreign exchange
fluctuations, taxes, rates etc.
No change in RFP terms
82 42 30.5 Information
Security
Bidder shall provide certificate/assurance from
application providers/OEMs that the application is free
from embedded malicious / fraudulent code.”
Such warranty can only be given on the date of
installation.
No change in RFP terms
83 42 31.1 Ownership and
retention
The Purchaser shall own the documents, information,
materials etc. prepared by or for the Bidder arising out
of or in connection with this Contract.
Ownership of all docuemnts, information, materials
prepared by Bidder shall be retained with the Bidder
only.
No change in RFP terms
84 43 32.7 Representations
and warranties
That the Bidder shall procure insurance policies for all
its present and future property and assets that are
developed, procured and created during the term of
this Contract with financially sound and reputable
insurers to the satisfaction of the Purchaser and shall
pay all premium in relation thereto and shall ensure
that nothing is done to make such insurance policies
void or voidable. The Bidder shall also furnish to the
Purchaser a certificate evidencing such insurance, risks
covered, names of beneficiaries, expiration dates,
names of insurers and all other features of the
insurance policy, both original and renewed and shall
keep the same alive during the term of this Contract.
Bank to obtain insurance of all assets belonging to
the Bank.
No change in RFP terms
85 44 32.16 Representations
and warranties
That the Bidder confirms that there has not and shall
not occur any execution, amendment or modification of
any agreement/contract without the prior written
consent of the Purchaser, which may directly or
indirectly have a bearing on the Contract or the project.
Any changes required by the Bidder will be discussd
with the Bank, which the Bank shall reasonably
consider.
No change in RFP terms
Page 18 of 35
S. No RFP Ref Page
no
RFP Clause no Existing clause Details Change Sought Bank's Response
Bank's Respone to Prebid Queries to RFP for Engagement of Service Provider for Relocation of Near Disaster Recovery Site (NDR) Under Hosting Model
REF No: IDBIBank/ITD/VMG/RFP/2020-21/22, September 08, 2020
86 45 33 Confidentiality 1. Confidenitality provisions to survive for a period
of 3 years after the expriy or termination of contract;
2. Bank shall also be bound by similar confidentilty
provisions for the confidential information shared by
the Bidder with the Bank.
No change in RFP terms
87 45 34.4 Term and
extension of contract
The Bank reserves the right to exit the contract after
serving due notice of 3 months without assigning any
reason
There shall be a fixed lock in period for the Bank,
within which if the Bank intends to terminate for
convenience, then the Bank shall be liable to pay
termination charges.
Even the Bidder shall be entilted to terminate for (i)
convenience, (ii) for non payment/ delayed payment
of fees.
No change in RFP terms
88 48 37.i(c) Termination Notwithstanding the provisions of the Contract and/or
the Bid Documents, the Purchaser at its sole discretion
and without prejudice to any other right or remedy and
without assigning any reasons, by written 90 days’
notice sent to the Bidder, may terminate the Contract,
in whole or in part, at any time for its convenience. The
There shall be a fixed lock in period for the Bank,
within which if the Bank intends to terminate for
convenience, then the Bank shall be liable to pay
termination charges.
Even the Bidder shall be entilted to terminate for (i)
convenience, (ii) for non payment/ delayed payment
of fees.
No change in RFP terms
89 49 38.3 Cosequenses of
termination
..... the Purchaser may retain such amounts from the
payment due and payable by the Purchaser to the
Bidder as may be required to offset any direct losses
caused to the Purchaser as a result of any act/omissions
of the Bidder. In case of any loss or damage due to
default on the part of the Bidder in performing any of
its obligations with regard to executing the scope of
work under this Contract [as laid down in the Service
Specifications,] the Bidder shall compensate the
Purchaser for any such direct loss, damages or other
costs, incurred by the Purchaser.
1. Bank shall make full payment for which services
are already provided.
2. Bank shall not retain / deduct any amount to
offset and losses to the Bank.
3. Bidder shall not be liable to compensate the Bank
for any direct loss, damages or other cost
whatsoever incurred by the Bank.
No change in RFP terms
Page 19 of 35
S. No RFP Ref Page
no
RFP Clause no Existing clause Details Change Sought Bank's Response
Bank's Respone to Prebid Queries to RFP for Engagement of Service Provider for Relocation of Near Disaster Recovery Site (NDR) Under Hosting Model
REF No: IDBIBank/ITD/VMG/RFP/2020-21/22, September 08, 2020
90 51 48.1 Limitation of
liablity
We suggest to modify clause for limitation of liability
as follows:
1. Notwithstanding what is mentioned in RFP,
Contract form or in any other document, in no event
shall either party be liable to the other for any
indirect, incidental, special, consequential,
exemplary or punitive damages including, but not
limited to, damages for lost revenue, lost profits,
loss of goodwill, loss of data, technology, equipment
or types of damages whatsoever, whether or not
caused by any acts of omission or commission and
regardless whether such party has been informed of
the possibility or the likelihood of such damages.
2. Maximum liablity cap as mentioned in clause
48.1(a) shall also include liablity under indemnities
and shall be limited to annual contract value.
3. For breach of services, maximum liability shall be
as per the agreed SLAs.
No change in RFP terms
91 52 49.1 Solicitation of
Employees
The selected Bidder, during the term of the contract
shall not without the express written consent of the
Bank, directly or indirectly: a) recruit, hire, appoint or
engage or attempt to recruit, hire, appoint or engage or
discuss employment with or otherwise utilize the
services of any person who has been an employee or
associate or engaged in any capacity, by the Bank in
rendering services in relation to the contract; or b)
induce any person who shall have been an employee or
associate of the Bank at any time to terminate his/ her
relationship with the Bank.
This clause shall not be applicable in case hiring is
done pursuant to notice issued to public at large.
No change in RFP terms
Page 20 of 35
S. No RFP Ref Page
no
RFP Clause no Existing clause Details Change Sought Bank's Response
Bank's Respone to Prebid Queries to RFP for Engagement of Service Provider for Relocation of Near Disaster Recovery Site (NDR) Under Hosting Model
REF No: IDBIBank/ITD/VMG/RFP/2020-21/22, September 08, 2020
92 88 Annex 14B ( Network
Services) 1 Vi
Response and Resolution Time
The Response and Resolution time for NW links is
mentioned as 10 mins
This is very steep and practically not possible.
We request Response time to be 20 Mins which shall
basically be the ticket logging and response time
from our Helpdesk.
and Resolution time ( MTTR) for each link to be 4
hours from time of call log.
Please refer corrigendum
93 89 Annexure 14B -3 (
Availability
Mesurements)
Replication Link Availability
Uptime for Each replication link is mentioned as 99.99%
per month
This is very steep on each link basis.
On per link basis we can give availability of 99.5%
per month and if both replicaiton links are taken
together for overall site uptime then we can give
99.8% as uptime considering either of two links as
available for site uptime.
No change in RFP terms.
Bidder has to ensure Uptime
availability of 99.99% for each
replication links as mentioned in the
RFP Annexure 14 clause no. B.3
94 90 Annexure 14B -3 (
Availability
Mesurements)
Latency
1Gbps link Round trip time to be less than 2 msec
2 millisecond latency over 25 kms distance should be
possible but it is still very steep on 365*24*7basis.
We request it to be make it to 4 millisecond atleast
for pentalty calculation purpose
No change in RFP terms.
Bidder has to ensure the latency of
<2ms as mentioned in the RFP
Annexure 14 clause no. B.3
95 90 Annexure 14B -3 (
Availability
Mesurements)
Latency
Link between DR in Chennai and links to DC in Mumbai
region
We request 75millisecond to be made as 95 ms No change in RFP terms.
Bidder has to ensure the latency as
mentioned in the RFP Annexure 14
clause no. B.3
Page 21 of 35
S. No RFP Ref Page
no
RFP Clause no Existing clause Details Change Sought Bank's Response
Bank's Respone to Prebid Queries to RFP for Engagement of Service Provider for Relocation of Near Disaster Recovery Site (NDR) Under Hosting Model
REF No: IDBIBank/ITD/VMG/RFP/2020-21/22, September 08, 2020
96 90 Annexure 14B -5 (
Penalty Charges)
Penalty Calcuation for Each Replication Link The penalty is very steep and we humbly requst for
following Penalty as percentate of Monthly reucrring
charges basis ( MRC)
100%-99.5% - No credit
< 99.5% to 99.0% - 3% of MRC
< 99.0% to 98.5% - 5% of MRC
< 98.5% to 98.0% - 8% of MRC
< 98.0% to 97.5% - 12% of MRC
< 97.5 % to 97.0% - 15% of MRC
< 97%- 25% of MRC value
Right to cancel contract below 97% is steep as even
one outage for 97% can result in cancellation. We
request to have it 3 incidents below 97% in 6 rolling
months as this criteria.
Further the annual cap of 10% is very high and we
request it to be not more than 5% of annual charges
in case of any case whatsoever
No change in RFP terms.
Page 22 of 35
S. No RFP Ref Page
no
RFP Clause no Existing clause Details Change Sought Bank's Response
Bank's Respone to Prebid Queries to RFP for Engagement of Service Provider for Relocation of Near Disaster Recovery Site (NDR) Under Hosting Model
REF No: IDBIBank/ITD/VMG/RFP/2020-21/22, September 08, 2020
97 90 Annexure 14B -5 (
Penalty Charges)
Penalty Calcuation for Each Monitoring Link The penalty is very steep and we humbly requst for
following Penalty as percentate of Monthly reucrring
charges basis ( MRC)
100%-99.5% - No credit
< 99.5% to 99.0% - 2% of MRC
< 99.0% to 98.5% - 4% of MRC
< 98.5% to 98.0% - 6% of MRC
< 98.0% to 97.5% - 10% of MRC
< 97.5 % to 97.0% - 12% of MRC
< 97%- 20% of MRC value
Right to cancel contract below 97% is steep as even
one outage for 97% can result in cancellation. We
request to have it 3 incidents below 97% in 6 rolling
months as this criteria.
Further the annual cap of 10% is very high and we
request it to be not more than 5% of annual charges
in case of any case whatsoever
No change in RFP terms.
98
Pg 94 Bidder must be in Data Centre Co-hosting business for a
minimum period of 4 yrs. (As on RFP date)
Please Consider OEM / Bidder must be in Data
Centre Co-hosting business for a minimum period of
4 yrs. (As on RFP date)
No change in RFP terms.
99
a) Bidder must have provided DC or DRC or
Near DR / DC co-hosting facility to at least
10 Companies co-hosting sites in India,
Requesting Bank to consider has OEM/bidder for
this criteria.
No change in RFP terms.
100
b) Out of which there should be at least 1
credentials of Schedule Commercial Banks
and 1 BFSI in India who have co–hosted
their data center or disaster recovery site or
Near DR site with the service provider at
proposed Near DR.
No change in RFP terms.
101
) Minimum of 4 Racks or 200 sqft. area for
each of these 2 sites referred in point (b)
above and should have been co-hosted as
on RFP date. It should have been hosted for
at least for 1 year)
No change in RFP terms.
Pg 94
Page 23 of 35
S. No RFP Ref Page
no
RFP Clause no Existing clause Details Change Sought Bank's Response
Bank's Respone to Prebid Queries to RFP for Engagement of Service Provider for Relocation of Near Disaster Recovery Site (NDR) Under Hosting Model
REF No: IDBIBank/ITD/VMG/RFP/2020-21/22, September 08, 2020
102
22 / 110 B. Bidders Past ExperienceThe bidder must have provided co-hosting space for at
least 10 rack space area per customer in Tier III Data
Centre colocation facility at the PROPOSED SITE for the
bank in India (Banks of Indian origin). Marks shall be
given as detailed below based on the project
Credentials submitted.
Request to modify this clause as. The bidder
must have provided co-hosting space to 5 customers
from any segment - vertical which includes BFSI /
Corporates / Pvt Organizaitons in their owned Tier III
Data Center colocation facilities.
Please refer the corrigendum
103
27 / 110 Clause No. 1.8 / 1.9 / 1.10The Bank requires a dedicated power meter that can
measure the actual power consumption by the Bank’s
equipment. The charges towards the consumed power
will be payable by the Bank quarterly in arrears after
due verification of the metered units and the electricity
rate as per the formula defined in clause 1.6 above. This
power usage will be ONLY for the racks that are setup
for Bank and not any other environmental devices such
as precision air conditioners etc.
Request change as follows for the wordings marked
in Bold. The charges towards the consumed power
will be payable by the bank monthly in arrears. This
is because the power bills from MSEB is raised - to
be paid by service providers every month and thus
suggest the abave changes
No change in RFP terms
104
27 / 110 Clause No. 1.12 The Bank will pay invoices within a period of 45 days
from the date of receipt of undisputed invoices.
Request changes as follow for the wordings marked
in Bold. The Bank will pay invoices within a period
of 15 days from the date of receipt of undisputed
invoices.
No change in RFP terms
105
29 / 110 Clause No. 5 & 5.1 The Delivery and time limit for commencement of work
shall be done at the specified locations (NDRBKC to
proposed Data Center site) within 6 Weeks from the
issuance of Purchase Order
Sugges to change the delivery period from 6 weeks
to within 8 to 10 weeks from the issuance of
Purchase Order.
No change in RFP terms
106
30/110 Clause No. 5 & 5.5 Bidder will have to pay late delivery charges to the Bank
@ 1% of the total contract value inclusive of all taxes,
duties, levies etc., per week or part thereof, for late
delivery beyond due date of delivery, to a maximum of
5% of the total contract value inclusive of all taxes,
duties, levies etc. If delay exceeds 5 weeks from due
date of delivery / commissioning or late delivery
charges exceeds the maximum percentage of 5%, Bank
reserves the right to cancel the order.
Suggest the change as below. Bidder will have to pay
late delivery charges to the Bank @ 0.5% of the total
contract value inclusive of all taxes, duties, levies
etc., per week or part thereof, for late delivery
beyond due date of delivery, to a maximum of 2% of
the total contract value inclusive of all taxes, duties,
levies etc. If delay exceeds 5 weeks from due date of
delivery / commissioning or late delivery charges
exceeds the maximum percentage of 2%, Bank
reserves the right to cancel the order.
No change in RFP terms
Page 24 of 35
S. No RFP Ref Page
no
RFP Clause no Existing clause Details Change Sought Bank's Response
Bank's Respone to Prebid Queries to RFP for Engagement of Service Provider for Relocation of Near Disaster Recovery Site (NDR) Under Hosting Model
REF No: IDBIBank/ITD/VMG/RFP/2020-21/22, September 08, 2020
107
36/110 Clause No. 15 & 15.1 LIQUIDATED DAMAGES. the Bank / Purchaser shall,
without prejudice to its other rights and remedies
under and in accordance with the Contract /
Agreement, deduct from the Contract price, as
liquidated damages, a sum equivalent to 1% per week
or part thereof of 1st year cost (One Time Cost+ Annual
Recurring Cost) subject to maximum deduction of 5% of
‘of 1st year cost (One Time Cost+ Annual Recurring
Cost)’ of the delayed Service(s) or unperformed
Service(s).
Suggest the change as below. a sum equivalent to
0.5% per week or part thereof of 1st year cost only
(Annual Recurring Cost) subject to maximum
deduction of 2%
No change in RFP terms
108
55/110 Clause No. 2 -
INDICATIVE
COMMERCIAL BID-
BILL OF MATERIAL
(ATTACHED as
Annexure 2 WITH RFP)
Attached separate file with hyperlink:
IndicativeCommercialBidformat-BOM.xlsx
Kindly provide us the indicative commercial bid
format - BOM, since provided hyper link doesn't
open
No change in RFP terms
109
74/110 Clause No. 13 & A
General Sr. No. 4
Bidder should provide space for 8 numbers of racks. The
said number of racks will be shifted from Near DR, BKC.
In order to minimize the Near DR down time, the empty
Racks at Near DR, BKC will be shifted first and the
remaining equipments will be shifted subsequently,
after ensuring that the empty racks shifted initially are
properly erected and fixed at the proposed site. The
equipments to be shifted from Near DR, BKC are
mentioned in the Annexure 23
Give details explanation since the clause is not giving
any clarity related to lift and shift of the racks &
server hardware / assets which will be done by SP or
the bank
No change in RFP terms
Please refer Annexure 13 clause A
110
75/110 Clause No. 13 & A
General Sr. No. 11
99.99% Uptime is required for the network availability Is this clause pertaining to cross connects. Network
availability related to inter-rack cabling is assumed
to be done by the Bank network team
No changes in RFP terms
Existing SAN inter rack fibre cable
can be used as mentioned in RFP
Annexure 13 clause no. B.10
Inter rack cabling / cross connect is
bidders responsibility and hence
included in uptime.
111
76/110 Clause No. 13 & B
Server Room Area Sr.
No. 3
The specification for the 8 no. of Racks to be shifted Kindly provide us the each rack dimension ie of n/w
& server racks, Netapp & IBM racks
Please refer corrigendum
Page 25 of 35
S. No RFP Ref Page
no
RFP Clause no Existing clause Details Change Sought Bank's Response
Bank's Respone to Prebid Queries to RFP for Engagement of Service Provider for Relocation of Near Disaster Recovery Site (NDR) Under Hosting Model
REF No: IDBIBank/ITD/VMG/RFP/2020-21/22, September 08, 2020
112
76/110 Clause No. 13 & B
Server Room Area Sr.
No. 5
Bidder should provide biometric access to the common
entry to the Server room
The clause should read as "The access to be
provided to the Bank caged area & to the common
entry to the server room
No change in RFP terms
113
77/110 Clause No. 13 & E BMS
Sr. No. 1
The SP shall provide Access cards, Gate passes to the 6
personnel who would be regularly visiting the site
Is this clause pertaining to cross connects. Network
availability related to inter-rack cabling is assumed
to be done by the Bank network team
No change in RFP terms
114
78/110 Clause No. 13 & F
Miscellaneous Sr. No. 5
The cabling within / between the racks will be done by
the system integrator chosen the Bank. The service
provider must ensure all the necessary support and
permissions in this regard for laying such cables
beneath the false flooring is provided to the system
integrator. The system integrator chosen by the bank
will do this cabling activity in consultation with the
service provider
Kindly ellaborate further on why your SI will require
access to the false flooring since bank will be doing
inter-rack cabling between the racks
Please refer corrigendum
115
78/110 Clause No. 13 & F
Miscellaneous Sr. No.
13
The Bidder shall provide power readings. Kindly clarify that power would require on rated
basis or consumed. Do you require a separate meter
box for meter reading
Please refer the RFP Annexure 13
clause H.11
116
79/110 Clause No. 13 & G
Network Link and
Bandwidth
Network link requirement Please be informed that the links are to be procured
by the Bank since SP are not an ISP & secondly the
same is not transferable to any third party as per the
ISP norms / DOT guidelines
No change in RFP terms
117
79 & 109/110 Clause No. 13 & E
Network Link and
Bandwidth
Network link requirement - Annexure 24 Kindly provide us your 6 ISPs details for us to check
the feasibility
No changes in RFP terms.
118
80/110 Clause No. 3. Network Cabling Kindly give clarification related to the bifercation of
all the 8 racks since it contradicts the number of
racks ie of of n/w & server racks, Netapp & IBM
racks
Please refer the corrigendum
Rack dimension is 800 mm X 1000
mm.
Out of 8 racks, 2 are spare.
119
80/110 Clause No. 3. H.
POWER SUPPLY
REQUIREMENTS
Minimum 6KVA of power is provided for each standard
rack
Since you have mentioned on page number 80 / 110
(Desirable Technical Requirements Sr. No. 4) Rated
Power of approximate 80 KVA to the Bank's cage
area in the server room which contracdicts the total
power requirement of 6 KVA each rack
No changes in RFP terms.
Consider the power requirements
mentioned in the inventory. Billing
has to be done on actual usage
basis
120
81/110 Clause No. 3. H.
POWER SUPPLY
REQUIREMENTS Point
No. 12
The factor considered for conversion from KV to KW is
(0.9)
As per the data center standard the power factor to
be considered for convesion from KV to KW is 0.8
No change in RFP terms
Page 26 of 35
S. No RFP Ref Page
no
RFP Clause no Existing clause Details Change Sought Bank's Response
Bank's Respone to Prebid Queries to RFP for Engagement of Service Provider for Relocation of Near Disaster Recovery Site (NDR) Under Hosting Model
REF No: IDBIBank/ITD/VMG/RFP/2020-21/22, September 08, 2020
121
84/110 Clause no. 2 Desirable
Technical
Requirements point
number 12
Proposed Data center to maintain the PUE (Power
Utilisation Efficiency) from 1.2 to 1.8
As per the data center standard the PUE is
maintained between 1.5 to 1.8
No change in RFP terms
122
84/110 Clause no. 2 Desirable
Technical
Requirements point
number 13
64 amps 3 phase power sockets will be made available
by Service provider as and when required by Bank
The socket will be 63 amps & not 64 amps Please refer corrigendum
123
84/110 Clause no. 2 Desirable
Technical
Requirements point
number 15
Latency for the 1 Gbps point to point link should be less
than or equal to 1 ms
The latency is completely dependent on ISP provider
& feasibility / availability at both the link POP / sites
No change in RFP terms
124
86/110 Clause No. 4 - Penalty
Charges
The SLA charges will be subject to an overall cap of 10%
of the Annual Recurring Charges (ARC) then the Bank
will have the right to cancel the contract
The SLA charges will be subject to an overall cap of
5% of the Annual Recurring Charges (ARC) then the
Bank will have the right to cancel the contract
No changes in RFP terms.
The SLA charges will be subject to
an overall cap of 10% of the Annual
Recurring Charges (ARC), after
which the Bank will have the right
to cancel the contract.
125
87/110 Clause No. 7 Fault
Reporting, Trouble
Ticketing and Call
Closure Procedure
Any call, which is not resolved within 10 minutes of
reporting, must be informed to Bank
We will share the escalation / resolution matrix
which is a standard process followed by all SP's
No change in RFP terms
126
88/110 B. Service level
definitions for
Network Bandwidth
(vi). Typical Resolution time will be applicable only if
any equipment or Infrastructure is down.
This will be third party dependancies and thus we
can not commit a specific resolution time, however
we will ensure to resolve any such services required
as per escalation matrix
Please refer corrigendum
127
96/110 D. Experience &
Support Infrastructure
b) Out of which there should be at least 1 credentials of
Schedule Commercial Banks and 1 BFSI in India who
have co–hosted their data center or disaster recovery
site or Near DR site with the service provider at
proposed Near DR.
b) Out of which there should be at least 1
credentials of Schedule Commercial Banks / 1
Schedule Bank / 1 Co-operative Bank in India who
have co–hosted their data center or disaster
recovery site or Near DR site with the service
provider at proposed Near DR.
No change in RFP terms
128
98/110 Sr. No. 19 Point No. 10 Information Security Certificate This IS Cerification is not pertaining to the colocation
services proposed to be colocation services & thus
request to remove the same
No change in RFP terms
129
109/110 24. THE TASKS AND
RESPONSIBILITIES
RELATED TO
NETWORKING
Shifting (1st Phase) Please provide us the details pertaining to each row
ownership since it deviates from each other
No chnages in RFP terms
Activity list and Ownership are
clearly mentioned in the RFP -
Annexure 24
Page 27 of 35
S. No RFP Ref Page
no
RFP Clause no Existing clause Details Change Sought Bank's Response
Bank's Respone to Prebid Queries to RFP for Engagement of Service Provider for Relocation of Near Disaster Recovery Site (NDR) Under Hosting Model
REF No: IDBIBank/ITD/VMG/RFP/2020-21/22, September 08, 2020
130
109/110 24. THE TASKS AND
RESPONSIBILITIES
RELATED TO
NETWORKING
Rack Installation - Sr. 14, Cabling, Inter rack connectivity
(patch panel to patch panel), Inter rack Fibre
connectivity (LIU to LIU)
It should be a joint responsibility between IDBI / SP No changes in RFP terms
As mentioned in RFP (Cable laying
should be done by bidder,
connections with devices will be
done by IDBI)
131
94 1 Bidder must be a Government Organization / PSU / PSE
/ partnership firm / LLP or private / public limited
company in India at least for the last 5 years.
Bidder must be a Government Organization / PSU /
PSE / partnership firm / LLP or private / public
limited company in India at least for the last 5 years.
OR
Live and operating data centres having an already
sunk in investment of Rs. 600 cr. or more, but
registered as 'Start up' with Department for
Promotion of Industry and Internal Trade
No change in RFP terms
132
94 2 Bidder must be in Data Centre Co-hosting business for a
minimum period of 4 yrs.
(As on RFP date)
Bidder must be in Data Centre Co-hosting business
for a minimum period of 4 yrs.
(As on RFP date)
OR
Live and operating data centres having an already
sunk in investment of Rs. 600 cr. or more, but
registered as 'Start up' with Department for
Promotion of Industry and Internal Trade
No change in RFP terms
133
95 9 a)The bidder providing the DC facility should have an
annual turnover of at least Rs. 50 Crores per annum in
last three
completed financial years i.e. 2017-18, 2018-19 and
2019-20 (Exclusive of the turnover of associate
companies
Live and operating data centres having an already
sunk in investment of Rs. 600 cr. or more, but
registered as 'Start up' with Department for
Promotion of Industry and Internal Trade
No change in RFP terms
134
95 10 The Bidder should have positive net- worth for 2 years
out of the last 4 financial years i.e. F.Y.2016-17,2017-18,
2018-19 and 2019-20, the Bidders must compulsorily
have a positive net-worth for FY 2019-20
Live and operating data centres having an already
sunk in investment of Rs. 600 cr. or more, but
registered as 'Start up' with Department for
Promotion of Industry and Internal Trade
No change in RFP terms
135
76 13 The data centre facility building should have clear and
marketable title and the Bidder should possess /hold
the same under valid agreement/contracts
The data centre facility should have clear and
marketable title and the Bidder should possess /hold
the same under valid agreement/contracts
No change in RFP terms
Page 28 of 35
S. No RFP Ref Page
no
RFP Clause no Existing clause Details Change Sought Bank's Response
Bank's Respone to Prebid Queries to RFP for Engagement of Service Provider for Relocation of Near Disaster Recovery Site (NDR) Under Hosting Model
REF No: IDBIBank/ITD/VMG/RFP/2020-21/22, September 08, 2020
136
24 7.2 Successful Bidder (L1) will be arrived at through an
Online Reverse Auction (ORA) on Total Cost of
Ownership (TCO). Bank reserves the right to negotiate
the price with the final successful bidder before
awarding the contract.
Request to remove online reverse auction No change in RFP terms
137
78 F. Miscellaneous
Point 3
The SP shall provide for staging area at the Near DR site
for 4 weeks for initial hardware deployment. However,
for further additional activities, if the staging area is
required by the Bank, the Bank shall inform the service
provider at least 7 days in advance and the service
provider will be expected to provide the staging area
for Bank’s use.
Yotta can offer secured storage rooms of
appropriate sizes in the Data Center premises for the
period of 4 weeks.
There is a shared staging area on server hall floor
that can be reserved for use by IDBI bank, before
deployment of their IT hardware inside the
designated racks, after advanced notification of 7
days.
No change in RFP terms
138
78 F. Miscellaneous
Point 5
The cabling within / between the racks will be done by
the system integrator chosen the Bank. The service
provider must ensure all the necessary support and
permissions in this regard for laying such cables
beneath the false flooring is provided to the system
integrator. The system integrator chosen by the bank
will do this cabling activity in consultation with the
service provider
Please note that Yotta data center is planned to
route passive copper/fiber networking cables from a
set of overhead basket trays and not under the false
floor.
Please refer corrigendum
139
78 F. Miscellaneous
Point 6
The Bank may in future require additional space at the
Near DR site. The SP agrees that in the event the Bank
wants additional space for expansion; the same will be
provided to the Bank within the same Near DR site /
floor or building. The per rack rate would be as per the
contract rate. Bank cannot provide any time frame to
inform SP for taking up additional space. The additional
seating space if required should be in the same
building.
It is recommended to provide for the additional
required space within the designated cage area on
day 1 to factor before development of caged
environment.
Yotta can offer to hold back the per rack rate for a
period of maximum 12 months.
No change in RFP terms
Page 29 of 35
S. No RFP Ref Page
no
RFP Clause no Existing clause Details Change Sought Bank's Response
Bank's Respone to Prebid Queries to RFP for Engagement of Service Provider for Relocation of Near Disaster Recovery Site (NDR) Under Hosting Model
REF No: IDBIBank/ITD/VMG/RFP/2020-21/22, September 08, 2020
140
78 F. Miscellaneous
Point 5
The cabling within / between the racks will be done by
the system integrator chosen the Bank. The service
provider must ensure all the necessary support and
permissions in this regard for laying such cables
beneath the false flooring is provided to the system
integrator. The system integrator chosen by the bank
will do this cabling activity in consultation with the
service provider
Please note that Yotta data center is planned to
route passive copper/fiber networking cables from a
set of overhead basket trays and not under the false
floor.
Please refer corrigendum
141
77 D. Communication
Area
Point 3
As part of telecom facility, bidder is expected to provide
necessary junction box / space in the telecom room for
multiplexer/s, and other equipment. Bidder needs to
also make provision for extending the links (fibre /
copper) up to the server room network racks where
routers will be placed.
Elaboration on the equipments that the bank is
expecting the bidder to provide like junction boxes,
multiplexers etc. in the communication room is
needed. Please specify
No change in RFP terms
Network Team Response:
Any equipment which will be
required for end to end connectivity
and bidder to make the
arrangement for same which is
clearly mentioned in the RFP
142
89 3. Availability
measurements:
Point first
Critical->Network Bandwidth – DC and Near
DR,Network Bandwidth – DR and Near DR->Availability
of each replication link ->99. 99%
We can commit expected service level 99.99% with
redundant replication links.
No change in RFP terms
Page 30 of 35
S. No RFP Ref Page
no
RFP Clause no Existing clause Details Change Sought Bank's Response
Bank's Respone to Prebid Queries to RFP for Engagement of Service Provider for Relocation of Near Disaster Recovery Site (NDR) Under Hosting Model
REF No: IDBIBank/ITD/VMG/RFP/2020-21/22, September 08, 2020
143
85 1. Detailed Service
Level and Definition
(vi). Typical Resolution
time will be applicable
only if any equipment
or Infrastructure is
down.
Critical->Environmental Infrastructure->
a. Access controls
b. UPS supply
c. Precision Air conditioning
d. Fire Detection System
e. Water detection systems
f. Humidity Controllers
g. Gen-sets
h. Building Management Systems
i. LAN cabling
j. Power
->Immediate->Within 10 minutes
Generally, 10 minutes is the response time for most
of the events, faults occuring in the data center.
After identification of the fault, the resolution time
may vary depending upon the nature of failure and
designed redundancy of the equipment.
For all the critical equipments like UPSs, PACs,
electrical panels etc. the DC facility is provisioned
with redundant infrastructure components
confirming to Uptime Tier IV.
In certain cases such as Access devices, Cameras etc,
while the response time could be 10 mins and the
fact that the spares will be maintained at site, its
replacement/putting back to service may vary
between 30 mins to 45 mins.
Please refer corrigendum
144
27 1.2 The bidder must accept the payment terms
proposed by the Bank. The commercial bid submitted
by the bidders must be in conformity with the payment
terms proposed by the Bank. Any deviation from the
proposed payment terms would not be accepted. The
Bank shall have the right to withhold any payment due
to the bidder, in case of delays or defaults on the part
of the bidder. Such withholding of payment shall not
amount to a default on the part of the Bank.
Withholding of payment should be only for the
reasons solely attributable to service provider.
No change in RFP terms
145
28 1.13 Any objection / dispute to the amounts invoiced in
the bill shall be raised by the Bank within reasonable
time from the date of receipt of the invoice. Upon
settlement of disputes with respect to any disputed
invoice(s), the Bank will make payment within
reasonable time of the settlement of such disputes.
Word 'reasonable' should be quanitified likewise in
preceding clause no. 1.12 ( 15 days and 45 days)
No change in RFP terms
SECTION 2
1. Payment Terms
Page 31 of 35
S. No RFP Ref Page
no
RFP Clause no Existing clause Details Change Sought Bank's Response
Bank's Respone to Prebid Queries to RFP for Engagement of Service Provider for Relocation of Near Disaster Recovery Site (NDR) Under Hosting Model
REF No: IDBIBank/ITD/VMG/RFP/2020-21/22, September 08, 2020
146
30 6. ORDER
CANCELLATION
6.1. The Bank reserves its right to cancel the order in
the event of one or more of the following situations,
that are not occasioned due to reasons solely and
directly attributable to the Bank alone:
i. Delay in shifting, site readiness, switch on at the
proposed new site and handing over the site to the
Bank.
ii. Discrepancy in the quality of service / facility /
security.
"Delay" should exclude any force majeure situations.
However the RFP document doesn’t not contain
Force-majeure clause requesting bank to
incorporate.
No change in RFP terms
147
30 6.2. In case of order cancellation, any payments made
by the Bank to the SP would necessarily have to be
returned to the Bank with interest @ 15% per annum,
further the SP would also be required to compensate
the Bank for any direct loss incurred by the Bank due to
the cancellation of the contract and any additional
expenditure to be incurred by the Bank to appoint any
other SP. This is after repaying the original amount paid.
Not acceptable.
Bank is liable to pay for the service rendered by the
bidder.
please refer corrigendum
148
33 7. INDEMNITY 7.2. The provisions under this clause and indemnity
shall survive the termination of the Contract.
Survival is open ended in present clause. Request
Bank to put survival period of maximum three
months post termination/expiry of the contract.
No change in RFP terms
149
34 9. INSPECTION &
QUALITY CONTROL
TESTS/CHECK
9.3. IDBI Bank reserves the right to evolve a procedure
of quality checking to ensure that the Services are
according to the prescribed specifications and
standards.
Bank has to provide an advance procedural
guidelines for any evolution of quality checks during
the period of contract.
No change in RFP terms
15036 15. LIQUIDATED
DAMAGES
Liquidated Damages Request you to exempt bidder for reasons not
attributable to bidder or Force majeure.
No change in RFP terms
151
37 17. DISPUTE
RESOLUTION
17.3. The Vendor shall not be entitled to suspend the
provision of the Services or the completion of the job,
pending resolution of any disputes between the Parties
and shall continue to render the Services in accordance
with the provisions of the Contract notwithstanding the
existence of any dispute between the Parties or the
subsistence of any arbitration or other proceedings.
Bank shall also continue to pay the Bidder for
services rendered notwithstanding existence of any
dispute.
Please rephrase the clause accordingly.
No change in RFP terms
Page 32 of 35
S. No RFP Ref Page
no
RFP Clause no Existing clause Details Change Sought Bank's Response
Bank's Respone to Prebid Queries to RFP for Engagement of Service Provider for Relocation of Near Disaster Recovery Site (NDR) Under Hosting Model
REF No: IDBIBank/ITD/VMG/RFP/2020-21/22, September 08, 2020
152
39 23. SURVIVAL 23.2. The provisions of the clauses of this Contract in
relation to documents, data, processes, property,
Intellectual Property Rights, indemnity, publicity and
confidentiality and ownership survive the expiry or
termination of this Contract and in relation to
confidentiality, the obligations continue to apply unless
the Purchaser notifies the Bidder of its release from
those obligations.
Survival is open ended in present clause. Request
Bank to put survival period of maximum three
months post termination/expiry of the contract.
No change in RFP terms
153
71 7. INDEMNITY 7. This indemnity shall survive the aforesaid Contract. Survival is open ended in present clause. Request
Bank to put survival period of maximum three
months post termination/expiry of the contract.
No change in RFP terms
154
84 1.7 Delivery 1. Introduction
Rated Power of approximate 80 KVA to the Bank's cage
area in the server room. Additional power if required to
be made available. If additional Racks are shifted in
future, the SP should have the provision to provide
sufficient power during the contract period.
Please clarify about whether 80KVA is rated total or
power for all 8 Racks. So Per Rack will be 10KVA
Rated power or Actual consumption power
No change in RFP terms
Please refer the power
requirements mentioned in
inventory (Annexure 23). Billing to
be done on actual consumption of
power units (Annexure 13 Clause
H.11)
155
21 5. TECHNICAL BID
EVALUATION (SECOND
STAGE)
5.3.5 If the proposed data center is Tier IV standard Kindly amend as follows----If the proposed data
center is Tier III/IV standard
No change in RFP terms
156
22 5. TECHNICAL BID
EVALUATION (SECOND
STAGE)
5.11.B. Bidders Past Experience
The bidder must have provided co-hosting space for at
least 10 rack space area per customer in Tier III Data
Centre colocation facility at the PROPOSED SITE for the
bank in India (Banks of Indian origin).
Kindly amend as follows---The bidder must have
provided co-hosting space for at least 10 rack space
area per customer in Tier III Data Centre colocation
facility at the PROPOSED SITE for the bank/BFSI
Customers in India (Banks/BFSI Customers of Indian
origin).
Please refer corrigendum
157
5 5.1. DELIVERY AND
TIME LIMIT FOR
COMMENCEMENT OF
WORK: PERIOD &
LOCATION
1. Introduction
1.
Making the server area ready and available for
installation of the Bank’s IT infrastructure (Site should
be ready with electrical and network cabling and other
facilities like CCTV, access control system etc. as
mentioned in SoW)
Kindly amend the Delivery timelines for all
Colocation Passive Infra or Power readiness
timelines to atleast 6 weeks from PO Date
No change in RFP terms
158
84 2. Desirable Technical
Requirements
Technical Requirement
Remote Monitoring Facility for Caged Area
CCTV Survelliance will be present along with 90 days
archival. Kindly confirm if this will cater the
requirement
No change in RFP terms
Page 33 of 35
S. No RFP Ref Page
no
RFP Clause no Existing clause Details Change Sought Bank's Response
Bank's Respone to Prebid Queries to RFP for Engagement of Service Provider for Relocation of Near Disaster Recovery Site (NDR) Under Hosting Model
REF No: IDBIBank/ITD/VMG/RFP/2020-21/22, September 08, 2020
159
29 5.1 # 3 NW links commissioning between DC and Near DR, DR and
Near DR - 5 weeks from the date of issuing the purchase
order to the SP
Sify request Bank to consider commissioning of link to
standard 8 weeks from date of issuing the purchase
order. Accordingly other timeline to revised.
No change in RFP terms
16076 Annex-13 A #11 99.99% Uptime is required for the network availability. Sify request to consider the uptime of 99.90% No change in RFP terms
161
79 G # 1 a. 1 Gbps (Two Links) dedicated point to point fibre links from
DC, Belapur to Hosting location from two different ISP having
latency ≤2 mili second.
Sify seek clarification on the required 1Gbps dedicated
point to point link:
1. is the link going to utilize for the SAN replication and
need FC? Or
2. will it be used for normal data transfer?
3. Is MACsec required in the proposed P2P service?
4. How many VLAN and MAC address will be passed?
No change in RFP terms
Dedicated Point to point fiber link
for data replication is required so
points 1-4 are not relevant.
162
79 G # 1 b. 10 Mbps (Two Links) dedicated point to point link from DR,
Chennai to Hosting location from two different ISP.
Sify seek clarification to understand the number of VLAN
and MAC to be considered in the proposed Point to Point
service.
Sify also needs to give clarification, this 10Mbps P2P link
will be considered without requirement of MACsec, and
the handoff will be over Copper.
No change in RFP terms
Dedicated Point to point for data
replication is required.
163
79 G # 2 B Both 1 Gbps links should be provided from link service
providers MUX having optical port (1/10G) & bidder has to
arrange fibre cable connectivity from that MUX to IDBI
network devices installed at proposed location.
Sify request Bank to freeze on the require module. Sify
recommeneds if the bandwidth requirement is of 1Gbps,
optical port and its modules shall be only on 1Gbps and
not 10Gbps or kindly confirm if it is okay to upgrade the
module from 1G to 10G in future when there is
requirement of higher bandwidth of more than 10Gbps
bandwidth.
No Change in RFP terms, bidder to
make arrangement for same
164
79 G # 2 C Switch Sify request to amend this clause for following:
1. Sify network standard policy of delivering the optical
handoff is over SM,LR
2. Since the required bandwidth size is of 1Gbps, the
optical module of SM,LR from Sify shall be 1G,SM,LR with
option to upgrade in the Future as per Future scalability
with applicable downtime.
No Change in RFP terms, bidder to
make arrangement for same
165
80 3 # D. Optical fibre cables should be Multi Mode (LC-LC) Sify Network policy for the WAN service link over optical
handoff is Single Mode - Long Range.
For DC Network or its LAN network, it will be as per DC
Network policy.
No change in RFP terms
166
84 2 S.N. 15 Latency for the 1 Gbps point to point link should be less than
or equal to 1 ms
Sify request Bank to kindly change the latency to same
figure across all the technical clause.No change in RFP terms
This is part of desirable technical
point & if any bidder is able to
provide the same, marks will be
given accordingly
Page 34 of 35
S. No RFP Ref Page
no
RFP Clause no Existing clause Details Change Sought Bank's Response
Bank's Respone to Prebid Queries to RFP for Engagement of Service Provider for Relocation of Near Disaster Recovery Site (NDR) Under Hosting Model
REF No: IDBIBank/ITD/VMG/RFP/2020-21/22, September 08, 2020
16785 A SLA
Point 1 # (i)
"Scheduled operation time” means the scheduled operating
hours of the System for the month.
Sify request Bank to kindly consider the standard SLA
cycle of Quarterly over Monthly.No change in RFP terms