safe machine parameters in lhc
DESCRIPTION
Safe Machine Parameters in LHC. Safe Machine Parameters in LHC. …ENERGY…. Energy Implementation 2010. Energy Implementation 2010. switch between A and B. Energy Implementation 2010. switch between A and B. ≈ 0.5 Hz cross-check - PowerPoint PPT PresentationTRANSCRIPT
Safe Machine Parameter System
MPP Internal ReviewB. Todd 17-18th June 2010
0v3
Towards Nominal Beams
CERNCERN
[email protected] Machine Protection Panel - Internal review - 17-18 th June [email protected]
CERNCERN
Machine Protection Panel - Internal review - 17-18 th June 2010
Safe Machine Parameters in LHC
DATA RECEIVERMachineEnergy LHC
Safe Machine
ParameterController
DATA RECEIVERBeam Intensity
Beam Mode
LHC Beam Presence Flag 1
LHC Set-up Beam Flag 2LHC Set-up Beam Flag 1
LHC Beam Intensity 1LHC Machine Energy
LHC Beam Intensity 2Moveable Devices Allowed In
Stable Beams FlagDirectly Transmitted
Broadcast
DATA RECEIVERBeam Presence
LHC GeneralMachineTiming
LHC Beam Presence Flag 2LHC Beam Presence Flag 1
LHC Set-up Beam Flag 2LHC Set-up Beam Flag 1
LHC Beam Presence Flag 2
CERNCERN
[email protected] Machine Protection Panel - Internal review - 17-18 th June 2010 3
Safe Machine Parameters in LHC
DATA RECEIVERMachineEnergy LHC
Safe Machine
ParameterController
DATA RECEIVERBeam Intensity
Beam Mode
LHC Beam Presence Flag 1
LHC Set-up Beam Flag 2LHC Set-up Beam Flag 1
LHC Beam Intensity 1LHC Machine Energy
LHC Beam Intensity 2Moveable Devices Allowed In
Stable Beams FlagDirectly Transmitted
Broadcast
DATA RECEIVERBeam Presence
LHC GeneralMachineTiming
LHC Beam Presence Flag 2LHC Beam Presence Flag 1
LHC Set-up Beam Flag 2LHC Set-up Beam Flag 1
LHC Beam Presence Flag 2
…ENERGY…
CERNCERN
[email protected] Machine Protection Panel - Internal review - 17-18 th June 2010 4
Energy Implementation 2010
BETS LBDS
LHCSafe
MachineParameterController
Dipole Currents
BETS
Energy 1B
Energy 2AEnergy 2B
Collimation
Injection Kickers
BLM
LBDSBeam-1
LBDSBeam-2
Energy 1A
LHC GeneralMachineTiming
LHC Machine Energy
CERNCERN
[email protected] Machine Protection Panel - Internal review - 17-18 th June 2010 5
Energy Implementation 2010
BETS LBDS
Dipole Currents
BETS
Energy 1B
Energy 2AEnergy 2B
Collimation
Injection Kickers
BLM
LBDSBeam-1
LBDSBeam-2
Energy 1A
LHC GeneralMachineTiming
LHC Machine Energy
switch between A and B
CERNCERN
[email protected] Machine Protection Panel - Internal review - 17-18 th June 2010 6
Energy Implementation 2010
≈ 0.5 Hz cross-check dipole currents must be equivalent to BLM energy reading (1%)
BETS LBDS
Dipole Currents
BETS
Energy 1B
Energy 2AEnergy 2B
Collimation
Injection Kickers
BLM
LBDSBeam-1
LBDSBeam-2
Energy 1A
LHC GeneralMachineTiming
LHC Machine Energy
EnergyConsistency
Check
SIS
switch between A and B
CERNCERN
[email protected] Machine Protection Panel - Internal review - 17-18 th June 2010 7
Intensity Implementation 2010
LHCSafe
MachineParameterController
Intensity 1B
Intensity 2AIntensity 2B
DCBCTSystems
Intensity 1A
LHC GeneralMachineTiming
LHC Beam-1 IntensityLHC Beam-2 Intensity
AB
Beam-1 Current
AB
Beam-2 Current LHC Setup Beam Flag 1
LHC Setup Beam Flag 2
CERNCERN
[email protected] Machine Protection Panel - Internal review - 17-18 th June 2010 8
Intensity 1B
Intensity 2AIntensity 2B
DCBCTSystems
Intensity 1A
LHC GeneralMachineTiming
LHC Beam-1 IntensityLHC Beam-2 Intensity
AB
Beam-1 Current
AB
Beam-2 Current LHC Setup Beam Flag 1
LHC Setup Beam Flag 2
Intensity Implementation 2010
switch between A and B
no cross-check
SMP 3v0 – 2011 will implement complete redundancyEnergy and Intensity will be from multiple sources
CERNCERN
[email protected] Machine Protection Panel - Internal review - 17-18 th June 2010 9
1. Remove an external ROM – HWSBF glitch - MPP 2010-25
http://lhc-mpwg.web.cern.ch/lhc-mpwg/MPP-Meetings/No25-19032010/MPP_190310_minutes.docx
HW
Outstanding Issues - SMP 2v0
2. Force SBF False at the start of every normal ramp – / / / .Improve SBF safety - modification authorised Evian 2010
http://indico.cern.ch/contributionDisplay.py?contribId=6&sessionId=3&confId=76921
ready
ready ready ready waitingHW FESA JAVA SEQUENCER
3. The Setup Beam Flag - HW / FESA / JAVAThe limit is too low for some studies
study in progress
CERNCERN
[email protected] Machine Protection Panel - Internal review - 17-18 th June 2010 10
GMT
BeamEnergy
Tracking System
BeamCurrent
Transformers
ENERGY
INTENSITY
FlagGenerator
Direct to Extraction Controller
SBF ADATA
RECEIVER
BeamEnergy
Tracking System
DATA RECEIVER
BeamInterlockController
SBF A
SBF ASBF BSBF
ThresholdROM
ENERGY THRESHOLD
Generating the Setup Beam Flag
If (INTENSITY < THRESHOLD) SBF = TRUE
Else SBF = FALSE
End if
CERNCERN
[email protected] Machine Protection Panel - Internal review - 17-18 th June 2010 11
GMT
BeamEnergy
Tracking System
BeamCurrent
Transformers
ENERGY
INTENSITY
FlagGenerator
Direct to Extraction Controller
SBF ADATA
RECEIVER
BeamEnergy
Tracking System
DATA RECEIVER
BeamInterlockController
SBF A
SBF ASBF BSBF
ThresholdROM
ENERGY THRESHOLD
x4 Timer
Generating the Setup Beam Flag
CERNCERN
[email protected] Machine Protection Panel - Internal review - 17-18 th June 2010 12
1. Remove an external ROM – HWSBF glitch - MPP 2010-25
http://lhc-mpwg.web.cern.ch/lhc-mpwg/MPP-Meetings/No25-19032010/MPP_190310_minutes.docx
HW
Outstanding Issues - SMP 2v0
2. Force SBF False at the start of every normal ramp – / / / .Improve SBF safety - modification authorised Evian 2010
http://indico.cern.ch/contributionDisplay.py?contribId=6&sessionId=3&confId=76921
4. Filter the Beam Presence Flag – HW / FESA / JAVAExtraction Denial of Service - MPP 2010-26
http://lhc-mpwg.web.cern.ch/lhc-mpwg/MPP-Meetings/No26-16042010/MPP_160410_minutes.docx
5. Improve the Beam Presence FlagFast Beam Current Transformer is currently the limiting factor….
ready
ready ready ready waiting
ready ready ready
It’s complicated
HW FESA JAVA SEQUENCER
HW FESA JAVA
3. The Setup Beam Flag - HW / FESA / JAVAThe limit is too low for some studies
study in progress
CERNCERN
[email protected] Machine Protection Panel - Internal review - 17-18 th June 2010 13
Beam Presence Flag Signal Path
Beam Current Transformer System
Beam Current Transformer System
Beam Currents
LHC Point 4
BPF_1BPF_2
CERNCERN
[email protected] Machine Protection Panel - Internal review - 17-18 th June 2010 14
Beam Presence Flag Signal Path
Beam Current Transformer System
Beam Current Transformer System
Beam Currents
LHC Point 4LHC
Safe Machine Parameters Controller
Control Room
BPF_1BPF_2
BPF_1
BPF_2
CERNCERN
[email protected] Machine Protection Panel - Internal review - 17-18 th June 2010 15
Beam Presence Flag Signal Path
Beam Current Transformer System
Beam Current Transformer System
Beam Currents
LHC Point 4LHC
Safe Machine Parameters Controller
Control Room
BPF_1BPF_2
Extraction Interlock
ControllerSPS East Area
Extraction Interlock
Controller
SPS West Area
BPF_1
BPF_2
ExtractionPermit
ExtractionPermit
CERNCERN
[email protected] Machine Protection Panel - Internal review - 17-18 th June 2010 16
Beam Presence Flag Signal Path
Beam Current Transformer System
Beam Current Transformer System
Beam Currents
LHC Point 4LHC
Safe Machine Parameters Controller
Control Room
BPF_1BPF_2
Extraction Interlock
ControllerSPS East Area
Extraction Interlock
Controller
SPS West Area
BPF_1
BPF_2
ExtractionPermit
ExtractionPermit
LHC General Machine Timing
Non-Critical Timing Users
BPF_1BPF_2
CERNCERN
[email protected] Machine Protection Panel - Internal review - 17-18 th June 2010 17
Beam Presence Flag Signal Path
Beam Current Transformer System
Beam Current Transformer System
Beam Currents
LHC Point 4LHC
Safe Machine Parameters Controller
Control Room
BPF_1BPF_2
Extraction Interlock
ControllerSPS East Area
Extraction Interlock
Controller
SPS West Area
BPF_1
BPF_2
ExtractionPermit
ExtractionPermit
LHC General Machine Timing
Data Interchange
Protocol
Non-Critical Timing Users
Non-Critical DIP Users
BPF_1BPF_2
CERNCERN
[email protected] Machine Protection Panel - Internal review - 17-18 th June 2010 18
Beam Presence Flag Signal Path
Beam Current Transformer System
Beam Current Transformer System
Beam Currents
LHC Point 4
BEAM_PRESENCE_LIMIT
LHCSafe Machine Parameters Controller
Control Room
BPF_1BPF_2
Extraction Interlock
ControllerSPS East Area
Extraction Interlock
Controller
SPS West Area
BPF_1
BPF_2
ExtractionPermit
ExtractionPermit
LHC General Machine Timing
Data Interchange
Protocol
Non-Critical Timing Users
Non-Critical DIP Users
BPF_1BPF_2
Thresholds Definitionhttps://edms.cern.ch/document/883620/
CERNCERN
[email protected] Machine Protection Panel - Internal review - 17-18 th June 2010 19
Beam Presence Flag Signal Path
LHCSafe Machine Parameters Controller
Control Room
BPF_1BPF_2
Extraction Interlock
ControllerSPS East Area
Extraction Interlock
Controller
SPS West Area
BPF_1
BPF_2
ExtractionPermit
ExtractionPermit
LHC General Machine Timing
Data Interchange
Protocol
Non-Critical Timing Users
Non-Critical DIP Users
BPF_1BPF_2
From end of September 2010
CERNCERN
[email protected] Machine Protection Panel - Internal review - 17-18 th June 2010 20
Beam Presence Flag Signal Path
Beam Position Monitor Hardware
Beam Position Monitor Hardware
Beam Position
LHC Point 4LHC
Safe Machine Parameters Controller
Control Room
BPF_1BPF_2
Extraction Interlock
ControllerSPS East Area
Extraction Interlock
Controller
SPS West Area
BPF_1
BPF_2
ExtractionPermit
ExtractionPermit
LHC General Machine Timing
Data Interchange
Protocol
Non-Critical Timing Users
Non-Critical DIP Users
BPF_1BPF_2
From end of September 2010
CERNCERN
[email protected] Machine Protection Panel - Internal review - 17-18 th June 2010 21
Beam Presence Flag Signal Path
Beam Position Monitor Hardware
Beam Position Monitor Hardware
Beam Position
LHC Point 4
BEAM_PRESENCE_LIMIT
LHCSafe Machine Parameters Controller
Control Room
BPF_1BPF_2
Extraction Interlock
ControllerSPS East Area
Extraction Interlock
Controller
SPS West Area
BPF_1
BPF_2
ExtractionPermit
ExtractionPermit
LHC General Machine Timing
Data Interchange
Protocol
Non-Critical Timing Users
Non-Critical DIP Users
BPF_1BPF_2
From end of September 2010
+ fibres to be pulled+ new hardware from BI
+ testing and commissioning
CERNCERN
[email protected] Machine Protection Panel - Internal review - 17-18 th June 2010 22
For high intensity beams we need to…Upgrade the operational controller → Ben & SMP Team
When: next technical stop?
Release a new GUI → Ivan & SMP TeamWhen: next technical stop?
Add a sequencer task → OPWhen: MPP to decide
Improve Beam Presence Flag safety• fibres in UA47 → Bruno & Fibre team
• New BPM hardware unit → BI• Testing and Commissioning → BI & SMP Team
When: Ready for end of September
Make the SBF more flexible → MPP & MIWhen:?
Complete redundancy SMP 3v0 → many When: January 2011
CERNCERN
[email protected] Machine Protection Panel - Internal review - 17-18 th June [email protected] 23Machine Protection Panel - Internal review - 17-18 th June 2010
CERNCERN
Fin
Thank you for your attention