safety in control design
TRANSCRIPT
-
7/30/2019 Safety in Control Design
1/23
INSTRUMENTATION ANDCONTROLS FOR SAFETY
M. B. Jennings
CHE 185
-
7/30/2019 Safety in Control Design
2/23
INHERENTLY SAFE DESIGN
PROCESS RISK MANAGEMENT METHODS USEDDURING THE DESIGN PHASE CAN BE PUTINTO 4 CATEGORIES: Inherent
PassiveActive
Procedural
TARGET IS A FAIL-SAFE INSTALLATION
FROM: Dennis C. Hendershot and Kathy Pearson-Dafft, Safety ThroughDesign in the Chemical Process Industry: Inherently SaferProcess Design , AIChE Process Plant Safety Symposium,27OCT98
-
7/30/2019 Safety in Control Design
3/23
INHERENT SAFETY DESIGN
Inherent Eliminating the hazard by usingmaterials and process conditions which are non-hazardous.
Minimize Reduce quantities of hazardous substances
Substitute Use less hazardous substances
Moderate Use less hazardous process conditions, lesshazardous forms of materials, or configure facilities tominimize impact from hazardous material releases or
uncontrolled energy release Simplify Configure facilities to simplify operation
-
7/30/2019 Safety in Control Design
4/23
PASSIVE SAFE DESIGN
Passive Minimizing the hazard by processand equipment design features which reduceeither the frequency or consequence of the
hazard without the active functioning of anydevice.
Location of facilities separation of ignitionsources and fuels from other facilities
Design equipment for design pressure in excess ofthe adiabatic pressure from a reaction.
-
7/30/2019 Safety in Control Design
5/23
ACTIVE SAFE DESIGN
Active Using facilities to detect and correctprocess conditions:
controls
safety interlocks
monitoring systems for hazards that develop overa long term
and emergency shutdown systems to detect andcorrect process deviations.
-
7/30/2019 Safety in Control Design
6/23
PROCEDURAL SAFE DESIGN
Procedural Prevention or minimization ofincident impacts using:
Safe operating procedures and operator
trainingAdministrative safety checks
Management of Change
Planned emergency response
-
7/30/2019 Safety in Control Design
7/23
DESIGN IN OVERALL SAFETY MANAGEMENTArt M. Dowell, III, Layer of Protection Analysis, 1998 PROCESS PLANT SAFETY
SYMPOSIUM, October 27, 1998 Houston, TX
-
7/30/2019 Safety in Control Design
8/23
DESIGN OF SAFETY INSTRUMENTED SYSTEMS
ACTIVE INHERENTLY SAFE DESIGNPROCEDURE (Separate instrumentationand control component in CHE 165
Design) First Level Alarm systems for out of
range situations and operator action
Second Level Interlock systems toautomatically activate safety devices
Third Level Devices to minimize impact
of out of control conditions
-
7/30/2019 Safety in Control Design
9/23
USE OF HAZAN AND HAZOP
PHAs (Process Hazards Analysis) Areused to define areas of concern
HAZAN and HAZOP provide a summary
of the type of risk associated withvarious process locations and operations
Frequency should be determined
Intensity should be determined
-
7/30/2019 Safety in Control Design
10/23
OVERPRESSURIZATION EXAMPLE
OVERPRESSURIZATION IS THE SUBJECT OFNUMEROUS CODES & REGULATIONS
AIChE Design Institute for Emergency ReliefSystems (DIERS)
OSHA 29 CFR 1910.119 Process SafetyManagement of Highly Hazardous Chemicals
NFPA 30 Flammable & Combustible Liquids
API RP 520 and API RP 521 Pressure Relieving
Devices and Depressurization SystemsASME Boiler & Pressure Vessel Code
ASME Performance Test Code 25, Safety & ReliefValves
-
7/30/2019 Safety in Control Design
11/23
SOURCES OF OVERPRESSURIZATION
API 521 LISTS THE FOLLOWINGCATEGORIES OF SOURCES
API RP
521 Item
No.
Overpressure Cause API RP
521 Item
No.
Overpressure Cause
1 Closed outlets on vessels 10 Abnormal heat or vapor input
2 Cooling water failure to condenser 11 Split exchanger tube
3 Top-tower reflux failure 12 Internal explosions
4 Side stream reflux failure 13 Chemical Reaction
5 Lean oil failure to absorber 14 Hydraulic expansion
6 Accumulation of noncondensables 15 Exterior fire
7 Entrance of highly volatile material 16 Power failure (steam, electric, or other)
8 Overfilling Storage or Surge Vessel Other
9 Failure of automatic control
-
7/30/2019 Safety in Control Design
12/23
FIRST LEVEL DESIGN
HOW ARE SOURCES ADDRESSED FOR ASTORAGE TANK?
Item 1 in previous list - Closed ou t lets on vessels
Would be a concern for a nozzle used for pressure control
in the tank, during filling operations. Perhaps a temporary blind flange would have been left in place after a
maintenance operation.
A pressure relief valve may malfunction.
A PAH pressure switch (
P) could be installed if there wasmeasurable difference between the Normal Operating
Pressure and the Maximum Allowable Working Pressure.
-
7/30/2019 Safety in Control Design
13/23
SECOND LEVEL DESIGN
HOW ARE SOURCES ADDRESSED FOR ASTORAGE TANK? Item 1 in previous list - Closed ou t lets on vessels
Add a pressure relief valve to allow gas to leave thetank and be directed to an appropriate flare orscrubber.
Set point needs to be at or slightly above theMaximum Allowable Working Pressure
Need an interlock to: Alarm to indicate valve has been activated and receiving
unit (flare or scrubber) is activated.
Shut down a valve in the tank fill line and/or shut off apump used for filling.
-
7/30/2019 Safety in Control Design
14/23
THIRD LEVEL DESIGN
HOW ARE SOURCES ADDRESSED FOR ASTORAGE TANK?
Item 1 in previous list - Closed ou t lets on vessels
Add a rupture disc to relieve to either a flare or
scrubber.
This level is to protect the equipment from failure
on a major scale
Need to have an indication that the rupture dischas opened typically a wire across the disc
Need to determine actions necessary when the
disc opens
stop filling, start flare, etc.
-
7/30/2019 Safety in Control Design
15/23
OTHER DESIGN CONSIDERATIONS
A large storage tank is filled manually byan operator opening and closing a valve.Once a year, the tank overfills as the
operator is distracted by other activities.A high pressure alarm is added to thetank. After the alarm is added, the tankis typically overfilled twice a year.
Why?
-
7/30/2019 Safety in Control Design
16/23
EXAMPLE 1
After the alarm was installed, theoperator relied on it to indicate a highlevel and did not supervise the filling
closely. The alarm loop turned out tohave a failure rate of twice per year, sothe system was not as reliable as themanual operation.
-
7/30/2019 Safety in Control Design
17/23
OTHER CONSIDERATIONSEXAMPLE 2
Fail-safe valves are either Air-to-Open or Air-to-Close, which equate to Fail Closed and FailOpen, respectively. Recommend the correctvalve for the following processes:
1. Flammable solvent heated by steam in a heatexchanger. Valve is on the steam supply line.
2. Exothermic reaction. Valve is on the reactantfeed line.
3. Endothermic reaction. Valve is on thereactant feed line.
4. Gas-fired utility furnace. Valve is on the gassupply line.
-
7/30/2019 Safety in Control Design
18/23
EXAMPLE 2 - CONTINUED
SPECIFY EITHER FAIL-CLOSED OR FAIL-OPEN FOR THE VALVES IN THESE SYSTEMS
5. Remote-operated valve on the drain for astorage tank.
6. Remote-operated valve on the fill line to astorage tank.
7. Gas-fired Combustion furnace. Valve is on
the air supply line.8. Steam supply line. Valve controls the
downstream steam pressure from the boiler.
-
7/30/2019 Safety in Control Design
19/23
EXAMPLE 2SOLUTIONS 1
1. Valve to FAIL-CLOSED to preventoverheating the solvent
2. Valve to FAIL-CLOSED to avoid a
runaway reaction3. Valve to FAIL-CLOSED to avoid reactor
thermal stresses.
4. Valve to FAIL-CLOSED to stop gas flowto uncontrolled combustion.
-
7/30/2019 Safety in Control Design
20/23
EXAMPLE 2SOLUTIONS 2
5. Valve to FAIL-CLOSED to preventdraining material from tank
6. Valve to FAIL-CLOSED to prevent
overfilling tank7. Valve to FAIL-OPEN to maximize air
flow to furnace
8. Valve to FAIL-OPEN to avoid localizedoverpressure of line
-
7/30/2019 Safety in Control Design
21/23
EXAMPLE 3
4 kg of water is trapped in between inletand discharge block valves in a pump.The pump continues to operate at 1 hp.
What is the rate of temperature increase inC/hr if the cP for the water is constant at 1kcal/(kg C)?
What will happen if the pump continues to
operate?
-
7/30/2019 Safety in Control Design
22/23
EXAMPLE 3 SOLUTION - 1
Assume adiabatic conditions for thecalculations: Set up a heat balance:Q m Cp T Tref
Take the derivative with respect to time and
rearrange to getdQ
dtm C
p
dT
dt . And
resolving to getdT
dt
1
m Cp
dQ
dt
Using conversions:1 hp 0.178kcal
sec
m 4 kg dQ/dt 0.178kcal
sec Cp 1
kcal
kg C
dT/dt1
m CpdQ/dt dT/dt 160.2
C
hr
3 SO O 2
-
7/30/2019 Safety in Control Design
23/23
EXAMPLE 3 SOLUTION - 2
Allowing the pump to continue to runwill eventually result in high pressuresteam formation. This could result in the
pump exploding. Adding a thermal switch or a high
pressure switch to shut down the pumpcan prevent this from occurring.