Timely Use of Federal and State Funds
Stella Liao, P.E.District Local Assistance Engineer
S A F E T Y * M O B I L I T Y * D E L I V E R Y * S T E WA R D S H I P * S E R V I C E2
OVERVIEW
What’s Covered:• Federal Authorizations
– Through the phases– Inactive Project Status
(How to find the list and how to get off it!)
• State Allocations– Request for Allocations– Request for Time Extension
(How to find the date and how to get it extended!)
• Cooperative Work Agreements (CWA) – When to request one– When you don’t need one
S A F E T Y * M O B I L I T Y * D E L I V E R Y * S T E WA R D S H I P * S E R V I C E3
Project Close-out
FEDERAL AUTHORIZATIONSFederal Transportation Act (Apportionments)
FTIP Published (Projects are programmed)
Request For Authorization (In the year programmed)• Preliminary Engineering (covers PA&ED, E&P, PS&E)• Right of Way (covers Acquisition & Support/Engineering)• Utility Relocation (can be separate from R/W)• Construction (can include Construction Engineering)• Construction Contract Award (within 60 days)• Final Report of Expenditures (within 180 days)
S A F E T Y * M O B I L I T Y * D E L I V E R Y * S T E WA R D S H I P * S E R V I C E4
FEDERAL AUTHORIZATIONS
S A F E T Y * M O B I L I T Y * D E L I V E R Y * S T E WA R D S H I P * S E R V I C E5
The E 76
S A F E T Y * M O B I L I T Y * D E L I V E R Y * S T E WA R D S H I P * S E R V I C E6
THE DATE THAT MATTERS
AUTHORIZATIONAUTHORIZATION TO PROCEED WITH REQUEST:PRE
FOR: PEDOCUMENT TYPE: AAGR
PREPARED BY:REVIEWED BY:
AUTHORIZED BY:PROCESSED BY:
LAST FHWA ELECTRONIC SIGNATURE EXECUTED BY:
ON 03/15/2010ON 03/23/2010ON 03/23/2010ON 03/24/2010 FOR CALTRANSON 03/26/2010 FOR FHWA
Authorization Date
You cannot charge for (reimbursed) work/expenses accomplished/billed prior to FHWA’s authorization date
Approval Timeframe(typically two to three weeks)
S A F E T Y * M O B I L I T Y * D E L I V E R Y * S T E WA R D S H I P * S E R V I C E
Program Supplement Agreement
Link to a blank form: http://www.dot.ca.gov/hq/LocalPrograms/lam/forms/chapter4/4d.pdf
7
S A F E T Y * M O B I L I T Y * D E L I V E R Y * S T E WA R D S H I P * S E R V I C E
Program Supplement Agreement
Link to a blank form: http://www.dot.ca.gov/hq/LocalPrograms/lam/forms/chapter4/4d.pdf
8
ADMINISTERING AGENCY agrees, as a minimum, to submit invoices at least once every six months commencing after the funds are encumbered for each phase by the execution of this Project Program Supplement Agreement, or by STATE’s approval of an applicable Finance Letter.
S A F E T Y * M O B I L I T Y * D E L I V E R Y * S T E WA R D S H I P * S E R V I C E9
Finance Letter
S A F E T Y * M O B I L I T Y * D E L I V E R Y * S T E WA R D S H I P * S E R V I C E10
INACTIVE PROJECTS
– What is an inactive project(Reference: 23 CFR 630.106)
– How to find the list• http://www.dot.ca.gov/hq/LocalPrograms/Inactiveproj
ects.htm
– How to get off it!
S A F E T Y * M O B I L I T Y * D E L I V E R Y * S T E WA R D S H I P * S E R V I C E11
STATE ALLOCATIONS
State Budget Act
Vote/Encumbrance (PSA/FL issued)• State Budget Authority & Timely Use of Funds
STIP Published (Projects are programmed)
Allocation (Vote) Request (In the year programmed)• CTC only meets ten times a year (check the calendar)
(Time Extension Request)
Project Close-out
S A F E T Y * M O B I L I T Y * D E L I V E R Y * S T E WA R D S H I P * S E R V I C E12
ALLOCATION DOCUMENTS
S A F E T Y * M O B I L I T Y * D E L I V E R Y * S T E WA R D S H I P * S E R V I C E13
ALLOCATION NOTIFICATION LETTER( INSTEAD OF AN e-76 )
S A F E T Y * M O B I L I T Y * D E L I V E R Y * S T E WA R D S H I P * S E R V I C E14
STATE ALLOCATIONS
Allocation (Begin reimbursed work for phase voted)
↘ E&P (PA&ED) must be completed within 2nd year after vote
↘ PS&E requires CEQA & must be completed within 2nd year after vote
↘Right of Way requires CEQA & must be completed within 2nd year after vote
↘ Construction requires CEQA & must be awarded within six months of vote, contract award date must be reported within 60 days, and the contract must be completed with three years of that award date.
S A F E T Y * M O B I L I T Y * D E L I V E R Y * S T E WA R D S H I P * S E R V I C E15
TIME EXTENSION
These completion dates are referred to as timely use offunds. If you can’t meet themthe CTC has establishedGuidelines to extend the datesup to 20 months - - - but only once!
Use Exhibit 23-B (LAPG)
S A F E T Y * M O B I L I T Y * D E L I V E R Y * S T E WA R D S H I P * S E R V I C E16
TIME EXTENSION
The guidelines to extend TUFs require that:
• Only grant time extensions when there is an unforeseen and/or extraordinary circumstance(s); be specific about the subject and provide a timeline of milestones to justify the extension period (Page 2 of Exhibit 23-B).
• All time extension requests due to District at least 60 days prior to the specific deadline (CALENDAR)(RTPAs/MPOs must concur on all time extension requests)
S A F E T Y * M O B I L I T Y * D E L I V E R Y * S T E WA R D S H I P * S E R V I C E17
Cooperative Work Agreement
When the State’s budget authority over Federal or State funds is within one year of lapsing local agencies can request that the life of the funds be extended to their maximum. A cooperative work agreement is the document needed to secure the funds.
S A F E T Y * M O B I L I T Y * D E L I V E R Y * S T E WA R D S H I P * S E R V I C E18
Finance Letter
S A F E T Y * M O B I L I T Y * D E L I V E R Y * S T E WA R D S H I P * S E R V I C E19
The Bottom Line (Again)
The bottom line (really) of your Finance Letter
Adv.Proj.ID Approp.Unit State Prog. Fed/State Encumbrance Amount Approp Year Expenditure Amount Encumbrance Balance Reversion Date0600000495 12102F 2030010600 F $663,975.00 1112 $0.00 $663,975.00 06/30/20170600000495 08102F 2030010600 F $3,000,000.00 0708 $3,000,000.00 $0.00 06/30/2014
ACCOUNTING INFORMATION - NCIIPLN-5109(110)
You can’t just reprogram or transfer funds into the next phase, encumbrances are time sensitive only
S A F E T Y * M O B I L I T Y * D E L I V E R Y * S T E WA R D S H I P * S E R V I C E20
Cooperative Work Agreement
CWA Website:• http://www.dot.ca.gov/hq/LocalPrograms/CWA/cwa.htm
– CWA Timeline– CWA Spreadsheet Instructions– Reason for Delay Codes– Frequently Asked Questions (FAQ)– CWA eligible encumbrance lists
S A F E T Y * M O B I L I T Y * D E L I V E R Y * S T E WA R D S H I P * S E R V I C E21
Cooperative Work Agreement
Your project has an encumbrance (any line on the bottom of the finance letter with a balance greater than $0) with a Reversion date of June 30, 2014. If you have any doubt you will not completely expend that encumbrance, and submit an invoice prior to April 2014, you should apply for a CWA.
Sample Request Link
S A F E T Y * M O B I L I T Y * D E L I V E R Y * S T E WA R D S H I P * S E R V I C E22
Cooperative Work Agreement
WHAT’S THE RISK?• If state or federal funding is lost due to lapsing
state budget authority, the Local Agency is responsible for completing the project using local funds. Failure to complete the project may result in the agency having to repay any state or federal funds already invoiced on the project and may jeopardize future funding.
S A F E T Y * M O B I L I T Y * D E L I V E R Y * S T E WA R D S H I P * S E R V I C E23
HOW TO GET HELP
• Training• Manuals & Guidebooks• Partnering
S A F E T Y * M O B I L I T Y * D E L I V E R Y * S T E WA R D S H I P * S E R V I C E24
SUMMARY
What’s Covered:• Federal Authorizations
– Through the phases– Inactive Project Status
• How to find the list and how to get off it!
• State Allocations– Request for Allocations– Request for Time Extension
• How to find the date and how to get it extended!
• Cooperative Work Agreements (CWA) – When to request one– When you don’t need one