SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - June 2008) Rev 3 30-Jun-08
SAUDI ARAMCO INSPECTION CHECKLIST SAIC NUMBER DATE APPROVED QR NUMBER
Essential Operating Facilities (EOF) HVAC Requirements SAIC-K-4006 15-Dec-09 HVAC
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIMESAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
A1 HVAC system for EOF shall be provided with standby system.
A2
A3
A4
A5
A6
A7
A8
A9
A10
ITEM No.
SAES-K-002Para 4.3.1
Buildings located in Class I, Zone 2 or Class I, Division 2 electrical areas shall be maintained at the positive pressure of 0.1 inch water gauge - (NFPA 496 Para 7.4.1)Note: See Item No. A3 in this SAIC for Control Building
SAES-K-002Para 5.1.1
Control building shall be maintained at a positive pressure of 0.25 inch water gauge with all the openings closed.
SAES-K-002Para 5.2
Auto changeover switches shall be provided between the operating and standby units. These switches shall be capable of providing changeover and equal wear and tear between the operating and standby units.
SAES-K-002Para 4.3.2
If the maximum design capacity of the HVAC system is supplied by two or more normally operating units, at least one standby unit shall be provided with a capacity equal to or greater than the capacity of the largest operating unit.
SAES-K-002Para 4.3.3.1
In case the maximum HVAC system demand is satisfied by one operating unit only, the capacity of the standby unit shall be at least equal to the capacity of the operating unit.
SAES-K-002Para 4.3.3.2
Alarms shall be provided for all HVAC systems to provide warning of power loss (from the normal supply) and failure of any portion of the HVAC system.
SAES-K-002Para 4.3.4.1
All alarm devices shall be independent of the normal power supply of the HVAC system
SAES-K-002Para 4.3.4.2
Individual alarm devices shall be connected to a master alarm in a location where they can be conveniently observed by an attendant or other responsible person designated by the management of this essential operating facility.
SAES-K-002Para 4.3.4.3
In cases where the facility is not attended full time, the system shall be connected to an alarm at the security office, utilities office, fire station or other full-time service unit with which arrangements can be made to alert the person in charge of this facility
SAES-K-002Para 4.3.4.3
Page 2 of 2
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - June 2008) Rev 3 30-Jun-08
SAUDI ARAMCO INSPECTION CHECKLIST SAIC NUMBER DATE APPROVED QR NUMBER
Essential Operating Facilities (EOF) HVAC Requirements SAIC-K-4006 HVAC
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
REFERENCE DOCUMENTS:
1-SAES-K-002 -- Air Conditioning Systems for Essential Operating Facilities 31 May, 2004
2-NFPA 496 -- Standard for Purged and Pressurized Enclosures for Electrical Equipment, 2008
Contractor / Third-Party Saudi Aramco
Name, Initials and Date:Work is Complete and Ready for Inspection:
Name, Initials and Date:T&I Witnessed QC Record Reviewed Work Verified
QC Inspector PID Representative
Name, Initials and Date:Performed Inspection Work / Rework May Proceed
Name, Initials and Date:T&I Witnessed QC Record Reviewed Work Verified
QC Supervisor Proponent and Others
Name, Sign and Date: Quality Record Approved: T&I Witnessed QC Record Reviewed Work Verified
*Person Responsible for Completion of Quality Work / Test Y = YES N = NO F = FAILED
REMARKS:
Construction Representative* PMT Representative
Name, Organization,Initials and Date: