san vicente dam raise update - may 2013

16
Engineering & Operations Committee Meeting May 23, 2013 Jerry Reed

Upload: san-diego-county-water-authority

Post on 12-Jun-2015

261 views

Category:

News & Politics


1 download

DESCRIPTION

Update on the San Vicente Dam Raise project provided at the San Diego County Water Authority Engineering & Operations Committee Board Meeting - May 2013

TRANSCRIPT

Page 1: San Vicente Dam Raise Update - May 2013

Engineering &Operations Committee MeetingMay 23, 2013

Jerry Reed

Page 2: San Vicente Dam Raise Update - May 2013

Raised Dam

2

Page 3: San Vicente Dam Raise Update - May 2013

Spillway

3

Page 4: San Vicente Dam Raise Update - May 2013

4

Downstream Step Repair

Page 5: San Vicente Dam Raise Update - May 2013

Upstream Liner Installation

5

Page 6: San Vicente Dam Raise Update - May 2013

Low Level Outlet Gate Structure

Low Level Outlet Pipe

Existing Dam

Cofferdam

Bedrock

Target  EL 594

EL 625

Future RCC Dam

Active Reservoir

Flood Buffer

6

Page 7: San Vicente Dam Raise Update - May 2013

Low Level Outlet Gate Structure

7

Page 8: San Vicente Dam Raise Update - May 2013

Outlet Tower

8

Page 9: San Vicente Dam Raise Update - May 2013

9

Outlet Tower Gates

Page 10: San Vicente Dam Raise Update - May 2013

10

Fish Screen

Page 11: San Vicente Dam Raise Update - May 2013

11

Lower Level Outlet108-inch Diameter Pipe

City 66-inchDiameter Pipe

EmergencyDischarge

Outlet WorksWater Authority

90-inchDiameter Pipe

Page 12: San Vicente Dam Raise Update - May 2013

Plunger and Gate Valve Installation

12

Page 13: San Vicente Dam Raise Update - May 2013

Picture of BFV flying in from Crane, update on Monday

13

108-inch Diameter Butterfly Valve Installation

Page 14: San Vicente Dam Raise Update - May 2013

108-inch Diameter Butterfly Valve

14

Page 15: San Vicente Dam Raise Update - May 2013

Contractor’s Baseline Schedule

Start-up Testing

Decommission Exist OW

108” Valve Actuator Delay

Schedule Update

NO

VEM

BER

2013

FIN

ISH

15

(Construction Contract Duration)

Complete Outlet Works

7 Months

Commence Reservoir Fill

CONTRACTORS BASELINE SCHEDULE

RESE

RVO

IR F

ILL

TO E

L.64

0FA

LL 2

014

-20

17

Page 16: San Vicente Dam Raise Update - May 2013

Award Package 5 Marina Construction -Summer of 2013

Complete Filling to Height of Existing Dam

Award Package 4 Bypass Pipeline Construction -Summer of 2014

Begin Filling to Full Height of Raised Dam

Upcoming Activities

16