Version: 01 Confidential Odisha Power Generation Corporation Limited Page 1 of 72 ODISHA POWER GENERATION CORPORATION LIMITED IB THERMAL POWER STATION AT/PO: BANHARPALI DIST.: JHARSUGUDA 768 234 (ODISHA) INDIA TELEFAX: +91 6645 289317 Email: [[email protected]] Bid Document for “Roll out of SAP Application and Implementation of DMSat OPGC.” NITNumber:ITPS/CC22/201718/14, Date: 9th February, 2018, Sl No. 01 Date of Issue: 21.02.2018

Upload: lynhi

Post on 31-Mar-2018

222 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 1 of 72

 

  

 

ODISHA POWER GENERATION CORPORATION LIMITED  

IB THERMAL POWER STATION 

AT/PO: BANHARPALI  

DIST.: JHARSUGUDA ‐ 768 234 (ODISHA) ‐ INDIA 

TELEFAX: +91 6645 289317 

Email: [[email protected]]    

 

 

 

 

 

 

Bid Document for 

 

“Roll out of SAP Application and Implementation of DMSat OPGC.”  

 

 

 

 

 

 

 

NITNumber:ITPS/CC‐22/2017‐18/14, Date: 9th February, 2018, Sl No. 01 

Date of Issue: 21.02.2018 

 

 

Page 2: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 2 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

TABLE OF CONTENTS  1. Project Introduction ............................................................................................................................... 4 

1.1.  About OPGC .................................................................................................................................................... 4 1.2.  Business locations ............................................................................................................................................ 4 1.3.  ERP Project – Background Note ......................................................................................................................... 4 1.4.  Brief Description of existing SAP Applications ..................................................................................................... 5 1.5.  Existing SAP landscape: .................................................................................................................................... 6 

2. Scope of Work ........................................................................................................................................ 8 2.1.  Overview ......................................................................................................................................................... 8 2.2.  Geographical scope .......................................................................................................................................... 8 2.3.  Detailed Scope ................................................................................................................................................. 8 2.4.  Detailed project activity scope: ....................................................................................................................... 10 

2.4.1.  Implementation methodology: .......................................................................................................... 10 2.4.2.  Project Management ........................................................................................................................ 10 2.4.3.  Business Process Study ...................................................................................................................... 12 2.4.4.  Hardware/ Infrastructure Sizing ......................................................................................................... 13 2.4.5.  Configuration and Customization ....................................................................................................... 13 2.4.6.  Data Conversion ............................................................................................................................... 13 2.4.7.  System administration ...................................................................................................................... 13 2.4.8.  Testing ............................................................................................................................................. 14 2.4.9.  Training and change management ..................................................................................................... 14 2.4.10.  Go‐Live preparedness & Acceptance .................................................................................................. 15 2.4.11.  Post Go‐Live support ......................................................................................................................... 16 2.4.12.  Performance Guarantee of the solution .............................................................................................. 16 2.4.13.  Final Acceptance of the Solution ........................................................................................................ 17 2.4.14.  Post Implementation SupportServices ................................................................................................ 17 2.4.15.  SLA during Support ........................................................................................................................... 18 2.4.16.  Conflict with Existing Support Vendor ................................................................................................. 18 

3. Qualification and Evaluation ................................................................................................................. 19 3.1.  Qualification to bid ........................................................................................................................................ 19 3.2.  Mandatory Qualification Criteria for Bidding .................................................................................................... 19 3.3.  Evaluation & Comparison of Bids ..................................................................................................................... 21 3.4.  Award Criteria ............................................................................................................................................... 24 3.5.  Negotiation ................................................................................................................................................... 24 3.6.  Signing Of Agreement .................................................................................................................................... 24 3.7.  Failure to Commence the Work ....................................................................................................................... 25 

4. Deliverables & Timeline ........................................................................................................................ 26 4.1.  Timelines ....................................................................................................................................................... 26 4.2.  Deliverables ................................................................................................................................................... 26 4.3.  Performance Parameters ................................................................................................................................ 27 

5. Price Schedule and Payment terms ........................................................................................................ 29 5.1.  Price Schedule for Project ............................................................................................................................... 29 5.1.1. Implementation of Roll‐Out in OPGC‐II & Additional Modules ............................................................................ 29 

Page 3: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 3 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

5.1.2. Change Request & Scope change ..................................................................................................................... 29 5.2.  Payment terms .............................................................................................................................................. 30 

6. CONDITIONS OF CONTRACT .................................................................................................................. 31 X.1  Liquidated Damages for Delay ........................................................................................................................ 41 X.2  Liquidated Damages for Performance .............................................................................................................. 41 

7. E‐Reverse Auction & its Rules & Regulations .......................................................................................... 47 8.  Instruction to Bidder: ........................................................................................................................... 50 9. Bid supporting documents .................................................................................................................... 59 

9.1 Letter of Undertaking by the Bidder .................................................................................................................... 59 9.2 Exclusions / Deviations Statement ...................................................................................................................... 61 9.3 Performa for Bank Guarantee for Bid Security (Earnest Money Deposit) ................................................................ 62 9.4 Integrity Pact..................................................................................................................................................................64 9.5 Owner Safety Rules…………………………………………………………………………………………………………………………………………………..70 

 

Page 4: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 4 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

 

1. Project Introduction 

1.1. About OPGC Odisha Power Generation Corporation Limited is a company incorporated under the Companies Act 1956, India in the year 1984  (“OPGC” or  the “Owner”).   OPGC started as a wholly owned company of  the Government of Odisha  (the “GoO”) with the main objective of establishing, operating and maintaining large thermal power generating stations.  In the pursuit of  its objective, OPGC established  IBThermal Power Station having  two units of 210 MW each  in  the  Ib valley area of Jharsuguda District in the state of Odisha (“Unit‐ 1 and 2” or “OPGC‐I”) (“ITPS”).  The plant has been in operation  since  1994.    The  entire  generation  from  these  units  is  contracted  to  GRIDCO,  the  state  owned  trading company/bulk supplier, on the basis of a long‐term power purchase agreement.   OPGC’s expansion project (“Unit‐3&4” or “OPGC‐II”) consisting of power plant of 2x660 MW and a dedicated railway line for transportation of coal, are in an advanced stage of construction and the plant is expected to be commissioned  by 2018.  OPGC also has seven mini‐micro hydro power projects spread out at various locations, with a total installedcapacity of 5.4 MW.   1.2. Business locations OPGC has two primary business  locations. The head office  is at Bhubaneswar, the capital city of the State of Odisha. Bhubaneswar is connected to most of the major cities in India through roads, railway and air. The plant is located at Ib Valley,  in Jharsuguda District, which  is  located at a distance of about 400 kms from Bhubaneswar. Jharsuguda  is well connected to Bhubaneswar through roads and railways.   

1.3. ERP Project – Background Note In line with OPGC IT strategy roadmap, SAP ERP Application was implemented in the organization for the operational Unit#1&2. SAP ECC 6.0 (EHP 7.0) on HANA Database was implemented with the following modules and the applicantion is hosted in SAP HANA Enterprise Cloud Infrastructure. 

1. Finance& Controlling (FICO) 2. Material Management (MM) 3. Plant Maintenance (PM) 4. Project System (PS)  5. Environment, Health and Safety (EHS) 6. Human Resource Management (HRM) which essentially should include ESS, Payroll, HR. 

 The Go‐Live of the  implementation was made on 1st February 2016 and currently SAP application  is being used by all business functions of OPGC‐I.  OPGC‐II construction work is in progress and it will be made operational by end of 2018. Hence, OPGC intends to roll out  the  existing  SAP  ERP  Application  to  Unit#3&4.  In  addition  to  the  roll  out,  OPGC  also  intends  to  implement  Document Management System (DMS) in both OPGC‐I & OPGC‐II.  Bidders are requested to provide a complete comprehensive solution and services to address the OPGC’s requirements envisaged as defined in the “scope of work” section.   

Page 5: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 5 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

SAP License details:  

Description SAP Application Professional  SAP ApplicationESS/MSS Existing  Addition  Existing  Addition 

SAP Named User  175 100 750  150Payroll Processing   2 units Master Record (Units of 500) EHS   One unit of Annual Revenue Level (unit of 100 Million EURs)SAP Application Netweaver Process Integration (PI) 

5 GB per month 

NB:  1. Existng Licenses have been procured by OPGC. 2. Additional Licenses are to be procured by OPGC. 

 For  smooth  conduct  of  the  project,  OPGC  would  be  identifying  and  forming  a  Steering  Committee,  Project Management team, Core team, Business Team andData Preparation Team. 

 1.4. Brief Description of existing SAP Applications 

Module  Process List 

PM  PM Master Data Management 

PM  Corrective maintenance Process 

PM  Preventive maintenance Process 

PM  Breakdown maintenance Process 

PM  Condition based monitoring process 

PM  Rectification & continuous improvement process 

PM  Overhauling Process 

PM  Work Clearance Management 

MM  Management of Material management Master Data 

MM  Coal Procurement Process 

MM  Procurement of Capital goods / Assets 

MM  Procurement of Subcontracting goods 

MM  Procurement of Services‐Contracts 

MM  Procurement for Projects (WBS) 

MM  Procurement of Consignment goods 

MM  Material Procurement process 

MM  Procurement of Fuel, Lubricant,HSD 

MM  Process for Physical Inventory 

MM  Issue of Goods 

MM  Scrap disposal and Ash Utilization process 

MM  Transfer Posting Process 

MM  Vendor Performance process (Vendor Rating) 

PS  Project System Master Data 

PS  Project Planning 

PS  Project Execution 

Page 6: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 6 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

Module  Process List 

PS  Project Closure 

FICO  Master Data 

FICO  General Ledger Accounting 

FICO  Accounts Payable 

FICO  Accounts Receivable 

FICO  Cash Accounting 

FICO  Bank Accounting 

FICO  Asset Accounting 

FICO  TDS & Service Tax Accounting 

FICO  Fund Management 

FICO  Closing Books/Year end process 

HR  Man Power Planning 

HR  Recruitment 

HR  Personal Administration 

HR  Performance Management System 

HR  Time Management 

HR  Payroll and Benefits 

HR  Personal  Development 

HR  General Administration 

EHS  IndustrialHygiene and Safety 

EHS  Occupational Health 

EHS  Waste Management 

EHS  Audit Management 

 

1.5. Existing SAP landscape: 

OPGCSAP ECC Landscape S. No.  Systems  SID  Database  Hostname 

1  ECC Dev  OED     OED 2  ECC QAS  OEQ     OEQ 3  ECC PRD  OEP     OEP 4  ECC Dev DB     HANA DB  HANA 5  ECC Quality DB     HANA DB  HANA QA 6  ECC Prod DB     HANA DB  HANAPRD 

Page 7: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 7 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

 Installed Products and Versions  S.No.  Product  Version  Description 

1  EHP7 FOR SAP ERP 6.0  EHP7 FOR SAP ERP 6.0  EHP7 FOR SAP ERP 6.0 2  SAP ERP  2005  SAP ERP 6.0 3  SAP NETWEAVER  7.4  SAP NETWEAVER 7.4 

ECC Host  Releases  ECC Database Releases Operating System  Linux 2.6, Linux 3, Linux  DB Release  HDB 1.0 OP Release   3.0.101‐0.40‐default  DBSL version 742.06 Machine type  x86_64  DBSL Patch Level 114

 

OPGC EP Landscape 

S. No.  Systems  SID Database 1  EP Dev CI + DB  OPD Sybase 2  EP Quality CI + DB  OPQ Sybase 3  EP PROD CI + DB  EPPRDAPP Sybase 

 

Installed Products and versions 

EP Host  Releases  EP Database Releases VM Name  SAP Java Server VM   Database Adaptive Server Enterprise (16.0.01.01)  VM Java Version   1.6.0_85   Driver Vendor Open SQL  VM Runtime Version  6.1.072 24.71‐b01  OS: Linux (amd64) 3.0.101‐0.40‐default

Page 8: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 8 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

 

2. Scope of Work 2.1. Overview  OPGC intends to roll out the existing SAP ERP Application and additional in its new units in order to  

1. Bring homogeneous corporate management approach across all the all the business units / locations 2. Bring all the business workflows with rightly configured validations and to avoid overhead activities 3. Availability of right information online for all the users concurrently 4. Complete and correctness in enterprise transactions at all the business scenarios 5. Enterprise wide user access based on roles and privileges 6. Maximise the operational excellence and lower the overall cost of operation  7. Configurability using the master data approach to meet the growing demand over the period including the 

future implementation at the new project locations by addition of new project specific master data.  2.2. Geographical scope The proposed project implementation will be carried out in the following geographical locations 

a)  ITPS Plant / Works – Banharpali, Jharsuguda (Odisha) b)  Head Office – Bhubaneswar   

 2.3. Detailed Scope 2.3.1 Roll Out of Existing Solution SAP  solution already  implemented  in Unit1&2 would be  rolled out  to Unit 3 & 4. The Roll out activity needs  to be carried for below mentioned modules. The existing Business Process list in each module is in section 1.4  

• Finance & Controlling  • Materials Management • Plant Maintenance • Project System • Human Capital Management • Payroll and ESS/MSS 

As part of the roll out, existing processes of SAP for Unit 1&2 to be rolled out for Unit 3&4. However, Minor changes 10‐15 % in business processes and system configuration to be considered, if it is found that those changes are required. A fresh blueprint is to be prepared based on the implementation of OPGC‐I to be rolled out for OPGC‐II with the minor changes in the business processes and system configuration.  Roll‐out would involve following activities  

• Study of Existing Blueprinting, identify delta changes required for roll out and preparing new blueprint.  • Extending Configurations & Custom Developments as available in Production system for Unit 1 & 2 to  

Unit 3 & 4.  • Training and Testing (Unit and Integration) • Data Migration • Cut‐Over &Go‐Live 

 2.3.2 Implementation of Additional Modules for all Units (OPGC‐I&II) The following additional Modules shall be implemented for both OPGC‐I and II.  

• Document Management System(DMS) 

Page 9: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 9 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

 A. Implementation of DMS 

SAP DMS will be  implemented  to  support document attachments  in approval  transactions and management of various documents in all modules in form of electronic repository.  • Business Processes to be covered in DMS 

Document Create/Change/Display/Find ∙   Document Change Management ∙   Document Status Management ∙   Document Object Linking ∙   Document Version Management 

• Master Data  Document info Record (DIR) ∙   Status of DIR Class and Characteristics 

• Integration of DMS with all the modules (PM, MM, PS, FICO, HCM). • Document types that will be uploaded may be .pdf,.doc,.xls,.jpeg,.drw. etc. Visual Enterprise Viewer 

integration is to be implemented to view drawing files. • Creation of Enhancement Workflows 

    The capping for custom RICEFW objects to be developed as part of roll out and additional modules in order to cater various legal, statutory & Management reporting for all modules is 40.  

Page 10: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 10 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

 

2.4. Detailed project activity scope: 

The bidder will be responsible for the following: • Implementation methodology • Project management, planning and scheduling,  project status reporting • Quality Assurance activities during the implementation process (Milestone deliverable completeness 

review / check list) • Additional Hardware/ Infrastructure sizing  • Business process study (current state business process, future state business process, business 

blueprint) • Design, configuration, customization and implementation of ERP to meet the solution requirements  • Reports development / configuration • Testing throughout project phases including related audit/ validation • Interfacing and integration with existing applications • Data conversion / Migration data validation  • Go‐Live preparedness (including UT/SIT/UAT, Cutover) • Post go‐live support and help desk • Warranty support services 

 2.4.1. Implementation methodology: The successful bidder must carry out the implementation based on well‐defined and proven methodology covering all the phases / activities of the project including the usage of predefined forms, templates and formats and best practices to start the implementation process with well‐defined framework and to cut down overall implementation time and to bring the better outcome at every stage of the project. The Bidder must have sufficient prior experience in using this methodology, tools and formats on sustained basis in implementing the ERP solution.  The bidders are  specifically asked  to provide  their approach on how  their proposed  solution will address  the above requirements with clear responses.  2.4.2. Project Management    Project Management Structure The Project Management Structure for this engagement consists of the following stakeholder groups:  

• Steering Committee consisting of OPGC top management and Program Manager  from the bidder. • Project Management Office,  consisting of  a project manager  from OPGC  and  Project Manager(s)  from  the 

Bidder. • Core Group,  consisting of  functional  experts,  technical  experts  and  infrastructural  experts provided by  the 

bidder, technical resources (IT) and functional resources (core and business users) from OPGC. • Non‐Core Group consisting of  the end users/power users  in OPGC, and  the Helpdesk  team  (resources  from 

both OPGC and bidder)  Project Team The Bidder will  form a  full‐time  team, specialized and experienced  in ERP  Implementations  to ensure successful and timely completion of the project,consisting of Program Manager, Project Manager, Functional & Technical Team Leads and   other  team members. The bidder  should be prepared  to  commit  the  team  to  the project and  should prevent changing of resources during the project. The Bidder shall not sub‐contract any part of the tender requirements stated 

Page 11: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 11 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

and should declare the same in the bid. The key personnel in the team must have the minimum qualifications and work experience as specified in Qualification and Evaluation, section 3. The  Bidder  should  submit  a  detailed  project  plan  (which  should  be  updated  regularly)  indicating  the  key  phases  / activities of the project and the expected time lines for each phase / activity. The Bidder will further detail the project plan  in  early  stages  of  the  project  and  get  the  same  validated  from OPGC. OPGC  Project Management  Team may suggest changes to the plan where necessary.   The project plan should include the following at minimum: 

• The project broken up into logical phases and sub‐phases • Activities making up the sub‐phases and phases • Key milestones and deliverables along with their dates • Start date and end date for each activity • The dependencies among activities • Resources / consultants to be assigned to each activity • Resources (core team, business team and process owners) expected from OPGC for each activity • Each  deliverableduring  the  implementation  phases  shall  have  clearly  assigned  duration  and  resource  for 

review, implemention of review comments and signoff • Formal review / singoff shall be doneusing the standard review checklist provided by the bidder and reviewed 

&agreed during the project kick off stage. • Risk review activiites with defined frequency and reporting 

 The  bidder  is  requested  to  provide  implementation  overview  training  to  the  core  team  members  based  on  the proposed implementationmethodology, which shall cover the following 

• Each phase activities / deliverables with its review process • Phase Dependencies • Roles and responsibilitiesof teams from Bidder and OPGC  

 Deployment of team The bidder would have to deploy a full‐time dedicated team for the ERP implementation project at OPGC.   After  the  ERP  system  goes  live,  all  the  implementation  resources  (Mandatorily  01  resource  for  each  respective module)that would be required to be present to support OPGC adequately and appropriately needs to remain on‐site at OPGC  till  end  of  Performance Gurantee  period.  Remaining  team members may  support  the  on‐site  team  from offshore delivery centres of the bidder as and when required.        The bidder  is requested to provide an  indicative manpower deployment plan (Pre go‐live and Post go‐live) as part of their response to this bid document.   To ensure commitment to the project from OPGC, OPGC  intends to deploy adequate number of people  in a full‐time dedicated manner  for  the  project  in  the  form  of  core  team  and  consultant.  The  core  team will  be  augmented  as required by part time team members for which bidder would plan with OPGC in advance.  Bidder  should  deploy  the  personnel  during  implementation.  If  any  change  in  position/person  is  required  during implementation  till  Final acceptance, prior approval  to be  taken by OPGC  to deploy alternate  resource with  similar qualification and experience.      

Page 12: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 12 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

  Project Reporting  The Bidders should describe the proposed project reporting methodology. At a minimum, the Bidder should submit to OPGC a written progress report every week. The frequency may be  increased during critical phases of the project.  In addition,  the  Bidder  shall  report  on  a  continuous  basis  exceptions  and  issues  that  require  immediate  attention  of OPGC.  Progress report shall have the following attributes as a minimum, 

a) Highlights / milestone achievements b) Project  c) phase progress (Planned, Actual, Delay, Deviation %) d) Activities during the period e) Activities planned for the next week f) Milestone delivery status  (Planned   / actual completion date,  reason  for  the delay  if any with planned next 

delivery date) g) Dependancy / requirement from OPGC h) Risk status with owner who responsible to mitigate these risks i) Team deployed at site (Role with no. of resources in each role) j) Items required management attention 

 For any dependencies on OPGC, the bidder should plan and intimate OPGC well in advance (at least 1 week) to avoid any delay from OPGC’s side.    The Bidder will be  responsible  for  informing  the Steering Committee about progress of  the project. The Committee Meetings should be held at  interval of around one month. The date and  time of  the meetings will be  finalized  from time to time.  2.4.3. Business Process Study  Business Process Study (Roll Out)  The Bidder will be required to study the current business blueprint documents for the modules implemented in OPGC‐I, requirement  study  for OPGC‐II,  suggest  suitable  changes  as may  be  necessary  and  prepare  a  new  set  of  Business Blueprint Documents.    Business Process Study (For Implementation of Additional Module)   The Bidder will be required to study the business processes, which would be covered in the implementation. OPGC will validate this list and suggest suitable changes as may be necessary.  Based on the agreed business process coverage of the implementation, the Bidder will:  • Conduct a detailed Business Process Study and propose process changes / improvements that would be facilitated 

by / necessitated in the solution • Identify the workaround solutions / customizations / interfaces to be developed as part of the implementation • Verify the above solutioning with the responses the bidder had provided in the bid response (functionality matrix) 

to ensure that the approach is consistent as best possible. Any deviation has to be provided in writing to OPGC. • Provide expert inputs based on implementations of similar industry • Refer  to any previous  implementations/ Center of Excellence  that bidder possesses, and provide best practices 

from the same 

Page 13: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 13 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

• Identify information requirements for each business process • Identify data conversion elements for each business process • Identify the legacy systems that may be retained • Involve Subject Matter Experts (SME) of the relevant business units during the design phase. 

 Bidders are expected  to bring  in  their best practices based on  their past experiences against each module  towards creation  of  the  best  business  process  to meet  all  the  functional  requirements with  efficient  operations  and  user experience. 

 2.4.4. Hardware/ Infrastructure Sizing As  OPGC  SAP  is  hosted  in  HEC  HANA  Enterprise  Cloud,  so  bidders  are  expected  to  finalize  the  additional  sizing requirement for the roll out and additional implementation in consultation with SAP HEC Team.  2.4.5. Configuration and Customization OPGC prefers  to have minimum customization  in  the ERP Solution. Preferably, change should be kept as minimal as possible to the ERP core modules. This  is  important to ensure that future upgrades, enhancements and bug fixes are not  impacted. Minimal customisation as may be necessary should be done only after obtaining approval from OPGC. Every custom development must be documented in detail and the script ownership should be passed on to OPGC. The capping of RICEFW is in the SOW.  Documentational  requirements:  The  bidder  shall  propose  a  governance  mechanism  for  management  of customizations. At minimum, every request for development of custom report must be documented  in a pre‐defined format  and  supported by  a business  case prepared by  the process owner while  requesting  for development. Every custom report development must be documented in terms of the person developing the report, the reference request in response to which the report is being developed, the report script and other technical specifications. Basic guidelines with  respect  to  all  custom  report  formats,  naming  convention  etc. must  be  agreed with OPGC well  in  advance  of commencing any customization effort.  In addition,  the bidder  is required  to  train OPGC Core/ Technical Team members on  the methodology of developing customizations, so that OPGC can take up the additional development as and when required.  2.4.6. Data Conversion The Bidder should submit a high level Data Conversion Strategy Document during the Business Process Study stage of the  project  describing  the  broad  data  elements  to  be  converted,  source  of  the  same,  target  ERP module  and  the detailed form  in which the same will be converted (i.e. both at transaction  level or at balance  level and the coverage period) with time frame for activities.  While  preparing  the  data  conversion  strategy  document,  bidder  should  consider  best  practices  for  master  data coverage, including optimal usage of SAP standard fields for capturing various information requirements.   2.4.7. System administration Typical system administration activities for ERP to be undertaken by the Bidder include:  

• Configuration, administration, trouble shooting and performance tuning of all servers  (database, application etc.) 

• Database software installation, memory allocation and usage monitoring • Backup, recovery and all other DBA related activities • Providing access to users as per the assigned roles • Installation of applications and related tools 

Page 14: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 14 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

• OS patch update/ Anti‐virus / Firewall update and necessary document management of the same.  The successful bidder would also assist OPGC in:  

• All authorization related activities till ERP System stabilizes • Assimilating knowledge through a proper knowledge transfer methodology, ensuring that the OPGC team can 

take care of system administration tasks including data backup, restore process. • Prepare system administration manual • Prepare end user manuals for all employees accessing the ERP enabled production environment • Prepare  owner  ERP  system  management  manual  keeping  in  mind  the  specific  configuration  of  solution 

implemented at OPGC • Prepare system configuration that takes into account disaster recovery scenario • Providing regular system performance reports and identifying root causes of issues 

 The Successful bidder is responsible to identify and inform OPGC about pre cutover requirements like database setup, application patching techniques, operating system patching, database tuning and database synchronization etc.  

 The system administration responsibility would be with the Bidder till the end of the project.  2.4.8. Testing The bidder shall provide detail strategy for different type of testing which should be carried out in different phases of implementation, pre‐ go‐live.   Details of  the  testing strategy and approach should be provided  in  the  response. The bidder is responsible to identify and inform OPGC regarding testing requirements and impacts.   The successful bidder shall work in a manner to satisfy all the testing requirements and adhere to the testing strategy outlined. The successful bidder must ensure deployment of necessary resources and tools during the testing phases. The bidder shall take remedial action based on outcome of the tests.  Bidder is expected to prepare the detailed test specification for each functional modulewhich shall cover the complete features,  reports,  master  data,  configuration  and  validation  etc.  for  all  varied  tests  to  be  conducted  during  the implementation life cycle. 

a) Standalone module testing b) Integration testing c) User Acceptance Test d) Data migration testing 

 2.4.9. Training and change management In the response document to OPGC, bidder should explicitly mention about:  

• The approach and plan for training Core / Business / Technology Team members at OPGC and end users along with the time frame, giving number of days for which each type of training will be provided 

• Provide a description of the training hand‐outs / manuals to be provided  The training plan as required and envisaged by OPGC is provided below. 

• During the initial project mobilization phase,  the core team members shall be provided brief overview trainingfor initial understanding of the ERP.   

• The Core Team members shall be given in‐work traiing during the implementation phases. • After User Acceptance Testing and before Go‐Live, the end‐users of the system shall be given training.  

 

Page 15: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 15 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

All core and key business users would be imparted training directly by the Bidder. The end‐user trainings before go‐live would be conducted in the ‘Train the Trainer’ mode. Here the bidder would train key core and power end‐users of the system directly who will further be the trainers. Further the ‘trainers’ will then train the rest of the end users. For end‐user training before go‐live the successful bidder would be training some end‐users apart from core and business team members.  The no. of users  to be  trained would be decided  at  the  time of  training by OPGC  and  successful bidder mutually. 

 The Bidder will be responsible for preparation of the training material and end user manuals. End user manuals should cover “how to use” concepts for all modules of the solution being  implemented.  Explanation  for  the  teams  to  be provided by OPGC is provided below. The teams may not be independent and separate but the teams will be present in the project in spirit to support smooth   completion of the project:  Change Management Workshops The Bidder will suggest anticipated change management related issues and proposed solutions to overcome them. The Bidder is expected to conduct Change Management programs / workshops for OPGC senior management / end users.   The change management workshops should be conducted at appropriate stages of the project and should not be less than two at each major phase by the bidder preferably after completion of each major project milestone to apprise the concerned end users of the changes decided upon.  As part of monitoring overall change management of the implementation, the bidder would be responsible for creating a change management approach strategy/ report after identifying the Change Management issues around: 

‐ Processes/Procedure ‐ Roles/Responsibility ‐ Organization structure/Group Working 

 2.4.10. Go‐Live preparedness & Acceptance Go‐Live of  the solution would occur at  the successful  transfer of  the solution  into production environment  (go‐live), and  subsequently,  a  comprehensive  post  go‐live  support  shall  be  provided  by  the  successful  bidder.  The  bidder  is responsible  for deploying  the  system  in Production Environment  in  line with  the overall  timelines of  the project.  In addition to this, upon successful deployment of solution to production environment, the successful bidder shall provide stabilization of  the solution and Performance Guarnatee services as elaborated  in subsequently  in  this  tender  in  the “Performance Guarantee” subsection 2.4.12.   User Acceptance and Go‐live Operational Acceptance Tests The Successful bidder will assist  in conducting the User Acceptance Tests by creation of test scripts, supporting core team members and removing deficiencies to ascertain whether the solution or any sub‐system(s) is capable of attaining the  functional and performance requirements  (relating to commissioning) as specified  in the Tender Documents and the Agreed and Finalized Project Plan. All deficiencies (technical and functional) arising as an analysis of the result of the  User  Acceptance  test  shall  be  duly  be  remedied  by  the  Successful  Bidder.  Upon  successful  conclusion  of  any retesting if required, and upon acceptance of the results of the test, Go‐Live activities would commence.  The Successful bidder will conduct Go‐live Operational Acceptance Tests to ensure that the solution is available for live transactions to attain the functional and performance requirements as specified in this document and the Agreed and Finalized Project Plan.    Cutover During Go‐Live stage, successful bidder shall review the readiness for cutover. Bidder shall prepare a detailed cutover strategy comprising of all relevant cutover dimensions (e.g. data, business processes, live transactions, communications to  internal and external  stakeholders, etc.).  In anticipation of go‐live, help desk activities  should be  ramped up and 

Page 16: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 16 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

resources  deployed  adequately  to  ensure  that  transition  to  production  environment  can  be  done  smoothly.  All activities  pertaining  to  phasing  out  legacy  systems  should  be  completed  by  the  time  transition  takes  place  to production environment and ensure that in the interim period, appropriate interfaces are there during the transition. The cut over from  legacy to new ERP system should be done  in accordance with the cut over strategy prepared and approved by bidder and OPGC respectively.  Review of data migration, test scenarios prior to go‐live and interfaces as well as integrations shall be monitored by the successful bidder at this point. All transaction data that would be critical to functioning of the integrated solution in the Production environment should be migrated to ensure successful functioning of the system.   At  the successful completion of aforementioned activities,  the successful bidder shall switch  the ERP solution  to  the Production  Environment  and  commence  Go‐Live.  Different  modules  rolled  out  (Go‐Live)  for  production  will  be operated  in an  integrated environment as per the agreed & finalized project plan. Upon successful operation of “ERP Solution” in the production environment, Go‐Live acceptance certificate will be issued  2.4.11. Post Go‐Live support 

The Post Go Live  Support will start from the date of Go live and continue for the period as mentioned at 4.1. During the Post Go live Support period, the Successful bidder will provide on‐site post implementation support (Mandatorily 01 Resource from each respective module). Bidder should cover the minor configuration elements changes (location change, minor  field edits, enterprise structure element extensions/ changes/release strategy) as part of post go‐live support.  Note: Any changes that are an enhancement in functionality and require new development/ substantial configuration may be raised as change request by bidder with proper justification for acceptance of OPGC as per their discretion.  Help desk support  The  Successful  bidder would  have  to  setup  a  Help  Desk  comprising  of  core  /  business  users  from OPGC  and  key representatives (functional and technical) from the Successful bidder’s project team. This Help Desk would be setup to support the usage of the system, to resolve issues and ensure smooth usage.  The bidder would be responsible for supporting and rectifying all issues identified, in line with the SLAs defined below. The bidder is requested to provide a manpower deployment plan for meeting post go‐live support requirements.  The help desk support to users shall be provided on 24 x 7 basis.  Vendor response time will be the basis for end‐user support response time in Owner’s service level agreements with the Vendor. The Vendor will follow response time as per  the  SLA  defined  at  2.4.15.  The  Help  Desk  should  have  established  communication  channels,  issue  reporting mechanisms, closure of issues etc.  2.4.12. Performance Guarantee of the solution The bidder will guarantee to OPGC, the performance of the Solution with respect to the parameters as achieved during Post Go Live phase. The period of Performance Guarantee (PG) shall be as per the timeline specified at 4.1.During the Performance Guarantee Period, the Successful bidder will provide on‐site post  implementation support (Mandatorily 01 Resource from each respective module).  Bidder should cover the minor configuration elements changes (location change, minor field edits, enterprise structure element extensions/ changes) as part of post go‐live support.   

Page 17: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 17 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

Note: Any changes that are an enhancement  in functionality and require new development or   substantial change  in configuration, may be raised as change request by bidder with proper justification for acceptance of OPGC as per their discretion.  2.4.13. Final Acceptance of the Solution The Solution will be taken as finally accepted at the end of Performance Guarantee Period.  2.4.14. Post Implementation SupportServices The successful bidder should provide Support Services of the ERP solution for a period of One Year from the date of Final Acceptance. Towards service support, the successful bidder shall provide support of the latest version/ release at any  point  of  time  (if  necessary).  The  support  should  include  new  releases,  upgrades,  updates,  bug  fixes,  defects, incremental  functionality  enhancements  and  patches  to  cater  to  changes  (including  tax,  legal  and  all  statutory requirements), etc. as well as 24X7 Technical support.  The successful bidder shall provide functional support and maintenance of ERP Solution, as a solution for the contract period. Annual  Functional  Support  shall  be  provided  by  trained  and  experienced  personnel  of  the  Implementation Partner and would entail the following activities: 

• 24x7 Support through telephone/Fax/E‐mail/Video Conferencing/ Installation visit as required. • Tuning of ERP, Databases, third party software’s and any other components provided as part of the business 

solution software  including reconfiguration of the system  in the event of any hardware/ network failures/  if any hardware/ network components have to be replaced. 

• Provide  and  apply  SAP  updates  &  patches  as  and  when  released.  Any  Upgrades  of  SAP Which  requires substantial changes  in  live SAP solution shall be considered  in change request mutually agree upon by OPGC and the Vendor. 

• Removing bugs as and when discovered. • Successful  Bidder must  create  and maintain  a  dedicated  centralized  Help  Desk  /  hotline  that will  resolve 

problems and answer questions that arise from the use of the ERP solutions. • Deployment of relevant technical/ functional / product consultants to Head Office/ Plant location (as decided 

by  OPGC)  of  the  installation  if  deemed  required  based  on  joint  consultation  and  agreement  between successful bidder and purchaser. 

• Bidder should cover the minor configuration elements changes (location change, minor field edits, enterprise structure element extensions/ changes) as part of post go‐live support. 

• In case of failure of any solution, reconfiguration of system should be part of scope   for bringing the system back  in  function  is  the  responsibility of  the  successful bidder. Required  casual analysis and  impact analysis should be done for such events. 

 Note:  Any  changes  that  are  an  enhancement  in  functionality  and  require  new  development/  substantial configuration may be raised as change request by bidder with proper justification for acceptance of OPGC as per their discretion. 

 The  successful  bidder  shall  consider  and  deploy  the  following  on‐site  resources  along with  necessary  off‐site resources during the tenure of support phase in consultation with OPGC.     S/N  Module  No.  of On‐Site

Resource 1.   Finance& Controlling (FICO)  1 2.   Material Management (MM)  1 3.   Plant Maintenance (PM)& Project System(PS) 1 

Page 18: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 18 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

4.   Document Management System & Basis 1 5.   Human  Resource  Management  (HRM)  which  essentially  should  include  ESS, 

Payroll, HR 1 

6.   ABAP & Webdynpro   1  The bidder shall submit the  list of such on‐siteresources along with their respective  Job Description, Experience, Role and Responsibilities and associate deliverable  for approval of OPGC. However,  in order to cater the on‐site requirement, off‐site resources of bidder would extend their support in such a manner that it does not hamper the support terms by any means.  

2.4.15. SLA during Support  The  successful  bidder  shall  adhere  to  the  following  SLA  for  responding  to  issues  during  Post  Implementation Support, Performance Gurantee period and Post  Implementation Spport phase. This  is  indicative only and would be finalized mutually between the bidder and OPGC.  

Support Category 

Criteria  MaxResponse Time 

Resolution 

Critical  The system is unable to be used for normal business activities.  

30 Minutes  90 Minutes 

Urgent  There is a problem with part of the system, which impacts on Owner’s decision making. No viable workaround is available. There is a likelihood of financial loss. 

1 Hour  4 Hours 

High  The efficiency of users is being impacted, but has a viable workaround. 

4 Hours  8 Hours 

Medium  A low impact problem that affects the efficiency of users but has a simple workaround. 

8 Hours  12 Hrs or Based on OEM confirmation 

Low  A fault, which has no particular impact on processing of normal business activities. 

8 Hours  24 Hrs or Based on OEM confirmation 

 In case of  failure to meet aforementioned response time criteria, penalty shall be  imposed  from each bill at the discretion of EIC.  If  the bidder  is  found  to be  incompetent  at meeting  the  support  guidelines,  the bidder  shall rectify the same,  failing which the bidder would be  liable to  forfeit the contract.  In any case of termination, the bidder would provide an adequate handover to either OPGC or incoming vendor. The approach for the handover shall be agreed beforehand between OPGC and the bidder.  

2.4.16. Conflict with Existing Support Vendor 

As  SAP Application  is  already  live  for OPGC‐1  and  undergoing  support  by  the  current  implementation Vendor, hence  during  roll  out  of  the  solution  in  OPGC‐2  and  subsequent  Performance  Guarantee  support  and  Post Implementation support phase, the new vendor (for OPGC‐2) is expected to function in tandem with the existing vendor  (for OPGC‐1). However,  if any conflict arises by the current support vendor on the solution support with the roll out implementation vendor then the same shall be mutually sorted out in consultation with OPGC Project Manager. In case of any dispute, the decision of OPGC Project Manager shallbe final and biding on bidder. 

Page 19: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 19 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

  

3. Qualification and Evaluation 3.1. Qualification to bid  The Bidder shall bear all costs associated with understanding the scope of work, bid preparation and bid submission. OPGC will  in no  case be  responsible or  liable  for  these  costs,  regardless of  the  conduct or outcome of  the bidding process.  The bidding process is open to any Authorised SAP Implementation Partner, who shall be able to supply, design, install and commission all of the components as described  in the Detail Scope of work at Section‐ 2 and be able to provide Post implementation support & warranty services. 

 The bidders must meet the following mandatory qualification criteria with respect to the above.  3.2. Mandatory Qualification Criteria for Bidding  

SN  Parameter  Description Supporting Documents

MQC1  Implementation capabilities in Power Generation  

The Bidder/ Implementation Partner must have done end‐to‐end SAP  implementation successfully  in 02(two) Power sector  companies  of  which  at  least  01(one)  in  Power Generation (IPP or CPP of minimum 120MW capacity) and 01  in any utility Companies.  (Modules  implemented must include FICO, MM, PM & DMS ) 

Documentary evidence in form of Completion Certificate  or Official email confirmation from client 

MQC2  Global SAP Implementation Experience  

Out  of  these  10  implementations,  there  has  to  be  a minimum of 5 end‐to‐end  implementations  containing at least four of the following modules.  1. Finance and Controlling (FICO) 2. Material Management (MM) 3. Plant Maintenance (PM) 4. Project System (PS) 5. Document Management System(DMS) 6. Human Resource Management (HRM)  

 

Documentary evidence in form of Completion Certificate  or Official email confirmation from client 

MQC3  Indian SAP Implementation Experience  

The  Bidder/  Implementation  Partner must  have  done  at least  5  successful  end‐to‐end  SAP  implementation  in  an Indian company.  All  the  implementations  should  have  been  done  for  at least  four of  the  following modules, with  a user base  of 150 or more.  1. Finance and Controlling (FICO) 2. Material Management (MM) 3. Plant Maintenance (PM) 4. Project System (PS) 5. Human Resource Management (HRM)  

Documentary evidence in form of Completion Certificate   Official email confirmation from client 

Page 20: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 20 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

SN  Parameter  Description Supporting Documents

MQC4  Financial Stability, Manpower & Quality  

a) The  company’s  turnover  from  IT  Application Implementation and Systems  Integration  services  for the  last three financial years (2014‐15, 15‐16 and 16‐17) should be at  least  INR 100 crores  for each of the three  years  and  should have  a positive net worth  in each of the last three years. 

 b) The  Implementation Partner  should have  its Delivery 

Centre  / R& D  /  CoE  in  India with  overall  employee strength of not less than 500 employees on its payroll as on 31stDec 2017. The Implementation Partner shall have  a  Delivery  staff  strength  of  at  least  50  SAP Certified  personnel  on  its  payroll,  as  on  31st  Dec 2017.   

 c) The  Implementation  Partner  should  have  a  CMMI 

Level  III  Certification  or  ISO  27001  certification  or similar SEI certification. 

  

Audited Financial Statements (Balance Sheet, Profit Loss Account / Statement of Profit and Loss etc) for the each of three years   Self‐certificate from company’s authorised signatory along with authorized valid signatory    Copy / details of certificate  

MQC5  Alliance with Vendors / Vendor Accreditation 

The Implementation Partner (IP) needs to be an authorized partner of SAP for the offered   SAP product. 

SAP declaration document highlighting the vendor partnership with SAP 

MQC6  Company documents  a) Initial company formation documents     

b) PAN and other tax details     

Certificate of Incorporation. Memorandum of Association / Articles of Association.  Scanned copy of valid GSTNTax Registration Certificate and PAN.  

 Bidders to note that “No consortium or subcontracting will be allowed” for participating in the tendering process. Note: 

Please note that the bidder should prepare a summary table (as per MQC table worksheet of “MQC Tabulation summary” excels that 

can  be  downloaded  as  part  of  the  RFP.  Please  note  that  the  bidder  would  be  responsible  for  completing  Columns  E  and  F 

respectively, and providing the same in excel format as part of “Technical Evaluation Sheet. Xlsx” of the submitted bid, mentioned in 

section 4.3. 

With regards to the bidder’s international customers only, if the bidder is under obligation not to disclose the required supporting 

documents,  the  bidder  shall  submit  an  undertaking  stating  the  details  of  their  experience  for  their  international  customers  on 

Company Letterhead with Company Seal duly signed by the authorised signatory of the bidder. 

Page 21: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 21 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

 3.3. Evaluation & Comparison of Bids  Stage‐1: Preliminary Examination of Proposals (Qualification requirement & Original EMD)  OPGC  will  examine  the  Proposals  to  determine  whether  they  are  complete,  whether  required  EMD  have  been furnished, whether the documents have been properly signed, and whether the Proposals are generally in order.  If a Proposal qualifies as per Mandatory Qualification Criteria, then Bid shall be considered for next stage of evaluation.  Stage‐2: Techno – Commercial evaluation: 

The technical scores will be calculated as 

 Technical Evaluation for SAP Implementation 

  Ts= (Tb1/Tmax1)*100 

Where 

Ts = Normalized technical score of the Bidder under consideration, 

Tb1 = Evaluated technical score for the Bidder under consideration, 

Tmax1= Maximum evaluated score for amongst all the Technically Qualified bidders. 

If the Techno Commercial Bid  fails to meet minimum criteria of 75, Techno Commercial Bid will be rejected and the Price Bid will not be opened.   The Techno Commercial Bid with highest evaluated  rating will  receive  the maximum marks of 100.  The number of points awarded to the other Techno Commercial Bids is arrived at by dividing the rating of each by the rating of the top Bid, and then multiplying by the maximum possible number of points.  

 OPGC  shall notify  the bidders  that have  secured  the minimum qualifying mark,  indicating  the date and  time  set  for opening the Financial Proposals.   The bids will be evaluated on the following Technical evaluation criteria (TEC): 

 TEC a ‐ Clarity & completeness of the Bid – 5% 

 TEC b ‐ Credentials of the bidder in implementing SAP (40%) – Breakup as below   

 TEC b (i) ‐  For Indian Customers covering at least FOUR of the following modules (SAP FICO, MM, PM, PS, HR, ESS, DMS) of which FICO, MM, PMare mandatory – 20%  TEC b (ii) ‐ For Global Customers covering at least FOUR of the following modules (SAP FICO, MM, PM, PS,  HR,ESS, DMS) of which FICO, PM are mandatory – 10% TEC b(iii) ‐ Customers in the Power Generation Companies / CPP where SAP has been implemented by the bidder – 10%   Note: The above details  should be populated  in  the  “Credential  in  SAP  Implementation” worksheet of “Technical Evaluation sheet.xlsx” attached with  this RFP and provide Y/N  in the respective column  (TEC b(i), TEC b(ii), TEC b (iii)) against each citation provided by the bidder. 

 

Page 22: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 22 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

TEC c ‐ Bidder’s Project Implementation Methodology, Project Management approach & depth of SAP Centre of Excellence (CoE) ‐ 10% 

 The  bidder  must  carry  out  the  implementation  based  on  a  well‐defined  and  latest  methodology  to jumpstart  the  implementation  process  and  cut‐down  on  the  overall  implementation  time.  The  bidder must have sufficient prior experience in using this methodology on sustained basis in implementing SAP in Power Generation Companies. 

 Bidder has to consider the following aspects in addition to above 

1. The  bidders  are  to  provide  innovative  and  proven  value  addition  to  the  standard  ASAP methodology and clearly indicate how it can benefit the overall Project deliverable. 

2. Project Control and Governance Mechanism such as Overall Project Team structure, Review and Escalation methods, etc. 

3. Showcase an SAP Center of Excellence and proposed tools and frameworks derived from the CoE that would be applied for this engagement (e.g. help desk monitoring, issue management tools, reusable  components,  similar  engagement  best  practice  incorporation,  process  beneficiation, etc) 

4. Understanding of the functional scope of the project and how best it could be solutioned in SAP.  

TEC  d  ‐  Bidder’s  Resource  Strength  in  SAP  –  List  of  Certified  SAP  professionals  employed  in  organization’s payroll in India ‐ 10%     

 TEC e ‐ Capability and experience of key personnel – 20% 

 Role  Criteria

Project Manager  Minimum 07 Years’ experience having at least three (03) SAP implementation cycle experiences 

Delivery Manager  Minimum 07 Years’ experience having at least three (03) SAP implementation cycle experiences 

Organization Change Management Lead 

Minimum 07 Years’ experience having at least three (03) project experience as Change Management Lead  

Functional Integration Lead / Sr. Consultant 

Minimum  06  years  of  experience  in  SAP  implementation which  includes  at least one project experience in a Generation plant. 

Technical Leads  Minimum 06 years of experience in Technical Lead position having at least (02) two  SAP  implementation  cycle  experience  for  the  offered  product  which includes experience in developing custom components / building interfaces to legacy applications 

Functional/Technical Consultant  Minimum 04 years of experience in SAP implementation including at least (01) one complete SAP implementation cycle experience for the function for which he/ she is proposed to represent 

ABAP/BASIS/ Technical Consultant  Minimum 04 years of experience in SAP implementation in the pertinent field

 Note:  The  above  details  should  be  populated  in  the  “Experience  of  Key  Personnel”  worksheet  of “Technical Evaluation sheet.xlsx” attached with this RFP against each role mentioned.  

Page 23: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 23 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

TEC f ‐ Presentation ‐ 15%  

Qualifying bidders would be expected to give a presentation of the proposed SAP solution at OPGC, at a time and place of the Owner's choosing, which would inter‐alia include the following:  

1. Understanding of scope & requirements 2 Solution approach 3. Project management approach, implementation methodology 4. Resource loading  5. Differentiators and use of knowledge base, SAP CoE 

 The  time, place and duration of  this presentation  shall be  communicated at a  later date. The presentation should include the following from the bidders end ‐ proposed project manager, account manager. 

     Note:  

Please note that the bidder should prepare a summary table  (as per Evaluation Criteria worksheet of “Technical Evaluation  criteria”  excels  that  can  be  downloaded  as  part  of  the  RFP.  Please  note  that  the  bidder would  be responsible for completing the necessary information sought, and providing the same in excel format as part of the submitted bid. The bid would be deemed incomplete without this information. 

 

With  regards  to  the bidder’s  international  customers only,  if  the bidder  is under obligation not  to disclose  the required supporting documents, the bidder shall submit an undertaking stating the details of their experience for their international customers on Company Letterhead with Company Seal duly signed by the authorized signatory of the bidder. 

 Also note, "SAP users" means transactional licensed users. Any licenses for Payroll or Web based Services (e.g. ESS) to Employee will not be accounted for above. 

 Stage‐3: Price Evaluation:     OPGC will  examine  the  Price  Proposals  to  determine whether  any  arithmetical  errors  have  been made, 

whether the documents have been signed, and whether the Proposals are generally  in order.  Arithmetical errors will be rectified on the following basis.   

• If there is a discrepancy between the unit price and the total price, which is obtained by multiplying the unit price and quantity, or between subtotals and the total price, the unit or subtotal price shall prevail, and the total price shall be corrected.   

• If there  is a discrepancy between words and figures, the amount  in words will prevail.   If a Bidder does not accept  the correction of errors,  its Proposal will be rejected and  its bid security may be forfeited.   

 E‐Reverse Auction will be conducted for the aforementioned works. Bidders are requested to go through the E‐Reverse Auction & its Rules & Regulations stipulated in section 7.0 After completion of e‐Reverse Auction, OPGC shall open the manual price bids submitted during tendering. The lowest evaluated bid of all the bids submitted  in  manual  and  e‐Reverse  Auction  process  shall  be  considered  for  further  evaluation.  The evaluation shall be based on the evaluated cost obtained through price comparison, discovered through E‐

Page 24: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 24 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

RA  and manual  price  bid  of  completing  the  contract  in  compliance with  all  commercial,  contractual  and technical obligations under this Bid including taxes, duties & levies etc.   The commercial scores will be calculated as Fn = Fmin / Fb * 100 Where Fn = Normalizd financial score of the Bidder under consideration, Fb = Evaluated cost for the Bidder under consideration, Fmin = Minimum evaluated cost amongst the techno‐commercially successful bidders 

     Note: ‐ The Minimum evaluated cost will receive maximum mark of 100. 

 Stage – 4: Final Evaluation:  

The overall score will be calculated as follows:‐ Bn = 0.7 * Ts + 0.3 * Fn Where Bn = overall score of Bidder under consideration Ts = Normalized technical score for the Bidder under consideration Fn = Normalized financial score of the Bidder under consideration  

3.4. Award Criteria 

OPGC will award the contract to the successful bidder whose bid has been determined to be substantially responsive and to be economically advantageous, which will be established by weighing Techno‐Commercial quality against price on a 70:30 basis. 

The selected Bidder for OPGC shall be the bidder with the highest score as per final evaluation. 

3.5. Negotiation The selected bidder will be notified in writing by OPGC inviting him for further Negotiations.   3.6. Signing Of Agreement 

On  finalization of negotiation,  to  the mutual  satisfaction of both  the parties, OPGC  shall  invite  the  selected bidder through  Letter of Award  (LOA)  for  the  signing of  the Agreement. The  selected bidder  shall execute  the Agreement within a period specified in the LOA from OPGC. The Agreement is to be signed in English language in two originals, one each for OPGC and the Bidder. 

Within 14 days of signing of the Agreement, the Bidder shall submit One Original and Two Photo Copies of the entire contract document duly bound to OPGC. 

The Bidder shall submit the following documents for signing of the formal Agreement: a) Copy of detailed LOA duly signed on all pages as a token of acknowledgement of receipt. b) Security Deposit as in the form of Bank Guarantee as per proforma Bank Guarantee for security deposit in 

the contract document. c) Non‐Judicial Stamp Paper of value Rs.100/‐ purchased in Odisha, India for the signing of Agreement. d) Permanent Account Number of all consortium partners allotted by Income Tax Department. e) Self‐attested  Photostat  copy  of Notarized  Power  of  Attorney  by  the  Competent  Authority  or  Board  of 

Director’s resolution authorizing the individual(s), to sign the Agreement. f) Self‐attested Photostat copy of the Registration under Odisha State VAT, Service Tax, as applicable. 

Page 25: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 25 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

 3.7. Failure to Commence the Work 

In case of  failure  to commence  the Work within  the 15days after  issue of LOA,  the LOA will be  terminated and  the Bidder will be  liable to be debarred  from participation  in the Owner’s Tenders for a period of two  (2) years, besides forfeiture of EMD. 

Page 26: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 26 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

 

4. Deliverables & Timeline 

4.1. Timelines  The proposed SAP implementation timeline is as follows.   Roll Out of existing SAP Modules & Implementation of Additional Modules: 

 Sl. No.  Project Activity  Duration (in Months)

1. Implementation Go‐Live  4 months from Kick‐Off2. Post Go‐Live Support  2 Months from end of Go‐Live 3. Performance Guarantee  (PG)  6 Months from end of Post Go Live Support4. Final Acceptance (FAC)  End of PG5. Post Implementation Support Service  12months from FAC

 The  Bidder  should  propose  timelines  for  the  various  phases/  activities  in  such  a  manner  that  overall  timelines mentioned above are maintained. The tasks that are provided in the deliverables but not listed in the delivery schedule are to be performed by the bidder in such a manner that it will not affect the project schedule.  4.2. Deliverables  The  following  table  lists out  the “salient”  indicative deliverables  in pertaining  to  individual phases of  the project  (in addition to the following, the bidders would also be responsible for creating deliverables based on the scope of work. 

 Sl No 

Brief Scope Description  Deliverables 

Study the Scope of the work with respect to existing processes, requirements, data availability, integration, customization etc., in particular the Functionality Requirements,  System  Requirements,  and  provide observations/understanding of the total work, resource commitment.   Bidder will Study the broad project schedule and preparation of detailed project plan highlighting critical path present his conclusions in the form of a Report and a presentation to the  Project management team 

Detailed  project  planInitial/ Kickoff presentation 

2 Training/Workshop  to  all  core  team  members  for  ERP  awareness    and workshop with senior management 

Initial Workshop (s) 

Study  of  the  current  business  blueprint  documents  for  the  modules implemented  in  OPGC‐I,  requirement  study  for  OPGC‐II,  suggest  suitable changes  as may  be  necessary  and  prepare  a  new  set  of  Business  Blueprint Documents.    For  additional  modules,  study  the  business  processes,  which would be covered in the implementation, validate this list and suggest suitable changes as may be necessary and prepare the Business Blueprint document. 

Business Blueprint Document and final RICEFW List 

4 Identify  the  customization  requirement  after  OPGC  finalizes  its  decision  to adopt some or all of the best practices of the ERP. The business blueprinting is done in this design phase 

Customization  Requirement  report  and Business Blueprint document 

5 Submit  the  Access  control matrix  template  to Owner,  after  the  template  is filled up, Configure the access control matrix in the application 

Access  control matrix  Template  and  the configured  application  print  of  the  user access. 

Page 27: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 27 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

 4.3. Performance Parameters 

Response Time for Tests: 

 User Activity to be guaranteed by the vendor Time Menu Navigation – Displaying the appropriate menu as per defined user role and profile 

< 1 sec  

Screen Opening – Display of the selected data entry screen from the menu < 2 sec Field Navigation – Navigation between different data entry fields in the Screen < 1 sec 

6  Finalization and configuration of user Role Authorization  User Role Authorization document 

7 The  Vendor  will  provide  the  template  in  which  each  data  element  to  be converted must be provided by Owner and must assist  in data collection  for feeding to ERP system 

Data conversion template 

8 Process and methodology adopted for Quality Assurance must be documented and periodic reports submitted to the project management team. 

Quality assurance  process document 

9 Provide a comprehensive cutover Strategy for going live with SAP considering all necessary business, data, personnel, process transitions 

Cutover Strategy document 

10  Provide testing strategy  Testing Strategy document 

11  UAT  User Acceptance Testing document 

12 Delivery of  the configured and customized ERP  solution  to  cater  to business requirements as envisaged in BBP / any mutually agreed subsequent changes 

Configured and customized  ERP solution (ready  for  deployment  in  production environment) 

13  Training to Core, Business and End Users Training  requirement  report,  Training Curriculum and Training materials 

14  Train the Trainer and Change Management workshop  Change management approach report 

15 

The  Vendor  will  conduct  change  management  programs  on  one‐on‐one individual  basis  or  in  groups  and  at  different  locations,  will  propose effectiveness  measurement  criteria  on  change  management  and  its monitoring and give a report /presentation to the Project management team on anticipated  change management  related  issues and proposed  solution  to overcome them. 

Change management Workshops 

16 

The supplier shall prepare System Manual / User Manual in adequate detail for use by appropriate  level of user to use system effectively. The Manuals must be exhaustive and shall contain detailed, step by step  instruction  for smooth access to, operations in and exit from the system 

System and User manuals 

17  Post Go Live Support  Intensive Post Go Live Support 

18  Warranty support services for ERP System  Support  with  bug  fixes,  configuration, new  releases,  etc.Documentation update 

19 

The  Vendor  is  expected  to  transfer  knowledge  to  Owner  and  provide guidelines  in  setting up and managing an SAP Helpdesk. The knowledge and guidelines will encompass all aspects of  the help desk such as configuration, report writing, database administration, system administration etc. 

Knowledge transfer 

20 The Vendor will be responsible for providing a detailed upgrade policy for the upgrade  (minor as well as major) of all applications being  implemented as a part of this Project implementation.  

Application upgrade policy 

21 The Vendor will also provide a patch application guideline based on the best practices in this regard 

Patch application guidelines 

Page 28: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 28 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

Look up response – Display of items from a List of Values < 1 sec Look up response – To display items from table <5 sec Screen Navigation – Navigation between different data entry screens  (from one to another) 

< 1 sec 

Transaction Commit – Transaction saving after completing the data entry < 2 sec Query retrieval – Online query entered by the userSimple query Medium Complexity query High Complexity query 

< 5 sec < 8 sec < 15 sec 

Reports response – Report fired by the user from the Report GeneratorSimple Report Medium Complexity report High Complexity report 

< 10 sec < 30 sec < 1 min 

 The Response time mentioned above should be measured by using standard testing tools. The response time will be tested at 65% concurrent users. 

Page 29: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 29 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

 

5. Price Schedule and Payment terms 

5.1. Price Schedule for Project 5.1.1. Implementation of Roll‐Out in OPGC‐II & Additional Modules 

SN  Description  UOM  Qty FOR Unit Rate in INR inclusive of all taxes & Duties except GST 

Amount in INR 

GST in INR 

Total Amount in INR 

P1  P1.1:  

SAP Roll Out in OPGC II and DMS Implementation 

LS  1        

P2  Warranty support for Yr 1  LS  1        

Total Amount (A)   

 Total Amount (A) in words:______________________________________________________________________ only  

5.1.2. Change Request & Scope change 

SN  Description MandaysRate in INR 

Taxes & Duties in INR 

1  RICEFW     

Total Amount (B)   

 Total Amount (B) in words:______________________________________________________________________ only

 

Net Total Amount (A + B) in figures: ________________________________________  

Net Total Amount (A + B) in words: __________________________________________________ only  

Note: Bidder has to use the above Price Bid/schedule Format failing which Bid will be rejected.

Page 30: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 30 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

5.2. Payment terms 

  Milestone  Vendor Deliverable Percentage Payment 

 

Payment component 

 

Duration in Months 

1  Project Start  Project Preparation (Resource mobilization, Project Kick‐off, core team finalization, and detailed Project Plan) 

10%  P1  4 

2  End of Core Team Training 

Completion of Core Team Training  5%  P1 

3  End of Business Blueprint 

Completion of business process study & business blueprinting and respective sign‐offs 

15%  P1 

4  End of Final Realization  

Completion of business process Configuration, Master data configuration and Integration Test Report 

15%  P1 

5  End of Final Preparation  

System ready for Live Transactions, Completion of UAT 

15%  P1 

6  Go Live   After issue of Go‐live acceptance certificate 

15%  P1 

7  Post go‐live support 

Successful completion of Post‐go live support 

10%  P1  2 

9  End of performance guarantee period  

End of performance guarantee period successful signoff ( end of 6th month) 

15%  P1  6 

10  Warranty support services for ERP System  for one Year 

Support with bug fixes, configuration, new releases, etc. (at end of each quarter) 

25% payable quarterly  

P2  12 

 NB: The payment shall be made based on  the achievement of  the above milestones. The expected  timeline  is  for explanation purpose.                 

Page 31: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 31 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

6. CONDITIONS OF CONTRACT  a. Agreement: The vendor selected for award of contract shall be entitled to enter into an agreement with 

OPGC.  b. Scope of Agreement: 

The Scope of Agreement covers work to be executed as indicated in the scope of work at Section 2 along with the supporting information provided. Unless otherwise expressly limited, the Vendor’s obligations involve  implementation,  integration,  testing,  acceptance,  achieving  go‐live,  training,  change management  (if  required),  stabilization  of  the  Project,  provision  of  all  the  Project  components  and materials as well as performance of all Services, as tendered in this document & in accordance with the plans, procedures, specifications, and any other documents specified in the Agreement and the Project Plan, at no additional cost. 

c. Term of Agreement • The Effective Date of the Agreement shall commence from the signing of Agreement. Time period 

for implementing the Project is 6 months (4 Months till Go‐live and 2 months for Post Go‐Live) from Kick Off date of the Project. 

• The Time period for the Performance Guarantee is 6 months from end of Post Go Live Support. The Warranty Support is for 12 Months from the end of Performance Guarantee .  

• The Owner has the right to extend the service term by additional periods, on at least 30 days’ notice before the expiry of the current service term. 

• The  Vendor  should  bear  in mind  that  the  stipulated  time  for  completing  the  scope  as  per  the Agreement  is  the  essence  of  the  Agreement,  unless  such  time  is  extended  pursuant  to  the provisions of this Agreement.  

d.  Termination of the Agreement I. Termination of Agreement on Vendor's Default   The Owner, without prejudice to any other remedy for material breach of Agreement, by written notice of default sent to the Vendor, may terminate this Agreement in whole or in part:  • If the Vendor materially fails or delays to complete any part of the work or all of the goods within 

the period(s) specified in the Agreement, or within any extension thereof granted by the Owner.  • If the Vendor fails to perform any other obligation(s) under the Agreement.  • If  the  Vendor,  in  the  judgment  of  the  Owner  has  engaged  in  Corrupt  Practices  or  Fraudulent 

Practices in competing for or in executing the Agreement.   For the purpose of this clause:  "Corrupt Practices" means  the offering, giving,  receiving or soliciting of anything of value  to  influence the action of any official, be  it from the Owner’s organisation or any other Govt. or non‐govt. body,  in the procurement process or in Agreement execution. "Fraudulent Practices" means a misrepresentation of facts in order to influence a procurement process or the execution of an Agreement to the detriment of the Owner and includes collusive practice among bidders (prior to or after bid submission) designed to establish bid prices at artificial non‐competitive  levels and  to deprive  the Owner of  the benefits of free and open competition".   In  the event  the Owner  terminates  the Agreement  in whole or  in part,  the Owner may procure / get repaired, upon  such  terms and  in  such manner as  it deems appropriate, Goods or Services  similar  to 

Page 32: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 32 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

those undelivered / un‐repaired, and the Vendor shall reimburse the Owner any excess costs for such similar Goods or Services. However,  the Vendor  shall continue performance of  the Agreement  to  the extent not terminated.   II. Termination for Insolvency of the Vendor  The Owner may  at  any  time  terminate  the Agreement by  giving written notice  to  the Vendor  if  the Vendor  becomes  bankrupt  or  otherwise  insolvent.  In  this  event,  termination  will  be  without compensation  to  the Vendor, provided  that  such  termination will not prejudice or affect any  right of action or remedy which has accrued or will accrue thereafter to the Owner.   III. Termination of Agreement on Owner's Initiative   • The Owner  reserves  the  right  to  terminate  the Agreement either  in part or  in  full due  to  reasons 

other than  those mentioned under clause entitled "Vendor's Default". The Owner shall  in such an event give thirty (30) days’ notice in writing to the Vendor of his decision to do so.  

• The Vendor upon receipt of such notice shall discontinue  the work on  the date and  to  the extent specified  in  the  notice,  make  all  reasonable  efforts  to  obtain  cancellation  of  all  orders  and Agreement to the Owner, stop all further sub‐contracting or purchasing activity related to the work terminated, and assist the Owner in storage, maintenance, protection, and disposition of the works acquired under the Agreement by the Owner.  

• In  the  event  of  termination  for  whatsoever  reason,  the  Vendor  shall  be  paid  equitable  and reasonable compensation, as deemed appropriate under the circumstances prevalent at the time of termination.  

• In the event of support service, if the Owner is not satisfied with the support & service of the vendor, Owner may  terminate  the Contract by  giving 30  (thirty) days notice. The  vendor  shall hand‐over proper documentation, configuration document, database and providing training to new consultant appointed by Owner. 

 e. Price:   The rates shall be quoted as per the prescribed price schedule of project stipulated in 5.1. f. Taxes, Duties & Statutory deductions:  

Taxes & Duties • The  price  shall  be  inclusive  of  all  taxes,  duties  cess  and  any  other  taxes  imposed  by  

State/Central/Local authorities etc but excluding applicable GST.  • New taxes & levies, if any, as may be applicable, shall be reimbursable against documentary proof to 

be submitted by the Vendor. Any omission, or non‐inclusion, either declared or not declared, of any taxes and duties that are applicable at the time of submission of price bid/revised price bid /revision in prices shall not be considered as a reason for reimbursement of such taxes and duties at a  later date. 

• If  the  work  is  delayed  for  the  reasons  attributable  to  Owner  and  extension  of  the  time  for completion  is  granted,  variation  in  taxes  and  duties  enacted  during  Contractual completion/execution period, the adjustment in contract price shall be allowed within the extended period of the Agreement. Similarly, if the work is delayed for the reasons attributable to the Vendor, variations in taxes and duties will not be paid. 

• The  Vendor  shall  bear  and  pay  all  the  liabilities  in  respect  of  non‐observance  of  all  legal requirements as per various statutory provisions. 

Page 33: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 33 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

• Invoice  shall be  submitted by  the Vendor members  as per  the GST  Law duly  complying with  the procedure and conditions stipulated by tax authorities to facilitate Owner to claim ITC if any.  

• The  adjustment  in  the  Contract  Price  towards  imposition  of  new  taxes  or  abrogation  of  existing taxes shall be applicable only  if  the new  tax  is enacted or existing  tax  is abrogated within original Contractual delivery/execution period. For any variation due to enactment of new tax or abrogation of  existing  tax  after  original  Contractual  delivery  /  execution  period,  adjustment  in  the  Contract Price shall not apply.  

• All formalities required under statutes, for availing any concessions under relevant tax laws shall be adhered to by the Vendor. 

 Deduction of Taxes At Source • Deduction of income tax at source shall be calculated at the rate prescribed from time to time under 

the Income Tax Act 1961 and other relevant sections of Income Tax Act shall be made from the bills of the Vendor and  the amount so recovered shall be deposited with  the  Income Tax Department. Necessary TDS  certificate  to  this effect will be  issued  to  the Vendor  in  the prescribed pro‐forma within statutory dates. 

• If any other taxes / duties / cess etc are to be recovered at source as per government regulations / Legislation  from  time  to  time,  the  same  shall be  recovered  from  the bills payable  to  the Vendor. Necessary  receipt  to  this  effect will be  issued  to  the Vendor  in  this  regard  as per  the  applicable legislation. 

g. Offloading of job:   In case it is observed during the tenure of the contract that you are not capable or in a position to 

complete  the  job,  OPGC  reserves  the  right  to  offload  the  same  and  get  it  done  through  other agencies at your cost and risk. 

h. Employees Provident Funds and Miscellaneous Provisions Act 1952 & Employees State Insurance Act 1948  • The  Vendor  shall  ensure  strict  compliance  of  provisions  of  the  Employees’  Provident  Funds  and 

Miscellaneous Provisions Act 1952 and the schemes framed there under so far as they are applicable to their establishments and agencies engaged by them. The Vendor is also required to indemnify the Owner against any loss or claims or penal damages whatsoever resulting out of non‐compliance on the part of the Vendor with the provisions of the aforesaid Act and the schemes framed there under. 

• The Vendor agrees to maintain all statutory records as required under various labour laws in respect of employees and payments. Any expenses  incurred  for  the contributions, making contribution or maintaining records shall be to the Vendor’s account. 

i. Security, Statutory and Safety Regulations • The Vendor shall abide by all the safety and security regulations of Owner in force and promulgated 

from time to time and other statutory requirements. The Vendor shall be responsible for the safety of all employees and/or workmen employed or engaged by  them on and  in  connection with  the work  and  shall  report  to  Owner  and  other  local  authorities  concerned  all  cases  of  accidents howsoever caused and wherever occurring on the works and shall make adequate arrangements for rendering  immediately  all  possible  aid  to  the  victims  of  the  accidents.  Owner’s  safety  rules &regulations are detailed in Annexure. 

• Owner shall not be  in any way held  responsible  for any accident or damages  incurred and claims arising there from during the period of installation, testing, commissioning and stabilizing IT solution. 

Page 34: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 34 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

The Vendor shall be responsible for following the provisions of all safety laws and rules made there‐under and other statutory requirements at his own cost. 

• The Vendor shall arrange to obtain from Owner the required gate pass for entry and exit to Owner’s plant  site  and  other  protected  areas  for  each  one  of  its  engineers/specialists,  representatives/ agents, supervisors, workmen and staff as per Owner’s prescribed procedure and format. Each entry and exit gate pass shall contain the photograph of the person concerned. In the event of loss and/or damage  to  the gate passes,  the Vendor  shall pay  to Owner  the prescribed penalty before a new entry  and exit  gate pass  can be  issued. Owner’s  security department  and  the  concerned officer/ engineer  shall  have  the  right  to  refuse  the  entry  and  exit  gate  passes  to  any  worker  or representatives of the Vendor without assigning any reason. 

• The Vendor shall register all equipment that may be taken inside the plant area in order to facilitate the issue of exit gate permits for such items to be taken out after the completion of work. 

• The Vendor shall not employ for the purpose of the Work, any person below the age of 18 years. Owner shall have the right to decide whether any person employed by the Vendor is below the age limit, and to refuse to allow any person, whom he considers to be under‐aged to be employed by the Vendor. 

• Factories Act, 1948: The Vendor shall follow the provisions of Indian Factories Act, Contract Labour (R&A) act 1970, Employees Compensation Act 1923 and other applicable Acts and  rules made there under  from  time  to  time  as  applicable,  and  shall  indemnify  Owner  against  all  claims  of compensations under the provisions of the Act  in respect of workmen employed by the Vendor  in carrying  out  the works  and  against  all  costs  and  expenses  or  penalties  that may  be  incurred  by Owner in connection therewith. 

• The Vendor shall submit labour license (if required). • The Vendor shall ensure that no explosive or inflammable material are used or stored at the Project 

Site.  In  the  event  such material  are  essential  as  part  of  execution  of  the  Project work, written permission shall be sought  from the Project Manager / Owner’s representative and  it shall be the sole responsibility of the vendor to ensure acquisition of necessary statutory permits and clearances and proper storage and handling of such material. 

j. Obligation of Vendor: • The Vendor has the overall responsibility of implementing, conducting Tests, successful running and 

stabilization of the Project.  • The  Vendor  shall  be  responsible  for  timely  provision  of  all  resources,  information,  and  decision 

making under its control that are necessary to reach a mutually accepted Project Plan and the Scope of work at Section 2.  

• The Vendor shall appoint its representative within seven (07) days of signing of the Agreement after mutual  discussions  and written  approval  of  Owner.  The  Vendor’s  representative  shall  have  the authority to represent the Vendor on all day‐to‐day matters relating to the Project. 

• The  Vendor  shall  provide  the  key  personnel  namely  the  project  leader, module  leaders,  quality assurance  personnel  any  specialist  /  analysts  required  as  appropriate,  and  having  sufficient experience  in  terms of  relevance and number of years  required  to  implement  the Project. Should the profile of any personnel not be acceptable to Owner, Owner will require the Vendor to suitably replace such personnel. The key personnel are to be assigned to the project on full time basis and to the satisfaction of Owner. If for any reason beyond the control of the Vendor, there arises a need to replace  any  personnel,  the  Vendor  shall  provide  a  replacement  person  of  equivalent  or  better qualification and experience, subject to the written approval of Owner. Further, at any time  in the opinion  of  the  Project  Manager,  any  additional,  qualified,  experienced  engineer  is  considered 

Page 35: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 35 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

necessary;  they shall be deployed by  the Vendor without any additional charge. The Vendor shall ensure  to  the  satisfaction  of  the  Project  Manager  competent  and  efficient  supervision  in  the Implementation of the Project. 

• In case project gets delayed due to any reason attributed to Vendor, the annual technical support / maintenance  up  to  the  stabilization  acceptance  of  the  project  shall  remain  in  the  scope  of  the Vendor with no financial implication on Owner. 

• The  vendor  has  overall  responsibility  of  providing  post  implementation  support  services  for  the successful  running of  the  System(s) as per  the  scope outlined  in  this Agreement and any  further terms and conditions as may be stipulated at the time of execution of the contract for post go‐live support and warranty support. 

• The Vendor shall ensure that all technology and equipment used to perform and deliver the Services is not obsolete and is kept in good working order at all times. 

• The Vendor’s representative and staff are obliged to work closely with Project Manager / Owner’s representative and act within their own authority, and abide by directives issued by Owner that are consistent  with  the  terms  of  the  Agreement.  The  Vendor’s  representative  is  responsible  for managing the activities of its personnel. 

• In the event if any discrepancy with respect to the qualifications of the employees of the Vendor is detected by Owner then the Vendor shall appoint a replacement to such objection  immediately  in accordance with this clause. 

• The Vendor’s  representative may,  subject  to  the written  approval  of Owner  (which  shall  not  be unreasonably withheld),  at  any  time  delegate  to  any  person  any  of  the  powers,  functions,  and authorities vested in him. Any such delegation may be revoked at any time with prior notice signed by  the  Vendor’s  representative  and  shall  specify  the  powers,  functions,  and  authorities  thereby delegated or revoked. No such delegation or revocation shall take effect unless and until a copy of such  a  notice  has  been  delivered  to  the  Project Manager  /  Owner’s  representative.  Any  act  or exercise by  any person of powers,  functions  and  authorities  so delegated  to him or her  shall be deemed to be an act or exercise by the Vendor’s representative. 

• The Vendor shall acquire  in  its name all permits, approvals, and/or  licenses from all  local, state, or national  government  and  other  statutory  authorities  and/or  public  service  undertakings  that  are necessary for the performance of the Agreement. 

• Neither  the  Vendor  nor  its  personnel  shall  during  the  term  of  the  Agreement,  engage  in  any business or professional activities  in  India/abroad which would conflict with the activities assigned to them under this Agreement 

• The Vendor  is responsible for performing and safely storing, timely and regular backups of  its data and  Software  in  accordance  with  accepted  data  management  principles,  except  where  such responsibility is clearly assigned to Owner elsewhere in the Agreement. 

 k. Vendor’s Staff and their Conduct 

• If any of  the Vendor’s employee,  in  the opinion of Project Manager  / Owner’s  representative, be found  guilty  of  any misconduct  or  be  incompetent  or  insufficiently  qualified  or  negligent  in  the performance of their duties or that in the opinion of the Project Manager / Owner’s representative, undesirable for administrative or any other reasons, for such person(s) to be employed for providing desired services, then at the directions of the Project Manager / Owner’s representative, the Vendor shall at once remove such person (s). Vacancy so created shall be immediately filled at the expense of  the  Vendor  by  a  qualified  and  competent  substitute.  Should  the  Vendor  be  requested  to 

Page 36: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 36 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

repatriate any person or  removed  from  this Agreement, he  shall do  so and  shall bear all costs  in connection therewith.  

• The  Vendor  shall  be  solely  responsible  for  the  proper  behaviour  of  his  employees  and  staff employed by him/deputed by him to provide IT Solution. The Vendor shall exercise proper degree of control over  them  and  in particular without prejudice  to  the  said  generality  the Vendor  shall be bound to prohibit/prevent any of his employees (as stipulated above) from trespassing or acting  in anyway detrimental or prejudicial to the interest of the community or the properties or occupiers of land  or  properties  in  the  neighbourhood.  In  the  event  of  such  trespassing,  the  Vendor  shall  be responsible  for  all  consequent  claims  or  actions  for  damages  or  injury  or  any  other  grounds whatsoever. The decision of the Project Manager / Owner’s representative upon any matter arising under this clause shall be final. 

• If  the Vendor or  their employees damage, break, deface  the property belonging  to  the Owner or others during the execution of the Agreement, the same shall be made good by the Vendor at his own  costs  and  expense,  the  Project Manager may  cause  the  same  to  be made  good  by  other agencies and  recover expenses  from  the Vendor  for which  the certificate of  the Project Manager shall be final. 

• All Vendors’ personnel entering Owner’s premises shall be properly  identified by badges of a type issued by Owner as per prevailing rules and must be worn at all times on Owner’s premises. 

• It  is made  clear  that no  relationship of Owner and employee  is  created between Owner and  the Vendor’s resident engineers, employees and no claim for employment of any such personnel shall be tenable or entertained. 

l. Vendor Responsibility with Other Agencies • Without repugnance to any other condition, it shall be the responsibility of the Vendor not to divert 

or withdraw the people working for IT solution for any other service contract with Owner. No claim shall be entertained on account of above. 

• The Vendor shall conform in all respects with the provisions of any statutory regulations, ordinances or byelaws of any  local or duly  constituted authorities or public bodies which may be applicable from time to time to the consulting services work. 

• All  notices,  instructions,  information,  and  other  communications  given  by  the  Vendor  to Owner under the Agreement shall be given to the Project Manager / Owner’s representative. 

• The Vendor  shall make  its own arrangements  for movement of personnel and equipment, within and outside the sites / units / offices at the various locations covered. 

m. Obligation of Owner • Owner  shall appoint a Project Manager and notify  the Vendor  in writing  the name of  the Project 

Manager within  seven  (07) days of  signing of  the Agreement. Owner may also  from  time  to  time appoint some other person as the Project Manager  in place of the person previously so appointed and shall give a notice of the name of such other person to the Vendor without delay. The Project Manager  shall  have  the  authority  to  represent Owner  on  all  day‐to‐day matters  relating  to  the Project or arising from the Agreement. All notices,  instructions, orders, certificates, approvals, and all other communications under  the Agreement  shall be given by  the Project Manager, except as otherwise provided for in the Agreement.  

• Owner  shall  be  responsible  for  timely  constitution  of  core  team  and  provision  of  resources, necessary access, and  information for the  installation, commissioning and Go‐live of the Project as identified  in  the  Project  Plan,  except where  provision of  such  items  is  explicitly  identified  in  the Agreement as being the responsibility of the Vendor. 

Page 37: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 37 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

• Unless otherwise  specified  in  the Agreement or agreed upon by  the Parties, Owner  shall provide personnel,  to  properly  carry  out  commissioning,  Go‐live  (including  successful  running  and stabilization of the system), at or before the time specified in the Project Plan.   

• Owner will designate  its appropriate  staff  for  the  training courses  to be given by  the Vendor and shall endeavour to make all appropriate logistical arrangements for such training as specified in the Project Plan. 

• Owner shall ensure  the availability of all  information and/or data  to be supplied by Owner  to  the Vendor. 

• The Project Manager / Owner’s representative may at any time delegate/revoke to any person any of the powers, functions, and authorities vested in him or her of which due notice in writing will be given. Failure of  the Project Manager  to  reject any part of  the  IT Solution viz., software modules, equipment,  Materials,  workmanship  etc.,  or  to  disapprove  any  service  or  materials  shall  not prejudice the Owner to reject such software module, equipment, Materials, workmanship etc., or to disapprove such work or materials and  to order re‐supply of such software module, equipment & Materials or to pull down, remove or break up such disapproved service at the cost of the Vendor, provided the Vendor fails to comply with the direction and requirement of the Owner there off. The decision, opinion, certificates or valuation of the Owner  in respect of any matter under this clause shall be final, binding and conclusive. If the Vendor is dissatisfied by reason of any decision, opinion, direction,  certificate or  valuation of  the Project Manager  / Owner’s  representative,  they  shall be entitled  to  refer  the matters  to  the  Owner who  shall  thereupon  confirm,  reverse  or  vary  such matters. 

• Owner by notice to the Vendor may object to any representative or person employed by the Vendor in  the execution of  the Agreement who,  in  the  reasonable opinion of Owner, may have behaved inappropriately, be incompetent, or be negligent. Where upon the Vendor shall remove such person from work on the Project. If any representative or person employed by the Vendor is removed, the Vendor shall, where required, promptly appoint a replacement. 

 n. Workplace/Facilities for Vendor’s Site Office 

• Owner shall provide the office space and other essential work  facilities within  its premises for the Vendor’s team. 

• Suitable workspace  in  the  respective  sites/offices may be provided  to  the Vendor  subject  to  the availability, free of charge. However, providing such space and store is for the smooth execution of Agreement and non‐provision of  such  space does not bind Owner and make Owner  liable  to  the Vendor  in any manner except as specifically provided  in the Agreement terms. Owner  is not  liable for any  loss or damage  to  the Vendor’s equipment/material as a  result of variation  in voltage or frequency or interruption in power supply or other loss to the Vendor arising there from. 

• Owner  will  supply  electric  power  220/440V,  single  phase/3  phase,  50  cycles  from  the  nearest established substation free of cost, for the site works and approved site offices. Only one outlet will be provided from the point of supply. 

• Though  efforts  will  be made  by  Owner  to maintain  regular  power  supply,  Owner  shall  not  be responsible  for any  failure  in power supply and any consequences arising  there  from. The Vendor shall  obtain  the  approval  of  the  Project  Manager  /  Owner’s  representative  for  installation  of machinery and electric power supply connection to them. The Vendor shall be responsible for any defect  therein. Any defects pointed out by  the Owner  in  the distribution system shall be rectified forthwith  to  the  satisfaction of  Project Manager  / Owner’s  representative by  the Vendor,  failing which the power supply may be cut off by the Owner. 

Page 38: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 38 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

o. Accommodation and Transportation Residential accommodation and Transportation will be provided by Owner  to  the  staff of Vendor on chargeable basis subject to availability. 

p. Implementation Plan Project Plan • In close cooperation with Owner and based on the preliminary Project Plan included in the Vendor’s 

bid, the Vendor shall develop a project plan hereinafter referred to as “Project Plan” encompassing the activities specified in the Agreement. 

• The Vendor shall  formally present  to the Owner the Project Plan  in accordance with  the technical requirements. The Vendor has  to  specify  the  strategy and methodology with  time  frame and  the synchronization of various phases of  the Project  to ensure completion of  the Project  in  time. The Project Plan shall also include a PERT chart describing the activities, resources required on the time for completion. The Project Plan shall also bring out the critical areas needing continuous attention of Owner.  

Design and Development • Vendor shall execute the basic and detailed design and the implementation activities necessary for 

successful  implementation of  the Project  in  compliance with  the provisions of  the Agreement or where not so specified, in accordance with best industry practice.  

• The Vendor shall be responsible for any discrepancies, errors or omissions in the specifications, and other  technical documents  that  it has prepared, whether such specifications, drawings, and other documents have been approved by the Project Manager or not, provided that such discrepancies, errors, or omissions are not because of inaccurate information furnished in writing to the Vendor by or on behalf of Owner. 

Approval/review of technical documents by Project Manager • The Vendor  shall prepare  and  furnish  to  the Project Manager  the documents  as  specified  in  the 

technical requirements for the Project Manager’s approval or review. • Within  twenty  one  (21)  working  days  after  receipt  by  the  Project  Manager  of  any  document 

requiring the Project Manager’s approval, the Project Manager shall either return one copy of the document to the Vendor with its approval endorsed on the document or shall notify the Vendor in writing of  its disapproval of  the document and  the  reasons  for disapproval and  the modifications that the Project Manager proposes. 

• If  the  Project Manager  disapproves  the  document,  the  Vendor  shall modify  the  document  and resubmit  it  for  the  Project Manager’s  approval.  If  the  Project Manager  approves  the  document subject  to modification(s),  the Vendor shall make  the  required modification(s), and  the document shall  then be deemed  to have been approved. The procedure set out above shall be repeated, as appropriate, until the Project Manager approves such documents. 

• The Vendor shall not depart from any approved document unless the Vendor has first submitted to the Project Manager an amended document and obtained  the Project Manager’s approval of  the document. 

• The Project Manager’s  approval, with or without modification of  the document  furnished by  the Vendor,  shall  not  relieve  the  Vendor  of  any  responsibility  or  liability  imposed  upon  it  by  any provisions  of  the  Agreement  except  to  the  extent  that  any  subsequent  failure  results  from inaccurate information furnished in writing to the Vendor by or on behalf of Owner.  

• The Vendor shall maintain accurate records of works executed as per the scope of the Agreement in a format that will permit audit.  

Review of Progress 

Page 39: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 39 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

• The work  shall  be  executed  strictly  as  per  the  time  Schedule,  indicated  in  the  Bid  documents. Monthly / weekly work programme will be drawn up by the Vendor before commencement of work &  submitted  to  Project Manager  for  approval.  The programme& progress will be  reviewed  from time to time and if required, the programme may be re‐scheduled by Project Manager. The Vendor shall also be responsible to provide materials within his scope in time to achieve the programme. In all matters concerning  the extent of programme set out weekly and monthly,  the decision of  the Project Manager will  be  final  and  binding  on  the  Vendor.  Both  Parties  shall  agree  to  a  planned review  of  the  progress  of  the works  executed  under  the  scope  of  the Agreement,  in  a  periodic interval with a view to Review the progress, Resolve pending issues,  Plan  for  resources  required  for ongoing and future works, Evaluate all escalated issues and address mechanisms to remedy them. 

• During  the  term  of  this Agreement Owner  reserves  the  right  to  formally  audit  and  evaluate  the performance of the Vendor upon reasonable notice and at reasonable times. 

q. Scope Change If  the  need  for  any  change  of work  is  felt  during  the  Project  Execution,  the  same will  be mutually discussed and decided through a Change Request Process (if needed) that would be clearly defined by the bidder in their proposal 

r. Assignment The Vendor shall neither transfer nor assign the Agreement or any part thereof or any benefit or interest therein  or  there  under  without  the  written  consent  of  the  Owner.  In  the  event  of  the  Vendor contravening  this  condition,  the Owner  shall  be  entitled  to  place  the  Agreement  elsewhere  on  the Vendor's account and at his risk and cost, then the Vendor shall be liable for any loss or damage which the Owner may  sustain  in  consequence or arising out of  such  replacing of Agreement. This  shall not relieve the Vendor of any responsibility under this Agreement. 

s. Subcontracting The Vendor shall not sub‐contract the whole or any part of the Project to any person or firm or company hereinafter  referred  as  “Sub‐Contractor”, without  the prior written  approval of  the Owner  and  such approval  if given shall not establish any contractual  relationship between  the Sub‐Contractor and  the Owner and shall not relieve the Vendor of any responsibility, liability or obligation under the Agreement and  the Vendor shall be  responsible  for  the acts, defaults and neglects of any Sub‐Contractor or Sub‐Contractor’s agents, servants or workmen as  fully as  if  they were the acts, defaults or neglects of the Vendor or his agents, servants or workmen.  Notwithstanding any approval given by the Owner for sub‐contract, it shall continue to be obligatory on the part of  the Vendor  to provide  to  the Owner all  the details viz., drawings, specifications,  technical data, detailed design, performance characteristics etc. from his Sub‐ Contractors. 

t. Waiver: Failure of Owner  to  insist upon strict performance of any terms and conditions of the Agreement will not be deemed  a waiver of  any  rights or  remedies  that Owner may have  and will not be deemed  a waiver of any subsequent default under the terms and conditions of the Agreement. No right or remedy of Owner will be exclusive of any other right or remedy and Owner will have all the rights and remedies given under the Agreement and now or hereafter, existing in law or by statute. The shipping or delivery by the Vendor or receiving of payment by Vendor for the work under the Agreement will not be deemed a waiver of any rights  for any prior  failure by  the Vendor  to comply with any of  the provisions of  the Agreement. 

u. Price and Payment The Owner shall pay to the vendor the price as per the Payment Milestone given at section 5.2. Price 

Page 40: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 40 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

• The FOR unit rates accepted by the Vendor as per the price schedule under section 5.1 shall remain firm and binding during the Term of Agreement. The Vendor shall perform all his works as envisaged in the Agreement. 

• All  fees,  duties,  royalties,  rent  and  compensation  to  Owner  for  surface  damage  or  taxes  and impositions payable  to  local authorities  in  respect of all materials  supplied  for  the work or other duties or expenses for which the Vendor may become liable or may be put to under any provision of the  law  for  the purpose of or  in connection with  the execution of  the Agreement  including  levies payable on all transactions are all inclusive in the price. 

v. Billing and Payment Terms • Billing and Payments  shall be  carried out  from  IB Thermal Power Station, Banharpali,  Jharsuguda 

office of Owner. All  interactions regarding the execution of the Agreement, submission of bills and correspondence on any matter shall be done with the Project Manager / Owner’s representative. 

Billing  •  Vendor shall submit running account bills as per the payment milestone with supporting documents 

for having achieved the designated milestone activities.  •  All bills/invoices must be  raised  in  INR only  taking  into account  the prevailing  taxes & duties with 

reference to the Payment milestone. Payment •  Owner  shall  release  payments  based  on  the  Payment Milestones  as  indicated  in  the  Section  5.2. 

Payment shall be released within 30 working days on submission of the bill complete  in all respect with  supporting  documents  duly  certified  by  the  Project Manager  / Owner’s  representative  after deducting taxes at source as prescribed by the legislative authorities, penalty and other recoverable if any. If such payment release day falls on a holiday of Owner, payment will be released on the next working day. Against deduction of statutory taxes, tax deduction certificates where ever applicable shall be issued as per the applicable provisions of the statute. The Project Manager may recover any amount wrongly paid in excess in any previous bills certified by him. 

•  All payments shall be made direct to the Vendor in the shape of crossed A/c payee Cheque / Demand Draft/ RTGS  / e‐payments under  internet banking  system  less Bank Charges on certification of  the Project Manager/Owner’s representative and on compliance of contractual terms & conditions. 

•  In case of shortage/missing/damage/ failure of any services identified at any point of time within the period  specified  by  the  Agreement  including  guarantee  period,  the  agency  shall supply/replace/rectify/resolve the same without any financial implication to Owner. The taxes, duties, clearing & forwarding and other charges incurred by Owner in this regard shall be recovered from the Vendor’s pending bills and in case no bills are pending the same shall be made good by the Vendor. The Vendor shall accordingly submit the subsequent invoices. 

w. Security Deposit Security Deposit for Project •  The Vendor shall stand guarantee for the overall performance including the services made and work 

to be done by the Vendor. •  The Vendor shall furnish a Performance Bank Guarantee Bond from any scheduled bank (other than 

cooperative Bank) in India before the signing of the Agreement, for an amount equivalent to 10% of the  Contract  price(P1)  towards  Project which  shall  be  valid  for Ninety Days  beyond  the  expiry  of  Performance Guarantee Support. The issuing bank should be advised to send a direct confirmation of issue  of  bank  guarantee  to  Owner.  Performance  Bank  Guarantee  Bond  will  be  released  after satisfactory completion of Performance Guarantee support services. Owner shall not be liable to the Vendor  for  any  matter  or  thing  arising  out  of  or  in  connection  with  the  Agreement  or  the 

Page 41: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 41 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

implementation  of  the  Project  unless  the  Vendor  shall  have made  a  claim  in  writing  in  respect thereof.  

•  The  Bank  Guarantee  for  security  deposit  shall  be  for  the  due  and  faithful  performance  of  the Agreement  and  shall  remain binding notwithstanding  such  variations,  alterations or  extensions of time as may be made, given, conceded or agreed to between the Vendor and Owner.  

•  Should the extent or the object of the Agreement be altered during the execution of the Agreement in  such  a way  as  to  effect  an  increase or decrease on  the Contract Price by more  than  10%,  the amount in the Bank Guarantee shall be increased or decreased correspondingly. 

•  The bank guarantee and any amendment thereto shall be executed on a non‐judicial stamp paper of requisite money value as prescribed by the Statute. 

•  All Bank Guarantees for security deposit, interest free recoverable advance and other payments and extensions  of  Bank  Guarantees  shall  be  sent  in  a  sealed  envelope  directly  by  the  Bank  through Registered Post to AGM‐Supply Chain Management, IB Thermal PS, Banharpali, Jharsuguda. 

•  Bank  Guarantees  /  extensions  of  Bank  Guarantees  submitted  by  the  Vendor  directly will  not  be admitted. 

•  The Non‐judicial stamp paper for the Bank Guarantee should be purchased in the name of executing Bank only. 

Forfeiture of Security Deposit •  Whenever any claim against the Vendor for the payment of a sum of money arises out of or under 

the Agreement, Owner shall be entitled to recover such sum by  in part or whole from the security deposits. In the event of the security deposit being insufficient or if no other security has been taken from  the  Vendor,  then  the  balance  or  the  total  sum  recoverable  as  the  case may  be,  shall  be deducted from any sum then due or which at any time thereafter may become due to the Vendor. The Vendor shall pay to Owner on demand any balance remaining due. 

•  In the event of any material breach by the Vendor or any loss or damage suffered by Owner which in the opinion of Owner that the loss or damage has arisen due to reasons attributable to Vendor or in the event of the termination of the Agreement for any such breach, the security deposit  is  liable to be forfeited. The decision of forfeiture by Owner shall be final and binding on the Vendor. 

x. Liquidated Damages:  x.1  Liquidated Damages for Delay The following LD factors  are applicable  

No.   Particulars   LD Factor  Percentage of Contract Value (Rs.)  

1 For every additional week of  delay in achieving Go‐Live target as per Delivery Schedule 

LD Factor 0.5% of  contract price  for  Implementation  / week subject to maximum 7.5% 

 x.2  Liquidated Damages for Performance The following LD factors  are applicable  

No.   Particulars   LD Factor  Percentage of Contract Value (Rs.)  

1  Failure to meet  performance as per 4.3  LD Factor 0.5% of contract price for each failure of performance specification subject to maximum 7.5%.  

 Notwithstanding anything to the contrary herein, the overall cap on cumulative  liquidated damages shall not exceed 10% of the total Contract Price for Project Roll out and Implementation i.e. P1 part of section 5. 

 

Page 42: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 42 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

y. Insurance •  The  comprehensive  insurance  and  safety  of  all  men  and  material  of  the  Vendor  shall  be  the 

responsibility of  the Vendor. The comprehensive  insurance should cover  for  full value against  loss, damage  or  destruction  by  fire,  lightning,  earth  quake,  theft,  pilferage,  non‐delivery  of package/packages  and  all  other  risks  including  strikes,  riots  and  civil  commotions  during  transit, storage,  testing &  commissioning and guarantee  tests  to protect Owner and  the Vendor  from any loss arising out of such condition. 

•  The  insurance  policy  shall  be  tripartite,  Owner  being  the  beneficiary.  The  insurance  cover  shall remain in full force up to the time the Project is accepted and Stabilization Acceptance Certificate is issued by the Owner. The Vendor shall produce the insurance policy and receipts for the premium at the appropriate  time. All money  received under any such policy shall be applied  in or  towards  the cost incurred for the damage/deficiency but this provision shall not affect the Vendor liabilities under the Agreement. 

•  The Vendor shall maintain  in full force and affect all such  insurances as above and required by the law for the purpose of the Agreement at the cost of the Vendor. 

•  The  Vendor  shall  furnish  to  the  Project Manager/Owner’s  representative  with  evidence  of  such insurance a copy of the issued policy and any cancellation or termination thereof. Should the Vendor default  in paying any premium when due, Owner, without prejudice to other remedies set forth  in this Agreement shall be at liberty to pay such premium and recover the same from Vendor. 

•  The provisions contained within this clause are not intended to and do not impair or in any manner limit the liabilities or obligation assumed by Vendor as may be set forth more fully elsewhere in the Agreement. 

•  The  Vendor’s  services  shall  include  the  filing  and  pursuance  of  all  insurance  claims  on  behalf  of Owner and the entire Work incidental thereto till realization of Claim. 

•  Owner shall be the principal holder of the policy along with the Vendor. Owner reserves the exclusive right to assign the policy. 

•  The Vendor shall be responsible for effecting  insurance under the Indian Employee’s Compensation Act and any other insurance in accordance with the Indian laws and regulations at his own cost. 

•  If any Agreement Scope  including  supplies and  services perishes or becomes unserviceable due  to any cause whatsoever,  including missing, shortage,  loss or damage and/or various destructions and risks as mentioned above, the Vendor shall on demand by Owner make replacement at his own cost and  in  such a way as  to avoid disturbances  in  the general progress of  IT Solution. This  shall apply irrespective of the question whether or not the risk has passed to Owner or who shall be responsible for such unserviceable condition as aforesaid. 

•  Upon arrival at Project Site, all equipment, Materials, commissioning spares, special tools & tackles, all  consumables, etc.,  the Vendor  shall assume  custody  thereof and  remain  responsible  therefore, until the physical possession taken by the Owner. 

•  The Vendor shall, as custodian, be responsible for communicating to the project manager / Owner’s representative any shortages, missing, breakages, damages, etc. as soon as they come to his notice without prejudice to his obligation under Agreement. 

•  The insurance policy obtained by the Vendor shall also cover liability for accidents resulting in death, injury, damage to property of Owner or any third party including employees of third parties’ and / or Owner employees within the premises and precincts of Owner. 

z. Indemnity The  Vendor  assumes  responsibility  for  and  shall  indemnify  and  hold  the  Owner  harmless,  from  all liability, claims, costs, expenses, taxes and assessments including penalties, punitive damages, attorney's 

Page 43: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 43 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

fees and court cost which are, or may be required with respect to any breach of the Vendor’s obligations under the Agreement, or in respect of all salaries, wages or statutory dues or any other compensation or dues of whatsoever, nature of all persons employed by the Vendor  in connection with performance of the Scope of Agreement. Owner shall the vendor to take sole control of the defence of such claims. The vendor shall execute and deliver such other further instruments as may be necessary to comply with all the  requirements  of  such  laws  and  regulations  as  may  be  necessary  there  under  to  confirm  and effectuate the Agreement and to fully protect and indemnify the Owner. The Vendor shall not indemnify Owner to the extent that such  liability, damage, claims; fines, penalties, and expenses were caused or contributed to by the sole fault of the Owner. The Owner shall not be  in any way held responsible for any accident or damages incurred or claims arising there from during and in the course of discharge of the obligations by Vendor under the Agreement. 

aa. Patent Infringement The  Vendor  shall  protect,  indemnify  and  hold  the  Owner,  his  customers  and  users  of  his  products harmless, against all  liability,  including cost, expenses, claims, suits or proceedings at  law  in equity or otherwise, growing out of or  in  connection with any actual or alleged patent  infringement  (including process patents, if any) or violation of any license and will defend or settle at the Vendor’s own expense any such claims, suits or proceedings.  The Owner will notify the Vendor in writing of any such claim, suit, action or proceeding coming to his attention, giving authority and all available  information and assistance for the Vendor’s defence of the same.  The  Vendor  shall  appoint  a  counsel  at  his  own  expenses  in  consultation with  the  Owner  to collaborate in the defence of any such claim, suit, action or proceeding. 

bb. Settlement of Disputes The Agreement shall in all respects be construed and carried into effect and rights and liabilities of the Parties hereto shall be regulated according to the laws of India. Mutual Settlement of Disputes Except where otherwise provided for in the Agreement, other than excepted matters all questions and dispute relating to any matter directly or indirectly connected with this Agreement shall in the first place be resolved through mutual discussions, negotiations, deliberation and consultations between both the Parties. Conciliation If the effort to resolve all or any of the disputes other than excepted matters through mutual settlement fails, such disputes shall be referred to the conciliator to be appointed by the mutual agreement of both Owner and  the Vendor. The  conciliator  shall make  the  settlement agreement after  the Parties  reach agreement  and  shall  give  an  authenticated  copy  thereof  to  each  of  the  Parties.  The  settlement agreement  shall be  final  and binding on  the Parties.  The  settlement  agreement  shall have  the  same status and effect of an arbitration award. The venue of Conciliation shall be Owner’s Corporate Office, Bhubaneswar. Arbitration In  the  event,  the  dispute  cannot  be  settled  mutually    or  through  conciliation  or  in  the  event  of disagreement  on  appointment  of  the  Conciliator,  the  same  shall  be  resolved  through  the  provisions contained  in  the Arbitration and Conciliation Act 1996, or any statutory modification or re‐enactment thereof and the rules made there under for the time being in force. The number of arbitrators shall be three, with  either  party  to  the  dispute  being  entitled  to  appoint  one  arbitrator.  The  two  arbitrators appointed by the Parties shall appoint a third arbitrator who shall act as chairman of the proceeding. All proceedings shall be conducted,  including all documents presented  in such proceedings,  in the English 

Page 44: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 44 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

language. The venue of arbitration shall be at Bhubaneswar only and  jurisdiction  for any proceedings arising  out  of  or  concerning  or  connected  with  such  arbitration  shall  be  of  appropriate  court  at Bhubaneswar  under  the  jurisdiction  of  Odisha  High  Court.  For  all  disputes,  appropriate  court  at Bhubaneswar under  the  jurisdiction of Odisha High Court alone  shall have exclusive  jurisdiction  in all matters arising under this Agreement. 

cc. Safety, Health and Environment: The following environment, safety & health points are to be adhered: • The  Vendor  must  adhere  to  all  the  applicable  statutory  laws  pertaining  to  safety,  health  and 

environment in general and E‐Waste Management and Handling Rules in particular • The Vendor must ensure that there is no wastage of water and power at the work site • All  the motor vehicles of  the Vendor used  for  transporting materials/machinery etc  should have 

pollution control certificates and the same should be submitted at the time of obtaining gate passes. A copy of the same must be exhibited/pasted on the vehicle also 

• The Vendor must ensure proper housekeeping at work station / site by keeping the work‐areas free from unwanted material. 

• The Vendor must ensure that any debris generated during the work is transported safely to dump yard such that there  is no spillage of debris on the road during transportation (by covering with a plastic sheet/tarpaulin) 

• All the material which may be recycled / reused should be transported to the designated place for reuse/recycling. 

• All  supervisors/ workers  of  Vendor must  take  safety  and  environmental  induction  training  and comply with the instructions given therein. 

• The Vendor  shall engage  its human  resources who are proven  to be of good  conduct and  clean antecedents. 

• Generally, it shall be the responsibility of the Vendor to complete with all the statutory enactments, regulations, directions, notifications etc. issued by the Central and State Governments or any other Pollution Control Authorities from time to time. 

dd. Force Majeure If at any time during the continuance of the Agreement, the performance in whole or in part by either party  or  any  obligations  under  the  Agreement  shall  be  prevented  or  delayed  by  reason  (s)  beyond reasonable control of  the Party  including without  limitation such as   any war, hostilities, act of public enemy,  civil  commotion,  sabotage,  fire,  floods,  earthquake,  explosions,  epidemics,  quarantine restrictions and acts of God (hereinafter referred to as 'Events') and provided notice of the happening of any of the above mentioned Event  is given by either Party to the other within 21 days from the date of occurrence thereof, the agreed timelines shall be extended by the Owner on receipt of application from the Vendor without imposition of penalty and  the services under the Agreement shall be resumed after such event has come to end/ceases to exist. Should one or both the Parties be prevented from fulfilling their contractual obligations by a state of force majeure  lasting continuously  for a period of at  least 3 months and the Owner not having terminated the Agreement by that time, the two Parties shall consult each  other  regarding  the  further  implementation  of  the  Agreement  with  the  provision  that  if  no mutually satisfactory arrangement is arrived at within a period of 2 months from the expiry of 3 months referred to above, the Agreement shall be deemed to have expired at the end of the 2 months referred to  above.  The  above  mentioned  expiry  of  the  Agreement  will  imply  that  both  the  Parties  have obligations to reach an agreement regarding the winding up and financial settlement of the Agreement. 

ee. Ownership Ownership of Documents and Copy Rights 

Page 45: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 45 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

All study documents, data and specification prepared by the Vendor subject to the Scope of Agreement shall  be  the  property  of Owner.  As  and when  required  or  upon  termination  of  the  Agreement,  the aforesaid documents of all versions shall be handed over to Owner. Vendor shall take all necessary steps to  ensure  confidentiality  in  handling  of  all  the matters  pertaining  to  business  process  studies,  data, specifications, methods and other information developed or acquired or furnished by Owner by means of the Agreement or in the performance thereof. Ownership and the terms of usage of the software and Materials supplied under the Agreement shall be governed by this clause. The vendor shall grant Owner a perpetual license to use the software without any additional payment or obligations to enter into a contact for maintenance or support. Transfer of Ownership The Project and its System(s) shall be deemed to have passed onto the Owner when the Project is tested for  its performance, validation and acceptance by Owner. However the Licensing rights with regard to Core SAP Product and  the  third party software shall be governed by  the End User License Agreement (EULA) of respective OEM. 

ff. Limitation of Liability •  Notwithstanding anything  to  the Contrary  in  the Agreement or  any other document,  the  aggregate 

liability of the vendor for actual direct damage shall be limited to the Contract Price provided that this limit  shall not  apply  to  the patent  infringement,  intellectual property  rights  violations, bodily  injury (including death) and damage to the real property and tangible personal property caused by Vendor’s negligence. 

•  In  no  event,  neither  party  shall  be  liable  to  the  other  party  for  any  indirect,  special,  punitive, consequential or  incidental damages  including without  limitation,  loss of  revenue, profits, business, goodwill, anticipated savings or data or third party claims. 

•  No Director or official or employee of Owner or Vendor shall in any way be personally bound or liable for the acts or obligations of the Owner or Vendor under the Agreement or answerable for any default or  omission  in  the  observance  or  performance  of  the  acts,  matters  or  things  which  are  herein contained. 

•  The Vendor shall not be entitled to any  increase on the scheduled rates or any other rights or claims whatsoever  by  reason  of  any  representation,  explanation,  statement  or  alleged  understanding, promise or guarantees given or to have been given to him by any person. 

gg. Time is the Essence Time is the essence of this Agreement.  The acceptance of a late performance with or without objection or reservation by Owner shall not waive any rights of Owner or constitute a waiver of the requirement of timely performance, of any obligations remaining to be performed. 

hh. Confidential Information In the performance of its obligations under this Agreement or in the contemplation thereof, the Vendor and  its employees may have access to private or confidential  information,  including but not  limited to information concerning costs, charges, operating procedures and technical  information, which may be owned  or  controlled  by  Owner  or  its  parent  or  affiliates. With  respect  to  any  such  information  so accessed or acquired, the Vendor and Owner, mutually agree as follows: 

 • All information provided by Owner shall be and shall remain the exclusive property of Owner or its 

parent or affiliates. The Vendor shall  limit access to such  information to  its employees who have a need to know, consistent with the Vendor's authorized use of such information; 

• The Vendor shall keep, and have its employees having access keep, all such information confidential. 

Page 46: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 46 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

• The Vendor shall not copy, publish or disclose to others, or permit its employees or anyone else to copy, publish or disclose to others, any such information; 

• The Vendor shall return such information to Owner at its request; • The Vendor shall use such information only for the purpose of performing its obligations hereunder; 

 The Vendor at all times shall maintain appropriate internal policies and procedures reasonably sufficient to  satisfy  its  obligations  under  this  provision.  If  the  Vendor  is  required  to  disclose  any  confidential information of Owner or its parent or affiliates pursuant to any governmental or legal proceedings, the Vendor  shall  not  be  liable  for  such  disclosure  provided  that  it  gives  Owner  written  notice  of  the proceeding  and  seeks  an  appropriate  protective  order  at  least  ten  (10)  business  days  prior  to  its disclosure of the aforementioned confidential information.  

  

Page 47: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 47 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

 

7. E‐Reverse Auction & its Rules & Regulations  

• E‐Reverse Auction will be conducted for the aforementioned works. The Transaction Fees for e‐Reverse Auction shall be deposited to the account of MSTC Limited directly.. 

• The  non‐refundable  Transaction  Fees  towards  e‐Reverse  Auction  as mentioned  above work  shall  be deposited  by  all  Techno‐Commercial  qualified  bidders  directly  to  the  account  of MSTC  before  E‐RA launch schedule. The date of conduct of E‐RA shall be  intimated  in  later stage  to Techno Commercial qualified bidders via e‐mail. Before participation in e‐Reverse Auction, the bidder has to register in MSTC e‐Procurement Portal well in advance and submit the E‐RA fee amounting to the value intimated by M/s. MSTC Limited. 

• The Techno‐commercially qualified bidders will participate in the Reverse Auction through MSTC Limited. The price may be finalized based on Reverse Auction or Sealed Price Bid. OPGC reserves the right to go for  reverse  auction  prior  to  opening  of  sealed  Envelope  price  bid,  submitted  by  bidder.  This will  be decided after techno‐Commercial Evaluation. All Bidders have to give their acceptance for participating in Reverse Auction as per “Rules and Regulations of the e‐Reverse Auction” which shall be binding on the bidders. Non Acceptance to participate  in Reverse Auction may result  in no consideration of their bids, in case OPGC decides to go for reverse auction. 

  

Rules and Regulations of the e‐Reverse Auction  Buyer’s Name/Owner  Ib Thermal Power Station

(A Unit of Odisha Power Generation Corporation Limited) Auction To Be Conducted By  MSTC LimitedDate & Time Of Auction 

Auction Date: [To be intimated later]  Online e‐Reverse Auction Time : [To be intimated later]  URL: www.mstcecommerce.com/eprochome/opgc 

Special Instructions  Bidding  in  the  last minutes and seconds should be avoided  in  the bidders own interest. Neither the Service Provider nor OPGC will be responsible for any lapses /failure on the part of the vendor, in such cases. 

Auto Extension of Closing Time  5 minutes NB:  If any bidder quotes 5 minutes before closing time, the closing time will be extended  automatically  for  another  05 minutes  and  so  on  till  05 minutes  idle time between the bids. 

Decremental Value       Minimum decrement is Rs. 10,000/‐ and in multiples of Rs. 10,000/‐

Start Price  The start price shall be confirmed before start of the e‐RA and the same should be the estimated price as decided by OPGC. 

 1. For  the  proposed  e‐Reverse  Auction,  techno‐commercially  qualified  bidders  only  shall  be  eligible  to 

participate. 2. Bidders      must      be  a  registered  user  to      bid      for  Buyer  (“OPGC”)  in  MSTC  portal 

www.mstcecommerce.com/eprochome/opgc. Bidders need to have their Login ID and Password prior to e‐Reverse Auction. 

Page 48: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 48 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

3. Bidder must honour and obey the guidelines  for registration & participation stipulated at MSTC portal  for reverse auction. 

4. Bidders  have to participate as per the  e‐Reverse Auction time  and date communicated to them  & based upon e‐Reverse Auction invitation for particular Auction. 

5. Quotation once submitted through e‐Reverse Auction cannot be withdrawn /deleted. Otherwise, the EMD submitted by the bidder shall stand forfeited.  

6. Buyer  reserves  the  right  to  ban  the  bidder  from  participating  in  e‐Reverse  Auction  without  any explanation/reason at any stage of e‐Reverse Auction. 

7. Buyer   reserves   the   rights   to   extend   /   cancel   the   e‐Reverse Auction. 8. E‐Reverse Auction shall be conducted in Indian Rupees only. 9. All prices submitted by Bidder in e‐Reverse Auction shall be as per Tender’s Terms & Conditions. 10. Validity of bids: As mentioned in Tender Document. 11. Written Confirmation shall be  taken  in advance  regarding participation  in  the e‐Reverse Auction  to buyer 

along with the Authorized person name and details. 12. Buyer reserves the right to award the Purchase Order / Service Order as per buyer’s discretion irrespective 

of Live Auction Rank. 13. Buyer reserves the right to repeat the e‐Reverse Auction of same package. 14. After completion of e‐Reverse Auction, OPGC shall open the manual price bids submitted during tendering. 

The  lowest  evaluated  bid  of  all  the  bids  submitted  in manual  and  e‐Reverse Auction  process  shall  be considered for further evaluation. 

15. The bidders shall quote from their own offices/ place of their choice. Internet connectivity shall have to be ensured by bidders themselves. 

16. If the Bidder or any of his representatives are found to be involved in Price manipulation/ cartel formation of any kind, directly or indirectly by communicating with other bidders, OPGC at its own discretion shall debar the bidder from the e‐Reverse Auction/Tender and future participation also. 

17. OPGC  reserves  the  right  to  cancel  the  e‐Reverse  Auction  process/  tender  at  any  time,  before  ordering, without assigning any reason and may go for manual opening of price bids as per standard practice. 

18. OPGC shall not be liable for any interruption or delay in accessing the MSTC portal irrespective of any cause. In such cases, the decision of OPGC shall be binding on the bidders. 

19. Other  terms  and  conditions  shall  be  as  per  NIT,  bidder’s  techno‐commercial  Bid  and  other  latest correspondences/ final confirmations, (if any) against the NIT. 

20. If any item is not quoted by a bidder, the maximum price quoted by the other participated bidders for that item shall be considered for arriving evaluated price of that bidder. 

21. The total L1 Price obtained through e‐Reverse Auction shall be proportionately distributed among each line item inline with the price quoted and evaluated in the hard copy price bid. 

22. The price quoted in e‐Reverse Auction is the total price for all the items and quantity as per Price Schedule of NIT irrespective of any omission by the bidder in the hard copy price bid. 

23. In  case,  the  L1  Bidder  in  e‐Reverse  Auction  and manual  Tender  happens  to  be  the  same  bidder,  then minimum price among both shall be considered as L1. If the bidder disagrees to accept the said condition, then his EMD shall be forfeited. Apart from this the bidder will be debarred from participating  in future e‐Reverse Auction/Tender of OPGC. 

24. Each  Bidder  shall  get  the  final  loading  factor  (%age  of  the  quoted  price)  from  OPGC  before  e‐Reverse Auction for the deviations, if any, taken by them in the techno‐commercial bid. 

25. The Price quoted  in  the e‐Reverse Auction shall be  inclusive of all  inclusive FOR  ITPS basis and deviations considering  the  loading  factor  (got  from OPGC/Tender  Condition  as mentioned  in  above  clause)  on  his quoted price. 

Page 49: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 49 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

  

UNDERTAKING  I hereby undertake that I agree to the “Rules and Regulations of the e‐Reverse Auction” mentioned herein.  Signature:     Name:     Date:     Company Name:              Seal: 

                 

Page 50: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 50 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

8.  Instruction to Bidder: 1. Tenders are invited on behalf of the OPGC Ltd.  2. The bids complete  in all  respects must be  submitted  in  two parts namely Techno‐commercial part and 

Price part. The envelopes containing the respective parts must be sealed and super scribed with tender enquiry number, Name of  the work and  the name of  the part. Both  the envelopes should be kept  in a third envelope and sealed and super scribed with tender enquiry number and Name of the work. NB: The bid documents are not transferable.   Techno‐Commercial Bid:  The bidder must submit the following along with the techno‐commercial bid: I. Cost of Bid Document i.e. Rs. 11,800.00 (Inclusive of GST) II.  EMD  i.e.  1%  of Quoted  Price  in  a  closed  envelope.  The  EMD  amount will  not  be  disclosed  to  the bidders during opening of Techno‐Commercial Bid. III. Photocopies of GST Registration Certificate, Provident Fund Registration Certificate and IT PAN. IV. Signed & Stamped Scope of work, signed & Stamped Conditions of Contract (all pages) and signed & stamped  on E‐RA conditions as a token of acceptance. V. Credentials in support of Qualification to bid and Mandatory Qualification Criteria for Bidding. VI.  Commercial terms and conditions and deviation statement (if any). VII.  Un‐price schedule of project stipulated in 5.1 specifying quoted/not quoted. 

3. The Tender & rates shall be in the prescribed form provided by OPGC. 4. The works are required to be completed as per schedule mentioned in Tender documents. 5. The person who  floats  the NIT  shall be  the Accepting Authority hereinafter  referred  to as  such  for  the 

purpose of this Tender. 6. The bidder has to submit an amount of Rs. 11,800/‐ (Inclusive of GST) in shape of Demand Draft in favour 

of Odisha Power Generation Corporation Ltd. drawn on State Bank of  India  (Code‐9510) / Andhra Bank (Code‐0662) / Central Bank of India (Code‐283899), ICICI Bank (Code‐ICIC0003679) payable at Telenpali on or after 21/02/2017 up to 20/03/2018 towards tender cost. The tender cost is non refundable. 

7. Last  date  of  submission  of  Pre‐bid  clarification  by  28.02.18  and  Pre‐bid meeting  shall  be  held  on 06.03.18. The venue of Pre‐bid meeting shall be communicated through website. 

8. Techno‐commercial bids to be opened in the presence of Bidders or their duly authorized representatives who may like to be present at 15:30 Hours onwards on 21/03/2018 in the office of Contract Cell, ITPS. 

9. Bidders are advised  to  inspect and examine the site and  its surroundings and satisfy themselves before submitting their Tenders as to the nature of the ground and sub‐soil (so far as is practicable and related to particular work),  the  form and nature of  the site, nature of work, capacity of concerned plant, present condition of the plant, labour force problem relating to present Contract labour, custom & system of the local folk, means of access to the site, accommodation they may require and in general shall themselves obtain all necessary  information as to risks, contingencies and other circumstances which may  influence or affect their Tender. A Bidder shall be deemed to have full knowledge of the site whether he inspects it or not and no extra charges consequent on any misunderstanding or otherwise shall be allowed. 

10. Submission of a Tender by a Bidder  implies  that he has  read  this notice along with  the notice  inviting tender advertised  in the newspaper and all other tender documents and has made himself aware of the scope and specifications of the work to be done and of local conditions and other factors bearing on the execution of the works. 

11. A Bidder should quote his rates in figures as well as in words. The amount for each item should be worked out and the requisite totals given. Special care shall be taken to write rates in figures as well as in words, and the amounts in figures only in such a way that interpolation is not possible.  The total amount shall be 

Page 51: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 51 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

written both in figures and in words. In case of figures, the words ‘Rs.’ should be written before the figure of  rupees  and  the words  ‘Paise’  after  the decimal  figures,  e.g. Rs.2.15 P.  In  case of words,  the words ‘Rupees’ should precede and the words ‘Paise’ should be written at the end.  Unless the rate is in whole rupees and followed by the word ‘Only’ it should invariably be up to two places of decimal. 

12. In the case of item rate Tenders, only rates quoted shall be considered. Any Tender containing percentage below  / above  the  schedule of  rate quoted  is  liable  to be  rejected.  In  case of  lump  sum  tenders, only quoted amount shall be considered. 

13. Any Bidder for the works shall not be witness in the Bid of any other Bidder for the same works. Failure to observe this condition shall render the Tender of the Bidder tendering as well as of those witnessing the Tender liable for rejection. 

14. Tender shall be received up to 15:00 Hours on 21/03/2018 and shall be opened at 15:30 Hours onwards on the same day  in the presence of those Bidders or their duly authorized representatives who may like to be present. 

15. The Tender  shall be accompanied by Earnest Money worth 1% of  the  total quoted price. The Earnest Money offered  shall be  in  shape of Demand Draft  /  Pay Order  in  favour of Odisha  Power Generation Corporation Ltd drawn on State Bank of India (Code‐9510) / Andhra Bank (Code‐0662) / Central Bank of India (Code‐283899), ICICI Bank (Code‐ICIC0003679) payable at Telenpali or Bank guarantee issued by any Nationalized /scheduled Bank. 

16. The Earnest Money shall be made payable without any condition/demure  to  the Owner on demand.  In case of DD/Pay Order  submitted  towards  Earnest Money  then  the date of  issue of  the  same  shall be within 21/02/2017 to the date of opening of Part‐1 bid.   In case the Earnest Money submitted in the form of Bank Guarantee  then  the same shall be valid  for a period of   six  (06) calendar months; however  the date of issue of bank guarantee shall be  within 21/02/2017 to the date of opening of Part‐1 bid.  

17. In consideration of the Owner opening and considering the Tender for purpose of award of Contract, the Bidder shall keep his Tender valid for a period of one hundred eighty (180) days from the date of opening of  the Tender, during which period  the Bidder agrees not  to vary, alter or  revoke his Tender either  in whole or in part. If the Bidder however, fails to keep his Tender valid for one hundred eighty (180) days or varies  its  terms  and  conditions  during  the  said  period  then  the Owner  shall  be  entitled  to  forfeit  the Earnest Money amount without any notice or proof of damages etc. The Bidder shall submit his Tender as required in the Tender documents along with letter of undertaking in the proforma enclosed herewith. 

18. The Earnest Money of all unsuccessful Bidders will be returned within thirty (30) days after the award of the Contract. 

19. Any Tender not accompanied with both Earnest Money and tender cost or any of the two in accordance with aforesaid provisions shall be rejected by the Owner as non‐responsive Bid. 

20. No  interest will  be  payable  by  the Owner  on  the  said  amount  covered  under  Earnest Money  /  other security deposits. 

21. On finalization of Tender, Earnest Money of successful Bidder will be treated as part of the initial security and  shall  be  returned  after  the  end  of  performance  guarantee  period.  In  case  the  Earnest  Money submitted  in  the  form  of Bank Guarantee  then  the  same  shall  keep  valid  till  the  end  of  performance guarantee period  

22. A Bidder shall submit  the Tender which satisfies each and every condition  laid down  in  this notice and other tender documents, failing which the Tender will be liable to be rejected.  

23. The  Odisha  Power  Generation  Corporation  Ltd.  do  not  bind  themselves  to  accept  the  lowest  or  any Tender or to give any reasons for their decision.  The Owner reserves the right to allow the Public Sector Undertakings price preference facilities as admissible under existing Govt. policy.  The prospective Bidders may apprise  themselves of  the  relevant Govt. notification  in  this  regard before submission of  their bid. 

Page 52: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 52 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

The Odisha Power Generation Corporation Ltd. reserves the right of accepting the whole or any part of the  Tender  or  split  the  total  scope  of work  among  eligible  Bidders  and  Bidder  (s)  shall  be  bound  to perform the same at his/their quoted rates. 

24. Preparation of Bid: The Bidder(s) shall submit the bid in two parts, namely‐   1)  Part‐I    :  Techno commercial Bid   2)  Part‐II    :  Price Bid  PART‐I : TECHNO‐COMMERCIAL BID A complete set of original Tender documents issued to the Bidder except blank price bid / bill of quantity duly  filled  in as prescribed  in different  clauses of  the Tender documents with  signature &  stamp  in all pages as token of unconditional acceptance shall constitute Techno‐commercial Bid.  The Bidder shall enclose the following documents in this Bid. a) Covering letter. b)  Crossed  Demand  Draft  for  requisite  amount  only  drawn  in  favour  of  Odisha  Power  Generation Corporation Ltd  towards the Tender Paper Cost. c)  Letter  of  undertaking  on Non‐judicial  stamp  paper  of worth  Rs.  10.00  in  the  prescribed  format  at Section‐9.0. d)  Crossed  Demand  Draft  for  requisite  amount  only  drawn  in  favour  of  Odisha  Power  Generation Corporation Ltd or Bank guarantee issued by any Nationalized Bank/scheduled Bank towards the Earnest Money  without  which  the  Tender  shall  be  liable  for  summarily  rejection.  The  DD/PO/BG  submitted towards EMD should be sealed and clearly superscribed as EMD.  e) Documents  in support of authentication of  the person who signed  the Bid. Only proprietor, partner, directors or permanent employee with due power of attorney/authority is recognized for such signature.   f) Details of work satisfying the Qualification to bid & Mandatory Qualification Criteria for Bidding  g) Exception & deviation (if any). h)  Photocopy  of  P.F.  Registration  Certificate,  IT  PAN  and  GST  registration  Certificate  of  appropriate category issued by competent authority. i) Photocopy copy of the Registration of Firm / Company. j) Present & permanent Address for correspondence along with Telephone No,/Fax No./E‐mail address etc. k) Any other technical information, Bidder wishes to furnish. l) Information about the Bidder including the Integrity pact duly signed given in Section 7.0 m) Exclusion /Deviation Statement as per Section 7. Any assumptions made at any point in the bid must be referred to in this section. n) In addition to the sealed envelopes described above, Bidder shall also submit a CD/DVD containing soft copy of the above in PDF and Word. Response to evaluation criteria must also be provided by the bidder in Excel. o) Evidences and declarations as sought in the RFP. p) Softcopy of the filled up excel sheets given with the RFP.    Note:  If required additional sheet may be used to furnish all above information      In case of discrepancies between the hard copy and soft copy, the hard copy shall prevail.  The techno‐commercial bid with all  its enclosures as mentioned should be put  in an envelope, sealed & superscribed as  “TECHNO‐COMMERCIAL BID”. This envelope must  contain Name of  the work, NIT No., Due date of opening and Name & Address of the Bidder on bottom left hand corner of the cover.   

Page 53: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 53 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

 PART‐II: PRICE BID/SCHEDULE Price bid/Schedule shall include ‐ a) Original price bid  /  schedule of quantity duly  filled  in,  signed &  stamped on each page  as  token of unconditional acceptance  shall constitute  the Price Bid. The Bidder  shall  take utmost care  in  filling  the tender documents corresponding to  instruction to Bidder and relevant  information elsewhere  in Tender document.    b) Price Bid/Schedule shall be completed in all respects with all their attachments / enclosures, if any. c)  The  price  bid/Schedule  shall  be  prepared  in  the  manner  prescribed  in  various  clauses  of  Tender document  and  put  in  a  separate  sealed  envelope  super  scribed  as  “PRICE  BID”.  This  envelope must contain Name of work, NIT No. at the top and Name & Address of the Bidder on left hand bottom corner of the cover.  COMPLETE BID: Both the Techno‐commercial & Price Bid in separate sealed cover shall be put in a third envelope, sealed &  superscribed with Name of  the Work, NIT No., Due date of opening. The  full name, postal address, telegraphic  address  and  telex/telephone/fax/E‐Mail  of  the  Bidder  shall  be written  on  the  bottom  left corner of the envelope.  

25. SUBMISSION OF BID: Completed Bid shall be submitted to the Owner within due date and during office hours only. The Tenders shall be put into a box, marked as Tender Box or handed over to Contract Cell against receipt of the same. 

26. OPENING OF TENDER: The  techno‐commercial bid shall be opened at a predetermined  time, venue & date  in presence of  the Bidder(s) or their authorized representative who may  like to be present. Partner, director or permanent employee of the firm duly authorized can only be authorized representative. Price  bid  shall  be  opened  at  a  future  date  under  intimation  to  all  technically  qualified Bidders  and  in presence of them or their authorized representatives who shall participate.  

27. CAUTION TO BIDDER: The  person who  shall  come  to  purchase  tender  documents,  submit  the  Tender  or  participate  in  the opening of  the Tender must  abide by  the  safety  rule of OPGC  right  from  the plant  gate.  Some of  the checkpoints are, the vehicle must have valid insurance & tax paid road permit, valid driving license of the driver / Owner as the case may be. Persons with full shoes shall be allowed to enter the plant & our plant gate shall provide other items such as hard hat, safety glass & visitor pass. Not more than 2(two) persons for one Tender shall be allowed to participate in Tender opening. 

28. ALL PAGES TO BE INITIALED: All the pages of Tender documents shall be  initialed. But first &  last pages of all volumes of documents shall be signed with date by the Bidders or their authorized representatives. 

29. The Bidder shall quote in English language only. 30. THE SCHEDULE: 

The work shall be executed strictly as per the Time Schedule, indicated in the tender documents. 31. RECORD KEEPING:Relevant records are to be maintained by the Contractor in day‐to‐day / monthly basis 

&  furnished  to  Engineer‐in‐charge or his  representative  for  scrutiny, Management  Information  System and payment etc. 

32. Bidder to obtain their own Information 

Page 54: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 54 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

a)  Bidder shall for all purposes and whatsoever reason may be, deemed to have independently obtained all necessary  information for the purpose of preparing his Bid. The correctness of the details given  in the Bid Document is for guideline/ information only, to help the Bidder to prepare his Bid. 

b)  Bidder  shall  be  deemed  to  have  examined  the  Bid  documents  and  to  have  obtained  his  own information  in  all matters whatsoever  that might  influence  carrying out  the  implementation of  the Project  at  the  scheduled  rates  and  satisfied  himself  to  the  sufficiency  of  his  Bid.  Any  error  in description  or  quantity  or  omission  there  from  shall  not  vitiate  the  Agreement  or  release  the Implementation Partner from executing the work comprised in the Agreement according to the scope of work and specifications at scheduled rates. He is deemed to know the scope, nature and magnitude of implementing the Project. 

c)  Bidder shall be deemed to have visited the sites, offices and surrounding areas, to have satisfied itself to the nature of all existing Business processes and also as to the nature and the conditions of available facilities and communications and possible interruptions there to the access and egress from site and to  have  made  enquiries,  examined  satisfied  himself  of  the  sites  in  respect  to  requirements  for implementing  Project  and  to  have made  local  independent  enquiries  on  all matters  affecting  the Agreement. He  is deemed to have acquainted himself his  liability for payment of Government Taxes, Customs and Duties and other charges. 

d)  Any neglect or failure on part of the Bidder  in obtaining necessary and reliable  information on  issues stated in the above clause or any other matters affecting the Agreement shall not relieve him from any risks or  liabilities or the entire responsibility for  implementing the Project at the scheduled rates and time in strict accordance with the contract documents. 

e)  Any  change  in  site  conditions or  technological  requirement  shall be binding on  the  Implementation Partner and no extra claim on this account shall be entertained. 

f)  The oral agreement or inference from conversation with any officer or employee of the Owner before, during or after  the execution of  the Agreement shall not  in any way affect or modify  the  terms and obligations herein contained. 

33. Addenda / Corrigenda / Amendments issued to this Tender a)  OPGC reserves the right to issue any addenda or corrigenda to the Bid document without assigning any 

reason thereto. In response to such addenda / corrigenda, the Bidders shall submit their Bid in a fresh schedule.  However,  if  the  Bidder  has  already  submitted  his  Bid  prior  to  issue  of  such  addenda  / corrigenda, they shall resubmit a fresh offer marked on the envelope as “Amended Offer”. The original offer submitted by such party shall not be returned/opened. 

b)  At any time prior to the deadline of submission of Bids, OPGC may, for any reason, whether at its own initiatives or  in response to a clarification by a prospective bidder, modify the bid document through Amendment(s). 

c)  The  Amendment(s)  will  be  notified  to  all  prospective  bidders  through  the  website  and  such Amendment(s) will be binding on them. 

d)  OPGC may extend the deadline for the submission of bids, in order to allow the prospective bidders a reasonable time in which to take the amendment(s) into account in preparing their Bids. 

34. Extension of Bid Opening Date OPGC may, at its sole discretion, decide to extend this Bid Opening Date and / or date for submission of Bids.  In such a case, all rights and obligations of OPGC and that of Bidders previously subject to the Bid Opening Date will thereafter be subject to the new Bid Opening Date. 

35. Bids Received Late Any bid received by OPGC after the expiry of the specified date and time for submission of bids will be rejected outright. The Bidders must  take all  responsibility of  submitting  the Bids within  the prescribed 

Page 55: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 55 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

date of submission of Bids. OPGC will not accept as valid reason or be responsible for any postal/courier delay or non‐receipt / non‐delivery of the Bids. 

36. Modification and Withdrawal of Bids Modification Request by Bidder The Bidder will not be allowed to modify its Bid after its submission, in any case.  Withdrawal of Bid by Bidder No bid shall be withdrawn during the period between the Bid Opening Date and the expiration of the bid validity period including its extension if any as specified in Notice Inviting Tender. Withdrawal of a bid may result in the forfeiture of the Bidder’s Bid Security (EMD).  Acceptance of Important Conditions Bidders may  note  that  no  deviations  whatsoever  to  certain  important  conditions  as  per    the  RFP  is permitted by the Owner and therefore, the Bidders are advised that while developing their proposals and prices,  these  conditions may appropriately be  taken  into  consideration especially with  respect  to  their effect, wherever applicable, on the cash flow projections during the execution of the Agreement. Bidders are  required  to  furnish  certificates/evidence  to  support  the  requirements  furnished  under mandatory Qualification Criteria. Any Bid not accompanied by  such certificate  shall be  liable  to be  rejected by  the Owner and shall not be opened. 

37. Extension of Period of Bid Validity In exceptional circumstances, OPGC may request all the Bidders consent to an extension of the period of validity of their respective bid. The request and the response thereto will be made in writing. Extension of validity period by the Bidder must be unconditional. A Bidder will not be permitted to modify his bid. EMD Bids not accompanied by the requisite EMD, or bids accompanied by EMD of  inadequate value or not  in the  prescribed  form  shall  not  be  entertained  and  in  such  a  case  bids  shall  be  rejected  and  further envelopes will not be opened. The EMD shall be liable to be forfeited, i. If  the Bidder unilaterally  revokes, withdraws,  cancels  its bid or unilaterally  varies any  term of  the 

tender document during the period of bid validity.  ii. In case the owner/OPGC decides to reject the bid for not containing all the parts or is found to be not 

complete in all respect. iii. In case  the owner/OPGC decides  to  reject  the bid as  the bidder quotes abnormal  rates as defined 

rejection of bid clause. iv. In case the owner/OPGC decides to reject the bid as the bidder makes false or misleading claims  in 

the bid as defined in rejection of bid clause. v. In case the owner/OPGC decides to reject the bid as the bidder is found to be involved in ‘corrupt or 

fraudulent practice’ as defined in rejection of bid clause. vi. In  the  case of a  successful Bidder,  if  the Bidder  fails within  the  specified  time  limit  to  furnish  the 

acceptance of Letter of Award and / or fails to submit Performance Guarantee of requisite amount. vii. If,  during  evaluation  of  bids,  OPGC  ascertains  that  there  is  discrepancy  in  the  bid  price  due  to 

arithmetical error, and on communicating such error to the Bidder, the Bidder does not accept the proposed correction of errors. 

38. Rates to Be In Figures & Words The  Bidder  shall  quote  both  in  figures  and  in words  for  the  rates  and  amount  quoted  by  him  in  the Schedule of quantities / Price schedule forming part of the Bid document, in such a way that interpolation 

Page 56: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 56 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

is not possible. The amount of each item shall be worked out and entered and requisite total given for all items. The quoted amount for the work shall be entered in the Bid and duly signed by the Bidder. If any ambiguities are observed in the rates & amount given in words & figures the following procedure shall be followed:  i. When there is difference between the rates in figures and words, rate which corresponds to the amount 

worked out by the Bidder, shall be taken as correct. ii. When  the  rate quoted by  the Bidder  in  figures and words  tally but  the amount  is  incorrect,  the  rate 

quoted by the Bidder shall be taken as correct but not the amount.  iii. When  it  is not possible  to ascertain  the  correct  rate by either of above methods,  the  rate quoted  in 

words shall be taken as correct.   39. Abnormal Rates 

The Bidder  is  expected  to  quote  the  rate  for  each  item  after  careful  analysis  of  cost  involved  for  the satisfactory performance  and  completion of  item work  considering  all  specifications  and  conditions of Agreement. This will avoid  loss of profit or gain  in case of curtailment or change  in specification for any other item. In case the rates quoted by the Bidder for any item are unusually high or unusually low it will be sufficient cause for the rejection of the Bid unless the Owner is convinced about the reasonableness of the analysis for rate furnished by the Bidder (on demand) after scrutiny.  

40. Corrections & Erases No erases or over writings are permissible. All corrections and alterations in the entries of Bid papers shall be signed by the Bidder with date and stamping. 

41. Details & Signature of Bidder The Bid shall contain the name, residence and place of business of person or persons making the Bid and shall be signed by the Bidder with his usual signature. Partnership firms shall furnish the full names of the partners in the Bid. It should be signed in the partnerships name by all the partners or by duly authorized representative followed by the name and designation of the person signing. Bid by a Corporation shall be signed  by  an  authorized  representative  and  a  power  of  attorney  /  authorization  on  its  behalf  shall accompany  the Bid. A copy of constitution of  the  firm with names of all partners shall be  furnished.  In case of cooperative society, the authorized representative of the society will sign the Bid. Similar principle shall  be  followed  in  case  of  any  Trust  and Hindu Undivided  Family  business.  The  signature  should  be attested, at least by one witness.  

42. False or Misleading Claims OPGC may in its absolute discretion exclude or reject any proposal that in the reasonable opinion only of OPGC  contains  any  false  or misleading  claims or  statements.   OPGC has no  liability  to  any person  for excluding or rejecting any such proposal. 

43. Fraud and Corruption Bidders are expected to observe the highest standard of ethics from RFP stage till execution of Contract and not to indulge in any corrupt practice, fraudulent practice, coercive practice, undesirable practice or restrictive practice. In pursuit of this policy, OPGC defines, for the purposes of this provision, the terms set forth below as follows: "Corrupt practice" means the offering, giving, receiving, or soliciting of anything of value to influence the action in the procurement process or in Contract execution; "fraudulent practice" means a misrepresentation of facts in order to influence a procurement process or the execution of a Contract to the detriment of the Buyer and includes collusive practices among Bidders (prior to or after Bid submission)designed to establish Bid prices at artificial, non‐competitive levels and to deprive the Buyer of the benefits of competition; 

Page 57: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 57 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

"Coercive practice" means  impairing or harming or  threatening  to  impair or harm directly or  indirectly, any person or property to influence any person’s participation or action in the Bidding Process;  "undesirable  practice" means  (i)  establishing  contact with  any person  connected with or  employed or engaged  by  the  Buyer  with  the  objective  of  canvassing,  lobbying  or  in  any  manner  influencing  or attempting to influence the Bidding Process; or (i) having a conflict of interest  “restrictive  practice" means  forming  a  cartel  or  arriving  at  any  understanding  or  arrangement  among Bidders with the objective of restricting or manipulating a full and fair competition in the Bidding Process.  Failure to comply with  the above requirement may result  in the disqualification of the Bidder  from this competition. 

44. Contacting the Owner From the time of bid opening to the time of Contract award, if any Bidder wishes to contact the Owner on any matter related to the bid, he shall do so in e‐mail. 

45. Conflict of Interest Bidders must state in their submission any circumstances, arrangements, understandings or relationships that constitute, or may reasonably be considered to constitute, an actual or potential conflict of interest with  the Bidders  (or  their consortium partners) obligations under  this RFP  (including but not  limited  to these conditions of proposal) or under any contract which may be negotiated or executed between the Bidder and OPGC. Bidders and their employees, agents, advisers and any other person associated with the Bidder must not place themselves in a position which may, or does, give rise to a conflict of interest (or a potential  conflict of  interest) between  the  interests of OPGC or any other  interests during  the bidding process. 

46. Ownership of Responses Without affecting any intellectual property rights, which may exist in a response to this RFP document, all responses submitted will become the property of OPGC. Without limiting this section, OPGC reserves the right  to copy and  reproduce  responses  for  the purposes of evaluation, clarification, negotiation and/or contract execution and anything else  related  to  these purposes.  In addition, OPGC will  retain  (soft and hard)  copies  of  all  responses,  evaluation,  negotiation  or  such  other materials  as  are  required  for  the discharge of  its  legal obligations and  in order to efficiently and effectively manage any contract entered into with a Bidder.  

47. Owner’s Right to Accept Any Bid and to reject any or all Bids OPGC reserves the right to accept or reject any bid or to annul the bidding process and reject all bids at any time prior to Contract award, without assigning any reasons thereof and OPGC shall not entertain any claim whatsoever on this account. 

48. Opening of Bids The Techno‐Commercial bids shall be opened at a predetermined time, venue & date in presence of the Bidder(s) or  their authorized  representative(s) who may  like  to be present. Bidders qualifying based on the  qualification  to  bid  and mandatory  evaluation  criteria  for  bidder  would  have  their  detailed  bids evaluated.  Bidders  not meeting  the  qualification  to  bid  and mandatory  evaluation  criteria  for  bidder would be dropped from any further evaluation/ consideration. Partner, Director or permanent employee of  the  firm duly  authorized only  can be  the  authorized  representative.  Price bid  shall  be opened  at  a future  date  under  intimation  to  all  technically  qualified  Bidders  and  in  presence  of  Bidder  or  their authorized representatives who are successful in technical bid evaluation. 

49. Preliminary examination & Clarification on Bids 

Page 58: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 58 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

OPGC will examine the bids to determine whether they are complete, whether the documents have been properly signed and whether the bids are generally in order. Any bids found to be non‐responsive for any reason or not meeting the minimum  levels of the performance or other criteria specified  in the Bidding Documents will be rejected by OPGC and shall not be  included for further consideration. OPGC will also carry out a preliminary examination of any alternative bids submitted by Bidders.  ‐ Prior to the detailed evaluation, OPGC will determine whether each bid is complete, and is substantially responsive to the Bidding Documents. For the purposes of this determination, a substantially responsive bid is one that conforms to all the terms, conditions, and specifications of the Bidding Documents without material deviations, exceptions, objections, conditionality or reservations. A material deviation, exception, objection, conditionality, or reservation is:  • One that limits in any substantial way the scope, quality, or performance of the desired system; or  • one that limits, in any substantial way that is inconsistent with the Bidding Documents, OPGC rights or the successful Bidder’s obligations under the Contract; and  • One that the acceptance of which would unfairly affect the competitive position of other Bidders who have submitted substantially responsive bids.  ‐  In particular, bids with deviations  from, objections  to or  reservations about critical provisions such as those  concerning Bid  Security, Governing  Law,  Taxes  and Duties, Defect  Liability, Maintenance period, Patent Indemnity or Limitation of Liability, that the Bidder is not prepared to withdraw, will be treated as non‐responsive. OPGC’s determination of a bid’s responsiveness will be based on the contents of the bid itself without recourse to extrinsic evidence.  During the bid evaluation, OPGC may, at its discretion, ask the Bidder for clarifications on its Proposal. The request for clarification and the response shall be  in writing, and no change  in the price or substance of the bid shall be sought, offered, or permitted. 

50. Language English  shall  be  the  binding  and  controlling  language  for  all  matters  relating  to  the  meaning  or interpretation of this bid document. 

51. Integrity Pact The Bidder  shall  submit  the  signed &  stamped  copy of  INTEGRITY PACT as per  the  format  specified at Section‐9.0  in the Techno Commercial bid; otherwise bid shall be liable for rejection. 

Page 59: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 59 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

 

9. Bid supporting documents  9.1 Letter of Undertaking by the Bidder 

 Letter of Undertaking by the Bidder 

 PROFORMA OF LETTER OF UNDERTAKING TO BE SUBMITTED BY THE BIDDER ALONG WITH HIS BID. 

(To be executed on non‐judicial stamp paper of requisite value)   Ref:                   Date:   To Odisha Power Generation Corporation Ltd., IB Thermal Power Station, Banharpali.  (Hereinafter referred to as the Owner)   I/We have read and examined the Bid documents relating to “Implementation of SAP ERP with Post‐Implementation 

support at OPGC”. 

 

I/We hereby tender for execution of the works referred to in the aforesaid documents upon the terms and conditions 

contained or referred to therein and in accordance in all respects with the specifications, designs, drawings and other 

relevant details contained in Schedule of Quantities / Price schedule attached with the Bid documents and the period 

(s) of completion as stipulated in the Contract. 

In consideration of I/We being invited to Bid, I/We agree to keep the Bid open for acceptance for 180 days from the 

due date of opening of bid thereof including the extended period if any and not to make any modifications in its terms 

and conditions which are not acceptable to the Owner. 

A sum of 1% of quoted price is hereby forwarded in shape of Demand Draft drawn in favour of Odisha Power 

Generation Corporation Ltd. and payable at State Bank of India (Code‐9510) / Andhra Bank (Code‐0662) / Central Bank 

of India (Code‐283899), ICICI Bank (Code‐ICIC0003679) payable at Telenpali or Bank Guarantee issued by a 

______________Bank as Earnest Money in the manner prescribed in NIT enclosed. If I/We fail to keep the Bid open as 

aforesaid or make any modifications in the terms and conditions of the Bid, which are not acceptable to the Owner, 

I/We agree that the Owner shall, without prejudice to any other remedy, be at liberty to forfeit the said earnest money 

Page 60: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 60 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

absolutely. Should this Bid be accepted, I/We hereby agree to abide by and fulfil all the terms, conditions and 

provisions of the aforesaid documents. 

 

If, after  the Bid  is accepted,  I/We  fail  to commence  the execution of  the works as provided  in  the conditions,  I/We 

agree  that  the Owner  shall without prejudice  to any other  right or  remedy be at  liberty  to  forfeit  the  said earnest 

money absolutely. 

 

Signature of Bidder ………………… 

 

  Duly authorized to sign the Bid on behalf  of the (in block capitals)………………….. 

            …………………………………………….. 

  Dated……………………………………… 

  Postal Address………………………… 

  Telegraphic Address…………………… 

  Telephone No…………………………….. 

  Fax No……………………………………. 

  E‐mail address …………………………… 

 

 

Witness…………….. 

 

Date……………….. 

 

Address……………              

Page 61: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 61 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

 9.2 Exclusions / Deviations Statement 

 DEVIATION / EXCLUSION / VARIATION STATEMENT 

 We confirm that the following are the only deviations / exclusions / variations to the requirements described  in your 

Bid Document Number …………..dated ……….and as responded in our proposal / bid Number ………. dated ……….  Except 

for these deviations / exclusions / variations, we confirm to all the other requirements of the said Bid Document. 

 

Sr. No. 

Page no. of Bid Document 

Serial no. of Bid Document 

Subject  Deviation / Exclusion / Variation 

                    

 We declare that any other deviations noted  in other places  in the bid documents / correspondences shall be  ignored 

and construed as our unconditional acceptance of the respective tender terms, unless mutually agreed under seal and 

signature from both sides. 

 

Thanking you, 

Yours faithfully 

 

Name and Designation of Signatory: 

Name of Firm: 

Address 

 

Notes:  

a) This form has to be signed by authorised signatories of the Bidder. b) Please use separate sheets in case the deviation / exclusion / variation that cannot be adequately described in the 

table above clearly mentioning the reasons).  c) The Bidders must  comply with all  requirements of  this Bid Document. However, where  the Bidder  is unable  to 

comply with specific  requirements  listed out  in  this document, he must specifically  indicate  these  in  the  format given  above. Anything  contained  in  this Bid Document, which has not been  specifically  excluded, or  for which deviations have not been indicated, will be regarded as being agreed to by the Bidder. 

Page 62: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 62 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

9.3 Performa for Bank Guarantee for Bid Security (Earnest Money Deposit)  

PROFORMA BANK GUARANTEE IN LIEU OF DD FOR EARNEST MONEY (on Non Judicial stamp paper of appropriate value) 

(Applicable to Bid value more than Rs. 25 lakh only) 

 

Ref:                   Date: 

                    Bank Guarantee No. 

 

To 

Odisha Power Generation Corporation Ltd., 

Ib Thermal Power Station, 

At/Po‐ Banharpali, 

Dist‐Jharsuguda‐768234. 

 

Dear Sir, 

   

In consideration of Odisha Power Generation Corporation having  its Registered office at 7th.Floor, Zone – A, Fortune 

Towers,  Chandrasekharpur,  Bhubaneswar‐751  023  (hereinafter  called  the  “Owner”  which  expression  shall  unless 

repugnant  to  the  subject  or  context  include  its  successors  and  assigns)  having  issued Bid  Specification Against NIT 

No_________________________________________  dt.________________  to 

M/s________________________________________  having  its  Registered  /  Head  office 

at_________________________________________  (hereinafter  called  the Bidder) who wishes  to participate  in  the 

said tender for _______________and you, as a special favour, have agreed to accept an irrevocable and unconditional 

Bank Bid Guarantee for an amount of Rs.________________________________ valid up to ___________________ On 

behalf of the Bidder, as a condition for participation in the said tender. 

 

We, the _____________________ Bank incorporated under ________________ law and having one of our branches at 

_________________ and having our Registered office/Head office at _________________ do here by unconditionally 

and  irrevocably  guarantee  and  under  take  to  pay  to  the  “Owner”  immediately  on  demand  without  any  demur, 

reservation,  protest,  contest  and  recourse  the  said  sum  of  Rs._____________  (Rupees  _______________________ 

only). Any such claim/demand made by the said “Owner” on us shall be conclusive and binding on us  irrespective of 

any dispute or differences raised by the Bidder. 

 

Page 63: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 63 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

This guarantee shall be irrevocable and shall remain valid up to ……………… if any further extension of this guarantee is 

required the same may be extended at Bank's sole discretion to such required period on receiving  instructions  from 

……………..on whose behalf this guarantee is issued.  

 

We, the said Bank lastly undertake not to revoke this guarantee during its currency except with the previous consent of 

the Owner  in writing and agree  that any  change  in  the  constitution of  the  said  tenderer or  the  said Bank  shall not 

discharge our liability.  In witness where of the Bank, through its authorised officer, has set its hand and stamp on this 

___________________________ day of _______________________20______ 

 

 

 

 

 

Witness: 

 

 

(Signature)              (Signature) 

 

____________________          __________________ 

Name                Name 

 

 

_____________________          (Designation with Bank stamp) 

Official Address 

 

 

                Attorney as per Power of Attorney 

 

                No.___________________ 

 

                                                                          Date.___________________ 

   

Page 64: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 64 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

9.4 Integrity Pact  

Between  

Odisha Power Generation Corporation Ltd.  (OPGC), a company  registered under  the Companies Act 1956 and having  its registered office at Zone‐A, 7th Floor, Fortune Towers, Chandrasekharpur, Bhubaneswar‐ 751023, Odisha (India) hereinafter referred to as “Principal”, which expression unless repugnant to the context or meaning hereof shall include its successors or assigns of the ONE PART  

And  

__________________________________________________________,  description  of  the  party  along  with  address), hereinafter referred to as “Bidder/ Contractor” which expression unless repugnant to the context or meaning hereof shall include its successors or assigns of the OTHER PART  (The Principal and the Bidder/ Contractor together are collectively referred to as the “Parties” and individually as a “Party” in this Pact).  

Preamble The  Principal  intends  to  award,  under  laid‐down  organizational  procedures,  contract/s  for… ………………………………………………………………(“Contract”) The Principal values full compliance with all relevant laws of the land, rules and regulations, and the principles of economic use of resources, and of fairness and transparency in its relations with its Bidder(s)/ Contractor(s).  In order to achieve these goals, the Principal enter into an Integrity Pact (“Pact”) with the Bidder(s)/ Contractor(s) for the tender  process  and  execution  of  the  Contract  and will  appoint  Independent  External Monitor(s), who will monitor  the tender process and the execution of the Contract for compliance with the principles mentioned above.  Section 1 – Commitments of the Principal  1.1   The Principal commits  itself  to  take all measures necessary  to prevent  corruption and  to observe  the  following 

principles:‐  1.1.1   No  employee/Director/management  representative  of  the  Principal,  personally  or  through  family members  or 

through third party, will in connection with the tender process for, or the execution of a Contract, demand, take a promise for or accept, for self or third person, any material or  immaterial benefit which the person  is not  legally entitled to. 

 1.1.2   The Principal will, during the tender process treat all Bidder(s)/ Contractor(s) with equity and reason. The Principal 

will in particular, before and during the tender process, provide to all Bidder(s) the same information ( other than the clarifications sought for by the Bidder(s)/Contractors with respect to the bidder specific information required to be provided  only to the concerned Bidder(s)/Contractor(s),) and will not provide to any Bidder(s)/Contractor(s) confidential  /  additional  information  through which  the  Bidder(s)  /Contractor(s)  could  obtain  an  advantage  in relation to the tender process or the contract execution. 

Page 65: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 65 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

 1.1.3   The  Principal will  exclude  from  the  tender  process  or  execution  of  the  Contract  all  known  prejudiced  persons 

including those employees/ Directors/management representatives of the Principal who have family relationships with the employees or Directors of the Bidder(s)/Contractor(s). 

 1.2   If the Principal obtains information on the conduct of any of its employees/ Directors/ management representative 

which  is a penal offence under the  Indian Penal Code 1860 and Prevention of Corruption Act 1988 or any other statutory penal enactment, or  if there be a substantive suspicion  in this regard, the Principal will  inform  its Chief Vigilance Officer for further enquiry and initiation of disciplinary actions against the person(s) concerned. 

 Section 2 – Commitments of the Bidder(s)/ Contractor(s)  2.1   The Bidder(s)/ Contractor(s) commit  itself  to  take all measures necessary  to prevent corruption. The Bidder(s) / 

Contractor(s) commits  itself to observe the following principles during  its participation  in the tender process and during the contract execution. 

 2.1.1   The Bidder(s)/ Contractor(s) will not, directly or  through any other person or  firm, offer, promise or give  to  the 

Principal or  to any of  the Principal’s employees/   Directors/ management  representative  involved  in  the  tender process or the execution of the Contract or to any third person any material, immaterial or any other benefit which he / she is not legally entitled to, in order to obtain in exchange any advantage of any kind whatsoever during the tender process or during the execution of the Contract. 

 2.1.2   The  Bidder(s)/  Contractor(s)  will  not  enter  with  other  Bidder(s)  into  any  illegal  or  undisclosed  agreement  or 

understanding,  whether  formal  or  informal.  This  applies  in  particular  to  prices,  specifications,  certifications, subsidiary contracts, submission or non‐submission of bids or any other actions to restrict competitiveness or to introduce cartelization in the bidding process. 

 2.1.3   The Bidder(s)/ Contractor(s) will not commit any penal offence under the relevant IPC/ PC Act and any other such 

similar applicable Acts; further the Bidder(s)/ Contractor(s) will not use improperly, for purposes of competition or personal gain, or pass on to others, any information or document provided by the Principal as part of the business relationship,  regarding  plans,  technical  proposals  and  business  details,  including  information  contained  or transmitted electronically. 

 2.1.4   The Bidder(s)/  Contractor(s) will, when  presenting his  bid,  disclose  any  and  all  payments  he  has made,  and  is 

committed to or intends to make to agents, brokers or any other intermediaries in connection with the award of the contract. 

 2.1.5  The Bidder(s)  / Contractor(s) will not, directly or  through  any other person or  firm,  approach  any Government 

officials, ministers, political persons public servants, or any external agencies in an effort to influence the bidding decision making process or to attain any undue favours to the Bidder(s) / Contractors(s). 

 2.1.6  The  Bidder(s)/Contractor(s)  shall  exclude,  from  the  tender  process  or  execution  of  the  Contract  all  known 

prejudiced  persons  including  those  employees  /  Directors  /management  representatives  of  the  Bidder(s)  / Contractor(s)  who have family relationships with the employees or Directors of the Principal. 

Page 66: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 66 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

 2.1.7  The  Bidder(s)/Contractor(s)  shall  disclose  the  circumstances,  arrangements,  undertakings  or  relationships  that 

constitute,  or may  reasonably  be  considered  to  constitute,  an  actual  or  potential  conflict  of  interest with  its obligations specified  in the tender process or under any contract which may be negotiated or executed with the Principal. Bidder(s)/Contractor(s) and their employees, agents, advisors and any other person associated with the Bidder(s)/Contractor(s) must not place themselves in a position which may, or does, give rise to conflict of interest (or a potential conflict of interest) between the interests of the Principal or any other interests during the tender process or through operation of the Contract. 

 2.1.8  The Bidder(s)/Contractor(s) will not indulge in any corrupt, fraudulent, coercive undesirable or restrictive practice 

in the tender process or the execution of the Contract.  2.2   The Bidder(s)/ Contractor(s) or its sub‐contractors or its agents will not instigate third persons to commit offences 

outlined above or be an accessory to such offences.   Section 3 – Disqualification from tender process, termination of the Contract and exclusion from future contracts  If the Bidder(s)/ Contractor(s), during the tender process or before award of the Contract or during the execution of the Contract has committed a transgression through a violation of Section 2 above, or acts in any other manner such as to put its reliability or credibility in question, the Principal may disqualify the Bidders(s)/ Contractor(s) from the tender process or  decide not  to award  the Contract or  terminate  the awarded Contract or blacklist  the Bidder(s)/Contractor(s).  l and  seek damages as specified in Section 4.  Section 4 – Compensation for Violations   4.1   If  the Principal has disqualified  the Bidder(s)/ Contractor(s)  from  the  tender process prior  to  the  award of  the 

Contract according to Section 3 or 5, the Principal is entitled to demand and recover the damages by encashment of the Earnest Money Deposit/ Bid Security deposited by the Bidder(s)/ Contractor(s) while making submission in the tender process. 

 4.2   If the Principal has terminated the Contract according to Section 3 or 5, or if the Principal is entitled to terminate 

the Contract  according  to  section 3 or 5,  the Principal  is  entitled  to demand  and  recover  from  the Contractor liquidated  damages  equivalent  to  10%  of  the  Contract  value  or  the  amount  equivalent  to  Security Deposit/Performance Bank Guarantee, whichever is higher, in addition to the Liquidated Damages already agreed to by the Bidder(s)/ Contractor(s) in the Contract. 

 Section 5 – Previous Transgression  5.1   The Bidder(s)/ Contractor(s) declares that no previous transgressions occurred in the last three (3) years with any 

other  organization  in  any  country  conforming  to  the  anti‐corruption  approach  or with  any  other  Public  Sector Enterprise in India that could justify its  exclusion from the tender process or the execution of the Contract. 

 

Page 67: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 67 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

5.2   If the Bidder/ Contractor has made  incorrect statement/disclosure on this subject or hides such  information, the Principal is entitled to disqualify the Bidder/Contractor from the tender process or the execution of the Contract, if already awarded, may terminate the Contract and claim compensation as mentioned in section 4. 

 Section 6 – Equal treatment of all Bidders/ Contractors/ Sub‐contractors  6.1    The Bidder(s)/ Contractor(s) undertake(s) to demand from his sub‐contractors a commitment consistent with this 

Integrity Pact. This commitment shall be taken only from those sub‐contractors whose contract value is more than 20% of Bidder’s/ Contractor’s contract value with the Principal. 

 6.2   The Principal will enter  into  individual  Integrity Pacts with  identical  conditions  as  this one with  all Bidders  and 

Contractors for the tender process.   6.3   Only those Bidder(s)/ Contractor(s) who have entered or expressed  intention of entering  into  Integrity Pact with 

the Principal shall be eligible to participate in the tender process or execution of the Contract.    6.4         The Principal will disqualify the Bidder(s)/ Contractor(s) from the tender process who do not execute the  Integrity 

Pact or violate its provisions.  Section 7 – Criminal Charges against violating Bidders/ Contractors/ Subcontractors  If  the  Principal  obtains  knowledge  of  conduct  of  a  Bidder,  Contractor  or  Subcontractor,  or  of  an  employee  or  a representative or an associate of a Bidder, Contractor or Subcontractor which constitutes corruption, or if the Principal has substantive suspicion in this regard, the Principal will inform the Vigilance Office of the State in which the Principal has its Registered Office.  Section 8 –Independent External Monitor(s)  8.1   The Principal will appoint one or more competent and credible  Independent External Monitor(s) (“Monitor”) for 

monitoring  the  implementation  of  this  Pact.  The  task  of  the  Monitor  will  be  to  review  independently  and objectively, whether and to what extent the Parties comply with the obligations of the Integrity Pact. 

 8.2   The Monitor  shall  not  be  subject  to  instructions  by  the  representatives  of  the  Parties  and  shall  perform  his 

functions neutrally and independently. The Monitor shall report to the OPGC Board.  8.3   The  Bidder(s)/  Contractor(s)  accepts  that  the  Monitor  has  the  right  to  access  without  restriction  to  all  the 

document related to the tender process or the execution of the Contract of the Principal including that provided by the  Bidder(s)/  Contractor(s).  The  Bidder(s)/  Contractor(s)  shall  grant  the  Monitor,  upon  his  request  and demonstration of a valid interest, unrestricted and unconditional access to the document in its possession related to the tender process or execution of the Contract. The same  is applicable to Sub‐contractor(s) of the Bidder(s)/ Contractor(s).  The  Monitor  is  under  contractual  obligation  to  treat  the  information  and  documents  of  the Bidder(s)/ Contractor(s) / Subcontractor(s) with strict confidentiality. 

 

Page 68: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 68 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

8.4   The Principal will provide to the Monitor sufficient information about all meetings among the Parties related to the tender process or the execution of the Contract provided such meetings could have an impact on the contractual relations between  the Principal and  the Bidder/ Contractor. The Parties shall offer  to the Monitor  the option  to participate in such meetings. 

 8.5   As soon as the Monitor notices, or believes to have noticed, a violation of the Integrity Pact, he will so inform the 

Managing Director of the Principal and request him to take corrective action, or heal the situation, or to take other relevant action. The Monitor may in this regard submit non‐binding recommendations. Beyond these actions, the Monitor shall have no right to demand from the Parties that they act in a specific manner, refrain from action or tolerate action. 

 8.6   If  the Monitor  reports  to  the Managing Director of  the Principal, a  substantiated  suspicion of an offence under 

relevant IPC / PC Act, the Managing Director of the Principal  shall within reasonable time, taken visible action to proceed against such offence.  

 8.7   The number of Independent External Monitor(s) shall be decided by OPGC.   8.8  The word ‘Monitor’ would include both singular and plural.  Section 9 – Pact Duration  9.1   This Pact shall become effective from the date when both the Parties have executed it or the Parties have shown 

their intent to enter into the Pact, whichever is earlier. This Pact will expire for the Contractor after it meets all the obligations of the Contract and for all other Bidders 6 months after the Contract has been awarded. 

 9.2   If any claim is made / lodged during this time, the same shall be binding and continue to be valid despite the lapse 

of this Pact as specified as above, unless it is discharged/ determined by the Principal  Section 10 – Other Provisions  10.1   This  agreement  is  subject  to  Indian  Laws  and  jurisdiction  shall  be  registered  office  of  the  Principal,  i.e. 

Bhubaneswar.  10.2   Changes and supplements to the Pact as well as notices of termination of the Pact to be sent to any Party shall be 

made in writing by mutual agreement between the Parties.   10.3   If the Bidder/ Contractor  is a partnership or a consortium, this Pact shall be signed by all partners or consortium 

members. 10.4   Should one or several provisions of this agreement turn out to be invalid, the remainder of this agreement remains 

valid. In this case, the parties will strive to come to an agreement to their original intentions.  10.5   Only those Bidder(s)/ Contractor(s) who have expressed their intention through submission in the tender process 

or have entered into this Pact with the Principal will be eligible to participate in the bidding.   

Page 69: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 69 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

For & On behalf of the Principal     For & On behalf of the Bidder/ Contractor (Office Seal)             (Office Seal) 

Place: ____________ Date: _____________ Witness: ____________________       Witness: _______________________ (Name & Address): ____________      (Name & Address): ________________ 

                                        

Page 70: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 70 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

9.5 Owner Safety Rules 

The Vendor shall provide Personal Protective Equipment (like helmet, shoes, safety glass, nose mask and earplug etc.) as many as required to all his workmen & ensure safety policy of Owner strictly otherwise they will not be allowed to work. Standard of personal protective equipment to be provided by the Vendor to their employees are indicated below.

1. Industrial safety helmet conforming IS: 2925 2. Safety shoes conforming IS: 9473-1993 3. Dust mask conforming IS: 9473-1983 4. Full body Harness along with Lifeline with fall arrestor 5. Safety glasses for dust protection (Lightweight safety glasses with side shield to protect against

wind & ultraviolet ray with adjustable side arms for personalized fit). 6. (i) Ear muff conforming IS:6229 (ii) Ear plug or Ear seal Unique closed cell polyester from smooth tapered surface similar to ear canal swells slowly to fit individual Ear canal. (Any one item out of three types of ear protection device should be issued) 7. Flame-Water-Oil-Acids & alkali resistant work wear (made of 100% cotton fabric) 8. Safety gloves of Kevlar or equivalent (high temp. resistance) 9. Face shield (conforming IS: 8521 part I type-I) 10. Electrical hand gloves 440v & 33 KV conforming IS: 4770 11. Hand gloves for chemical laboratory made from pure latex Acid and Alkali proof 12. Hand gloves for concentrated chemicals made from superior PVC inside cotton reinforce for better grip 13. Split chrome leather hand gloves for handling rough object. 14. Canvas hand gloves for handling smooth object & doing light work with it. 15. Flip up goggles with stationery frame fitted with ophthalmic grade zero power toughened lens and

fitting frame, Blue lens for furnace, Green shade No.4 for gas cutting, dark green No.11 for glasses for ARC welding whenever is required.

16. Panoramic type safety goggles for acid & alkali whenever is required. Vendor shall ensure proper use of personal protective equipment by their workmen and supervisor on duty.

Before issue of the above PPEs depending on the need of the area of work the sample of the same must be provided to Owner Safety Officer for inspection & approval. The Vendor shall be issued entry pass for their employees after due verification of the quality of the standard PPEs and imparting necessary training well in advance (i.e. before 7 days of commencement of work) by Project Manager / Safety Officer. a) None of the Vendor’s employees shall be allowed inside the plant premises without valid gate pass,

safety shoes, helmet & safety glasses. b) Vendor shall ensure that all his employees use proper PPEs inside the plant premises as per the

work & site requirement. c) During the course of execution of the work the Vendor must ensure use of appropriate tested tools

by their workmen. Safe working practice must strictly be followed, e.g. use of proper plug & socket for electrical connections, right size & standard spanner, right capacity and tested lifting & pulling equipment etc.

d) The Vendor must ensure tidiness of the work place during & after completion of the work. e) In case of any doubt relating to safety guidelines, the Vendor should seek advice of Project

Manager / Safety Officer immediately for clarification.

Page 71: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 71 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

f) The Vendor must provide adequate first aid boxes at different locations and maintain a register to this effect.

g) The Vendor should follow proper firefighting procedure while executing the work. h) The Vendor must provide proper barricades for excavations & other hazardous areas with proper

marking even during night time. i) The Vendor should use proper & safe scaffoldings wherever required. j) The Vendor should take utmost care & precaution while handling inflammable gases, compressed

gases & explosives. k) The Vendor should use proper fall protection equipment while working at height and guard the

bottom area. l) The Vendor should not use any metallic ladders inside ITPS premises. m) The Vendor should use proper electrical & lifting tools having periodic testing. n) The Vendor should follow Owner policy for PTW, Hot work permit & confined space. Before

starting any work the Vendor should obtain the required clearance from the concerned authority. o) The Vendor should follow all safety standards, codes, rules, regulations & acts as in force. p) The Vendor must engage only experienced and qualified manpower to prevent any safety lapses

during execution of the work. ANY DEFICIENCY IN SAFETY ASPECTS SHALL BE VIEWED SERIOUSLY BY OWNER. THE VENDOR WILL BE PENALISED UP TO THE EXTENT OF Rs.10, 000/- (RUPEES TEN THOUSAND ONLY) PER EACH LAPSE AS DETERMINED BY THE PROJECT MANAGER. OWNER RESERVES THE RIGHT TO TERMINATE THE AGREEMENT AND DEBAR THE VENDOR TO PARTICIPATE ANY FUTURE BIDDING IN CASE OF CONTINUED FLOUTING OF THE SAFETY NORMS PRESCRIBED BY OWNER.

Page 72: SAP DMSat OPGC.” · Version: 01 Confidential Odisha Power Generation Corporation Limited Page 2 of 72 Roll out of SAP Application and Implementation of DMS at OPGC

Version: 01  Confidential  Odisha Power Generation Corporation Limited  Page 72 of 72

       

Roll out of SAP Application and Implementation of DMS at OPGC. 

Bidders shall strictly follow OPGC EHS Policy guidelines. The spirit of the EHS Policy shall be

reflected during the course of contract execution by implementing minimum EHS expectation of