SAP Utility Overview Innovate with the Power of SAP
2CONFIDENTIAL© 2018 SAP SE or an SAP affiliate company. All rights reserved. ǀ
SAP Customers – Power Utility
Key Highlights▪ Global Leader for last 12 years as per Gartner Magic Quadrant for Utility Solutions.
▪ All Major Power Generation Companies Run on SAP – NTPC, Maha Genco, AP Genco, TS
Genco, WBPDCL, Tata Power, Adani Power ….35 Plus Customers in Power Generation
▪ Major Transmission Companies Run on SAP - PGCIL, MahaTransco, AP Transco, TS
Transco, Rajasthan Transco, WBSETCL, DTL, HP Transco…
▪ Major Discoms Run SAP ER and CIS Solution – WBSEDCL, CSPDCL, PSPCL, Ap Discoms,
TS Discom, HPSEB, JSEB, GED, MSEDCL, TPDDL, BSES, Torrent Power, Reliance Infra ….
▪ More than 60 Million Power Billing Generated from SAP solution every month.
Andhra
Pradesh
AssamNagaland
Manipur
MizoramTripura
MeghalayaBihar
Chhattisgarh
Haryana
Goa
Delhi
Himachal
Pradesh
Maharashtra
Odisha
Rajasthan
Punjab
Telangana
Uttarakhand
West
Bengal
Sikkim
Arunachal
Pradesh
50 # of Public Utility
(Power) On SAP 60 Million Power
Bills from SAP 15+ Power Discoms using
SAP ERP in India
3CONFIDENTIAL© 2018 SAP SE or an SAP affiliate company. All rights reserved. ǀ
Few Customer Reference
Power Distribution Utility Customers in India (Implemented SAP ERP)
Public Utility Private Utility
4CONFIDENTIAL© 2018 SAP SE or an SAP affiliate company. All rights reserved. ǀ
What Is Enterprise Resource Planning – 1 of 3
Power
Procurement to
Settlement
Meter to CashConsumer to
Utility
Asset
Erection to
Maintenance
Procure to Pay Hire to Retire
Finance & Accounting Human Resource Mgmt. Procurement Project Management Stores Mgmt. Customer ManagementAsset Mgmt.
Transformer/Sub Station SCADA/DMS Energy Meter PD/Spot Billing M/C Tools Customer, VendorCustomer Care
Corporate Office Division Office Section Office
5CONFIDENTIAL© 2018 SAP SE or an SAP affiliate company. All rights reserved. ǀ
What Is Enterprise Resource Planning – 2 of 3
Power
Procurement to
Settlement
Meter to CashConsumer to
Utility
Asset
Erection to
Maintenance
Procure to Pay Hire to Retire
Finance & Accounting
Asset Mgmt.
Corporate Office
Human Resource
Mgmt.
Section Office
Customer, Vendor
Project Mgmt.
Procurement
Stores Mgmt.
Transformer / Sub Station
Tools
DB/Manual
Division Office
6CONFIDENTIAL© 2018 SAP SE or an SAP affiliate company. All rights reserved. ǀ
What Is Enterprise Resource Planning – 3 of 3
Power
Procurement to
Settlement
Meter to CashConsumer to
Utility
Asset
Erection to
Maintenance
Procure to Pay Hire to Retire
Finance & Accounting
Corporate Office
Human Resource
Mgmt.
Section Office
Customer, Vendor
Project Mgmt.
Procurement
Stores Mgmt.
Transformer / Sub Station
Tools
DB/Manual
Division Office
Transformer/
Substation
SCADA/
DMS
Energy
Meter
PD/ Spot
billing M/C Tools
Customer
Care
Customer,
Vendor
Finance &
Accounting
Human
Resource Mgmt
Procurement Stores Mgmt Asset Mgmt
7CONFIDENTIAL© 2018 SAP SE or an SAP affiliate company. All rights reserved. ǀ
Typical Scope of ERP @ Power Distribution Utility
HR Projects MISFinancials Purchasing & Inventory
▪ Employee File
▪ Time Management
▪ Training, skills mapping
▪ Performance Management
▪ Court cases, Grievances
▪ Employee services, Pension,
LTC
▪ Project Planning
▪ Cost Estimates
▪ Project Execution
▪ Monitoring
▪ Vendor Collaboration
▪ Capitalization, Accounting
▪ Business Intelligence
▪ Dashboards
▪ Integration with legacy
applications
▪ General Ledgers
▪ Accounts Payable,
Receivable
▪ Assets Accounting, FAR
▪ Budgets, Controls,
Investments
▪ Payroll, Claims,
Reimbursements
▪ Financial Statements
▪ Masters, Indents, Enquiries
▪ Quotations, E-tendering
▪ Orders, Contracts, Receipts,
Bills passing
▪ Quality, Scrap Disposal
▪ Stores, Transfers, Issues
▪ Vendor Rating, Material
Planning
8CONFIDENTIAL© 2018 SAP SE or an SAP affiliate company. All rights reserved. ǀ
Benefits
Value Drivers for Selected Areas Benefits SAP Customer Success Proof Points
Project Management
▪ Reduction in project monitoring costs through employee efficiency improvements
▪ Reduction in cost of delays for projects vulnerable to be delayed and exceed
budgets
▪ Energen Utility: Time required for project approval reduced from
2 – 4 weeks to a few hours
▪ Shanghai Electric: 100% improvement in reduction of % of capital projects
exceeding budget. 80% reduction in time to generate project reports
Sourcing, Procurement and Inventory Management
▪ Reduction in procurement spend due to optimized spend on stores, spares and
consumables procured
▪ Reduction in materials, tools and fuel inventory
▪ 5 – 10% improvement in safety stock due to reduction in procurement lead times
▪ Energen Utility: Improvement in PO efficiency by around 50% – 70%
▪ Energy East: Decreased procurement spend by 4 – 6% or $20 – 30 M annually.
Procurement employee productivity improvement by 40% – 50%. Inventory
reduction by 33% resulting in $13 M capital reduction
▪ Shanghai Electric Power: Improved inventory turnover from 2.2 to 4.0
Asset Management and Plant Maintenance
▪ Reduction in maintenance expenses
▪ Reduction in administrative and waiting time during maintenance
▪ Energen Electric Utility: Reduced maintenance cost for mission critical items by
50%; Reduced storeroom costs by 50%
▪ Conectiv Energy: 10–20% reduction in emergency & urgent work orders
Business Support in Finance and Accounting
▪ Improvement in productivity of finance FTEs
▪ Improvement in budgeting, planning & forecasting
▪ Energy East: Finance FTE productivity improvement of 50%
▪ Energen Utility: Reduced financial close cycle by 3 days. Reduced number of
accounting full time equivalents by 5%
Business Support in Human Resource Management
▪ Improvement in productivity due to ESS & MSS
▪ Improvement in productivity of HR employees due to elimination of manual work
▪ Energen Utility: Reduction in number of payroll full time employees by 25%. Ability
to fulfill reporting request improved by 30% – 40%
3%
3%
20%
10%
10%
20%
20%
5%
15%
10%
10%
5%
5%
30%
20%
15%
25%
30%
10%
25%
15%
20%
Note: Analysis is directional in nature; Access to specific data will be required to develop more accurate estimates
9CONFIDENTIAL© 2018 SAP SE or an SAP affiliate company. All rights reserved. ǀ
Digital Energy Network – Utility Value Map
Utility Specific
Core ERP
User Access
Analytics
Energy Supply Chain
Optimization
Fuel Supply Chain Management
Load Forecasting
Operational Excellence
Predictive Maintenance
Asset Operation and Maintenance
Environment health and Safety
Intelligent Grid
Grid Infrastructure Analytics
Mobility
IT-OT Integration
Consumer Excellence
Metering / Billing / Collection
Smart metering / TOU Billing
Pre-Paid Metering
Call Center
Customer Self-Service (mobile app)
Customer Energy Analysis
Energy Management
Energy Theft Detection
Demand side Management
Energy Audit
Recovery Management
Real time Analytics
Field Force Automation
Onsite Billing
Fiori based User Interface / Mobile Access
Project System
Financial & Management Acctg
HCM
Procurement Inventory Management
Payroll
Quality Management
Employee Self service
Plant Maintenance
Others +++
10CONFIDENTIAL© 2018 SAP SE or an SAP affiliate company. All rights reserved. ǀ
SAP Contact Center
Next Gen Billing Engine & CRM
Customer
SAP Customer Relationship Management for Utilities
Customer 360 Degree View
Interaction CenterNew Connection
ProcessesCustomer Service
ProcessesOn Spot resolution
Marketing Management
Call Routing IVRS
Multi Channel
Foundation
for Utilities
Consumer Website
and Mobile app
Metering and Device Management Billing and Invoice Collection and Accounting
Technical Data
Management
Installation, Removal,
Replacement
Meter Reading and validations
Device Inspection
Energy Audit
Energy theft Management
Tariff ManagementBilling, Invoicing and Validations
Spot Billing Retrospective
Billing
Pre Paid Metering TOU Billing
Receivable management
Collection, Prompt payment incentive
Dunning and Interest
Reconciliation and Closing
Recovery Management
Payment Gateway integration
Enterprise Mobility
Syclo Work Manager Mobile Platform
Enterprise Analytics
S/4 HANA embedded Analytics
Business Objects reporting / Predictive Analytics
11CONFIDENTIAL© 2018 SAP SE or an SAP affiliate company. All rights reserved. ǀ
Integrated Utility - IT Road Map
Back End Process(Finance, Controlling,
Procurement, Inventory,
Projects, HR, Payroll, ESS)
Asset
Consumer
Legacy Application
COTS MBC
SCADA, GIS
CRM, Call Ctr, Portal
ADMS
Cons App, Big Data Analytics
Smart Metering,
Load Forecasting,
Field Force Automation
Predictive Maintenance
Manual Process
Basics COTS EAM
IoT - Asset Health Monitoring,
Asset Information Network
Treasury, GRC, Fuel Supply
Chain Mgmnt.
Manual Process
ERP
In Memory DB, OLAP + OLTP,
Cockpit, Embedded Analytics
Digitalization - P2P,
H2R, O2C
IT M
atu
rity
Timelines
NTPC - Success Story –Learnings from Large Project Implementation
13CONFIDENTIAL© 2018 SAP SE or an SAP affiliate company. All rights reserved. ǀ
‘One NTPC’: Current IT Landscape
Dreams
Claims &
ReimbursementPayroll Roaster
Loan
ManagementTaxation LTC
India Localization
SAP Supplier Relationship Management (E-Tendering / Reverse Auction)
The SAP ERP Packaged Solution for Utilities
SAP XI/NetWeaver Technology
Business Planning and Simulation
SAP Enterprise Portal SAP Business Warehouse
Standardized Processes Across All Locations
Quality
Management
Sales
Management
Human
Resources
Financials &
Controls
Project
Systems
Material
Management
Corporate
Finance Mgmt.
Plant
Maintenance
SAP Modules Localized for
India specific requirementsSAP Modules currently in use Non SAP
Corporate
Project –Site
Subcontractors
Location 1 Location 2 Location 3 Supplier Supplier Supplier
Customers
Harmonized Master Data
14CONFIDENTIAL© 2018 SAP SE or an SAP affiliate company. All rights reserved. ǀ
The Genesis of Project ‘Lakshya’ @ NTPC
Select the right IT
PartnerPilot Implementation Complete Roll Outs
Define the Business
Strategy
Develop a Supporting IT
Strategy
▪ Evaluate and award the
contract to the best ERP
solution provider
▪ Selected SAP as the IT
platform for NTPC
▪ Awarded the contract to SAP
Consulting & SISL to
implement the project
▪ Implemented the whole suite
of SAP applications across 5
locations
▪ First pilot projects live in 10
months
▪ Rolled out the application to
across the rest of the 25
locations
▪ Organisation restructuring
and business process
reengineering
– Long term business
strategy
– HR Strategy
– IT strategy
▪ Define the IT
strategy/roadmap and select
the right approach
– Home grown
– Best of breed
– Standard off-the shelf
application
Roll Out Completion
Aug 2008
Project Start
May 2006
Pilot Go Live
June 2007
Given the large scale of NTPC’s operations and the complexity of our structure, we wanted to implement a business software
solution that would establish uniform business processes, better decision support and better control over operations.
Mr. T Sankaralingam, Then Chairman and Managing Director, NTPC“”
15CONFIDENTIAL© 2018 SAP SE or an SAP affiliate company. All rights reserved. ǀ
All Locations Are Successfully Live
S.No Location Actual Go live Date S.No Location Actual Go live Date
1 Faridabad Jun-07
Project
L A K S H Y A
16 Vindhyachal Dec-07
2 Ramagundam Jun-07 17 Korba Feb-08
3 Koldam Jul-07 18 Lucknow RO Feb-08
4 NCR & Engg Jul-07 19 Rihand May-08
5 Corp HQ Aug-07 20 Sipat May-08
6 Hyderabad Aug-07 21 Unchahar May-08
7 Subs. Aug-07 22 Badarpur Jun-08
8 Anta Sep-07 23 Barh Jun-08
9 Gandhar Sep-07 24 Dadri Jun-08
10 Mumbai RO Sep-07 25 Farakka Jul-08
11 Kawas Nov-07 26 Talcher 1 Jul-08
12 Kayamkulam Nov-07 27 Talcher 2 Jul-08
13 Patna RO Nov-07 28 Tanda Jul-08
14 Auraiya Dec-07 29 Kahalgoan Aug-08
15 Simhadri Dec-07 30 Singrauli Aug-08
16CONFIDENTIAL© 2018 SAP SE or an SAP affiliate company. All rights reserved. ǀ
Project Lakshya: Major Achievements
1
2
3
End to end mapping of all the business process from
Concept to Commissioning stage of a typical Power
Station, using various SAP functionality
Introduction of internal and external (vendor)
Collaboration for various Engineering and non-
engineering activities
Creation and standardization of Engineering
knowledge-base and introduction of
“Building block” concept for re-use of design & shorter
project development time
4
5
6
Implementation of “Fuel management” functionality to
meet the business requirement of capturing, tracking
and handling of data relating to fuel company as well
as the Railways
Energy Billing as per Availability Based Tariff in IS-U
Implementation of ‘Works Bill Processing”
7
8
9
Centralized Payroll and employee self service for all
the 25000 employees across diverse locations
Visible and immediate benefits from e-tendering and
reverse auctions enabled by the SRM platform
NTPC specific enhancements along with work-flows
in Claims and reimbursements, Leave travel
concession (LTC), Loan application
17CONFIDENTIAL© 2018 SAP SE or an SAP affiliate company. All rights reserved. ǀ
Recognition For Being The Best Run Business
SAP Awards for Customer Excellence for Best-Run Companies
2007 2008
18CONFIDENTIAL© 2018 SAP SE or an SAP affiliate company. All rights reserved. ǀ
Critical Success Factors @ NTPC
▪ Customer Competence Centre
▪ Communication
▪ Change Management
▪ Sustained Organization Attention
▪ Manage risk of Business Exposure
▪ Project Planning & Monitoring
▪ Resources
▪ Standardization of Processes at Locations
▪ Site Readiness
▪ End user training
▪ Data Management
19CONFIDENTIAL© 2018 SAP SE or an SAP affiliate company. All rights reserved. ǀ
Involvement of Top Management: A Key Success Factor
Event Activity Management Participation
Project Kick Off OCM Workshop CMD & Directors
PP Phase Organization Climate Assessment CMD, Directors, Functional Heads
BBP Phase Org Structure Mapping In SAP Directors & Functional Heads
BBP Phase Process Walk Through Directors & Functional Heads
ALL Phases SCM Once In 4 Week Directors & Functional Heads
Closure of BBP & RP Management Committee CMD, Directors, Functional Heads
Closure of RP High Level UAT Functional Heads
RP Phase Cut Over Strategy Review Functional Heads & GM of Go Live Location
PGLS Phase Review Go Live Location Progress Directors
20CONFIDENTIAL© 2018 SAP SE or an SAP affiliate company. All rights reserved. ǀ
Pre Preparation Activities @ NTPC
▪ Fully Functional ERP Team (Functional & Technical)
▪ Visit Key Customers
▪ Initiated Master Data Collection Work – Separate Tender
▪ Initiated Core Team formation Work
▪ Setup ERP Office
▪ Procure Hardware (Development Environment)
▪ Initiated Change Management Activities
▪ Conduct Overview Sessions
– STA’s
– Power Users
– Change Agent
– Pilot Locations
▪ Create As Is documents
▪ Discussion – Single or Multiple Co Code, S Loc stock ……..
21CONFIDENTIAL© 2018 SAP SE or an SAP affiliate company. All rights reserved. ǀ
Learning's @ NTPC
▪ TTT Model of Training didn't worked
▪ Scope Definition
▪ Synchronization of Solution Design & Data Requirement
▪ Prioritization of Solution Roll out really helped
▪ Monitoring of Project by CMG helped
▪ Avoid conflict of responsibility for Data (Multiple Vendors)
▪ Regular Project Review by separate team
▪ Create Location Champions
▪ Add-on Modules usability
▪ Data Collection for Work Flow
▪ Changes in Policy / Process
▪ Big Bang Approach
▪ Create Pilot Success Story
22CONFIDENTIAL© 2018 SAP SE or an SAP affiliate company. All rights reserved. ǀ
What UPPCL Should do @ this stage
▪ Formation of Core Team (Team Leads)
▪ Visit few Successful Implementations
▪ Identify Full Core Team
▪ Master Data Collection Work
▪ Initiate OCM activity
▪ Office Setup
▪ Infrastructure Requirements
▪ Development Server (If not part of Tender)
▪ High Level As Is Document
▪ Identify Existing Pain Points
▪ Organization KPI assessment WS
▪ High level process list (Detailing in BBP Phase)
▪ Set up PMO
▪ Conduct ERP Awareness WS
▪ Project Name, Newsletter, Internal Communication
23CONFIDENTIAL© 2018 SAP SE or an SAP affiliate company. All rights reserved. ǀ
Process
Owners
Project Team – Skilled & Full Time
Project Team Structure
Project Sponsor
Steering Committee
Program Manager
Project Manager - UPPCL
Team LeadTraining
Manager
Integration
Manager
Program & Project Mgr
Team LeadTechnical
TeamBasis Lead
Team
Members
Team
Members
Process
Owners Nominee
Power Users
Change Management Team
24CONFIDENTIAL© 2018 SAP SE or an SAP affiliate company. All rights reserved. ǀ
Project Team Requirements
Finance HRMaterial
MgmntMaintenance Projects
Technical
TeamPMO
1 Team Lead
1 GL
2 Accounts Payable
1 Accounts Receivables
1 Budgeting
1 Controlling
1 Tax and Commercials
1 Team Lead
1 Organization
Management
1 Personal Management
2 Payroll
1 ESS
1 Training & Recruitment
Part-time PMS
1 Team Lead
2 Corporate Contracts
including eTendering
1 O&M Contracts
2 Inventory and Service
Management
1 Team Lead
3 Team Members
▪ Preventive Maint
▪ Break Down Maint
▪ Tech Objects
▪ Condition Based
Maint
▪ Permits
▪ Predictive Maint
1 Team Lead
2 Project Planning,
Monitoring and Execution
2 Design and Engineering
1 Quality and Inspections
1 Team Lead Basis
1 Team Lead ABAP and
BI
5 Team Members Basis
15 Team Members
ABAP and BI
1 Program Manager
1 Project Manager
1 Integration Manager
3 PMO Office
59Total Team Size
8 7 6 4 6 22 6
25CONFIDENTIAL© 2018 SAP SE or an SAP affiliate company. All rights reserved. ǀ
ASAP Methodology Overview
1 2 3 4 5
▪ Project organization and
standards
▪ Prepare project charter
▪ Initial project planning
▪ Level 1 training for project
team and Process Owners
▪ Technical requirements
planning
▪ Prepare executive kickoff
meeting
▪ Customer requirements
gathering in interviews
▪ Questionnaires and
models assist to create
the Business Blueprint
▪ Level 2 training
▪ System installation
▪ Management review of
Business Blueprint
▪ Baseline Configuration
▪ Final Configuration/
Integration Test
▪ Design, develop and test
interfaces, reports,
and conversions
▪ Go-live plan
▪ End-user training
▪ Integration, volume and
stress testing
▪ Establish internal help desk
▪ Data migration
▪ Cut-over to productive
environment
▪ Application support
▪ Verify accuracy of
productive system
▪ Measurement of
business benefits
Project Preparation Business Blueprint Realization Final Preparation Go Live & Support
Continuous change
26CONFIDENTIAL© 2018 SAP SE or an SAP affiliate company. All rights reserved. ǀ
Phase Wise Activities for Core Team
Realization Final Preparation Post Go Live SupportPreparation Business Blueprint
▪ Basic Configuration and Unit
Testing
▪ Integration Scenario
preparation
▪ Testing of critical
Developments
▪ Testing of Upload and Data
Migration program
▪ Data Migration Workshops
▪ Authorization data collection
▪ Integration Testing
▪ Issue Resolution and closure
▪ Set up Production
Environment
▪ EUT Content Finalization
▪ Project Review and
Monitoring
▪ Coordinate for EUT
▪ Data Collection and
Validations
▪ Preparation for Cut Over
▪ Authorization Profile creation
and Allocation
▪ EUT for all Users
▪ Move Requests to PRD and
testing in Pre Production
▪ Infrastructure Readiness
▪ Documentation
▪ Help Desk Plan
▪ Project Review and
Monitoring
▪ Operationalize Help Desk
▪ Monitoring and Early Watch
▪ Handholding
▪ Issue Resolution
▪ Enhanced Training Program
▪ Create Roll Out Template
▪ Project Review and
Monitoring
▪ Team Identification
▪ Core Team Training
▪ Infrastructure Planning
▪ First Level Project Plan
▪ Project Charter
▪ Define Process List
▪ KPI Assessment
▪ Project Review and
Monitoring
▪ Explain As Is Process
▪ Evolve Org Structure in SAP
▪ Discuss and Evolve To Be
Process
▪ Process wise Integration
Meeting
▪ Authorization Control
discussion
▪ Review Development Plan
▪ Set Up Development and
QAS system
▪ Discussion around Data
Migration
▪ Project Review and
Monitoring
27CONFIDENTIAL© 2018 SAP SE or an SAP affiliate company. All rights reserved. ǀ
Core Team Training PlanWeek Date Day Room 1 | Capacity 12 Room 2 | Capacity 12 Room 3 | Capacity 12 Room 4 | Capacity 12 Room 5 | Capacity 12
1 12-Jun-06 M
Financial Accounting
Training
FI Academy (TFIN10)
- Week 1
Plant Maintenance
Training
PM Academy (PLM300,
PLM305) - Week 1
Project System
Training
PS Academy (PLM200,
PLM210) - Week 1
Basis Administration
Training
Basis Academy
(TADM10...)
Week 1
13-Jun-06 T
14-Jun-06 W
15-Jun-06 Th
16-Jun-06 F
2 19-Jun-06 M
I Academy (TFIN10 2
days, AC305 3 days)
- Week 2
PM Academy (PLM310,
PLM315) - Week 2
PS Academy (PLM220,
PLM240) - Week 2
Basis Academy
(...TADM10 2 days,
TADM12… 3 days)
Week 2
20-Jun-06 T
21-Jun-06 W
22-Jun-06 Th
23-Jun-06 F
3 26-Jun-06 MFI Academy (IPS910 3
days) - Week 3PM Academy (PLM316,
PLM320) - Week 3PS Academy (PLM230,
PLM235) - Week 3
Basis Academy
(...TADM12 4 days,
TADM52.. 1 days)
Week 3
27-Jun-06 T
28-Jun-06 W
29-Jun-06 Th
Management Accounting
Training
CO Academy
(TFIN12...) - Week 130-Jun-06 F
4 03-Jul-06 MCO Academy
(...TFIN12 3 days,
TFIN30... 2 day)
- Week 2
Materials
Management - Batch
1 Training
MM Academy
(TSCM50...) - Week 1
Production Planning
Training
PP Academy
(TSCM20) - Week 1IS-U Training
IS-U Academy (IUT110
- 3 days, IUT210 2
days)
04-Jul-06 T
05-Jul-06 W
06-Jul-06 Th
07-Jul-06 F
5 10-Jul-06 MCO Academy
(...TFIN30 - 4 days)
- Week 3
MM Academy
(...TSM50 2 days,
TSCM52... - 3 days)
- Week 2
PP Academy
(TSCM20, TSCM32)
- Week 2
HR Training
HCM Academy
(SAPHR, HR100,
HR110) - Week 1
IS-U Academy (IUT225
- 2 days)11-Jul-06 T
12-Jul-06 W
EHS Training
EHS Academy (EH202
2 days; EH102A 1 day)
- Week 1
13-Jul-06 Th
14-Jul-06 F
6 17-Jul-06 M
Investment Mgmt Training
IM Academy (AC020 2
days, AC040... 3 days)
- Week 1
MM Academy
(...TSCM52... - 4 days)
- Week 3LDM Training
LDM Academy
(PLM100, PLM110)
- Week 1
HCM Academy
(HR305, HR400)
- Week 2
EHS Academy (EH502-
2 days; EH602 - 2
days; EH602A 1 day)
- Week 2
18-Jul-06 T
19-Jul-06 W
20-Jul-06 Th
21-Jul-06 F
7 24-Jul-06 MIM Academy (AC350...
3 days) - Week 2
Sales & Distribution
Training
SD Academy
(TSCM60)
- Week 1
LDM Academy
(PLM112, PLM120)
- Week 2
SRM Training
SRM Academy
(TSRM10)
Week 1
25-Jul-06 T
26-Jul-06 W
27-Jul-06 Th
28-Jul-06 F
8 31-Jul-06 M
Quality Management
Training
QM Academy
(PLM400, PLM405)
- Week 1
SD Academy
(TSCM62)
- Week 2
LDM Academy
(PLM150) - Week 2
CFM Training
CFM Academy (FS100,
FS110)
- Week 1
01-Aug-06 T
02-Aug-06 W
Sol. Mgr Solution Manager /
ASAP methodology
Training - SMI210 -
Track 1
03-Aug-06 Th
04-Aug-06 F
9 07-Aug-06 M
QM Academy
(PLM410, PLM415,
LO750) - Week 2
Sol. MgrCFM Academy (FS111,
FS112)
- Week 2
08-Aug-06 T
09-Aug-06 W
Sol. Mgr
Solution Manager /
ASAP methodology
Training - SMI210 -
Track 1
10-Aug-06 Th
11-Aug-06 F
APDISCOMs – Journey to Business
Excellence with SAP ERP
Reaching Levels of Business Excellence
with Project ASCEND
29CONFIDENTIAL© 2018 SAP SE or an SAP affiliate company. All rights reserved. ǀ
The Genesis of Project ‘ASCEND’
Select the right IT Partner
▪ Evaluate and award the contract to
the best ERP solution provider
▪ Selected SAP as the IT platform
Roll Out
▪ Rolled out the application across all
the four DISCOMs
Define the Business Strategy
▪ Business process reengineering
▪ Long term business strategy
▪ IT strategy
Develop a Supporting IT
Strategy
▪ Define the IT strategy/roadmap and
select the right approach
– Home grown
– Best of breed
– Standard off-the shelf application
Project Start
April 2009
Project Go Live
April/May 2010
10 April 2009
Project Kicked off
5 April 2010
Go Live APCPDCL, APNPDCL and APEPDCL
5 May 2010
Go Live at APSPDCL
30CONFIDENTIAL© 2018 SAP SE or an SAP affiliate company. All rights reserved. ǀ
ASCEND: SAP Solution ImplementedPhase 1
▪ Financials and Controlling
▪ Funds Management
▪ Investment Management
▪ Procurement &Logistics
▪ Plant Maintenance
▪ Project System
▪ HR & Payroll
▪ BW – Analytics & Reports
▪ Enterprise portal – ESS
▪ Governance Risk & Compliance (GRC) – Access Control
31CONFIDENTIAL© 2018 SAP SE or an SAP affiliate company. All rights reserved. ǀ
Business Value Unlocked – Key Benefits Achieved (1/3)
Area of Business Benefits Achieved
Finance and Accounting
▪ Improved financial accounting, which would translate into efficient financial book closure
▪ Seamless reconciliation and improved accounting efficiency
▪ Automation of Letter of Credit and Letter of Advice process for payments from Circle and Division
levels. This reduced manual efforts, reconciliation, faster process and tighter controls and more
transparency
▪ Access to up-to-date cost records
▪ System-enforced consistency in adherence to policies/ std. procedures across all locations
Human Resource
▪ Improved employee satisfaction due to automation of key HR processes
▪ Creation of centralized employee skill database
▪ Use of Roster Functionality to monitor reservation policies at sub category levels
▪ Reduction in manual efforts around the areas of employee data management, expense management
and claims management
32CONFIDENTIAL© 2018 SAP SE or an SAP affiliate company. All rights reserved. ǀ
Business Value Unlocked – Key Benefits Achieved (2/3)
Area of Business Benefits Achieved
Procurement
▪ Automatic annual R&M cost requirement consolidation at Division and Circle
▪ Stock visibility up to sub division level
▪ Tendering process with system generated automated price comparison reports
▪ Automatic Tax calculations based on Tax codes.
▪ End to end Sub contracting process for Pole manufacturing
▪ Integration with maintenance and projects for initiating RFQs directly from WBS or maintenance
orders
Power Procurement
(APPCC)
▪ The process of power purchase from APTRANSCO, and inter DISCOM power purchase and related
transactions are now maintained in SAP leading to reduction in manual and error prone processes
▪ DISCOM wise trial balance of power procurement can be directly downloaded from the SAP system,
which is used in reconciliation meeting with APTRANSCO. This has improved the process of
reconciliation, reduced disputes with APTRANSC and reduced preparation work for the reconciliation
meetings
33CONFIDENTIAL© 2018 SAP SE or an SAP affiliate company. All rights reserved. ǀ
Business Value Unlocked – Key Benefits Achieved (3/3)
Area of Business Benefits Achieved
Enterprise Asset
Management/ Plant
Maintenance
▪ 100% cost booking for manpower and materials during maintenance works resulting in generation of
equipment wise cost history
▪ Reduced efforts in creating indent for spares and consumables. Maintenance executives take 5 – 10
mins to create the indents
▪ Financial vetting of indents take few minutes against earlier case of days and weeks
▪ Complete visibility into asset maintenance history and spare parts movement
▪ Reduced efforts in managing preventive maintenance schedules
▪ Improved work permit process flow with permits getting directly printed through the system
Projects
▪ Multiple level of workflow based approvals for project estimates
▪ Ability to undertake estimation and re-estimation for project works by circle and division level reducing
the overall process duration for such work from an average of 10 days to 1 day
▪ Improved transparency and control in project estimation and budgeting
▪ Integration of project systems with procurement resulted in automatic generation of indents against
WBS leading to substantial reduction in manual efforts
▪ Effective monitoring of projects during execution through automated reports around plan vs. actual
physical progress and cost incurred
34CONFIDENTIAL© 2018 SAP SE or an SAP affiliate company. All rights reserved. ǀ
ASCEND: Project Challenges
Project Challenges
▪ Geographically Dispersed Team locations
▪ Satisfied all the requirements of all 4 DISCOMS
▪ Availability of Core team is a big Challenge
▪ Unavailability of a formal PMO
What went Well
▪ Senior Management Commitment and Support.
▪ Proactive and Excellent Support from Core
team during Data Migration.
35CONFIDENTIAL© 2018 SAP SE or an SAP affiliate company. All rights reserved. ǀ
Facts About APDISCOMs (Central, Eastern, Southern and Northern) – PS
Work Orders
DetailsAPCPDCL (Central
DISCOM)
APEPDCL (Eastern
DISCOM)
APSPDCL (Southern
DISCOM)
APNPDCL (Northern
DISCOM)
No. Of Work Orders
Uploaded.35,890 36,318 31,957 12,292
New Work Orders Created in
ECC 6.020,109 8,742 5,640 5,758
No of Work Orders under
Execution40,879 35,740 36930 14,417