scaffolding safety (erecting and dismantling)
TRANSCRIPT
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
1/55
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
2/55
ScafoldingSaetyErecting & Dismantling
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
3/55
Introduction
As a person who erects and dismantles scaffolding, your
safety - and the safety of those who will work on the
scaffold - depends on your ability to closely follow theminimum safety requirements for constructing and using
scaffolds.
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
4/55
Introduction
The scaffold system you erect will support many workers
and allow them to carry out their ob functions. !ow well
you follow proper procedures and safe work practiceswhile erecting scaffolds will ha"e a direct affect on their
safety. #f you ha"e any questions about erecting or
dismantling scaffolding, ask your super"isor.
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
5/55
Pre-planning
#t is important that thorough pre-planning takes place
before scaffolding is erected. This should include$
% Evaluation and Preparation of the Site
% Identification of Any Potential Hazards
% Determining the Type of Scaffolding to be Used
% Activities to be Performed and their eight !e"uirements
% eight #apacity of the Scaffold
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
6/55
Pre-planning
Evaluating the Site
hile e"aluating the site there are many factors to
consider. There may be a number of steps you willneed to take to prepare the site.
Some items to chec$ could include%
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
7/55
Pre-planning
% Is the surface level and sound&
% #an the ground support the scaffold unit&
% Are there any unguarded openings or potential
underground utility 'or$ that may affect the stability of
the scaffold&
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
8/55
% Are there any nearby electrical po'er lines&
% If so( can the scaffold be erected 'hile $eeping aminimum safe approach distance from the lines&
% #an 'or$ be performed on the scaffold 'hile
maintaining a minimum safe approach distance from the
electrical po'er lines&
're-planning
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
9/55
Pre-planning
% hat type of pedestrian( vehicular( or e"uipment traffic
'ill be in the area&
% hat type of fall protection 'ill be feasible&
% ill safe access 'hile erecting and dismantling the
scaffold be feasible&
% ill conditions such as high 'inds( storms( or icy
conditions e)ist&
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
10/55
Scafolding Inspection
To make sure scaffold components are in good
working order, carefully inspect all scaffolding partsbefore and during its erection. A defecti"e or
damaged part could affect the integrity of the whole
scaffold.
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
11/55
Scafolding Inspection
Items to #hec$
% Are plan$s and 'ood components free of splits( rot( burns(
'arps( splintering( oil( or paint and opa"ue finishes that
could cover potential defects*
% Are 'ood plan$s scaffold grade&
% Are 'elds and bolted connections in good condition*
(ome areas to inspect include the following$
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
12/55
Scafolding Inspection
#AUTI+,-
% Any defective parts must not be used*
% Any damaged or 'ea$ened scaffold part must be
immediately repaired or removed from service until it is
repaired*
% ,ever ris$ your safety by using damaged parts*
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
13/55
Load Capacity
The load capacity of a scaffold "aries, depending on its
design and application. )eneral capacity requirementsfor all scaffolds include$
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
14/55
% The scaffold and each scaffold component must be capable
of supporting four times the ma)imum intended load* This
includes all personnel( e"uipment( and supplies*
% Direct connections and counter'eights used to balance
ad.ustable suspension scaffolds must be able to resist at
least four times the tipping moment of the scaffold(
including stall loads*
*oad +apacity
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
15/55
Load Capacity
% All suspension ropes and connecting hard'are must be
capable of supporting at least si) times the ma)imum
intended load*
% Scaffolds must be designed by a "ualified person( and
built and loaded according to that design*
% ,ever overload the scaffold*
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
16/55
Platorm Construction
The platform surface that supports workers and materials
on the scaffold is called planks. 'lanks are usually made
of steel, aluminum, or wood. ood scaffold planks
should be by inches, scaffold plank grade, and
stamped by an agency appro"ed by the American
*umber (tandards +ommittee. Any unsafe planks should
be remo"ed from ser"ice and clearly marked or madeunusable.
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
17/55
Platorm Construction
%hen erecting scaffolding it is most important to ma$e
sure the first unit of any scaffold is plumb( aligned( and
level*
%Each platform on all 'or$ing levels of scaffolds are
re"uired to be fully plan$ed or dec$ed( e)cept 'hen used
only as 'al$'ays or for erecting or dismantling scaffolding*
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
18/55
Platorm Construction
% The platform and 'al$'ay must be at least /0 inches
'ide*
% Install each platform unit 1plan$( fabricated dec$( or
fabricated platform2 so that the space bet'een plan$s(
and the space bet'een the platform and the uprights( is
no more than one inch*
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
19/55
Platorm Construction
% The front edge of the platform must be no more than /3
inches from the face of the 'or$( unless guardrails are used
along the front edge and4or personal fall arrest systems are
used*
% ,ever cover 'ood platforms 'ith opa"ue finishes 1such as
paint2( e)cept for the edges( 'hich may be covered or mar$ed
for identification*
% ,ever intermi) scaffold components by different
manufacturers( unless a competent person determines they
are compatible and the scaffold5s structural integrity is
maintained*
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
20/55
Platorm Construction
% Each end of the platform( unless cleated or restrained by
hoo$s or other means( must e)tend over the center line of
its support at least si) inches*
% If the platform is /6 feet or less in length( the end cannot
e)tend over its support more than /7 inches*
% If the platform is over /6 feet in length( its end cannot
e)tend over the support more than /0 inches*
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
21/55
Platorm Construction
% hen platforms are overlapped to create a long platform(
the overlap must occur only over supports and must be at
least /7 inches( unless the platforms are restrained to
prevent movement*
% Each abutted end of a plan$ must rest on a separate
support surface*
% hen the platform changes direction( any platform thatrests on a bearer at an angle other than a right angle must
be laid first* Platforms that rest at right angles over the
same bearer must be laid second( on top of the first
platform*
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
22/55
Supported Scafolds
(upported scaffolds ha"e one or more platforms that
are supported by outrigger beams, brackets, poles,
legs, uprights, posts, frames, or similar rigid supports.The following are some general requirements for
supported scaffolds$
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
23/55
(upported (caffolds
% hen using mud sills( the base plates should be attached
to it* 8or added stability( it is recommended the mud sill beone continuous sill under both legs* The sill should e)tend
at least /7 inches beyond the center line of the pole*
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
24/55
Supported Scafolds
% All supported scaffold poles( legs( posts( frames( and
uprights must bear on base plates( mud sills( or other
firm foundation*
% They must also be plumb and braced to prevent
s'aying and displacement*
% 8ootings must be level( sound( rigid( and capable ofsupporting the load of the scaffold 'ithout settling or
displacing*
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
25/55
Supported Scafolds
% ,ever use cinder bloc$s( bric$s( gravel( loose fill( or other
means for leveling uneven surfaces( or providing a
foundation for the base plate*
% hen supported scaffolds have a height9to9base 'idth
ratio of more than 39to9/ 1four feet of height for every one
foot of 'idth2( then guys( ties( or braces must be installed
at locations 'here horizontal members support both inner
and outer legs*
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
26/55
Suspension Scafolds
(uspension scaffolds ha"e one or more platforms
suspended by ropes or other non-rigid means from
an o"erhead structure. /efore the suspensionscaffold is used, a competent person must confirm
that the supporting surfaces are capable of
supporting the loads imposed on them.
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
27/55
Suspension Scafolds
The follo'ing are some general re"uirements for
suspension scaffolds%
!opes
% ,E:E! use repaired 'ire rope as
suspension rope*
% !opes need to be inspected by a
competent person for defects before each
'or$ shift and after any occurrence that
could affect a rope5s integrity*
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
28/55
Suspension Scafolds
Hoists
% ;asoline9po'ered e"uipment and hoists must not be usedon suspension scaffolds*
% ;ears and bra$es of po'er9operated hoists used on
suspension scaffolds must be enclosed*
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
29/55
Suspension Scafolds
Support Devices
% All suspension scaffold support devices 1such as outrigger
beams( cornice hoo$s( and parapet clamps2 must rest onsurfaces that are capable of supporting four times the load
imposed on them*
% T'o9point and multi9point suspension scaffolds must be tied
or other'ise secured to prevent them from s'aying if a
competent person determines it is necessary* ,ever use
'indo' cleaners5 anchors for this purpose*
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
30/55
Suspension Scafolds
+utrigger
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
31/55
Suspension Scafolds
#ounter'eights
% ,ever use sand( gravel( or other materials that can
be easily dislocated as counter'eights* +nly ob.ectsspecifically designed as counter'eights must be
used*
% #ounter'eights must be secured by mechanical
means to the outrigger beams to prevent accidental
displacement*
% Do not remove the counter'eights until the scaffold
is disassembled*
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
32/55
Suspension Scafolds
Tiebac$s
% +utrigger beams that are not stabilized by both bolts
or other direct connections to the floor or the roof dec$
must be secured by tiebac$s*
% Tiebac$s must be e"ual in strength to the suspension
ropes*
% Tiebac$s must be secured to a structurally sound
anchorage on the building or structure* Do ,+T use
standpipes( vents( or electrical conduits as anchorages*
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
33/55
Access Requirements
0any scaffold-related inuries occur while
improperly getting on or off platforms. 1e"er umponto a scaffold.
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
34/55
Access 2equirements
% hen the scaffold platform is more than t'o feet above or
belo' a point of access( then a portable ladder( stair'ay(
ramp( or other means of access that does not affect the
scaffold5s stability must be used*
% ,ever use cross braces to climb onto the scaffold or another
level of the scaffold*
% Direct access from one scaffold to another can only be used
'hen the scaffold surfaces are not more than /3 inches
horizontally and 73 inches vertically from each other*
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
35/55
Access Requirements
Portable( Hoo$9+n( and Attachable =adders
% Place hoo$9on and attachable ladders so their bottom rung
is not more than 73 inches above the scaffold support level*
% hen hoo$9on and attachable ladders are used on a
supported scaffold that is more than >? feet high( rest
platforms must be provided at least every >? feet*
% The minimum rung length for hoo$9on and attachable
ladders is //9/47 inches* !ungs must be uniformly spaced
'ith a ma)imum spacing of /@9>43 inches bet'een rungs*
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
36/55
Access Requirements
Stair'ay9Type =adders
% Place stair'ay9type ladders so their bottom rung is
not more than 73 inches above the scaffoldsupporting level.
% !est platforms are re"uired at least every /7 feet*
% The step 'idth should be a minimum of /@ inches*
obile scaffold stair'ay9type ladders must have a
minimum step 'idth of //9/47 inches*
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
37/55
Access Requirements
Integral Prefabricated Scaffold
Access 8rames
% !ungs on integral prefabricated scaffold access frames
must be at least 0 inches long*
% !est platforms must be provided at least every >? feet on
supported scaffolds more than >? feet high*
% !ungs must be spaced no more than /@9>43 inches apart*
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
38/55
Access Requirements
Stairto'ers 1Scaffold Stair'ay4To'ers2
% Stairto'ers must be positioned so their bottom step is
not more than 73 inches above the scaffold supporting
level*
% Stair'ays must be installed bet'een 36 degrees and @6
degrees from the horizontal* Each stair'ay must be atleast /0 inches bet'een stair rails*
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
39/55
Access Requirements
% Each side of the scaffold stair'ay must have a stair rail
that includes a toprail and a midrail* Stair rails must bebet'een 70 inches and >B inches in height( from the top
of the stair rail to the surface of the thread*
% The toprail of each stair rail system must also serve as
a handrail( unless a separate handrail is provided* All
handrails must provide a good handhold for employees*
Stairto'ers 1Scaffold Stair'ay4To'ers2
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
40/55
Access Requirements
% A landing platform at least /0 inches 'ide and at least/0 inches long must provided at each level* All treads
and landing must have slip9resistant surfaces*
;uardrails must be provided on the open sides and
ends of each landing*
Stairto'ers 1Scaffold Stair'ay4To'ers2
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
41/55
Access Requirements
!amps and al$'ays
% All ramps and 'al$'ays that are si) feet or more above
lo'er levels must have guardrails*
% A ramp or 'al$'ay that is steeper than one vertical to
eight horizontal( must have cleats not more than /3 inches
apart that are securely fastened to the flan$s to provide
footing* !amps and 'al$'ays may not incline more than aslope of one vertical to three horizontal*
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
42/55
Access Requirements
Access for Supported Scaffolds
% hen erecting or dismantling a scaffold( a safe means of
access must be provided( if possible* A competent person'ill determine this based on site conditions and the type
of scaffold being erected or dismantled*
% Hoo$9on or attachable ladders must be installed as soon
as safe installation and use are possible*
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
43/55
Access Requirements
Access for Supported Scaffolds
% hen erecting or dismantling tubular 'elded framescaffolds( end frames 'ith horizontal members that are
parallel( level( and not more than 77 inches apart
vertically may be used as climbing devices for access*
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
44/55
Fall Protection
A competent person will determine if fall protection
is feasible during erecting and dismantling
procedures. +heck with your super"isor or thecompetent person if you are not sure what type of
fall protection is required.
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
45/55
Fall Protection
;uardrail Systems
% ;uardrails must be installed along all open sides and ends
of scaffolds that are more than /6 feet above a lo'er level*
% The top edge height of toprails on supported scaffolds
manufactured or in service after Canuary /( 7666 must be
installed bet'een 70 and 3? inches above the platform*
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
46/55
Fall Protection
;uardrail Systems
% The top edge height on supported scaffolds
manufactured or in service before that date( and on all
suspended scaffolds 'here both a guardrail and
personal fall arrest system are re"uired( must be
installed bet'een >@ and 3? inches*
% hen midrails( screens( mesh( intermediate verticalmember( solid panels( or similar structural members
are used( they must be installed bet'een the top edge of
the guardrail system and the scaffold platform*
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
47/55
Fall Protection
Personal 8all Arrest Systems
% hen engineering controls( such as guardrails and safety
nets cannot protect you from fall hazards( then a personalfall arrest system must be used* In the construction
industry( a personal fall arrest system is re"uired at
heights of @ feet or more*
% A personal fall arrest system must be attached by a
lanyard to a vertical lifeline( horizontal lifeline( or
scaffold structural member*
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
48/55
Fall Protection
Personal 8all Arrest Systems
% The personal fall arrest system must limit free fall to
si) feet or less*
% Do not attach the personal fall arrest system to the
guardrail system*
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
49/55
Fall Protection
% The anchor point must be able to support ?(666 pounds
per attached 'or$er* hen vertical lifelines are used(
the anchor point must be independent of the scaffold*Standpipes( vents( other piping systems( electrical
conduits( outrigger beams( and counter'eights are
,+T considered safe points of anchorage*
% Inspect the personal fall arrest system before each use*
=oo$ for 'ear( tears( cuts( and other signs of damage*
Personal 8all Arrest Systems
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
50/55
Falling Obect Protection
A hard hat must be worn whene"er there is a possibility
of being struck by falling obects, impact while handling
material at head le"el, or other situations where thedanger of inuries to the head e3ists. 4(!A
54ccupational (afety and !ealth Administrator6
recommends that if a hard hat is needed anywhere on the
ob site, then you should wear it at all times.
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
51/55
Falling Obect Protection
% If tools( materials( or e"uipment could fall and stri$e
employees belo'( then the area must be barricaded
and unauthorized personnel must not be allo'ed to
enter* If the platform is more than /6 feet above alo'er level( then toeboards must be used*
% Toeboards must be at least >9/47 inches high from the
top edge of the toeboard to the level of the 'al$ing
surface( have no more than a /43 inch clearance above
the 'al$ing4'or$ing surface( and solid or have
openings no larger than one inch in size*
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
52/55
Falling Obect Protection
% If tools( materials( or e"uipment are piled higher than
the top edge of the toeboard( then mesh( debris nets(
canopies( or other means of protection must beinstalled*
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
53/55
!ismantling Scafolding
All scaffolds must be dismantled only under the
super"ision or direction of a competent person who is
qualified.
%
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
54/55
!ismantling Scafolding
% =o'er all components to the ground by rope( hoist( or man9
to9man* ,ever thro' the parts to the ground*
% If possible( avoid leaving the scaffold partially dismantled(
post 'arning notices at each point of access*
% hether erecting or dismantling scaffolding( 'or$ should
al'ays be suspended during high 'inds and storms*
-
7/25/2019 Scaffolding Safety (Erecting and Dismantling)
55/55
Summit Training Source(Inc*
#ontact us at%
/90669037963@@
or at
infosafetyonthe'eb*com