scaffolding safety (erecting and dismantling)

Upload: anonymous-vpfljmmkk

Post on 27-Feb-2018

327 views

Category:

Documents


13 download

TRANSCRIPT

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    1/55

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    2/55

    ScafoldingSaetyErecting & Dismantling

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    3/55

    Introduction

    As a person who erects and dismantles scaffolding, your

    safety - and the safety of those who will work on the

    scaffold - depends on your ability to closely follow theminimum safety requirements for constructing and using

    scaffolds.

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    4/55

    Introduction

    The scaffold system you erect will support many workers

    and allow them to carry out their ob functions. !ow well

    you follow proper procedures and safe work practiceswhile erecting scaffolds will ha"e a direct affect on their

    safety. #f you ha"e any questions about erecting or

    dismantling scaffolding, ask your super"isor.

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    5/55

    Pre-planning

    #t is important that thorough pre-planning takes place

    before scaffolding is erected. This should include$

    % Evaluation and Preparation of the Site

    % Identification of Any Potential Hazards

    % Determining the Type of Scaffolding to be Used

    % Activities to be Performed and their eight !e"uirements

    % eight #apacity of the Scaffold

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    6/55

    Pre-planning

    Evaluating the Site

    hile e"aluating the site there are many factors to

    consider. There may be a number of steps you willneed to take to prepare the site.

    Some items to chec$ could include%

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    7/55

    Pre-planning

    % Is the surface level and sound&

    % #an the ground support the scaffold unit&

    % Are there any unguarded openings or potential

    underground utility 'or$ that may affect the stability of

    the scaffold&

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    8/55

    % Are there any nearby electrical po'er lines&

    % If so( can the scaffold be erected 'hile $eeping aminimum safe approach distance from the lines&

    % #an 'or$ be performed on the scaffold 'hile

    maintaining a minimum safe approach distance from the

    electrical po'er lines&

    're-planning

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    9/55

    Pre-planning

    % hat type of pedestrian( vehicular( or e"uipment traffic

    'ill be in the area&

    % hat type of fall protection 'ill be feasible&

    % ill safe access 'hile erecting and dismantling the

    scaffold be feasible&

    % ill conditions such as high 'inds( storms( or icy

    conditions e)ist&

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    10/55

    Scafolding Inspection

    To make sure scaffold components are in good

    working order, carefully inspect all scaffolding partsbefore and during its erection. A defecti"e or

    damaged part could affect the integrity of the whole

    scaffold.

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    11/55

    Scafolding Inspection

    Items to #hec$

    % Are plan$s and 'ood components free of splits( rot( burns(

    'arps( splintering( oil( or paint and opa"ue finishes that

    could cover potential defects*

    % Are 'ood plan$s scaffold grade&

    % Are 'elds and bolted connections in good condition*

    (ome areas to inspect include the following$

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    12/55

    Scafolding Inspection

    #AUTI+,-

    % Any defective parts must not be used*

    % Any damaged or 'ea$ened scaffold part must be

    immediately repaired or removed from service until it is

    repaired*

    % ,ever ris$ your safety by using damaged parts*

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    13/55

    Load Capacity

    The load capacity of a scaffold "aries, depending on its

    design and application. )eneral capacity requirementsfor all scaffolds include$

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    14/55

    % The scaffold and each scaffold component must be capable

    of supporting four times the ma)imum intended load* This

    includes all personnel( e"uipment( and supplies*

    % Direct connections and counter'eights used to balance

    ad.ustable suspension scaffolds must be able to resist at

    least four times the tipping moment of the scaffold(

    including stall loads*

    *oad +apacity

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    15/55

    Load Capacity

    % All suspension ropes and connecting hard'are must be

    capable of supporting at least si) times the ma)imum

    intended load*

    % Scaffolds must be designed by a "ualified person( and

    built and loaded according to that design*

    % ,ever overload the scaffold*

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    16/55

    Platorm Construction

    The platform surface that supports workers and materials

    on the scaffold is called planks. 'lanks are usually made

    of steel, aluminum, or wood. ood scaffold planks

    should be by inches, scaffold plank grade, and

    stamped by an agency appro"ed by the American

    *umber (tandards +ommittee. Any unsafe planks should

    be remo"ed from ser"ice and clearly marked or madeunusable.

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    17/55

    Platorm Construction

    %hen erecting scaffolding it is most important to ma$e

    sure the first unit of any scaffold is plumb( aligned( and

    level*

    %Each platform on all 'or$ing levels of scaffolds are

    re"uired to be fully plan$ed or dec$ed( e)cept 'hen used

    only as 'al$'ays or for erecting or dismantling scaffolding*

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    18/55

    Platorm Construction

    % The platform and 'al$'ay must be at least /0 inches

    'ide*

    % Install each platform unit 1plan$( fabricated dec$( or

    fabricated platform2 so that the space bet'een plan$s(

    and the space bet'een the platform and the uprights( is

    no more than one inch*

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    19/55

    Platorm Construction

    % The front edge of the platform must be no more than /3

    inches from the face of the 'or$( unless guardrails are used

    along the front edge and4or personal fall arrest systems are

    used*

    % ,ever cover 'ood platforms 'ith opa"ue finishes 1such as

    paint2( e)cept for the edges( 'hich may be covered or mar$ed

    for identification*

    % ,ever intermi) scaffold components by different

    manufacturers( unless a competent person determines they

    are compatible and the scaffold5s structural integrity is

    maintained*

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    20/55

    Platorm Construction

    % Each end of the platform( unless cleated or restrained by

    hoo$s or other means( must e)tend over the center line of

    its support at least si) inches*

    % If the platform is /6 feet or less in length( the end cannot

    e)tend over its support more than /7 inches*

    % If the platform is over /6 feet in length( its end cannot

    e)tend over the support more than /0 inches*

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    21/55

    Platorm Construction

    % hen platforms are overlapped to create a long platform(

    the overlap must occur only over supports and must be at

    least /7 inches( unless the platforms are restrained to

    prevent movement*

    % Each abutted end of a plan$ must rest on a separate

    support surface*

    % hen the platform changes direction( any platform thatrests on a bearer at an angle other than a right angle must

    be laid first* Platforms that rest at right angles over the

    same bearer must be laid second( on top of the first

    platform*

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    22/55

    Supported Scafolds

    (upported scaffolds ha"e one or more platforms that

    are supported by outrigger beams, brackets, poles,

    legs, uprights, posts, frames, or similar rigid supports.The following are some general requirements for

    supported scaffolds$

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    23/55

    (upported (caffolds

    % hen using mud sills( the base plates should be attached

    to it* 8or added stability( it is recommended the mud sill beone continuous sill under both legs* The sill should e)tend

    at least /7 inches beyond the center line of the pole*

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    24/55

    Supported Scafolds

    % All supported scaffold poles( legs( posts( frames( and

    uprights must bear on base plates( mud sills( or other

    firm foundation*

    % They must also be plumb and braced to prevent

    s'aying and displacement*

    % 8ootings must be level( sound( rigid( and capable ofsupporting the load of the scaffold 'ithout settling or

    displacing*

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    25/55

    Supported Scafolds

    % ,ever use cinder bloc$s( bric$s( gravel( loose fill( or other

    means for leveling uneven surfaces( or providing a

    foundation for the base plate*

    % hen supported scaffolds have a height9to9base 'idth

    ratio of more than 39to9/ 1four feet of height for every one

    foot of 'idth2( then guys( ties( or braces must be installed

    at locations 'here horizontal members support both inner

    and outer legs*

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    26/55

    Suspension Scafolds

    (uspension scaffolds ha"e one or more platforms

    suspended by ropes or other non-rigid means from

    an o"erhead structure. /efore the suspensionscaffold is used, a competent person must confirm

    that the supporting surfaces are capable of

    supporting the loads imposed on them.

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    27/55

    Suspension Scafolds

    The follo'ing are some general re"uirements for

    suspension scaffolds%

    !opes

    % ,E:E! use repaired 'ire rope as

    suspension rope*

    % !opes need to be inspected by a

    competent person for defects before each

    'or$ shift and after any occurrence that

    could affect a rope5s integrity*

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    28/55

    Suspension Scafolds

    Hoists

    % ;asoline9po'ered e"uipment and hoists must not be usedon suspension scaffolds*

    % ;ears and bra$es of po'er9operated hoists used on

    suspension scaffolds must be enclosed*

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    29/55

    Suspension Scafolds

    Support Devices

    % All suspension scaffold support devices 1such as outrigger

    beams( cornice hoo$s( and parapet clamps2 must rest onsurfaces that are capable of supporting four times the load

    imposed on them*

    % T'o9point and multi9point suspension scaffolds must be tied

    or other'ise secured to prevent them from s'aying if a

    competent person determines it is necessary* ,ever use

    'indo' cleaners5 anchors for this purpose*

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    30/55

    Suspension Scafolds

    +utrigger

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    31/55

    Suspension Scafolds

    #ounter'eights

    % ,ever use sand( gravel( or other materials that can

    be easily dislocated as counter'eights* +nly ob.ectsspecifically designed as counter'eights must be

    used*

    % #ounter'eights must be secured by mechanical

    means to the outrigger beams to prevent accidental

    displacement*

    % Do not remove the counter'eights until the scaffold

    is disassembled*

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    32/55

    Suspension Scafolds

    Tiebac$s

    % +utrigger beams that are not stabilized by both bolts

    or other direct connections to the floor or the roof dec$

    must be secured by tiebac$s*

    % Tiebac$s must be e"ual in strength to the suspension

    ropes*

    % Tiebac$s must be secured to a structurally sound

    anchorage on the building or structure* Do ,+T use

    standpipes( vents( or electrical conduits as anchorages*

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    33/55

    Access Requirements

    0any scaffold-related inuries occur while

    improperly getting on or off platforms. 1e"er umponto a scaffold.

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    34/55

    Access 2equirements

    % hen the scaffold platform is more than t'o feet above or

    belo' a point of access( then a portable ladder( stair'ay(

    ramp( or other means of access that does not affect the

    scaffold5s stability must be used*

    % ,ever use cross braces to climb onto the scaffold or another

    level of the scaffold*

    % Direct access from one scaffold to another can only be used

    'hen the scaffold surfaces are not more than /3 inches

    horizontally and 73 inches vertically from each other*

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    35/55

    Access Requirements

    Portable( Hoo$9+n( and Attachable =adders

    % Place hoo$9on and attachable ladders so their bottom rung

    is not more than 73 inches above the scaffold support level*

    % hen hoo$9on and attachable ladders are used on a

    supported scaffold that is more than >? feet high( rest

    platforms must be provided at least every >? feet*

    % The minimum rung length for hoo$9on and attachable

    ladders is //9/47 inches* !ungs must be uniformly spaced

    'ith a ma)imum spacing of /@9>43 inches bet'een rungs*

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    36/55

    Access Requirements

    Stair'ay9Type =adders

    % Place stair'ay9type ladders so their bottom rung is

    not more than 73 inches above the scaffoldsupporting level.

    % !est platforms are re"uired at least every /7 feet*

    % The step 'idth should be a minimum of /@ inches*

    obile scaffold stair'ay9type ladders must have a

    minimum step 'idth of //9/47 inches*

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    37/55

    Access Requirements

    Integral Prefabricated Scaffold

    Access 8rames

    % !ungs on integral prefabricated scaffold access frames

    must be at least 0 inches long*

    % !est platforms must be provided at least every >? feet on

    supported scaffolds more than >? feet high*

    % !ungs must be spaced no more than /@9>43 inches apart*

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    38/55

    Access Requirements

    Stairto'ers 1Scaffold Stair'ay4To'ers2

    % Stairto'ers must be positioned so their bottom step is

    not more than 73 inches above the scaffold supporting

    level*

    % Stair'ays must be installed bet'een 36 degrees and @6

    degrees from the horizontal* Each stair'ay must be atleast /0 inches bet'een stair rails*

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    39/55

    Access Requirements

    % Each side of the scaffold stair'ay must have a stair rail

    that includes a toprail and a midrail* Stair rails must bebet'een 70 inches and >B inches in height( from the top

    of the stair rail to the surface of the thread*

    % The toprail of each stair rail system must also serve as

    a handrail( unless a separate handrail is provided* All

    handrails must provide a good handhold for employees*

    Stairto'ers 1Scaffold Stair'ay4To'ers2

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    40/55

    Access Requirements

    % A landing platform at least /0 inches 'ide and at least/0 inches long must provided at each level* All treads

    and landing must have slip9resistant surfaces*

    ;uardrails must be provided on the open sides and

    ends of each landing*

    Stairto'ers 1Scaffold Stair'ay4To'ers2

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    41/55

    Access Requirements

    !amps and al$'ays

    % All ramps and 'al$'ays that are si) feet or more above

    lo'er levels must have guardrails*

    % A ramp or 'al$'ay that is steeper than one vertical to

    eight horizontal( must have cleats not more than /3 inches

    apart that are securely fastened to the flan$s to provide

    footing* !amps and 'al$'ays may not incline more than aslope of one vertical to three horizontal*

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    42/55

    Access Requirements

    Access for Supported Scaffolds

    % hen erecting or dismantling a scaffold( a safe means of

    access must be provided( if possible* A competent person'ill determine this based on site conditions and the type

    of scaffold being erected or dismantled*

    % Hoo$9on or attachable ladders must be installed as soon

    as safe installation and use are possible*

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    43/55

    Access Requirements

    Access for Supported Scaffolds

    % hen erecting or dismantling tubular 'elded framescaffolds( end frames 'ith horizontal members that are

    parallel( level( and not more than 77 inches apart

    vertically may be used as climbing devices for access*

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    44/55

    Fall Protection

    A competent person will determine if fall protection

    is feasible during erecting and dismantling

    procedures. +heck with your super"isor or thecompetent person if you are not sure what type of

    fall protection is required.

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    45/55

    Fall Protection

    ;uardrail Systems

    % ;uardrails must be installed along all open sides and ends

    of scaffolds that are more than /6 feet above a lo'er level*

    % The top edge height of toprails on supported scaffolds

    manufactured or in service after Canuary /( 7666 must be

    installed bet'een 70 and 3? inches above the platform*

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    46/55

    Fall Protection

    ;uardrail Systems

    % The top edge height on supported scaffolds

    manufactured or in service before that date( and on all

    suspended scaffolds 'here both a guardrail and

    personal fall arrest system are re"uired( must be

    installed bet'een >@ and 3? inches*

    % hen midrails( screens( mesh( intermediate verticalmember( solid panels( or similar structural members

    are used( they must be installed bet'een the top edge of

    the guardrail system and the scaffold platform*

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    47/55

    Fall Protection

    Personal 8all Arrest Systems

    % hen engineering controls( such as guardrails and safety

    nets cannot protect you from fall hazards( then a personalfall arrest system must be used* In the construction

    industry( a personal fall arrest system is re"uired at

    heights of @ feet or more*

    % A personal fall arrest system must be attached by a

    lanyard to a vertical lifeline( horizontal lifeline( or

    scaffold structural member*

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    48/55

    Fall Protection

    Personal 8all Arrest Systems

    % The personal fall arrest system must limit free fall to

    si) feet or less*

    % Do not attach the personal fall arrest system to the

    guardrail system*

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    49/55

    Fall Protection

    % The anchor point must be able to support ?(666 pounds

    per attached 'or$er* hen vertical lifelines are used(

    the anchor point must be independent of the scaffold*Standpipes( vents( other piping systems( electrical

    conduits( outrigger beams( and counter'eights are

    ,+T considered safe points of anchorage*

    % Inspect the personal fall arrest system before each use*

    =oo$ for 'ear( tears( cuts( and other signs of damage*

    Personal 8all Arrest Systems

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    50/55

    Falling Obect Protection

    A hard hat must be worn whene"er there is a possibility

    of being struck by falling obects, impact while handling

    material at head le"el, or other situations where thedanger of inuries to the head e3ists. 4(!A

    54ccupational (afety and !ealth Administrator6

    recommends that if a hard hat is needed anywhere on the

    ob site, then you should wear it at all times.

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    51/55

    Falling Obect Protection

    % If tools( materials( or e"uipment could fall and stri$e

    employees belo'( then the area must be barricaded

    and unauthorized personnel must not be allo'ed to

    enter* If the platform is more than /6 feet above alo'er level( then toeboards must be used*

    % Toeboards must be at least >9/47 inches high from the

    top edge of the toeboard to the level of the 'al$ing

    surface( have no more than a /43 inch clearance above

    the 'al$ing4'or$ing surface( and solid or have

    openings no larger than one inch in size*

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    52/55

    Falling Obect Protection

    % If tools( materials( or e"uipment are piled higher than

    the top edge of the toeboard( then mesh( debris nets(

    canopies( or other means of protection must beinstalled*

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    53/55

    !ismantling Scafolding

    All scaffolds must be dismantled only under the

    super"ision or direction of a competent person who is

    qualified.

    %

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    54/55

    !ismantling Scafolding

    % =o'er all components to the ground by rope( hoist( or man9

    to9man* ,ever thro' the parts to the ground*

    % If possible( avoid leaving the scaffold partially dismantled(

    post 'arning notices at each point of access*

    % hether erecting or dismantling scaffolding( 'or$ should

    al'ays be suspended during high 'inds and storms*

  • 7/25/2019 Scaffolding Safety (Erecting and Dismantling)

    55/55

    Summit Training Source(Inc*

    #ontact us at%

    /90669037963@@

    or at

    infosafetyonthe'eb*com