SCDL – 3rd Semester – Software Engineering and Project Management
LIST OF ATTEMPTED QUESTIONS AND ANSWERS Multiple Choice Multiple Answer Question Operational Testing is carried out by :-
Correct Answer Stress Testing , Performance Testing , Recovery Testing
Your Answer Alpha & Beta Test , Recovery Testing , Stress Testing
True/False Question Spiral model itself is a model which is base for other software development models
Correct Answer False
Select The Blank Question SE Methodology rides on two components, System Engineering and ________.
Correct Answer Development Engineering
Match The FollowingQuestion Correct Answer Your Answer
Performance of the System Non Functional Requirements Non Functional Requirements
SRS Structured System Analysis Structured System Analysis
Design Phase Design Documentation Design Documentation
SSAD Functions & Features Functions & Features
Select The Blank Question ________ evaluates the run time performance of the system developed.
Correct Answer Performance Testing
Multiple Choice Single Answer Question An Output of a Structured System Analysis is:-
Correct Answer Software Requirement Specification
Multiple Choice Multiple Answer Question OOSAD development approach uses
Correct Answer Objects , Process modeling , Object attributes
Your Answer Objects , Object attributes , Sub-system approach
Select The Blank Question An accounting System based on rules and Principles could be an example of ________
System. Correct Answer Deterministic
True/False Question A Software solution is evolved in parts as in an incremental fashion in incremental model
Correct Answer True Multiple Choice Single Answer Question Who Defines SE as the application of a Systematic, disciplined and quantifiable
approach to the development and maintenance of a Software
Page 1 of 155 1
SCDL – 3rd Semester – Software Engineering and Project Management
Correct Answer IEEE Select The Blank Question ________ is developed or engineered not manufactured
Correct Answer Software
Multiple Choice Multiple Answer Question A good test is one that has:- Correct Answer High Probability of detecting an error , Not Redundant , Simple to execute & Independent
Your Answer High Probability of detecting an error , Not Redundant , Simple to execute & Independent
True/False Question The Data Management is not easy with relational Model.
Correct Answer False
True/False Question The results of the test case is recorded in the test specification document.
Correct Answer True
True/False Question The ultimate goal of the SQA is to write test cases which fixes the errors.
Correct Answer False
Match The FollowingQuestion Correct Answer Your Answer
Entity Object which is Uniquely Distinguished
Object which is Uniquely Distinguished
Hierarchical Model Tree Structure Tree Structure
Network Model Network Communications Network Communications
Relational Model Data are Linked Data are Linked
Multiple Choice Multiple Answer Question The responsibilities of Software Managerare
Correct Answer To maintain budget , Keep schedules from slipping , Improve quality
Multiple Choice Single Answer Question A System which is adaptable to changes arising out of environmental changes:-
Correct Answer Open System Multiple Choice Single Answer Question A software which directly communicates with the hardware and provides an interface to
perform certain tasks is termed as Correct Answer System Software True/False Question Proactive risk strategies are applied to deal with risk when it occurs.
Correct Answer False
Select The Blank Question The basic tangible measure of the software is ________
Correct Answer Lines of Code
Page 2 of 155 2
SCDL – 3rd Semester – Software Engineering and Project Management
Multiple Choice Multiple Answer Question Database Design Specification include:-
Correct Answer Data Model , Internal & External File Structure , Referential Details
Your Answer Data Model , Internal & External File Structure , Referential Details
Multiple Choice Multiple Answer Question Following are the data models namely:-
Correct Answer Hierarchical Model , Network Model , Relational Model
Select The Blank Question The company shall establish a ________ to control flow of documents that relate to the
requirements of the ISO. Correct Answer Document Control System
True/False Question Stress Testing is a part of Integration testing.
Correct Answer False
Multiple Choice Multiple Answer Question Test Case Design for real time systems strategically should include:-
Correct Answer Task Testing , Behavioral Testing , Intertask Testing
Select The Blank Question Requirements Management Begins with ________.
Correct Answer Identification
True/False Question Database Design is a major component of system design and development.
Correct Answer True
Multiple Choice Multiple Answer Question The broad quality parameters are:-
Correct Answer Reliability , Safety , Security
True/False Question Documentation testing tests and verifies whether the troubleshooting is easily achieved
or not. Correct Answer True
Multiple Choice Single Answer Question Changes in the Customer requirements are understood and incorporated in which
phase? Correct Answer Support
Your Answer Analysis
Multiple Choice Single Answer Question A process of creating a document Statement of Work, and planning the major task
deliveries is :-
Page 3 of 155 3
SCDL – 3rd Semester – Software Engineering and Project Management
Correct Answer Project Planning
Your Answer Project Development
Multiple Choice Multiple Answer Question Project Risk Management Includes:-
Correct Answer Risk Prevention , Risk Avoidance , Risk Mitigation
Multiple Choice Single Answer Question A model which creates sources and destinations for the data flows of data i.e. input and
output is:- Correct Answer Data Flow Diagrams
Multiple Choice Single Answer Question The Extent of effort to modify the software components to meet the requirements is :-
Correct Answer Flexibility
True/False Question A computer system without system software can not function
Correct Answer True
Select The Blank Question A ________ is largely depends upon the meeting of functional requirements and
performance measures with ease in operations. Correct Answer Customer Satisfaction
Multiple Choice Multiple Answer Question Fourth generation technology helps to control
Correct Answer Effort , Resource , Cost development
Multiple Choice Single Answer Question A Software developed to perform certain functionality and later on embedded into the
hardware is called as Correct Answer Embedded Software
Select The Blank Question Cohesion and Coupling is the criteria for measuring ________.
Correct Answer Functional Dependency
Select The Blank Question In the ________ model data elements are organized in tree structure in parent-child
format. Correct Answer Hierarchical
Multiple Choice Single Answer Question An Approach foucsses on Objects and Processing Methods
Correct Answer OOSAD
Multiple Choice Multiple Answer Question Resources required for a Software development activity could be :-
Page 4 of 155 4
SCDL – 3rd Semester – Software Engineering and Project Management
Correct Answer People , Development Environment , Reusable Components
Multiple Choice Single Answer Question A process that ensures the delivery of the desired software product with the requisite
quality standards to the customer is :- Correct Answer Quality Assurance
Multiple Choice Single Answer Question A testing technique which reveals errors like Incorrect functions , Missing Functions or
Interface errors is:- Correct Answer Black Box Testing
Select The Blank Question A ________ is all about providing hardware and software tools as and when required by
the development team to manage process effectively Correct Answer Configuration Management
Your Answer Resources Management
Multiple Choice Multiple Answer Question The Examples of Business Software are
Correct Answer Payroll ,Accounting, , Inventory , customer Relation Management
Your Answer Payroll ,Accounting, , Inventory
LIST OF ATTEMPTED QUESTIONS AND ANSWERS True/False Question An E-R Diagram explain in graphical Model the nature of relations and
attributes. Correct Answer True
True/False Question Decomposition breaks the System into smaller modules and components.
Correct Answer True
Your Answer True
Select The Blank Question PRM stands for ________
Correct Answer Prototyping Model
True/False Question People, Procedures and Parameters are the Drivers of the Technology.
Correct Answer False
Your Answer True
Multiple Choice Multiple Answer
Page 5 of 155 5
SCDL – 3rd Semester – Software Engineering and Project Management
Question A good test is one that has:-
Correct Answer High Probability of detecting an error , Not Redundant , Simple to execute & Independent
Your Answer High Probability of detecting an error , Not Redundant , Simple to execute & Independent
Select The Blank Question Cohesion and Coupling is the criteria for measuring ________.
Correct Answer Functional Dependency
Your Answer System Dependency
Multiple Choice Single Answer Question How to develop or build a particular software module is defined by
Correct Answer Software Engineering Methods
Multiple Choice Multiple Answer Question The Functionality of the Client application is tested using :-
Correct Answer Server Tests , Database Tests , Transaction Tests
Your Answer Server Tests , Transaction Tests
True/False Question Systems running on web platforms needs high level of protection from testers.
Correct Answer False
Your Answer True
Select The Blank Question ________ layer of the Systems focuses on User Interfaces, data entry,
operation flows and maintenance. Correct Answer Operational
Your Answer Conceptual
Multiple Choice Multiple Answer Question Architecture Design Consists of:-
Correct Answer Module Structure , Program Structure , Hierarchy in the Structure
Your Answer Module Structure , Hierarchy in the Structure
Multiple Choice Multiple Answer Question The types of Software are
Correct Answer Business Software , Embedded Software , System Software
Select The Blank Question Generally in an ongoing project a project manager fixes up more ________ to
have proper control measurement of the project activities Correct Answer Major Milestone
Page 6 of 155 6
SCDL – 3rd Semester – Software Engineering and Project Management
Your Answer Milestone
Multiple Choice Single Answer Question An Activity that has a definite Start and a definite end is termed as ?
Correct Answer Project
Multiple Choice Single Answer Question Source Code of the Software is available so that the engineers can make the
local modifications and use the component Correct Answer Open Source
Your Answer Open Source/freeware
True/False Question Proactive risk strategies are applied to deal with risk when it occurs.
Correct Answer False
Multiple Choice Multiple Answer Question The next development in software engineering is
Correct Answer The use of tool generate the code , The extensive use od CASE tool for analysis and design , The use of Component technology
Your Answer The extensive use od CASE tool for analysis and design , The use of Component technology
Multiple Choice Single Answer Question A System is one that is self contained and self reliant:-
Correct Answer Closed System
True/False Question Domain Specific applications are developed mostly integrating components
which are similar in functionality Correct Answer True
Multiple Choice Single Answer Question A type of testing which verifies that all the system elements are meshed
properly and that overall system function / performance is achieved is:- Correct Answer System testing
Match The FollowingQuestion Correct Answer Your Answer
World Wide Web Content provider Integrated System
Software Deteriorates Content provider
System Software File Management File Management
Application Software Standalone Programs Standalone Programs
Multiple Choice Single Answer Question A Discipline that integrates Process, Methods and tools for development of a
software is
Page 7 of 155 7
SCDL – 3rd Semester – Software Engineering and Project Management
Correct Answer Software Engineering
Multiple Choice Multiple Answer Question Software Risk could be of :-
Correct Answer Process Risk , Project Risk , Product Risk
Your Answer Process Risk , Project Risk , Design Risk
Select The Blank Question In ________model two sets of data are linked by a relationship.
Correct Answer Relational
Multiple Choice Single Answer Question Application of tools and techniques of analysis, design, testing, assessment and
improvement is used to manage :- Correct Answer Software Project
Multiple Choice Multiple Answer Question System Testing Techniques are :-
Correct Answer Alpha Test , Beta Test
Your Answer Alpha Test , Beta Test , Gama Test
Multiple Choice Multiple Answer Question Operational Testing is carried out by :-
Correct Answer Recovery Testing , Stress Testing , Performance Testing
Your Answer Alpha & Beta Test , Stress Testing , Performance Testing
True/False Question White Box Testing Measures the Correctness of the Inputs and Basic
Processes. Correct Answer True
Select The Blank Question A Module Tests focuses on ________.
Correct Answer Functions & Design
Multiple Choice Single Answer Question A Phenomenon which states that over a period of times the system gets into a
phase of degrading and disorganization is:- Correct Answer Entropy
Your Answer Maintenance
Select The Blank Question The company shall establish a ________ to control flow of documents that
relate to the requirements of the ISO. Correct Answer Document Control System
Select The Blank
Page 8 of 155 8
SCDL – 3rd Semester – Software Engineering and Project Management
Question ________ is developed or engineered not manufactured
Correct Answer Software
Multiple Choice Single Answer Question A process that ensures the delivery of the desired software product with the
requisite quality standards to the customer is :- Correct Answer Quality Assurance
Multiple Choice Single Answer Question A Systematic approach to organise and documents the need of the customer
which is a basis for software development is :- Correct Answer Requirements Management
Select The Blank Question A ________ is largely depends upon the meeting of functional requirements
and performance measures with ease in operations. Correct Answer Customer Satisfaction
Multiple Choice Single Answer Question A process of acquiring hardware, software and development services and
entering into contract with customers and business partners to deliver the software product is :-
Correct Answer Project Procurement Management
True/False Question SE is applied for software development through Engineering Methods
Correct Answer True
True/False Question The Data Management is not easy with relational Model.
Correct Answer False
Multiple Choice Single Answer Question A type of testing which eliminates the errors in the design, architecture and
development & deployment process is. Correct Answer Non Execution based testing
Multiple Choice Multiple Answer Question The stages of the Iterative Models are
Correct Answer Requirement Analysis , System Design , Development Coding & Unit Testing
Select The Blank Question Usually the test cases are written using ________.
Correct Answer Testing Techniques
Your Answer Requirements Specifications
Select The Blank Question Requirements Management Begins with ________.
Correct Answer Identification
Page 9 of 155 9
SCDL – 3rd Semester – Software Engineering and Project Management
True/False Question The ultimate goal of the SQA is to write test cases which fixes the errors.
Correct Answer False
Multiple Choice Multiple Answer Question Test cases are designed to tests:-
Correct Answer Internal Logic , Software Requirements
Your Answer Software Performance , Internal Logic , Software Requirements
Multiple Choice Multiple Answer Question A documentation is tested through :-
Correct Answer Technical Review , Actual Operational Review
LIST OF ATTEMPTED QUESTIONS AND ANSWERS Multiple Choice Single Answer Question A process of identifying, assessing , evaluating risk exposure, prioritizing the risk
incidences, and developing risk monitoring, management and mitigation plan is :- Correct Answer Project Risk Management
Your Answer Project Risk Management
Multiple Choice Multiple Answer
Question Artificial Intelligent Domain Systems Could be
Correct Answer Expert System , Image & Voice Recognition System , Neural Networks
Your Answer Expert System , Image & Voice Recognition System , Neural Networks
Multiple Choice Multiple Answer
Question In a Software Risk Management Risk drivers are :-
Correct Answer Technology , People , Requirements
Your Answer Technology , People , Requirements
True/False Question Reactive risk strategies are applied to deal with risk when it occurs.
Correct Answer True
Your Answer True
Multiple Choice Multiple Answer
Question Design Constraints include:-
Page 10 of 155 10
SCDL – 3rd Semester – Software Engineering and Project Management
Correct Answer Resource Limitations , Platform Limitations , Protocol Limitations
Your Answer Resource Limitations , Protocol Limitations
Multiple Choice Multiple Answer
Question Resources required for a Software development activity could be :-
Correct Answer People , Development Environment , Reusable Components
Your Answer People , Development Environment , Reusable Components
Multiple Choice Single Answer
Question A Software that makes use of non numerical algorithms to solve complex problems that are not amenable to straightforward analysis
Correct Answer Artificial Intelligence
Your Answer Embedded Software
Select The Blank Question Software is classified into two categories, Generic and ________.
Correct Answer Cutomised
Your Answer Cutomised
Multiple Choice Single Answer Question The Scope of the work in a Software Project is defined by :-
Correct Answer Statement of Work
Your Answer Statement of Work
Select The Blank Question A ________ deals with identification and assessment of potential hazards of software
failing and its impact on the systems. Correct Answer Software Safety
Your Answer Software Testing
Multiple Choice Single Answer Question A Step in risk Management which identifies and enumerates the risk is :-
Correct Answer Risk Identification
Your Answer Risk Identification
Multiple Choice Single Answer
Question A Modification of the Software is done to accommodate the changes forced by the external environment is
Page 11 of 155 11
SCDL – 3rd Semester – Software Engineering and Project Management
Correct Answer Adaptive Maintenance
Your Answer Adaptive Maintenance
Select The Blank
Question One of the most important guideline for the reviewing the product is review the product not the ________.
Correct Answer Producer
Your Answer Developer
Multiple Choice Single Answer Question Software Engineering attempts to identify what information is to be processed, what
function and performance is desired in which phase? Correct Answer Definition Phase
Your Answer Definition Phase
True/False Question A software review is a filter for the software development process.
Correct Answer True
Your Answer True
True/False Question SRS is Systems requirement specifications in the software development phase
Correct Answer True
Your Answer True
True/False Question Software Development becomes complex due to the variety and heterogeneity of
requirement of different Users and Stakeholders Correct Answer True
Your Answer True
Multiple Choice Single Answer
Question Changes in the Customer requirements are understood and incorporated in which phase?
Correct Answer Support
Your Answer Development
Select The Blank Question ________ is characterized by longetivity and business criticality
Page 12 of 155 12
SCDL – 3rd Semester – Software Engineering and Project Management
Correct Answer Legacy Software
Your Answer Legacy Software
Multiple Choice Multiple Answer Question Some of the Steps involve in Integration Testing is :-
Correct Answer Main Control Module is a Test Driver , Tests are conducted as each component is added , Regression Testing is done
Your Answer Main Control Module is a Test Driver , Regression Testing is done
Multiple Choice Single Answer Question In Design Phase at data and data Structure stage the focus is on:-
Correct Answer Entities and Attributes
Your Answer Entities and Attributes
Multiple Choice Multiple Answer Question The outcome of Debugging Process is :-
Correct Answer The Error cause will be detected and corrected , The Error Cause will not be detected
Your Answer The Error cause will be detected and corrected , Design Errors
Match The FollowingQuestion Correct Answer Your Answer
Spiral Model Boehm Spiral model Incremental Model
Legacy software Poor Quality Poor Quality
Objects Attribute, Methods Attribute, Methods
SSAD yourdan & DeMarco Structured Methodology
Multiple Choice Single Answer
Question Most of the Software's Continues to be custom built because
Correct Answer Reusability of the Component
Your Answer Reusability of the Component
Select The Blank Question ________ is a System Engineering approach that is used to define architecture that
enables a business to use Information Effectively. Correct Answer Business Processing Engineering
Your Answer Business Processing Engineering
Page 13 of 155 13
SCDL – 3rd Semester – Software Engineering and Project Management
Multiple Choice Single Answer Question The success of the software depends upon ?
Correct Answer Usability
Your Answer Usability
True/False
Question A computer system without system software can not function
Correct Answer True
Your Answer True
Select The Blank
Question An incorrect decision by the designer, programmer or analyst that leads to improper result is an ________.
Correct Answer Error
Your Answer Error
Multiple Choice Multiple Answer Question The broad quality parameters are:-
Correct Answer Security , Reliability , Safety
Your Answer Reliability , Safety , Security
Multiple Choice Multiple Answer Question Black Box testing attempts to find error in following categories :-
Correct Answer Incorrect or Missing Functions , Interface Errors , Performance Errors
Your Answer Incorrect Output , Incorrect or Missing Functions , Interface Errors
Multiple Choice Single Answer
Question What is the tool which enforces consistency in naming the entities across the system?
Correct Answer Data Dictionary
Your Answer SFC
Multiple Choice Multiple Answer
Question The Scope of the Software Project is defined by Statement of Work which is agreed by ?
Correct Answer Users , Stakeholders , Customers
Your Answer Users , Stakeholders , Customers
Page 14 of 155 14
SCDL – 3rd Semester – Software Engineering and Project Management
True/False
Question System Performance is measured through effectiveness and its efficiency.
Correct Answer True
Your Answer True
True/False Question CAD/CAM/CAE are the examples of embedded Software
Correct Answer False
Your Answer False
True/False Question SQA is ensured through a Quality Management System.
Correct Answer True
Your Answer True
Select The Blank
Question A ________ Measures the Efforts / cost / time used to achieve the output.
Correct Answer Efficiency
Your Answer Effort Estimation
Select The Blank Question ________ type of testing evaluate the logical access to the basic functionality of the
System. Correct Answer Security Testing
Your Answer Security Testing
Multiple Choice Multiple Answer Question Legacy software -Poor quality has
Correct Answer Inextensible design , Convoluted Code , Poor or nonexistent documentation
Your Answer Convoluted Code , Poor or nonexistent documentation
Multiple Choice Single Answer Question A System in which next state of the system cannot be predicted even if the current
state of the system is known:- Correct Answer Probabilistic
Your Answer Probabilistic
Page 15 of 155 15
SCDL – 3rd Semester – Software Engineering and Project Management
Multiple Choice Single Answer Question The extent of software functions with precision without any failure is :-
Correct Answer Reliability
Your Answer Reliability
Multiple Choice Single Answer
Question A set of Computer Programs which performs set of preset functions is called as ?
Correct Answer Software
Your Answer Interface
Multiple Choice Single Answer
Question A process which breaks statement of work into smaller activities with clear start - finish definition is called as :-
Correct Answer Work Break Down Structure
Your Answer Work Break Down Structure
Multiple Choice Multiple Answer Question The Software Risk affects :-
Correct Answer Project Development , Software Product , Process of Development
Your Answer Project Development , Software Product , Process of Development
Multiple Choice Single Answer Question A software which directly communicates with the hardware and provides an interface
to perform certain tasks is termed as Correct Answer System Software
Your Answer System Software
Multiple Choice Multiple Answer Question Risk Management is a Process based on application of :-
Correct Answer Game Theory , Probability Theory , Decision Theory
Your Answer Probability Theory , Decision Theory
Match The FollowingQuestion Correct Answer Your Answer
Performance of the System Non Functional Requirements Non Functional Requirements
SRS Structured System Analysis Functions & Features
Page 16 of 155 16
SCDL – 3rd Semester – Software Engineering and Project Management
Design Phase Design Documentation Design Documentation
SSAD Functions & Features Structured System Analysis
LIST OF ATTEMPTED QUESTIONS AND ANSWERS Match The FollowingQuestion Correct Answer Your Answer
Data Structure & Specific Values Test Case Tracing
Verification & Validation Testing Test Case
Incorrect Logical Decision White Box Testing White Box Testing
Incorrect Functions In a program Black Box Testing Black Box Testing
True/False Question The prime objective of Formal Technical Review is to locate the error before it passes on
to the other activity. Correct Answer True
Your Answer True
Multiple Choice Single Answer Question A model in which software development cycle is sequential process is :-
Correct Answer Waterfall Model
Your Answer Waterfall Model
Multiple Choice Single Answer Question Application of Knowledge, Resources , tools and techniques to deliver customer needs
within agreed terms of cost and time is :- Correct Answer Project Management
Your Answer Project Management
True/False Question SRS is one of the cause of not meeting the SQA.
Correct Answer True
Your Answer True
Select The Blank
Page 17 of 155 17
SCDL – 3rd Semester – Software Engineering and Project Management
Question Usually the test cases are written using ________.
Correct Answer Testing Techniques
Your Answer Testing Techniques
Select The Blank Question ________ is developed or engineered not manufactured
Correct Answer Software
Your Answer Software
Multiple Choice Single Answer Question Application of tools and techniques of analysis, design, testing, assessment and
improvement is used to manage :- Correct Answer Software Project
Your Answer Software Project
Multiple Choice Single Answer Question A project management activity globally viewed as :-
Correct Answer A System
Your Answer A System
Multiple Choice Single Answer Question A set of activities ensure that the software that has been built is traceable to customer
requirements:- Correct Answer Validation
Your Answer Verification & Validation
Multiple Choice Single Answer Question A Model which Supports Modern Software Development is :-
Correct Answer Boehm's
Your Answer Boehm's
Match The FollowingQuestion Correct Answer Your Answer
Entity Object which is Uniquely Distinguished
Object which is Uniquely Distinguished
Hierarchical Model Tree Structure Tree Structure
Page 18 of 155 18
SCDL – 3rd Semester – Software Engineering and Project Management
Network Model Network Communications Network Communications
Relational Model Data are Linked Data are Linked
Multiple Choice Multiple Answer Question The outcome of the Risk Resolution Process is :-
Correct Answer Acceptable Risk , Reduced Reworks , Corrective actions
Your Answer Acceptable Risk , Reduced Reworks , Corrective actions
Multiple Choice Multiple Answer Question SQA efforts most primarily assures:-
Correct Answer Software Quality , Software Reliability , Software Availability
Your Answer Software Quality , Software Reliability , Software Maintenance
True/False Question Domain Specific applications are developed mostly integrating components which are
similar in functionality Correct Answer True
Your Answer False
Select The Blank Question ________ type of an error is class I error and needs corrective measures to be
implemented immediately. Correct Answer Fatal
Your Answer Fatal
Multiple Choice Multiple Answer Question Boehm's Model has following Stages:-
Correct Answer Production , Engineering
Your Answer Engineering , Engineering
Multiple Choice Multiple Answer Question Test cases are designed to tests:-
Correct Answer Internal Logic , Software Requirements
Your Answer Internal Logic , Software Requirements , A Quality aspect of a Program
Select The Blank Question A ________ arises due to uncertainties involved in assessing, estimating various inputs
Page 19 of 155 19
SCDL – 3rd Semester – Software Engineering and Project Management
to the software process. Correct Answer Process Risk
Your Answer Process Risk
True/False Question System Performance is measured through effectiveness and its efficiency.
Correct Answer True
Your Answer True
Select The Blank Question An incorrect decision by the designer, programmer or analyst that leads to improper
result is an ________. Correct Answer Error
Your Answer Error
Multiple Choice Multiple Answer Question Black Box testing techniques are:-
Correct Answer Graph Based Testing Methods , Equivalence Portioning , Boundary Value Analysis
Your Answer Graph Based Testing Methods , Equivalence Portioning , Boundary Value Analysis
Multiple Choice Single Answer Question A continuous process through out the development cycle and is an integral of the
complete development cycle:- Correct Answer Testing
Your Answer Verification
True/False Question The major resources in the project is people and funds.
Correct Answer False
Your Answer True
Select The Blank Question ________ evaluates the run time performance of the system developed.
Correct Answer Performance Testing
Your Answer Performance Testing
Select The Blank
Page 20 of 155 20
SCDL – 3rd Semester – Software Engineering and Project Management
Question Generally in an ongoing project a project manager fixes up more ________ to have proper control measurement of the project activities
Correct Answer Major Milestone
Your Answer Milestone
True/False Question SE is applied for software development through Engineering Methods
Correct Answer True
Your Answer True
Multiple Choice Single Answer Question A set of Computer Programs which performs set of preset functions is called as ?
Correct Answer Software
Your Answer Software
True/False Question Documentation testing tests and verifies whether the troubleshooting is easily achieved
or not. Correct Answer True
Your Answer True
Multiple Choice Multiple Answer Question IN OOSAD, Objects have
Correct Answer attribute , Methods , relationship
Your Answer attribute , Methods , relationship
Select The Blank Question The company should establish a ________ and maintain a documented quality system
as a means of ensuring that it conforms to the specified requirements of ISO. Correct Answer Quality System Procedure
Your Answer Quality Control System
Multiple Choice Single Answer Question A process which is iterative in nature which ensures that the RDD & SRS is transformed
into Design to meet the data is called:- Correct Answer Design
Your Answer Design
Page 21 of 155 21
SCDL – 3rd Semester – Software Engineering and Project Management
Multiple Choice Single Answer Question In Interface Stage of SSAD phase the focus is on:-
Correct Answer User Comfort
Your Answer User Comfort
Multiple Choice Multiple Answer Question Design Constraints include:-
Correct Answer Resource Limitations , Platform Limitations , Protocol Limitations
Your Answer Resource Limitations , Platform Limitations , Protocol Limitations
Multiple Choice Multiple Answer Question Operational Testing is carried out by :-
Correct Answer Recovery Testing , Stress Testing , Performance Testing
Your Answer Recovery Testing , Stress Testing , Performance Testing
Multiple Choice Multiple Answer Question OOSAD development approach uses
Correct Answer Objects , Process modeling , Object attributes
Your Answer Objects , Process modeling , Object attributes
Select The Blank Question In ________ model the data elements are organized indifferent areas that work together
through network communications. Correct Answer Network
Your Answer Network - Relational
Multiple Choice Multiple Answer Question Project Risk Management Includes:-
Correct Answer Risk Prevention , Risk Avoidance , Risk Mitigation
Your Answer Risk Avoidance , Risk Mitigation
Multiple Choice Single Answer Question A Process in which subsystems are organized into clusters with clear boundary and
defined goal is:- Correct Answer Simplification
Your Answer Decomposition
Page 22 of 155 22
SCDL – 3rd Semester – Software Engineering and Project Management
Select The Blank Question A Module Tests focuses on ________.
Correct Answer Functions & Design
Your Answer Functions & Design
True/False Question Recovery testing focuses on the Cost Recovery Plan of the Software Implemented.
Correct Answer False
Your Answer False
True/False Question Spiral model itself is a model which is base for other software development models
Correct Answer False
Your Answer False
Multiple Choice Single Answer Question The Extent of effort to locate the error and fix it is :-
Correct Answer Maintainability
Your Answer Maintainability
Multiple Choice Multiple Answer Question Test Case Design for real time systems strategically should include:-
Correct Answer Task Testing , Behavioral Testing , Intertask Testing
Your Answer Task Testing , Behavioral Testing , Intertask Testing
True/False Question The Unit of the Software is the smallest entity to be tested.
Correct Answer True
Your Answer True
Multiple Choice Multiple Answer Question The Software Risk affects :-
Correct Answer Project Development , Software Product , Process of Development
Page 23 of 155 23
SCDL – 3rd Semester – Software Engineering and Project Management
Your Answer Project Development , Software Product , Programmer & Team
Select The Blank Question A ________ is the most effective filter from a quality assurance stand point.
Correct Answer Formal Technical Review
Your Answer Formal Technical Review
LIST OF ATTEMPTED QUESTIONS AND ANSWERS Multiple Choice Single Answer Question The Extent of effort to modify the software components to meet the requirements
is :- Correct Answer Flexibility
Your Answer Reusability
Multiple Choice Multiple Answer Question The most affected elements of the Quality of the software is:-
Correct Answer Customer , Developer , Stake Holders
Your Answer Customer , Developer , Stake Holders
True/False Question CAD/CAM/CAE are the examples of embedded Software
Correct Answer False
Your Answer False
Multiple Choice Single Answer Question A System which is adaptable to changes arising out of environmental changes:-
Correct Answer Open System
Your Answer Open System
True/False Question Simplification rationalizes the complex , breakdown into clusters, making a
meaningful and functionally complete design. Correct Answer True
Your Answer True
Multiple Choice Single Answer
Page 24 of 155 24
SCDL – 3rd Semester – Software Engineering and Project Management
Question A type of testing where the focus is user and user Behavior is:-
Correct Answer Usage based testing
Your Answer Usage based testing
Multiple Choice Multiple Answer Question The next development in software engineering is
Correct Answer The use of tool generate the code , The extensive use od CASE tool for analysis and design , The use of Component technology
Your Answer Graphical tool , The use of tool generate the code , The extensive use od CASE tool for analysis and design
Multiple Choice Multiple Answer Question The responsibilities of Software Managerare
Correct Answer To maintain budget , Keep schedules from slipping , Improve quality
Your Answer To maintain budget , Keep schedules from slipping , Improve quality
Multiple Choice Single Answer Question The Quality aspect which includes the grade of materials, physical and
performance specifications, tolerance and process standards is :- Correct Answer Design
Your Answer Design
Multiple Choice Single Answer Question A system which operates in a predictable manner is :-
Correct Answer Deterministic System
Your Answer Deterministic System
Multiple Choice Multiple Answer Question Resources required for a Software development activity could be :-
Correct Answer People , Development Environment , Reusable Components
Your Answer People , Development Environment , Reusable Components
Multiple Choice Multiple Answer Question Project Metrics enable a software project manager to:-
Correct Answer Assess the Status of the Ongoing Project , Identify the Risk Potential , Uncover problem areas before they go Critical
Your Answer Assess the Status of the Ongoing Project , Uncover problem areas before they go Critical , Manage the resources
Page 25 of 155 25
SCDL – 3rd Semester – Software Engineering and Project Management
Select The Blank Question Each & every ________ has a Specific format as a record.
Correct Answer Test
Your Answer Test
True/False Question A computer system without system software can not function
Correct Answer True
Your Answer True
Select The Blank Question A ________ is understood as a possibility of Loss.
Correct Answer Risk
Your Answer Risk
True/False Question ISO 9001 is used to develop quality assurance systems.
Correct Answer True
Your Answer True
Select The Blank Question A unit tests major focuses on ________
Correct Answer Processes & Code
Your Answer Processes & Code
Multiple Choice Single Answer Question A software which resides in the read only memory and controls the functions of the
resident Products Correct Answer Embedded Software
Your Answer Embedded Software
True/False Question SRS is Systems requirement specifications in the software development phase
Correct Answer True
Your Answer True
True/False
Page 26 of 155 26
SCDL – 3rd Semester – Software Engineering and Project Management
Question Decomposition breaks the System into smaller modules and components.
Correct Answer True
Your Answer True
Multiple Choice Single Answer Question A process of acquiring hardware, software and development services and entering
into contract with customers and business partners to deliver the software product is :-
Correct Answer Project Procurement Management
Your Answer Project Procurement Management
Multiple Choice Single Answer Question A System is one that is self contained and self reliant:-
Correct Answer Closed System
Your Answer Open System
Select The Blank Question Software is classified into two categories, Generic and ________.
Correct Answer Cutomised
Your Answer Cutomised
True/False Question Reactive risk strategies are applied to deal with risk when it occurs.
Correct Answer True
Your Answer True
Multiple Choice Single Answer Question The Scope of the work in a Software Project is defined by :-
Correct Answer Statement of Work
Your Answer Statement of Work
Multiple Choice Multiple Answer Question White Box Testing Checks :-
Correct Answer All Paths in the process are correctly operational , All Logical decision are executed with true or false , All Loops are executed
Your Answer All Paths in the process are correctly operational , All Logical decision are executed with true or false , All Loops are executed
Page 27 of 155 27
SCDL – 3rd Semester – Software Engineering and Project Management
True/False Question An E-R Diagram explain in graphical Model the nature of relations and attributes.
Correct Answer True
Your Answer True
Select The Blank Question An accounting System based on rules and Principles could be an example of
________ System. Correct Answer Deterministic
Your Answer Deterministic
Multiple Choice Single Answer Question A System in which next state of the system can be predicted without doubt is :-
Correct Answer Deterministic
Your Answer Deterministic
Multiple Choice Multiple Answer Question RMMM Plan deals with :-
Correct Answer Mitigation , Monitoring , Management
Your Answer Mitigation , Monitoring , Management
Multiple Choice Multiple Answer Question Some of the Steps involve in Integration Testing is :-
Correct Answer Main Control Module is a Test Driver , Tests are conducted as each component is added , Regression Testing is done
Your Answer Main Control Module is a Test Driver , Tests are conducted as each component is added , Regression Testing is done
Select The Blank Question The company shall establish a ________ to control flow of documents that relate to
the requirements of the ISO. Correct Answer Document Control System
Your Answer Document Control System
True/False Question The results of the test case is recorded in the test specification document.
Correct Answer True
Page 28 of 155 28
SCDL – 3rd Semester – Software Engineering and Project Management
Your Answer True
Select The Blank Question ________ is characterized by longetivity and business criticality
Correct Answer Legacy Software
Your Answer Legacy Software
Select The Blank Question Inadequacy or misout in SRS & RDD is ________.
Correct Answer Defect
Your Answer Defect
Multiple Choice Single Answer Question A type of testing which eliminates the errors in the design, architecture and
development & deployment process is. Correct Answer Non Execution based testing
Your Answer Module based testing
Multiple Choice Multiple Answer Question Legacy software -Poor quality has
Correct Answer Inextensible design , Convoluted Code , Poor or nonexistent documentation
Your Answer Inextensible design , Convoluted Code , Poor or nonexistent documentation
Select The Blank Question Cohesion and Coupling is the criteria for measuring ________.
Correct Answer Functional Dependency
Your Answer Functional Dependency
True/False Question Integration testing is done when the modules are integrated or when new
component is added to the system. Correct Answer True
Your Answer True
Select The Blank Question In ________model two sets of data are linked by a relationship.
Page 29 of 155 29
SCDL – 3rd Semester – Software Engineering and Project Management
Correct Answer Relational
Your Answer Relational
Match The FollowingQuestion Correct Answer Your Answer
Closed System Parameter are fixed Parameter are fixed
Deterministic System Predictable Behavior Predictable Behavior
Probabilistic System Unpredictable Behavior Unpredictable Behavior
Open System Parameters are Variables Parameters are Variables
Multiple Choice Single Answer Question A type of testing carried out during the software product development process is:-
Correct Answer Execution Based testing
Your Answer Non Execution based testing
Select The Blank Question One of the most important guideline for the reviewing the product is review the
product not the ________. Correct Answer Producer
Your Answer Producer
Match The FollowingQuestion Correct Answer Your Answer
Performance of the System Non Functional Requirements Non Functional Requirements
SRS Structured System Analysis Functional Requirements
Design Phase Design Documentation Design Documentation
SSAD Functions & Features Functions & Features
Multiple Choice Multiple Answer Question The stages of the Iterative Models are
Correct Answer Requirement Analysis , System Design , Development Coding & Unit Testing
Your Answer Requirement Analysis , System Design , Development Coding & Unit Testing
Multiple Choice Multiple Answer Question Characteristics of a test could be:-
Page 30 of 155 30
SCDL – 3rd Semester – Software Engineering and Project Management
Correct Answer Not Redundant , Best of Breed , Neither too simple Nor to Complex
Your Answer Not Redundant , Best of Breed , Neither too simple Nor to Complex
Multiple Choice Multiple Answer Question The outcome of Debugging Process is :-
Correct Answer The Error cause will be detected and corrected , The Error Cause will not be detected
Your Answer The Error cause will be detected and corrected
LIST OF ATTEMPTED QUESTIONS AND ANSWERS Multiple Choice Multiple Answer Question The Customer Requirements could be analyzed by:-
Correct Answer Interviewing , Questionnaire , Meeting with Key Users
Your Answer Interviewing , Questionnaire , Meeting with Key Users
Multiple Choice Multiple Answer Question The Contents which are recorded by the Data Dictionary for an typical item is:-
Correct Answer Definition , Identification , Validation Text & Relationship
Your Answer Table Name , Definition , Validation Text & Relationship
Multiple Choice Single Answer Question An Approach foucsses on Objects and Processing Methods
Correct Answer OOSAD
Your Answer OOSAD
Multiple Choice Multiple Answer Question The Examples of Business Software are
Correct Answer Payroll ,Accounting, , Inventory , customer Relation Management
Your Answer Payroll ,Accounting, , Inventory , customer Relation Management
Multiple Choice Multiple Answer Question A documentation is tested through :-
Correct Answer Technical Review , Actual Operational Review
Your Answer Technical Review , Actual Operational Review
Select The Blank
Page 31 of 155 31
SCDL – 3rd Semester – Software Engineering and Project Management
Question The key requirements of the systems are identified in ________ Phase
Correct Answer Definition
Your Answer Definition
Multiple Choice Single Answer Question Changes in the Customer requirements are understood and incorporated in which
phase? Correct Answer Support
Your Answer Analysis
Multiple Choice Single Answer Question The Software development engineering which builds objects of models independent
of the system under consideration is ? Correct Answer OOSAD
Your Answer OOSAD
True/False Question SQA is ensured through a Quality Management System.
Correct Answer True
Your Answer True
Select The Blank Question The ________ phase of software engineering focuses on how data are to be
structured and programs are to be developed Correct Answer Development
Your Answer Development
Multiple Choice Single Answer Question A process which breaks statement of work into smaller activities with clear start -
finish definition is called as :- Correct Answer Work Break Down Structure
Your Answer Work Break Down Structure
Multiple Choice Multiple Answer Question System Testing Techniques are :-
Correct Answer Alpha Test , Beta Test
Your Answer Stress Testing
Page 32 of 155 32
SCDL – 3rd Semester – Software Engineering and Project Management
Select The Blank Question ________ is the Significant project risk the management has to face in software
development activity due to budgeting constraints. Correct Answer Funding
Your Answer Resources
True/False Question A software review is a filter for the software development process.
Correct Answer True
Your Answer True
Select The Blank Question ________ layer of the Systems focuses on User Interfaces, data entry, operation
flows and maintenance. Correct Answer Operational
Your Answer Operational
Multiple Choice Multiple Answer Question Artificial Intelligent Domain Systems Could be
Correct Answer Expert System , Image & Voice Recognition System , Neural Networks
Your Answer Expert System , Image & Voice Recognition System , Neural Networks
True/False Question A Software solution is evolved in parts as in an incremental fashion in incremental
model Correct Answer True
Your Answer True
Multiple Choice Single Answer Question A modeling and Analysis tool used for System Design and Development is :-
Correct Answer Data Flow Diagrams
Your Answer Data Flow Diagrams
Multiple Choice Multiple Answer Question Project Metrics helps the project manager in following ways :-
Correct Answer Assess Product Quality regularly , Minimize the Development Schedule
Your Answer Minimize the Development Schedule , Assess Product Quality regularly , Planning the Risk
Page 33 of 155 33
SCDL – 3rd Semester – Software Engineering and Project Management
Multiple Choice Single Answer Question How to develop or build a particular software module is defined by
Correct Answer Software Engineering Methods
Your Answer Software Engineering Methods
Select The Blank Question ________ combines software, Hardware and a software engineering database to
create a software engineering environment for hardware Correct Answer CASE
Your Answer CASE
Select The Blank Question A ________ is an activity incorporating both software quality control and quality
assurance. Correct Answer Software Quality Management
Your Answer Software Quality Management
Select The Blank Question The basic tangible measure of the software is ________
Correct Answer Lines of Code
Your Answer Lines of Code
Multiple Choice Single Answer Question To set the standards and measure and compare the quality according to American
Heritage dictionary, what is essential? Correct Answer Attribute
Your Answer Attribute
Multiple Choice Single Answer Question The extent of software functions with precision without any failure is :-
Correct Answer Reliability
Your Answer Reliability
True/False Question Stress Testing is a part of Integration testing.
Correct Answer False
Page 34 of 155 34
SCDL – 3rd Semester – Software Engineering and Project Management
Your Answer False
True/False Question Six Sigma is one of the most widely used strategy for statistical quality assurance in
an industry. Correct Answer True
Your Answer True
Multiple Choice Multiple Answer Question The Customer Requirements could be analysed by :-
Correct Answer Interviewing , Questionnaire , Meeting with Key Users
Your Answer Interviewing , Questionnaire , Meeting with Key Users
True/False Question White Box Testing Measures the Correctness of the Inputs and Basic Processes.
Correct Answer True
Your Answer True
Multiple Choice Multiple Answer Question Following are the data models namely:-
Correct Answer Hierarchical Model , Network Model , Relational Model
Your Answer Hierarchical Model , Network Model , Relational Model
True/False Question Black Box testing Finds out Missing Functions & Interface Errors.
Correct Answer True
Your Answer True
Multiple Choice Multiple Answer Question In a Software Risk Management Risk drivers are :-
Correct Answer Technology , People , Requirements
Your Answer Technology , People , Requirements
Multiple Choice Single Answer Question A set of activities ensure that software correctly implements a specific function is
called as software:-
Page 35 of 155 35
SCDL – 3rd Semester – Software Engineering and Project Management
Correct Answer Verification
Your Answer Verification
Multiple Choice Single Answer Question Source Code of the Software is available so that the engineers can make the local
modifications and use the component Correct Answer Open Source
Your Answer Open Source
Match The FollowingQuestion Correct Answer Your Answer
System Software Operating System Operating System
Machine & assembly Language Scientists and engineers Embeded System
software efficiency Optimum use of resources Good Documentation
Software Usability Good Documentation Optimum use of resources
True/False Question Software Development becomes a costly and risky if the the development process
does not follow a systematic, scientific approach to produce the software Correct Answer True
Your Answer True
Select The Blank Question ________ tests confirms that the needs and requirements are fulfilled on the
deployment platform. Correct Answer Beta
Your Answer Beta
Select The Blank Question The Failure Curve of a Hardware is called as ________
Correct Answer Bathtub Curve
Your Answer Bathtub Curve
True/False Question The ultimate goal of the SQA is to write test cases which fixes the errors.
Correct Answer False
Your Answer False
Page 36 of 155 36
SCDL – 3rd Semester – Software Engineering and Project Management
True/False Question The Data Management is not easy with relational Model.
Correct Answer False
Your Answer False
Select The Blank Question A ________ is largely depends upon the meeting of functional requirements and
performance measures with ease in operations. Correct Answer Customer Satisfaction
Your Answer Customer Satisfaction
Multiple Choice Multiple Answer Question Risk Management is a Process based on application of :-
Correct Answer Game Theory , Probability Theory , Decision Theory
Your Answer Probability Theory , Logical Theory , Decision Theory
Multiple Choice Single Answer Question A Discipline that integrates Process, Methods and tools for development of a software
is Correct Answer Software Engineering
Your Answer Software Engineering
Multiple Choice Multiple Answer Question Software Risk could be of :-
Correct Answer Process Risk , Project Risk , Product Risk
Your Answer Process Risk , Project Risk , Product Risk
Multiple Choice Single Answer Question A method of testing carried out formally with the help of some kind of checklist:-
Correct Answer Inspections
Your Answer Walkthroughs
Match The FollowingQuestion Correct Answer Your Answer
Testing Error Tracing Error Tracing
Page 37 of 155 37
SCDL – 3rd Semester – Software Engineering and Project Management
Test Plan Test Cases Test Document
Functional Testing Functions & Features Test Cases
Test Case Test Document Functions & Features
Select The Blank Question A ________ Measures the Efforts / cost / time used to achieve the output.
Correct Answer Efficiency
Your Answer Effectiveness & Efficiency
Page 38 of 155 38
SCDL – 3rd Semester – Software Engineering and Project Management
LIST OF ATTEMPTED QUESTIONS AND ANSWERS Multiple Choice Multiple Answer Question Project Risk Management Includes:-
Correct Answer Risk Mitigation , Risk Prevention , Risk Avoidance
Your Answer Risk Analysis , Risk Prevention , Risk Mitigation
Multiple Choice Single Answer Question A method of testing carried out formally with the help of some kind of checklist:-
Correct Answer Inspections
Your Answer Walkthroughs
Select The Blank Question A collection of programs written to service other set of programs and its functions is called as
________ Correct Answer System Software
Your Answer System Software
True/False Question Reactive risk strategies are applied to deal with risk when it occurs.
Correct Answer True
Your Answer True
Multiple Choice Multiple Answer Question Fourth generation technology helps to control
Correct Answer Effort , Resource , Cost development
Your Answer Effort , Resource , Cost development
Multiple Choice Single Answer Question A project management activity globally viewed as :-
Correct Answer A System
Your Answer Software Development
Multiple Choice Single Answer Question A Discipline that integrates Process, Methods and tools for development of a software is
Correct Answer Software Engineering
Your Answer Software Engineering
Page 39 of 155 39
SCDL – 3rd Semester – Software Engineering and Project Management
Multiple Choice Multiple Answer Question Design Constraints include:-
Correct Answer Resource Limitations , Platform Limitations , Protocol Limitations
Your Answer Resource Limitations , Platform Limitations , Protocol Limitations
Multiple Choice Multiple Answer Question The types of Software are
Correct Answer Business Software , Embedded Software , System Software
Your Answer Business Software , Embedded Software , System Software
Multiple Choice Multiple Answer Question The most affected elements of the Quality of the software is:-
Correct Answer Customer , Developer , Stake Holders
Your Answer Customer , Developer
True/False Question Documentation testing tests and verifies whether the troubleshooting is easily achieved or not.
Correct Answer True
Your Answer True
Multiple Choice Multiple Answer Question The Scope of the Software Project is defined by Statement of Work which is agreed by ?
Correct Answer Users , Stakeholders , Customers
Your Answer Stakeholders , Customers
Select The Blank Question Usually the test cases are written using ________.
Correct Answer Testing Techniques
Your Answer Procedural Plan
Match The FollowingQuestion Correct Answer Your Answer
Development of the Software Software Programs Software Modules
Page 40 of 155 40
SCDL – 3rd Semester – Software Engineering and Project Management
Corrective Maintenance Maintenance
Process, Tools & Methods Software Engineering Layers Software Engineering Layers
Requirement Specifications Definition Phase Analysis
Multiple Choice Single Answer Question An Approach which majorly focuses on Functions and data structure designed for those
functions. Correct Answer SSAD
Your Answer OOSAD
Multiple Choice Single Answer Question How to develop or build a particular software module is defined by
Correct Answer Software Engineering Methods
Your Answer ISO - 9001
True/False Question System Performance is measured through effectiveness and its efficiency.
Correct Answer True
Your Answer True
Multiple Choice Multiple Answer Question The stages of the Iterative Models are
Correct Answer Requirement Analysis , System Design , Development Coding & Unit Testing
Your Answer Requirement Analysis , System Design , Development Coding & Unit Testing
Multiple Choice Single Answer Question What is the tool which enforces consistency in naming the entities across the system?
Correct Answer Data Dictionary
Your Answer ERD
Multiple Choice Single Answer Question A process which is iterative in nature which ensures that the RDD & SRS is transformed into
Design to meet the data is called:- Correct Answer Design
Your Answer Development
Page 41 of 155 41
SCDL – 3rd Semester – Software Engineering and Project Management
Multiple Choice Single Answer Question At the beginning testing focuses on each component individually, ensuring that it function
properly as a unit or not this is termed as:- Correct Answer Unit Testing
Your Answer Unit Testing
Select The Blank Question PRM stands for ________
Correct Answer Prototyping Model
Your Answer Prototyping Model
Select The Blank Question A ________ is largely depends upon the meeting of functional requirements and performance
measures with ease in operations. Correct Answer Customer Satisfaction
Your Answer Customer Satisfaction
Select The Blank Question The basic tangible measure of the software is ________
Correct Answer Lines of Code
Your Answer Lines of Code
Select The Blank Question Generally in an ongoing project a project manager fixes up more ________ to have proper
control measurement of the project activities Correct Answer Major Milestone
Your Answer Minor Milestone
Select The Blank Question LOC Means________
Correct Answer Lines of Code
Your Answer Lines of Code
True/False Question Risk which can be known is termed as unpredictable risk.
Correct Answer False
Your Answer False
Page 42 of 155 42
SCDL – 3rd Semester – Software Engineering and Project Management
True/False Question System testing checks the abnormality in the software system.
Correct Answer False
Your Answer True
Multiple Choice Single Answer Question A type of testing where the focus is on error/ mistake or fault detection and correction is:-
Correct Answer Process based Testing
Your Answer Unit based testing
True/False Question The prime objective of Formal Technical Review is to locate the error before it passes on to the
other activity. Correct Answer True
Your Answer True
Select The Blank Question A ________ Measures the Quality of the output produced by the System
Correct Answer Effectiveness
Your Answer Effectiveness & Efficiency
True/False Question Software Development becomes complex due to the variety and heterogeneity of requirement
of different Users and Stakeholders Correct Answer True
Your Answer True
True/False Question Software Development becomes a costly and risky if the the development process does not
follow a systematic, scientific approach to produce the software Correct Answer True
Your Answer True
Multiple Choice Single Answer Question A type of testing which mainly focuses on the functional aspect of the software product is:-
Correct Answer Functional Testing
Page 43 of 155 43
SCDL – 3rd Semester – Software Engineering and Project Management
Your Answer Functional Testing
True/False Question A computer system without system software can not function
Correct Answer True
Your Answer True
Multiple Choice Single Answer Question A type of testing in which all the requirements of the module is cross referenced with the
developed module is called as:- Correct Answer Validation Testing
Your Answer Integration Testing
Select The Blank Question A ________ is an activity incorporating both software quality control and quality assurance.
Correct Answer Software Quality Management
Your Answer Software Quality Management
Multiple Choice Single Answer Question The Application of a systematic, disciplined, quantifiable approach to the development,
operation and maintenance of the software is termed as Correct Answer Software Engineering
Your Answer Software Engineering
Multiple Choice Multiple Answer Question The responsibilities of Software Managerare
Correct Answer To maintain budget , Keep schedules from slipping , Improve quality
Your Answer To maintain budget , Keep schedules from slipping , Improve quality
Select The Blank Question ________ type of testing evaluate the logical access to the basic functionality of the System.
Correct Answer Security Testing
Your Answer Security Testing
True/False Question Functional Testing focuses on the Basic Functionality of the Software.
Page 44 of 155 44
SCDL – 3rd Semester – Software Engineering and Project Management
Correct Answer True
Your Answer True
Multiple Choice Single Answer Question The Scope of the work in a Software Project is defined by :-
Correct Answer Statement of Work
Your Answer Requirement Specifications
Multiple Choice Multiple Answer Question Operational Testing is carried out by :-
Correct Answer Recovery Testing , Stress Testing , Performance Testing
Your Answer Alpha & Beta Test , Stress Testing
Match The FollowingQuestion Correct Answer Your Answer
Closed System Parameter are fixed Parameter are fixed
Deterministic System Predictable Behavior Predictable Behavior
Probabilistic System Unpredictable Behavior Controlled Changes
Open System Parameters are Variables Normalized External Parameters
Multiple Choice Multiple Answer Question The Examples of Business Software are
Correct Answer Payroll ,Accounting, , Inventory , customer Relation Management
Your Answer Payroll ,Accounting, , Inventory , customer Relation Management
Multiple Choice Multiple Answer Question A formal Technical Review may include:-
Correct Answer Walkthroughs , Inspections , Roundrobin reviews
Your Answer Inspections , Roundrobin reviews
Multiple Choice Single Answer Question A Process of organizing the sub systems as one system to reduce the number of connectivities
or interfaces:- Correct Answer Simplification
Page 45 of 155 45
SCDL – 3rd Semester – Software Engineering and Project Management
Your Answer Simplification
LIST OF ATTEMPTED QUESTIONS AND ANSWERS Select The Blank Question An Operational deviation made by the user leading to improper result is said to be ________.
Correct Answer Fault or Mistake of the System
Your Answer Defect
Multiple Choice Multiple Answer Question Black Box testing techniques are:-
Correct Answer Graph Based Testing Methods , Equivalence Portioning , Boundary Value Analysis
Your Answer Equivalence Portioning , Boundary Value Analysis , Graph Based Testing Methods
True/False Question The last step in the design process is the Software development.
Correct Answer False
Your Answer False
True/False Question The results of the test case is recorded in the test specification document.
Correct Answer True
Your Answer True
Match The FollowingQuestion Correct Answer Your Answer
Closed System Parameter are fixed Parameter are fixed
Deterministic System Predictable Behavior Predictable Behavior
Probabilistic System Unpredictable Behavior Unpredictable Behavior
Open System Parameters are Variables Parameters are Variables
Select The Blank Question Usually the test cases are written using ________.
Correct Answer Testing Techniques
Your Answer Testing Techniques
Page 46 of 155 46
SCDL – 3rd Semester – Software Engineering and Project Management
Multiple Choice Single Answer Question A type of testing in which all the requirements of the module is cross referenced with the developed
module is called as:- Correct Answer Validation Testing
Your Answer Validation Testing
Multiple Choice Multiple Answer Question Design Constraints include:-
Correct Answer Resource Limitations , Platform Limitations , Protocol Limitations
Your Answer Resource Limitations , Platform Limitations , Protocol Limitations
Select The Blank Question ________ evaluates the run time performance of the system developed.
Correct Answer Performance Testing
Your Answer Beta Test
Multiple Choice Multiple Answer Question The next development in software engineering is
Correct Answer The extensive use od CASE tool for analysis and design , The use of tool generate the code , The use of Component technology
Your Answer Graphical tool , The use of tool generate the code , The extensive use od CASE tool for analysis and design
Select The Blank Question ________ is characterized by longetivity and business criticality
Correct Answer Legacy Software
Your Answer Mainframes
Multiple Choice Single Answer Question Software Engineering attempts to identify what information is to be processed, what function and
performance is desired in which phase? Correct Answer Definition Phase
Your Answer Definition Phase
True/False Question System testing Starts when Software Integration is about to be completed.
Correct Answer False
Page 47 of 155 47
SCDL – 3rd Semester – Software Engineering and Project Management
Your Answer False
Multiple Choice Multiple Answer Question The stages of the Iterative Models are
Correct Answer Requirement Analysis , System Design , Development Coding & Unit Testing
Your Answer Requirement Analysis , System Design , Development Coding & Unit Testing
Multiple Choice Single Answer Question Who Defines SE as the application of a Systematic, disciplined and quantifiable approach to the
development and maintenance of a Software Correct Answer IEEE
Your Answer ISO - 9001
Multiple Choice Single Answer Question A set of Computer Programs which performs set of preset functions is called as ?
Correct Answer Software
Your Answer Software
Multiple Choice Single Answer Question A Systematic approach to organise and documents the need of the customer which is a basis for
software development is :- Correct Answer Requirements Management
Your Answer Project Management
Match The FollowingQuestion Correct Answer Your Answer
Development of the Software Software Programs Software Programs
Corrective Maintenance Maintenance
Process, Tools & Methods Software Engineering Layers Software Engineering Layers
Requirement Specifications Definition Phase Definition Phase
Multiple Choice Single Answer Question A System which is designed to interact and to exchange with the environment and reacts to the
inputs accordingly:- Correct Answer Open System
Your Answer Open System
Page 48 of 155 48
SCDL – 3rd Semester – Software Engineering and Project Management
True/False Question E-R Diagrams are used to identify the Weak and Strong Relations.
Correct Answer True
Your Answer True
Select The Blank Question The Plat Form of the software is developed keeping in mind of certain hardware and ________
Correct Answer Operating System
Your Answer Operating System
True/False Question System testing checks the abnormality in the software system.
Correct Answer False
Your Answer True
Multiple Choice Single Answer Question Changes in the Customer requirements are understood and incorporated in which phase?
Correct Answer Support
Your Answer Analysis
Select The Blank Question Inadequacy or misout in SRS & RDD is ________.
Correct Answer Defect
Your Answer Defect
Multiple Choice Single Answer Question How to develop or build a particular software module is defined by
Correct Answer Software Engineering Methods
Your Answer Software Engineering Methods
Multiple Choice Single Answer Question The Extend to which the software product is protected from an unauthorized access is :-
Correct Answer Integrity
Your Answer Integrity
Page 49 of 155 49
SCDL – 3rd Semester – Software Engineering and Project Management
True/False Question Systems running on web platforms needs high level of protection from testers.
Correct Answer False
Your Answer True
Multiple Choice Multiple Answer Question Resources required for a Software development activity could be :-
Correct Answer Development Environment , Reusable Components , People
Your Answer People , Development Environment , Reusable Components
Multiple Choice Multiple Answer Question The most affected elements of the Quality of the software is:-
Correct Answer Customer , Developer , Stake Holders
Your Answer Customer , Developer , Stake Holders
Select The Blank Question A ________ is an activity incorporating both software quality control and quality assurance.
Correct Answer Software Quality Management
Your Answer Software Quality Management
Multiple Choice Single Answer Question A process to commit the organisation to start the project and complete the project document
providing a broad spectrum of the project is :- Correct Answer Project Initiation
Your Answer Project Initiation
Multiple Choice Single Answer Question A Cost which includes quality planning, measuring & monitoring the quality aspect and its training
is :- Correct Answer Achievement Cost
Your Answer Quality Training Cost
Multiple Choice Multiple Answer Question Resources required for a Software development activity could be :-
Correct Answer People , Development Environment , Reusable Components
Page 50 of 155 50
SCDL – 3rd Semester – Software Engineering and Project Management
Your Answer People , Development Environment , Reusable Components
True/False Question Six Sigma is one of the most widely used strategy for statistical quality assurance in an industry.
Correct Answer True
Your Answer True
Select The Blank Question The basic tangible measure of the software is ________
Correct Answer Lines of Code
Your Answer Lines of Code
Multiple Choice Single Answer Question A technique in which participants have freedom to express their views is known as :-
Correct Answer Brainstorming
Your Answer Questionnaire
Multiple Choice Single Answer Question A Modification of the Software is done to accommodate the changes forced by the external
environment is Correct Answer Adaptive Maintenance
Your Answer Adaptive Maintenance
Multiple Choice Single Answer Question The Application of a systematic, disciplined, quantifiable approach to the development, operation and
maintenance of the software is termed as Correct Answer Software Engineering
Your Answer Software Engineering
Multiple Choice Single Answer Question The variation in quality is monitored by keeping the attributes at the desired level, this phenomenon
is called as :- Correct Answer Quality Control
Your Answer Check & Go Tactics
Multiple Choice Multiple Answer Question Project Risk Management Includes:-
Page 51 of 155 51
SCDL – 3rd Semester – Software Engineering and Project Management
Correct Answer Risk Prevention , Risk Avoidance , Risk Mitigation
Your Answer Risk Prevention , Risk Avoidance , Risk Mitigation
Multiple Choice Single Answer Question A Discipline that integrates Process, Methods and tools for development of a software is
Correct Answer Software Engineering
Your Answer Software Engineering
True/False Question A computer system without system software can not function
Correct Answer True
Your Answer True
Select The Blank Question The ________ phase of software engineering focuses on how data are to be structured and
programs are to be developed Correct Answer Development
Your Answer Development
True/False Question The Major risk involved in software project is to identify the programmers required and the pay scales
of them. Correct Answer False
Your Answer False
Select The Blank Question One of the most important guideline for the reviewing the product is review the product not the
________. Correct Answer Producer
Your Answer Project
Multiple Choice Multiple Answer Question Fourth generation technology helps to control
Correct Answer Effort , Resource , Cost development
Your Answer Effort , Resource , Cost development
Select The Blank
Page 52 of 155 52
SCDL – 3rd Semester – Software Engineering and Project Management
Question A ________ is understood as a possibility of Loss.
Correct Answer Risk
Your Answer Un Structured Plan
LIST OF ATTEMPTED QUESTIONS AND ANSWERS True/False Question Spiral model itself is a model which is base for other software development models
Correct Answer False
Your Answer False
Multiple Choice Multiple Answer Question The broad quality parameters are:-
Correct Answer Reliability , Safety , Security
Your Answer Safety , Security , Reliability
Select The Blank Question ________ is achieved by carving out a module that is responsible for any unique function
and which does not need to interact with other parts of the system. Correct Answer Functional Dependency
Your Answer Functional Dependency
Multiple Choice Single Answer Question A set of activities ensure that software correctly implements a specific function is called as
software:- Correct Answer Verification
Your Answer Verification
Multiple Choice Single Answer Question Software Engineering attempts to identify what information is to be processed, what
function and performance is desired in which phase? Correct Answer Definition Phase
Your Answer Definition Phase
True/False Question Reactive risk strategies are applied to deal with risk when it occurs.
Correct Answer True
Page 53 of 155 53
SCDL – 3rd Semester – Software Engineering and Project Management
Your Answer True
Multiple Choice Multiple Answer Question Test Case Design for real time systems strategically should include:-
Correct Answer Task Testing , Behavioral Testing , Intertask Testing
Your Answer Task Testing , Behavioral Testing , Intertask Testing
Multiple Choice Single Answer Question How to develop or build a particular software module is defined by
Correct Answer Software Engineering Methods
Your Answer Software Engineering Methods
True/False Question Proactive risk strategies are applied to deal with risk when it occurs.
Correct Answer False
Your Answer False
Select The Blank Question A ________ Measures the Quality of the output produced by the System
Correct Answer Effectiveness
Your Answer Effectiveness
Select The Blank Question SE Methodology rides on two components, System Engineering and ________.
Correct Answer Development Engineering
Your Answer Development Engineering
Multiple Choice Single Answer Question The Application of a systematic, disciplined, quantifiable approach to the development,
operation and maintenance of the software is termed as Correct Answer Software Engineering
Your Answer Software Engineering
Multiple Choice Multiple Answer Question Project Risk Management Includes:-
Correct Answer Risk Prevention , Risk Avoidance , Risk Mitigation
Page 54 of 155 54
SCDL – 3rd Semester – Software Engineering and Project Management
Your Answer Risk Prevention , Risk Avoidance , Risk Mitigation
Multiple Choice Multiple Answer Question The Customer Requirements could be analysed by :-
Correct Answer Interviewing , Questionnaire , Meeting with Key Users
Your Answer Interviewing , Questionnaire , Meeting with Key Users
Multiple Choice Single Answer Question A document which identifies and helps the project manager to focus on the grey areas or
critical functions in the project is :- Correct Answer Software Requirement Specifications
Your Answer Software Requirement Specifications
Multiple Choice Single Answer Question The Software development engineering which builds objects of models independent of the
system under consideration is ? Correct Answer OOSAD
Your Answer OOSAD
Select The Blank Question ________ tests confirms that the needs and requirements are fulfilled on the deployment
platform. Correct Answer Beta
Your Answer Beta
Multiple Choice Multiple Answer Question Test cases are built for :-
Correct Answer Data Structure , Specific Value Conditions
Your Answer Data Structure , Specific Value Conditions
True/False Question System testing Starts when Software Integration is about to be completed.
Correct Answer False
Your Answer False
Multiple Choice Multiple Answer Question The Scope of the Software Project is defined by Statement of Work which is agreed by ?
Correct Answer Users , Stakeholders , Customers
Page 55 of 155 55
SCDL – 3rd Semester – Software Engineering and Project Management
Your Answer Users , Stakeholders , Customers
Multiple Choice Multiple Answer Question The Functionality of the Client application is tested using :-
Correct Answer Server Tests , Database Tests , Transaction Tests
Your Answer Server Tests , Database Tests , Transaction Tests
Multiple Choice Multiple Answer Question The Examples of Business Software are
Correct Answer Payroll ,Accounting, , Inventory , customer Relation Management
Your Answer Payroll ,Accounting, , Inventory , customer Relation Management
Select The Blank Question The Errors which have impact on look and feel of the system is classified as ________
errors Correct Answer Cosmetic
Your Answer Cosmetic
Multiple Choice Single Answer Question What is the tool which enforces consistency in naming the entities across the system?
Correct Answer Data Dictionary
Your Answer Data Dictionary
Match The FollowingQuestion Correct Answer Your Answer
World Wide Web Content provider Content provider
Software Deteriorates Deteriorates
System Software File Management File Management
Application Software Standalone Programs Standalone Programs
True/False Question SQA is ensured through a Quality Management System.
Correct Answer True
Your Answer True
Select The Blank
Page 56 of 155 56
SCDL – 3rd Semester – Software Engineering and Project Management
Question A ________ deals with identification and assessment of potential hazards of software failing and its impact on the systems.
Correct Answer Software Safety
Your Answer Software Safety
Select The Blank Question Requirements Management Begins with ________.
Correct Answer Identification
Your Answer Identification
True/False Question Documentation testing tests and verifies whether the troubleshooting is easily achieved or
not. Correct Answer True
Your Answer True
Multiple Choice Multiple Answer Question The responsibilities of Software Managerare
Correct Answer To maintain budget , Keep schedules from slipping , Improve quality
Your Answer To maintain budget , Keep schedules from slipping , Improve quality
Multiple Choice Multiple Answer Question Risk Management is a Process based on application of :-
Correct Answer Game Theory , Probability Theory , Decision Theory
Your Answer Game Theory , Probability Theory , Decision Theory
Multiple Choice Single Answer Question A process to commit the organisation to start the project and complete the project
document providing a broad spectrum of the project is :- Correct Answer Project Initiation
Your Answer Project Initiation
Multiple Choice Single Answer Question A system for the support of software development is called
Correct Answer Computer Aided Software Engineering
Your Answer Computer Aided Software Engineering
Multiple Choice Multiple Answer
Page 57 of 155 57
SCDL – 3rd Semester – Software Engineering and Project Management
Question The stages of the Iterative Models are
Correct Answer Requirement Analysis , System Design , Development Coding & Unit Testing
Your Answer Requirement Analysis , System Design , Development Coding & Unit Testing
Multiple Choice Multiple Answer Question Following are the data models namely:-
Correct Answer Hierarchical Model , Network Model , Relational Model
Your Answer Hierarchical Model , Network Model , Relational Model
Match The FollowingQuestion Correct Answer Your Answer
Testing Error Tracing Error Tracing
Test Plan Test Cases Test Cases
Functional Testing Functions & Features Functions & Features
Test Case Test Document Test Document
True/False Question People, Procedures and Parameters are the Drivers of the Technology.
Correct Answer False
Your Answer False
Select The Blank Question A ________ arises due to uncertainties involved in assessing, estimating various inputs to
the software process. Correct Answer Process Risk
Your Answer Process Risk
Select The Blank Question A unit tests major focuses on ________
Correct Answer Processes & Code
Your Answer Processes & Code
True/False Question SRS is one of the cause of not meeting the SQA.
Correct Answer True
Page 58 of 155 58
SCDL – 3rd Semester – Software Engineering and Project Management
Your Answer True
True/False Question The Emphasis in SSAD is on functions and features.
Correct Answer True
Your Answer True
Multiple Choice Single Answer Question The variation in quality is monitored by keeping the attributes at the desired level, this
phenomenon is called as :- Correct Answer Quality Control
Your Answer Quality Control
Select The Blank Question ________ is a System Engineering approach that is used to define architecture that
enables a business to use Information Effectively. Correct Answer Business Processing Engineering
Your Answer Business Processing Engineering
Select The Blank Question Usually the test cases are written using ________.
Correct Answer Testing Techniques
Your Answer Testing Techniques
True/False Question Database Design is a major component of system design and development.
Correct Answer True
Your Answer True
Multiple Choice Single Answer Question A Step in risk Management which identifies and enumerates the risk is :-
Correct Answer Risk Identification
Your Answer Risk Identification
Multiple Choice Single Answer Question A model which creates sources and destinations for the data flows of data i.e. input and
output is:- Correct Answer Data Flow Diagrams
Page 59 of 155 59
SCDL – 3rd Semester – Software Engineering and Project Management
Your Answer Data Flow Diagrams
LIST OF ATTEMPTED QUESTIONS AND ANSWERS
Multiple Choice Multiple Answer Question Software Risk could be of :-
Correct Answer Process Risk , Project Risk , Product Risk
Your Answer Process Risk , Project Risk , Product Risk
Multiple Choice Multiple Answer Question Architecture Design Consists of:-
Correct Answer Module Structure , Program Structure , Hierarchy in the Structure
Your Answer Module Structure , Program Structure , Process Structure
Multiple Choice Multiple Answer Question The Customer Requirements could be analyzed by:-
Correct Answer Interviewing , Questionnaire , Meeting with Key Users
Your Answer Interviewing , Questionnaire , Case Study
Multiple Choice Single Answer Question A layer in which rules and regulations , functions and processes, dataflows and
process flows are visualized:- Correct Answer Logical
Your Answer Logical
Multiple Choice Multiple Answer Question Characteristics of a test could be:-
Correct Answer Not Redundant , Best of Breed , Neither too simple Nor to Complex
Your Answer Not Redundant , Best of Breed
Multiple Choice Multiple Answer Question A formal Technical Review may include:-
Correct Answer Walkthroughs , Inspections , Roundrobin reviews
Your Answer Walkthroughs , Inspections , Roundrobin reviews
Multiple Choice Single Answer Question A Phenomenon which states that over a period of times the system gets into a
phase of degrading and disorganization is:-
Page 60 of 155 60
SCDL – 3rd Semester – Software Engineering and Project Management
Correct Answer Entropy
Your Answer Discard
Multiple Choice Single Answer Question A method of testing carried out formally with the help of some kind of checklist:-
Correct Answer Inspections
Your Answer Module
Multiple Choice Single Answer Question A Software developed to perform certain functionality and later on embedded into
the hardware is called as Correct Answer Embedded Software
Your Answer Embedded Software
Multiple Choice Multiple Answer Question Following are the data models namely:-
Correct Answer Hierarchical Model , Network Model , Relational Model
Your Answer Hierarchical Model , Network Model , Relational Model
Multiple Choice Single Answer Question A principle in which the system is factored into smaller sub systems:-
Correct Answer Decomposition
Your Answer Decomposition
True/False Question A computer system without system software can not function
Correct Answer True
Your Answer False
Multiple Choice Multiple Answer Question Some of the Steps involve in Integration Testing is :-
Correct Answer Main Control Module is a Test Driver , Tests are conducted as each component is added , Regression Testing is done
Your Answer Main Control Module is a Test Driver , Tests are conducted as each component is added , Stress Testing
True/False
Page 61 of 155 61
SCDL – 3rd Semester – Software Engineering and Project Management
Question SRS is Systems requirement specifications in the software development phase
Correct Answer True
Your Answer False
Select The Blank Question ________ is achieved by carving out a module that is responsible for any unique
function and which does not need to interact with other parts of the system. Correct Answer Functional Dependency
Your Answer Functional Dependency
Multiple Choice Single Answer Question A software metrics use a measure of the functionality delivered by the application as
a normalisation value is :- Correct Answer Function oriented Software Metrics
Your Answer Function oriented Software Metrics
True/False Question E-R Diagrams are used to identify the Weak and Strong Relations.
Correct Answer True
Your Answer True
Select The Blank Question ________ is a process of executing a program with the intent of finding an error.
Correct Answer Testing
Your Answer Testing
True/False Question Software Development becomes a costly and risky if the the development process
does not follow a systematic, scientific approach to produce the software Correct Answer True
Your Answer True
True/False Question Domain Specific applications are developed mostly integrating components which
are similar in functionality Correct Answer True
Your Answer True
Page 62 of 155 62
SCDL – 3rd Semester – Software Engineering and Project Management
True/False Question Recovery testing focuses on the Cost Recovery Plan of the Software Implemented.
Correct Answer False
Your Answer False
True/False Question System testing checks the abnormality in the software system.
Correct Answer False
Your Answer False
Select The Blank Question A ________ deals with identification and assessment of potential hazards of
software failing and its impact on the systems. Correct Answer Software Safety
Your Answer Software Safety
Multiple Choice Single Answer Question A process in which a project is broken down into smaller manageable units is called
as :- Correct Answer Project Compartmentalization
Your Answer Project Compartmentalization
Select The Blank Question ________ type of an error is class I error and needs corrective measures to be
implemented immediately. Correct Answer Fatal
Your Answer Fatal
Multiple Choice Multiple Answer Question Project Metrics enable a software project manager to:-
Correct Answer Assess the Status of the Ongoing Project , Identify the Risk Potential , Uncover problem areas before they go Critical
Your Answer Assess the Status of the Ongoing Project , Identify the Risk Potential , Uncover problem areas before they go Critical
Multiple Choice Single Answer Question A Cost of in-process inspection, calibration and maintenance and testing of all that
is used in the process of producing the required quality is :- Correct Answer Process Maintenance Cost
Your Answer Process Maintenance Cost
Page 63 of 155 63
SCDL – 3rd Semester – Software Engineering and Project Management
Select The Blank Question The Errors which have impact on look and feel of the system is classified as
________ errors Correct Answer Cosmetic
Your Answer Cosmetic
Multiple Choice Multiple Answer Question Resources required for a Software development activity could be :-
Correct Answer Development Environment , Reusable Components , People
Your Answer People , Development Environment , Reusable Components
Match The FollowingQuestion Correct Answer Your Answer
Spiral Model Boehm Spiral model Boehm Spiral model
Legacy software Poor Quality Poor Quality
Objects Attribute, Methods Attribute, Methods
SSAD yourdan & DeMarco Structured Methodology
Multiple Choice Single Answer Question A DD type which models internals of the process i.e. the details namely how ,
where, by whom and so on is known as:- Correct Answer Physical DFD
Your Answer System DFD
Select The Blank Question The objective of a ________ is to test for what we want to achieve and not what is
actually achieved. Correct Answer Test Plan
Your Answer Test Plan
True/False Question The Water Fall Model is used where the risk factor is almost nil
Correct Answer True
Your Answer False
True/False
Page 64 of 155 64
SCDL – 3rd Semester – Software Engineering and Project Management
Question Black Box testing Finds out Missing Functions & Interface Errors.
Correct Answer True
Your Answer False
Select The Blank Question ________ is a System Engineering approach that is used to define architecture that
enables a business to use Information Effectively. Correct Answer Business Processing Engineering
Your Answer Business Processing Engineering
Multiple Choice Multiple Answer Question SQA efforts most primarily assures:-
Correct Answer Software Quality , Software Reliability , Software Availability
Your Answer Software Quality , Software Reliability , Software Maintenance
Select The Blank Question ________ testing confirms that the needs and requirements are fulfilled in the
development environment. Correct Answer Alpha
Your Answer Alpha
Select The Blank Question An Operational deviation made by the user leading to improper result is said to be
________. Correct Answer Fault or Mistake of the System
Your Answer Error
Match The FollowingQuestion Correct Answer Your Answer
Entity Object which is Uniquely Distinguished
Object which is Uniquely Distinguished
Hierarchical Model Tree Structure Tree Structure
Network Model Network Communications Mesh Structure
Relational Model Data are Linked Sequence Structure
Multiple Choice Multiple Answer Question A documentation is tested through :-
Page 65 of 155 65
SCDL – 3rd Semester – Software Engineering and Project Management
Correct Answer Technical Review , Actual Operational Review
Your Answer Technical Review , Actual Operational Review
Select The Blank Question In ________Model the risk of the Software development is almost Nil
Correct Answer Water Fall
Your Answer Incremental
Select The Blank Question Each & every ________ has a Specific format as a record.
Correct Answer Test
Your Answer Verification Procedure
True/False Question SE is applied for software development through Engineering Methods
Correct Answer True
Your Answer True
Multiple Choice Multiple Answer Question The Contents which are recorded by the Data Dictionary for an typical item is:-
Correct Answer Definition , Identification , Validation Text & Relationship
Your Answer Table Name , Definition , Identification
Multiple Choice Single Answer Question A testing is carried out continuously as the software components are built or
incremented is:- Correct Answer Incremental Testing
Your Answer Incremental Testing
Multiple Choice Single Answer Question A Process of organizing the sub systems as one system to reduce the number of
connectivities or interfaces:- Correct Answer Simplification
Your Answer Decoupling
Multiple Choice Single Answer Question A process which audits and inspects whether the people responsible for quality and
Page 66 of 155 66
SCDL – 3rd Semester – Software Engineering and Project Management
customer satisfaction follow the quality control measures & standards or not is :- Correct Answer Quality Assurance
Your Answer Quality Control
LIST OF ATTEMPTED QUESTIONS AND ANSWERS
True/False Question CAD/CAM/CAE are the examples of embedded Software
Correct Answer False
Your Answer False
Multiple Choice Multiple Answer Question The Scope of the Software Project is defined by Statement of Work which is agreed by
? Correct Answer Users , Stakeholders , Customers
Your Answer Users , Stakeholders , Customers
Select The Blank Question A ________ Measures the Quality of the output produced by the System
Correct Answer Effectiveness
Your Answer Design
Multiple Choice Multiple Answer Question IN OOSAD, Objects have
Correct Answer attribute , Methods , relationship
Your Answer attribute , Methods , relationship
Multiple Choice Multiple Answer Question System Testing Techniques are :-
Correct Answer Alpha Test , Beta Test
Your Answer Alpha Test , Beta Test , Stress Testing
Select The Blank Question The Errors which have impact on look and feel of the system is classified as ________
errors
Page 67 of 155 67
SCDL – 3rd Semester – Software Engineering and Project Management
Correct Answer Cosmetic
Your Answer Cosmetic
Select The Blank Question A Module Tests focuses on ________.
Correct Answer Functions & Design
Your Answer Processes & Code
Select The Blank Question ________ evaluates the run time performance of the system developed.
Correct Answer Performance Testing
Your Answer Performance Testing
Multiple Choice Single Answer Question The Application of a systematic, disciplined, quantifiable approach to the development,
operation and maintenance of the software is termed as Correct Answer Software Engineering
Your Answer Software Engineering
Select The Blank Question Usually the test cases are written using ________.
Correct Answer Testing Techniques
Your Answer Requirements Specifications
Match The FollowingQuestion Correct Answer Your Answer
Recovery Testing Recovery Procedures Recovery Procedures
Integration testing Top Down Approach Integration Testing
Bottom Up Approach Integration Testing Top Down Approach
System testing Alpha & Beta Testing Alpha & Beta Testing
Select The Blank Question ________ layer of the Systems focuses on User Interfaces, data entry, operation flows
and maintenance. Correct Answer Operational
Your Answer Operational
Page 68 of 155 68
SCDL – 3rd Semester – Software Engineering and Project Management
Multiple Choice Single Answer Question A system for the support of software development is called
Correct Answer Computer Aided Software Engineering
Your Answer Supporting Modules
Match The FollowingQuestion Correct Answer Your Answer
Testing Error Tracing Error Tracing
Test Plan Test Cases Test Cases
Functional Testing Functions & Features Functions & Features
Test Case Test Document Test Document
Multiple Choice Single Answer Question A Software that makes use of non numerical algorithms to solve complex problems
that are not amenable to straightforward analysis Correct Answer Artificial Intelligence
Your Answer Artificial Intelligence
True/False Question The Unit of the Software is the smallest entity to be tested.
Correct Answer True
Your Answer True
Multiple Choice Single Answer Question Software Engineering attempts to identify what information is to be processed, what
function and performance is desired in which phase? Correct Answer Definition Phase
Your Answer Definition Phase
Multiple Choice Single Answer Question A Phenomenon which states that over a period of times the system gets into a phase
of degrading and disorganization is:- Correct Answer Entropy
Your Answer Entropy
Multiple Choice Single Answer Question Changes in the Customer requirements are understood and incorporated in which
Page 69 of 155 69
SCDL – 3rd Semester – Software Engineering and Project Management
phase? Correct Answer Support
Your Answer Support
Multiple Choice Single Answer Question A Modification of the Software is done to accommodate the changes forced by the
external environment is Correct Answer Adaptive Maintenance
Your Answer Corrective & Adaptive Maintenance
Multiple Choice Multiple Answer Question The Examples of Business Software are
Correct Answer Payroll ,Accounting, , Inventory , customer Relation Management
Your Answer Payroll ,Accounting, , Inventory , customer Relation Management
Multiple Choice Single Answer Question A Principle in which the Functional Cohesion between the sub system is maintained:-
Correct Answer Decomposition
Your Answer Simplification
True/False Question The results of the test case is recorded in the test specification document.
Correct Answer True
Your Answer True
Multiple Choice Multiple Answer Question Resources required for a Software development activity could be :-
Correct Answer People , Development Environment , Reusable Components
Your Answer People , Development Environment , Reusable Components
Multiple Choice Single Answer Question An Output of a Structured System Analysis is:-
Correct Answer Software Requirement Specification
Your Answer Software Analysis
Select The Blank
Page 70 of 155 70
SCDL – 3rd Semester – Software Engineering and Project Management
Question A ________ has to be performed regularly throughout the achievement life cycle.
Correct Answer Risk Management
Your Answer Risk Management
True/False Question A computer system without system software can not function
Correct Answer True
Your Answer True
True/False Question Spiral model itself is a model which is base for other software development models
Correct Answer False
Your Answer False
True/False Question Software Development becomes complex due to the variety and heterogeneity of
requirement of different Users and Stakeholders Correct Answer True
Your Answer True
Multiple Choice Multiple Answer Question The Contents which are recorded by the Data Dictionary for an typical item is:-
Correct Answer Definition , Identification , Validation Text & Relationship
Your Answer Definition , Identification , Validation Text & Relationship
True/False Question The Major risk involved in software project is to identify the programmers required and
the pay scales of them. Correct Answer False
Your Answer False
Multiple Choice Multiple Answer Question Test Case Design for real time systems strategically should include:-
Correct Answer Task Testing , Behavioral Testing , Intertask Testing
Your Answer Task Testing , Behavioral Testing , Intertask Testing
Page 71 of 155 71
SCDL – 3rd Semester – Software Engineering and Project Management
Select The Blank Question Generally in an ongoing project a project manager fixes up more ________ to have
proper control measurement of the project activities Correct Answer Major Milestone
Your Answer Major Milestone
Select The Blank Question ________ type of an error is class I error and needs corrective measures to be
implemented immediately. Correct Answer Fatal
Your Answer Fatal
True/False Question SE is applied for software development through Engineering Methods
Correct Answer True
Your Answer True
Multiple Choice Single Answer Question A Discipline that integrates Process, Methods and tools for development of a software
is Correct Answer Software Engineering
Your Answer Software Engineering
Multiple Choice Single Answer Question A testing technique which is critically important and it ensures correctness of all inputs
and basic processes of a unit is called as ? Correct Answer White Box Testing
Your Answer White Box Testing
Multiple Choice Multiple Answer Question Resources required for a Software development activity could be :-
Correct Answer People , Development Environment , Reusable Components
Your Answer People , Development Environment , Reusable Components
Multiple Choice Multiple Answer Question A documentation is tested through :-
Correct Answer Technical Review , Actual Operational Review
Your Answer Technical Review , Actual Operational Review
Page 72 of 155 72
SCDL – 3rd Semester – Software Engineering and Project Management
Multiple Choice Single Answer Question How to develop or build a particular software module is defined by
Correct Answer Software Engineering Methods
Your Answer Software Engineering Methods
Multiple Choice Single Answer Question A software which directly communicates with the hardware and provides an interface
to perform certain tasks is termed as Correct Answer System Software
Your Answer System Software
Multiple Choice Single Answer Question A System in which next state of the system can be predicted without doubt is :-
Correct Answer Deterministic
Your Answer Deterministic
True/False Question Documentation testing tests and verifies whether the troubleshooting is easily
achieved or not. Correct Answer True
Your Answer True
Multiple Choice Single Answer Question When the System requirements are easy to establish and are stable, the development
is customer specific, and changes are not foreseen then the model used is? Correct Answer Water Fall Model
Your Answer Water Fall Model
True/False Question The last step in the design process is the Software development.
Correct Answer False
Your Answer False
Select The Blank Question The ________ phase of software engineering focuses on how data are to be
structured and programs are to be developed Correct Answer Development
Page 73 of 155 73
SCDL – 3rd Semester – Software Engineering and Project Management
Your Answer Development
Multiple Choice Single Answer Question A software which resides in the read only memory and controls the functions of the
resident Products Correct Answer Embedded Software
Your Answer Embedded Software
LIST OF ATTEMPTED QUESTIONS AND ANSWERS
True/False Question SRS is Systems requirement specifications in the software development phase
Correct Answer True
Your Answer True
Multiple Choice Multiple Answer Question Fourth generation technology helps to control
Correct Answer Effort , Resource , Cost development
Your Answer Resource , Cost development , Effort
Multiple Choice Multiple Answer Question The responsibilities of Software Managerare
Correct Answer To maintain budget , Keep schedules from slipping , Improve quality
Your Answer To maintain budget , Keep schedules from slipping , Improve quality
Multiple Choice Single Answer Question A process which ensures that the materials input (Process input), the manufacturing
process (software development process) and outgoing quality are of requisite standards is :-
Correct Answer Quality Assurance
Your Answer Quality Control
Multiple Choice Multiple Answer Question The software designed with the correct choice of technology and architecture to ensure:
Correct Answer Customer Satisfaction , On-time Delivery , Developed with the budgeted cost
Page 74 of 155 74
SCDL – 3rd Semester – Software Engineering and Project Management
Your Answer Customer Satisfaction , On-time Delivery , Developed with the budgeted cost
Select The Blank Question A ________ is understood as a possibility of Loss.
Correct Answer Risk
Your Answer Risk
Select The Blank Question The key requirements of the systems are identified in ________ Phase
Correct Answer Definition
Your Answer Definition
Multiple Choice Single Answer Question A type of testing which mainly focuses on the functional aspect of the software product
is:- Correct Answer Functional Testing
Your Answer Functional Testing
True/False Question Risk which can be known is termed as unpredictable risk.
Correct Answer False
Your Answer False
True/False Question Database Design is a major component of system design and development.
Correct Answer True
Your Answer True
Select The Blank Question The Plat Form of the software is developed keeping in mind of certain hardware and
________ Correct Answer Operating System
Your Answer Operating System
Match The FollowingQuestion Correct Answer Your Answer
Page 75 of 155 75
SCDL – 3rd Semester – Software Engineering and Project Management
Development of the Software Software Programs Software Programs
Corrective Maintenance Maintenance
Process, Tools & Methods Software Engineering Layers Software Engineering Layers
Requirement Specifications Definition Phase Definition Phase
Multiple Choice Single Answer Question Most of the Software's Continues to be custom built because
Correct Answer Reusability of the Component
Your Answer Reusability of the Component
Multiple Choice Single Answer Question A type of testing where the focus is user and user Behavior is:-
Correct Answer Usage based testing
Your Answer Usage based testing
Select The Blank Question Software is classified into two categories, Generic and ________.
Correct Answer Cutomised
Your Answer Cutomised
Multiple Choice Single Answer Question A degree to which the design aspect of the Quality is met is termed as :-
Correct Answer Quality Conformance
Your Answer Quality Conformance
Multiple Choice Multiple Answer Question Database Design Specification include:-
Correct Answer Data Model , Internal & External File Structure , Referential Details
Your Answer Data Model , Referential Details , Normalization
Select The Blank Question ________ is developed or engineered not manufactured
Correct Answer Software
Your Answer Software
Page 76 of 155 76
SCDL – 3rd Semester – Software Engineering and Project Management
Multiple Choice Single Answer Question Source Code of the Software is available so that the engineers can make the local
modifications and use the component Correct Answer Open Source
Your Answer Open Source
Select The Blank Question In ________Model the risk of the Software development is almost Nil
Correct Answer Water Fall
Your Answer Water Fall
Multiple Choice Single Answer Question The Software development engineering which builds objects of models independent of
the system under consideration is ? Correct Answer OOSAD
Your Answer OOSAD
Multiple Choice Single Answer Question A Process of organizing the sub systems as one system to reduce the number of
connectivities or interfaces:- Correct Answer Simplification
Your Answer Decoupling
True/False Question White Box Testing Measures the Correctness of the Inputs and Basic Processes.
Correct Answer True
Your Answer False
Multiple Choice Single Answer Question The Extent of effort to locate the error and fix it is :-
Correct Answer Maintainability
Your Answer Maintainability
Multiple Choice Single Answer Question The success of the software depends upon ?
Correct Answer Usability
Page 77 of 155 77
SCDL – 3rd Semester – Software Engineering and Project Management
Your Answer Usability
Select The Blank Question The objective of a ________ is to test for what we want to achieve and not what is
actually achieved. Correct Answer Test Plan
Your Answer Testing
Multiple Choice Multiple Answer Question The outcome of Debugging Process is :-
Correct Answer The Error cause will be detected and corrected , The Error Cause will not be detected
Your Answer The Error cause will be detected and corrected , The Error Cause will not be detected
Multiple Choice Multiple Answer Question Software Risk could be of :-
Correct Answer Process Risk , Project Risk , Product Risk
Your Answer Process Risk , Project Risk , Product Risk
True/False Question Stress Testing is a part of Integration testing.
Correct Answer False
Your Answer False
Multiple Choice Multiple Answer Question The Factors enabling easy change are :-
Correct Answer Maintainability , Flexibility , Testability
Your Answer Maintainability , Flexibility , Reusability
Multiple Choice Single Answer Question A series of steps framed to meet the desired standards during the complete phase of
production is called as :- Correct Answer Quality Control
Your Answer Quality Control
Select The Blank Question Inadequacy or misout in SRS & RDD is ________.
Page 78 of 155 78
SCDL – 3rd Semester – Software Engineering and Project Management
Correct Answer Defect
Your Answer Error
True/False Question Reactive risk strategies are applied to deal with risk when it occurs.
Correct Answer True
Your Answer True
Select The Blank Question To become a registered, one of the quality assurance system models contained in ISO
9000 a company's quality system is scrutinized by ________. Correct Answer Third Party Auditor
Your Answer ISO Manager
True/False Question System testing Starts when Software Integration is about to be completed.
Correct Answer False
Your Answer False
Select The Blank Question ________ is a System Engineering approach that is used to define architecture that
enables a business to use Information Effectively. Correct Answer Business Processing Engineering
Your Answer Business Processing Engineering
Multiple Choice Multiple Answer Question Characteristics of a test could be:-
Correct Answer Not Redundant , Best of Breed , Neither too simple Nor to Complex
Your Answer Not Redundant , Yield Better Results
Multiple Choice Single Answer Question A set of Computer Programs which performs set of preset functions is called as ?
Correct Answer Software
Your Answer Software
Multiple Choice Multiple Answer
Page 79 of 155 79
SCDL – 3rd Semester – Software Engineering and Project Management
Question In a Software Risk Management Risk drivers are :-
Correct Answer Technology , People , Requirements
Your Answer Technology , People , Requirements
Match The FollowingQuestion Correct Answer Your Answer
Normalization Table Design Data Management With Ease
Performance Management Efficiency & Effectiveness Efficiency & Effectiveness
Relational Model Data Management With Ease Relationship Management
E-R Diagrams Strong & Weak Entities Table Design
True/False Question Six Sigma is one of the most widely used strategy for statistical quality assurance in an
industry. Correct Answer True
Your Answer True
Multiple Choice Single Answer Question The First step in the design and development process is to build the:-
Correct Answer Data Dictionary
Your Answer Data Models
Select The Blank Question An incorrect decision by the designer, programmer or analyst that leads to improper
result is an ________. Correct Answer Error
Your Answer Defect
Multiple Choice Single Answer Question A type of testing carried out during the software product development process is:-
Correct Answer Execution Based testing
Your Answer Plan based testing
True/False Question Software Development becomes a costly and risky if the the development process does
not follow a systematic, scientific approach to produce the software Correct Answer True
Page 80 of 155 80
SCDL – 3rd Semester – Software Engineering and Project Management
Your Answer True
Multiple Choice Single Answer Question A System which is designed to interact and to exchange with the environment and reacts
to the inputs accordingly:- Correct Answer Open System
Your Answer Open System
True/False Question The ultimate goal of the SQA is to write test cases which fixes the errors.
Correct Answer False
Your Answer False
LIST OF ATTEMPTED QUESTIONS AND ANSWERS
Multiple Choice Single Answer Question A testing technique which is critically important and it ensures correctness of all inputs
and basic processes of a unit is called as ? Correct Answer White Box Testing
Your Answer Black Box Testing
Select The Blank Question Cohesion and Coupling is the criteria for measuring ________.
Correct Answer Functional Dependency
Your Answer Module Dependency
Select The Blank Question An incorrect decision by the designer, programmer or analyst that leads to improper
result is an ________. Correct Answer Error
Your Answer Defect
True/False Question E-R Diagrams are used to identify the Weak and Strong Relations.
Correct Answer True
Your Answer True
Multiple Choice Single Answer
Page 81 of 155 81
SCDL – 3rd Semester – Software Engineering and Project Management
Question A Standard Method which helps in keeping the system as an acceptable standards is:-
Correct Answer Periodical Maintenance
Your Answer Periodical Maintenance
Select The Blank Question The company shall establish a ________ to control flow of documents that relate to the
requirements of the ISO. Correct Answer Document Control System
Your Answer Document Control System
True/False Question The last step in the design process is the Software development.
Correct Answer False
Your Answer False
Multiple Choice Multiple Answer Question The Contents which are recorded by the Data Dictionary for an typical item is:-
Correct Answer Definition , Identification , Validation Text & Relationship
Your Answer Definition , Identification , Validation Text & Relationship
Select The Blank Question ________ testing confirms that the needs and requirements are fulfilled in the
development environment. Correct Answer Alpha
Your Answer Beta
Multiple Choice Single Answer Question A model in which software development cycle is sequential process is :-
Correct Answer Waterfall Model
Your Answer Spiral Model
Multiple Choice Multiple Answer Question Some of the Steps involve in Integration Testing is :-
Correct Answer Main Control Module is a Test Driver , Tests are conducted as each component is added , Regression Testing is done
Your Answer Tests are conducted as each component is added , Regression Testing is done , Stress Testing
Page 82 of 155 82
SCDL – 3rd Semester – Software Engineering and Project Management
Multiple Choice Single Answer Question When the System requirements are easy to establish and are stable, the development is
customer specific, and changes are not foreseen then the model used is? Correct Answer Water Fall Model
Your Answer Water Fall Model
True/False Question System testing checks the abnormality in the software system.
Correct Answer False
Your Answer False
Multiple Choice Multiple Answer Question Project Metrics enable a software project manager to:-
Correct Answer Assess the Status of the Ongoing Project , Identify the Risk Potential , Uncover problem areas before they go Critical
Your Answer Assess the Status of the Ongoing Project , Identify the Risk Potential , Manage the resources
Multiple Choice Multiple Answer Question The Customer Requirements could be analyzed by:-
Correct Answer Interviewing , Questionnaire , Meeting with Key Users
Your Answer Interviewing , Questionnaire , Meeting with Key Users
Multiple Choice Single Answer Question A type of testing where the focus is on error/ mistake or fault detection and correction is:-
Correct Answer Process based Testing
Your Answer Unit based testing
Multiple Choice Multiple Answer Question White Box Testing Checks :-
Correct Answer All Paths in the process are correctly operational , All Logical decision are executed with true or false , All Loops are executed
Your Answer All Paths in the process are correctly operational , All Logical decision are executed with true or false , All Loops are executed
Multiple Choice Multiple Answer Question OOSAD development approach uses
Correct Answer Objects , Process modeling , Object attributes
Your Answer Objects , Object attributes , Sub-system approach
Page 83 of 155 83
SCDL – 3rd Semester – Software Engineering and Project Management
Select The Blank Question A ________ is used to show the system flow stage by stage in a logical sequence
Correct Answer System Flow Chart
Your Answer System Flow Chart
True/False Question Simplification rationalizes the complex , breakdown into clusters, making a meaningful
and functionally complete design. Correct Answer True
Your Answer False
Multiple Choice Single Answer Question A method of testing carried out formally with the help of some kind of checklist:-
Correct Answer Inspections
Your Answer Inspections
True/False Question SQA is ensured through a Quality Management System.
Correct Answer True
Your Answer True
Multiple Choice Single Answer Question Most of the Software's Continues to be custom built because
Correct Answer Reusability of the Component
Your Answer Reusability of the Component
True/False Question Systems running on web platforms needs high level of protection from testers.
Correct Answer False
Your Answer False
Multiple Choice Multiple Answer Question Operational Testing is carried out by :-
Correct Answer Recovery Testing , Stress Testing , Performance Testing
Page 84 of 155 84
SCDL – 3rd Semester – Software Engineering and Project Management
Your Answer Recovery Testing , Stress Testing , Performance Testing
Match The FollowingQuestion Correct Answer Your Answer
Testing Error Tracing Error Tracing
Test Plan Test Cases Test Cases
Functional Testing Functions & Features Functions & Features
Test Case Test Document Test Document
True/False Question SE is applied for software development through Engineering Methods
Correct Answer True
Your Answer True
Multiple Choice Single Answer Question A Systematic approach to organise and documents the need of the customer which is a
basis for software development is :- Correct Answer Requirements Management
Your Answer Project Management
Select The Blank Question The Plat Form of the software is developed keeping in mind of certain hardware and
________ Correct Answer Operating System
Your Answer Operating System
Select The Blank Question A ________ Measures the Efforts / cost / time used to achieve the output.
Correct Answer Efficiency
Your Answer Efficiency
Multiple Choice Multiple Answer Question System Design Consists of:-
Correct Answer Level DFD's , System Flowcharts , ERD's
Your Answer Level DFD's , System Flowcharts , ERD's
Page 85 of 155 85
SCDL – 3rd Semester – Software Engineering and Project Management
Multiple Choice Single Answer Question A unit testing technique which concentrates only of the functions and features of the
software product is:- Correct Answer Black Box Testing
Your Answer Black Box Testing
Select The Blank Question Each & every ________ has a Specific format as a record.
Correct Answer Test
Your Answer Validation
Multiple Choice Multiple Answer Question Project Metrics helps the project manager in following ways :-
Correct Answer Minimize the Development Schedule , Assess Product Quality regularly
Your Answer Assess Product Quality regularly , Planning the Task , Planning the Risk
Multiple Choice Multiple Answer Question The responsibilities of Software Managerare
Correct Answer To maintain budget , Keep schedules from slipping , Improve quality
Your Answer To maintain budget , Keep schedules from slipping , Improve quality
Multiple Choice Single Answer Question A Cost which includes quality planning, measuring & monitoring the quality aspect and
its training is :- Correct Answer Achievement Cost
Your Answer Achievement Cost
Multiple Choice Single Answer Question A process of acquiring hardware, software and development services and entering into
contract with customers and business partners to deliver the software product is :- Correct Answer Project Procurement Management
Your Answer Project Procurement Management
Multiple Choice Multiple Answer Question Software Risk could be of :-
Correct Answer Process Risk , Project Risk , Product Risk
Your Answer Process Risk , Project Risk , Product Risk
Page 86 of 155 86
SCDL – 3rd Semester – Software Engineering and Project Management
True/False Question People, Procedures and Parameters are the Drivers of the Technology.
Correct Answer False
Your Answer True
Match The FollowingQuestion Correct Answer Your Answer
Development of the Software Software Programs Software Programs
Corrective Maintenance Maintenance
Process, Tools & Methods Software Engineering Layers Software Engineering Layers
Requirement Specifications Definition Phase Definition Phase
Multiple Choice Single Answer Question A type of testing which verifies that all the system elements are meshed properly and
that overall system function / performance is achieved is:- Correct Answer System testing
Your Answer System testing
Select The Blank Question A ________ is the most effective filter from a quality assurance stand point.
Correct Answer Formal Technical Review
Your Answer Formal Technical Review
Select The Blank Question A ________ is an activity incorporating both software quality control and quality
assurance. Correct Answer Software Quality Management
Your Answer Software Quality Management
Select The Blank Question In ________ model the data elements are organized indifferent areas that work together
through network communications. Correct Answer Network
Your Answer Network
Multiple Choice Multiple Answer
Page 87 of 155 87
SCDL – 3rd Semester – Software Engineering and Project Management
Question Artificial Intelligent Domain Systems Could be
Correct Answer Expert System , Image & Voice Recognition System , Neural Networks
Your Answer Expert System , Image & Voice Recognition System , Neural Networks
True/False Question The results of the test case is recorded in the test specification document.
Correct Answer True
Your Answer True
True/False Question The prime objective of Formal Technical Review is to locate the error before it passes on
to the other activity. Correct Answer True
Your Answer True
LIST OF ATTEMPTED QUESTIONS AND ANSWERS
Multiple Choice Multiple Answer Question Project Risk Management Includes:-
Correct Answer Risk Prevention , Risk Avoidance , Risk Mitigation
Your Answer Risk Mitigation , Risk Prevention , Risk Avoidance
True/False Question Proactive risk strategies are applied to deal with risk when it occurs.
Correct Answer False
Your Answer False
Select The Blank Question The company should establish a ________ and maintain a documented quality system
as a means of ensuring that it conforms to the specified requirements of ISO. Correct Answer Quality System Procedure
Your Answer Quality Management System
Select The Blank Question The objective of a ________ is to test for what we want to achieve and not what is
actually achieved.
Page 88 of 155 88
SCDL – 3rd Semester – Software Engineering and Project Management
Correct Answer Test Plan
Your Answer Testing
True/False Question The Emphasis in SSAD is on functions and features.
Correct Answer True
Your Answer True
Multiple Choice Multiple Answer Question The most affected elements of the Quality of the software is:-
Correct Answer Customer , Developer , Stake Holders
Your Answer Customer , Developer , Stake Holders
True/False Question Software Development becomes complex due to the variety and heterogeneity of
requirement of different Users and Stakeholders Correct Answer True
Your Answer True
Multiple Choice Multiple Answer Question A documentation is tested through :-
Correct Answer Technical Review , Actual Operational Review
Your Answer Technical Review , Actual Operational Review
Multiple Choice Single Answer Question In Interface Stage of SSAD phase the focus is on:-
Correct Answer User Comfort
Your Answer Functions
Multiple Choice Multiple Answer Question IN OOSAD, Objects have
Correct Answer attribute , Methods , relationship
Your Answer attribute , Methods , relationship
Multiple Choice Single Answer Question A Software developed to perform certain functionality and later on embedded into the
Page 89 of 155 89
SCDL – 3rd Semester – Software Engineering and Project Management
hardware is called as Correct Answer Embedded Software
Your Answer Embedded Software
Multiple Choice Single Answer Question An Approach foucsses on Objects and Processing Methods
Correct Answer OOSAD
Your Answer OOSAD
Multiple Choice Single Answer Question Who Defines SE as the application of a Systematic, disciplined and quantifiable
approach to the development and maintenance of a Software Correct Answer IEEE
Your Answer IEEE
Multiple Choice Single Answer Question A testing technique which reveals errors like Incorrect functions , Missing Functions or
Interface errors is:- Correct Answer Black Box Testing
Your Answer Black Box Testing
Multiple Choice Multiple Answer Question Risk Management is a Process based on application of :-
Correct Answer Game Theory , Probability Theory , Decision Theory
Your Answer Game Theory , Probability Theory , Decision Theory
Multiple Choice Multiple Answer Question The broad quality parameters are:-
Correct Answer Reliability , Safety , Security
Your Answer Reliability , Safety , Security
Multiple Choice Single Answer Question The extent the software meets the customer quality goals and expectations is termed
as :- Correct Answer Correctness
Your Answer Reliability
Multiple Choice Multiple Answer
Page 90 of 155 90
SCDL – 3rd Semester – Software Engineering and Project Management
Question The Examples of Business Software are
Correct Answer Payroll ,Accounting, , Inventory , customer Relation Management
Your Answer Payroll ,Accounting, , Inventory , customer Relation Management
Multiple Choice Multiple Answer Question Following are the data models namely:-
Correct Answer Hierarchical Model , Network Model , Relational Model
Your Answer Hierarchical Model , Relational Model , Modular Model
Multiple Choice Single Answer Question The Software development engineering which builds objects of models independent of
the system under consideration is ? Correct Answer OOSAD
Your Answer OOSAD
Multiple Choice Single Answer Question A software which resides in the read only memory and controls the functions of the
resident Products Correct Answer Embedded Software
Your Answer Embedded Software
True/False Question Errors in documentation give rise to fatal results.
Correct Answer True
Your Answer True
Match The FollowingQuestion Correct Answer Your Answer
Entity Object which is Uniquely Distinguished
Object which is Uniquely Distinguished
Hierarchical Model Tree Structure Tree Structure
Network Model Network Communications Network Communications
Relational Model Data are Linked Sequence Structure
Multiple Choice Multiple Answer Question The types of Software are
Page 91 of 155 91
SCDL – 3rd Semester – Software Engineering and Project Management
Correct Answer Embedded Software , System Software , Business Software
Your Answer Business Software , Embedded Software , System Software
Multiple Choice Multiple Answer Question The stages of the Iterative Models are
Correct Answer Requirement Analysis , System Design , Development Coding & Unit Testing
Your Answer Requirement Analysis , System Design , Development Coding & Unit Testing
Multiple Choice Multiple Answer Question Legacy software -Poor quality has
Correct Answer Inextensible design , Convoluted Code , Poor or nonexistent documentation
Your Answer Inextensible design , Convoluted Code , Poor or nonexistent documentation
Select The Blank Question ________ is achieved by carving out a module that is responsible for any unique
function and which does not need to interact with other parts of the system. Correct Answer Functional Dependency
Your Answer Module Dependency
True/False Question Domain Specific applications are developed mostly integrating components which are
similar in functionality Correct Answer True
Your Answer True
Select The Blank Question ________ is the Significant project risk the management has to face in software
development activity due to budgeting constraints. Correct Answer Funding
Your Answer Resources
Select The Blank Question The key requirements of the systems are identified in ________ Phase
Correct Answer Definition
Your Answer Definition
Multiple Choice Multiple Answer
Page 92 of 155 92
SCDL – 3rd Semester – Software Engineering and Project Management
Question Architecture Design Consists of:-
Correct Answer Module Structure , Program Structure , Hierarchy in the Structure
Your Answer Module Structure , Hierarchy in the Structure , Process Structure
Multiple Choice Single Answer Question A Project performance measurement technique that integrates scope, time and cost data
is :- Correct Answer Earned Value Analysis
Your Answer Earned Value Analysis
Select The Blank Question The ________ phase of software engineering focuses on how data are to be structured
and programs are to be developed Correct Answer Development
Your Answer Development
Multiple Choice Single Answer Question A process which is iterative in nature which ensures that the RDD & SRS is transformed
into Design to meet the data is called:- Correct Answer Design
Your Answer Design
Multiple Choice Single Answer Question A process which breaks statement of work into smaller activities with clear start - finish
definition is called as :- Correct Answer Work Break Down Structure
Your Answer Project Planning
Multiple Choice Multiple Answer Question A formal Technical Review may include:-
Correct Answer Walkthroughs , Inspections , Roundrobin reviews
Your Answer Walkthroughs , Inspections , Roundrobin reviews
Multiple Choice Single Answer Question An Approach which majorly focuses on Functions and data structure designed for those
functions. Correct Answer SSAD
Your Answer OOSAD
Page 93 of 155 93
SCDL – 3rd Semester – Software Engineering and Project Management
Multiple Choice Single Answer Question Source Code of the Software is available so that the engineers can make the local
modifications and use the component Correct Answer Open Source
Your Answer Open Source
Multiple Choice Single Answer Question At Functional Level of the SSAD the design focuses on:-
Correct Answer Functions and Features
Your Answer Structured Approach
Multiple Choice Multiple Answer Question The software designed with the correct choice of technology and architecture to ensure:
Correct Answer Customer Satisfaction , On-time Delivery , Developed with the budgeted cost
Your Answer Customer Satisfaction , On-time Delivery , Developed with the budgeted cost
Multiple Choice Multiple Answer Question RMMM Plan deals with :-
Correct Answer Mitigation , Monitoring , Management
Your Answer Mitigation , Monitoring , Management
Select The Blank Question Inventory Control System which is designed based on demand and supply variations
could be an example of ________ system Correct Answer Probabilistic
Your Answer Probabilistic
Multiple Choice Single Answer Question A testing is carried out continuously as the software components are built or incremented
is:- Correct Answer Incremental Testing
Your Answer Incremental Testing
Select The Blank Question To become a registered, one of the quality assurance system models contained in ISO
9000 a company's quality system is scrutinized by ________. Correct Answer Third Party Auditor
Your Answer Third Party Auditor
Page 94 of 155 94
SCDL – 3rd Semester – Software Engineering and Project Management
Match The FollowingQuestion Correct Answer Your Answer
Spiral Model Boehm Spiral model Boehm Spiral model
Legacy software Poor Quality yourdan & DeMarco
Objects Attribute, Methods Attribute, Methods
SSAD yourdan & DeMarco Structured Methodology
Multiple Choice Multiple Answer Question Boehm's Model has following Stages:-
Correct Answer Production , Engineering
Your Answer Engineering , Production , Inception
Multiple Choice Single Answer Question A process of identifying, assessing , evaluating risk exposure, prioritizing the risk
incidences, and developing risk monitoring, management and mitigation plan is :- Correct Answer Project Risk Management
Your Answer Project Risk Management
LIST OF ATTEMPTED QUESTIONS AND ANSWERS
Multiple Choice Single Answer Question A process of creating a document Statement of Work, and planning the major task
deliveries is :- Correct Answer Project Planning
Your Answer Project Planning
Select The Blank Question A ________ deals with identification and assessment of potential hazards of software
failing and its impact on the systems. Correct Answer Software Safety
Your Answer Software Testing
Select The Blank Question In ________Model the risk of the Software development is almost Nil
Page 95 of 155 95
SCDL – 3rd Semester – Software Engineering and Project Management
Correct Answer Water Fall
Your Answer Incremental
True/False Question Reactive risk strategies are applied to deal with risk when it occurs.
Correct Answer True
Your Answer True
Multiple Choice Single Answer Question A process which ensures that the materials input (Process input), the manufacturing
process (software development process) and outgoing quality are of requisite standards is :-
Correct Answer Quality Assurance
Your Answer Quality Control
Multiple Choice Multiple Answer Question In a Software Risk Management Risk drivers are :-
Correct Answer Technology , People , Requirements
Your Answer Technology , People , Requirements
Multiple Choice Single Answer Question A Step in risk Management which identifies and enumerates the risk is :-
Correct Answer Risk Identification
Your Answer Risk Identification
Multiple Choice Multiple Answer Question System Testing Techniques are :-
Correct Answer Alpha Test , Beta Test
Your Answer Alpha Test , Beta Test
True/False Question An E-R Diagram explain in graphical Model the nature of relations and attributes.
Correct Answer True
Your Answer True
Multiple Choice Single Answer
Page 96 of 155 96
SCDL – 3rd Semester – Software Engineering and Project Management
Question A Discipline that integrates Process, Methods and tools for development of a software is
Correct Answer Software Engineering
Your Answer Software Engineering
Match The FollowingQuestion Correct Answer Your Answer
OOSAD Object Oriented Approach Object Oriented Approach
IEEE Institute of Electrical and Electronics Engineers
Institute of Electrical and Electronics Engineers
Water Fall Model Customer Specific Customer Specific
SSAD Structured Approach Structured Approach
Multiple Choice Single Answer Question Changes in the Customer requirements are understood and incorporated in which
phase? Correct Answer Support
Your Answer Development
Multiple Choice Single Answer Question A system for the support of software development is called
Correct Answer Computer Aided Software Engineering
Your Answer Computer Aided Software Engineering
Select The Blank Question Software is classified into two categories, Generic and ________.
Correct Answer Cutomised
Your Answer Cutomised
Multiple Choice Single Answer Question A Modification of the Software is done to accommodate the changes forced by the
external environment is Correct Answer Adaptive Maintenance
Your Answer Adaptive Maintenance
True/False Question Recovery testing focuses on the Cost Recovery Plan of the Software Implemented.
Correct Answer False
Page 97 of 155 97
SCDL – 3rd Semester – Software Engineering and Project Management
Your Answer False
Multiple Choice Single Answer Question The extent of software functions with precision without any failure is :-
Correct Answer Reliability
Your Answer Reliability
Multiple Choice Single Answer Question A set of Computer Programs which performs set of preset functions is called as ?
Correct Answer Software
Your Answer Software
Select The Blank Question Inadequacy or misout in SRS & RDD is ________.
Correct Answer Defect
Your Answer Defect
Multiple Choice Multiple Answer Question Black Box testing techniques are:-
Correct Answer Graph Based Testing Methods , Equivalence Portioning , Boundary Value Analysis
Your Answer Equivalence Portioning , Boundary Value Analysis , Graph Based Testing Methods
True/False Question Documentation testing tests and verifies whether the troubleshooting is easily achieved
or not. Correct Answer True
Your Answer False
Multiple Choice Single Answer Question A Phenomenon which states that over a period of times the system gets into a phase of
degrading and disorganization is:- Correct Answer Entropy
Your Answer Entropy
Multiple Choice Single Answer Question A type of testing which mainly focuses on the functional aspect of the software product
is:-
Page 98 of 155 98
SCDL – 3rd Semester – Software Engineering and Project Management
Correct Answer Functional Testing
Your Answer Functional Testing
Select The Blank Question A ________ has to be performed regularly throughout the achievement life cycle.
Correct Answer Risk Management
Your Answer Risk Management
Multiple Choice Single Answer Question A software which directly communicates with the hardware and provides an interface to
perform certain tasks is termed as Correct Answer System Software
Your Answer System Software
Multiple Choice Single Answer Question A type of testing in which all the requirements of the module is cross referenced with the
developed module is called as:- Correct Answer Validation Testing
Your Answer Module testing
Select The Blank Question A collection of programs written to service other set of programs and its functions is
called as ________ Correct Answer System Software
Your Answer System Software
Select The Blank Question In the ________ model data elements are organized in tree structure in parent-child
format. Correct Answer Hierarchical
Your Answer Hierarchical
Multiple Choice Multiple Answer Question Characteristics of a test could be:-
Correct Answer Not Redundant , Best of Breed , Neither too simple Nor to Complex
Your Answer Not Redundant , Best of Breed , Neither too simple Nor to Complex
True/False
Page 99 of 155 99
SCDL – 3rd Semester – Software Engineering and Project Management
Question Spiral model itself is a model which is base for other software development models
Correct Answer False
Your Answer True
Select The Blank Question A ________ is all about providing hardware and software tools as and when required by
the development team to manage process effectively Correct Answer Configuration Management
Your Answer Configuration Management
Multiple Choice Single Answer Question The Application of a systematic, disciplined, quantifiable approach to the development,
operation and maintenance of the software is termed as Correct Answer Software Engineering
Your Answer Software Engineering
Select The Blank Question A Module Tests focuses on ________.
Correct Answer Functions & Design
Your Answer Functions & Design
Multiple Choice Multiple Answer Question The Scope of the Software Project is defined by Statement of Work which is agreed by ?
Correct Answer Users , Stakeholders , Customers
Your Answer Users , Stakeholders , Customers
Multiple Choice Multiple Answer Question The next development in software engineering is
Correct Answer The use of tool generate the code , The extensive use od CASE tool for analysis and design , The use of Component technology
Your Answer The use of tool generate the code , The extensive use od CASE tool for analysis and design , The use of Component technology
Multiple Choice Multiple Answer Question Resources required for a Software development activity could be :-
Correct Answer People , Development Environment , Reusable Components
Your Answer People , Development Environment , Reusable Components
Select The Blank
Page 100 of 155 100
SCDL – 3rd Semester – Software Engineering and Project Management
Question ________is a key management in the development of effective software solutions
Correct Answer Software Process Management
Your Answer Software Process Management
Multiple Choice Multiple Answer Question Work Break Down Structure can also be traced back to ?
Correct Answer System Requirements Specifications , Requirement Definition & Description
Your Answer System Requirements Specifications , Requirement Definition & Description , Statement of Work
Multiple Choice Multiple Answer Question SQA efforts most primarily assures:-
Correct Answer Software Quality , Software Reliability , Software Availability
Your Answer Software Quality , Software Reliability , Software Availability
Match The FollowingQuestion Correct Answer Your Answer
Quality Management Cost Cost
ISO 9000 Quality Assurance System Quality Assurance System
Customer Satisfaction Malcolm Baldridge Approach Malcolm Baldridge Approach
Testing Finding Errors & Fixing it Finding Errors & Fixing it
Multiple Choice Multiple Answer Question Black Box testing attempts to find error in following categories :-
Correct Answer Incorrect or Missing Functions , Interface Errors , Performance Errors
Your Answer Incorrect or Missing Functions , Interface Errors , Performance Errors
True/False Question A computer system without system software can not function
Correct Answer True
Your Answer True
True/False Question System Performance is measured through effectiveness and its efficiency.
Correct Answer True
Page 101 of 155 101
SCDL – 3rd Semester – Software Engineering and Project Management
Your Answer True
True/False Question Black Box testing Finds out Missing Functions & Interface Errors.
Correct Answer True
Your Answer True
Multiple Choice Single Answer Question How to develop or build a particular software module is defined by
Correct Answer Software Engineering Methods
Your Answer Software Engineering Methods
True/False Question Database Design is a major component of system design and development.
Correct Answer True
Your Answer True
LIST OF ATTEMPTED QUESTIONS AND ANSWERS Multiple Choice Single AnswerQuestion: Changes in the Customer requirements are understood and incorporated in which phase? Correct Answer: Support Your Answer: Analysis Multiple Choice Single AnswerQuestion: A Software that makes use of non numerical algorithms to solve complex problems that are not amenable to straightforward analysis Correct Answer: Artificial Intelligence Your Answer: Artificial Intelligence Multiple Choice Multiple AnswerQuestion: Following are the data models namely:- Correct Answer: Hierarchical Model , Network Model , Relational Model Your Answer: Hierarchical Model , Network Model , Relational Model Multiple Choice Multiple AnswerQuestion: Project Metrics helps the project manager in following ways :- Correct Answer: Minimize the Development Schedule , Assess Product Quality regularly Your Answer: Assess Product Quality regularly , Planning the Task , Planning the Risk Multiple Choice Multiple AnswerQuestion: White Box Testing Checks :- Correct Answer: All Paths in the process are correctly operational , All Logical decision are executed with true or false , All Loops are executed
Page 102 of 155 102
SCDL – 3rd Semester – Software Engineering and Project Management
Your Answer: All Logical decision are executed with true or false , All Loops are executed , Interfaces are designed Properly Match The FollowingQuestion Correct Answer Your AnswerDevelopment of the Software Software Programs Software Modules Corrective Maintenance Software Programs Process, Tools & Methods Software Engineering Layers Analysis Requirement Specifications Definition Phase Definition Phase Multiple Choice Single AnswerQuestion: A type of testing where the focus is on design and development of the software architecture is termed as:- Correct Answer: Integration Testing Your Answer: Integration Testing Multiple Choice Single AnswerQuestion: An activity that distributes estimated effort across the planned project duration by allocating the effort to specific software engineering tasks is :- Correct Answer: Software Project Scheduling Your Answer: Project Planning Multiple Choice Multiple AnswerQuestion: Testing a Design Includes:- Correct Answer: Test Procedures , Test Plans , Design Renew Plans Your Answer: Test Procedures , Test Plans Multiple Choice Multiple AnswerQuestion: Project Metrics enable a software project manager to:- Correct Answer: Uncover problem areas before they go Critical , Assess the Status of the Ongoing Project , Identify the Risk Potential Your Answer: Assess the Status of the Ongoing Project , Identify the Risk Potential , Manage the resources Match The FollowingQuestion Correct Answer Your AnswerNormalization Table Design Table Design Performance Management Efficiency & Effectiveness Efficiency & Effectiveness Relational Model Data Management With Ease Data Management With Ease E-R Diagrams Strong & Weak Entities Strong & Weak Entities Select The BlankQuestion: An accounting System based on rules and Principles could be an example of ________ System. Correct Answer: Deterministic Your Answer: Deterministic True/FalseQuestion: Proactive risk strategies are applied to deal with risk when it occurs. Correct Answer: False Your Answer: False Multiple Choice Single AnswerQuestion: A set of Computer Programs which performs set of preset functions is called as ? Correct Answer: Software Your Answer: Software
Page 103 of 155 103
SCDL – 3rd Semester – Software Engineering and Project Management
True/FalseQuestion: Systems running on web platforms needs high level of protection from testers. Correct Answer: False Your Answer: True Select The BlankQuestion: ________ testing confirms that the needs and requirements are fulfilled in the development environment. Correct Answer: Alpha Your Answer: Beta Multiple Choice Single AnswerQuestion: Most of the Software's Continues to be custom built because Correct Answer: Reusability of the Component Your Answer: Reusability of the Component Multiple Choice Multiple AnswerQuestion: SQA efforts most primarily assures:- Correct Answer: Software Quality , Software Reliability , Software Availability Your Answer: Software Quality , Software Reliability , Software Availability Multiple Choice Single AnswerQuestion: A System which operates in a unpredictable manner is :- Correct Answer: Probabilistic Your Answer: Probabilistic True/FalseQuestion: The Data Management is not easy with relational Model. Correct Answer: False Your Answer: False Multiple Choice Multiple AnswerQuestion: Risk Management is a Process based on application of :- Correct Answer: Game Theory , Probability Theory , Decision Theory Your Answer: Game Theory , Probability Theory , Decision Theory Multiple Choice Single AnswerQuestion: A layer in which rules and regulations , functions and processes, dataflows and process flows are visualized:- Correct Answer: Logical Your Answer: Operational Multiple Choice Single AnswerQuestion: A Phenomenon which states that over a period of times the system gets into a phase of degrading and disorganization is:- Correct Answer: Entropy Your Answer: Entropy Select The BlankQuestion: Inventory Control System which is designed based on demand and supply variations could be an example of ________ system Correct Answer: Probabilistic Your Answer: Probabilistic
Select The BlankQuestion: PRM stands for ________
Page 104 of 155 104
SCDL – 3rd Semester – Software Engineering and Project Management
Correct Answer: Prototyping Model Your Answer: Prototyping Model Multiple Choice Multiple AnswerQuestion: Project Risk Management Includes:- Correct Answer: Risk Avoidance , Risk Mitigation , Risk Prevention
Select The BlankQuestion: A Module Tests focuses on ________. Correct Answer: Functions & Design Multiple Choice Single AnswerQuestion: A process in which a project is broken down into smaller manageable units is called as :- Correct Answer: Project Compartmentalization Select The BlankQuestion: The company should establish a ________ and maintain a documented quality system as a means of ensuring that it conforms to the specified requirements of ISO. Correct Answer: Quality System Procedure True/FalseQuestion: SRS is Systems requirement specifications in the software development phase Correct Answer: True Select The BlankQuestion: One of the most important guideline for the reviewing the product is review the product not the ________. Correct Answer: Producer True/FalseQuestion: The Emphasis in SSAD is on functions and features. Correct Answer: True Multiple Choice Single AnswerQuestion: Application of Knowledge, Resources , tools and techniques to deliver customer needs within agreed terms of cost and time is :- Correct Answer: Project Management Multiple Choice Multiple AnswerQuestion: RMMM Plan deals with :- Correct Answer: Mitigation , Monitoring , Management
True/FalseQuestion: A Software solution is evolved in parts as in an incremental fashion in incremental model Correct Answer: True True/FalseQuestion: Documentation testing tests and verifies whether the troubleshooting is easily achieved or not. Correct Answer: True Multiple Choice Multiple AnswerQuestion: Design Constraints include:- Correct Answer: Resource Limitations , Platform Limitations , Protocol Limitations
Page 105 of 155 105
SCDL – 3rd Semester – Software Engineering and Project Management
Multiple Choice Single AnswerQuestion: Software Engineering attempts to identify what information is to be processed, what function and performance is desired in which phase? Correct Answer: Definition Phase
Multiple Choice Single AnswerQuestion: A Modification of the Software is done to accommodate the changes forced by the external environment is Correct Answer: Adaptive Maintenance Multiple Choice Single AnswerQuestion: A System flow chart is also called as:- Correct Answer: State Transaction Diagram Select The BlankQuestion: Cohesion and Coupling is the criteria for measuring ________. Correct Answer: Functional Dependency Multiple Choice Single AnswerQuestion: A software metrics use a measure of the functionality delivered by the application as a normalisation value is :- Correct Answer: Function oriented Software Metrics Select The BlankQuestion: The basic tangible measure of the software is ________ Correct Answer: Lines of Code Multiple Choice Single AnswerQuestion: A testing methodology where two types of testing techniques are applied viz. Black Box & White Box Testing is ? Correct Answer: Unit Testing Multiple Choice Single AnswerQuestion: A testing technique which is critically important and it ensures correctness of all inputs and basic processes of a unit is called as ? Correct Answer: White Box Testing Your Answer: Component Testing True/FalseQuestion: A computer system without system software can not function Correct Answer: True Your Answer: True Select The BlankQuestion: The ________ phase of software engineering focuses on how data are to be structured and programs are to be developed Correct Answer: Development Your Answer: Development
LIST OF ATTEMPTED QUESTIONS AND ANSWERS Multiple Choice Multiple AnswerQuestion: Test cases are designed to tests:- Correct Answer: Internal Logic , Software Requirements Your Answer: Internal Logic , Software Requirements , A Quality aspect of a Program
Page 106 of 155 106
SCDL – 3rd Semester – Software Engineering and Project Management
Select The BlankQuestion: Requirements Management Begins with ________. Correct Answer: Identification Your Answer: Identification Select The BlankQuestion: A collection of programs written to service other set of programs and its functions is called as ________ Correct Answer: System Software Your Answer: System Software True/FalseQuestion: System testing Starts when Software Integration is about to be completed. Correct Answer: False Your Answer: True Select The BlankQuestion: ________ layer of the Systems focuses on User Interfaces, data entry, operation flows and maintenance. Correct Answer: Operational Your Answer: Conceptual Select The BlankQuestion: Inadequacy or misout in SRS & RDD is ________. Correct Answer: Defect Your Answer: Error Multiple Choice Single AnswerQuestion: An Approach foucsses on Objects and Processing Methods Correct Answer: OOSAD Your Answer: OOSAD Multiple Choice Multiple AnswerQuestion: Some of the Steps involve in Integration Testing is :- Correct Answer: Main Control Module is a Test Driver , Tests are conducted as each component is added , Regression Testing is done Your Answer: Main Control Module is a Test Driver , Tests are conducted as each component is added , Regression Testing is done , Stress Testing Multiple Choice Single AnswerQuestion: When the System requirements are easy to establish and are stable, the development is customer specific, and changes are not foreseen then the model used is? Correct Answer: Water Fall Model Your Answer: Spiral Model Match The FollowingQuestion Correct Answer Your AnswerWorld Wide Web Content provider Deteriorates Software Deteriorates Wear's Out System Software File Management Integrated System Application Software Standalone Programs File Management Multiple Choice Multiple AnswerQuestion: The stages of the Iterative Models are Correct Answer: Requirement Analysis , System Design , Development Coding & Unit Testing Your Answer: Requirement Analysis , System Design , Development Coding & Unit Testing
Page 107 of 155 107
SCDL – 3rd Semester – Software Engineering and Project Management
Multiple Choice Single AnswerQuestion: At the beginning testing focuses on each component individually, ensuring that it function properly as a unit or not this is termed as:- Correct Answer: Unit Testing Your Answer: Component Testing Select The BlankQuestion: An Operational deviation made by the user leading to improper result is said to be ________. Correct Answer: Fault or Mistake of the System Your Answer: Failure Multiple Choice Single AnswerQuestion: An outcome of Requirements Management Stage is :- Correct Answer: Software Requirement Specifications Your Answer: Software Requirement Specifications Multiple Choice Single AnswerQuestion: A set of activities ensure that the software that has been built is traceable to customer requirements:- Correct Answer: Validation Your Answer: Verification & Validation Multiple Choice Multiple AnswerQuestion: The Examples of Business Software are Correct Answer: Payroll ,Accounting, , Inventory , customer Relation Management Your Answer: Inventory , customer Relation Management , Compiler , Payroll ,Accounting, Select The BlankQuestion: ________ is a System Engineering approach that is used to define architecture that enables a business to use Information Effectively. Correct Answer: Business Processing Engineering Your Answer: Business Processing Engineering Multiple Choice Multiple AnswerQuestion: Boehm's Model has following Stages:- Correct Answer: Production , Engineering Your Answer: Engineering , Engineering , Inception Multiple Choice Multiple AnswerQuestion: Fourth generation technology helps to control Correct Answer: Effort , Resource , Cost development Your Answer: Effort , Resource , Cost development , Coding Match The FollowingQuestion Correct Answer Your AnswerClosed System Parameter are fixed Parameter are fixed Deterministic System Predictable Behavior Parameters are Variables Probabilistic System Unpredictable Behavior Unpredictable Behavior Open System Parameters are Variables Normalized External Parameters True/FalseQuestion: SQA is ensured through a Quality Management System. Correct Answer: True Your Answer: True
Page 108 of 155 108
SCDL – 3rd Semester – Software Engineering and Project Management
Multiple Choice Multiple AnswerQuestion: The next development in software engineering is Correct Answer: The use of Component technology , The use of tool generate the code , The extensive use od CASE tool for analysis and design Your Answer: Graphical tool , The use of tool generate the code , The extensive use od CASE tool for analysis and design , The use of Component technology Select The BlankQuestion: Usually the test cases are written using ________. Correct Answer: Testing Techniques Your Answer: Requirements Specifications Select The BlankQuestion: A ________ is all about providing hardware and software tools as and when required by the development team to manage process effectively Correct Answer: Configuration Management Your Answer: Configuration Management Multiple Choice Multiple AnswerQuestion: The types of Software are Correct Answer: Business Software , Embedded Software , System Software Your Answer: Business Software , Embedded Software , System Software Multiple Choice Single AnswerQuestion: The Behavioral Aspect of the System could be Shown using :- Correct Answer: Data Flow Diagrams Your Answer: System Design True/FalseQuestion: People, Procedures and Parameters are the Drivers of the Technology. Correct Answer: False Your Answer: True True/FalseQuestion: The ultimate goal of the SQA is to write test cases which fixes the errors. Correct Answer: False Your Answer: True Multiple Choice Multiple AnswerQuestion: Software Risk could be of :- Correct Answer: Process Risk , Project Risk , Product Risk Your Answer: Process Risk , Project Risk , Product Risk Multiple Choice Multiple AnswerQuestion: SQA efforts most primarily assures:- Correct Answer: Software Quality , Software Reliability , Software Availability Your Answer: Software Quality , Software Reliability , Software Availability Multiple Choice Single AnswerQuestion: A System which is designed to interact and to exchange with the environment and reacts to the inputs accordingly:- Correct Answer: Open System Your Answer: Open System Multiple Choice Multiple AnswerQuestion: A documentation is tested through :-
Page 109 of 155 109
SCDL – 3rd Semester – Software Engineering and Project Management
Correct Answer: Technical Review , Actual Operational Review Your Answer: Technical Review , Testing Techniques Multiple Choice Single AnswerQuestion: A Model which Supports Modern Software Development is :- Correct Answer: Boehm's Your Answer: Boehm's True/FalseQuestion: SRS is one of the cause of not meeting the SQA. Correct Answer: True Your Answer: False Multiple Choice Multiple AnswerQuestion: Resources required for a Software development activity could be :- Correct Answer: People , Development Environment , Reusable Components Your Answer: People , Development Environment , Reusable Components Multiple Choice Single AnswerQuestion: A process in which a project is broken down into smaller manageable units is called as :- Correct Answer: Project Compartmentalization Your Answer: Project Management Multiple Choice Single AnswerQuestion: A process to commit the organisation to start the project and complete the project document providing a broad spectrum of the project is :- Correct Answer: Project Initiation Your Answer: Project Planning Select The BlankQuestion: ________is a key management in the development of effective software solutions Correct Answer: Software Process Management Your Answer: Software Development Model Select The BlankQuestion: The company shall establish a ________ to control flow of documents that relate to the requirements of the ISO. Correct Answer: Document Control System Your Answer: Document Control System Select The BlankQuestion: ________ type of testing evaluate the logical access to the basic functionality of the System. Correct Answer: Security Testing Your Answer: Security Testing Multiple Choice Multiple AnswerQuestion: A good test is one that has:- Correct Answer: High Probability of detecting an error , Not Redundant , Simple to execute & Independent Your Answer: High Probability of detecting an error , Not Redundant , Simple to execute & Independent
Multiple Choice Multiple AnswerQuestion: The responsibilities of Software Managerare
Page 110 of 155 110
SCDL – 3rd Semester – Software Engineering and Project Management
Correct Answer: To maintain budget , Keep schedules from slipping , Improve quality Your Answer: To maintain budget , Keep schedules from slipping , Improve quality True/FalseQuestion: The last step in the design process is the Software development. Correct Answer: False Your Answer: False Multiple Choice Single AnswerQuestion: A software which resides in the read only memory and controls the functions of the resident Products Correct Answer: Embedded Software Your Answer: Embedded Software Multiple Choice Single AnswerQuestion: A model which creates sources and destinations for the data flows of data i.e. input and output is:- Correct Answer: Data Flow Diagrams Your Answer: Data Flow Diagrams Multiple Choice Multiple AnswerQuestion: The software designed with the correct choice of technology and architecture to ensure: Correct Answer: Customer Satisfaction , On-time Delivery , Developed with the budgeted cost Your Answer: Customer Satisfaction , On-time Delivery , Developed with the budgeted cost True/FalseQuestion: Database Design is a major component of system design and development. Correct Answer: True Your Answer: True
LIST OF ATTEMPTED QUESTIONS AND ANSWERS
Multiple Choice Single AnswerQuestion: In Interface Stage of SSAD phase the focus is on:-Correct Answer: User ComfortYour Answer: Functions Multiple Choice Multiple AnswerQuestion: The Customer Requirements could be analyzed by:-Correct Answer: Interviewing , Questionnaire , Meeting with Key Users Your Answer: Interviewing , Questionnaire , Meeting with Key Users Multiple Choice Single AnswerQuestion: How to develop or build a particular software module is defined byCorrect Answer: Software Engineering MethodsYour Answer: Software Engineering Methods True/FalseQuestion: E-R Diagrams are used to identify the Weak and Strong Relations.Correct Answer: TrueYour Answer: False
True/FalseQuestion: Black Box testing Finds out Missing Functions & Interface Errors.
Page 111 of 155 111
SCDL – 3rd Semester – Software Engineering and Project Management
Correct Answer: TrueYour Answer: True True/FalseQuestion: The ultimate goal of the SQA is to write test cases which fixes the errors.Correct Answer: FalseYour Answer: False Select The BlankQuestion: A ________ is largely depends upon the meeting of functional requirements and performance measures with ease in operations.Correct Answer: Customer SatisfactionYour Answer: Customer Satisfaction Multiple Choice Single AnswerQuestion: A testing is carried out before the execution of the development Process is :-Correct Answer: Non Execution based testingYour Answer: Execution Based testing Select The BlankQuestion: A ________ Measures the Quality of the output produced by the SystemCorrect Answer: EffectivenessYour Answer: Effectiveness Select The BlankQuestion: The key requirements of the systems are identified in ________ PhaseCorrect Answer: DefinitionYour Answer: Definition Multiple Choice Single AnswerQuestion: A type of testing which eliminates the errors in the design, architecture and development & deployment process is.Correct Answer: Non Execution based testingYour Answer: Execution Based testing Select The BlankQuestion: A unit tests major focuses on ________Correct Answer: Processes & CodeYour Answer: Interface True/FalseQuestion: Domain Specific applications are developed mostly integrating components which are similar in functionalityCorrect Answer: TrueYour Answer: True Multiple Choice Single AnswerQuestion: A Discipline that integrates Process, Methods and tools for development of a software isCorrect Answer: Software EngineeringYour Answer: Software Engineering Select The BlankQuestion: ________ is developed or engineered not manufacturedCorrect Answer: SoftwareYour Answer: Software
Page 112 of 155 112
SCDL – 3rd Semester – Software Engineering and Project Management
True/FalseQuestion: ISO 9001 is used to develop quality assurance systems.Correct Answer: TrueYour Answer: True Multiple Choice Multiple AnswerQuestion: Architecture Design Consists of:-Correct Answer: Module Structure , Program Structure , Hierarchy in the Structure
True/FalseQuestion: System Performance is measured through effectiveness and its efficiency.Correct Answer: True
Multiple Choice Single AnswerQuestion: The Application of a systematic, disciplined, quantifiable approach to the development, operation and maintenance of the software is termed asCorrect Answer: Software Engineering
Multiple Choice Multiple AnswerQuestion: The most affected elements of the Quality of the software is:-Correct Answer: Customer , Developer , Stake Holders Your Answer: Customer , Developer , Stake Holders Multiple Choice Single AnswerQuestion: A system which operates in a predictable manner is :-Correct Answer: Deterministic SystemYour Answer: Deterministic System Multiple Choice Multiple AnswerQuestion: The Functionality of the Client application is tested using :-Correct Answer: Server Tests , Database Tests , Transaction Tests Your Answer: Server Tests , Database Tests Multiple Choice Multiple AnswerQuestion: Software Risk could be of :-Correct Answer: Process Risk , Project Risk , Product Risk Your Answer: Process Risk , Project Risk , Product Risk Multiple Choice Multiple AnswerQuestion: Test cases are designed to tests:-Correct Answer: Internal Logic , Software Requirements Your Answer: Internal Logic , Software Requirements Multiple Choice Single AnswerQuestion: A Step in risk Management which identifies and enumerates the risk is :-Correct Answer: Risk IdentificationYour Answer: Risk Identification True/FalseQuestion: SE is applied for software development through Engineering MethodsCorrect Answer: TrueYour Answer: True
Select The BlankQuestion: The Errors which have impact on look and feel of the system is classified as ________ errorsCorrect Answer: Cosmetic
Page 113 of 155 113
SCDL – 3rd Semester – Software Engineering and Project Management
Your Answer: Fatal True/FalseQuestion: Spiral model itself is a model which is base for other software development modelsCorrect Answer: FalseYour Answer: False Match The FollowingQuestion Correct Answer Your AnswerData Dictionary Meta Data Meta DataSSAD Analysis Tools Analysis ToolsDFD Source & Destination of Data NormalizationERD Relationship of the Attributes Relationship of the Attributes Multiple Choice Multiple AnswerQuestion: The next development in software engineering isCorrect Answer: The use of tool generate the code , The extensive use od CASE tool for analysis and design , The use of Component technology Your Answer: The use of tool generate the code , The extensive use od CASE tool for analysis and design , The use of Component technology Multiple Choice Single AnswerQuestion: A model in which software development cycle is sequential process is :-Correct Answer: Waterfall ModelYour Answer: Waterfall Model True/FalseQuestion: The major resources in the project is people and funds.Correct Answer: FalseYour Answer: True Multiple Choice Multiple AnswerQuestion: The Software Risk affects :-Correct Answer: Project Development , Software Product , Process of Development Your Answer: Project Development , Software Product , Process of Development Multiple Choice Single AnswerQuestion: A tool used to understand the system and used for analysis of the system is:-Correct Answer: System ModelingYour Answer: System Modeling Match The FollowingQuestion Correct Answer Your AnswerIEEE Institute of Electrical and Institute of Electrical and
Electronics Engineers Electronics EngineersWater Fall Model Customer Specific Customer SpecificSSAD Structured Approach Structured ApproachOOSAD Object Oriented Approach Object Oriented Approach Multiple Choice Multiple AnswerQuestion: The Factors enabling easy change are :-Correct Answer: Maintainability , Flexibility , Testability Your Answer: Maintainability , Flexibility , Reusability True/FalseQuestion: CAD/CAM/CAE are the examples of embedded Software
Page 114 of 155 114
SCDL – 3rd Semester – Software Engineering and Project Management
Correct Answer: FalseYour Answer: False Select The BlankQuestion: ________ is the Significant project risk the management has to face in software development activity due to budgeting constraints.Correct Answer: FundingYour Answer: Man Power Multiple Choice Multiple AnswerQuestion: Database Design Specification include:-Correct Answer: Data Model , Internal & External File Structure , Referential Details Your Answer: Data Model , Internal & External File Structure , Referential Details Multiple Choice Single AnswerQuestion: A software which directly communicates with the hardware and provides an interface to perform certain tasks is termed asCorrect Answer: System SoftwareYour Answer: System Software Multiple Choice Multiple AnswerQuestion: A formal Technical Review may include:-Correct Answer: Walkthroughs , Inspections , Roundrobin reviews Your Answer: Inspections , Roundrobin reviews , Testing Techniques Multiple Choice Multiple AnswerQuestion: Resources required for a Software development activity could be :-Correct Answer: People , Development Environment , Reusable Components Your Answer: People , Development Environment , Reusable Components Multiple Choice Single AnswerQuestion: A process of acquiring hardware, software and development services and entering into contract with customers and business partners to deliver the software product is :-Correct Answer: Project Procurement ManagementYour Answer: Project Procurement Management Select The BlankQuestion: A ________ arises due to uncertainties involved in assessing, estimating various inputs to the software process.Correct Answer: Process RiskYour Answer: Process Risk Select The BlankQuestion: A ________ is understood as a possibility of Loss.Correct Answer: RiskYour Answer: Risk Select The BlankQuestion: The company shall establish a ________ to control flow of documents that relate to the requirements of the ISO.Correct Answer: Document Control SystemYour Answer: Document Scanning System Select The BlankQuestion: A ________ is the most effective filter from a quality assurance stand point.Correct Answer: Formal Technical ReviewYour Answer: A good Tests
Page 115 of 155 115
SCDL – 3rd Semester – Software Engineering and Project Management
LIST OF ATTEMPTED QUESTIONS AND ANSWERS Multiple Choice Multiple AnswerQuestion: The stages of the Iterative Models areCorrect Answer: Development Coding & Unit Testing , Requirement Analysis , System Design Your Answer: Development Coding & Unit Testing , Requirement Analysis , System Design Select The BlankQuestion: Requirements Management Begins with ________.Correct Answer: IdentificationYour Answer: Identification Multiple Choice Multiple AnswerQuestion: System Design Consists of:-Correct Answer: Level DFD's , System Flowcharts , ERD's Your Answer: Level DFD's , ERD's Multiple Choice Single AnswerQuestion: The Paradigm Structured System Analysis and Design was developed by:-Correct Answer: Yourdon & De MacroYour Answer: Yourdon & Boehm Multiple Choice Multiple AnswerQuestion: In a Software Risk Management Risk drivers are :-Correct Answer: Technology , People , Requirements Your Answer: Technology , People , Programmers Multiple Choice Multiple AnswerQuestion: IN OOSAD, Objects haveCorrect Answer: attribute , Methods , relationship Your Answer: attribute , Methods , relationship Multiple Choice Single AnswerQuestion: A Standard Method which helps in keeping the system as an acceptable standards is:-Correct Answer: Periodical MaintenanceYour Answer: Periodical Maintenance Select The BlankQuestion: For managing change the SQA plan inculcates ________ to monitor the change.Correct Answer: Software Configuration ManagementYour Answer: ISO Auditor Multiple Choice Multiple AnswerQuestion: Artificial Intelligent Domain Systems Could beCorrect Answer: Expert System , Image & Voice Recognition System , Neural Networks Your Answer: Expert System , Image & Voice Recognition System Multiple Choice Multiple AnswerQuestion: Characteristics of a test could be:-Correct Answer: Not Redundant , Best of Breed , Neither too simple Nor to Complex Your Answer: Best of Breed , Neither too simple Nor to Complex , Yield Better Results True/False
Page 116 of 155 116
SCDL – 3rd Semester – Software Engineering and Project Management
Question: Software Development becomes complex due to the variety and heterogeneity of requirement of different Users and StakeholdersCorrect Answer: TrueYour Answer: True Multiple Choice Multiple AnswerQuestion: The outcome of Debugging Process is :-Correct Answer: The Error cause will be detected and corrected , The Error Cause will not be detected Your Answer: The Error Cause will not be detected , Product Errors , Design Errors True/FalseQuestion: Integration testing is done when the modules are integrated or when new component is added to the system.Correct Answer: TrueYour Answer: True Multiple Choice Multiple AnswerQuestion: Risk Management is a Process Made up of following :-Correct Answer: Risk Identification , Risk Analysis , Risk Assessment Your Answer: Risk Assessment , Risk Handling , Risk Identification Multiple Choice Multiple AnswerQuestion: The broad quality parameters are:-Correct Answer: Reliability , Safety , Security Your Answer: Reliability , Security , Development Select The BlankQuestion: ________ evaluates the run time performance of the system developed.Correct Answer: Performance TestingYour Answer: Beta Test Multiple Choice Single AnswerQuestion: An Activity that has a definite Start and a definite end is termed as ?Correct Answer: ProjectYour Answer: Program True/FalseQuestion: Six Sigma is one of the most widely used strategy for statistical quality assurance in an industry.Correct Answer: TrueYour Answer: True True/FalseQuestion: The Water Fall Model is used where the risk factor is almost nilCorrect Answer: TrueYour Answer: True Match The FollowingQuestion Correct Answer Your AnswerStress testing Testing with Abnormal Situations Fix ItDebugging Finding & Fixing Errors Locating ErrorsBlack Box Testing Incorrect or Missing Functions Incorrect or Missing FunctionsWhite Box Testing Glass Box Testing Glass Box Testing
Select The Blank
Page 117 of 155 117
SCDL – 3rd Semester – Software Engineering and Project Management
Question: SE Methodology rides on two components, System Engineering and ________.Correct Answer: Development EngineeringYour Answer: Requirement analysis Select The BlankQuestion: A ________ Measures the Efforts / cost / time used to achieve the output.Correct Answer: EfficiencyYour Answer: Efficiency Select The BlankQuestion: ________ is a System Engineering approach that is used to define architecture that enables a business to use Information Effectively.Correct Answer: Business Processing EngineeringYour Answer: Business Processing Engineering Match The FollowingQuestion Correct Answer Your AnswerPerformance of the System Non Functional Requirements Functional RequirementsSRS Structured System Analysis DocumentationDesign Phase Design Documentation Design DocumentationSSAD Functions & Features Structured System Analysis Multiple Choice Single AnswerQuestion: A principle in which the system is factored into smaller sub systems:-Correct Answer: DecompositionYour Answer: Decomposition True/FalseQuestion: Decomposition breaks the System into smaller modules and components.Correct Answer: TrueYour Answer: True Multiple Choice Single AnswerQuestion: A project management activity globally viewed as :-Correct Answer: A SystemYour Answer: A System Select The BlankQuestion: ________ tests confirms that the needs and requirements are fulfilled on the deployment platform.Correct Answer: BetaYour Answer: Beta Multiple Choice Multiple AnswerQuestion: Some of the Steps involve in Integration Testing is :-Correct Answer: Main Control Module is a Test Driver , Tests are conducted as each component is added , Regression Testing is done Your Answer: Tests are conducted as each component is added , Regression Testing is done , Stress Testing Multiple Choice Single AnswerQuestion: A process which audits and inspects whether the people responsible for quality and customer satisfaction follow the quality control measures & standards or not is :-Correct Answer: Quality AssuranceYour Answer: Quality Assurance Multiple Choice Single Answer
Page 118 of 155 118
SCDL – 3rd Semester – Software Engineering and Project Management
Question: The Extent of effort to locate the error and fix it is :-Correct Answer: MaintainabilityYour Answer: Reliability Multiple Choice Single AnswerQuestion: The Scope of the work in a Software Project is defined by :-Correct Answer: Statement of WorkYour Answer: Requirement Specifications True/FalseQuestion: Stress Testing is a part of Integration testing.Correct Answer: FalseYour Answer: True Select The BlankQuestion: The Failure Curve of a Hardware is called as ________Correct Answer: Bathtub CurveYour Answer: Bathtub Curve Multiple Choice Single AnswerQuestion: A testing is carried out continuously as the software components are built or incremented is:-Correct Answer: Incremental TestingYour Answer: Incremental Testing Select The BlankQuestion: LOC Means________Correct Answer: Lines of CodeYour Answer: Lines of Code Multiple Choice Multiple AnswerQuestion: OOSAD development approach usesCorrect Answer: Objects , Process modeling , Object attributes Your Answer: Objects , Process modeling , Object attributes True/FalseQuestion: System testing checks the abnormality in the software system.Correct Answer: FalseYour Answer: False True/FalseQuestion: System testing Starts when Software Integration is about to be completed.Correct Answer: FalseYour Answer: True Multiple Choice Single AnswerQuestion: The Software development engineering which builds objects of models independent of the system under consideration is ?Correct Answer: OOSADYour Answer: OOSAD Select The BlankQuestion: ________ type of testing evaluate the logical access to the basic functionality of the System.Correct Answer: Security TestingYour Answer: Security Testing
Page 119 of 155 119
SCDL – 3rd Semester – Software Engineering and Project Management
Multiple Choice Single AnswerQuestion: A software which resides in the read only memory and controls the functions of the resident ProductsCorrect Answer: Embedded SoftwareYour Answer: Embedded Software Select The BlankQuestion: A ________ deals with identification and assessment of potential hazards of software failing and its impact on the systems.Correct Answer: Software SafetyYour Answer: Software Implementation Multiple Choice Single AnswerQuestion: A system for the support of software development is calledCorrect Answer: Computer Aided Software EngineeringYour Answer: Supporting Modules True/FalseQuestion: Recovery testing focuses on the Cost Recovery Plan of the Software Implemented.Correct Answer: FalseYour Answer: False True/FalseQuestion: A software review is a filter for the software development process.Correct Answer: TrueYour Answer: False Multiple Choice Multiple AnswerQuestion: Black Box testing techniques are:-Correct Answer: Graph Based Testing Methods , Equivalence Portioning , Boundary Value Analysis Your Answer: Stress Testing , Boundary Value Analysis
LIST OF ATTEMPTED QUESTIONS AND ANSWERS
Multiple Choice Single AnswerQuestion: The success of the software depends upon ?Correct Answer: UsabilityYour Answer: Maintenance Match The FollowingQuestion Correct Answer Your AnswerSystem Software Operating System Operating SystemMachine & assembly Language Scientists and engineers Scientists and engineersSoftware efficiency Optimum use of resources Optimum use of resourcesSoftware Usability Good Documentation Good Documentation Multiple Choice Single AnswerQuestion: A process which audits and inspects whether the people responsible for quality and customer satisfaction follow the quality control measures & standards or not is :-Correct Answer: Quality AssuranceYour Answer: Quality Assurance Multiple Choice Single AnswerQuestion: A Process of organizing the sub systems as one system to reduce the number ofconnectivities or interfaces:-
Page 120 of 155 120
SCDL – 3rd Semester – Software Engineering and Project Management
Correct Answer: SimplificationYour Answer: Simplification True/FalseQuestion: Risk which can be known is termed as unpredictable risk.Correct Answer: FalseYour Answer: False Multiple Choice Single AnswerQuestion: How to develop or build a particular software module is defined byCorrect Answer: Software Engineering MethodsYour Answer: Software Engineering Methods Multiple Choice Single AnswerQuestion: A system for the support of software development is calledCorrect Answer: Computer Aided Software EngineeringYour Answer: Computer Aided Software Engineering Multiple Choice Single AnswerQuestion: The extent the software meets the customer quality goals and expectations is termed as :-Correct Answer: CorrectnessYour Answer: Correctness Multiple Choice Multiple AnswerQuestion: Risk Management is a Process based on application of :-Correct Answer: Game Theory , Probability Theory , Decision Theory Your Answer: Game Theory , Probability Theory , Decision Theory Multiple Choice Single AnswerQuestion: A System which is adaptable to changes arising out of environmental changes:-Correct Answer: Open SystemYour Answer: Open System True/FalseQuestion: The Major risk involved in software project is to identify the programmers required and the pay scales of them.Correct Answer: FalseYour Answer: True Select The BlankQuestion: ________ tests confirms that the needs and requirements are fulfilled on the deployment platform.Correct Answer: BetaYour Answer: Beta Multiple Choice Multiple AnswerQuestion: IN OOSAD, Objects haveCorrect Answer: attribute , Methods , relationship Your Answer: attribute , Methods , relationship Select The BlankQuestion: Inventory Control System which is designed based on demand and supply variations could be an example of ________ systemCorrect Answer: ProbabilisticYour Answer: Probabilistic
Page 121 of 155 121
SCDL – 3rd Semester – Software Engineering and Project Management
Multiple Choice Multiple AnswerQuestion: Risk Management is a Process Made up of following :-Correct Answer: Risk Identification , Risk Analysis , Risk Assessment Your Answer: Risk Identification , Risk Analysis , Risk Assessment Select The BlankQuestion: Generally in an ongoing project a project manager fixes up more ________ to have proper control measurement of the project activitiesCorrect Answer: Major MilestoneYour Answer: Milestone Multiple Choice Multiple AnswerQuestion: The outcome of Debugging Process is :-Correct Answer: The Error cause will be detected and corrected , The Error Cause will not be detected Your Answer: The Error Cause will not be detected , The Error cause will be detected and corrected Select The BlankQuestion: An accounting System based on rules and Principles could be an example of ________ System.Correct Answer: DeterministicYour Answer: Deterministic Multiple Choice Single AnswerQuestion: A Discipline that integrates Process, Methods and tools for development of a software isCorrect Answer: Software EngineeringYour Answer: Software Engineering True/FalseQuestion: Six Sigma is one of the most widely used strategy for statistical quality assurance in an industry.Correct Answer: TrueYour Answer: True Multiple Choice Multiple AnswerQuestion: A formal Technical Review may include:-Correct Answer: Walkthroughs , Inspections , Roundrobin reviews Your Answer: Walkthroughs , Inspections , Roundrobin reviews Select The BlankQuestion: A ________ has to be performed regularly throughout the achievement life cycle.Correct Answer: Risk ManagementYour Answer: Risk Analysis True/FalseQuestion: SRS is Systems requirement specifications in the software development phaseCorrect Answer: TrueYour Answer: True Select The BlankQuestion: In the ________ model data elements are organized in tree structure in parent-child format.Correct Answer: HierarchicalYour Answer: HierarchicalTrue/False
Page 122 of 155 122
SCDL – 3rd Semester – Software Engineering and Project Management
Question: System testing checks the abnormality in the software system.Correct Answer: FalseYour Answer: False Multiple Choice Multiple AnswerQuestion: System Design Consists of:-Correct Answer: Level DFD's , System Flowcharts , ERD's Your Answer: Level DFD's , System Flowcharts , ERD's Multiple Choice Multiple AnswerQuestion: Characteristics of a test could be:-Correct Answer: Not Redundant , Best of Breed , Neither too simple Nor to Complex Your Answer: Not Redundant , Best of Breed , Neither too simple Nor to Complex Multiple Choice Single AnswerQuestion: An Activity that has a definite Start and a definite end is termed as ?Correct Answer: ProjectYour Answer: Project True/FalseQuestion: The Unit of the Software is the smallest entity to be tested.Correct Answer: TrueYour Answer: True Select The BlankQuestion: ________ is a process of executing a program with the intent of finding an error.Correct Answer: TestingYour Answer: Validations Select The BlankQuestion: A ________ is used to show the system flow stage by stage in a logical sequenceCorrect Answer: System Flow ChartYour Answer: System Flow Chart Multiple Choice Multiple AnswerQuestion: The Scope of the Software Project is defined by Statement of Work which is agreed by ?Correct Answer: Users , Stakeholders , Customers Your Answer: Users , Stakeholders , Customers Multiple Choice Multiple AnswerQuestion: Artificial Intelligent Domain Systems Could beCorrect Answer: Expert System , Image & Voice Recognition System , Neural Networks Your Answer: Expert System , Image & Voice Recognition System , Neural Networks Match The FollowingQuestion Correct Answer Your AnswerSpiral Model Boehm Spiral model Boehm Spiral modelLegacy software Poor Quality Poor QualityObjects Attribute, Methods Attribute, MethodsSSAD yourdan & DeMarco yourdan & DeMarco Multiple Choice Multiple AnswerQuestion: Design Constraints include:-Correct Answer: Resource Limitations , Platform Limitations , Protocol Limitations Your Answer: Resource Limitations , Platform Limitations , Protocol Limitations Multiple Choice Single Answer
Page 123 of 155 123
SCDL – 3rd Semester – Software Engineering and Project Management
Question: The Application of a systematic, disciplined, quantifiable approach to the development, operation and maintenance of the software is termed asCorrect Answer: Software EngineeringYour Answer: Software Engineering Multiple Choice Single AnswerQuestion: A type of testing which verifies that all the system elements are meshed properly and that overall system function / performance is achieved is:-Correct Answer: System testingYour Answer: Component Testing True/FalseQuestion: CAD/CAM/CAE are the examples of embedded SoftwareCorrect Answer: FalseYour Answer: False Select The BlankQuestion: Software is classified into two categories, Generic and ________.Correct Answer: CutomisedYour Answer: Cutomised Multiple Choice Single AnswerQuestion: A Step in risk Management which identifies and enumerates the risk is :-Correct Answer: Risk IdentificationYour Answer: Risk Identification Multiple Choice Multiple AnswerQuestion: The Contents which are recorded by the Data Dictionary for an typical item is:-Correct Answer: Definition , Identification , Validation Text & Relationship Your Answer: Definition , Identification , Validation Text & Relationship Multiple Choice Single AnswerQuestion: A costs which includes cost of rework, repair and failure analysis is :-Correct Answer: Failure CostYour Answer: Maintenance Cost True/FalseQuestion: Recovery testing focuses on the Cost Recovery Plan of the Software Implemented.Correct Answer: FalseYour Answer: False Select The BlankQuestion: For managing change the SQA plan inculcates ________ to monitor the change.Correct Answer: Software Configuration ManagementYour Answer: Software Configuration Management True/FalseQuestion: System Performance is measured through effectiveness and its efficiency.Correct Answer: TrueYour Answer: True True/FalseQuestion: A software review is a filter for the software development process.Correct Answer: TrueYour Answer: True Multiple Choice Single Answer
Page 124 of 155 124
SCDL – 3rd Semester – Software Engineering and Project Management
Question: The Extend to which the software product is protected from an unauthorized access is :-Correct Answer: IntegrityYour Answer: Integrity
LIST OF ATTEMPTED QUESTIONS AND ANSWERS Multiple Choice Multiple AnswerQuestion: Legacy software -Poor quality hasCorrect Answer: Inextensible design , Convoluted Code , Poor or nonexistent documentation Your Answer: Poor or nonexistent documentation , Inextensible design , Convoluted Code Multiple Choice Single AnswerQuestion: A System which is not influenced by the external environment:-Correct Answer: Closed SystemYour Answer: Closed System Select The BlankQuestion: ________ combines software, Hardware and a software engineering database to create a software engineering environment for hardwareCorrect Answer: CASEYour Answer: Integrated Wizard Multiple Choice Single AnswerQuestion: An Approach which majorly focuses on Functions and data structure designed for those functions.Correct Answer: SSADYour Answer: SSAD Select The BlankQuestion: To become a registered, one of the quality assurance system models contained in ISO 9000 a company's quality system is scrutinized by ________.Correct Answer: Third Party AuditorYour Answer: Third Party Auditor Multiple Choice Single AnswerQuestion: A Modification of the Software is done to accommodate the changes forced by the external environment isCorrect Answer: Adaptive MaintenanceYour Answer: Corrective Maintenance Multiple Choice Single AnswerQuestion: A set of Computer Programs which performs set of preset functions is called as ?Correct Answer: SoftwareYour Answer: Software Multiple Choice Multiple AnswerQuestion: The Factors enabling easy change are :-Correct Answer: Maintainability , Flexibility , Testability Your Answer: Maintainability , Flexibility , Reusability Select The BlankQuestion: In ________ model the data elements are organized indifferent areas that work together through network communications.Correct Answer: NetworkYour Answer: Network - Relational
Page 125 of 155 125
SCDL – 3rd Semester – Software Engineering and Project Management
True/FalseQuestion: Software Development becomes a costly and risky if the the development process does not follow a systematic, scientific approach to produce the softwareCorrect Answer: TrueYour Answer: True Select The BlankQuestion: ________ testing confirms that the needs and requirements are fulfilled in the development environment.Correct Answer: AlphaYour Answer: Beta Multiple Choice Single AnswerQuestion: Changes in the Customer requirements are understood and incorporated in which phase?Correct Answer: SupportYour Answer: Development Multiple Choice Multiple AnswerQuestion: Black Box testing techniques are:-Correct Answer: Graph Based Testing Methods , Equivalence Portioning , Boundary Value Analysis Your Answer: Graph Based Testing Methods , Stress Testing , Boundary Value Analysis Select The BlankQuestion: A ________ Measures the Quality of the output produced by the SystemCorrect Answer: EffectivenessYour Answer: Efficiency True/FalseQuestion: Simplification rationalizes the complex , breakdown into clusters, making a meaningful and functionally complete design.Correct Answer: TrueYour Answer: True Multiple Choice Multiple AnswerQuestion: Resources required for a Software development activity could be :-Correct Answer: People , Development Environment , Reusable Components Your Answer: Modules , People , Development Environment Select The BlankQuestion: One of the most important guideline for the reviewing the product is review the product not the ________.Correct Answer: ProducerYour Answer: Developer True/FalseQuestion: The Emphasis in SSAD is on functions and features.Correct Answer: TrueYour Answer: True Multiple Choice Multiple AnswerQuestion: Project Metrics enable a software project manager to:-Correct Answer: Assess the Status of the Ongoing Project , Identify the Risk Potential , Uncover problem areas before they go Critical
Page 126 of 155 126
SCDL – 3rd Semester – Software Engineering and Project Management
Your Answer: Assess the Status of the Ongoing Project , Identify the Risk Potential , Manage the resources Multiple Choice Single AnswerQuestion: Most of the Software's Continues to be custom built becauseCorrect Answer: Reusability of the ComponentYour Answer: Reusability of the Component Select The BlankQuestion: A ________ is an activity incorporating both software quality control and quality assurance.Correct Answer: Software Quality ManagementYour Answer: ISO Standards Multiple Choice Multiple AnswerQuestion: Operational Testing is carried out by :-Correct Answer: Recovery Testing , Stress Testing , Performance Testing Multiple Choice Single AnswerQuestion: A process of creating a document Statement of Work, and planning the major task deliveries is :-Correct Answer: Project Planning
Multiple Choice Single AnswerQuestion: Source Code of the Software is available so that the engineers can make the local modifications and use the componentCorrect Answer: Open Source True/FalseQuestion: The Data Management is not easy with relational Model.Correct Answer: False Match The FollowingQuestion Correct Answer Your AnswerDevelopment of the Software Software Programs Software Engineering LayersCorrective Maintenance Software ModulesProcess, Tools & Methods Software Engineering Layers AnalysisRequirement Specifications Definition Phase Definition Phase True/FalseQuestion: A Software solution is evolved in parts as in an incremental fashion in incremental modelCorrect Answer: True
Select The BlankQuestion: The Errors which have impact on look and feel of the system is classified as ________ errorsCorrect Answer: Cosmetic True/FalseQuestion: Software Development becomes complex due to the variety and heterogeneity of requirement of different Users and StakeholdersCorrect Answer: True
Select The BlankQuestion: SE Methodology rides on two components, System Engineering and ________.Correct Answer: Development Engineering
Page 127 of 155 127
SCDL – 3rd Semester – Software Engineering and Project Management
Multiple Choice Single AnswerQuestion: A Software that makes use of non numerical algorithms to solve complex problems that are not amenable to straightforward analysisCorrect Answer: Artificial Intelligence
Select The BlankQuestion: PRM stands for ________Correct Answer: Prototyping Model Multiple Choice Single AnswerQuestion: A DD type which models internals of the process i.e. the details namely how , where, by whom and so on is known as:-Correct Answer: Physical DFD
Match The FollowingQuestion Correct Answer Your AnswerVerification & Validation Testing TestingIncorrect Logical Decision White Box Testing DebuggingIncorrect Functions In a program Black Box Testing TracingData Structure & Specific Values Test Case Black Box Testing Multiple Choice Single AnswerQuestion: Software Engineering attempts to identify what information is to be processed, what function and performance is desired in which phase?Correct Answer: Definition PhaseYour Answer: Development Phase Multiple Choice Single AnswerQuestion: The Quality aspect which includes the grade of materials, physical and performance specifications, tolerance and process standards is :-Correct Answer: DesignYour Answer: Requirements Specifications Multiple Choice Multiple AnswerQuestion: Architecture Design Consists of:-Correct Answer: Module Structure , Program Structure , Hierarchy in the Structure Your Answer: Module Structure , Hierarchy in the Structure , Process Structure Multiple Choice Multiple AnswerQuestion: The Functionality of the Client application is tested using :-Correct Answer: Server Tests , Database Tests , Transaction Tests Your Answer: Server Tests , Transaction Tests , Client Tests True/FalseQuestion: The results of the test case is recorded in the test specification document.Correct Answer: TrueYour Answer: True Multiple Choice Multiple AnswerQuestion: Project Risk Management Includes:-Correct Answer: Risk Prevention , Risk Avoidance , Risk Mitigation Multiple Choice Multiple AnswerQuestion: Project Metrics helps the project manager in following ways :-Correct Answer: Minimize the Development Schedule , Assess Product Quality regularly
Page 128 of 155 128
SCDL – 3rd Semester – Software Engineering and Project Management
Multiple Choice Single AnswerQuestion: A process which ensures that the materials input (Process input), the manufacturing process (software development process) and outgoing quality are of requisite standards is :-Correct Answer: Quality Assurance Multiple Choice Single AnswerQuestion: A process of identifying, assessing , evaluating risk exposure, prioritizing the risk incidences, and developing risk monitoring, management and mitigation plan is :-Correct Answer: Project Risk Management
Multiple Choice Single AnswerQuestion: A type of testing where the focus is on design and development of the software architecture is termed as:-Correct Answer: Integration Testing
Select The BlankQuestion: ________ is characterized by longetivity and business criticalityCorrect Answer: Legacy Software
Multiple Choice Single AnswerQuestion: Who Defines SE as the application of a Systematic, disciplined and quantifiable approach to the development and maintenance of a SoftwareCorrect Answer: IEEE Multiple Choice Single AnswerQuestion: A Software developed to perform certain functionality and later on embedded into the hardware is called asCorrect Answer: Embedded Software
LIST OF ATTEMPTED QUESTION:S AND ANSWERS
Multiple Choice Multiple AnswerQuestion: The software designed with the correct choice of technology and architecture to ensure:Correct Answer: Customer Satisfaction , On-time Delivery , Developed with the budgeted costYour Answer: Customer Satisfaction , On-time Delivery , Developed with the budgeted cost
True/FalseQuestion: Risk which can be known is termed as unpredictable risk.Correct Answer: FalseYour Answer: False
Multiple Choice Single AnswerQuestion: A type of testing which eliminates the errors in the design, architecture and development & deployment process is.Correct Answer: Non Execution based testingYour Answer: Non Execution based testing
Multiple Choice Multiple AnswerQuestion: The broad quality parameters are:-Correct Answer: Reliability , Safety , SecurityYour Answer: Reliability , Safety , Security
True/FalseQuestion: E-R Diagrams are used to identify the Weak and Strong Relations.Correct Answer: TrueYour Answer: True
Page 129 of 155 129
SCDL – 3rd Semester – Software Engineering and Project Management
Multiple Choice Multiple AnswerQuestion: Resources required for a Software development activity could be :-Correct Answer: People , Development Environment , Reusable ComponentsYour Answer: People , Development Environment , Reusable Components
Multiple Choice Multiple AnswerQuestion: A good test is one that has:-Correct Answer: High Probability of detecting an error , Not Redundant , Simple to execute & IndependentYour Answer: High Probability of detecting an error , Not Redundant , Simple to execute & Independent
Multiple Choice Single AnswerQuestion: A System in which next state of the system can be predicted without doubt is :-Correct Answer: DeterministicYour Answer: Probabilistic
Multiple Choice Multiple AnswerQuestion: System Design Consists of:-Correct Answer: Level DFD's , System Flowcharts , ERD'sYour Answer: Level DFD's , System Flowcharts , ERD's
Match The FollowingQuestion: Correct Answer: Your Answer:World Wide Web Content provider Content providerSoftware Deteriorates Integrated SystemSystem Software File Management DeterioratesApplication Software Standalone Programs File Management
True/FalseQuestion: A software review is a filter for the software development process.Correct Answer: TrueYour Answer: True
True/FalseQuestion: Reactive risk strategies are applied to deal with risk when it occurs.Correct Answer: TrueYour Answer: True
Multiple Choice Single AnswerQuestion: A type of testing where the focus is on error/ mistake or fault detection and correction is:-Correct Answer: Process based TestingYour Answer: Process based Testing
Match The FollowingQuestion: Correct Answer: Your Answer:IEEE Institute of Electrical and Institute of Electrical and
Electronics Engineers Electronics EngineersWater Fall Model Customer Specific Structured ApproachSSAD Structured Approach Customer SpecificOOSAD Object Oriented Approach Object Oriented Approach
Multiple Choice Multiple AnswerQuestion: The Scope of the Software Project is defined by Statement of Work which is agreed by ?Correct Answer: Customers , Users , StakeholdersYour Answer: Users , Stakeholders , Customers
Page 130 of 155 130
SCDL – 3rd Semester – Software Engineering and Project Management
Select The BlankQuestion: ________ testing confirms that the needs and requirements are fulfilled in the development environment.Correct Answer: AlphaYour Answer: Alpha
True/FalseQuestion: SQA is ensured through a Quality Management System.Correct Answer: TrueYour Answer: True
Select The BlankQuestion: The Failure Curve of a Hardware is called as ________Correct Answer: Bathtub CurveYour Answer: Bathtub Curve
Multiple Choice Multiple AnswerQuestion: The next development in software engineering isCorrect Answer: The use of tool generate the code , The extensive use od CASE tool for analysis and design , The use of Component technologyYour Answer: The use of tool generate the code , The extensive use od CASE tool for analysis and design , The use of Component technology
Multiple Choice Multiple AnswerQuestion: A formal Technical Review may include:-Correct Answer: Walkthroughs , Inspections , Roundrobin reviewsYour Answer: Walkthroughs , Inspections , Roundrobin reviews
True/FalseQuestion: Domain Specific applications are developed mostly integrating components which are similar in functionalityCorrect Answer: TrueYour Answer: True
Multiple Choice Single AnswerQuestion: A Principle in which the Functional Cohesion between the sub system is maintained:-Correct Answer: DecompositionYour Answer: Decomposition
Multiple Choice Multiple AnswerQuestion: Architecture Design Consists of:-Correct Answer: Module Structure , Program Structure , Hierarchy in the StructureYour Answer: Module Structure , Hierarchy in the Structure , Process Structure
True/FalseQuestion: White Box Testing Measures the Correctness of the Inputs and Basic Processes.Correct Answer: TrueYour Answer: True
Select The BlankQuestion: A ________ is understood as a possibility of Loss.Correct Answer: RiskYour Answer: Risk
Select The BlankQuestion: An incorrect decision by the designer, programmer or analyst that leads to improper result is an ________.
Page 131 of 155 131
SCDL – 3rd Semester – Software Engineering and Project Management
Correct Answer: ErrorYour Answer: Error
Multiple Choice Single AnswerQuestion: An Approach which majorly focuses on Functions and data structure designed for those functions.Correct Answer: SSADYour Answer: SSAD
True/FalseQuestion: CAD/CAM/CAE are the examples of embedded SoftwareCorrect Answer: FalseYour Answer: False
Multiple Choice Single AnswerQuestion: A process which ensures that the materials input (Process input), the manufacturing process (software development process) and outgoing quality are of requisite standards is :-Correct Answer: Quality AssuranceYour Answer: Quality Management
True/FalseQuestion: Simplification rationalizes the complex , breakdown into clusters, making a meaningful and functionally complete design.Correct Answer: TrueYour Answer: True
Select The BlankQuestion: In the ________ model data elements are organized in tree structure in parent-child format.Correct Answer: HierarchicalYour Answer: Hierarchical
Select The BlankQuestion: A Module Tests focuses on ________.Correct Answer: Functions & DesignYour Answer: Functions & Design
Multiple Choice Multiple AnswerQuestion: White Box Testing Checks :-Correct Answer: All Paths in the process are correctly operational , All Logical decision are executed with true or false , All Loops are executedYour Answer: All Paths in the process are correctly operational , All Logical decision are executed with true or false , All Loops are executed
Multiple Choice Single AnswerQuestion: A process which breaks statement of work into smaller activities with clear start - finish definition is called as :-Correct Answer: Work Break Down StructureYour Answer: Work Break Down Structure
True/FalseQuestion: Errors in documentation give rise to fatal results.Correct Answer: TrueYour Answer: True
Select The BlankQuestion: ________ is a process of executing a program with the intent of finding an error.Correct Answer: Testing
Page 132 of 155 132
SCDL – 3rd Semester – Software Engineering and Project Management
Your Answer: Testing
Select The BlankQuestion: ________ is achieved by carving out a module that is responsible for any unique function and which does not need to interact with other parts of the system.Correct Answer: Functional DependencyYour Answer: Functional Dependency
Multiple Choice Multiple AnswerQuestion: System Testing Techniques are :-Correct Answer: Alpha Test , Beta TestYour Answer: Alpha Test , Beta Test
Multiple Choice Single AnswerQuestion: A model in which software development cycle is sequential process is :-Correct Answer: Waterfall ModelYour Answer: Waterfall Model
Select The BlankQuestion: To become a registered, one of the quality assurance system models contained in ISO 9000 a company's quality system is scrutinized by ________.Correct Answer: Third Party AuditorYour Answer: SQM
Multiple Choice Single AnswerQuestion: A software which resides in the read only memory and controls the functions of the resident ProductsCorrect Answer: Embedded SoftwareYour Answer: Embedded Software
Multiple Choice Single AnswerQuestion: A document which identifies and helps the project manager to focus on the grey areas or critical functions in the project is :-Correct Answer: Software Requirement SpecificationsYour Answer: Software Requirement Specifications
Multiple Choice Multiple AnswerQuestion: Project Metrics enable a software project manager to:-Correct Answer: Assess the Status of the Ongoing Project , Identify the Risk Potential , Uncover problem areas before they go CriticalYour Answer: Assess the Status of the Ongoing Project , Identify the Risk Potential , Uncover problem areas before they go Critical
Multiple Choice Single AnswerQuestion: A system for the support of software development is calledCorrect Answer: Computer Aided Software EngineeringYour Answer: Computer Aided Software Engineering
Multiple Choice Single AnswerQuestion: A Collection of Interrelated, Interdependent group of elements which interact to achieve certain objectives is called as:-Correct Answer: SystemYour Answer: Software
Select The BlankQuestion: Inadequacy or misout in SRS & RDD is ________.Correct Answer: Defect
Page 133 of 155 133
SCDL – 3rd Semester – Software Engineering and Project Management
Your Answer: Defect
Select The BlankQuestion: LOC Means________Correct Answer: Lines of CodeYour Answer: Lines of Code
LIST OF ATTEMPTED QUESTIONS AND ANSWERS Multiple Choice Single AnswerQuestion: A process of identifying, assessing , evaluating risk exposure, prioritizing the risk incidences, and developing risk monitoring, management and mitigation plan is :- Correct Answer: Project Risk Management Your Answer: Project Risk Management Multiple Choice Single AnswerQuestion: A Modification of the Software is done to accommodate the changes forced by the external environment is Correct Answer: Adaptive Maintenance Your Answer: Corrective Maintenance Multiple Choice Multiple AnswerQuestion: A documentation is tested through :- Correct Answer: Technical Review , Actual Operational Review Your Answer: Technical Review , Actual Operational Review , Code Multiple Choice Single AnswerQuestion: In Interface Stage of SSAD phase the focus is on:- Correct Answer: User Comfort Your Answer: Design of the Output Formats Multiple Choice Single AnswerQuestion: A type of testing which verifies that all the system elements are meshed properly and that overall system function / performance is achieved is:- Correct Answer: System testing Your Answer: Component Testing Select The BlankQuestion: A ________ deals with identification and assessment of potential hazards of software failing and its impact on the systems. Correct Answer: Software Safety Your Answer: Software Testing True/FalseQuestion: The Water Fall Model is used where the risk factor is almost nil Correct Answer: True Your Answer: True Multiple Choice Single AnswerQuestion: A System in which next state of the system can be predicted without doubt is :- Correct Answer: Deterministic Your Answer: Open System True/FalseQuestion: Spiral model itself is a model which is base for other software development models Correct Answer: False
Page 134 of 155 134
SCDL – 3rd Semester – Software Engineering and Project Management
Your Answer: True True/FalseQuestion: System testing checks the abnormality in the software system. Correct Answer: False Your Answer: True True/FalseQuestion: ISO 9001 is used to develop quality assurance systems. Correct Answer: True Your Answer: True Multiple Choice Single AnswerQuestion: A type of testing where the focus is on design and development of the software architecture is termed as:- Correct Answer: Integration Testing Your Answer: Module testing True/FalseQuestion: The results of the test case is recorded in the test specification document. Correct Answer: True Your Answer: True Multiple Choice Single AnswerQuestion: A Principle in which the Functional Cohesion between the sub system is maintained:- Correct Answer: Decomposition Your Answer: Decoupling Multiple Choice Multiple AnswerQuestion: SQA efforts most primarily assures:- Correct Answer: Software Quality , Software Reliability , Software Availability Your Answer: Software Quality , Software Reliability , Software Availability Multiple Choice Multiple AnswerQuestion: The Customer Requirements could be analyzed by:- Correct Answer: Interviewing , Questionnaire , Meeting with Key Users Your Answer: Questionnaire , Case Study , Meeting with Key Users Multiple Choice Single AnswerQuestion: The extent the software meets the customer quality goals and expectations is termed as :- Correct Answer: Correctness Your Answer: Reliability Multiple Choice Multiple AnswerQuestion: The Factors enabling easy change are :- Correct Answer: Maintainability , Flexibility , Testability Your Answer: Maintainability , Flexibility , Reusability Match The FollowingQuestion Correct Answer Your AnswerDevelopment of the Software Programs Software Engineering Layers Software Corrective Maintenance Analysis Process, Tools & Methods Software Engineering Layers Software Modules Requirement Specifications Definition Phase Software Programs
Page 135 of 155 135
SCDL – 3rd Semester – Software Engineering and Project Management
Select The BlankQuestion: Cohesion and Coupling is the criteria for measuring ________. Correct Answer: Functional Dependency Your Answer: Functional Dependency Select The BlankQuestion: A collection of programs written to service other set of programs and its functions is called as ________ Correct Answer: System Software Your Answer: Integrated Software Select The BlankQuestion: ________ is a System Engineering approach that is used to define architecture that enables a business to use Information Effectively. Correct Answer: Business Processing Engineering Your Answer: Business Process Models Multiple Choice Single AnswerQuestion: The Application of a systematic, disciplined, quantifiable approach to the development, operation and maintenance of the software is termed as Correct Answer: Software Engineering Your Answer: Software Maintenance Multiple Choice Multiple AnswerQuestion: RMMM Plan deals with :- Correct Answer: Mitigation , Monitoring , Management Your Answer: Mitigation , Monitoring , Management Select The BlankQuestion: In ________Model the risk of the Software development is almost Nil Correct Answer: Water Fall Your Answer: Water Fall True/FalseQuestion: Stress Testing is a part of Integration testing. Correct Answer: False Your Answer: False Multiple Choice Multiple AnswerQuestion: Black Box testing techniques are:- Correct Answer: Graph Based Testing Methods , Equivalence Portioning , Boundary Value Analysis Your Answer: Graph Based Testing Methods , Stress Testing , Boundary Value Analysis Multiple Choice Multiple AnswerQuestion: The types of Software are Correct Answer: Business Software , Embedded Software , System Software Your Answer: Business Software , Embedded Software , System Software Multiple Choice Multiple AnswerQuestion: Following are the data models namely:- Correct Answer: Hierarchical Model , Network Model , Relational Model Your Answer: Hierarchical Model , Network Model , Relational Model Select The BlankQuestion: ________ is achieved by carving out a module that is responsible for any unique function and which does not need to interact with other parts of the system.
Page 136 of 155 136
SCDL – 3rd Semester – Software Engineering and Project Management
Correct Answer: Functional Dependency Your Answer: Functional Dependency Multiple Choice Multiple AnswerQuestion: The stages of the Iterative Models are Correct Answer: Requirement Analysis , System Design , Development Coding & Unit Testing Your Answer: Requirement Analysis , System Design , Development Coding & Unit Testing Multiple Choice Multiple AnswerQuestion: In a Software Risk Management Risk drivers are :- Correct Answer: Technology , People , Requirements Your Answer: Technology , People , Requirements Select The BlankQuestion: ________ tests confirms that the needs and requirements are fulfilled on the deployment platform. Correct Answer: Beta Your Answer: Stress True/FalseQuestion: The major resources in the project is people and funds. Correct Answer: False Your Answer: False Match The FollowingQuestion Correct Answer Your AnswerEntity Object which is Uniquely Object which is Uniquely
Distinguished Distinguished Hierarchical Model Tree Structure Tree Structure Network Model Network Communications Network Communications Relational Model Data are Linked Data are Linked Select The BlankQuestion: The company should establish a ________ and maintain a documented quality system as a means of ensuring that it conforms to the specified requirements of ISO. Correct Answer: Quality System Procedure Your Answer: Quality Management System Multiple Choice Single AnswerQuestion: Who Defines SE as the application of a Systematic, disciplined and quantifiable approach to the development and maintenance of a Software Correct Answer: IEEE Your Answer: ISO - 9001 True/FalseQuestion: People, Procedures and Parameters are the Drivers of the Technology. Correct Answer: False Your Answer: True True/FalseQuestion: Six Sigma is one of the most widely used strategy for statistical quality assurance in an industry. Correct Answer: True Your Answer: False Select The BlankQuestion: A ________ has to be performed regularly throughout the achievement life cycle.
Page 137 of 155 137
SCDL – 3rd Semester – Software Engineering and Project Management
Correct Answer: Risk Management Your Answer: Risk Management Multiple Choice Multiple AnswerQuestion: Work Break Down Structure can also be traced back to ? Correct Answer: System Requirements Specifications , Requirement Definition & Description Your Answer: System Requirements Specifications , Statement of Work , Planning Multiple Choice Single AnswerQuestion: A type of testing where the focus is user and user Behavior is:- Correct Answer: Usage based testing Your Answer: Usage based testing True/FalseQuestion: A Software solution is evolved in parts as in an incremental fashion in incremental model Correct Answer: True Your Answer: True Multiple Choice Multiple AnswerQuestion: System Testing Techniques are :- Correct Answer: Alpha Test , Beta Test Your Answer: Alpha Test , Beta Test , Stress Testing Select The BlankQuestion: ________ testing confirms that the needs and requirements are fulfilled in the development environment. Correct Answer: Alpha Your Answer: Beta Multiple Choice Single AnswerQuestion: In Design Phase at data and data Structure stage the focus is on:- Correct Answer: Entities and Attributes Your Answer: Entities and Attributes Multiple Choice Single AnswerQuestion: The Extent of effort to locate the error and fix it is :- Correct Answer: Maintainability Your Answer: Flexibility Multiple Choice Single AnswerQuestion: A process of identifying, assessing , evaluating risk exposure, prioritizing the risk incidences, and developing risk monitoring, management and mitigation plan is :- Correct Answer: Project Risk Management Your Answer: Project Risk Management Multiple Choice Multiple AnswerQuestion: RMMM Plan deals with :- Correct Answer: Mitigation , Monitoring , Management Your Answer: Mitigation , Monitoring , Management Select The BlankQuestion: In ________Model the risk of the Software development is almost Nil Correct Answer: Water Fall Your Answer: Water Fall True/False
Page 138 of 155 138
SCDL – 3rd Semester – Software Engineering and Project Management
Question: Stress Testing is a part of Integration testing. Correct Answer: False Your Answer: False Multiple Choice Multiple AnswerQuestion: Black Box testing techniques are:- Correct Answer: Graph Based Testing Methods , Equivalence Portioning , Boundary Value Analysis Your Answer: Graph Based Testing Methods , Stress Testing , Boundary Value Analysis Multiple Choice Multiple AnswerQuestion: The types of Software are Correct Answer: Business Software , Embedded Software , System Software Your Answer: Business Software , Embedded Software , System Software Multiple Choice Multiple AnswerQuestion: Following are the data models namely:- Correct Answer: Hierarchical Model , Network Model , Relational Model Your Answer: Hierarchical Model , Network Model , Relational Model Select The BlankQuestion: ________ is achieved by carving out a module that is responsible for any unique function and which does not need to interact with other parts of the system. Correct Answer: Functional Dependency Your Answer: Functional Dependency Multiple Choice Multiple AnswerQuestion: The stages of the Iterative Models are Correct Answer: Requirement Analysis , System Design , Development Coding & Unit Testing Your Answer: Requirement Analysis , System Design , Development Coding & Unit Testing Multiple Choice Multiple AnswerQuestion: In a Software Risk Management Risk drivers are :- Correct Answer: Technology , People , Requirements Your Answer: Technology , People , Requirements Select The BlankQuestion: ________ tests confirms that the needs and requirements are fulfilled on the deployment platform. Correct Answer: Beta Your Answer: Stress True/FalseQuestion: The major resources in the project is people and funds. Correct Answer: False Your Answer: False Match The FollowingMatch The FollowingQuestion Correct Answer Your AnswerEntity Object which is Uniquely Object which is Uniquely
Distinguished Distinguished Hierarchical Model Tree Structure Tree Structure Network Model Network Communications Network Communications Relational Model Data are Linked Data are Linked Select The Blank
Page 139 of 155 139
SCDL – 3rd Semester – Software Engineering and Project Management
Question: The company should establish a ________ and maintain a documented quality system as a means of ensuring that it conforms to the specified requirements of ISO. Correct Answer: Quality System Procedure Your Answer: Quality Management System
LIST OF ATTEMPTED QUESTIONS AND ANSWERS
Multiple Choice Multiple AnswerQuestion: The software designed with the correct choice of technology and architecture to ensure:Correct Answer: Customer Satisfaction , On-time Delivery , Developed with the budgeted costYour Answer: Customer Satisfaction , On-time Delivery , Developed with the budgeted cost
True/FalseQuestion: Risk which can be known is termed as unpredictable risk.Correct Answer: FalseYour Answer: False
Multiple Choice Single AnswerQuestion: A type of testing which eliminates the errors in the design, architecture and development & deployment process is.Correct Answer: Non Execution based testingYour Answer: Non Execution based testing
Multiple Choice Multiple AnswerQuestion: The broad quality parameters are:-Correct Answer: Reliability , Safety , SecurityYour Answer: Reliability , Safety , Security
True/FalseQuestion: E-R Diagrams are used to identify the Weak and Strong Relations.Correct Answer: TrueYour Answer: True
Multiple Choice Multiple AnswerQuestion: Resources required for a Software development activity could be :-Correct Answer: People , Development Environment , Reusable ComponentsYour Answer: People , Development Environment , Reusable Components
Multiple Choice Multiple AnswerQuestion: A good test is one that has:-Correct Answer: High Probability of detecting an error , Not Redundant , Simple to execute & IndependentYour Answer: High Probability of detecting an error , Not Redundant , Simple to execute & Independent
Multiple Choice Single AnswerQuestion: A System in which next state of the system can be predicted without doubt is :-Correct Answer: DeterministicYour Answer: Probabilistic
Multiple Choice Multiple Answer
Page 140 of 155 140
SCDL – 3rd Semester – Software Engineering and Project Management
Question: System Design Consists of:-Correct Answer: Level DFD's , System Flowcharts , ERD'sYour Answer: Level DFD's , System Flowcharts , ERD's
Match The FollowingQuestion: Correct Answer: Your Answer:World Wide Web Content provider Content providerSoftware Deteriorates Integrated SystemSystem Software File Management DeterioratesApplication Software Standalone Programs File Management
True/FalseQuestion: A software review is a filter for the software development process.Correct Answer: TrueYour Answer: True
True/FalseQuestion: Reactive risk strategies are applied to deal with risk when it occurs.Correct Answer: TrueYour Answer: True
Multiple Choice Single AnswerQuestion: A type of testing where the focus is on error/ mistake or fault detection and correction is:-Correct Answer: Process based TestingYour Answer: Process based Testing
Match The FollowingQuestion: Correct Answer: Your Answer:IEEE Institute of Electrical and Institute of Electrical and
Electronics Engineers Electronics EngineersWater Fall Model Customer Specific Structured ApproachSSAD Structured Approach Customer SpecificOOSAD Object Oriented Approach Object Oriented Approach
Multiple Choice Multiple AnswerQuestion: The Scope of the Software Project is defined by Statement of Work which is agreed by ?Correct Answer: Customers , Users , StakeholdersYour Answer: Users , Stakeholders , Customers
Select The BlankQuestion: ________ testing confirms that the needs and requirements are fulfilled in the development environment.Correct Answer: AlphaYour Answer: Alpha
True/FalseQuestion: SQA is ensured through a Quality Management System.Correct Answer: TrueYour Answer: True
Select The BlankQuestion: The Failure Curve of a Hardware is called as ________
Page 141 of 155 141
SCDL – 3rd Semester – Software Engineering and Project Management
Correct Answer: Bathtub CurveYour Answer: Bathtub Curve
Multiple Choice Multiple AnswerQuestion: The next development in software engineering isCorrect Answer: The use of tool generate the code , The extensive use od CASE tool for analysis and design , The use of Component technologyYour Answer: The use of tool generate the code , The extensive use od CASE tool for analysis and design , The use of Component technology
Multiple Choice Multiple AnswerQuestion: A formal Technical Review may include:-Correct Answer: Walkthroughs , Inspections , Roundrobin reviewsYour Answer: Walkthroughs , Inspections , Roundrobin reviews
True/FalseQuestion: Domain Specific applications are developed mostly integrating components which are similar in functionalityCorrect Answer: TrueYour Answer: True
Multiple Choice Single AnswerQuestion: A Principle in which the Functional Cohesion between the sub system is maintained:-Correct Answer: DecompositionYour Answer: Decomposition
Multiple Choice Multiple AnswerQuestion: Architecture Design Consists of:-Correct Answer: Module Structure , Program Structure , Hierarchy in the StructureYour Answer: Module Structure , Hierarchy in the Structure , Process Structure
True/FalseQuestion: White Box Testing Measures the Correctness of the Inputs and Basic Processes.Correct Answer: TrueYour Answer: True
Select The BlankQuestion: A ________ is understood as a possibility of Loss.Correct Answer: RiskYour Answer: Risk
Select The BlankQuestion: An incorrect decision by the designer, programmer or analyst that leads to improper result is an ________.Correct Answer: ErrorYour Answer: Error
Multiple Choice Single AnswerQuestion: An Approach which majorly focuses on Functions and data structure designed for those functions.Correct Answer: SSADYour Answer: SSAD
Page 142 of 155 142
SCDL – 3rd Semester – Software Engineering and Project Management
True/FalseQuestion: CAD/CAM/CAE are the examples of embedded SoftwareCorrect Answer: FalseYour Answer: False
Multiple Choice Single AnswerQuestion: A process which ensures that the materials input (Process input), the manufacturing process (software development process) and outgoing quality are of requisite standards is :-Correct Answer: Quality AssuranceYour Answer: Quality Management
True/FalseQuestion: Simplification rationalizes the complex , breakdown into clusters, making a meaningful and functionally complete design.Correct Answer: TrueYour Answer: True
Select The BlankQuestion: In the ________ model data elements are organized in tree structure in parent-child format.Correct Answer: HierarchicalYour Answer: Hierarchical
Select The BlankQuestion: A Module Tests focuses on ________.Correct Answer: Functions & DesignYour Answer: Functions & Design
Multiple Choice Multiple AnswerQuestion: White Box Testing Checks :-Correct Answer: All Paths in the process are correctly operational , All Logical decision are executed with true or false , All Loops are executedYour Answer: All Paths in the process are correctly operational , All Logical decision are executed with true or false , All Loops are executed
Multiple Choice Single AnswerQuestion: A process which breaks statement of work into smaller activities with clear start - finish definition is called as :-Correct Answer: Work Break Down StructureYour Answer: Work Break Down Structure
True/FalseQuestion: Errors in documentation give rise to fatal results.Correct Answer: TrueYour Answer: True
Select The BlankQuestion: ________ is a process of executing a program with the intent of finding an error.Correct Answer: TestingYour Answer: Testing
Select The Blank
Page 143 of 155 143
SCDL – 3rd Semester – Software Engineering and Project Management
Question: ________ is achieved by carving out a module that is responsible for any unique function and which does not need to interact with other parts of the system.Correct Answer: Functional DependencyYour Answer: Functional Dependency
Multiple Choice Multiple AnswerQuestion: System Testing Techniques are :-Correct Answer: Alpha Test , Beta TestYour Answer: Alpha Test , Beta Test
Multiple Choice Single AnswerQuestion: A model in which software development cycle is sequential process is :-Correct Answer: Waterfall ModelYour Answer: Waterfall Model
Select The BlankQuestion: To become a registered, one of the quality assurance system models contained in ISO 9000 a company's quality system is scrutinized by ________.Correct Answer: Third Party AuditorYour Answer: SQM
Multiple Choice Single AnswerQuestion: A software which resides in the read only memory and controls the functions of the resident ProductsCorrect Answer: Embedded SoftwareYour Answer: Embedded Software
Multiple Choice Single AnswerQuestion: A document which identifies and helps the project manager to focus on the grey areas or critical functions in the project is :-Correct Answer: Software Requirement SpecificationsYour Answer: Software Requirement Specifications
Multiple Choice Multiple AnswerQuestion: Project Metrics enable a software project manager to:-Correct Answer: Assess the Status of the Ongoing Project , Identify the Risk Potential , Uncover problem areas before they go CriticalYour Answer: Assess the Status of the Ongoing Project , Identify the Risk Potential , Uncover problem areas before they go Critical
Multiple Choice Single AnswerQuestion: A system for the support of software development is calledCorrect Answer: Computer Aided Software EngineeringYour Answer: Computer Aided Software Engineering
Multiple Choice Single AnswerQuestion: A Collection of Interrelated, Interdependent group of elements which interact to achieve certain objectives is called as:-Correct Answer: SystemYour Answer: Software
Select The BlankQuestion: Inadequacy or misout in SRS & RDD is ________.Correct Answer: Defect
Page 144 of 155 144
SCDL – 3rd Semester – Software Engineering and Project Management
Your Answer: Defect
Select The BlankQuestion: LOC Means________Correct Answer: Lines of CodeYour Answer: Lines of Code
LIST OF ATTEMPTED QUESTIONS AND ANSWERS
Select The BlankQuestion: The objective of a ________ is to test for what we want to achieve and not what is actually achieved.Correct Answer: Test PlanYour Answer: Testing
Multiple Choice Multiple AnswerQuestion: The Functionality of the Client application is tested using :-Correct Answer: Server Tests , Database Tests , Transaction TestsYour Answer: Transaction Tests , Client Tests , Server Tests
Multiple Choice Single AnswerQuestion: COCOMO Model is :-Correct Answer: Constructive Cost ModelYour Answer: Cost Control & Observe Model
Multiple Choice Multiple AnswerQuestion: OOSAD development approach usesCorrect Answer: Objects , Process modeling , Object attributesYour Answer: Objects , Process modeling , Object attributes
Multiple Choice Multiple AnswerQuestion: Test cases are built for :-Correct Answer: Data Structure , Specific Value ConditionsYour Answer: Data Structure , Specific Value Conditions , Units & Functions
Multiple Choice Single AnswerQuestion: A process of creating a document Statement of Work, and planning the major task deliveries is :-Correct Answer: Project PlanningYour Answer: Project Planning
Multiple Choice Multiple AnswerQuestion: The stages of the Iterative Models areCorrect Answer: Requirement Analysis , System Design , Development Coding & Unit TestingYour Answer: Requirement Analysis , System Design , Development Coding & Unit Testing
Multiple Choice Single AnswerQuestion: Source Code of the Software is available so that the engineers can make the local modifications and use the componentCorrect Answer: Open SourceYour Answer: Open Source
Page 145 of 155 145
SCDL – 3rd Semester – Software Engineering and Project Management
True/FalseQuestion: System Performance is measured through effectiveness and its efficiency.Correct Answer: TrueYour Answer: True
True/FalseQuestion: Software Development becomes complex due to the variety and heterogeneity of requirement of different Users and StakeholdersCorrect Answer: TrueYour Answer: True
Select The BlankQuestion: Usually the test cases are written using ________.Correct Answer: Testing TechniquesYour Answer: Testing Techniques
True/FalseQuestion: SRS is Systems requirement specifications in the software development phaseCorrect Answer: TrueYour Answer: True
True/FalseQuestion: Proactive risk strategies are applied to deal with risk when it occurs.Correct Answer: FalseYour Answer: True
Multiple Choice Single AnswerQuestion: A Systematic approach to organise and documents the need of the customer which is a basis for software development is :-Correct Answer: Requirements ManagementYour Answer: Requirements Management
True/FalseQuestion: System testing checks the abnormality in the software system.Correct Answer: FalseYour Answer: False
Select The BlankQuestion: ________ is the Significant project risk the management has to face in software development activity due to budgeting constraints.Correct Answer: FundingYour Answer: Funding
Multiple Choice Single AnswerQuestion: A System which is not influenced by the external environment:-Correct Answer: Closed SystemYour Answer: Closed System
Multiple Choice Multiple AnswerQuestion: SQA efforts most primarily assures:-Correct Answer: Software Quality , Software Reliability , Software AvailabilityYour Answer: Software Quality , Software Reliability , Software Availability
True/False
Page 146 of 155 146
SCDL – 3rd Semester – Software Engineering and Project Management
Question: People, Procedures and Parameters are the Drivers of the Technology.Correct Answer: FalseYour Answer: True
Multiple Choice Multiple AnswerQuestion: Testing a Design Includes:-Correct Answer: Test Procedures , Test Plans , Design Renew PlansYour Answer: Test Procedures , Test Plans , Design Renew Plans
Select The BlankQuestion: Inventory Control System which is designed based on demand and supply variations could be an example of ________ systemCorrect Answer: ProbabilisticYour Answer: Probabilistic
Multiple Choice Single AnswerQuestion: Who Defines SE as the application of a Systematic, disciplined and quantifiable approach to the development and maintenance of a SoftwareCorrect Answer: IEEEYour Answer: ISO - 9001
Select The BlankQuestion: SE Methodology rides on two components, System Engineering and ________.Correct Answer: Development EngineeringYour Answer: Requirement analysis
Select The BlankQuestion: A unit tests major focuses on ________Correct Answer: Processes & CodeYour Answer: Processes & Code
Match The FollowingQuestion: Correct Answer: Your Answer:Entity Object which is Uniquely Object which is Uniquely
Distinguished DistinguishedHierarchical Model Tree Structure Tree StructureNetwork Model Network Communications Network CommunicationsRelational Model Data are Linked Data are Linked
True/FalseQuestion: Recovery testing focuses on the Cost Recovery Plan of the Software Implemented.Correct Answer: FalseYour Answer: False
Multiple Choice Multiple AnswerQuestion: Risk Management is a Process based on application of :-Correct Answer: Game Theory , Probability Theory , Decision TheoryYour Answer: Game Theory , Probability Theory , Decision Theory
True/FalseQuestion: The prime objective of Formal Technical Review is to locate the error before it passes on to the other activity.Correct Answer: True
Page 147 of 155 147
SCDL – 3rd Semester – Software Engineering and Project Management
Your Answer: True
Select The BlankQuestion: A ________ Measures the Quality of the output produced by the SystemCorrect Answer: EffectivenessYour Answer: Effectiveness
Multiple Choice Multiple AnswerQuestion: RMMM Plan deals with :-Correct Answer: Mitigation , Monitoring , ManagementYour Answer: Mitigation , Monitoring , Management
Select The BlankQuestion: ________ tests confirms that the needs and requirements are fulfilled on the deployment platform.Correct Answer: BetaYour Answer: Beta
Select The BlankQuestion: A collection of programs written to service other set of programs and its functions is called as ________Correct Answer: System SoftwareYour Answer: System Software
Multiple Choice Multiple AnswerQuestion: The responsibilities of Software ManagerareCorrect Answer: To maintain budget , Keep schedules from slipping , Improve qualityYour Answer: To maintain budget , Keep schedules from slipping , Improve quality
Multiple Choice Single AnswerQuestion: A Step in risk Management which identifies and enumerates the risk is :-Correct Answer: Risk IdentificationYour Answer: Risk Mitigation
Multiple Choice Multiple AnswerQuestion: Software Risk could be of :-Correct Answer: Process Risk , Project Risk , Product RiskYour Answer: Process Risk , Project Risk , Product Risk
Multiple Choice Single AnswerQuestion: A Process of organizing the sub systems as one system to reduce the number of connectivities or interfaces:-Correct Answer: SimplificationYour Answer: Simplification
Multiple Choice Single AnswerQuestion: A layer in which rules and regulations , functions and processes, dataflows and process flows are visualized:-Correct Answer: LogicalYour Answer: Operational
Multiple Choice Multiple AnswerQuestion: IN OOSAD, Objects haveCorrect Answer: attribute , Methods , relationship
Page 148 of 155 148
SCDL – 3rd Semester – Software Engineering and Project Management
Your Answer: attribute , Methods , relationship
Multiple Choice Single AnswerQuestion: The Software development engineering which builds objects of models independent of the system under consideration is ?Correct Answer: OOSADYour Answer: OOSAD
Multiple Choice Single AnswerQuestion: A Modification of the Software is done to accommodate the changes forced by the external environment isCorrect Answer: Adaptive MaintenanceYour Answer: Adaptive Maintenance
Select The BlankQuestion: The ________ phase of software engineering focuses on how data are to be structured and programs are to be developedCorrect Answer: DevelopmentYour Answer: Development
True/FalseQuestion: Stress Testing is a part of Integration testing.Correct Answer: FalseYour Answer: False
True/FalseQuestion: ISO 9001 is used to develop quality assurance systems.Correct Answer: TrueYour Answer: True
Multiple Choice Multiple AnswerQuestion: Test Case Design for real time systems strategically should include:-Correct Answer: Task Testing , Behavioral Testing , Intertask TestingYour Answer: Task Testing , Behavioral Testing , Intertask Testing
Select The BlankQuestion: Cohesion and Coupling is the criteria for measuring ________.Correct Answer: Functional DependencyYour Answer: Functional Dependency
Multiple Choice Single AnswerQuestion: A system is divided broadly into how many layers?Correct Answer: 4 layersYour Answer: 3 layers
Match The FollowingQuestion: Correct Answer: Your Answer:Closed System Parameter are fixed Parameter are fixedDeterministic System Predictable Behavior Predictable BehaviorProbabilistic System Unpredictable Behavior Unpredictable BehaviorOpen System Parameters are Variables Parameters are Variables
Page 149 of 155 149
SCDL – 3rd Semester – Software Engineering and Project Management
LIST OF ATTEMPTED QUESTIONS AND ANSWERS
Multiple Choice Multiple AnswerQuestion Software Risk could be of :-Correct Answer Process Risk , Project Risk , Product Risk Your Answer Product Risk , Process Risk , Project Risk
Multiple Choice Single AnswerQuestion A type of testing which verifies that all the system elements are meshed properly and that overall system function / performance is achieved is:-Correct Answer System testingYour Answer System testing
Multiple Choice Multiple AnswerQuestion Black Box testing techniques are:-Correct Answer Graph Based Testing Methods , Equivalence Portioning , Boundary Value Analysis Your Answer Graph Based Testing Methods , Equivalence Portioning , Boundary Value Analysis
Multiple Choice Single AnswerQuestion A unit testing technique which concentrates only of the functions and features of the software product is:-Correct Answer Black Box TestingYour Answer Black Box Testing
Multiple Choice Multiple AnswerQuestion Design Constraints include:-Correct Answer Resource Limitations , Platform Limitations , Protocol Limitations Your Answer Resource Limitations , Platform Limitations , Protocol Limitations
True/FalseQuestion The Unit of the Software is the smallest entity to be tested.Correct Answer TrueYour Answer True
True/FalseQuestion The Major risk involved in software project is to identify the programmers required and the pay scales of them.Correct Answer FalseYour Answer False
Select The BlankQuestion The Plat Form of the software is developed keeping in mind of certain hardware and ________
Page 150 of 155 150
SCDL – 3rd Semester – Software Engineering and Project Management
Correct Answer Operating SystemYour Answer Operating System
Multiple Choice Single AnswerQuestion To set the standards and measure and compare the quality according to American Heritage dictionary, what is essential?Correct Answer AttributeYour Answer Attribute
True/FalseQuestion SRS is one of the cause of not meeting the SQA.Correct Answer TrueYour Answer True
Select The BlankQuestion ________ is achieved by carving out a module that is responsible for any unique function and which does not need to interact with other parts of the system.Correct Answer Functional DependencyYour Answer Functional Dependency
True/FalseQuestion Functional Testing focuses on the Basic Functionality of the Software.Correct Answer TrueYour Answer True
Multiple Choice Multiple AnswerQuestion Test Case Design for real time systems strategically should include:-Correct Answer Task Testing , Behavioral Testing , Intertask Testing Your Answer Task Testing , Behavioral Testing , Intertask Testing
Multiple Choice Single AnswerQuestion A System flow chart is also called as:-Correct Answer State Transaction DiagramYour Answer State Transaction Diagram
Multiple Choice Single AnswerQuestion A Systematic approach to organise and documents the need of the customer which is a basis for software development is :-Correct Answer Requirements ManagementYour Answer Requirements Management
Match The FollowingQuestion Correct Answer Your AnswerDevelopment of the Software Software Programs Software ProgramsCorrective Maintenance MaintenanceProcess, Tools & Methods Software Engineering Layers Software Engineering LayersRequirement Specifications Definition Phase Definition Phase
Page 151 of 155 151
SCDL – 3rd Semester – Software Engineering and Project Management
Multiple Choice Multiple AnswerQuestion RMMM Plan deals with :-Correct Answer Mitigation , Monitoring , Management Your Answer Mitigation , Monitoring , Management
Multiple Choice Single AnswerQuestion The extent of software functions with precision without any failure is :-Correct Answer ReliabilityYour Answer Reliability
Multiple Choice Multiple AnswerQuestion IN OOSAD, Objects haveCorrect Answer attribute , Methods , relationship Your Answer attribute , Methods , relationship
Select The BlankQuestion A ________ Measures the Efforts / cost / time used to achieve the output.Correct Answer EfficiencyYour Answer Efficiency
True/FalseQuestion The major resources in the project is people and funds.Correct Answer FalseYour Answer False
Multiple Choice Single AnswerQuestion A Standard Method which helps in keeping the system as an acceptable standards is:-Correct Answer Periodical MaintenanceYour Answer Periodical Maintenance
Multiple Choice Single AnswerQuestion A System is one that is self contained and self reliant:-Correct Answer Closed SystemYour Answer Closed System
Multiple Choice Multiple AnswerQuestion The Factors enabling easy change are :-Correct Answer Maintainability , Flexibility , Testability Your Answer Maintainability , Flexibility , Testability
Multiple Choice Single AnswerQuestion At the beginning testing focuses on each component individually, ensuring that it function properly as a unit or not this is termed as:-Correct Answer Unit TestingYour Answer Unit Testing
Select The BlankQuestion LOC Means________
Page 152 of 155 152
SCDL – 3rd Semester – Software Engineering and Project Management
Correct Answer Lines of CodeYour Answer Lines of Code
Multiple Choice Single AnswerQuestion A Cost which includes quality planning, measuring & monitoring the quality aspect and its training is :-Correct Answer Achievement CostYour Answer Achievement Cost
Multiple Choice Multiple AnswerQuestion Fourth generation technology helps to controlCorrect Answer Effort , Resource , Cost development Your Answer Effort , Resource , Cost development
True/FalseQuestion System Performance is measured through effectiveness and its efficiency.Correct Answer TrueYour Answer True
True/FalseQuestion Reactive risk strategies are applied to deal with risk when it occurs.Correct Answer TrueYour Answer True
Select The BlankQuestion Inadequacy or misout in SRS & RDD is ________.Correct Answer DefectYour Answer Defect
Match The FollowingQuestion Correct Answer Your AnswerEntity Object which is Uniquely Distinguished Object which is Uniquely DistinguishedHierarchical Model Tree Structure Tree StructureNetwork Model Network Communications Network CommunicationsRelational Model Data are Linked Data are Linked
Select The BlankQuestion Requirements Management Begins with ________.Correct Answer IdentificationYour Answer Identification
Multiple Choice Multiple AnswerQuestion Project Metrics enable a software project manager to:-Correct Answer Assess the Status of the Ongoing Project , Identify the Risk Potential , Uncover problem areas before they go Critical Your Answer Assess the Status of the Ongoing Project , Identify the Risk Potential , Uncover problem areas before they go Critical
Page 153 of 155 153
SCDL – 3rd Semester – Software Engineering and Project Management
Select The BlankQuestion The company should establish a ________ and maintain a documented quality system as a means of ensuring that it conforms to the specified requirements of ISO.Correct Answer Quality System ProcedureYour Answer Quality System Procedure
Select The BlankQuestion SE Methodology rides on two components, System Engineering and ________.Correct Answer Development EngineeringYour Answer Development Engineering
Multiple Choice Multiple AnswerQuestion The stages of the Iterative Models areCorrect Answer Requirement Analysis , System Design , Development Coding & Unit Testing Your Answer Requirement Analysis , System Design , Development Coding & Unit Testing
Multiple Choice Single AnswerQuestion The Scope of the work in a Software Project is defined by :-Correct Answer Statement of WorkYour Answer Statement of Work
True/FalseQuestion People, Procedures and Parameters are the Drivers of the Technology.Correct Answer FalseYour Answer False
Select The BlankQuestion ________ testing confirms that the needs and requirements are fulfilled in the development environment.Correct Answer AlphaYour Answer Alpha
Multiple Choice Multiple AnswerQuestion The Software Risk affects :-Correct Answer Project Development , Software Product , Process of Development Your Answer Project Development , Software Product , Process of Development
Select The BlankQuestion In ________model two sets of data are linked by a relationship.Correct Answer RelationalYour Answer Relational
Multiple Choice Single AnswerQuestion A Phenomenon which states that over a period of times the system gets into a phase of degrading and disorganization is:-Correct Answer EntropyYour Answer Entropy
Page 154 of 155 154
SCDL – 3rd Semester – Software Engineering and Project Management
Multiple Choice Multiple AnswerQuestion Project Risk Management Includes:-Correct Answer Risk Prevention , Risk Avoidance , Risk Mitigation Your Answer Risk Prevention , Risk Avoidance , Risk Mitigation
True/FalseQuestion SE is applied for software development through Engineering MethodsCorrect Answer TrueYour Answer True
Select The BlankQuestion An accounting System based on rules and Principles could be an example of ________ System.Correct Answer DeterministicYour Answer Deterministic
True/FalseQuestion A Software solution is evolved in parts as in an incremental fashion in incremental modelCorrect Answer TrueYour Answer True