scdot and asset management. bridge services current contract – 2008-2013 – asset maintenance...

7
SCDOT and Asset Management

Upload: erica-tench

Post on 02-Apr-2015

222 views

Category:

Documents


6 download

TRANSCRIPT

Page 1: SCDOT and Asset Management. Bridge Services Current Contract – 2008-2013 – Asset Maintenance Contract for Arthur Ravenel Bridge System in Charleston and

SCDOT and

Asset Management

Page 2: SCDOT and Asset Management. Bridge Services Current Contract – 2008-2013 – Asset Maintenance Contract for Arthur Ravenel Bridge System in Charleston and

Bridge Services

• Current Contract – 2008-2013– Asset Maintenance Contract for Arthur Ravenel

Bridge System in Charleston and several other select bridge systems in Beaufort, Berkeley, and Charleston counties

– Schedule of services

Page 3: SCDOT and Asset Management. Bridge Services Current Contract – 2008-2013 – Asset Maintenance Contract for Arthur Ravenel Bridge System in Charleston and

Bridge Services

• Planned Contract – 2013–RFP sent to MMO for advertisement–Expanding the contract to add:• 8 moveable bridge systems•Maintenance and operation

Page 4: SCDOT and Asset Management. Bridge Services Current Contract – 2008-2013 – Asset Maintenance Contract for Arthur Ravenel Bridge System in Charleston and

Road Services - Planned

• Performance based contract for fence to fence maintenance of 116 miles of I-85 and I-85 Bus. including bridges and overpasses

• Advertised and received proposals for the baseline / third-party assessment contract

Page 5: SCDOT and Asset Management. Bridge Services Current Contract – 2008-2013 – Asset Maintenance Contract for Arthur Ravenel Bridge System in Charleston and

Current Status - Delayed

• Other contracts– I-85/I-385 Interchange Project– I-85 OGFC Project– I-85 Widening Project

• Funding– State Funds Only

Page 6: SCDOT and Asset Management. Bridge Services Current Contract – 2008-2013 – Asset Maintenance Contract for Arthur Ravenel Bridge System in Charleston and

Questions?

David CookState Maintenance Engineer

SC Department of Transportation(803) 737-1290

Page 7: SCDOT and Asset Management. Bridge Services Current Contract – 2008-2013 – Asset Maintenance Contract for Arthur Ravenel Bridge System in Charleston and

5TH ANNUAL CONFERENCE