schedule20 commercially sensitive information waste... · sj/ adb/73626/120029/ukm/3341 0506.23 427...
TRANSCRIPT
Schedule 20 - Commercially Sensitive Information
SCHEDULE20
Commercially Sensitive Information
I.
1.1
1.1.1
1.1.2
1.1.3
1.1.4
1.2
1.2.1
1.2.2
1.2.2.1
SJ/ ADB/73626/120029/UKM/3341 0506.23 409
Schedule 20 - Commercially Sensitive Information
1.2.2.2
1.2.2.3
1.2.2.4
1.2.2.5
1.2.2.6
1.2.2. 7
1.2.3
1.3
1.3 .I
1.3.2
1.3 .3
1.3.4
1.3 .5
1.3 .6
1.3. 7
1.3.8
1.3.9
1.3 .I 0
1.3.11
1.3.12
SJ I AD 8/73626/120029/UKM/3341 05 06.23 410
Schedule 20 -Commercially Sensitive Information
1.3 .13
1.3.14
1.3.15
1.3.16
1.3.17
1.3.18
1.4
1.5
1.6
1.6.1
1.6.2
1.6.3
1.6.4
SJ/ ADB/73626/120029/UKM/3341 0506.23 411
Schedule 20 - Commercially Sensitive Information
1.6.5
1.6.6
1.6.7
1.6.8
1.6.9
1.6.10
1.6.11
1.6.12
1.6.13
1.6.14
1.6.15
1.6.16
1.6.17
1.6.18
1.6.19
1.6.20
1.6.20 1
Sl/ AD B/73626/120029/UKM/3341 0 506.23 412
Schedule 20- Commercially Sensitive Information
1.6.20.2"
1.6.20.3 "
1.6.20.4"
1.6.20.5
1.6.20.7"
1.6.20.8"
1.6.20.9"
1.6.20.10
1.6.20.11
1.6.20.12
1.6.20.13
1.6.20.14
1.6.20.15
1.6.20.16
1.6.21
1.6.22
SJ/ADB/73626/120029/UKM/33410506.23 413
Schedule 20 - Commercially Sensitive Information
1. 7
1.8
1.8.1
1.8.2
1.8.3
1.8.4
1.8.5
1.8.6
1.9
1.1 0
1.11
1.12
1.13
SJ/ADB/73626/120029/UKM/33410506.23 414
Schedule 20 - Commercially Sensitive Information
1.13.1
J.l3.2
J.l3.3
1.13.4
J.l3.5
1.13.6
1.13.7
SJ/ADB/73626/120029/UKM/33410506.23 415
Schedule 20 - Commercially Sensitive Infonnation
APPENDIX
I.
1.1
1.1.1
1.1.1.1
1.1.1.2
1.1.1.3
1.1.2
1.1.2.1
1.1.2.2
1.1.2.3
1.1.2.4
1.1.2.5
1.1.2.6
1.1.2.7
1.1.2.8
SJ/ADB/73626/120029/UKM/33410506.23 416
Schedule 20 - Commercially Sensitive Information
1.1.2.9
1.1.2.10
1.1.2.11
1.1.2.12
1.1.2.13
1.1.2.14
1.1.3
1.1.3.1
(a)
(b)
(c)
(d)
(e)
(f)
(g)
(h)
(i)
G)
(k)
(I)
(m)
SJ/ADB/73626/120029/UKM/33410506.23 417
Schedule 20 - Commercially Sensitive Information
(n)
(o)
(p)
1.1.3.2
1.1.3.3
1.1.3.4
1.1.3 .5
1.1.3.6
1.1.3.7
1.1.3.8
1.1.3.9
1.1.3.10
1.1.3.11
1.1.3.12
1.1.3.13
1.1.3.14
1.1.3.15
1.1.4
SJ/ AD B/73 626/120029/UKM/3341 05 06.23 418
Schedule 20- Commercially Sensitive Information
1.1.5
1.1.6
1.1. 7
2.
SJ/ ADB/73 626/120029/UKM/3341 0506.23 419
Schedule 20 - Commercially Sensitive Information
SJ/ AD B/73626/120029/UKM/3 341 0506.23 420
Schedule 20 - Commercially Sensitive Information
SJ/ ADB/73626/12002 9/UKM/3 3 41 05 06.23 421
Schedule 20 - Commercially Sensitive Information
SJ/ ADB/73 626/120029/UKM/3341 0 5 06. 23 422
Schedule 20 - Commercially Sensitive Information
SJ I AD B/73626/120029/UKM/3341 05 06.23 423
Schedule 21- Collateral Warranties
SCHEDULE21
Collateral Warranties
SJ/ ADB/73626/120029/UKM/3341 0506.23 424
Schedule 21- Collateral Warranties
DATED
(1) [CONSTRUCTION CONTRACTOR]
-and-
(2) [LEEDS CITY COUNCIL]
-and-
(3) [CONTRACTOR]
DUTY OF CARE DEED relating to
the design and construction of residual waste treatment facilities in the City of Leeds
SJ I ADB/73626/120029/UKM/3 341 0506 .23
2012
425
Schedule 21 -Collateral Warranties
TIDS DEED is made on 2012
BETWEEN
(I) [CONSTRUCTION CONTRACTOR] (company number+ ) whose registered
office is at + ("Construction Contractor");
(2) LEEDS CITY COUNCIL of Civic Hall, Leeds LSI IUR ("City Council"), which
expression includes its permitted successors in title and assigns; and
(3) CONTRACTOR (company number +
+ ("Contractor").
) whose registered office IS at
BACKGROUND
A By a project agreement dated [ + ] ("Project Agreement") the City
Council has appointed the Contractor to carry out, in relation to the waste treatment facilities
therein described as the Facilities ("Facilities"), the provision of services relating to tl1e
design, installation, operation and maintenance of residual waste treatment facilities for the
City of Leeds including the carrying out of the Works and the provision of the Services.
B The Construction Contractor has been appointed by the Contractor under a contract dated
[ + ] ("Construction Contract") to carry out, in relation to the Sites, the design
and construction of the Works.
C The Construction Contractor is obliged under the Construction Contract to give a warranty in
this form in favour of the City Council.
I. DEFINITIONS AND INTERPRETATIONS
Unless expressly defined otherwise in this Deed, any defined term in this Deed shall have the
same meaning given to such term in the Construction Contract.
2. OPERATIVE PROVISIONS
In consideration of the payment of one pound (£1.00) by the City Council to the Construction
Contractor, receipt of which the Construction Contractor acknowledges:
SJ/ ADB/73626/120029/UKM/3341 0506.23 426
Schedule 21 -Collateral Warranties
3. CONSTRUCTION CONTRACTOR'S WARRANTY AND LIABILITY
3 .I The Construction Contractor warrants to the City Council that it has carried out and will
continue to carry out its duties under the Construction Contract in accordance with the
Construction Contract and that it has exercised and will continue to exercise, in carrying out
the design of the Works, the level of skill and care reasonably to be expected from an
appropriately qualified and competent professional designer providing those services in
relation to a project of a similar size and scope to the Works. In particular and without
limiting the generality of the foregoing the Construction Contractor covenants with the City
Council that it has carried out and will carry out and complete the Works in accordance with
the Construction Contract and duly observe and perform all its duties and obligations
thereunder.
3.2 The Construction Contractor shall be entitled in any action or proceedings by the City
Council to raise equivalent rights in defence of liability (except for set off or counterclaim) as
it would have against the Contractor under the Construction Contract, and shall have no
liability under this Deed that is of greater or of longer duration than it would have had if the
City Council had been a party to the Construction Contract as joint employer. Upon the
expiry of twelve (12) years from the date of completion of the Works in accordance with the
Construction Contract, the liability of the Construction Contractor under this Deed shall cease
and determine, save in relation to any claims made by the City Council against the
Construction Contractor and notified by the City Council to the Construction Contractor in
writing prior thereto.
3.3 The Construction Contractor shall have no liability to the City Council in respect of any delay
in the completion of the Works howsoever caused save to the extent that the liability arises
under the Construction Contract and the City Council shall have exercised its right to step in
under clause 9.
4. PROJECT DATA
4.1 The Construction Contractor hereby grants (or, if such grant cannot legally take place until a
later date, agrees to grant) to the City Council with effect from the date of this Deed or in the
case of Project Data not yet in existence with effect from the creation thereof, a royalty-free
non-exclusive licence (such licence to remain in full force and effect notwithstanding
completion of the Construction Contractor's obligations under the Construction Contract or
the termination of the Construction Contract or the determination of the Construction
SJ/ ADB/73626/120029/UKM/3341 0506.23 427
Schedule 21 -Collateral Warranties
Contractor's engagement under it or any dispute thereunder or hereunder) to use and to
reproduce all Project Data for any purpose whatsoever connected with the Works and such
other purposes as are reasonably foreseeable including, but without limitation, the execution,
completion, maintenance, letting, advertisement, modification, extension, reinstatement and
repair of the Works. Such licence will carry the right to grant sub-licences and will be
transferable to third parties.
4.2 The City Council will not hold the Construction Contractor liable for any use it may make of
the Project Data for any purpose other than that for which they were originally provided by it
and other than for such other uses as are reasonably foreseeable unless the Construction
Contractor authorises such use and confinns the Project Data are suitable for it.
4.3 The Construction Contractor will not grant to any third party the right to use any of the
Project Data save under any warranty it is obliged to give under the Construction Contract or
hereunder or as otherwise required to enable it to fulfil its obligations under the Construction
Contract.
4.4 The Construction Contractor agrees on reasonable request at any time and following
reasonable written prior notice to give the City Council or those authorised by it access to the
Project Data and to provide copies (including copy negatives and CAD disks) thereof at the
City Cotmcil's expense.
4.5 The Construction Contractor warrants to the City Council that he has used the standard of
skill, care and diligence as set out in clause 3.1 see that the Project Data (save to the extent
duly appointed sub-contractors have been used to prepare the same) are its own original work
and that in any event their use in connection with the Works will not infringe the rights of any
third party
5. INSURANCE
5 .I The Construction Contractor hereby covenants with the City Council to:
5 .1.1 take out and maintain Professional Indemnity insurance cover with a limit of
indemnity that shall be a minimum often million pounds (£10,000,000) for each and
every loss and that it will maintain such insurance with reputable insurers carrying on
business in the European Union from the date hereof until twelve (12) years after
practical completion of the Works, provided that such insurance is generally available
in the market to members of the Construction Contractor's profession at commercially
SJ I AD B/73626/ 120029/U KM/3341 0506.23 428
Schedule 21 -Collateral Warranties
reasonable rates and provided further that payment of any increased or additional
premiums required by insurers by reason of the Construction Contractor's own claims
record or other acts, omissions, matters or things peculiar to the Construction
Contractor will be deemed to be within the reasonable rates;
5.1.2 provide evidence (as and when reasonably required by the City Council) satisfactory
to the City Council of the Professional Indemnity insurance referred to in clause 5.1.1
being in full force and effect from the date of the Construction Contract (such
evidence to include details of the cover);
5 .1.3 provide the City Council with notice of:
5 .1.3 .I any cancellation of the Professional Indemnity insurance referred to in
clause 5.1.1 not less than thirty (30) days prior to the relevant cancellation
date; and
5 .1.3 .2 any adverse material changes to or suspension of cover relevant to the Works
not less than thirty (30) days prior to the relevant change or suspension;
5 .1.4 inform the City Council as soon as reasonably practicable of any claim under the
Professional Indemnity insurance referred to in clause 5 .1.1 in respect of the Works in
excess of five hundred thousand pounds (£500,000) and provide such information to
the City Council as the City Council may reasonably require in relation to such claim
and provide notice of any potential breach of the limit of the policy; and
5.1.5 indemnify the City Council in respect of any subrogation claim by the insurers
brought in connection with any claim made under the Professional Indemnity
insurance referred to in clause 5 .I. I.
6. CITY COUNCIL'S REMEDIES
The rights and benefits conferred upon the City Council by this Deed are in addition to any
other rights and remedies it may have against the Construction Contractor including without
prejudice to the generality of the foregoing any remedies in negligence.
7. ASSIGNMENT
The benefit of and the rights of the City Council under this Deed may be assigned without the
consent of the Construction Contractor and the City Council will notify the Construction
Contractor in writing following any such assignment specifying the name and address of the
SJ/ADB/73626/120029/UKM/33410506.23 429
Schedule 21 - Collateral Warranties
assignee and the date of the assignment. The Construction Contractor will not contend that
any such assignee is precluded from recovering any loss resulting from any breach of this
Deed (whatever the date of such breach) by reason only that that person is an assignee and not
the original beneficiary hereunder or by reason that the original beneficiary or any
intermediate beneficiary escaped any loss resulting from such breach by reason of the
disposal of any interest in the Site or that the original beneficiary or any intermediate
beneficiary has not suffered any, or as much, loss.
8. INSPECTION OF PROJECT DATA
The Construction Contractor's liabilities under this Deed will not be in any way reduced or
extinguished by reason of any inspection or approval of the Project Data or attendance at site
meetings or other enquiry or inspection which the City Council may make or procure to be
made for its benefit or on its behalf.
9. STEP-IN RIGHTS IN FAVOUR OF THE CITY COUNCIL
9 .I The Construction Contractor will not exercise or seek to exercise any right which may be or
become available to it to terminate or treat as terminated or repudiated the Construction
Contract or its engagement under it or discontinue or suspend the performance of any duties
or obligations thereunder without first giving to the City Council not less than thirty (30) days'
prior written notice specifYing the Construction Contractor's ground for terminating or
treating as terminated or repudiated the Construction Contract or its engagement under it or
discontinuing or suspending its performance thereof and stating the amount (if any) of monies
outstanding under the Construction Contract. Within such period of notice:
9.1.1 the City Council may give written notice to the Construction Contractor that the City
Council will thenceforth become the Contractor under the Construction Contract to
the exclusion of the Contractor and thereupon the Constmction Contractor will admit
that the City Council is the Contractor under the Construction Contract and the
Construction Contract will be and remain in full force and effect notwithstanding any
of the said grounds;
9.1.2 if the City Council has given such notice as aforesaid or under clause 9.3, the City
Council shall accept liability for the Contractor's obligations under the Construction
Contract and will as soon as practicable thereafter remedy any outstanding breach by
the Contractor which properly has been included in the Construction Contractor's
specified grounds and which is capable of remedy by the City Council; and
SJ/ADB/73626/120029/UKM/33410506.23 430
Schedule 21 -Collateral Warranties
9.1.3 if the City Council has given such notice as aforesaid or under clause 9.3, the City
Council shall from the service of such notice become responsible for all sums
properly payable to the Construction Contractor under the Construction Contract
accruing due after the service of such notice but the City Council shall in paying such
sums be entitled to the same rights of set-off and deduction as wonld have applied to
the Contractor nnder the Construction Contract.
9.2 Notwithstanding anything contained in this Deed and notwithstanding any payments which
may be made by the City Council to the Construction Contractor, the City Council will not be
under any obligation to the Construction Contractor nor will the Construction Contractor have
any claim or cause of action against the City Council unless and until the City Council has
given written notice to the Construction Contractor pursuant to clause 9.1.1 or clause 9.3.
9.3 The Construction Contractor further covenants with the City Council that if the Project
Agreement is terminated by the City Council the Construction Contractor, if requested by the
City Council by notice in writing and subject to clause 9.1.2 and clause 9.1.3, will accept the
instructions of the City Council to the exclusion of the Contractor in respect of its duties
under the Construction Contract upon the terms and conditions of the Construction Contract
and will if so requested in writing enter into a novation agreement whereby the City Council
is substituted for the Contractor under the Construction Contract.
9.4 The Contractor acknowledges that the Construction Contractor will be entitled to rely on a
notice given to the Construction Contractor by the City Council under clause 9.3 as
conclusive evidence that the Project Agreement has been terminated by the City Council.
9.5 The City Council may by notice in writing to the Construction Contractor appoint another
person to exercise its rights under this clause 9 subject to the City Council remaining liable to
the Construction Contractor as guarantor for its appointee in respect of its obligations under
this Deed.
9.6 Upon request by the City Council the Construction Contractor agrees to co-operate with the
City Council in determining the duties perfonned or to be performed by the Construction
Contractor and to provide a copy of the Construction Contract and any variations thereto and
details of all monies paid and due under the Construction Contract.
SJ/ADB/73626/120029/UKM/33410506.23 431
Schedule 21 -Collateral Warranties
10. INTERRELATIONSHIP BETWEEN STEP IN AND COMPENSATION ON
TERMINATION
In the event that the City Council has made any payments to the Construction Contractor
pursuant to clause 9 above and the Project Agreement terminates for a Contractor Default,
then the City Council shall be entitled to be reimbursed by the Contractor for any payments so
made. For the avoidance of doubt, the City Council shall be entitled to set-off any sums
owing to it by the Contractor under this paragraph against any payments to be made by the
Authority to the Contractor under Part 2 (Compensation on Termination for Contractor
Default) of schedule 16 (Compensation on Termination) of the Project Agreement.
II. LIMITATION
Without prejudice to the provisions of clause 9.1, the City Council shall not be entitled to take
any action or proceedings against the Construction Contractor pursuant to this Deed unless
and until the Project Agreement has been terminated or has expired.
12. THE CONTRACTOR'S INCLUSION AS PARTY
The Contractor has agreed to be a party to this Deed for the purpose of clause 16 and for
acknowledging that the Construction Contractor shall not be in breach of the Construction
Contract by complying with the obligations imposed on it by this Deed.
13. COUNTERPARTS
This Deed may be executed in one or more counterparts. Any single counterpart or a set of
counterparts executed, in either case, by all the parties shall constitute a full and original
instrument for all purposes.
14. SUB-CONTRACTORS
Following a written request from the City Council the Construction Contractor will (unless it
has already done so) and/ or procure that its sub-contractors execute a deed of collateral
warranty in the relevant form specified in the Construction Contract in favour of any person
in whose favour the Construction Contract obliges the Construction Contractor to give or
procure the giving of such a warranty.
15. APPLICABLE LAW AND JURISDICTION
This Deed will be construed in accordance with English law and be in all respects subject to
the exclusive jurisdiction of the English courts.
SJ I ADB/73626/120029 /UKM/3 341 0 5 06.23 432
Schedule 21 - Collateral Warranties
16. THIRD PARTY RIGHTS
This Deed is enforceable by the original parties to it and by their successors in title and
permitted assignees. Any rights of any person to enforce the terms of this Deed pursuant to
the Contracts (Rights of Third Parties) Act 1999 are excluded.
17. NOTICES
Any notice to be given by any party will be sufficiently served if sent by hand, by facsimile
transmission or by post to the registered office or if there is none the last known address of
the party to be served. Any notice sent by hand will be deemed to be served on the date of
delivery and any notice sent by facsimile transmission will be deemed to be served in full at
the time recorded on the facsimile report sheet, provided that if any notice sent by hand or
facsimile is sent after 4.45pm on any day it will be deemed to be served on the next Business
Day. Any notice sent by post will be deemed to have been duly served at the expiration of
forty-eight (48) hours after the time of posting if the end of that period falls before 4.45pm on
a Business Day and otherwise on the next Business Day.
IN WITNESS of which this document is executed as a Deed and is delivered on the date first before
written
Executed as a deed by the CONSTRUCTION ) CONTRACTOR acting by a director and its ) secretary/two directors: ) Signature ________________________________ _
Name (block capitals) . ______________________________ _
Director
Signature . _______________________________ _
Name (block capitals) --------------------------------Secretaryillirector
SJ/ AD B/73626/120029/UKM/3341 0 506.23 433
Executed as a deed by the CONTRACTOR acting by a director and its secretary /two directors:
The Common Seal of LEEDS CITY COUNCIL was affixed in the presence of:
SJ/ AD B/73626/120029/UKM/3341 05 06.23
) ) )
) )
Schedule 21 - Collateral Warranties
Signature . _______________________________ _
Name (block capitals) --------------------------------Director
Signature . _______________________________ _
Name (block capitals) --------------------------------Secretary/Director
Signature ______________________________ _
Name (block capitals) ______________________________ _ _ _ All_t_l!().':i_s_e£1_ ~!g!'.!l!()_ry ___ _
434
Schedule 21 - Collateral Warranties
DATED
(1) [CONSULTANT]
-and-
(2) LEEDS CITY COUNCIL
-and-
(3) [CONSTRUCTION CONTRACTOR]
DUTY OF CARE DEED relating to
the design and construction of residual waste treatment facilities in the City of Leeds
SJ/ADB/73626/120029/UKM/33410506.23
2012
435
Schedule 21 -Collateral Warranties
THIS DEED is made on 2012
BETWEEN
(1) [THE PARTNERS IN [insert name of partnership]J (being the persons listed in the
schedule hereto) whose principal place of business is at [ + ] OR
[[ + LIMITED/PLC] (registered in England and Wales under company
number)[+ ] whose registered office is at [ + ] ("Consultant");
(2) LEEDS CITY COUNCIL of Civic Hall, Leeds, LSI IUR ("City Council"), (which
expression includes its permitted successors in title and assigns); and
(3) [CONSTRUCTION CONTRACTOR] (Compauy No. + ) whose registered
office is at + ("Construction Contractor")
BACKGROUND
A By a project agreement dated [ + 1 ("Project Agreement") the City Council has
appointed [ + 1 (Company No.+ ) ("Contractor") to carry out, in
relation to the waste treatment facilities therein described as the facilities ("Facilities"), the
provision of services relating to the design, installation, operation, and maintenance of
residual waste treatment facilities for the City of Leeds including the carrying out of the
Works aud the provision of the Services.
B The Construction Contractor has been appointed by the Contractor under a contract dated
] ("Construction Contract") to carry out, in relation to the Sites, the design
and construction of the Works.
C The Consultant has been appointed by the Construction Contractor under a [letter/deed] of
appointment dated [ +
Works.
] ("Appointment") to provide services in relation to the
D The Consultant is obliged under the Appointment to give a warranty in this form in favour of
the City Council.
I. DEFINITIONS AND INTERPRETATIONS
Unless expressly defmed otherwise in this Deed, auy defined term in this Deed shall have the
same meaning given to such term in the [Construction Contract/Appointment].
SJ/ ADB/73626/120029/UKM/3341 0506.23 436
Schedule 21 - Collateral Warranties
2. OPERATIVE PROVISIONS
In consideration of the payment of one pound (£1.00) by the City Council to the Consultant,
receipt of which the Consultant acknowledges:
3. CONSULTANT'S WARRANTY AND LIABILITY
3 .I The Consultant warrants to the City Council that it has carried out and will continue to carry
out all its obligations and duties under the Appointment in accordance with and to the
standard required by the Appointment, and that it has exercised and will continue to exercise
in the perfonnance of those duties the reasonable skill care and diligence to be expected of a
properly qualified member of its profession experienced in carrying out duties such as its
duties under the Appointment in relation to works of similar scope, nature and complexity to
the Works.
3.2 The Consultant shall be entitled in any action or proceedings by the City Council to raise
equivalent rights in defence of liability (except for set off or counterclaim) as it would have
against the Construction Contractor under the Appointment and shall have no liability under
this Deed that is of greater or of longer duration than it would have had if the City Council
had been a party to the Appointment as joint employer. Upon the expiry of twelve (12) years
from the date of completion of the Works in accordance with the Construction Contract, the
liability of the Consultant under this Deed shall cease and determine, save in relation to any
claims made by the City Council against the Consultant and notified by the City Council to
the Consultant in writing prior thereto.
4. PROJECT DATA
4.1 The Consultant hereby grants (or, if such grant cannot legally take place until a later date,
agrees to grant) to the City Council with effect from the date of this Deed or in the case of
Project Data not yet in existence with effect from the creation thereof, an irrevocable royalty
free non-exclusive licence (such licence to remain in full force and effect notwithstanding
completion of the Consultant's obligations under the Appointment or the tennination of the
Appointment or the determination of the Consultant's engagement under it or any dispute
thereunder or hereunder) to use and to reproduce all Project Data for any purpose whatsoever
connected with the Works and such other purposes as are reasonably foreseeable including,
but without limitation, the execution, completion, maintenance, letting, advertisement,
modification, extension, reinstatement and repair of the Works. Such licence will carry the
right to grant sub-licences and will be transferable to third parties.
SJ/ AD B/7 3626/120029/UKM/3 341 0 5 06.23 437
Schedule 21 -Collateral Warranties
4.2 The City Council will not hold the Consultant liable for any use it may make of the Project
Data for any purpose other than that for which they were originally provided by it unless the
Consultant authorises such use and confirms that the Project Data are suitable for it.
4.3 The Consultant will not grant to any third party the right to use any of the Project Data save
under any warranty it is obliged to give under the Appointment or hereunder or as otherwise
required to enable it to fulfil its obligations under the Appointment.
4.4 The Consultant agrees on reasonable request at any time following reasonable written prior
notice to give the City Council or those authorised by it access to the Project Data and to
provide copies (including copy negatives and CAD disks) thereof at the City Council's
expense.
4.5 The Consultant warrants to the City Council that he has used the standard of skill, care and
diligence as set out in clause 3.1 to see that the Project Data (save to the extent duly appointed
sub- contractors have been used to prepare the same) are its own original work and that in any
event their use in connection with the Works will not infringe the rights of any third party.
5. INSURANCE
5 .I The Consultant hereby covenants with the City Council to:
5 .1.1 take out and maintain Professional Indemnity insurance cover with a limit of
indemnity that shall be a minimum often million pounds (£10,000,000) for each and
every loss and that it will maintain such insurance with reputable insurers carrying on
business in the European Union from the date hereof until twelve (12) years after
practical completion of the Works, provided that such insurance is generally available
in the market to members of the Consultant's profession at commercially reasonable
rates and provided further that payment of any increased or additional premiums
required by insurers by reason of the Consultant's own claims record or other acts,
omissions, matters or things peculiar to the Consultant will be deemed to be within
the reasonable rates;
5 .1.2 provide evidence (as and when reasonably required by the City Council) satisfactory
to the City Council of the Professional Indenmity insurance referred to in clause 5 .1.1
being in full force and effect from the date of the Appointment (such evidence to
include details of the cover);
SJ/ ADB/73626/120029/UKM/3341 0506.23 438
Schedule 21- Collateral Warranties
5 .1.3 provide the City Council with notice of:
5 .1.3 .1 any cancellation of the Professional Indemnity insurance referred to in
clause 5.1.1 not less than thirty (30) days prior to the relevant cancellation
date; and
5 .1.3 .2 any adverse material changes to or suspension of cover relevant to the Works
not less than thirty (30) days prior to the relevant change or suspension;
5 .1.4 inform the City Council as soon as reasonably practicable of any claim under the
Professional Indenmity insurance referred to in clause 5 .1.1 in respect of the Works in
excess of five hundred thousand pounds (£500,000) and provide such information to
the City Council as the City Council may reasonably require in relation to such claim
and provide notice of any potential breach of the limit of the policy; and
5. 1.5 indemnity the City Council in respect of any subrogation claim by the msurers
brought in connection with any claim made under the Professional h1demnity
insurance referred to in clause 5 .1.1.
6. LIABILITY OF PARTNERS
Where the Consultant is a partnership, references in this Deed to the "Consultant" will be
deemed to include reference to each and every present and future partner of such partnership
and the liability of each and every such partner under this Deed will be deemed to be joint and
several.
7. ASSIGNMENT
The benefit of and the rights of the City Council under this Deed may be assigned without the
consent of the Consultant and the City Council will notifY the Consultant in writing following
any such assignment specifYing the name and address of the assignee and the date of the
assignment. The Consultant will not contend that any such assignee is precluded from
recovering any loss resulting from any breach of this Deed (whatever the date of such breach)
by reason only that that person is an assignee and not the original beneficiary hereunder or by
reason that the original beneficiary or any intermediate beneficiary escaped any loss resulting
from such breach by reason of the disposal of any interest in the Site or that the original
beneficiary or any intermediate beneficiary has not suffered any, or as much, loss
SJ/ AD B/73 626/ 120029/UKM/3 3 41 0 5 06.23 439
Schedule 21 - Collateral Warranties
8. CITY COUNCIL'S REMEDIES
The rights and benefits conferred upon the City Council by this Deed are in addition to any
other rights and remedies it may have against the Consultant including without prejudice to
the generality of the foregoing any remedies in negligence.
9. INSPECTION OF [PROJECT DATA]
The Consultant's liabilities under this Deed will not be in any way reduced or extinguished by
reason of any inspection or approval of the [Project Data] or attendance at site meetings or
other enquiry or inspection which the City Council may make or procure to be made for its
benefit or on its behalf.
10. STANDARDS OF PRODUCTS AND MATERIALS
10.1 The Consultant warrants that it has exercised and will exercise reasonable skill, care and
diligence in accordance with this Deed to see that it has not specified for use and it will not
specifY for use and (as appropriate) it has not authorised or approved and it will not authorise
or approve the specification or use by others, of any products or materials not in conformity
with relevant British or European Union Standards or Codes of Practice or which at the time
of specification are widely known to members of the Consultant's profession within the
European Union to be deleterious to health and safety or to the durability of buildings and/or
other structures and/or finishes and/or plant and machinery in the particular circumstances in
which they are used.
I 0.2 If in the performance of its duties under the Appointment the Consultant becomes aware that
it or any other person has specified or used, or authorised or approved the specification or use
by others of any such products or materials the Consultant will notifY the City Council in
writing forthwith. This clause does not create any additional duty for the Consultant to inspect
or check the work of others which is not required by the Appointment.
II. STEP-IN RIGHTS IN FAVOUR OF THE CITY COUNCIL
11.1 The Consultant will not exercise or seek to exercise any right which may be or becomes
available to it to terminate or treat as terminated or repudiated the Appointment or its
engagement under it or discontinue or suspend the performance of any duties or obligations
thereunder without first giving to the City Council not less than thirty (30) Business Days
prior written notice specifying the Consultant's ground for terminating or treating as
terminated or repudiated the Appointment or its employment under it or discontinuing or
SJ/ ADB/73626/120029/UK.M/3341 0506.23 440
Schedule 21 -Collateral Warranties
suspending its performance thereof and stating the amount (if any) of monies outstanding
under the Appointment. Within such period of notice:
11.1.1 the City Council may give written notice to the Consultant that the City Council will
thenceforth become the Construction Contractor under the Appointment to the
exclusion of the Construction Contractor and thereupon the Consultant will admit that
the City Council is the Construction Contractor under the Appointment and the
Appointment will be and remain in fi1ll force and effect notwithstanding any of the
said grounds;
11.1.2 if the City Council has given such notice as aforesaid or under clause 1111.3, the City
Council shall accept liability for the Construction Contractor's obligations under the
Appointment and will as soon as practicable thereafter remedy any outstanding
breach by the Construction Contractor which properly has been included in the
Consultant's specified grounds and which is capable of remedy by the City Council;
and
11.1.3 if the City Council has given such notice as aforesaid or under clause 11.3, the City
Council shall from the service of such notice become responsible for all sums
properly payable to the Consultant under the Appointment accruing due after the
service of the Consultant's notice but the City Council shall in paying such sums be
entitled to the same rights of set-off and deduction as would have applied to the
Construction Contractor under the Appointment.
11.2 Notwithstanding anything contained in this Deed and notwithstanding any payments which
may be made by the City Council to the Consultant, the City Council will not be under any
obligation to the Consultant nor will the Consultant have any claim or cause of action against
the City Council unless and until the City Council has given written notice to the Consultant
pursuant to clause 11.1.1 or clause 11.3 of this Deed.
11.3 The Consultant further covenants with the City Council that if the Project Agreement is
terminated by the City Council the Consultant, if requested by the City Council by notice in
writing and subject to clause 11.1.2 and clause 11.1.3, will accept the instructions of the City
Council to the exclusion of the Construction Contractor in respect of its duties under the
Appointment upon the terms and conditions of the Appointment and will if so requested in
writing enter into a novation agreement whereby tl1e City Council is substituted for the
Construction Contractor under the Appointment.
SJ/ AD B/73 626/120029/UKM/3341 05 06.23 441
Schedule 21 -Collateral Warranties
11.4 The Contractor acknowledges that the Consultant will be entitled to rely on a notice given to
the Consultant by the City Council under clause 11.3 as conclusive evidence that the Project
Agreement has been terminated by the City Council.
11.5 The City Council may by notice in writing to the Consultant appoint another person to
exercise its rights under this clause 11 subject to the City Council remaining liable to the
Consultant as guarantor for its appointee in respect of its obligations under this Deed.
12. LIMITATION
Without prejudice to the provisions of clause 11.1, the City Council shall not be entitled to
take any action or proceedings against the Consultant pursuant to this Deed unless and until
the Project Agreement has been terminated or has expired.
13. THE CONSTRUCTION CONTRACTOR'S INCLUSION AS PARTY
The Construction Contractor has agreed to be a party to this Deed for the purpose of clause 11
and for acknowledging that the Consultant shall not be in breach of the Appointment by
complying with the obligations imposed on it by this Deed.
14. COUNTERPARTS
This Deed may be executed in one or more counterparts. Any single counterpart or a set of
counterparts executed, in either case, by all the parties shall constitute a full and original
instrument for all purposes.
15. SUB-CONSULTANTS
Fallowing a written request from the City Council the Consultant will (unless it has already
done so) and/or procure that its sub-consultants execute a deed of collateral warranty in the
relevant fonn specified in the Appointment in favour of any person in whose favour the
Appointment obliges the Consultant to give or procure the giving of such a warranty.
16. APPLICABLE LAW AND JURISDICTION
This Deed will be construed in accordance with English law and be in all respects subject to
the exclusive jurisdiction of the English courts.
SJ/ AD B/73626/120029/UKM/3341 0 506.23 442
Schedule 21 -Collateral Warranties
17. THIRDPARTYRIGHTS
This Deed is enforceable by the original parties to it and by their successors in title and
permitted assignees. Any rights of any person to enforce the terms of this Deed pursuant to
the Contracts (Right of Third Parties) Act 1999 are excluded.
18. NOTICES
Any notice to be given by either party will be sufficiently served if sent by hand, by facsimile
transmission or by post to the registered office or ifthere is none the last known address of
the party to be served. Any notice sent by hand will be deemed to be served on the date of
delivery and any notice sent by facsimile transmission will be deemed to be served in full at
the time recorded on the facsimile report sheet, provided that if any notice sent by hand or
facsimile is sent after 4.45 pm on any day it will be deemed to be served on the next Business
Day. Any notice sent by post will be deemed to have been duly served at the expiration of
forty-eight ( 48) hours after the time of posting if the end of that period falls before 4.45pm on
a Business Day and otherwise on the next Business Day.
IN WITNESS whereof this document is executed by the parties as a Deed and delivered on the date
stated at the beginning of this Deed
SJ/ ADB/7362 6/120029/UKM/3341 0 5 06.23 443
Schedule 21 - Collateral Warranties
EXECUTED as a Deed by the [CONSULTANT] acting by a Director and its Secretary/two Directors:
) ) ) )
Director
Director/Secretary
EXECUTED as a Deed by the ) [CONSTRUCTION CONTRACTOR] ) acting by a Director ) and its Secretary/two Directors: )
Director
Director/Secretary
SJ/ADB/73626/120029/UKM/33410506.23 444
The Conunon Seal of LEEDS CITY COUNCIL was affixed in the presence of:
SJ I ADB/7362 6/120029/UKM/3 341 05 06.23
Schedule 21 - Collateral Warranties
) ) )
Authorised Signatory
Authorised Signatory
445
Schedule 21 - Collateral Warranties
DATED
(1) [SUB-CONTRACTOR]
-and-
(2) [LEEDS CITY COUNCIL]
-and-
(3) [CONSTRUCTiON CONTRACTOR]
DUTY OF CARE DEED relating to
the design and construction of residual waste treatment facilities in the City of Leeds
SJ/ AD B/73626/120029 /UKM/3341 0506.23
2012
446
Schedule 21- Collateral Warranties
THIS DEED is made on
BETWEEN
2012
(I) [SUB-CONTRACTOR] (company number + ) whose registered office 1s at
+ ("Sub-Contractor");
(2) LEEDS CITY COUNCIL of Civic Hall, Leeds LSI I UR ("City Council"), (which
expression includes its permitted successors in title and assigns); and
(3) CONSTRUCTION CONTRACTOR (company number+ ) whose registered
office is at + ("Construction Contractor").
BACKGROUND
A By a project agreement dated [+ ] ("Project Agreement") the City
Council has appointed Veolia ES Leeds Limited ("Contractor") to carry out, in relation to
the waste treatment facilities therein described as the Facilities ("Facilities"), the provision of
services relating to the design, installation, operation and maintenance of residual waste
treatment facilities for the City of Leeds including the carrying out of the Works and the
provision of the Services.
B The Construction Contractor has been appointed been appointed by the Contractor under a
contract dated [ + ] ("Construction Contract") to carry out the design,
construction, commissioning and testing of the Works.
C The Sub-Contractor has been appointed by the Construction Contractor under a contract dated
] ("Sub-Contract") to perform certain of the Construction Contractor's
obligations under the Construction Contract, as more particularly defined in the Sub-Contract.
D The Sub-Contractor is obliged under the Sub-Contract to give a warranty in this form in favour
of the City Council.
1. DEFINITIONS AND INTERPRETATIONS
1.1 In this Deed unless the context otherwise requires, the following expressions shall
have the following meanings:
"Project Data" means all drawings, reports, documents, plans, software, formulae,
calculations and other data relating to the design, construction, testing or operation of
the Works in each case tl1at is used by or on behalf of the Sub-Contractor and/or its
SJ/ADB/73626/120029/UKM/33410506.23 447
Schedule 21 - Collateral Warranties
sub-contractors in connection with the provision of the Works or the performance of
the Sub-Contractor's obligations under the Sub-Contract;
1.2 Unless expressly defined otherwise in this Deed, any defined term in this Deed shall
have the same meaning given to such term in the Sub-Contract.
2. OPERATIVE PROVISIONS
In consideration of the payment of one pound (£ 1.00) by the City Council to the Sub
Contractor, receipt of which the Sub-Contractor acknowledges:
3. SUB-CONTRACTOR'S WARRANTY AND LIABILITY
3.1 The Sub-Contractor warrants to the City Council that it has carried out and will continue to
carry out its duties under the Sub-Contract in accordance with the Sub-Contract and that it
has exercised and will continue to exercise, in carrying out the design of the Works, the level
of skill and care reasonably to be expected from an appropriately qualified and competent
professional designer providing those services in relation to a project of a similar size and
scope to the Works. In particular and without limiting the generality of the foregoing the
Sub-Contractor covenants with the City Council that it has carried out and will carry out and
complete the Works in accordance with the Sub-Contract and duly observe and perform all its
duties and obligations thereunder.
3 .2 The Sub-Contractor shall be entitled in any action or proceedings by the City Council to raise
equivalent rights in defence of liability (except for set off or counterclaim) as it would have
against the Construction Contractor under the Sub-Contract, and shall have no liability under
this Deed that is of greater or of longer duration than it would have had if the City Council
had been a party to the Sub-Contract as joint employer. Upon the expiry of twelve (12) years
from the date of completion of the Works in accordance with the Sub-Contract, the liability of
the Sub-Contractor under this Deed shall cease and determine, save in relation to any claims
made by the City Council against the Sub-Contractor and notified by the City Council to the
Sub-Contractor in writing prior thereto.
3.3 The Sub-Contractor shall have no liability to the City Council in respect of any delay in the
completion of the Works howsoever caused save to the extent that the liability arises under
the Sub-Contract and the City Council shall have exercised its right to step in under clause 9.
SJ/ ADB/7 362 6/120029/UKM/3341 0 5 06.23 448
Schedule 21 -Collateral Warranties
4. PROJECT DATA
4.1 The Sub-Contractor hereby grants (or, if such grant cannot legally take place until a later date,
agrees to grant) to the City Council with effect from the date of this Deed or in the case of
Project Data not yet in existence with effect from the creation thereof, a royalty-free non
exclusive licence (such licence to remain in full force and effect notwithstanding completion
of the Sub-Contractor's obligations under the Sub-Contract or the termination of the Sub
Contract or the determination of the Sub-Contractor's engagement under it or any dispute
thereunder or hereunder) to use and to reproduce all Project Data for any purpose whatsoever
connected with the Works and such other purposes as are reasonably foreseeable including,
but without limitation, the execution, completion, maintenance, letting, advertisement,
modification, extension, reinstatement and repair of the Works. Such licence will carry the
right to grant sub-licences and will be transferable to third parties.
4.2 The City Council will not hold the Sub-Contractor liable for any use it may make of the
Project Data for m1y purpose other than that for which they were originally provided by it and
other thm1 for such other uses as are reasonably foreseeable unless the Sub-Contractor
authorises such use and confirms the Project Data are suitable for it.
4.3 The Sub-Contractor will not grant to any third party the right to use any of the Project Data
save under any warranty it is obliged to give under the Sub-Contract or hereunder or as
otherwise required to enable it to fulfil its obligations under the Sub-Contract.
4.4 The Sub-Contractor agrees on reasonable request at any time and following reasonable
written prior notice to give the City Council or those authorised by it access to the Project
Data and to provide copies (including copy negatives and CAD disks) thereof at the City
Council's expense.
4.5 The Sub-Contractor warrants to the City Council that he has used the standard of skill, care
and diligence as set out in clause 3.1 to see that the Project Data (save to the extent duly
appointed sub-contractors have been used to prepare the smne) are its own original work and
that in any event their use in connection with the Works will not infringe the rights of any
third party
SJ/ ADB/73 626/120029/UKM/3 341 0506.23 449
Schedule 21- Collateral Warranties
5. INSURANCE
5 .I The Sub-Contractor hereby covenants with the City Council to:
5 .1.1 take out and maintain Professional Indemnity insurance cover with a limit of
indemnity that shall be a minimum often million pounds (£10,000,000) for each and
every loss and that it will maintain such insurance with reputable insurers carrying on
business in the European Union from the date hereof until twelve (12) years after
practical completion of the Works, provided that such insurance is generally available
in the market to members of the Sub-Contractor's profession at commercially
reasonable rates and provided further that payment of any increased or additional
premiums required by insurers by reason of the Sub-Contractor's own claims record
or other acts, omissions, matters or things peculiar to the Sub-Contractor will be
deemed to be within the reasonable rates;
5.1.2 provide evidence (as and when reasonably required by the City Council) satisfactory
to the City Council of the Professional Indemnity insurance referred to in clause 5 .1.1
being in full force and effect from the date of the Sub-Contract (such evidence to
include details of the cover);
5.1.3 provide the City Council with notice of:
5 .1.3 .I any cancellation of the Professional Indemnity insurance referred to in
clause 5.1.1 not less than thirty (30) days prior to the relevant cancellation
date; and
5 .1.3 .2 any adverse material changes to or suspension of cover relevant to the Works
not less than thirty (30) days prior to the relevant change or suspension;
5.1.4 inform the City Council as soon as reasonably practicable of any claim under the
Professional Indemnity insurance referred to in clause 5 .1.1 in respect of the Works in
excess of five hundred thousand pounds (£500,000) and provide such information to
the City Council as the City Council may reasonably require in relation to such claim
and provide notice of any potential breach of the limit of the policy; and
5.1.5 indemnify the City Council in respect of any subrogation claim by the insurers
brought in connection with any claim made under the Professional Indemnity
insurance referred to in clause 5 .1.1.
SJ I ADB/73 626/120029/UKM/3341 05 06.23 450
Schedule 21 - Collateral Warranties
6. CITY COUNCIL'S REMEDIES
The rights and benefits conferred upon the City Council by this Deed are in addition to any
other rights and remedies it may have against the Sub-Contractor including without prejudice
to the generality of the foregoing any remedies in negligence.
7. ASSIGNMENT
The benefit of and the rights of the City Council under this Deed may be assigned without the
consent of the Sub-Contractor and the City Council will notifY the Sub-Contractor in writing
following any such assignment specifYing the name and address of the assignee and the date
of the assignment. The Sub-Contractor will not contend that any such assignee is precluded
from recovering any loss resulting from any breach of this Deed (whatever the date of such
breach) by reason only that that person is an assignee and not the original beneficiary
hereunder or by reason that the original beneficiary or any intermediate beneficiary escaped
any loss resulting from such breach by reason of the disposal of any interest in the Site or that
the original beneficiary or any intermediate beneficiary has not suffered any, or as much, loss.
8. INSPECTION OF PROJECT DATA
The Sub-Contractor's liabilities under this Deed will not be in any way reduced or
extinguished by reason of any inspection or approval of the Project Data or attendance at site
meetings or other enquiry or inspection which the City Council may make or procure to be
made for its benefit or on its behalf.
9. STEP-IN RIGHTS IN FAVOUR OF THE CITY COUNCIL
9.1 The Sub-Contractor will not exercise or seek to exercise any right which may be or
become available to it to tenninate or treat as terminated or repudiated the Sub
Contract or its engagement under it or discontinue or suspend the performance of any
duties or obligations thereunder without first giving to the City Council not Jess than
thirty (30) days' prior written notice specifYing the Sub-Contractor's ground for
terminating or treating as terminated or repudiated the Sub-Contract or its
engagement under it or discontinuing or suspending its performance thereof and
stating the amount (if any) of monies outstanding under the Sub-Contract. Within
such period of notice:
9.1.1 the City Council may give written notice to the Sub-Contractor that the City
Council will thenceforth become the Construction Contractor under the Sub
Contract to the exclusion of the Construction Contractor and thereupon the
SJ/ ADB/73 626/12002 9 /UKM/3341 0506.23 451
Schedule 21- Collateral Warranties
Sub-Contractor will admit that the City Council is the Construction
Contractor under the Sub-Contract and the Sub-Contract will be and remain
in full force and effect notwithstanding any of the said grounds;
9 .1.2 if the City Council has given such notice as aforesaid or under clause 9 .3, the
City Council shall accept liability for the Construction Contractor's
obligations under the Sub-Contract and will as soon as practicable thereafter
remedy any outstanding breach by the Construction Contractor which
properly has been included in the Sub-Contractor's specified grounds and
which is capable of remedy by the City Council; and
9.1.3 if the City Council has given such notice as aforesaid or under clause 9.3, the
City Council shall from the service of such notice become responsible for all
sums properly payable to the Sub-Contractor under the Sub-Contract
accruing due after the service of such notice but the City Council shall in
paying such sums be entitled to the same rights of set-off and deduction as
would have applied to the Construction Contractor under the Sub-Contract.
9.2 Notwithstanding anything contained in this Deed and notwithstanding any payments which
may be made by the City Council to the Sub-Contractor, the City Council will not be under
any obligation to the Sub-Contractor nor will the Sub-Contractor have any claim or cause of
action against the City Council unless and until the City Council has given written notice to
the Sub-Contractor pursuant to clause 9 .1.1 or clause 9.3.
9.3 The Sub-Contractor further covenants with the City Council that if the Project Agreement is
terminated by the City Council the Sub-Contractor, if requested by the City Council by notice
in writing and subject to clause 9.1.2 and clause 9.1.3, will accept the instructions of the City
Council to the exclusion of the Construction Contractor in respect of its duties under the Sub
Contract upon the tenns and conditions of the Sub-Contract and will if so requested in writing
enter into a novation agreement whereby the City Council is substituted for the Construction
Contractor under the Sub-Contract.
9.4 The Construction Contractor acknowledges that the Sub-Contractor will be entitled to rely on
a notice given to the Sub-Contractor by the City Council under clause 9.3 as conclusive
evidence that the Project Agreement has been terminated by the City Council.
SJ/ ADB/73626/120029/UKM/3341 0506.23 452
Schedule 21 -Collateral Warranties
9.5 The City Couucil may by notice in writing to the Sub-Contractor appoint another person to
exercise its rights under this clause 9 subject to the City Council remaining liable to the Sub
Contractor as guarantor for its appointee in respect of its obligations under this Deed.
9.6 Upon request by the City Council the Sub-Contractor agrees to co-operate with the City
Council in determining the duties performed or to be performed by the Sub-Contractor and to
provide a copy of the Sub-Contract and any variations thereto and details of all monies paid
and due under the Sub-Contract.
10. LIMITATION
Without prejudice to the provisions of clause 9 .I, the City Council shall not be entitled to take
any action or proceedings against the Sub-Contractor pursuant to this Deed unless and until
the Project Agreement has been terminated or has expired.
II. THE CONSTRUCTION CONTRACTOR'S INCLUSION AS PARTY
The Construction Contractor has agreed to be a party to this Deed for the purpose of clause 16
and for acknowledging that the Sub-Contractor shall not be in breach of the Sub-Contract by
complying with the obligations imposed on it by this Deed.
12. COUNTERPARTS
This Deed may be executed in one or more counterparts. Any single counterpart or a set of
counterparts executed, in either case, by all the parties shall constitute a full and original
instrument for all purposes.
13. SUB-CONTRACTORS
Following a written request from the City Council the Sub-Contractor will (uuless it has
already done so) and/ or procure that its sub-contractors execute a deed of collateral warranty
in tl1e relevant form specified in the Sub-Contract in favour of any person in whose favour tl1e
Sub-Contract obliges the Sub-Contractor to give or procure the giving of such a warranty.
14. APPLICABLE LAW AND JURISDICTION
This Deed will be construed in accordance with English law and be in all respects subject to
the exclusive jurisdiction of the English courts.
SJ/ADB/73626/120029/UKM/33410506.23 453
Schedule 21 -Collateral Warranties
15. THIRDPARTYRIGHTS
This Deed is enforceable by the original parties to it and by their successors in title and
permitted assignees. Any rights of any person to enforce the terms of this Deed pursuant to
the Contracts (Rights of Third Parties) Act 1999 are excluded.
16. NOTICES
Any notice to be given by any party will be sufficiently served if sent by hand, by facsimile
transmission or by post to the registered office or if there is none the last known address of
the party to be served. Any notice sent by hand will be deemed to be served on the date of
delivery and any notice sent by facsimile transmission will be deemed to be served in full at
the time recorded on the facsimile report sheet, provided that if any notice sent by hand or
facsimile is sent after 4.45pm on any day it will be deemed to be served on the next Business
Day. Any notice sent by post will be deemed to have been duly served at the expiration of
forty-eight (48) hours after the time of posting if the end of that period falls before 4.45pm on
a Business Day and othervvise on the next Business Day.
IN WITNESS of which this docUillent is executed as a Deed and is delivered on the date first before
written
Executed as a deed by the SUB- ) CONTRACTOR acting by a director and its ) secretary /two directors: ) Signature
Name (block capitals)
Signature
Name (block capitals)
SJ/ADB/73626/120029/UKM/33410506.23
Director
Secretaryillirector
454
Schedule 21 - Collateral Warranties
Executed as a deed by the CONSTRUCTION ) CONTRACTOR acting by a director and its ) secretary/two directors: ) Signature
Name (block capitals)
Signature
Name (block capitals)
SJ I AD B/736261120029/U KM/3341 0506.23
Director
Secretary/Director
455
The Common Seal of LEEDS CITY COUNCIL was affixed in the presence of:
SJ/ ADB/73 626/120029 /UKM/3 341 0506.23
) )
Schedule 21 - Collateral Warranties
Signature . _______________________ _
Name (block capitals) ·------------------------------
456
Schedule 21 -Collateral Warranties
DATED 2012
(1) [PROCESS SUB-CONTRACTOR]
-and-
(2) LEEDS CITY COUNCIL
-and-
(3) VEOLIA ES LEEDS LIMITED
-and-
(4) CONSTRUCTIONS INDUSTRIELLES DE LA MEDITERRANEE S.A.
AGREEMENT relating to
the design and construction of residual waste treatment facilities in the Ci1y of Leeds
SJ/ADB/73626/120029/UKM/33410506.23 457
Schedule 21- Collateral Warranties
TIDS DEED is made on 2012
BETWEEN
(1) [PROCESS SUB-CONTRACTOR] (Company No.[ ]) whose registered office is at
[ ] ("the Sub-Contractor");
(2) LEEDS CITY COUNCIL of Civic Hall, Leeds LS 1 IUR, (which expression includes its
permitted successors in title and assigns) (the "BENEFICIARY COUNCIL");
(3) VEOLIA ES LEEDS LIMITED (company number 07876913) whose registered office is at
8th Floor, 210 Pentonville Road, London, United Kingdom, Nl 9JY (the "BENEFICIARY
PURCHASER"); and
(4) CONSTRUCTIONS INDUSTRIELLES DE LA MEDITERRANEE S.A. a societe
anonyme incorporated under the laws of France whose principal office is at 35 Rue de
Bassano, 75008, Paris, France ("CNIM") (the "Process Contractor").
BACKGROUND
A In accordance with the Government's Private Finance Initiative and pursuant to a notice
published in the Official Journal of the European Union on [ + ] the
Beneficiary Council invited expressions of interest from appropriately qualified consortia for
waste management services (the "Project") including the design, installation, operation, and
maintenance of residual waste management facilities (comprising a treatment and energy
from waste facility and all supporting infrastructure including associated plant and amenities)
("the Facility") (as more particularly defined in the Construction Contract as hereafter
B
defined) at the [ + ] (the "Site").
By an agreement dated [ + ] (the "Project Agreement") the Beneficiary
Council has appointed the Beneficiary Purchaser for the carrying out of the Project in relation
to the Site including the design, construction, installation, testing, commissioning and
completion and management, operation and maintenance of the Facility . The Project
Agreement is entered into under the Government's Private Finance Initiative.
C By an agreement dated [ + ] (the "Construction Contract") the
Beneficiary Purchaser has appointed CNIM Clugston (Leeds) Limited (the "Construction
Contractor") to carry out the design, construction, installation, testing, commissioning and
SJ/ADB/73626/120029/UKM/33410506.23 458
Schedule 21 - Collateral Warranties
completion of the Facility including all related works and as all more particularly described
and defined in the Construction Contract (the "Construction Works").
D By an agreement of even date ("the Process Contract") the Construction Contractor has
appointed the Process Contractor to carry out that part of the Construction Works which
relates to process plant works ("the Process Works") all as more particularly described in the
Process Contract.
E The Process Contractor has entered into an agreement with the Sub-Contractor dated [
+ ] (the "Sub-Contract") whereby the Sub-Contractor agrees to design
[and install] the [turbine ]/[boiler ]/[grate] and obligations and duties all as more particularly
described under the Sub-Contract (the "Sub-Contract Works"). Under the Sub-Contract the
Sub-Contractor is required to execute and deliver a warranty in this form in favour of the
Beneficiary Council and Beneficiary Purchaser in respect of the Sub-Contract Works (and all
obligations of the Sub-Contractor under the Sub-Contract).
OPERATIVE PROVISIONS
I. CONSIDERATION AND INTERPRETATION
1.1 This Agreement is made in consideration of the payment of one pound (£1.00) by the
each of the Beneficiary Council and Beneficiary Purchaser to the Sub-Contractor
receipt of which the Sub-Contractor acknowledges.
1.2 h1 this agreement the terms "Beneficiary" shall mean either the Beneficiary Council
or the Beneficiary Purchaser and "Beneficiaries" shall mean both of them.
2. SUB-CONTRACTOR'S WARRANTIES
The Sub-Contractor warrants to the Beneficiaries that it has carried out and will continue to
carry out and complete the Sub-Contract Works and all its obligations under the Sub-Contract
in accordance with the Sub-Contract.
3. INTELLECTUAL PROPERTY RIGHTS
3.1 Subject to the following provisions of this Agreement, all Intellectual Property in the
drawings, designs, charts, specifications, plans, software and any other documents or
materials in any medium which have been created and/or developed by the Sub
Contractor in the course of performing any of its Services or obligations under the
SJ/ADB/73626/120029/UKM/33410506.23 459
Schedule 21 -Collateral Warranties
Sub-Contract (the "Documents") will remain vested in the Sub-Contractor. For the
purposes of this clause 3, "Intellectual Property" shall mean all copyright and all
database rights and moral rights, registered designs, registered and unregistered
design rights, or any rights or property similar to the foregoing in any part of the
world whether registered or unregistered, together with the right to apply for the
registration of such rights in any part of the world and the rights to current
applications for registration of any such intellectual property referred to above.
3.2 The Sub-Contractor grants (or, if such a grant cannot legally take place until a later
date, agrees to grant) to the Beneficiary Council and Beneficiary Purchaser, with
effect from the date of this Agreement or in the case of any of the Intellectual
Property not yet in existence with effect from the creation of such Intellectual
Property, an irrevocable, royalty-free, non-exclusive licence (such licence to remain
in full force and effect notwithstanding the completion of the Sub-Contractor's
obligations under the Sub-Contract or the termination of the Sub-Contract or this
Agreement or the determination of the Sub-Contractor's employment under the Sub
Contract or any dispute under the Sub-Contract or this Agreement) to use and to
reproduce all Documents for the operation and maintenance of the Project. Such
licence will enable the Beneficiary Council and Beneficiary Purchaser to use and
reproduce the Documents for any extension of the Project, but shall not include a
licence to replicate any design in the Documents. Such licence shall be transferable
to any third party subject to prior approval by the Sub-Contractor (not to be
unreasonably withheld or delayed) to whom the rights under this clause are
transferred.
3.3 The Sub-Contractor will not grant to any third party the right to use any of the
Documents save under any warranty it is obliged to give under the Sub-Contract or
under this Agreement or as otherwise required to enable it to fulfil its obligations
under the Sub-Contract and then only provided that the Documents are used strictly
for the purpose for which they were prepared.
3.4 The Sub-Contractor will not be liable for any use the Beneficiaries may make of the
Documents for any purpose other than the purposes set out in clause 3 .2.
3.5 The Sub-Contractor warrants that the Documents (except to the extent that duly
authorised sub-contractors or sub-consultants have been used to prepare the same) are
SJ/ ADB/73 626/120029/UKM/3341 0 5 06.23 460
Schedule 21 - Collateral Warranties
the Sub-Contractor's own work and that in any event their use in connection with the
Construction Works will not infringe the rights of any third party.
3 .6 The Sub-Contractor shall include provision in any contracts with its sub-contractors
and/or sub-consultants so as to give full effect to and ensure compliance with the Sub
Contractor's obligations under clause 3 .2.
3.7 Not used.
4. INSURANCE
4.1 The Sub-Contractor by this Agreement covenants with the Beneficiaries that it has
European Union product liability insurance with reputable insurers carrying on
business in the European Union with a limit of indemnity of not less than GBP
5,000,000 (Five Million pounds) for any one occurrence or series of occurrences
arising out of any one event and in the aggregate in relation to the Sub-Contract
Works and otherwise performance of the Sub-Contract provided always that:
4.1 .1 such insurance shall be in place from the commencement of the Sub-Contract
Works until no less than end of the Sub-Contractor's liability under the Sub
Contract between the Process Sub-Contractor and the Sub-contractor
4.1.2 the insurance premiums in respect of the insurance shall at all times be the
responsibility of the Sub-Contractor;
4.1.3 if such insurance is not available to the Sub-Contractor (and/or design and
engineering consultants engaged in projects of a similar scope, size, nature
and complexity as the Sub-Contractor in respect of the Project) at
commercially reasonable rates and terms (excluding any mcrease m
premiums attributable to the actions, omissions, errors or defaults of the Sub
Contractor), the Sub-Contractor and the Beneficiary Council and Beneficiary
Purchaser will meet and the Sub-Contractor will outline the steps he intends
to take to manage such risks. lfthe steps proposed by the Sub-Contractor are
not reasonably acceptable to the Beneficiary Council and Beneficiary
Purchaser, the parties shall agree an alternative method of managing such
risk.
4.2 The Sub-Contractor will provide each of the Beneficiary Council and Beneficiary
Purchaser within fourteen (14) days of either the Beneficiary Council or Beneficiary
SJ/ ADB/73626/120029/UKM/3341 0506.23 461
Schedule 21 -Collateral Warranties
Purchaser's written request with certificates of insurance or written confirmation from
an independent company of insurance brokers (including a full list of the material
limits and exclusions) by way of evidence that the policies referred to in this
clause 4.2 (Insurance) are in full force and effect.
5. NOTICES
Any notice to be given by either party under this Agreement will be sufficiently served if sent
by hand, by facsimile transmission or by post to the registered office or if there is none the
last known address of the party to be served with copy to each of the Beneficiaries. Any
notice sent by hand will be deemed to be served on the date of delivery and any notice sent by
facsimile transmission will be deemed to be served in full at the time recorded on the
facsimile report sheet provided that if any notice sent by hand or facsimile is sent after
4.45p.m. on any day it will be deemed to be served on the next working day. Any notice sent
by post will be deemed to have been duly served at the expiration of forty-eight ( 48) hours
after the time of posting if the end oftl1at period falls before 4.45p.m. on a working day and
otherwise on the next working day.
6. ASSIGNMENT
The benefit of and the rights on the part of either the Beneficiary Council or the Beneficiary
Purchaser under this Agreement may be assigned without the consent of the Sub-Contractor
on two occasions only. The relevant Beneficiary will give the Sub-Contractor written notice
following any such assignment specifying the name and address of the assignee and the date
of the assignment. Further assignments shall require the Sub-Contractor's consent. The Sub
Contractor will not contend that any such assignee is precluded from recovering any loss
resulting from any breach of this Agreement (whatever the date of such breach) by reason
only that that person is an assignee and not the original beneficiary under this Agreement or
by reason that the original beneficiary or any intermediate beneficiary escaped any loss
resulting from such breach by reason of the disposal of any interest in the Site or that the
original beneficiary or any intermediate beneficiary has not suffered any or as mnch loss. The
Sub-Contractor shall not unreasonably withhold or delay consent to any assigmnent requested
by a Beneficiary. The Sub-Contractor will not assign the benefits of this Agreement without
the consent of both Beneficiaries.
SJ I AD B/73626/120029/UKM/3341 05 06.23 462
Schedule 21 -Collateral Warranties
7. NOAPPROVAL
The Sub-Contractor's liabilities under this Agreement will not be in any way reduced or
extinguished by reason of any inspection or approval of the Documents or attendance at site
meetings or other enquiry or inspection which the either of the Beneficiaries may make or
procure to be made for the Beneficiaries' benefit or on their behalf.
8. PROHIBITED MATERIALS
8.1 The Sub-Contractor warrants that, to the extent it either is obliged under the Sub
Contract to specifY or approve products or materials for use in the Construction
Works or does so specifY or approve, it has exercised and will exercise reasonable
skill and care in accordance with this Agreement not to specifY, approve or use any
products or materials which are generally known within the construction industry to
be deleterious in the particular circumstances in which they are used, or those
identified as potentially hazardous in or not in conformity with:
8.1.1 the report entitled "Good Practice in the Selection of Construction Materials"
(1997, by Tony Sheehan, Ove Arup & Partners, published by the British
Council for Offices and the British Property Federation) other than the
recommendations for good practice contained in Section 2 of that report;
8.1.2 relevant British or European Standards or Codes of Practice.
8.2 If in the performance of any of its duties under the Sub-Contract, the Sub-Contractor
becomes aware that it or any other person has specified or used, or authorised or
approved the specification or use by others, of any such products or materials the
Sub-Contractor will immediately give both Beneficiaries written notice of the same.
This clause 8.2 does not create any additional duty for the Sub-Contractor (under this
Agreement) to inspect or check the work of others which is not required by the Sub
Contract.
9. STEP-IN RIGHTS
9.1 The Sub-Contractor will not exercise or seek to exercise any right which may be or
become available to it to terminate or treat as terminated or repudiated the Sub
Contract or its employment under it or discontinue or suspend the performance of any
duties or obligations under the Sub-Contract without first giving to the each of the
Beneficiaries not less than twenty-one (21) days' prior written notice (provided that
SJ/ ADB/73626/120029/UKM/3341 0506.23 463
Schedule 21 -Collateral Warranties
when there has been a suspension under the Sub-Contract pursuant to Part II of the
Housing Grants Construction & Regeneration Act 1996 or equivalent Legislation
such period shall be seven (7) days prior written notice) specifYing the Sub
Contractor's grounds for terminating or treating as terminated or repudiated the Sub
Contract or its employment under it or discontinuing or suspending its performance of
the Sub-Contract and stating the amount (if any) of monies outstanding under the
Sub-Contract. Within such period of notice:
9 .I. I either Beneficiary may give written notice to the Sub-Contractor that the
relevant Beneficiary shall become the client under the Sub-Contract to the
exclusion of the Process Contractor and, upon giving such notice, that will be
the case and the Sub-Contract will be and remain in full force and effect
notwithstanding any of the grounds in the Sub-Contractor's notice under
clause 9 .I; and
9 .1.2 if either Beneficiary has g1ven such notice under clause 9 .I. I or under
clause 9.3, the will then as soon as practicable remedy any outstanding breach
by the Process Contractor (provided that where the notice is given under
clause 9 .I. I rather than under clause 9.3 such breach has properly been
included in the Sub-Contractor's specified grounds under clause 9.1); and
9.1.3 if:
9 .1.3 .I either Beneficiary has given such notice under clause 9 .1.1 then from
the date of the Sub-Contractor's notice; or
9 .1.3 .2 either Beneficiary has given notice under clause 9.3 then from the
date of the Beneficiary Council or Beneficiary Purchaser (as
appropriate) notice ,
that Beneficiary will, by clause 9 .1.1, become responsible for all sums
properly payable to the Sub-Contractor under the Sub-Contract and for the
observance and performance of all of the other duties and obligations on the
part of the Process Contractor to be observed and performed under the Sub
Contract accruing due after the service of such Sub-Contractor's notice or the
relevant Beneficiary's notice (as applicable) but the relevant Beneficiary will
in paying such sums be entitled to the same rights as would have applied to
the Process Contractor under the Sub-Contract.
SJ/ADB/73626/120029/UKM/33410506.23 464
Schedule 21 -Collateral Warranties
9.2 Notwithstanding anything contained in this Agreement and notwithstanding any
payments which may be made by the Beneficiaries to the Sub-Contractor, neither
Beneficiary will be under any obligation to the Sub-Contractor nor will the Sub
Contractor have any claim or cause of action against either Beneficiary unless and
until that Beneficiary has given written notice to the Sub-Contractor under either
clause 9 .1.1 or clause 9.3.
9.3 Provided that the Sub-Contract has not previously been terminated the Sub
Contractor further covenants with tbe Beneficiaries that, if the employment of the
Construction Contractor under the Construction Contract is determined or if the
Construction Contract is tenninated, the Sub-Contractor, if requested by a Beneficiary
by written notice and subject to clause 9.1.2 and clause 9.1.3, will accept the
instructions of that Beneficiary to the exclusion of the Process Contractor in respect
of the Sub-Contract Works upon the terms and conditions of tbe Sub-Contract. The
relevant Beneficiary shall then become the client under the Sub-Contract to the
exclusion of the Process Contractor and the Sub-Contractor will, if so requested, enter
into a novation agreement in order to substitute the relevant Beneficiary for the
Process Contractor under the Sub-Contract.
9.4 Where the Sub-Contractor has given rights in relation to the Sub-Contract similar to
those contained in this clause 9 (Step-In Rights) to any other person then if the
Construction Contractor or either Beneficiary serve notice under clause 9 .I. I or
clause 9.3 or its equivalent the notice served by the relevant Beneficiary shall prevail,
and as between notices served by the Beneficiaries, the notice by the Beneficiary
Council shall prevail.
9.5 The Process Contractor acknowledges that the Sub-Contractor will be entitled to rely
on a notice given to the Sub-Contractor by the Construction Contractor under
clause 9.3 as conclusive evidence that the Construction Contractor is entitled to serve
such notice.
9.6 Either Beneficiary may by written notice to the Sub-Contractor appoint another
person to exercise its rights under this clause 9 (Step-In Rights) subject to tl1e relevant
Beneficiary remaining liable to the Sub-Contractor as guarantor for its appointee in
respect of its obligations under this Agreement.
SJ/ ADB/73626/J 20029/UKM/334 l 0506.23 465
Schedule 21 - Collateral Warranties
10. GOVERNING LAW AND JURISDICTION
This Agreement and any non-contractual obligations arising out of or in connection with it
will be construed and governed in accordance with English law and be in all respects subject
to the exclusive jurisdiction of the English courts.
11. THIRDPARTYRIGHTS
The parties to this Agreement do not intend that any of its terms will be enforceable by virtue
of the Contracts (Rights of Third Parties) Act 1999 by any person not a party to it.
\2. EFFECT AND LIMITATION OF LIABILITY
12.1 The Sub-Contractor has no liability under this Agreement which is greater or of
longer duration than the Sub-Contractor would have had if the Beneficiaries had been
a party to the Sub-Contract as joint employers with the Process Contractor.
12.2 The Sub-Contractor shall be entitled in any action or proceedings brought by the
either Beneficiary under this Agreement to rely on any limitation in the Sub-Contract
and to raise equivalent rights in defence of liability as it would have against the
Process Contractor under the Sub-Contract (and vice versa).
12.3 Subject to Clause 9 (Step-In Rights) the Beneficiaries shall only be entitled to make
claims against the Sub-Contractor under this Agreement if:
12.3.1 the Sub-Contract has been terminated and:
12.3 .1.1 in respect of the Beneficiary Council the Construction Contract and
the Project Agreement have terminated; or
12.3.1.2in respect of the Beneficiary Purchaser the Construction Contract has
terminated; or
12.3.2 the Process Contractor became insolvent except where business continues to
operate under administration or otherwise and:
12.3.2.lin respect of the Beneficiary Council the Construction Contract and
the Project Agreement have terminated; or
SJ/ ADB/73 62 6/120029 /UKM/3341 05 06.23 466
Schedule 21 -Collateral Warranties
12.3.2.2in respect of the Beneficiary Purchaser the Construction Contract has
terminated.
12.4 No action or proceedings for any breach of this Agreement shall be commenced
against the Sub-Contractor after the expiry of six ( 6) years from Acceptance under the
Sub-Contract.
THIS DOCUMENT is executed on the date stated at the beginning.
The Common Seal of LEEDS CITY COUNCIL was affixed in the presence of:
) ) Signature ·- ____________________________ _
Name (block capitals) ______________________________ _
Executed as a deed by CONSTRUCTIONS ) INDUSTRIELLES DE LA ) MEDITERRANEE S.A acting by a director ) and its secretary/two directors: Signature
Executed as a deed by VEOLIA ES LEEDS ) LIMITED acting by a director and its )
Name (block capitals)
Signature
Name (block capitals)
secretary/two directors: ) Signature
Name (block capitals)
Signature
Name (block capitals)
SJ/ADB/73626/120029/UK.M/33410506.23
_ _ ~u_t_hl)_ri~-~~- ~!g!'.~!f)_ry ___ _
Director
Secretaryillirector
Director
Secretaryillirector
467
Schedule 21 -Collateral Warrauties
Executed as a deed by [PROCESS ) SUBCONTRACTOR] acting by a director ) audits secretary/two directors: ) Signature
Name (block capitals)
Signature
Name (block capitals)
SJ/ ADB/73626/120029/UKM/3341 0506.23
Director
Secretaryillirector
468
Schedule 22 - Planning
SCHEDULE22
1.
1.1
1.1.1
1.1.1.1
1.1.1.2
1.1.2
1.1.3
1.1.3 .I
1.1.3 .2
1.1.4
SJ/ ADB/73626/120029/UKM/3341 0506.23 469
Schedule 22 - Planning
1.1.5
1.1.5 .1
1.1.5.2
SJ/ ADB/73626/120029/UKM/3341 0506.23 470
Schedule 22 - Planning
1.1.6
1.2
1.2.1
1.2.1.1
1.2.1.2
1.2.1.3
1.2.2
1.2.3
SJ/ADB/73626/120029/UKM/33410506.23 471
Schedule 22 - Planning
1.2.4
1.3
1.3.1
1.3 .2
1.4
1.4.1
1.4.1.1
1.4.1.2
SJ/ADB/73626/120029/UKM/33410506.23 472
Schedule 22 - Planning
1.4.1.3
1.4.2
I .4.3
1.4.4
1.4 .4.1
1.4.4.2
SJ/ADB/73626/120029/UKM/33410506.23 473
Schedule 22 -Planning
1.4.5
1.4.5.1
1.4.5.2 ,
.
1.4.6
1.5
1.5.1
1.5.2
1.5.3
SJ/ ADB/73626/120029/UKM/3341 0506.23 474
Schedule 22 - Planning
1.5.3.1
1.5.3.2
(a)
(b)
1.5.4
SJ/ ADB/7 3626/120029/UKM/3341 0506.23 475
Schedule 22 - Planning
1.6
1.6.1
1.6.2
1. 7
1.7.1
SJ/ ADB/73626/120029/U KM/3341 0506.23 476
Schedule 22 - Planning
1.7.1.1
I. 7 .1.2
I. 7 .1.3
1. 7 .1.4
I. 7.2
1.8
1.9
SJ/ADB/73626/120029/UKM/33410506.23 477
Schedule 22 - Planning
2.
2.1
2.1.1
2.1.1.1
2.1.1.2
(a)
(b)
(c)
2.1.2
SJ I AD B/73 6261120029/UKM/3341 0506. 23 478
Schedule 22 - Planning
2.1.3
2.1.3.1
2.1.3.2
(a)
(b)
2.1.4
2.1.5
2.1.6
SJ/ADB/73626/120029/UKM/33410506.23 479
Schedule 22 - Planning
2.1.7
2.1.8
2.1.8.1
SJ/ADB/73626/120029/UKM/33410506.23 480
Schedule 22 - Pla1ming
2.1.8.2
2.1.9
2.1.9.1
2.1.9 .2
2.1.1 0
2.2
2.2.1
SJ/ADB/73626/120029/UKM/33410506.23 481
Schedule 22 - Planning
2.2.2
2.2.3
2.2.4
2.2.5
2.2.6
2.2.7
2.3
2.3.1
2.3.2
SJ I AD B/73626/ 120029/UKM/33 41 0506.23 482
Schedule 22 - Plauning
2.3.3
2.3 .3 .I
2.3.3.2
2.3 .3 .3
2.3 .3 .4
2.3.3.5
2.3.3.6
2.3 .3. 7
2.3.3.8
2.3 .3 .9
2.3 .3. I 0
SJ/ADB/73626/120029/UKM/33410506.23 483
Schedule 22 - Planning
2.3.3.11
2.3.3.12
2.3.3.13
2.3.3.14
2.3.3.15
2.3.3.16
2.3.3.17
2.3.3.18
2.3.3.19
2.3 .4
2.3.4.1
2.3.4.2
SJ/ADB/73626/120029/UKM/33410506.23 484
Schedule 22 - Planning
2.3 .4.3
2.3.5
2.3.5.1
2.3.5.2
2.3.6
2.3.7
2.3.7.1
SJ/ADB/73626/120029/UKM/33410506.23 485
Schedule 22 - Planning
2.3.7.2
2.4
2.5
2.5.1
2.5.2
(a)
SJ/ AD B/73 626/120029/UKM/3 341 0506.23 486
Schedule 22- Planning
(i)
(ii)
(b)
f
2.6
2.6.1
2.6.1.1
2.6.1.2
SJ/ ADB/73626/120029/UKM/3341 0506.23 487
Schedule 22 - Planning
2.6.2
2.6.3
2.6.3.1
2.6.3 .2
(a)
(b)
(c)
2.6.4
2.6.4.1
SJ/ADB/73626/120029/UKM/33410506.23 488
Schedule 22 - Planning
2.6.4.2
2.6.5
2.6.6
2.6.7
2.6.8
2.6.8.1
SJ/ ADB/7 3 626/120029 /UKM/3341 0 5 06. 23 489
Schedule 22 - Planning
2.6.8.2
2.6.8.3
2.6.9
2.6.1 0
.
SJ/ AD B/73626/120029/UKM/3341 0 5 06 .23 490
Schedule 22 - Planning
2.6.11
2.7
2.7.1
2.7.2
2.8
SJ/ ADB/73626/1 20029/UKM/3341 0506.23 491
Schedule 22 - Planning
2.9
2.9.1
2.9.1.1
(a)
(b)
(c)
2.9.1.2
SJ/ ADB/73626/120029/UKM/3 3 41 0506.23 492
Schedule 22 -Planning
2.9.2
2.9.3
2.9.4
2.9 .4.1
2.9.4.2
SJ/ADB/73626/120029/UKM/33410506.23 493
Schedule 22 - Planning
2.9.4.3
2.9.4.4
2.9.4.5
2.9.5
2.9.5.1
2.9.5.2
(a)
SJ/ADB/73626/120029/UKM/33410506.23 494
Schedule 22 - Planning
(b)
2.9.5.3
(a)
(b)
(c)
(d)
2.9.5.4
2.9.6
SJ/ ADB/73626/120029/UKM/3341 0506.23 495
Schedule 22 -Planning
2.9.6.1
2.9.6.2
2.9.6.3
2.9. 7
2.9. 7 .I
2.9.7.2
SJ/ ADB/73626/120029/UKM/3341 0506.23 496
Schedule 22 - Planning
2.9.7.3
2.9.7.4
2.9.8
2.10
2.1 0.1
SJ/ ADB/73626/120029/UKM/3341 0506.23 497
Schedule 22 - Planning
2.10.2
2.10.3
2.10.3.1
2.10.3.2
2.10.3.3
2.10.4
2.10.4.1
2.1 0.4.2
SJ/ADB/73626/120029/UKM/33410506.23 498
Schedule 22 - Planning
2.10.4.3
(a)
(b)
2.1 0.5
2.10.6
3.
3.1
3.2
3.2.1
SJ/ ADB/73626/120029/UKM/3341 0506.23 499
Schedule 22- Planning
3 .2.2
3 .2.3
3.2.4
3.2.4.1
3.2.4.2
3.2.5
SJ/ADB/73626/120029/UKM/33410506.23 500
Schedule 22 - Planning
3.3
3.3.1
3.3.!.1
3.3.!.2
3.3 .2
3.3 .2.1
3.3 .2.2
SJ/ADB/73626/120029/UKM/33410506.23 501
Schedule 22 - Planning
3.4
3 .4.1
3 .4.1.1
3.4.1.2
3 .4.1.3
3.4.1.4
3 .4.2
3.5
3.6
3.6.1
SJ/ADB/73626/120029/UKM/33410506.23 502
Schedule 22 - Planning
3.6.2
SJ/ ADB/73626/J 20029/UKM/334 J 0506.23 503
Schedule 23 -Design Proposals
SCHEDULE23
Basic Design Proposals
The design proposals identified in schedule 3 (Contractors Proposals) under each of the
following headings and sub-headings, including all attachments referenced therein:
Technical Design
CP2.1 Technology Capacity and Flexibility
CP2.2 Facility Process Information
CP2.2.1 Waste Reception
CP2.2.2 Mechanical Pre-Treatment
CP2.2.3 Thermal Treatment Technology Process
CP2.2.4 Energy Export Connections
CP2.2.5 Statutory Undertakers
CP2.3 BREEAM and CEEQUAL
CP2.5.1 Design Drawings including the Planning Drawings and process plant drawings
CP.2.5.2 Materials and Specifications
CP 2. 7 City Council Accommodation
SJ/ADB/73626/120029/UKM/33410506.23 504
Schedule 24 - Waste Delivery Protocol
SCHEDULE24
Waste Delivery Protocol
1.
2.
2.1
2.1.1
SJ/ADB/73626/120029/UKM/33410506.23 505
Schedule 24- Waste Delivery Protocol
S.l/ A OR/i~ ri26i120029/l JKM/3341 0506.23 506
Schedule 24- Waste Delivery Protocol
2.1.2
2.1.3
2.1.3.1
2.1.3.2
2.1.3 .3
2.1.3 .4
2.1.3 .5
2.1.3 .6
2.1.3.7
2.1.3.8
2.1.3.9
2.1.3.10
2.1.3.11
2.1.4
SJ/ AD B/73 626/12002 9/UKM/3 341 05 06.23 507
Schedule 24 - Waste Delivery Protocol
2.1.5
2.1.6
2.1. 7
2.1.8
2.1.9
2.1.9.1
SJ/ AD 8/73 626/120029/UKM/3341 05 06.23 508
Schedule 24- Waste Delivery Protocol
2.1.9.2
2.1.9.3
2.1.10
2.1.11
2.1.12
2.1.13
2.1.14
SJ/ADB/73626/120029/UKM/33410506.23 509
Schedule 24- Waste Delivery Protocol
2.2
2.2.1
2.2.2
2.2.2.1
2.2.2.2
2.2.2.3
.
2.2.3
SJ/ ADB/73626/120029/UKM/3341 0506.23 510
Schedule 24 - Waste Delivery Protocol
2.2.4
2.2.5
2.3
2.3.1
2.3.2
2.3.3
2.4
2.4.1
2.4.2
SJ/ADB/73626/120029/UKM/33410506.23 511
Schedule 24 - Waste Delivery Protocol
2.4.3
2.4.4
3.
3.1
3.1.1
3.1.2
3.2
SJ I AD B/73626/120029 /UKM/3 341 05 06.23 512
Schedule 24 - Waste Delivery Protocol
3.3
3.4
3.5
3.6
SJ/ADB/73626/120029/UKM/33410506.23 513
Schedule 24 - Waste Delivery Protocol
3. 7
3.7.1
3.7.2
3.7.2.1
3.7.2.2
3.8
SJ/ AD 8/73626/120029/U KM/3 341 0506.23
514
Schedule 24 - Waste Delivery Protocol
3.9
4.
4.1
4.2
4.3
SJ/ ADB/7 3 626/120029/UKM/3 341 0506.23
515
Schedule 24 - Waste Delivery Protocol
.
5.
5 .I
5.2
5.2.1
5.2.2
5.3
5.3 .I
5.3.2
5.3.3
5.4
SJ/ADB/73626/120029/UKM/33410506.23 516
Schedule 24 - Waste Delivery Protocol
5.5
5.6
5.6.1
5.6.2
5.7
5.8
5.9
5.9.1
5.9.1.1
5.9 .1.2
5.9 .1.3
SJ I ADB/73626/120029/UKM/3 341 05 06.23 517
Schedule 24- Waste Delivery Protocol
5.9.2
5.9.3
5.9.3.1
5.9.3.2
5.9.4
5.9.5
5.9.5.1
SJ/ ADB/73626/120029/UKM/3341 0506.23 518
Schedule 24 - Waste Delivery Protocol
(a)
(b)
5.9.6
5.10
5.10.1
SJ/ AD B/73 626/120029/UKM/3341 0506.23 519
Schedule 24 - Waste Delivery Protocol
5.10.2
5.10.2.1
5.10.2.2
5.10.3
5.10.4
5 .II
5.11.1
5.11.1.1
5.11.1.2
5 .11.1.3
5 .11.1.4
5.11.1.5
SJ I ADB/736261 120029/UKM/3341 05 06 .23 520
Schedule 24- Waste Delivery Protocol
5.11.1.6
5.11.1.7
5.11.2
6.
6.1
6.2
6.3
7.
7 .I
SJ/ADB/73626/120029/UKM/33410506.23 521
Schedule 24 -Waste Delivery Protocol
7.2
7.2.1
7.2.2
7.3
7.4
7.5
8.
8.1
8.1.1
8.1.2
SJ/ ADB/73 62 6/120029/UKM/3 3 41 0 506.23 522
Schedule 24 - Waste Delivery Protocol
--------------
8.1.3
SJ/ AD B/73 626/120029/UKM/3341 05 06.23 523
Schedule 24 - Waste Delivery Protocol
8.2
8.2.1
8.2.2
8.2.3
8.2.4
9.
SJ/ADB/73626/120029/UKM/33410506.23 524
Schedule 24- Waste Delivery Protocol
9.1
9.2
9.3
10.
I 0.1
SJ/AD Bi7362 6/12()029/U KJ\.1/3341 0506.23 525
Scht::dulu 24- Wasle Ddivcry Protocol
10.2
f
10.3
.
10.4
10.5
10.6 .
11.
SJ/li.JJB/73626/120029tlJKM/33410506.23 526
Schedule 24 - Waste Delivery Protocol
1.
SJ I AD B/736261120029/UKM/33 41 05 06.23 527
Schedule 24 - Waste Delivery Protocol
SJ/ADB/73626/120029/UKM/33410506.23 528
Schedule 24 - Waste Delivery Protocol
2.
2.1
2.2
2.3
2.4
2.5
2.6
2.7
3.
3.1
3.2
3.3
3.4
3.5
SJ/ ADB/73626/120029/UKM/3341 0506.23 529
Schedule 24- Waste Delivery Protocol
3.6
3.7
3.8
3.9
4.
4.1
4 .1.1
4.1.2
4.1.3
S.J! A!JR/73626/120029/t:KM/3341 0506.23 530
Schedule 24- Waste Delivery Protocol
4.1.4
4.1.5
4.1.6
4.1.7
4.2
4.3
4.4
4.5
4.6
4.7
4.8
4.9
4.10
4.11
SJ/ADB/73626/120029/UKM/33410506.23 531
Schedule 24- Waste Delivery Protocol
4.12
5.
5.1
5.2
5.2.1
5.3
5.4
5.5
5.6
5.7
5.8
5.9
5.9.1
5.10
5.11
SJ/ ADB/73626/1 20029/UKM/334 10506.23 532
Schedule 24 - Waste Delivery Protocol
5.12
5.13
5.13 .I
5.13 .2
5.13 .3
5.14
5.15
5.16
5.17
5.18
5.19
5.20
5.21
5.22
5.23
5.24
SJ/ AD B/7 3626/ 120029/UKM/3341 05 06.23 533
Schedule 24- Waste Delivery Protocol
6.
6.1
6.2
6.3
6.4
6.5
6.6
6. 7
6.8
6.9
7.
7 .I
7.2
7.3
7.3.1
SJ/ADB/73626/120029/UKM/33410506.23 534
Schedule 24- Waste Delivery Protocol
7.4
7.5
7.6
7 .6.1
8.
8.1
SJ/ ADB/7362 6/120029 /UKM/3341 05 06.23
•
535
Schedule 24 - Waste Delivery Protocol
9.
10.
I 0.1
SJ/ A DB/73 626/120029/UKM/3341 0506.23 536
Schedule 24 - Waste Delivery Protocol
I 0.2
10.2.1
I 0.2.2
I 0.3
10.3.1
I 0.4
I 0.5
10.6
SJ I ADB/73 626/120029/UKM/3341 0 5 06.23 537
Schedule 24 - Waste Delivery Protocol
SJ/ ADB/73626/120029/UKM/3341 0506.23 538
Schedule 25 -Relevant Discharge Terms
SCHEDULE25
Relevant Discharge Terms
I. The sums referred to in paragraph 2.1 below and the adjustment between the parties of the
rights and liabilities relating to the Assets referred to in paragraph 2.2 below shall be relevant
discharge terms in relation to this Contract for the purposes of Section 6 of the Local
Government (Contracts) Act 1997.
2. In the event of the making of a determination or order by a court of final jurisdiction on an
application for judicial review or audit review (within the meaning of the Local Government
(Contracts) Act 1997), the result of which is that this Contract does not or ceases to have
effect or is otherwise unenforceable, then:
2.1 the City Council shall pay to the Contractor the sum equivalent to:
2.1.1 the City Council Default Termination Sum where the City Council has
initiated proceedings that resulted in the determination or court order referred
to above; or
2.1.2 the Force Majeure Termination Sum in all other cases,
in each case calculated as at the date of such determination or order; and
2.2 the City Council shall have the option to require the Contractor to transfer its right,
title and interest in and to the Assets to the City Cotmcil or as directed by the City
Council.
3. The City Council shall pay to the Contractor the sums referred to in paragraph 2.1 within
forty (40) Business Days of the determination or order of the court referred to in paragraph 2
and the provisions of paragraphs I and 2 of Part 6 (General) of schedule 16 (Compensation on
Termination) shall apply.
4. Any payment of compensation in accordance with this schedule 25 shall be in full satisfaction
of any claim of the Contractor in relation to the termination of this Contract and shall be the
sole remedy of the Contractor against the City Council in respect of the circumstances
contemplated by paragraph I above.
SJ/ADB/73626/120029/UKM/33410506.23 539
Schedule 26 )Ton Leeds Waste Information
SCHEDULE26
.Part 1
City Conndl Administrative Boundary
l'f«<Lie!Oj~ .tastii.Digamnl~ 111111
l~i !-,-u:;<:l::l .=:-~·
SJ/ AJ)B/736261120029/U Kl'vl/3341 0506.23 540
Schedule 26 Non Leeds Waste Information
Part2
Transfer and Treatment Stations in Leeds
Name Address Post Code Primary Activity (Note 1)
1 Associated Waste Carr Crofts, LS12 3HB Transfer & Management Ltd Armley, Leeds Treatment
2 B W Skip Hire Ltd Ashfield Way, Whitehall Road LS12 5JB Transfer Industrial Estate, Leeds
3 B W Skip Hire Ltd Far Royds Industrial Estate, LS12 6ER Transfer Whitehall Road, Wortley, Leeds
4 B iff a Waste Services Ltd Pontefract Lane, LS15 9AD Transfer Newsam Green, Leeds
5 Biffa Waste Services Ltd Geldered Road, LS12 6DG Transfer Leeds
6 Bill Dyson Skip Hire Whitehall Industrial Estate, LS12 5JB Transfer Whitehall Road, Leeds
7 H W Martin Waste Ltd Parkside Lane, LSI! 5TD Transfer & Parkside h1dustrial Estate, Leeds Treatment
8 Jeff Skinner Skip Hire Ltd The Sidings, Copley Hill, LS121HY Transfer Leeds
9 LSS Waste Management Ltd Cross Green Industrial Estate, LS9 OPF Transfer & Knowsthorpe Way, Leeds Treatment
10 Leeds Paper Recycling Ltd Valley Farm Road, LSIO lSD Treatment Stourton, Leeds
11 Skelton Ltd Knowsthorpe Road, Cross Green LS9 OSW Treatment Industrial Estate, Leeds
12 Tom Shea & Sons Knowsthorpe Road, Cross Green LS90BW Transfer & Industrial Estate, Leeds Treatment
13 TradpakLtd Brancepeth Place, LS122EH Treatment Armley Road, Leeds
14 Waddington Mark Aireborough Miniskips, Milner LS197JE Transfer Road, Yeadon, Leeds
15 Wetherby Skip Services Ltd Champagne Whin, Spring Lane, LS23 7DN Transfer & Walton, Wetherby Treatment
NOTE 1: Primary Activity provided as a guide for information only- typically all facilities will carry out some degree of both transfer and treatment
SJ I ADB/73626/120029/UKM/3 341 0 5 06.23 541
Schedule 27- Parent Company Guarantee
SCHEDULE27
Parent Company Guarantee
SJ/ADB/73626/120029/UKM/33410506.23 542
Schedule 27 -Parent Company Guarantee
DATED 2012
(1) VEOLIA ENVIRONMENTAL SERVICES UKPLC
-and-
(2) LEEDS C1TY COUNCIL
GUARANTEE relating to
Residual Waste Treatment Contract
SJ/ADB/73626/120029/UKM/33410506.23 543
Schedule 27 - Parent Company Guarantee
THIS GUARANTEE is made on 2011
BETWEEN:
(I) VEOLIA ENVIRONMENTAL SERVICES (UK) PLC, a public limited company
incorporated in England with company number 02215767 and with its registered office at
Veolia House, 154a Pentonville Road, London, Nl 9PE (the "Guarantor"); and
(2) LEEDS CITY COUNCIL of Civic Hall, Leeds LSI IUR (the "Authority").
BACKGROUND
Under the terms of a Residual Waste Treatment Contract entered into on the date hereof (the
"Contract") and made between the Authority and Veolia ES Leeds Limited (the "Contractor"), the
Authority has selected the Contractor to design, install, finance, operate and maintain an energy from
waste facility.
Under the terms of this Guarantee the Guarantor guarantees to the Authority the performance by the
Contractor of each and every one of its obligations under the Contract.
OPERATIVE PROVISIONS
I. DEFINITIONS
In this Deed the following expressions have the following meanings unless inconsistent with
the context:
"Adjusted FairValne of the Contract" has the meaning given in the Contract;
"Adjusted Highest Compliant Tender Price" has the meaning given in the Contract;
"Guaranteed Obligations" has the meaning given in clause 3.1; and
"Indexed" has the meaning given to it in the Contract.
2. INTERPRETATION
Clause 1.2 of the Contract shall apply to this Guarantee.
SJ/ ADB/73 626/120029/UKM/3341 0 5 06.23 544
Schedule 27 - Parent Company Guarantee
3. GUARANTEE
3.1 In consideration of the Authority entering into the Contract with the Contractor and in
consideration of the payment of one pound (£1) by the Authority to the Guarantor, receipt of
which the Guarantor acknowledges, subject to paragraphs 3.4 and 3.6, the Guarantor as
principal obligor and not merely as surety:
3.1.1 guarantees unconditionally and irrevocably to the Authority the due and punctual
observance and performance by the Contractor of its obligations under the Contract as
may be modified, amended or supplemented or diminished by partial termination
("Guaranteed Obligations"); and
3.1.2 in the event that the Contractor fails to perfonn and/or observe and/or breaches the
Contract, agrees to promptly procure that the Contractor makes good the failure to
perform and/or breach or otherwise cause it to be made good and to indemnity and
hold harmless the Authority against any loss, damage, demands, charges, payments,
liability, proceedings, claims, costs and expenses suffered or incurred by the
Authority arising from or in connection with the failure to perform or the breach
(including all reasonable costs and expenses which the Authority may incur in
enforcing this Guarantee) as if the Guarantor instead of the Contractor was expressed
to be the Contractor under the Contract.
3.2 The Guarantor irrevocably and unconditionally agrees to indemnity the Authority on demand
against:
3 .2.1 any cost, loss or liability suffered by the Authority if any of the Guarantor's
obligations and/or commitments under this Guarantee become unenforceable, invalid
or illegal (the amount of the cost, loss or liability being equal to the amount which the
Authority would otherwise have been entitled to recover had the relevant obligations
and/or commitments not been unenforceable, invalid or illegal); and
3.2.2 all costs and expenses (including without limitation legal costs) charged or incurred
by the Authority in enforcing this Guarantee and/or in the recovery or attempted
recovery of money due to the Authority under this Guarantee.
3.3 The Guarantor shall pay interest on all sums demanded under this Guarantee from the date of
demand until actual payment (as well after as before any judgement) at tl1e Prescribed Rate as
defined under the Contract.
SJ/ ADB/73626/120029/UKM/3341 0506.23 545
Schedule 27- Parent Company Guarantee
3.4 The following provisions shall apply in respect of the Guarantor's obligations and liabilities
hereunder:
3.4.1 Subject to any amounts properly claimed under clause 3.2.2, the Guarantor shall have
no greater obligation or liability under this Guarantee in relation to all or any of the
Guaranteed Obligations than that of the Contractor arising out of the same matter
pursuant to the terms of the Contract and any addendum or variation thereto.
3.4.2 In any action by the Authority under this Guarantee, the Guarantor shall have
available to it all defences, counter-claims contractual rights and set-offs as may have
been available to the Contractor under the terms of the Contract.
3.4.3 The same periods of! imitation which apply between the Contractor and the Authority
under the Contract shall apply to any claim under this Guarantee.
3.5 The Authority shall not be obliged to exhaust all remedies against the Contractor before
enforcing the terms of this Guarantee.
3.6
4. PRESERVATION OF RIGHTS
4.1 The obligations of the Guarantor herein contained shall be in addition to and independent of
every other security which the Authority may now or hereafter hold in relation to the
Guaranteed Obligations or any of them.
4.2 Neither the obligations of the Guarantor herein contained nor the rights, powers and remedies
conferred upon the Authority by law in respect of the Guarantor shall be discharged, impaired
or otherwise affected by:
4.2.1 the winding-up, dissolution, administration or reorganisation of the Contractor or any
change in its status, function, control or ownership;
4.2.2 any incapacity or lack of power or authority and any change in the members or status
of the Guarantor or any other person;
SJ/ADB/73626/120029/UKM/33410506.23 546
Schedule 27 -Parent Company Guarantee
4.2.3 any of the Guaranteed Obligations or any of the obligations of the Contractor under
any other security relating to the Guaranteed Obligations being or becoming illegal,
invalid, unenforceable or ineffective in any respects;
4.2.4 time, conduct, concession, compromise, forbearance or other indulgence being
granted or agreed to be granted to the Contractor in respect of the Guaranteed
Obligations or any of them or under any such other security in which circumstances
the obligations of the Guarantee shall be varied by the extent of the time or other
indulgence;
4.2.5 any amendment to, or any variation, waiver or release of, any of the Guaranteed
Obligations or any such other security and the Contract may be modified, amended or
supplemented in any manner whatsoever without the consent of the Guarantor;
4.2.6 any delay or failure in full or in part to exercise any right under this Guarantee; or
4.2.7 any other matter or circumstance whereby but for this provision the Guarantor would
or might be discharged from liability.
4.3 Any settlement or discharge given by the Authority to the Guarantor in respect of the
Guarantor's obligations hereunder or any other agreement reached between the Authority and
the Guarantor in relation thereto shall be, and be deemed always to have been, void if any act
on the faith of which the Authority gave the Guarantor that settlement or discharge or entered
into that agreement is subsequently avoided by or in pursuant of any provisions of law.
5. REPRESENTATIONSANDWARRANTIES
5 .I The Guarantor represents and warrants that:
5.1.1 it is duly incorporated and has the power to enter into and perform the Guarantee and
has taken all necessary corporate action to authorise the execution, delivery and
perfonnance of this Guarantee;
5.1.2 the execution, delivery and performance of this Guarantee will not contravene any
law or regulation to which the Guarantor is subject or any provision of the
Guarantor's memorandum and articles of association and all governmental or other
consents requisite for such execution, delivery and performance are in full force and
effect;
SJ/ADB/73626/120029/UKM/33410506.23 547
Schedule 27 -Parent Company Guarantee
5 .1.3 the obligations expressed to be assumed by it under this Guarantee are legal, valid,
binding and enforceable obligations; and
5.1.4 the execution, delivery and performance of this Guarantee will not cause the
Guarantor to be in breach or default under any agreement binding on it or any of its
assets and no material litigation or administrative proceeding before, by or of any
court or governmental authority is pending or (so far as the Guarantor knows)
threatened against it or any of its assets.
6. PAYMENTS
All payments to be made by the Guarantor to the Authority hereunder shall be made in full
without set-off or counterclaim and without any deduction or withholding whatsoever. If the
Guarantor is obliged by law to make any deduction or withholding from any such payment,
the amount due from the Guarantor in respect of such payment shall be increased to the extent
necessary to ensure that, after the making of such deduction or withholding, the Authority
shall receive a net amount equal to the amount which the Authority would have received had
no deduction or withholding been required to be made.
7. CONTINUING SECURITY
The obligations of the Guarantor herein contained shall constitute and be continuing
obligations notwithstanding any settlement of account or other matter or thing whatsoever,
and in particular but without limitation, shall not be considered satisfied by any intermediate
payment or satisfaction of all or any of the obligations of the Contractor in relation to any of
the Guaranteed Obligations, save to the extent of such payment or satisfaction, and, save as
aforesaid, shall continue in full force and effect until final payment in full of all amounts
owing by the Contractor under the Contract and total satisfaction of all the Contractor's actual
and contingent obligations under the Contract.
8. PRIORITY OF THE AUTHORITY
8.1 So long as any liability incurred by the Contractor to the Authority under or in connection
with the Contract (and which forms part of the Guaranteed Obligations) remains unsatisfied,
the Guarantor shall not:
8.1.1 seek to enforce payment by receipt of money, set-off, counterclaim, enforcement of
security, proof of debt, subrogation or otherwise against the Contractor of the
amounts paid by the Guarantor under this Guarantee;
SJ/ADB/73626/120029/UKM/33410506.23 548
Schedule 27 -Parent Company Guarantee
8.1.2 in the event of insolvency, winding up, liquidation or dissolution of the Contractor
prove in competition with the Authority in respect of any money owing to the
Guarantor by the Contractor; or
8.1.3 have the benefit of, or share m any payment from or composition with, the
Contractor.
8.2 lf, notwithstanding the provisions of clause 8.1 above, at a time when any liability incurred by
the Contractor to the Authority under or in connection with the Contract (and which forms
part of the Guaranteed Obi igations) remains unsatisfied, the Guarantor receives from the
Contractor any monies or property in respect of amounts paid by the Guarantor under this
Guarantee or owing to the Guarantor by the Contractor, the Guarantor shall hold such monies
or property on trust for the Authority and shall pay or transfer the same to the Authority
immediately on request to the extent of the unsatisfied liability at that time.
9. EVIDENCE OF LIABILITY OF THE CONTRACTOR
Any money judgement of the court or decision of an adjudicator against the Contractor in
favour of the Authority under the Contract shall be conclusive evidence for the purposes of
this Guarantee as to any liability of the Contractor to which such judgement or award or
decision relates (unless or until the same is set aside by any competent court or tribunal).
10. NOTICES
I 0.1 Any demand, notice or other communication given in connection with or required by this
Guarantee shall:
10.1.1 be made in writing (entirely in the English language);
I 0.1.2 set out the reasons for any such demand or notice m relation to the relevant
Guaranteed Obligations; and
I 0.1.3 be delivered to, or sent by pre-paid first class post to, or sent by facsimile
transmission to:
10.1.3.1in the case of the Authority, the Director of Environments and
Neighbourhoods, 4th Floor Merrion House, II 0 Merrion Street, Leeds LS2
8DT (facsimile number 0113 224 3543) (or such other address or number as
may be notified in writing from time to time); or
SJ/ ADB/73626/120029/UKM/3341 0506.23 549
Schedule 27 - Parent Company Guarantee
I 0.1.3.2in the case of the Guarantor, to its registered office or its address stated in this
Guarantee (or such other address as may be notified in writing from time to
time) or for the attention of Ben Lambert (General Counsel) to facsimile
number 020 7812 5001 (or such other number may be notified in writing
from time to time).
10.2 Any such demand, notice or communication shall be deemed to have been duly served:
10.2.1 if delivered by hand, when left at the proper address for service; or
10.2.2 if given or made by pre-paid first class post, two Business Days after being posted; or
10.2.3 if sent by facsimile, on the day of transmission provided that a confirmatory copy is
on the same day that the facsimile is transmitted, sent by pre-paid first class post in
the manner provided for in this clause 1 0.2;
Provided, in each case, that if the time of such deemed service is either after 4:00 pm on a
Business Day or on a day other than a Business Day service shall be deemed to occur instead
at 10:00 am on the next following Business Day.
11. GOVERNINGLAW
This Guarantee shall be governed by and construed in accordance with English law and the
Guarantor hereby irrevocably submits to the jurisdiction of the English Courts.
12. ASSIGNMENT
12.1 The Authority may without the consent of the Guarantor assign or charge the benefit of this
Guarantee to any person to whom the Authority lawfully assigns or charges the whole of the
benefit ofthe Contract in accordance with clause 75 (Assignment and Sub-Contracting) of the
Contract.
12.2 The Guarantor may not assign or transfer any of its rights and/or obligations under this
Guarantee.
12.3 This Guarantee shall be binding on the Guarantor's successors in title.
IN WITNESS of which the parties have duly executed and delivered this document as a deed the day
and year first herein before mentioned.
SJ/ ADB/73626/120029/UKM/3341 0506.23 550
EXECUTED as a deed by VEOLIA ) ENVIRONMENTAL SERVICES ) (UK) PLC acting by two directors or a director and the company secretary:
) )
Director
Director/Secretary
The Common Seal of LEEDS CITY ) COUNCIL was hereunto affixed ) byorder: )
Name
SJ/ADB/73626/120029/UKM/33410506.23
Schedule 27 -Parent Company Guarantee
551
Schedule 28- Title Documents
SCHEDULE28
Title Documents
Site at Pontefract Lane, Cross Green Indnstrial Estate, Leeds
I. Official copies and title plan for title number WYK865414.
2. A copy conveyance dated II January 1993 and made between (1) Leeds City Council and
(2) Francis Quinlan.
3. A copy conveyance dated 25 March 1903 and made between (1) Thomas Briggs, James
Sutcliffe and John Charles Thackray and (2) James Sutcliffe.
4. A copy conveyance dated 25 March 1903 and made between (1) Thomas Briggs, James
Sutcliffe and John Charles Thackray and (2) Harry Midgley.
5. A copy conveyance dated 25 March 1903 and made between (1) Thomas Briggs, James
Sutcliffe and John Charles Thackray and (2) Hemy Thompson.
6. A copy conveyance dated 10 January 1996 and made between (1) Leeds City Council and (2)
Francis Quinlan.
7. A copy conveyance dated 20 September 1909 and made between (1) The Honourable Edward
Frederick Lindley Wood and The Honourable Charles Lindley Viscount Halifax Colonel and
The Honourable Henry William Lowry Corry and George Herbert Peake and (2) The Lord
Mayor Aldermen and Citizens of the City of Leeds.
8. A copy deed dated 9 May 1913 and made between the same parties as the conveyance dated
20 September 1909 referred to above.
9. A copy agreement dated 20 February 1959 made between (1) Sir Arthur Horace Penn and
Stanley Albinus Spofforth and Arthur Rimmington Glazebrook and (2) The British Transport
Commission.
10. A copy conveyance dated 8 August 1963 made between (1) the City of Leeds and S.A.
Spofforth Esq and another and (2) The Lord Mayor Aldermen and Citizens of the City of
Leeds.
11. Official copies of title plan for title number WYK647494.
SJ/ ADB/73626/ 120029/UKM/3341 05 06.23 552
Schedule 28 - Title Documents
12. A copy lease dated 31 March 1999 and made between (I) Leeds City Council and
(2) AR Timmermans and Pearson Jones and Company (Trustees) Limited and MN Chapman.
13. Official copies and title plans for title number WYK423854.
14. A copy lease dated I September 1988 and made between (I) Leeds City Council and
(2) Yorkshire Electricity Board.
15. A copy licence re: 10" gas main dated I December 1959 and made between (I) The Trustees
of the Temple Newsam Est and (2) North Eastern Gas Board.
16. A copy licence re: 12" gas main dated 25 April 1933 and made between (I) The Right Han
Baron Irwin and (2) The Lord Mayor Aldermen and Citizens of the City of Leeds.
17. Commercial drainage and water search dated 20 January 2009.
18. Coal Authority search dated 6 January 2009.
19. Local search dated 10 December 2008.
20. Commercial Property Standard Enquiries (CPSE I and CPSE 3) dated 17 September 2009
relating to land at Pontefract Lane, Cross Green Industrial Estate, Leeds.
21. Conveyance dated 18 September 1962 between F L Wood, Viscount Halifax, H W L Corry and G H Peake (I) and Leeds Corporation (2).
22. A copy lease dated 21 June 1967 and made between (I) Leeds City Council and (2) Yorkshire Electricity Board.
SJ/ AD B/73626/12002 9/UKM/3 341 0506.23 553
Schedule 29-
SCHEDULE29
SJI ADB/73626/120029/UKM/3341 0506.23 554
Schedule 29-
Part 1
Base Case
Attached separately as a disk, initialled by the parties for the purposes of identification only.
SJ/ AD B/73 626/120029/UKM/3 341 0 506.23 555
Schedule 29-
Part2
SJ/ ADB/73 62 6/120029/UKM/3341 05 06.23 556
Schedule 30- Independent Certifier's Deed of Appointment
SCHEDULE30
Independent Certifier's Deed of Appointment
DATED
(1) LEEDS CITY COUNCIL
-and-
(2) VEOLIA ES LEEDS LIMITED
-and-
(3) [INDEPENDENT CERTIFIER]
DEED OF APPOINTMENT OF INDEPENDENT CERTIFIER
relating to the design and construction of residual waste treatment facilities in the City
of Leeds
SJ/ AD B/7 3 6261120029 /UKM/3 341 0506.23
20I2
557
Schedule 30- Independent Certifier's Deed of Appointment
TillS DEED OF APPOINTMENT is made on 2012
BETWEEN
(I) LEEDS CITY COUNCIL of Civic Hall, Leeds, LSI lUR ("City Council") which
expression shall include its successors and assigns;
(2) VEOLIA ES LEEDS LIMITED a company registered in England and Wales with number
07876913 whose registered office is at 8th Floor, 210 Pentonville Road, London Nl 9JY or
any substitute or its permitted successors in title or assigns ("Contractor");
(3) [INDEPENDENT CERTIFIER] a company registered in England and Wales with number
+ whose registered office is at + or such other Person
duly appointed pursuant to the terms of this Deed ("Independent Certifier").
BACKGROUND
A The City Council and the Contractor have entered into the Project Agreement for Services
relating to the design, installation, operation and maintenance of residual waste treatment
facilities.
B The Contractor has sublet the design and construction of a part of the residual waste treatment
facilities to the Construction Contractor under a construction contract (the "Construction
Contract") upon like terms to its obligations under the Project Agreement.
C The terms of the Project Agreement require the City Council and Contractor jointly to appoint
the Independent Certifier.
D The Contractor wishes the administration of the Construction Contract to be consistent with
decisions to he taken under the Project Agreement.
E The City Council, the Contractor and the Independent Certifier have agreed to enter into this
Deed for the purposes of setting out the terms upon which the Independent Certifier is
appointed.
SJI ADB/73626/120029/UKM/3341 0506.23 558
Schedule 30- Independent Certifier's Deed of Appointment
OPERATIVE PROVISIONS
I. DEFINITIONS AND INTERPRETATION
"City Council Additional Fee" means the amounts payable to the Independent Certifier in
consideration of the performance of any City Council Additional Services;
"City Council Additional Services" means any services other than the Joint Services and
the Contractor Additional Services which the Independent Certifier performs on behalf of the
City Council pursuant to clause 7;
"Constructioo Contractor" means CNIM Clugston (Leeds) Limited;
"Contractor Additional Fee" means the amounts payable to the Independent Certifier in
consideration of the performance of any Contractor Additional Services;
"Contractor Additiooal Services" means any services other than the Joint Services and the
City Council Additional Services which the Independent Certifier performs on behalf of
Contractor pursuant to clause 7, which shall include the services set out in Schedule 4 of this
Deed to be carried out in relation to the Construction Contract;
"Construction Programme" means the programme set out in the Construction Contract as
updated from time to time in accordance with the Construction Contract;
"Couoterparties" means each of the parties numbered (I) and (2) above and "Counterparty"
shall mean any one or more of them as the context of any particular provision of this Deed so
reqmres;
"Director" means the person named in schedule I Part I or such replacement person
appointed in accordance with clause 4.2;
"EPC Acceptance Tests" has the meaning given to Acceptance Tests under the Construction
Contract;
"EPC Acceptaoce Test Certificate" has the meaning given to Acceptance Test Certificate
under the Construction Contract;
"EPC Readiness Tests" has the meaning given to Readiness Tests under the Construction
Contract;
SJI ADB/73 626/120029/UKM/3341 05 06.23 559
Schedule 30 -Independent Certifier's Deed of Appointment
"EPC Readiness Test Certificate" has the meaning given to Readiness Test Certificate
under the Construction Contract;
"EPC Works" has the meaning given to Works under the Construction Contract;
"Fee" means the amounts stated in schedule 2 payable to the Independent Certifier m
consideration of the performance of the services set out in schedule 3 and the body of this
Deed (excluding any Contractor Additional Services and/or any City Council Additional
Services);
"IC Services" means all the serviCes to be performed by the Independent Certifier in
connection with the Project as set out in schedule 3 and the body of this Deed including any
Contractor Additional Services and/or any City Council Additional Services;
"Joint Services" means the services set out in schedule 3 to this Deed to be carried out in
relation to the Project Agreement;
"Parties" means each of the parties numbered ( 1) to (3) above and "Party" shall mean any
one or more of them as the context of any particular provision of this Deed so requires;
"Payer" means:
(a) in the case of any City Council Additional Fee, the City Council; and
(b) in the case of the Fee and any Contractor Additional Fee, the Contractor;
"Project Agreement" means the agreement dated + (including any variation or
replacement of such agreement from time to time) entered into between the City Council and
Contractor for the provision of the Project; and
"Project Data" means all teclmical information (whether or not stored in computer systems),
drawings, models, bills of quantities, specifications, schedules, details, plans, programmes,
budgets, reports, calculations or other documents whatsoever provided or to be provided by
the h1dependent Certifier in connection with the Project.
1.1 The clause headings in this Deed are for the convenience of the Parties only and do not affect
its interpretation.
1.2 Words importing the singular meaning include the plural meaning and vice versa.
SJ/ AD B/73 626/120029/UKM/3 341 0 506.23 560
Schedule 30 -Independent Certifier's Deed of Appointment
1.3 Words denoting the masculine gender include the feminine and neuter genders and words
denoting natural persons include corporations and firms and all such words shall be construed
interchangeably in that manner.
1.4 Reference in this Deed to a clause or schedule or Appendix are to a clause or schedule or
Appendix of this Deed unless otherwise specified.
1.5 Reference in this Deed to any statute or statutory instrument includes and refers to any
statutory amendment or re-enactment thereof from time to time and for the time being in
force.
1.6 Any reference to this Deed or any other document shall include any permitted variation,
amendment or supplement to this Deed or such document.
1.7 The words and phrases "other", "including" and "in particular" shall not limit the generality of
any preceding words or be construed as being limited to the same class as any preceding
words where a wider construction is possible.
1.8 Terms used in this Deed that are defined in the Project Agreement shall have the meanings
given to them in the Project Agreement save where otherwise expressly defined herein.
2. APPOINTMENT OF INDEPENDENT CERTIFIER
2.1 The City Council and the Contractor hereby appoint the Independent Certifier and the
Independent Certifier hereby agrees to perform the JC Services. The Independent Contractor
acknowledges that, notwithstanding any provisions herein, it is jointly instructed by the
Counterparties and that it owes a joint and several duty of care to those Counterparties.
2.2 All Parties shall act in good faith towards each other at all times.
3. INDEPENDENT CERTIFIER'S DUTIES
3.1 The Independent Certifier shall perform the IC Services fully and faithfully upon and subject
to the provisions of this Deed and the Independent Certifier acknowledges and agrees that
each of the Counterparties is relying and will continue to rely on the professional skill and
care of the Independent Certifier required pursuant to clause 3 .4 of this Deed in the
performance of the IC Services and that it owes a duty of care to each of the Counterparties in
relation to all aspects thereof notwithstanding that this Deed differentiates between Joint
Services, City Council Additional Services and Contractor Additional Services. For the
avoidance of doubt, the Counterparties agree that nothing in this clause shall affect their
SJ/ADB/73626/120029/UKM/33410506.23 561
Schedule 3 0 - Independent Certifier's Deed of Appointment
respective rights, remedies, responsibilities and obligations under the Project Agreement and
that for the purposes of the Project Agreement and the Construction Contract (but without
prejudice to the Independent Certifier's duty of care to each of the Counterparties in respect of
the IC Services as a whole) when performing:
3.1.1 the Joint Services the Independent Certifier is acting for and on behalf of the City
Council and the Contractor;
3 .1.2 the City Council Additional Services the Independent Certifier is acting for and on
behalf of the City Council and not for the Contractor; and
3 .1.3 when performing the Contractor Additional Services the Independent Certifier is
acting for and on behalf of the Contractor and not for the City Council.
3 .2 Where, in the performm1ce of the IC Services, the Independent Certifier is required or entitled
to exercise a discretion as between the Counterparties or between the Counterparties and any
third party, the Independent Certifier shall at all times act objectively m1d impartially and
shall in no circumstances place the interests of any one party above those of any other party
including any third party.
3.3 Where, in the performance of the IC Services, the Independent Certifier seeks or is obliged to
seek the approval or agreement of the Counterparties to any matter or issue, the giving or
confirming of the same shall not in any way derogate from the Independent Certifier's
obligations under this Deed nor diminish any liability on its part for breach of such
obligations and no enquiry, inspection, comment, consent, decision or instruction at any time
made or given by or on behalf of the Counterparties shall operate to exclude or limit the
obligations of the Independent Certifier to exercise all the skill care and diligence required by
clause 3.4 or to comply with the obligations contained in this Deed.
3 .4 The Independent Certifier warrants to each of the Counterparties that it has exercised and will
continue to exercise, in the performance of the IC Services and all its duties hereunder, all the
reasonable skill, care and diligence as may reasonably be expected of a suitably qualified and
competent professional rendering the IC Services and experienced in projects of a similar
type, size, scope and complexity as the Project. For the avoidance of doubt such warranty
may be relied upon by either party independently or by both parties together.
SJ/ AD B/73626/120029/UKM/3341 0506.23 562
Schedule 30- Independent Certifier's Deed of Appointment
3.5 The h1dependent Certifier warrants that it will act promptly and with due regard to deadlines
established wiiliin the Programme and Construction Programme and that it will maintain
adequate resources to ensure that it can satisfY its obligations under iliis Agreement.
3.6 The mdependent Certifier warrants that it will act independently at all times.
3. 7 The mdependent Certifier further warrants to each of the Counterparties severally iliat in the
provision ofilie IC Services it will comply with all law and, without limiting the generality of
the foregoing, have due and proper regard to:
3. 7 .I ilie CDM Regulations; and
3. 7.2 ilie Approved Code of Practice "Managing Construction for Health & Safety"
produced by ilie Health & Safety Executive as amended from time to time; and
3.7.3 relevant Consents; and
shall comply with all lawful and reasonable directions, instructions or requests relating to or
in pursuance of the same given or made by and/or on behalf of Contractor, tile Construction
Contractor and/or ilie City Council whilst ilie mdependent Certifier is present on the Site,
and/or the Adjoining Property.
3.8 The Counterparties shall procure that ilie mdependent Certifier has all such access to tile Site
as it may reasonably require for the purposes of carrying out ilie IC Services and all purposes
ancillary or related to this Deed.
3.9 ill ilie performance of the IC Services the Independent Certifier shall have full regard to any
relevant requirements and/or obligations ofilie Project Agreement, the Construction Contract
and any relevant third party agreements of which it has knowledge and shall perform the IC
Services in such manner and at such times iliat no act, omission or default of the Independent
Certifier in relation iliereto shall constitute or cause any breach by ilie City Council and/or the
Contractor of any such requirements and/or obligations contained in the Project Agreement
and/or the Construction Contract provided always that this shall not extend tile obligations of
ilie Independent Certifier under iliis Deed beyond ilie standard of skill, care and diligence set
out in clause 3.4 hereof.
SJ/ADB/73626/120029/UKM/33410506.23 563
Schedule 30- Independent Certifier's Deed of Appointment
3.10 Without prejudice to clause 3.7:
3.10.1 the Independent Certifier shall liaise and co operate with the Counterparties and the
Construction Contractor and provide each of them with all such information in
relation to the Project and the IC Services as they together may from time to time
reasonably require promptly and in good time so as not to delay or disrupt the
progress of the Project or cause the Counterparties or the Construction Contractor to
be in breach of or delay in achieving any of their respective obligations under the
Project Agreement and/or the Constmction Contract;
3.10.2 the Independent Certifier shall in respect of the Facility, where the requirements of
clause 23 of the Project Agreement have been met, forthwith issue a Readiness Test
Certificate and Acceptance Test Certificate;
3.10.3 the Independent Certifier shall in respect of the Facility (as defined in the
Construction Contract) and for the purposes of the Construction Contract only, where
the requirements of clause 21 of the Construction Contract have been met, forthwith
issue an EPC Readiness Test Certificate and EPC Acceptance Test Certificate;
3 .I 0.4 the Independent Certifier shall have due regard to any written representations made to
it by either the City Council and/or Contractor and/or the Construction Contractor,
(the party making the representation having at the same time sent the others parties a
copy), in respect of any matter connected with the IC Services and, in particular, the
achievement of completion of the Facility;
3.10.5 nothing in clause 3.10.1, 3.10.2, or clause 3.10.4 shall in any way fetter the decision
of the Independent Certifier as to its obligations under clause 3.10.3;
3 .I 0.6 the Independent Certifier shall provide copies of all certificates issued under clause
23 of the Project Agreement to each of the Counterparties forthwith upon their issue;
3.10.7 the Independent Certifier shall, for the purposes of the Constmction Contract only,
provide copies of the EPC Readiness Certificate and EPC Acceptance Certificate
issued under clause 21 of the Construction Contract to each of the Contractor and the
Construction Contractor forthwith upon their issue;
3.10.8 At the joint request of the City Council and the Contractor having regard to any
written representations made by the Counterparties pursuant to clause 3.10.4 the
Independent Certifier shall provide a professional view to both Counterparties on any
SJ/ ADB/73626/120029/UKM/3 341 0 5 06.23 564
Schedule 30 - Independent Certifier's Deed of Appointment
matters within the Independent Certifier's professional expertise regarding the cause
of and mitigation of Compensation Events in an effort to facilitate an agreement
between the Counterparties as to the effect of Compensation Events. (For the
avoidance of doubt, any such view expressed shall have no effect under the Project
Agreement or the Construction Contract.)
3.10.9 At the joint request of the City Council and the Contractor having regard to any
written representations made by the Counterparties pursuant to clause 3.10.4 the
Independent Certifier shall provide a professional view to both Counterparties on any
matters within the Independent Certifier's professional expertise regarding the cause
of and mitigation of Relief Events or Force Majeure Events in an effort to facilitate an
agreement between the Counterparties as to the effect of Relief Events or Force
Majeure Events. (For the avoidance of doubt, any such view expressed shall have no
effect under the Project Agreement or the Construction Contract).
3 .II The Parties agree that, notwithstanding the terms and effect of any provision of the Limitation
Act 1980 (including any amendment or re-enactment of the same) to the contrary, subject to
clause 3.12 the Independent Certifier acknowledges that nothing contained in this Deed shall
prejudice or affect its liability in tort to any of the Counterparties.
3.12 The Independent Certifier shall only be liable under this Deed in respect of claims whether for
any breach of this Agreement or in tort, negligence, for breach of statutory duty or otherwise
which are notified to the Independent Certifier before the expiration of the period of 12 years
from the date of completion of all of the IC Services under the terms of this Deed.
3.13 The Independent Certifier shall not have any authority to and shall not make or purport to
make any alteration or addition to or omission from the design of the Project (including,
without limitation, the setting of performance standards) or (save to the extent expressly
provided in this Deed) issue any instruction or direction to Contractor, the Construction
Contractor, any Sub-Contractors, any member of the Professional Team or any other
contractor, sub contractor or professional consultant employed or engaged in connection with
the Project and shall not have any authority to and shall not consent or agree to any waiver or
release of any obligation, right, remedy, recourse or responsibility of any party under the
Project Agreement, the Construction Contract, the Operating Contract or of any contract
pursuant to which any contractor, sub contractor or professional consultant is employed or
engaged by any party to the Project Agreement, in connection with the Project.
SJ/ADB/73626/120029/UKM/33410;06.23 565
Schedule 30- Independent Certifier's Deed of Appointment
3.14 The City Council and the Contractor may, by joint notice in writing to the Independent
Certifier suspend all or part of the IC Services for a period previously agreed or determined
by the City Council and the Contractor.
3.15 The City Council may, by notice in writing to the Independent Certifier copied to Contractor,
suspend all or part of the City Council Additional Services for a period previously agreed or
determined by the City Council.
3.16 Not used.
3 .I 7 The Independent Certifier shall within 5 days of the date of execution of this deed execute a
deed of warranty in favour of the Construction Contractor in the form set out in Appendix I
or in such similar or varied terms thereto as the Contractor and Construction Contractor may
agree (acting reasonably) and deliver the same duly executed to the Construction Contractor.
4. INDEPENDENT CERTIFIER'S PERSONNEL
4.1 The Independent Certifier shall forthwith appoint the Director to direct and control the overall
performance by the Independent Certifier of the IC Services and act as the primary contact
and liaison with the Counterparties and the Construction Contractor. Such person or any
replacement approved by the Counterparties pursuant to clause 4.2 from time to time shall
have full authority to act on behalf of the Independent Certifier for all purposes in connection
with this Deed.
4.2 The Independent Certifier shall not replace the Director nor any person approved by the
Counterparties pursuant to this clause 4.2 without the prior approval of the Counterparties
(which approval shall not be unreasonably withheld or delayed) as to the fact, identity,
experience and expertise of such replacement and if such approval is given the identity of the
replacement must be previously approved in writing by the Counterparties.
4.3 Either Counterparty, acting on behalf of the other Counterparty and with its prior written
approval, may request the removal of the Director or any such replacement if it believes in its
reasonable discretion the conduct and/or performance of the Director or any such replacement
to be unsatisfactory, whereupon the Independent Certifier shall replace that person in
accordance with the procedure described in clause 4.2 above.
5. OBLIGATIONS OF THE CITY COUNCIL AND THE CONTRACTOR
5 .I Each Counterparty shall supply to the Independent Certifier on request, in such time so as not
to delay or disrupt the performance by the Independent Certifier of the IC Services, any and
SJ/ADB/73626/120029/UKM/33410506.23 566
Schedule 30- Independent Certifier's Deed of Appointment
all necessary and relevant data and information in the possession of that Counterparty and its
servants or agents.
5.2 Each Counterparty shall give such assistance as shall reasonably be required by the
Independent Certifier in the performance ofthe IC Services and shall give a timely response
to enable the Independent Certifier to comply with its obligations and duties under the
Appointment.
6. REMUNERATION
6.1 In full consideration of the performance of the JC Services in accordance with this Deed, the
Independent Certifier shall be entitled to be paid:
6.1.1 the Fee;
6.1.2 the City Council Additional Fee (if any); and
6.1.3 the Contractor Additional Fee (if any),
in accordance with this clause 6. For the avoidance of doubt, the Fee and any City Council
Additional Fee and any Contractor Additional Fee are inclusive of all disbursements
including travel, photocopying, printing and accommodation, save as expressly provided in
schedule 2 but exclusive of any applicable Value Added Tax and payment thereof shall (for
the avoidance of doubt subject to clause 7) constitute full reimbursement to the Independent
Certifier of all costs, losses, expenses, overheads or profits suffered, incurred or earned, as the
case may be, by the Independent Certifier in respect of the performance of its obligations
under this Deed whenever they may be performed.
6.2 The Independent Certifier may submit invoices to the Contractor no more frequently than
once a month and at the address set out in and marked for the attention of the person
identified in schedule I Part 2:
6.2.1 for the Fee in the instalments and at the times provided for in schedule 2 on or after
the occurrence of the event allocated to that instahnent (with a copy to the City
Council);
6.2.2 for the amount of any Contractor Additional Fee valued in the manner agreed
between Contractor and the h1dependent Certifier at the time that the Contractor
Additional Service is instructed and agreed between them and provided that the
SJ/ AD Bl73 626/120029/UKM/3341 05 06.23 567
Schedule 30 - Independent Certifier's Deed of Appointment
Independent Certifier shall specifY in the invoice the Contractor Additional Services
to which the Contractor Additional Fee relates.
6.3 The Independent Certifier may submit an invoice to the City Council at the address set out in
and marked for the attention of the person identified in schedule I Part 3 for any City Council
Additional Fee in such amounts and at such times as shall be agreed between the City Council
and the Independent Certifier at the time that the City Council Additional Service is instructed
and agreed between them provided that the Independent Certifier shall specifY in the invoice
the City Council Additional Services to which the City Council Additional Fee relates.
6.4 Any sum properly included in an invoice submitted under and in accordance with this clause
6 shall become due on the date 28 days before the end of the month following the month in
which the invoice is received by the Payer.
6.5 The frnal date for the making of any payment of any sum due pursuant to this Deed shall be
28 days after the sum becomes due under the terms of this Deed ("the Final Date For
Payment"). Subject to clause 6.6, the Payer may (without prejudice to any other right or
remedy which the Payer may have under or arising from or pursuant to this Deed, any other
agreement or statute, at common law or otherwise) deduct or withhold from any money
otherwise due to the Independent Certifier 1mder or pursuant to this Deed any sum or sums for
which the Independent Certifier is liable to the Payer under, arising from or pursuant to this
Deed, any other agreement or statute, at common law or otherwise.
6.6 Not later than five days after the date on which any sum becomes due or would have become
due to the Independent Certifier pursuant to this Deed if:
6.6.1 the Independent Certifier had carried out its obligations under this Deed; and
6.6.2 no set-off or abatement was permitted by reference to any sum claimed;
the Payer shall give notice to the Independent Certifier specifYing the amount (if any) of the
payment made or proposed to be made and the basis on which that amount is calculated.
6. 7 If the Payer intends to withhold payment of any sum due to the Independent Certifier under
this Deed pursuant to clause 6.5, the Payer shall give the Independent Certifier a notice not
later than four days prior to the Final Date For Payment of that sum specifYing:
6.7.1 the amount proposed to be withheld and the ground for withholding payment; or
SJI ADB/73626/120029/UKM/3341 0506.23 568
Schedule 30- Independent Certifier's Deed of Appointment
6. 7.2 ifthere is more than one ground, each ground and the amount attributable to it.
6.8 The relevant Payer shall be liable to pay to the Independent Certifier any applicable VAT
properly chargeable by the Independent Certifier in respect of the Fee and, if any, the
Contractor Additional Fee and/or the City Council Additional Fee.
6.9 Amounts agreed by a Payer to be paid to the Independent Certifier on a time basis shall
subject to any other agreement be paid at the rates shown in schedule 2. For the avoidance of
doubt any endorsement by a Counterparty of the time and personnel of the Independent
Certifier occupied in the provision of any service shall not constitute an agreement to make a
payment upon a time basis.
7. ADDITIONAL SERVICES
The Independent Certifier shall perform such Contractor Additional Services and such City
Council Additional Services as the Contractor or the City Council (as appropriate) may from
time to time instruct in writing (with copies to the other Counterparty) and which the
Independent Certifier (acting reasonably) may agree to perform provided always that such
City Council Additional Services and/or Contractor Additional Services do not conflict with
and/or prejudice the Joint Services and/or any previously agreed City Council Additional
Services and/or any previously agreed Contractor Additional Services.
8. PROFESSIONAL INDEMNITY INSURANCE
8. I Without prejudice to its other obligations under this Deed or otherwise at law, the
h1dependent Certifier confirms that it has and shall maintain at all times with reputable
insurers or underwriters carrying on business within the European Union from the
commencement of IC Services and for a period expiring no earlier than 12 years after the
completion of all of the IC Services and notwithstanding the termination for any reason of the
Independent Certifier's engagement under this Deed, professional indemnity insurance with a
limit of indemnity of not less than ten million pounds (£10,000,000) in respect of each and
every claim or series of claims consequent upon or attributable to the same cause or original
source (but such limit may apply in aggregate in any year of insurance in relation to claims
arising out of pollution and/or contamination and/or date recognition) in respect of any
negligence on the part of the Independent Certifier which it may incur under this Deed,
provided always that such insurance continues to be available to it in the European Union
insurance market upon reasonable terms and at commercially reasonable premium rates and
(for the avoidance of doubt) provided further that for the purposes of this clause 8.1 and
clause 8.3 payment of any increased or additional premiums and any terms required by
SJ I AD B/7362 6/ 120029/UKM/3341 0506.23 569
Schedule 30 -Independent Certifier's Deed of Appointment
insurers by reason of the Independent Certifier's own claims record or other acts omissions
matters or things peculiar to the Independent Certifier will be deemed to be reasonable terms
and/or commercially reasonable premium rates as applicable.
8.2 As and when it is reasonably required to do so, the Independent Certifier shall produce for
inspection by either Counterparty documentary evidence that the insurance required by clause
8. I is being properly maintained subject to the same not constituting a breach of the terms of
such insurance.
8.3 The Independent Certifier shall forthwith notify the Counterparties if the insurance required
by clause 8.1 ceases to be available upon reasonable terms and at commercially reasonable
premium rates and (in this event) shall continue to maintain insurance upon such terms and
with such a limit of indemnity as may then be so available upon reasonable terms and at
commercially reasonable rates.
8.4 The Independent Certifier shall not compromise, settle or waive any claim which it may have
under such insurance in respect of any professional liability which it may incur under this
Deed without the prior written consent of the Counterparties.
9. CONFIDENTIALITY
9.1 The Independent Certifier shall not at any time during the period of its engagement hereunder
(save in the proper course of its duties or as may be required by law or any regulatory
authority) and at any time after its expiry or termination for any reason, disclose to any person
nor otherwise make use of any confidential information (including, but without limitation, the
provisions of the Project Agreement and/or the Construction Contract and/or any Project
Document and/or the Financing Documents, information relating to methods and techniques
of construction for the Project and financial information relating to the Project) of which it
has or may in the course of its engagement hereunder become aware relating to the Project,
any of the Counterparties or otherwise, nor shall it disclose to any person whatsoever (save as
aforesaid or to its insurance or professional advisers) anything contained in this Deed, without
the prior written consent of the Counterparties.
9.2 The Independent Certifier will not without the City Council's and the Contractor's pnor
written approval take or pennit to be taken any photographs of the Project for use in any
publicity or advertising or publish alone or in conjunction with any other person any articles
photographs or other illustrations relating to the Project nor impart to any publication journal
or newspaper or any radio or television programme any information regarding the Project.
SJ/ ADB/73626/120029/UKM/3341 0506.23 570
Schedule 30 - Independent Certifier's Deed of Appointment
The Independent Certifier shall be entitled to take and keep records and photographs of the
work in progress for its own use subject to the confidentiality requirements in clause 9 .1.
9.3 The Independent Certifier shall comply with its obligations under the Data Protection Act
1998 and other applicable law in respect of such data.
9.4 This clause 9 does not restrict the Independent Certifier's use of information which is in the
public domain (otherwise than due to a breach of this clause 9 by the Independent Certifier) or
which carne to the Independent Certifier otherwise than in relation to its appointment as
Independent Certifier for the Project.
10. ASSIGNMENT AND SUB LETTING
10.1 The Independent Certifier shall not assign any of its interests in this Deed or any part thereof
nor any right arising hereunder to any person without the prior consent of the Counterparties
and only then on terms expressly approved by the Connterparties and subject to the
Independent Certifier's obligations under this Deed remaining in full force and effect.
10.2 The Independent Certifier shall not, without the prior consent of the Counterparties to the
identity and terms of appointment of any sub consultant, sub contract to any person the
performance of any of the IC Services and where the Counterparties give consent to the
Independent Certifier sub contracting any of its duties pursuant to this clause 10.2:
I 0.2.1 the Independent Certifier shall be responsible for the breaches acts omissiOns
negligence or other defanlt of any sub consultant its agents or employees appointed
by the Independent Certifier as fully as if they were the breaches acts omissions
negligence or other defaults of the Independent Certifier its agents or employees and
such sub contracting shall not modifY release diminish or in any way affect the
liabilities and/or obligations of the Independent Certifier under this Deed and/or at
law or otherwise; and
10.2.2 the remuneration payable to the Independent Certifier in accordance with clause 6
shall not be increased by any amount payable by the Independent Certifier to its sub
consultants.
10.3 Each of the Counterparties may at any time assigu, charge or transfer its respective interest in
this Deed and/or any rights arising hereunder (whether or not accrued) to any person to whom
they are permitted to assign under the Project Agreement upon notice to the Independent
SJ/ ADB/73626/J 20029/UKM/3341 0506.23 571
Schedule 30 -Independent Certifier's Deed of Appointment
Certifier, plus any other person upon notice to the Independent Certifier provided that not
more than two such assignments shall be permitted by any one Counterparty.
11. TERMINATION OF INDEPENDENT CERTIFIER'S ENGAGEMENT BY COUNTERPARTY
11.1 In the event of a material breach by the Independent Certifier of its obligations under this
Deed which it shall fail to remedy after receiving a 28 day notice in writing from Contractor
or the City Council (on behalf of the other Counterparty and having first obtained the consent
of the other Counterparty such consent not to be unreasonably withheld or delayed)
specifYing the breach and requiring its remedy, the Contractor or the City Council (on behalf
of the other Counterparty and having first obtained the consent of the other Counterparty to
do so such consent not to be unreasonably withheld or delayed) may then by a further 21 days'
notice in writing to the Independent Certifier terminate the Independent Certifier's
engagement under this Deed.
11.2 In the event that the Independent Certifier is subject to an order by the court to be wound up
or a resolution for a voluntary winding up is passed, or any receiver or manager in respect of
the Independent Certifier is appointed or possession is taken by or on behalf of any creditor of
any property that is the subject of a charge, or any voluntary arrangements is made for a
composition of debts or a scheme of arrangement is approved under the Insolvency Act 1986
or the Companies Act 2006 in respect of the Independent Certifier, an administration order is
made or an administrator is appointed in respect of the Independent Certifier, the Contractor
or the City Council ( ou behalf of the other Counterparty and having first obtained the consent
of the other Counterparty to do so such consent not to be unreasonably withheld or delayed)
may then by notice in writing to the Independent Certifier having immediate effect terminate
the Independent Certifier's engagement under this Deed.
11.3 Either the Contractor or the City Council (on behalf of the other Counterparty and having first
obtained the consent of the other Counterparty (such consent not to be unreasonably withheld
or delayed)) may by such notice in writing bring to an end the performance of any divisible
part of the IC Services.
11.4 Either the Contractor or the City Council (on behalf of the other Counterparty and having first
obtained the consent of the other Counterparty (such consent not to be unreasonably withheld
or delayed)) may by notice in writing require the Independent Certifier to suspend
performance of all or any of the IC Services. If the Contractor or the City Council shall not
have required the Independent Certifier to resume performance of the IC Services within a
SJ I ADB/73 626/120029/UKM/3 341 0 506.23 572
Schedule 30 - Independent Certifier's Deed of Appointment
period of 12 months from the date of such notice then the City Council, the Contractor or the
Independent Certifier may thereafter forthwith terminate the employment of the Independent
Certifier under this Appointment.
I 1.5 In any case in which a Counterparty has required the Independent Certifier to suspend the
Services under clause 11.4 either the Contractor or the City Council (on behalf of the other
Counterparty and having first obtained the consent of the other Counterparty (such consent
not to be unreasonably withheld or delayed)) may by notice in writing require the Independent
Certifier to resume the performance of the Services. In such event the Independent Certifier
shall as soon as reasonably practicable resume the performance of the IC Services in
accordance with this Deed.
12. TERMINATION OF INDEPENDENT CERTIFIER'S ENGAGEMENT BY iNDEPENDENT CERTIFIER
In the event that any one or more of the Counterparties fails to make a payment of any
undisputed sum due pursuant to this Deed by the Final Date for Payment which breach it or
they, as appropriate, shall fail to remedy after receiving a 28 day notice in writing from the
Independent Certifier (such notice to be copied simultaneously to the other Counterparty)
specifying the breach and requiring its remedy, the Independent Certifier may then by a
further notice in writing to the Counterparties (subject to clause 14) terminate its engagement
under this Deed 21 days from the date of receipt by the Counterparties of such notice unless
the breach referred to in the first notice has been remedied by any one or more of the
Counterparties before the expiry of the 21 days' notice period.
13. CONSEQUENCES OF TERMINATION OF INDEPENDENT CERTIFIER'S ENGAGEMENT
13.1 Upon any notice of termination of the Independent Certifier's engagement being served under
clause II or clause 12, the Independent Certifier shall take such steps as are necessary or
reasonably desirable such that by the end of the 21 days' notice period (or in the
circumstances set out in clause 11.2, with immediate effect) the IC Services have been
brought to an end in an orderly manner but with all reasonable speed and economy and that
there has been delivered to the Counterparties or any person nominated by them copies of all
Project Data, reports, minutes of meetings and other documents prepared or in the course of
preparation by the Independent Certifier in connection with the Project and (in the event that a
replacement firm has been appointed to complete the performance of the IC Services) shall co
operate fully with such replacement to the extent that it is reasonable to do so.
SJ/ ADB/73626/120029/UKM/3341 0506.23 573
Schedule 30 -Independent Certifier's Deed of Appointment
13.2 If the Independent Certifier's engagement under this Deed is tenninated (save other than for
any act omission, negligence or other default of the Independent Certifier), the relevant Payer
shall (subject to any withholdings, deductions or set-offs which they are entitled to make and
to clauses 13.3, 13.4 and 13.5) pay to the Independent Certifier such parts of the Fee, any
Contractor Additional Fee and any City Council Additional Fee which shall have accrued due
prior to the date of such termination less the amount of any payments in respect of the same
previously paid to the Independent Certifier under this Deed.
13.3 Upon any termination of the Independent Certifier's engagement howsoever arising, the
Counterparties shall not be liable, save as is exclusively set out in clause 13 .2, to the
Independent Certifier for any further sums whether in respect of loss of profit, loss of
contracts or other costs, losses and/or expenses arising out of or in connection with such
termination.
13.4 Termination of the Independent Certifier's engagement howsoever arising shall, subject to
clause 13.3, be without prejudice to the rights and remedies of any party to this Deed in
relation to any omission, negligence, act or other default of any other party to this Deed prior
to such termination.
13.5 The provisions of this Deed shall continue to bind each party to this Deed insofar as and for
as long as may be necessary to give effect to their respective rights and obligations under this
Deed.
14. "STEP IN" PROVISIONS"
14.1 The Independent Certifier shall not exercise nor seek to exercise any right to terminate its
engagement under this Deed or serve a notice terminating its engagement under clause 12 or
to discontinue the performance of the IC Services for any reason whatsoever, including
breach on the part of any one or both Counterparties, without giving to each Counterparty not
less than 28 days' notice in writing of its intention to do so and specifying the grounds for the
proposed termination or discontinuance together with details of any sums due under this Deed
which have not yet been paid.
14.2 Any period stipulated in this Deed for the exercise by the Independent Certifier of a right of
termination shall be extended as necessary to take account of the period of notice required
under clause 14 .I.
14.3 The Independent Certifier's right to terminate its engagement under this Deed or to
discontinue the performance of the IC Services shall cease if, within the period of 28 days
SJ/ AD B/73626/120029 /UKM/3341 0506.23 574
Schedule 30 - Independent Certifier's Deed of Appointment
referred to in clause 14.1, any Counterparty not in breach of this Deed shall give notice to the
Independent Certifier:
14.3.1 requiring it to continue the performance of the 1C Services;
14.3.2 acknowledging that it is assuming all the obligations of the other Counterparty in
breach under this Deed; and
14.3.3 undertaking to the Independent Certifier to discharge all payments which may
subsequently become due to the Independent Certifier under this Deed and paying to
the Independent Certifier any sums which have already become due but which remain
unpaid.
14.4 On compliance by any Counterparty with clause 14.3, this Deed shall continue in full force
and effect as if the right of termination or discontinuance on the part of the Independent
Certifier had not arisen and on the basis that all references in this Deed to either and/or both
Counterparties shall thereafter be read and construed as references to the Counterparty
complying with clause 14.3.
14.5 Where a Counterparty has given notice in compliance with clause 14.3 and has given an
undertaking pursuant to clause 14.3.3 and has assumed responsibility under this Deed in
accordance with clause 14.4 the Counterparty in breach shall reimburse and indemnifY the
other Counterparty against each and every liability which that other Counterparty may have to
the Independent Certifier under this Deed by virtue of such undertaking and assumption of
responsibility and against any claims, demands, proceedings, damages, costs and expenses
directly sustained, incurred or payable by that other Counterparty as a consequence thereof
insofar as and to the extent that the same has arisen by reason of any breach by such
Connterparty of its obligations under this Deed.
15. MISCELLANEOUS
15.1 All additions, amendments and variations to this Deed shall be binding only if in writing and
signed by the duly authorised representative of each party to this Deed.
15.2 No waiver by any party to this Deed of any default or defaults by any other party to this Deed
in the performance of any of the provisions of this Deed shall operate or be construed as a
waiver of any other or further default or defaults whether of a like or different character.
SJ I AD B/73626/12002 9/UKM/3341 0506.23 575
Schedule 30- Independent Certifier's Deed of Appointment
15.3 This Deed supersedes any previous agreement or arrangement made with the Independent
Certifier by either or both of the Counterparties in respect of the IC Services (whether oral or
written) and (but without prejudice to or derogation from the respective rights,
responsibilities, remedies, recourse and obligations of the Counterparties to each other
pursuant to the Project Agreement) represents the entire understanding between the
Counterparties and the Independent Certifier in relation thereto. For the avoidance of doubt
as between the Counterparties, in the event of any ambiguity or discrepancy between the
provisions of this Deed and the provisions of the Project Agreement, the provisions of the
Project Agreement shall prevail.
15.4 Notwithstanding the date of this Deed, it shall have effect as if it had been executed upon the
actual commencement of the IC Services by the Independent Certifier.
15.5 This Deed is for the sole benefit of the Parties. No provision of this agreement is intended to
create or creates any right or benefit enforceable against the Parties to this Deed under the
Contracts (Rights of Third Parties) Act 1999. This clause does not affect any right or remedy
of any person which exists or is available otherwise than pursuant to that Act.
16. CONFLICTS OF INTEREST
The Independent Certifier shall use all reasonable endeavours to avoid any conflict of interest
detrimental to the Project. If such conflict of interest shall arise the Independent Certifier
shall immediately notifY the Counterparties thereof.
17. PROJECTDATA
17.1 Copyright in the Project Data shall remain vested in the Independent Certifier and subject
thereto the Independent Certifier hereby grants to each Counterparty an irrevocable non
exclusive royalty free licence with full title guarantee (for the avoidance of doubt such licence
to remain in full force and effect notwithstanding detennination of the Independent Certifier's
appointment for whatever reason or any dispute under this Deed) to copy and use the Project
Data and to reproduce the works designs and inventions contained in the Project Data for all
purposes related to the Project including but without limitation the construction completion
reconstruction alteration extension maintenance letting promotion advertisement
reinstatement use and repair of the Project or the Counterparties' interests in it (but so that
such licence shall not extend to or include a licence to reproduce the designs contained in
them for any extension of the Facilities) and each Counterparty shall be entitled to grant sub
licences on terms equivalent to the provisions of this clause 17.1 and the Counterparty's
licence and such sub licence shall be transferable to other persons without charge or consent
SJ/ AD B/7 3 62 6/120029/UKM/3341 0506.23 576
Schedule 30- Independent Certifier's Deed of Appointment
provided always that the Independent Certifier shall not be liable for the consequences of any
use of the Project Data by the Counterparties for any purpose other than that for which they
were prepared and provided by the Independent Certifier.
17.2 The Independent Certifier shall provide to the Counterparties at their request in such manner
and fonn as is reasonably requested such additional copies of all or any of the Project Data as
are reasonably required by the Counterparties beyond those required for the construction and
completion of the Project and shall provide such additional information and co-operation as is
reasonably required in connection with the same.
17.3 Where any rights are vested in the Independent Certifier by virtue of Chapter IV (Moral
Rights) of Part 1 of the Copyright Designs and Patents Act 1988 the Independent Certifier
hereby irrevocably waives any such rights in relation to the Project or any part thereof and to
any Project Data and shall obtain a written waiver from its employees from time to time of
any rights that they may have in respect of the same.
18. CUMULATIVE RIGHTS AND ENFORCEMENT
18.1 Any rights and remedies provided for in this Deed whether in favour of the Counterparties or
the Independent Certifier are cumulative and in addition to any further rights or remedies
which may otherwise be available to those parties.
18.2 The duties and obligations of the Independent Certifier arising under or in connection with
this Deed arise to the Counterparties jointly and severally and the Counterparties may
accordingly enforce the provisions of this Deed and pursue the prospective rights under this
Deed in their own name, whether separately or with each other.
18.3 The Counterparties covenant with each other that they will not waive any rights, remedies or
entitlements or take any other action under this Deed that would or might reasonably be
expected to adversely affect the rights, remedies or entitlements of the other Counterparty
without the other Counterparty's prior written consent, such consent not to be unreasonably
withheld or delayed.
19. SEVERANCE
If any provision of this Deed is declared invalid, unenforceable or illegal, such invalidity,
unenforceability or illegality shall not prejudice or affect the validity, enforceability or
legality of the remaining provisions of this Deed.
SJ/ADB/73626/120029/UKM/33410506.23 577
Schedule 30- Independent Certifier's Deed of Appointment
20. NOTICES
20.1 Any demand, notice or other communication given in connection with or required by this
Deed shall be made in writing (entirely in the English language) and shall be delivered or sent
by pre paid first class post to the other parties to this Deed at their registered office or address
stated in this Deed (or such other address as may be notified to the other parties in writing
from time to time) or sent by facsimile transmission to the recipient, in the case of the City
Council to facsimile number 0113 + , in the case of the Contractor to facsimile
number + and in the case of the Independent Certifier to facsimile number
• (or such other number as may be notified in writing from time to time) and
unless otherwise expressly stated in this Deed marked for the attention of the [Project
Director] in the case of the City Council, + in the case of Contractor and
+ in the case of the Independent Certifier.
20.2 Any such demand, notice or communication shall be deemed to have been duly served:
20 .2.1 if delivered by hand, when left at the proper address for service; or
20.2.2 if given or made by pre-paid first class post, two Business Days after being posted; or
20.2.3 if sent by facsimile, on the day of transmission provided that a confirmatory copy is
on the same day that the facsimile is transmitted, sent by pre-paid first class post in
the manner provided for in this clause 20.2;
20.3 provided in each case that if the time of such deemed service is either after 4.00 pm on a
Business Day or on a day other than a Business Day service shall be deemed to occur instead
at 10.00 am on the next following Business Day.
21. COUNTERPARTS
This Deed may be executed in one or more counterparts. Any single counterpart or a set of
counterparts executed, in either case, by all the parties shall constitttte a full and original
instrument for all purposes.
22. APPLICABLE LAW AND JURISDICTION
This Deed will be construed in accordance with English law and be in all respects subject to
the exclusive jurisdiction of the English courts.
SJ/ AD B/73 626/120029/UKM/3 341 05 06.23 578
Schedule 30 -Independent Certifier's Deed of Appointment
23. ADJUDICATION
Where Part II of the Housing Grants, Construction and Regeneration Act 1996 applies, any
party may refer any dispute or difference arising under this Deed to adjudication. The
adjudication procedures and the agreement for the appointment of an adjudicator will be as set
out in the Model Adjudication Procedures published by the Construction Industry Council
current at the date of reference. The nominating body will be the Royal Institution of
Chartered Surveyors or any successor organisation.
IN WITNESS whereof the Independent Certifier, the City Council and the Contractor have executed
this document as a deed.
SJ/ A DB/73 626/120029/UKM/3 341 0 506.23 579
Schedule 30- Independent Certifier's Deed of Appointment
SCHEDULE 1
Part 1
Director:
Tel:
Fax:
Email:
Mobile:
Part2
Invoices for the Contractor:
Name:
Address:
Fax:
Part3
Invoices for the City Council:
Name:
Address:
Fax:
SJ/ ADB/73 626/120029/UKM/3341 0506.23 580
A:
Schedule 30 -Independent Certifier's Deed of Appointment
SCHEDULE2
Details for submission of invoices: Invoices for Joint Services shall be submitted no
more frequently than monthly and shall include a breakdown of the instalments by reference
to the events set out in this schedule 2. The invoices must also be valid for the recovery of
VAT.
B: Facilities available to the Independent Certifier free of charge:
C: Fixed Fee (excluding VAT) payable to the Independent Certifier in consideration of the
performance of the services set out in schedule 3:
D: INSTALMENTS IN RESPECT OF THE FEE
The Independent Certifier may apply for nom m/ qtr £ per month Amount£ instalments in respect of the Fee no earlier or quarter than and in no greater amounts than as detailed below:
E: Contractor Additional Services fees
To be invoiced to the Contractor within 5 days after issue of the relevant Certificate
SJ/ADB/736261120029/UKM/33410506.23 581
Schedule 30 - Independent Certifier's Deed of Appointment
SCHEDULE3
Joint Services
The Independent Certifier shall;
I. fulfil the role of the Independent Certifier as described in the Project Agreement in respect of
the IC Services and in accordance with all the provisions of this Deed;
2. familiarise itself with and acquire a good understanding of:
2.1 the Project Agreement (including the Works Delivery and Service Delivery Plans in schedule
3 (Contractor's Proposals) and any changes/derogations implemented from time to time under
schedule 9 (Review Procedure) of the Project Agreement, Services Specification and any
other relevant documentation or infonnation referred to in the Project Agreement) to the
extent necessary to be in a position to carry out the lC Services in accordance with the terms
of the Project Agreement and this Deed;
2.2 the relevant provisions of the Construction Contract (including the Purchaser's Requirements
(as defined in the Construction Contract) and the Basic Design Proposal (as defined in the
Construction Contract) and the relevant aspects of the Construction Contract (both expressed
and implied) to the extent necessary to be in a position to carry out the services in accordance
with this Deed; and
2.3 the relevant variations in relation to the Facility (as defined in the Construction Contract)
implemented pursuant to the Construction Contract including their effect on Purchaser's
Requirements (as defined in the Construction Contract) and the Basic Design Proposal (as
defined in the Construction Contract) to the extent necessary to be in a position to carry out
the services in accordance with this Deed;
3. satisfY itself that the City Council and Contractor have fulfilled their respective duties as
"client" under the CDM Regulations with regard to appointment of competent CDM
coordinators and principal contractors with adequate resources for the Works;
4. satisfY itself that a health and safety plan covering the Works at the Facility has been prepared
by the CDM Coordinator and is in place prior to the commencement of the Works at the
Facility;
5. satisfY itself that the relevant quality management certification and Quality Management Plan
with regard to the Construction Contactor are in place;
SJ/ ADB/73626/120029/UKM/3341 0506.23 582
Schedule 30- Independent Certifier's Deed of Appointment
6. promptly notify the Contractor (copied simultaneously to the Contractor and the City
Council) in writing if the Independent Certifier becomes aware of the Contractor's failure to
comply with its obligations under the Project Agreement which may, in its opinion, prevent
achievement of satisfactory completion of the Readiness Tests and/or Acceptance Tests of the
Facility;
7. monitor a sample number of construction working drawings and specifications which in its
professional judgement is appropriate to be selected by the Independent Certifier to verify
they comply with the approved outline construction specification as described in the Project
Agreement. If in the professional judgment of the Independent Certifier, because of the
results of its sample or other circumstances a different sampling percentage is appropriate, it
shall provide a detailed report in respect of that and, if so agreed (or determined as between
the Contractor and the City Council by the Dispute Resolution Procedure) any change in the
percentage sampling resulting in a change in fees will be borne by the City Council or the
Contractor as they shall agree or as determined by the Dispute Resolution Procedure;
8. conduct Site visits to inspect and monitor the state and progress of the Works to the extent
necessary to be in a position to carry-out the services in accordance with this Deed in order to
familiarise itself with the Works and perform the services. The frequency and timing of the
Independent Certifier's Site visits are dependent on the progress of the construction on Site
but on a minimum of a monthly basis;
9. attend, where appropriate, and participate as necessary m regular monthly Site meetings
relating to the Works;
I 0. provide monthly progress reports and quarterly audit reports for the Contractor and the City
Council to include updated checklists and an outstanding information schedule;
II. agree the methodology and criteria for auditing as are necessary for it to determine whether or
not the;
11.1 Readiness Tests; or
11.2 Acceptance Tests; and
11.3 required standards set out at Appendix 9 (Availability Standards) to the Output Specification;
have been achieved by making appropriate enquiries of the Contractor and the Construction
Contractor. This will include reviewing the Works and notifying the Contractor of any
SJ/ ADB/73626/120029/UKM/3341 o;o6.23 583
Schedule 30 - Independent Certifier's Deed of Appointment
outstanding matters to be attended to before the relevant certification can be deemed as
achieving the requirements for schedule 11 (Tests) to the Project Agreement;
1 2. confirm that a completion certificate has been issued to the Contractor by the Construction
Contractor at the end of Hot Commissioning;
13. observe and witness the Readiness and/or Acceptance Tests and review all results and data
resulting from all such Tests. Having reviewed such results and data, the Independent
Certifier shall advise the Contractor of which tests have been passed and which have been
failed;
14. within the period of two (2) Business Days of the Independent Certifier's receipt of a notice
from the Contractor stating that the Contractor considers that the Readiness and/or
Acceptance Tests have been passed, each by reference to the standards required in schedule
1 1 (Tests) to the Project Agreement, the h1dependent Certifier will either:
14.1 issue the Readiness and/or Acceptance Test Certificate (as the case may be); or
14.2 notify the Counterparties that it considers that the Readiness and/or the Acceptance
Tests have not been passed, by reference to the standards required by schedule 11
(Tests) to the Project Agreement, together with a report setting out the respects in
which it considers that the same has not been so passed;
15. m determining whether to issue the Readiness Test Certificate and/or Acceptance Test
Certificate (as the case may be) the Independent Certifier shall only have regard to whether
the Readiness and/or Acceptance Tests (as the case may be) have been passed in accordance
with the Project Agreement and shall not have regard to any other matter including but not
limited to those other matters for which the Independent Certifier is responsible in accordance
with this Deed;
16. provide a copy of such certificate simultaneously upon its issue by the Independent Certifier
to the City Council;
17. provide a test performance report including the programme, guarantees to be met,
methodology and procedures, results against guarantees and analysis of results;
1 8. certify that the City Council Accommodation has achieved the standards set out in Appendix
9 (Availability Standards) to the Output Specification that are necessary at Completion of
Works and the Extended Commissioning Date;
SJ/ ADB/73626/120029/UKM/3341 0506.23 584
Schedule 30 -Independent Certifier's Deed of Appointment
19. advise the Counterparties if it believes that the Works have not been carried out in accordance
with the Project Agreement, at any time prior to the issue of the Readiness Test Certificate or
Acceptance Test Certificate (as appropriate) in respect of the Facility;
20. collate, produce and issue a Snagging List in accordance with the Project Agreement and
monitor compliance by the Construction Contractor with the Snagging List and report to the
City Council and the Contractor if any completed works have not, or the Independent
Certifier believes that the completed works have not, been carried out in accordance with the
Project Agreement, and sign off Snagging Items when completed;
21. issue and serve a defects notice on the Contractor specifYing defects where the Works have
not been or are not being carried out in accordance with the Project Agreement at any time;
22. confirm that as-built drawings and relevant operating manuals have been issued to the City
Council; and
23. in addition to the above, the Independent Certifier will ensure that:
23 .I connections to all required utilities have been made and are adequate for safe and
normal operation of the Facility; and
23.2 the requirements of West Yorkshire Constabulary and the Fire Service have been met
and that both organisations have been informed of the programme for the
Commissioning of the Facility.
SJ/ADB/73626/120029/UKM/33410506.23 585
Schedule 30 -Independent Certifier's Deed of Appointment
SCHEDULE4
Contractor Additional Services
The Independent Certifier shall, for the purposes of the Construction Contract only:
I. fulfil the role of the Independent Certifier as described in the Construction Contract m
accordance with all the provisions of this Deed;
2. familiarise itself with and acquire a good understanding of:
2.1 the relevant provisions of the Construction Contract (including the Purchaser's Requirements
(as defined in the Construction Contract) and the Basic Design Proposal (as defined in the
Construction Contract) and the relevant aspects of the Construction Contract (both expressed
and implied) to the extent necessary to be in a position to carry out the Contractor Additional
Services in accordance with this Deed; and
2.2 the relevant variations in relation to the Facility (as defmed in the Construction Contract)
implemented pursuant to the Construction Contract including their effect on the Purchaser's
Requirements (as defined in the Construction Contract) and the Basic Design Proposal (as
defined in the Construction Contract) to the extent necessary to be in a position to carry out
the Contractor Additional Services in accordance with this Deed;
3. Not used
4. Not used
5. observe and witness the EPC Readiness Tests and/or EPC Acceptance Tests and review all
results and data resulting from all such tests. Having reviewed such results and data, the
Independent Certifier shall advise [the Contractor and] the Construction Contractor of which
tests have been passed and which have been failed;
6. within the period of two (2) Business Days of the Independent Certifier's receipt of a notice
from the Construction Contractor stating that the Construction Contractor considers that the
EPC Readiness Tests and/or EPC Acceptance Tests have been passed, each by reference to
the standards required in schedule 11 (Tests) to the Construction Contract, the Independent
Certifier will either:
6.1 issue the EPC Readiness Test Certificate and/or EPC Acceptance Test Certificate (as the case
may be); or
SJ/ AD B/73626/120029/UKM/3341 0506.23 586
Schedule 30 - Independent Certifier's Deed of Appointment
6.2 notifY the Contractor and the Construction Contractor that it considers that the EPC Readiness
Tests and/or the EPC Acceptance Tests have not been passed, by reference to the standards
required by schedule II (Tests) to the Construction Contract, together with a report setting
out the respects in which it considers that the same has not been so passed;
7. in determining whether to issue the EPC Readiness Test Certificate and/or EPC Acceptance
Test Certificate (as the case may be) the Independent Certifier shall only have regard to
whether the EPC Readiness Tests and/or EPC Acceptance Tests (as the case may be) have
been passed by reference to the standards required in schedule II (Tests) and the Construction
Contract and shall not have regard to any other matter, including but not limited to those other
matters for which the Independent Certifier may be responsible in accordance with this Deed;
and
8. provide a copy of such certificate simultaneously upon its issue by the Independent Certifier
to the Contractor and the Construction Contractor.
9. collate, produce and issue a snagging list in accordance with the Construction Contract for
issue with the Acceptance Certificate and monitor compliance by the Construction Contractor
with the snagging list and report to the Contractor if any completed works have not, or the
Independent Certifier believes that the completed works have not, been carried out m
accordance with the Construction Contract, and sign off snagging items when completed;
SJ/ AD B/73 626/120029/UKM/3341 05 06.23 587
Schedule 30 - Independent Certifier's Deed of Appointment
APPENDIX 1- COLLATERAL WARRANTY TO THE CONSTRUCTION CONTRACTOR
SJI ADB/73626/120029/UKM/3341 0506.23 588
Schedule 30 - Independent Certifier's Deed of Appoin1ment
THIS DEED is made on 2012
BETWEEN
(I) [EPC CONTRACTOR] ("EPC Contractor"); and
(2) [INDEPENDENT CERTIFIER] (registered number • ) of
+ ("Independent Certifier").
BACKGROUND
(A) By an agreement dated ("Agreement") Leeds City Council ("Council") has appointed
Veolia ES Leeds Limited ("Contractor") to carry out the design and construction of certain
works in relation to the provision of waste management facilities including the design and
construction and the commissioning and testing of an energy from waste plant, to be
constructed at a site at Pontefract Lane, Leeds ("Project").
(B) By an agreement dated + ("EPC Contract") the Contractor has subcontracted
the part of the Project to the EPC Contractor ("Works").
(C) The Independent Certifier has been appointed by the Contractor and the Council under a deed
of appointment dated + ("Appointment") to provide services in relation to the
Project and in addition, the Contractor has requested that the Independent Certifier undertake
a number of Contractor Additional Services (as defined in the Appoin1ment) in relation to the
Works, these Additional Services for the purpose of this deed shall mean the "Services".
(D) The Independent Certifier is obliged under the Appointment to give a warranty in this form in
favour of the EPC Contractor.
JT IS AGREED:
In consideration of the payment of £10 by the EPC Contractor to the Independent Certifier, receipt of
which the Independent Certifier acknowledges:
1. INDEPENDENT CERTIFIER'S WARRANTY AND LIABILITY
1.1 The h1dependent Certifier warrants to the EPC Contractor that it has carried out and
will continue to carry out the Services in accordance with the Appointment and that it
has exercised and will continue to exercise in the performance of those Services the
SJ/ AD B/73626/120029/UKM/3341 05 06.23 589
Schedule 30 -Independent Certifier's Deed of Appointment
reasonable skill care and diligence to be expected of a properly qualified member of
its profession experienced in carrying out services such as the Services in relation to
works of similar scope, nature and complexity to the Works and has and will act
impartially and independently in undertaking the Services.
1.2 Subject to clauses 1.3 and 1.4 the Independent Certifier has no liability hereunder
which is greater or of longer duration than it would have had if the EPC Contractor
had been a party to the Appointment as joint employer provided that the Independent
Certifier shall not be entitled to set-off or deduct from any sums payable to the EPC
Contractor under this Deed any sums due or claimed as due by the Independent
Certifier from the Contractor under the Appointment. Upon the expiration of 12
years from the date of completion of the Services the liability of the Independent
Certifier under this Deed shall cease and detennine, save in relation to any claims
made by the EPC Contractor against the Independent Certifier and notified by the
EPC Contractor to the Independent Certifier in writing prior thereto.
1.3 The Independent Certifier acknowledges it has received a copy of and is familiar with
the tenus of the EPC Contract including the terms and extent of any damages
liquidated or otherwise which may become payable in the event of any delay in the
issue of any certificate required to be issued by the Independent Certifier pursuant to
the Appointment and recognise that such payment of such damages may be a direct
and foreseeable result of any failure of the h1dependent Certifier to issue certificates
in breach of the Appointment.
1.4 The Independent Certifier shall perform its duties under the Appointment in such
manner and at such time so that no act, omission or default by the Independent
Certifier within the exercise of the duty of care in clause 1.1 shall cause the EPC
Contractor to be in material breach of the EPC Contract or to otherwise give rise to a
claim against or reduce any entitlement of the EPC Contractor. The Independent
Certifier agrees that in any claim by the EPC Contractor in reliance on this deed it
will not raise by way of defence or otherwise that the EPC Contractor has not
suffered and could not suffer any loss under the Appointment.
2. INSURANCE AND LIMITATION OF LIABILITY
2.1 The Independent Certifier shall take out and maintain Professional Indemnity
Insurance with a limit of indemnity of not less than £10,000,000 on an each and every
SJ/ ADB/73626/120029/UKM/3341 0506.23 590
Schedule 30 -Independent Certifier's Deed of Appointment
claim basis from the date of this Deed and for a period expiring no earlier than 12
years from the date of the completion of the Independent Certifier's duties under the
Appointment.
2.2 The Independent Certifier shall maintain such Professional Indemnity Insurance with
reputable insurers carrying on business in the European Union provided that such
insurance continues to be available in the market upon reasonable terms and at
commercially reasonable rates.
2.3 Any increased or additional premium required by insurers by reason of the
Independent Certifier's own claims record or other acts or omissions particular to the
Independent Certifier shall be deemed to be within commercially reasonable rates.
2.4 As and when it is reasonably required to do so, the h1dependent Certifier must
produce to the EPC Contractor for inspection copies of the insurance policy and any
other relevant documents which are required under the insurance policy, as well as
proof that the relevant premium has been paid, and that the relevant policy remains in
full force and effect.
2.5 The Independent Certifier must forthwith notifY the EPC Contractor if the insurance
required to be maintained by it under clause 2.1 ceases to be available upon
reasonable terms and at commercially reasonable rates or if, for any other reason, the
Independent Certifier is unable to continue to maintain such insurance but, unless the
parties agree an alternative way of protecting their respective interests, must continue
to maintain insurance upon such terms and with such a limit of indemnity as may then
be so available and reasonable for the Independent Certifier to maintain.
2.6 The h1dependent Certifier must not compromise, settle or waive any claim which it
may have under such insurance in respect of any professional liability which it may
incur under this Deed and/or the Appointment without the prior written consent of the
EPC Contractor, provided that nothing in this clause 2.6 precludes the Independent
Certifier's insurers from taking over (in the name of the Independent Certifier) the
defence of any claim made by the EPC Contractor under this Deed and from
conducting and settling the same as they see fit. h1 this event the Independent
Certifier must keep the EPC Contractor informed of the progress of any claim in
excess of£10,000.
SJ/ AD B/73 626/120029/UKM/3341 0506. 23 591
Schedule 30- Independent Certifier's Deed of Appointment
3. LIABILITY OF PARTNERS
Where the Independent Certifier is a partnership, references in this Deed to "the Independent
Certifier" will be deemed to include reference to each and every present and future partner of
such partnership and the liability of each and every such partner under this Deed will be
deemed to be joint and several.
4. NOTICES
4.1 Any notice or other communication given in connection with or required by this Deed
shall be made in writing and sent by hand, by facsimile transmission or by first class
pre-paid post to the relevant address or facsimile number set out below or to such
other address or facsimile number as a party may notifY the others in writing by not
less than + Business Days' (as that term is defined in the Agreement)
prior notice.
EPC Contractor
Address: +
Fax: +
Attention: +
Independent Certifier
Address: +
Fax: +
Attention: +
4.2 Subject to clause 4.3:
4.2.1 any notice sent by hand will be deemed to be received on the date of delivery
when left at the proper address for service;
4.2.2 any notice sent by facsimile transmission will be deemed to be received in
full on the day of transmission provided that a confirmatory copy is, on the
same day that the facsimile is transmitted, sent by first class pre-paid post the
manner provided for in clause 4.1;
SJ/ ADB/73626/120029/UKM/3341 0506.23 592
Schedule 30 - Independent Certifier's Deed of Appointment
4.2.3 any notice sent by first class prepaid post will be deemed to have been
received on the second Business Day after the time of posting.
4.3 A notice or other communication received on a day which is not a Business Day or
after 4.00pm on any Business Day is deemed to be received at I O.OOam on the next
following Business Day.
5. ASSIGNMENT
The Independent Certifier shall not assign, transfer or sub-contract the benefits or obligations
of this Deed or any part thereof without the prior written consent of the EPC Contractor, such
consent not to be unreasonably withheld or delayed. The benefit of and the rights on the part
of the EPC Contractor under this Deed may be assigned without the consent of the
Independent Certifier only if the EPC Contract is assigned in accordance with its own terms.
6. EPC CONTRACTOR'S REMEDIES
The rights and benefits conferred upon the EPC Contractor by this Deed are in addition to any
other rights and remedies it may have against the Independent Certifier including without
prejudice to the generality ofthe foregoing any remedies in negligence.
7. INSPECTION OF DOCUMENTS
The Independent Certifier's liabilities under this Deed will not be in any way reduced or
extinguished by reason of any inspection or approval of the Documents or attendance at site
meetings or other enquiry or inspection which the EPC Contractor may make or procure to be
made for its benefit or on its behalf.
8. APPLICABLE LAW AND JURISDICTION
This Deed and all and any obligations contractnal or otherwise arising out of or in connection
with it will be construed in accordance with English law and be in all respects subject to the
exclusive jurisdiction of the English courts.
9. THIRDPARTYRIGHTS
This Deed is enforceable by the original parties to it and by their successors in title and
pennitted assignees. Any rights of any person to enforce the terms of this Deed pursuant to
the Agreements (Rigbts of Third Parties) Act 1999 are excluded.
SJ I ADB/73626/120029/UKM/3 341 05 06.23 593
Schedule 3 0 - fudependent Certifier's Deed of Appointment
IN WITNESS whereof the parties have executed this appointment as a deed on the day and year first
before written.
SJ/ADB/73626/120029/UKM/33410506.23 594
Schedule 30 - Independent Certifier's Deed of Appointment
The Common Seal of LEEDS CITY ) COUNCIL was hereby affixed in the presence ) of: )
Witness signature
Witness name (block capitals)
Witness address
Executed as a deed by VEOLIA ES LEEDS LIMITED acting by two of its directors or a director and its secretary:
Executed as a deed by [INDEPENDENT CERTIFIER] acting by two of its directors or a director and its secretary:
SJ/ ADB/73626/120029/UKM/3341 0506.23
) ) )
) ) )
Signature
Name (block capitals)
Director
Signature ________________________________ _
Name (block capitals) --------------------------------Director
Signature ________________________________ _
Name (block capitals) ·--------------------------------[Secretaryi]Director
Signature . _______________________________ _
Name (block capitals) --------------------------------Director
Signature ________________________________ _
Name (block capitals) ·--------------------------------[Secretaryi]Director
595
Schedule 31 -Site Plans
SCHF.DULF. 31
Site Plans
........
SJ/ AlJB/7~626! 12UU29fUKl'vL'.B41 0506.23 596
e
SJ/ AD B/7362 6/120029/UKM/3341 0 506.23
Schedule 32 -Currency Hedging Profile
SCHEDULE32
597