Scheduling / Project Management Scheduling / Project Management System (SPMS) System (SPMS)

Indiana Department of Transportationand

Info Tech, Inc.

Page 2: Scheduling / Project Management Scheduling / Project

SPMS Project GoalsSPMS Project Goals

l Develop a full lifecycle Project Management Information Systemdriven off a centralized, enterprise-level database

l Improve the project scheduling and planning activities of a transportation agency from project concept (pre-proposal) to project closure (open to traffic), including support for historical analyses

l Complement the existing functionality of Trns•port CES, PES, LAS, CAS, DSS, and SiteManager using the same multi-tier, client/server technology and guidelines accepted by AASHTO

l Interface with other agency systems to create a fully integratedEnterprise System including Geographical Information, Right-of-Way, and off-the-shelf Project Tools

Page 3: Scheduling / Project Management Scheduling / Project

Status of SPMS DevelopmentStatus of SPMS Development

l SPMS 1.0a in production at Indiana DOT since October 2000

l Proposal to integrate SPMS with Trns•port accepted by AASHTO and pending solicitation of funds

l SPMS 2.0a is going into production at Indiana DOT this month, September 2002

l Interested agencies may implement and license SPMS prior to availability of ‘genericized’ Trns•port version – Installation, training, and customization fees will vary according to

each agency’s specific requirements

Page 4: Scheduling / Project Management Scheduling / Project

SPMS ComponentsSPMS Components

Page 5: Scheduling / Project Management Scheduling / Project

SPMS Core FunctionalitySPMS Core Functionality

l Project Management

l Project Scheduling

l Project Estimate/Cost Analysis

l Organization Management

l Program Information

Page 6: Scheduling / Project Management Scheduling / Project

Project Management Project Management

l General information (location, key dates, federal,

division and district data)

l Status information (from concept of a project

through post construction)

l National Bridge Inventory (NBI)

l State route inventory data

l Coordination of Utility, Railroad, and Vendor

activities

l Ability to group and associate projects

Page 7: Scheduling / Project Management Scheduling / Project

Project Scheduling Project Scheduling

l Based on schedule templates for different types of

projects

l Tracks activity and sub-activity dates, durations,

resources, logs, status

l Allows activity level security

l Predecessor and successor relationship

adjustment

l Critical path calculations

Page 8: Scheduling / Project Management Scheduling / Project

Project Estimate/Cost Analysis Project Estimate/Cost Analysis

l Tracks Cost Estimates – Throughout estimation stages (e.g., design, environmental

assessment)

– Throughout project phases (e.g., ROW, utility, construction)

l Tracks Funding– by funding program and amount

– by fiscal year

– by funding priority and associated appropriation codes

l Tracks Actual Costs – voucher/purchase orders

– direct expenditures

Page 9: Scheduling / Project Management Scheduling / Project

Organization ManagementOrganization Management

l Resource Pool for Project and Activity

assignments

– e.g., Consultants, Utility Companies, Government

Agencies

l Information on a position basis

– e.g., name, title, primary address, contact numbers,

and position

Page 10: Scheduling / Project Management Scheduling / Project

Program InformationProgram Information

l Maintains Funding Programs by– Federal

– State

– Local

– Joint

l Maintains Funding Amounts by – Fiscal Year

– Program

– Appropriation Code

Page 11: Scheduling / Project Management Scheduling / Project

SPMS 2.0a EnhancementsSPMS 2.0a Enhancements

l New Functionality– Enhanced Scheduling and Management

– Permit Tracking

– One-Way Interface to Trns•port CES

– Batch Job Processing

l Trns•port Architectural Components– Report Template Facility (RTF) and Customizable Reports

– OLE/COM Interface Infrastructure for future Microsoft Project Interface

– Distributed Processing Services (DPS) and Batch Processing

Page 12: Scheduling / Project Management Scheduling / Project

Technical SpecificationsTechnical Specifications

l Object-oriented, client/server application using a

multi-tier architecture

l Currently installed at INDOT using:

– Oracle 8i database server

– Windows 2000 application server

– Windows 95/98/NT/2000 client operating systems

Page 13: Scheduling / Project Management Scheduling / Project

Future Development GoalsFuture Development Goals

l Complete the Trns•port Integration

l Fully genericize for Multi-State Use

l Interface with commercial project scheduling tools– Microsoft Project

– Primavera

– Etc.

l Add Geographic Information System (GIS) interface – ESRI Arc*

l Add Web-based functions

Page 14: Scheduling / Project Management Scheduling / Project

SPMS 2.0a DemonstrationSPMS 2.0a Demonstration

Software Demonstration

Page 15: Scheduling / Project Management Scheduling / Project

SPMS ContactsSPMS Contacts

Teresa Franklin, Info [email protected]