scheme update newport city council · a48 sdr from the m4 eastbound off-slip and cleppa park and...

11
Scheme Update Newport City Council 30/1/17

Upload: lythuy

Post on 24-Apr-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Scheme Update Newport City Council · A48 SDR from the M4 eastbound off-slip and Cleppa Park and elongation of the roundabout with additional traffic lanes and signals

Scheme Update – Newport City

Council

30/1/17

Page 2: Scheme Update Newport City Council · A48 SDR from the M4 eastbound off-slip and Cleppa Park and elongation of the roundabout with additional traffic lanes and signals

Team

• Welsh Government – Mark Dixon (Project Engineer)

– Andy Falleyn (Director)

• Costain – Tom Kenyon (Project Manager)

– Brian Greaves (PLO)

– Hannah Lewis (PLO)

• WSP|PB – Ian Morris (Project Manager)

– Rob Davies (Project Engineer)

• Arup – Richard Sanders (Project Manager)

– Simon Westwood (Design Engineer)

– Simon Westwood (Traffic Engineer)

Page 3: Scheme Update Newport City Council · A48 SDR from the M4 eastbound off-slip and Cleppa Park and elongation of the roundabout with additional traffic lanes and signals

Scheme Background• Existing Issues

• The junctions are operating at the limit of their capacity…

• …and at times there is blocking back of queues between junctions

which leads to long delays and gridlock.

• … and the local road network is difficult for pedestrians and

cyclists to navigate.

• Scheme Objectives

• Provide increased capacity improvements.

• Alleviate congestion throughout key junctions.

• Improve facilities for NMUs.

• Enhance road safety at junctions.

• Minimise adverse impact on the environment.

Page 4: Scheme Update Newport City Council · A48 SDR from the M4 eastbound off-slip and Cleppa Park and elongation of the roundabout with additional traffic lanes and signals

M4 Jct 28 Scheme Overview

Pont Ebbw Roundabout

J28 Roundabout

Bassaleg Roundabout

Page 5: Scheme Update Newport City Council · A48 SDR from the M4 eastbound off-slip and Cleppa Park and elongation of the roundabout with additional traffic lanes and signals

Scheme Development

• Design

• Traffic & Ground Investigation surveys

• Modelling of junctions with traffic simulations

• Environmental and ecological surveys

• Geotechnical design

• Highway alignment

• Detailed design

• Geometry

• Drainage

• Traffic signals

• Signs, VRS etc….

Page 6: Scheme Update Newport City Council · A48 SDR from the M4 eastbound off-slip and Cleppa Park and elongation of the roundabout with additional traffic lanes and signals

Consultations during Design

Environmental Process:

• Natural Resources Wales

• CADW

• Newport City Council Officers

Design and Construction (Including temporary traffic regulation orders):

• Newport City Council Officers

• Morgan Vinci

• Sustrans

• SWTRA

• Gwent Police

• Junction 28 Forum (Including Office of National Statistics, International

Rectifier, Go Compare, Intellectual Property Office)

• Bus Operators (Cardiff Bus, New Adventure Travel,

Stagecoach)

• Bassaleg School

Page 7: Scheme Update Newport City Council · A48 SDR from the M4 eastbound off-slip and Cleppa Park and elongation of the roundabout with additional traffic lanes and signals

Bassaleg - Benefits

• Improved junction capacity with road

widening on the A467 Forge Road,

A468 Forge Road and on the

roundabout.

• Junction is now signalised allowing

smoother traffic movements by

providing balanced traffic flows

between the routes.

• Enhanced NMU facilities with

signalised pedestrian crossing on the

A467 Forge Road.

• New LED street lighting.

• New surfacing.

A467 North

Phase 1Phase 2Phase 3Phase 3 Cont.Phase 4Phase 5Final

Layout

Page 8: Scheme Update Newport City Council · A48 SDR from the M4 eastbound off-slip and Cleppa Park and elongation of the roundabout with additional traffic lanes and signals

M4 J28 - Benefits• Improved junction capacity including

widening on the M4 eastbound off-

slip, new dedicated through road to

A48 SDR from the M4 eastbound off-

slip and Cleppa Park and elongation

of the roundabout with additional

traffic lanes and signals.

• Supplementary traffic islands to

separate flows, increasing capacity

and improving safety.

• New traffic signals for the A48 Cardiff

Road from Newport to help balance

the flows.

• Enhanced NMU facilities with new

signalised crossing points.

• New LED street lighting.

• New surfacing.

M4 West

M4

East

A48

Newport

Phase 1Phase 1 Cont.Phase 2Phase 3Phase 4Phase 5Phase 5

(Traffic Signal

Commissioning)

Phase 6

(Cont.)Phase 6Final

Layout

Page 9: Scheme Update Newport City Council · A48 SDR from the M4 eastbound off-slip and Cleppa Park and elongation of the roundabout with additional traffic lanes and signals

Phase 1 & 2

Pont Ebbw - Benefits

• Improved junction capacity with

new though-links for the A48 SDR

and road widening on A48

eastbound approach to the

junction.

• Additional lanes on the

roundabout to provide extra

capacity.

• Supplementary traffic islands

have been provided to separate

flows, increasing capacity and

improving safety.

• Full time signal control allowing

smoother traffic movements.

• New LED street lighting.

• New surfacing.

A48

West

ONS/IPO/IR

Duffryn Drive

Phase 3Phase 4Phase 5Phase 6Final

Layout

Page 10: Scheme Update Newport City Council · A48 SDR from the M4 eastbound off-slip and Cleppa Park and elongation of the roundabout with additional traffic lanes and signals

Visualisation now and afterPresent-day: blocking

back between junctions

Future scenario:

Congestion minimised with

increased capacity and

more traffic management

(with full signal control)

Page 11: Scheme Update Newport City Council · A48 SDR from the M4 eastbound off-slip and Cleppa Park and elongation of the roundabout with additional traffic lanes and signals

What happens next…..

• Seek Ministerial Approval.

• Commence mobilisation and start construction works

from Feb 2017.

• 16 months construction programme.

• Bassaleg & Tredegar start first.

• Pont Ebbw works commence upon completion of

Bassaleg around October 2017.