Scheme Update – Newport City
Council
30/1/17
Team
• Welsh Government – Mark Dixon (Project Engineer)
– Andy Falleyn (Director)
• Costain – Tom Kenyon (Project Manager)
– Brian Greaves (PLO)
– Hannah Lewis (PLO)
• WSP|PB – Ian Morris (Project Manager)
– Rob Davies (Project Engineer)
• Arup – Richard Sanders (Project Manager)
– Simon Westwood (Design Engineer)
– Simon Westwood (Traffic Engineer)
Scheme Background• Existing Issues
• The junctions are operating at the limit of their capacity…
• …and at times there is blocking back of queues between junctions
which leads to long delays and gridlock.
• … and the local road network is difficult for pedestrians and
cyclists to navigate.
• Scheme Objectives
• Provide increased capacity improvements.
• Alleviate congestion throughout key junctions.
• Improve facilities for NMUs.
• Enhance road safety at junctions.
• Minimise adverse impact on the environment.
M4 Jct 28 Scheme Overview
Pont Ebbw Roundabout
J28 Roundabout
Bassaleg Roundabout
Scheme Development
• Design
• Traffic & Ground Investigation surveys
• Modelling of junctions with traffic simulations
• Environmental and ecological surveys
• Geotechnical design
• Highway alignment
• Detailed design
• Geometry
• Drainage
• Traffic signals
• Signs, VRS etc….
Consultations during Design
Environmental Process:
• Natural Resources Wales
• CADW
• Newport City Council Officers
Design and Construction (Including temporary traffic regulation orders):
• Newport City Council Officers
• Morgan Vinci
• Sustrans
• SWTRA
• Gwent Police
• Junction 28 Forum (Including Office of National Statistics, International
Rectifier, Go Compare, Intellectual Property Office)
• Bus Operators (Cardiff Bus, New Adventure Travel,
Stagecoach)
• Bassaleg School
Bassaleg - Benefits
• Improved junction capacity with road
widening on the A467 Forge Road,
A468 Forge Road and on the
roundabout.
• Junction is now signalised allowing
smoother traffic movements by
providing balanced traffic flows
between the routes.
• Enhanced NMU facilities with
signalised pedestrian crossing on the
A467 Forge Road.
• New LED street lighting.
• New surfacing.
A467 North
Phase 1Phase 2Phase 3Phase 3 Cont.Phase 4Phase 5Final
Layout
M4 J28 - Benefits• Improved junction capacity including
widening on the M4 eastbound off-
slip, new dedicated through road to
A48 SDR from the M4 eastbound off-
slip and Cleppa Park and elongation
of the roundabout with additional
traffic lanes and signals.
• Supplementary traffic islands to
separate flows, increasing capacity
and improving safety.
• New traffic signals for the A48 Cardiff
Road from Newport to help balance
the flows.
• Enhanced NMU facilities with new
signalised crossing points.
• New LED street lighting.
• New surfacing.
M4 West
M4
East
A48
Newport
Phase 1Phase 1 Cont.Phase 2Phase 3Phase 4Phase 5Phase 5
(Traffic Signal
Commissioning)
Phase 6
(Cont.)Phase 6Final
Layout
Phase 1 & 2
Pont Ebbw - Benefits
• Improved junction capacity with
new though-links for the A48 SDR
and road widening on A48
eastbound approach to the
junction.
• Additional lanes on the
roundabout to provide extra
capacity.
• Supplementary traffic islands
have been provided to separate
flows, increasing capacity and
improving safety.
• Full time signal control allowing
smoother traffic movements.
• New LED street lighting.
• New surfacing.
A48
West
ONS/IPO/IR
Duffryn Drive
Phase 3Phase 4Phase 5Phase 6Final
Layout
Visualisation now and afterPresent-day: blocking
back between junctions
Future scenario:
Congestion minimised with
increased capacity and
more traffic management
(with full signal control)
What happens next…..
• Seek Ministerial Approval.
• Commence mobilisation and start construction works
from Feb 2017.
• 16 months construction programme.
• Bassaleg & Tredegar start first.
• Pont Ebbw works commence upon completion of
Bassaleg around October 2017.