school of electrical and computer engineering addis ababa ... · school of electrical and computer...
TRANSCRIPT
22-Sep-14
1
1
Addis Ababa Institute of Technology
School of Electrical and Computer Engineering
Addis Ababa University
Chapter - Six
Electrical Construction and Documentation
2
Addis Ababa Institute of Technology
School of Electrical and Computer Engineering
Addis Ababa University
An engineering project in which electrical installation works include
may be residential, public , commercial buildings; entertainment
complexes; industries, etc.
Electrical Contracting Works
In such projects, generally the following sub-works are involved:
i. Architectural work
ii. Structural and building works
iii. Sanitation work
iv. Electrical installation work
v. Data, telephone, access control system, fire alarm & security system,
vi. Lift/escalator systems
vii. MATV [Master Antenna Television System] and PAS [ Public announcer
system ] system
viii.HVAC system
ix. Building Management Systems (BMS)
22-Sep-14
2
3
Addis Ababa Institute of Technology
School of Electrical and Computer Engineering
Addis Ababa University
Contracting parties
In an engineering project of the above type at least three
main parties are involved, viz.,
� The client
� The consultant, and
� The contractor
4
Addis Ababa Institute of Technology
School of Electrical and Computer Engineering
Addis Ababa University
The client
� The client is generally the owner of a project for which much no.
of the above sub works may be involved.
� The client may be an individual, a business firm/company, an NGO
or a public/ govt entity
22-Sep-14
3
5
Addis Ababa Institute of Technology
School of Electrical and Computer Engineering
Addis Ababa University
The consultant
� The consultant is a firm of qualified and experienced team of
various professionals (architects, civil, electrical, computer etc
engineers )
� The team may be under one license or a consortium of licensed
professionals
The consultant’s main functions are:
� to design one or more of the above sub works for the client
� to supervise & inspect the correct implementation of the
design on behalf of the client until commissioned.
� Serves as the coordinators of the whole or sub-work
Since it is usually difficult to hire and maintain professionals of all
spectrum, the consultant may out source some of the works to sub
contractor/s
6
Addis Ababa Institute of Technology
School of Electrical and Computer Engineering
Addis Ababa University
The contractor
� The contractor is a firm that may be owned by a lay or professional
business man/woman but consisting of :
� sufficient number of qualified , skilled engineers and technicians
� sufficient construction facilities and equipment
� sufficient financial capital
� The main function of the contractor is to implement each of the
above construction/installation designs in the project according to
the design & supervision provided by the consultant
� For the service it rendered, the contractor is paid by the client.
� The contractor, like the consultant, may out source some of its
duties to sub contractor/s.
22-Sep-14
4
7
Addis Ababa Institute of Technology
School of Electrical and Computer Engineering
Addis Ababa University
Typical construction work flow1. A client/owner wants electrical installation construction done 1. A client/owner wants electrical installation construction done 1. A client/owner wants electrical installation construction done 1. A client/owner wants electrical installation construction done
�The client will have prepared a tender document using own
expert or external consultant
� In either case, an installation engineer (an expert of the client or
an employee of the consultant) participates in the preparation of
the tender document especially in specifying the design work.
�The tender is floated for design companies to compete
2. Consultant/Design companies bid to win the design work.2. Consultant/Design companies bid to win the design work.2. Consultant/Design companies bid to win the design work.2. Consultant/Design companies bid to win the design work.
� Installation engineer prepares tender document “offers and
considerations” to the specified design.
3. Winning consultant company prepares the design3. Winning consultant company prepares the design3. Winning consultant company prepares the design3. Winning consultant company prepares the design
�A contract is signed b/n the client and the design consultant
� Installation engineer designs the electrical installation for the
construction as the employee of the consultant or a consultant.
8
Addis Ababa Institute of Technology
School of Electrical and Computer Engineering
Addis Ababa University
Typical construction work flow… (contd)4444.... TheTheTheThe client/ownerclient/ownerclient/ownerclient/owner preparespreparespreparesprepares bid/tenderbid/tenderbid/tenderbid/tender forforforfor constructionconstructionconstructionconstruction basedbasedbasedbased onononon thethethethe
designdesigndesigndesign drawingsdrawingsdrawingsdrawings andandandand specificationspecificationspecificationspecification ofofofof thethethethe constructionconstructionconstructionconstruction
� Installation engineer participates in preparation of tender
document especially in specifying the construction or installation
work
� The installation engineer does this as an employee of the client
or consultant
5555.... Contractor/ConstructionContractor/ConstructionContractor/ConstructionContractor/Construction CompaniesCompaniesCompaniesCompanies bidbidbidbid totototo winwinwinwin thethethethe constructionconstructionconstructionconstruction
workworkworkwork
� Installation engineer participates in estimation of material and
labour cost of the construction and prepares tender document
“offer and condition” in response to the design document.
� The installation engineer does this as an employee of a
contractor or a self competent contractor
22-Sep-14
5
9
Addis Ababa Institute of Technology
School of Electrical and Computer Engineering
Addis Ababa University
Typical construction work flow
6 Awarded contractor/construction company takes up the 6 Awarded contractor/construction company takes up the 6 Awarded contractor/construction company takes up the 6 Awarded contractor/construction company takes up the
constructionconstructionconstructionconstruction
� A contract is signed b/n the client/owner and the awarded
contractor
� Installation engineer prepares shop/layout drawing, specifies
materials, gets approval of the consultant, participates or
supervises wiring work to be done according to design and
applicable regulations
� The installation engineer does the supervision and wiring works in
coordination with other disciplinary works such as structural,
sanitary, HVAC, data-telecom, MATV, etc
10
Addis Ababa Institute of Technology
School of Electrical and Computer Engineering
Addis Ababa University
Typical construction work flow
� The installation engineer produces as-built drawings for
documentation purpose that account alterations and
modifications of original drawings
� The installation engineer does this as a contractor, employee of
the contractor, or as counterpart for the owner.
22-Sep-14
6
11
Addis Ababa Institute of Technology
School of Electrical and Computer Engineering
Addis Ababa University
Typical construction work flow
7. The construction is tested and commissioned and handed over for 7. The construction is tested and commissioned and handed over for 7. The construction is tested and commissioned and handed over for 7. The construction is tested and commissioned and handed over for
operation.operation.operation.operation.
� Electrical Engineer with necessary licence participates in testing
and commissioning as representative engineer for the owner,
representative for the contractor, licensed inspection engineer,
etc.
8. Inspection and commissioning done and document prepared by 8. Inspection and commissioning done and document prepared by 8. Inspection and commissioning done and document prepared by 8. Inspection and commissioning done and document prepared by
licensed entity.licensed entity.licensed entity.licensed entity.
� Participate in commissioning document preparation and
signature.
12
Addis Ababa Institute of Technology
School of Electrical and Computer Engineering
Addis Ababa University
Expectations from Electrical engineers in installation work
�Electrical engineers participate in the construction work as
contractors, subcontractors, employees of contractors, employees of
the owner of the construction, or as consultants.
� In all cases electrical engineers are faced with preparing essential
documents in addition to the design and construction engineering
work they are usually ready for.
� In addition to the engineering knowledge they have, electrical
engineers need legal and writing skills which are usually obtained
through experience and use of proper references.
�As an example of a contract document we will discuss here about a
construction work based on the design and additional specifications
22-Sep-14
7
13
Addis Ababa Institute of Technology
School of Electrical and Computer Engineering
Addis Ababa University
Contract
� A contract is an agreement in the form of written text as well as
drawings among partakers of a project
� The content of the contract includes
� The qualitative, technical and material specifications of the project
� Methodologies of carrying out the project etc
� The duties and responsibilities of the client, the consultant and
contractor
� The contract serves :
� To correctly and smoothly implement each of the project sub
works
� To resolve any probable disputes
14
Addis Ababa Institute of Technology
School of Electrical and Computer Engineering
Addis Ababa University
Contract
� The contract document is prepared by own/external experts
entrusted by the client
� Contracts are signed between agreeing parties
The following are usually considered parts of the contract:
� The bid/tender document
� Design drawings
� Offered documents in response to bid
A project contract is usually managed/coordinated by the architect
22-Sep-14
8
15
Addis Ababa Institute of Technology
School of Electrical and Computer Engineering
Addis Ababa University
Contract document: Electrical Construction Specification
General Provision (Typical)General Provision (Typical)General Provision (Typical)General Provision (Typical)
1. Portions of the sections of the documents in the other part of the
work (civil, mechanical, etc.) under “General Requirements” apply to
this too.
2. Refer to index to be certain that set of documents and specifications
is complete. Report omissions or discrepancies to the architect.
3. Scope of the work
16
Addis Ababa Institute of Technology
School of Electrical and Computer Engineering
Addis Ababa University
The scope of the work consists of
� furnishing and installing of complete electrical system exterior and
interior –including miscellaneous systems.
� The electrical contractor shall provide all supervision, labor,
materials, equipment, machinery, and any and all other items
necessary to complete the systems.
� The electrical contractor shall note that all items of equipments are
specified in the singular;
� however, the contractor shall provide and install the number of
items of equipment as indicated on the drawings and as required
for complete systems.
22-Sep-14
9
17
Addis Ababa Institute of Technology
School of Electrical and Computer Engineering
Addis Ababa University
� It is the intention of the specification and drawings to call for
finished work, tested, and ready for operation.
� Any apparatus, appliance, material, or work not shown on the
drawings but mentioned in specification, or vise versa or any
incidental accessories necessary to make the work complete and
perfect in all aspects and ready for operation even if not
particularly specified shall be furnished, delivered and installed by
the contractor without additional expense to the owner.
18
Addis Ababa Institute of Technology
School of Electrical and Computer Engineering
Addis Ababa University
� Minor details not shown or specified but necessary for proper
operation shall be included in the contractor’s estimate the same as if
herein specified or shown.
� With submission of bid the electrical contractor shall give written
notice to the architect of any materials or apparatus believed
inadequate or unsuitable in violation of laws, ordinances, rules and any
necessary items or work omitted.
� In the absence of such written notice it is mutually agreed that the
constructer has included the cost of all required items in this proposal,
and that he will be responsible for the approved satisfactory
functioning of the entire system with out extra compensation.
22-Sep-14
10
19
Addis Ababa Institute of Technology
School of Electrical and Computer Engineering
Addis Ababa University
BoQ of material, labor and cost estimating in an electrical installation work
� Any electrical installation construction work requires quantifyingmaterial cost and labor cost.
� Estimation of these costs helps a client/owner to award an eligiblecontractor as well as secure budget and release a right portion at theright time.
� Determination of these costs helps a contractor to decide to venture ornot on the contract.
� The consultant uses the cost information to monitor the work as wellas deploy the right amount of money at the right time to thecontractor.
� To determine these costs determining the types and extent/quantity ofworks involved is essential.
� Furthermore, probable variation of work, change of currency in time,labor and material cost variations etc should be accounted ascontingency.
20
Addis Ababa Institute of Technology
School of Electrical and Computer Engineering
Addis Ababa University
List of works in an installation include
I. Manual layout of flush (within slab or wall) and/or surface mounted
conduits/raceways and junction boxes for the whole installation
based on the shop drawing version of the installation schematic
drawing.
� This is required for power feeder cables from transformer to MDB,
from MDB to SDBs, from each SDB to SDBs and/or branch circuits,
from branch circuits to outlets and appliances, etc,
� Concrete ducting (for SDB inter connection of branch circuits) and
manhole construction (underground cable running through PVC
conduit) should also be made in consultation with civil
contractors.
� To avoid collisions with water supply and sewerage lines, HVAC
lines etc, consultation should also be made with respective
engineers/technicians ON THE SITE.
22-Sep-14
11
21
Addis Ababa Institute of Technology
School of Electrical and Computer Engineering
Addis Ababa University
List of works in an installation includeIIIIIIII.... FeederFeederFeederFeeder cablecablecablecable runningrunningrunningrunning fromfromfromfrom transformertransformertransformertransformer househousehousehouse totototo MDBMDBMDBMDB
� This involves laying under ground (with PVC or concrete duct) or
overhead mounting on poles of feeder cable from transformer house
after kWh & kVARh meters and isolator switch to MDB in the building
main control room.
� Cable splicing (twisting and/or soldering, insulating, etc) to lengthen
� Cable termination/connection at the transformer house is part of this
work.
IIIIIIIIIIII.... MDBMDBMDBMDB installationinstallationinstallationinstallation
� Mounting the MDB enclosure at the designated site on a wall
(recessed) or in a closet (surface)
� Assembling of entrance isolator switch, bus bars, protective earth,
protective CBs & fuses, etc and terminal interconnections in the MDB
22
Addis Ababa Institute of Technology
School of Electrical and Computer Engineering
Addis Ababa University
List of works in an installation include
IV.IV.IV.IV. FeederFeederFeederFeeder cablecablecablecable runningrunningrunningrunning fromfromfromfrom MDBMDBMDBMDB totototo (isolator(isolator(isolator(isolator switches,switches,switches,switches, ifififif any,any,any,any, of)of)of)of) SDBsSDBsSDBsSDBs
�This involves drawing of feeder cables through flush or surface
mounted PVC conduits, concrete ducts and/or metalic raceways.
�Cable splicing (twisting and/or soldering, insulating, etc) to lengthen
�Cable termination/connection at each SDB is part of the work
V.V.V.V. SDBSDBSDBSDB InstallationsInstallationsInstallationsInstallations
�Mounting each SDB enclosure at the designated site on a wall
(recessed) or in a closet (surface)
�Assembling of isolator switch (if any), CBs, fuses, bus bars, protective
earth, etc and terminal & branch circuit interconnections in each SDB at
the designated site/s on a wall (recessed) or in a closet (surface)
22-Sep-14
12
23
Addis Ababa Institute of Technology
School of Electrical and Computer Engineering
Addis Ababa University
24
Addis Ababa Institute of Technology
School of Electrical and Computer Engineering
Addis Ababa University
List of works in an installation includeVIVIVIVI.... BranchBranchBranchBranch circuitcircuitcircuitcircuit wire/swire/swire/swire/s orororor cablecablecablecable runningrunningrunningrunning
�Branch circuit wires/cables are drawn through conduits (flush) in ducts
or race ways (surface) from each SDB to junction boxes for termination,
tapping etc.
�The cables/conductors are drawn from junction boxes to appliance
outlet (light point, light switch, socket outlet, or appliance)
VIIVIIVIIVII.... InstallationInstallationInstallationInstallation ofofofof receptaclesreceptaclesreceptaclesreceptacles andandandand fixturesfixturesfixturesfixtures
�This involves installation of light switches, lighting fixtures, socket
outlets, etc at designated points on walls and ceilings
VIIIVIIIVIIIVIII.... InstallationInstallationInstallationInstallation ofofofof backupbackupbackupbackup powerpowerpowerpower systemsystemsystemsystem
�This involves installation of diesel generator set, PV system, and/or wind
turbine system/s at a designated site in the premises
�Includes laying of cables from the backup system to the exchange
switch center, interconnection with associated switch gear (ATS or
manual exchange switch) on the MDB
GO
22-Sep-14
13
25
Addis Ababa Institute of Technology
School of Electrical and Computer Engineering
Addis Ababa University
26
Addis Ababa Institute of Technology
School of Electrical and Computer Engineering
Addis Ababa University
List of works in an installation includeXIXIXIXI.... InstallationInstallationInstallationInstallation ofofofof powerpowerpowerpower factorfactorfactorfactor correctioncorrectioncorrectioncorrection systemsystemsystemsystem
� This involves installation of capacitor bank and/or reactor at a
designated position with associated automatic or manual switch gear
XI. Installation of harmonic filters XI. Installation of harmonic filters XI. Installation of harmonic filters XI. Installation of harmonic filters
� at a designated position with associated switch gear
XI.XI.XI.XI. Installation of groundingInstallation of groundingInstallation of groundingInstallation of grounding
� This involves installation of operational grounding and protective
grounding
� Protective grounding may involve neutralization, protective earthing
with/without earth leakage detection and reacting device
� Verification of design parameters on site measurements should be done
XII.XII.XII.XII.Installation of Installation of Installation of Installation of lightening protection system lightening protection system lightening protection system lightening protection system
� for the building and campus premises
XIII.XIII.XIII.XIII.Testing Testing Testing Testing
� of the interconnections considering essential points of test and
appropriate testing procedure
>>
>>
>>
>>
22-Sep-14
14
27
Addis Ababa Institute of Technology
School of Electrical and Computer Engineering
Addis Ababa University
Back
28
Addis Ababa Institute of Technology
School of Electrical and Computer Engineering
Addis Ababa University
Back
22-Sep-14
15
29
Addis Ababa Institute of Technology
School of Electrical and Computer Engineering
Addis Ababa University
Back
30
Addis Ababa Institute of Technology
School of Electrical and Computer Engineering
Addis Ababa University
Back
22-Sep-14
16
31
Addis Ababa Institute of Technology
School of Electrical and Computer Engineering
Addis Ababa University
BOQ of works and materials� In ordinary projects, a contractor supplies only labor while the client
purchases required materials either on a grant or on a bid competitive
basis from suppliers.
�Payment to the contractor is made after completion of a distinct phase
of the project
� In a more autonomous project, both materials and labor are supplied
by the contractor itself.
� In a turn key project, all design, materials and labor are supplied by the
contractor itself.
� In any case, the shop drawing/layout diagram (usually on 2D
AutoCAD floor plan) generated from the schematic/wiring diagram
(and refined on site after award) helps a lot in estimating the BoQ of
materials.
�3D shop drawing/layout diagrams (e.g. using Autocad or CadPIPE)
facilitates even more the determination of BoQ faster and accurate
32
Addis Ababa Institute of Technology
School of Electrical and Computer Engineering
Addis Ababa University
We recall the AutoCAD drawing shows
1) the actual route, number, length, and diameter of conduits in each floor
slab and in wall (and/or in raceways on walls/ceilings) of the building
determined on the basis of the number and size of cables each carries
2) the position, number and sizes of the junction boxes, concrete ducts,
outlets and appliance positions in each floor slab and walls (and/or on
walls/ceilings) of the building
3) The number, type, size and colour of cables/conductors to be run in each
conduit/raceway and connected in each junction box
4) The position of SDBs, MDB and service entrance
5) The position of, if any, transformer, backup power system, switching
system etc in a house/control room
6) The position of earth and lightening protection
22-Sep-14
17
33
Addis Ababa Institute of Technology
School of Electrical and Computer Engineering
Addis Ababa University
Accordingly, from a scaled drawing of the shop drawing, we can
read/count all essential parameters such as length, diameter, number etc of
the installation materials used in the installation work
Conduit/raceway works
�Conduit/raceway layout work includes laying, tying, lengthening,
cutting, bending, etc in slabs, walls, or ducts (flush) or mounting on
walls, ceilings, etc (surface)
� The associated work (labor) as well as the quantity of material is
conveniently rated by linear meter.
� Thus the linear meter serves for quantifying the required
conduit/race way as well as for costing of conduit/raceway layout
work
� The material and labor costs may thus be rated with Birr/linear
meter/mm sq of conduit or raceway
34
Addis Ababa Institute of Technology
School of Electrical and Computer Engineering
Addis Ababa University
Junction box and duct works
� Junction box layout work includes mounting the boxes in slab and in
wall (flush) or on wall and on ceilings (surface), tying it,
conduit/raceway fitting, etc
� The associated work (labor) as well as the quantity of material is
conveniently rated by the count in number, size and type of junction
boxes on each of the floors
� The material and labor costs may thus be rated Birr/junction box/box
size
22-Sep-14
18
35
Addis Ababa Institute of Technology
School of Electrical and Computer Engineering
Addis Ababa University
Sample bill of quantities of electrical installation materials
Sample BOQ!