[scope description and recovery plan] ocean research foundation
TRANSCRIPT
Ocean Research Foundation
Thaisa Fernandes • Mar BlancoScope Description and Recovery Plan
Scope Description
Who is the client?
Ocean Research Foundation. The nonprofit is dedicated to the advancement
of marine conservation.
The primary goals are to support and conduct marine research and
education to enhance stewardship of ocean resources.
Goal
Grow ORF online presence and spread the word in Social Media channels.
Deliverables
Services:
○ Visual identity
○ New Social channels
○ Schedule
○ Communication style
○ Also mentor Social Media content volunteers, providing guidance on
writing style and post schedule.
Assumptions:
○ ORF team is going to support the project and be involved
○ SM channels selected are reliable
○ People are interested and agree with content
Constrains:
○ Budget: 0
○ Volunteer time and engagement
○ Lack of resources
○ Lack of awareness
Not included:
○ Website Design
○ Partnership
○ Publicity & Advertising
○ Volunteer performance
○ Events
Time and Cost:
○ 24 weeks
Start in: 09/21/2015
Finish in: 01/28/2016
○ TOTAL: 1,071 hours
820 volunteer hours
251.70 risk
Project Status
Milestones
○ Plan Approved
○ Approval received
○ Deliver completed project
○ Acceptance, sign-off, :-))
○ Completion
Allocation
Network Diagram
○ The critical activities are 1b, 1e, 1f, 1g, 2a, 2b, 3a, 3b, 3c, 3d, 3e, 3g, 4a, 4b, 5a, 6a○ The total project duration is 24 weeks○ 19 activities
Gantt Chart
○ 24 weeks
Start in: 09/21/2015
Finish in: 01/28/2016
Project Status
○ We have completed 7 weeks and we have 17 weeks left.
○ The project is 2 hours of effort late making the project a week behind the schedule.
○ We have completed 99% of the work expected by that time and the 52% of the project.
○ We already spent 302 and we completed 268 of work, so the project is 12% over budget.
Updated status (activities completed)
Activity Hours completed Hours of effort Extra work Efficiency Completion
1a 16 18 12% 0.88 On time
1b 128 133 3% 0.96 On time
1c 6 8 33% 0.75 On time
1d 10 12 20% 0.83 1 week late
1e 30 35 16% 0.85 1 week late
1f 58 63 9% 0.92 1 week late
Updated status (activities in progress)
○ 1g is affected by 1e and 1f
○ 1g It’s on the critical path so it can delay the project
○ 2a cannot start until 1g finishes
Activity Hours completed
Hours of effort Extra work Efficiency Work left
1g 20 25 25% 0.8 2h
Forecast
If we keep working as so far:
○ Total number of weeks: 27 (3 more than expected)○ We are going to need to deliver 921 hours to complete the project (+101
hours)
Recovery plan
○ Since it is a non-profit, we cannot add more budget.
○ Since it is a volunteer job we can ask them to make an extra effort to finish it earlier or agree to finish later
○ They can hire a new volunteer to help them to finish the project on time.
○ We need to extend it 3 more weeks.
Thank You