scope management by jeffrey k. pinto

34
INSTRUCTOR’S RESOURCE MANUAL CHAPTER FIVE Scope Management To Accompany PROJECT MANAGEMENT: Achieving Competitive Advantage By Jeffrey K. Pinto Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 1

Upload: kennethllantos

Post on 18-Jul-2016

49 views

Category:

Documents


0 download

DESCRIPTION

INSTRUCTOR’S RESOURCE MANUALCHAPTER FIVEScope ManagementTo AccompanyPROJECT MANAGEMENT: Achieving Competitive AdvantageByJeffrey K. Pinto

TRANSCRIPT

INSTRUCTOR’S RESOURCE MANUAL

CHAPTER FIVEScope Management

To Accompany

PROJECT MANAGEMENT: Achieving Competitive Advantage

ByJeffrey K. Pinto

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

1

CHAPTER FIVE

PROJECT PROFILE — Airbus A380: Plane of the Future or Enormous White Elephant?

Introduction

5.1 CONCEPTUAL DEVELOPMENT

The Statement of Work

5.2 THE SCOPE STATEMENT

The Work Breakdown Structure

Purpose of the Work Breakdown Structure

The Organization Breakdown Structure

The Responsibility Assignment Matrix

5.3 WORK AUTHORIZATION

5.4 SCOPE REPORTING

Project Management Research in Brief: IT Project Failure – Burying Our Heads in the

Sand

5.5 CONTROL SYSTEMS

Configuration Management

5.6 PROJECT CLOSEOUT

Summary

Key Terms

Discussion Questions

Problems

Case Study 5.1: Calcutta’s Metro

Case Study 5.2: Project Management at Dotcom.com

Cas Study 5.3: Runaway Scope – The Bradley Fighting Vehicle

Internet Exercises

MSProject Exercises

Integrated Project – Developing the Work Breakdown Structure

Bibliography

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

2

TRANSPARENCIES

5.1 ELEMENTS IN PROJECT SCOPE MANAGEMENT

1. Conceptual Development

- Problem statement

- Information gathering

- Constraints

- Alternative analysis

- Project objectives

- Statement of Work (SOW)

2. Scope Statement

- Goal criteria

- Management plan

- Work Breakdown Structure (WBS)

- Scope baseline

- Responsibility Assignment Matrix (RAM)

3. Work Authorization

- Contractual requirements

- Valid consideration

- Contracted terms

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

3

5.1 ELEMENTS IN PROJECT SCOPE MANAGEMENT

(Con’d)

4. Scope Reporting

- Cost, Schedule, Technical performance status

- S curves

- Earned value

- Variance or exception reports

5. Control Systems

- Configuration control

- Design control

- Trend monitoring

- Document control

- Acquisition control

- Specification control

6. Project Closeout

- Historical records

- Post-project analysis

- Financial closeout

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

4

5.2 PURPOSES OF THE WORK BREAKDOWN STRUCTURE

1. IT ECHOES PROJECT OBJECTIVES.

2. IT IS THE ORGANIZATION CHART FOR THE PROJECT.

3. IT CREATES THE LOGIC FOR TRACKING COSTS,

SCHEDULE, AND PERFORMANCE SPECIFICATIONS FOR

EACH ELEMENT IN THE PROJECT.

4. IT MAY BE USED TO COMMUNICATE PROJECT STATUS.

5. IT MAY BE USED TO IMPROVE OVERALL PROJECT

COMMUNICATION.

6. IT DEMONSTRATES HOW THE PROJECT WILL BE CONTROLLED.

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

5

5.3 PARTIAL WORK BREAKDOWN STRUCTURE

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

6

1.0

1.2 1.3 1.4 1.5

1.2.1

1.2.2

1.2.3

1.3.1

1.3.2

1.4.1

1.4.2

1.4.3

1.0

1.2 1.3 1.4 1.5

1.2.1

1.2.2

1.2.3

1.3.1

1.3.2

1.4.1

1.4.2

1.4.3

5.4 THE INTERSECTION OF THE WBS AND OBS

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

7

Seek & hireIT consultant

IT Installation

Selectconsultant

Searchcommittee

Developcriteria

Project

DeliverablesPrepareproposal

1.3 1.4

Seek supportfor IT

1.5

1.0

1.4.1 1.4.2 1.4.3

WorkPackages

HumanResources

Procurement

InformationSystems

Departments

CostAccount

Cost Account

CostAccount

CostAccount

CostAccount

CostAccount

Seek & hireIT consultantSeek & hireIT consultant

IT Installation

Selectconsultant

Searchcommittee

Developcriteria

Project

DeliverablesPrepareproposal

1.3

PrepareproposalPrepareproposal

1.3 1.4

Seek supportfor IT

1.5

Seek supportfor ITSeek supportfor IT

1.5

1.0

1.4.1 1.4.2 1.4.3

WorkPackages

HumanResources

Procurement

InformationSystems

Departments

HumanResourcesHumanResources

ProcurementProcurement

InformationSystemsInformationSystems

Departments

CostAccount

Cost Account

CostAccount

CostAccount

CostAccount

CostAccount

5.5 COST ACCOUNT ROLLUP USING OBS

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

8

Seek & hireIT consultant

IT Installation

Selectconsultant

Searchcommittee

Developcriteria

Project

DeliverablesPrepareproposal

1.3 1.4

Seek supportfor IT

1.5

1.0

1.4.1 1.4.2 1.4.3

WorkPackages

HumanResources

Procurement

InformationSystems

Departments

$1,500

$500

$500

$500

- 0 - $1,000

$1,000

Totals

Seek & hireIT consultantSeek & hireIT consultant

IT Installation

Selectconsultant

Searchcommittee

Developcriteria

Project

DeliverablesPrepareproposal

1.3

PrepareproposalPrepareproposal

1.3 1.4

Seek supportfor IT

1.5

Seek supportfor ITSeek supportfor IT

1.5

1.0

1.4.1 1.4.2 1.4.3

WorkPackages

HumanResources

Procurement

InformationSystems

Departments

HumanResourcesHumanResources

ProcurementProcurement

InformationSystemsInformationSystems

Departments

$1,500

$500

$500

$500

- 0 - $1,000

$1,000

Totals

5.6 RESPONSIBILITY ASSIGNMENT MATRIX

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

9

LEAD PROJECT PERSONNEL

BobIS

DavidIS

SusanHR

BethProcurement

JamesEngineering

TerryLegalTask

& CodeDeliverable

Match IT toOrg. Tasks –1.1

ProblemAnalysis - 1.1.1

Develop infoon IT technology- 1.1.2

Identify ISuser needs –1.2

Interview potential users- 1.2.1

Developpresentation- 1.2.2

Gain user “buy in”- 1.2.3

Prepareproposal- 1.3

Develop cost/benefit info- 1.3.1

Notification

Responsible Support

Approval

LEAD PROJECT PERSONNEL

BobIS

DavidIS

SusanHR

BethProcurement

JamesEngineering

TerryLegalTask

& CodeDeliverable

Match IT toOrg. Tasks –1.1

ProblemAnalysis - 1.1.1

Develop infoon IT technology- 1.1.2

Identify ISuser needs –1.2

Interview potential users- 1.2.1

Developpresentation- 1.2.2

Gain user “buy in”- 1.2.3

Prepareproposal- 1.3

Develop cost/benefit info- 1.3.1

LEAD PROJECT PERSONNEL

BobIS

DavidIS

SusanHR

BethProcurement

JamesEngineering

TerryLegalTask

& CodeDeliverable

LEAD PROJECT PERSONNEL

BobIS

DavidIS

SusanHR

BethProcurement

JamesEngineering

TerryLegalTask

& CodeDeliverable

Match IT toOrg. Tasks –1.1

ProblemAnalysis - 1.1.1

Develop infoon IT technology- 1.1.2

Identify ISuser needs –1.2

Interview potential users- 1.2.1

Developpresentation- 1.2.2

Gain user “buy in”- 1.2.3

Prepareproposal- 1.3

Develop cost/benefit info- 1.3.1

Notification

Responsible Support

Approval

DISCUSSION QUESTIONS

1. What are the primary benefits of developing a comprehensive project scope analysis?

A comprehensive project scope analysis serves several benefits that permit a company to

guide the dream of a project to a successful completion. One benefit is transforming the

idea of the project into a working concept. Once the concept is developed, project details

can be mapped out. Scope analysis outlines each step of the project in a detailed manner.

The primary benefit to this is it aligns the project so that the final product will be

consisted with the original goals/objectives. By outlining each step, scope analysis

increases the likelihood that the project will stay within budget and time constraints as

well as meet predetermined specifications and quality parameters.

2. Refer to the Bradley Fighting Vehicle case at the end of the chapter (Case Study 5.3).

When is “Scope creep” useful and when is it dangerous? Under what circumstances

might an organization refuse to freeze design specifications for valid reasons (e.g.

Microsoft)?

Scope creep occurs when the project specifications are continually readjusted. This is

undesirable when the objective of the project is highly standardized product – one that is

needed to serve a very exact purpose. However, in the case of a product such as

computer software, scope creep may be beneficial. Companies like Microsoft stay

competitive through innovation. By allowing project team members to have more

freedom in design and creation, they are fostering an environment conducive to

innovation. As software engineers see areas for improvement or innovation they are

allowed to act on it. Thereby creating a more creative and competitive product.

3. What are the key characteristics of a work package?

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

10

A work package is a specific step of the project. Work packages are smaller pieces of the

whole project, which are more manageable and definable than the whole. They create a

chronological map from one step to the next detailing what needs to be completed at each

stage. Each work package includes its own deadline, resource requirements and

supervisor. Work packages can be further broken down into subtasks that can be

assigned to an individual worker or group. Collectively, all the work packages of a

project combined lead the project team from the start to completion of the project.

4. Create a Work Breakdown Structure for a term paper project or another school-related

project you are working on. What are the steps in the WBS? Can you identify any sub-

steps for each step?

This assignment is designed to get students comfortable with deconstructing the project

into various levels, including Deliverables, and Work Packages. The goal is identifying

the relevant elements in the project, not the sequential nature of those steps. If instructors

wish, they can ask students, as a second step, to create some idea of the sequentiality of

these WBS elements.

5. What are the benefits of designing a Responsibility Assignment Matrix (RAM) for a

project?

An RAM outlines the team members directly responsible for each task. It also includes a

list of supporting organizational members. It is beneficial for following chain of

command, solving interdepartmental issues and receiving proper approval. Additionally,

an RAM increases the flow of communication throughout the team. By knowing who is

in charge of what, members can notify the necessary people of progress or completion of

tasks. This keeps the group informed of potential problems and up-to-date on the

project’s current status.

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

11

The process of creating the RAM is also beneficial to the project manager. It requires the

identification of team members’ abilities, qualifications, strengths and weaknesses.

Tasks and assignments can then be better coordinated to create the highest level of

efficiency.

6. Develop an argument for scope reporting mechanisms. At a minimum, what types of

reports do you consider necessary for document control of a project? Why?

Two main concerns of project scope are seeing that the project meets time and budget

constraints. Without some sort of limits (i.e. project scope), projects can quickly become

expensive, long-term investments of a company’s time and resources. Scope reporting

can help reduce the risk of such runaway projects. Reports that update on costs incurred

using S-curves and variance updates are important for keeping the project within budget

constraints. These reports may also serve as control mechanisms. If team members

know they will have to publish spending reports frequently to other members in the

organization, they may be less likely to approve unscheduled expenditures. Reports

related to adherence to the planned time schedule work in a similar fashion. If the project

begins to lag behind, team members may have more incentive to look for the cause of the

delays if they are required to report variances from the planned time table.

7. What is the chief purpose of configuration management? In your opinion, why has it

become increasingly popular in recent years as part of the project management process?

The main purpose of configuration management is to manage and control change within

projects. A plan for execution of activities and tasks is agreed upon by those involved in

the project. Configuration management then monitors variations from this pre-

established plan. Change is an anticipated factor of project management. Configuration

management provides a way to deal with changes as they arise, so they do not cause more

disruption than necessary. Changes are documented so that all involved in the project

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

12

may be notified and modifications can be made universally. By identifying necessary

changes as early as possible and handling the problem early on, configuration

management decreases time delays related to unforeseen conditions and helps reduce

obstacles that may result from change later on in the project process.

8. What is the logic behind developing a plan for project close-out prior to even

beginning the project?

Upon completion of the project, certain documentation will be required by management

and/or the client involved. The documentation may be used for legal purposes, as

training material or in auditing procedures. Therefore, it is important that the closeout

information be thorough and accurate. Creating a plan early on is important because

proper documentation may need to be performed as the project progresses. By knowing

what information will be required at the end of the project, the team can keep proper

records at various stages as the project advances. Trying to create this documentation

after the fact may be difficult or inaccurate.

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

13

CASE STUDIES

Case Study 5.1: Calcutta’s Metro

Calcutta’s Metro project is a true story of a project disaster, when measured against

schedule and budget. The case lists a number of problems with a project that was

relatively modest in scope (10 miles of track and 17 stations) but ended up costing over

$5 billion dollars and taking 23 years to complete. The case is enjoyable for students

because, using 20/20 hindsight, several of the problems they encountered seem to be

obvious. It is useful to send students to the internet to research Boston’s “Big Dig”

harbor tunnel project and develop some comparisons and contrasts between that project

(which is also well over budget and behind schedule) and the Calcutta metro case. For

example, the Big Dig’s final cost is expected to be $14.6 billion and one of the two

tunnels has become leaking! Students can be directed to an interesting website for the

Boston project at http://www.tollroadsnews.com/cgi-bin/a.cgi/6S2C!

DOMEdmcEIJ61nsxIA. It presents a useful starting point to their own analysis of the

Calcutta project.

Questions:

1) Assume that you are the mayor of Calcutta soliciting bids for the construction of

the Metro. How would you construct a Statement of Work for the project to

encourage efficient and creative means for undertaking this project?

Students can be asked to use the sample Statement of Work (SOW) from the chapter to

begin developing their own set of details and specifications for the project’s scope. How

would they redesign the scope to minimize the disruptions that digging a metro through a

densely populated city are bound to create? Among the interesting elements of this

problem are the identification of significant risks of all types. How do they account for

them? Also, what about resource requirements? It is useful to get students thinking in

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

14

terms of a society with huge amounts of manpower but limited machinery means to

engage in a project of this scope? How are these various factors each accounted for?

2) How much of the problems the Metro project faced were the result of a poorly

conceived project scope and how much was due to simple bad luck? Defend your

position.

This question allows people to debate the two perspectives. Certainly, there is always

some bad luck associated with large projects, like the Calcutta Metro. The question

becomes whether or not such “bad luck” should be factored into the initial scope

statement and expectations for project development. For example, while it is not the fault

of the project organization that they kept hitting gas and water pipes due to poorly

charted infrastructure, the lack of these maps should have been taken into consideration

when they originally developed the timeframe for completion. Without detailed

drawings, they were bound to hit these mains. Further, common sense might suggest that

when the organization provided comprehensive housing, wages, and benefits (including

school for workers’ children) for employees, they were bound to work at a pace that

allowed them to maximize those benefits (in this case, 23 years).

Case Study 5.2: Project Management at Dotcom.com

This case is based on a true story and illustrates some of the key challenges that IT

organizations face when they attempt to develop solutions for clients. Many of these

clients understand their problems but don’t see how to create an appropriate solution.

Others, however, think they understand their needs but find the solutions generated for

them to be inadequate or simply addressing the wrong issues. It is a classic story of cope

definition that many IT organizations routinely deal with when trying to satisfy the needs

of clients.

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

15

Questions:

1. How would you begin redesigning Dotcom.com’s project management processes

to minimize the problems they are experiencing with poor scope management?

One suggestion might be the inclusion on the project team of a representative of the

client. It appears that one key problem lies in the fact that project teams talk to the

customer and then go away to develop the solution in a vacuum. Then, at the back end of

the development cycle, the customer is presented with a project solution that many times

does not satisfy them. This lack of communication is a key factor in the problems the

company is experiencing with their projects.

2. How do the company’s consulting clients contribute to the problems with “scope

creep?” If you were to hold a meeting with a potential customer, what message

would you want them to clearly understand?

Customers often do not recognize the link between project changes and cost. They may

assume that the project contract gives them unlimited rights to suggest or demand any

changes after the project was developed, or that the IT solution presented to them is only

a working model and subject to modifications. Without good communication between

the project organization and their clients, these misunderstandings will escalate as the

consulting firm demands more money for the changes and the clients argue that they will

not pay for modifications because the project firm did not do it right the first time. “Why

should we pay for your mistakes,?” is a comment commonly expressed by customers.

The key message that the customers must understand is the need to maintain strong lines

of communication and develop some milestones that allow for “reality checks”

throughout the development cycle. There should be no surprises at the time of delivery.

3. How do you balance the need to involve clients with the equally important need to

freeze project scope in order to complete the project in a timely fashion?

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

16

This may be the key conundrum in managing IT projects and is a great point of departure

for in-class discussion. Students are usually quick to point the finger of blame; either at

the IT firm for not getting clear information or at the customer for not providing it.

Instructors can set up a “point/counter-point” discussion on the causes of IT project

failure and how many are linked precisely to this problem and the failure to resolve it as

early in the project contract as possible.

4. Why are configuration management and project change control so difficult to

perform in the midst of a complex software development project such as those

undertaken by Dotcom.com?

One of the keys to configuration management is communication between customer and

client as both parties observe early versions of the system and identify the needed

modifications. The problem for IT organizations is that they are loath to grant too much

power to modify the system in mid-development for fear that the initially contracted

terms will become meaningless through multiple changes orders. They desire spec freeze

precisely for the reason that customers hate it. Hence, configuration management is

difficult because it is hard for customers, who are not sophisticated with IT technologies,

to identify relevant points when configuration management should occur. Their lack of

understanding of the development process often makes it hard to create good a priori

change controls processes. Instead, they usually simply react (negatively) to perceived

inadequacies of the solution, after installation.

Case Study 5.3: Runaway Scope: The Bradley Fighting Vehicle

This case is a famous true story of a project for which the original scope (the

development of a replacement armored infantry vehicle) changed so often and

dramatically that the Army ended up with a hybrid vehicle that could not perform any of

its missions well (e.g., too little room to transport troops, too lightly armored and slow to

serve as a scout vehicle).

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

17

1) The Bradley suffered from the problem of “scope creep,” the continual

reassessment and change of a project’s original specifications. How did scope

creep directly affect the Bradley’s final design?

Scope creep is the process of allowing a project’s scope to remain unfixed; that is, to

refuse to lock in the specifications prior to the start of project execution. As a result, the

final product can undergo numerous changes and reconfigurations throughout its

development and end up as a product that satisfies nobody. In the case of the Bradley,

the desire to create an armored scout and an infantry transport vehicle resulted in a design

that did not perform either task well.

2) When is scope creep useful and when is it dangerous? Under what circumstances

might an organization refuse to freeze project design specifications for valid

reasons?

Scope creep can be useful in cases where the project is still undergoing modifications of

its initial specifications; that is, when the scope has not yet been loced in. It can also be

useful when it reflects market realities. For example, a company may be developing a

product only to have a competitor get their version to market first. Under this situation,

remodification of the project could result in a superior design or help correct deficiencies

that could only be detected once the project was under development. Scope creep is

dangerous if it is not coupled with discipline in the project management process. At

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

18

some point, it does become necessary to stop the design phase and get started with the

execution of the project.

The reasons an organization may refuse to freeze specs are usually related to technical

issues that require continuous testing and approvals or when market conditions mandate a

change in the project’s characteristics to reflect realities. One famous example was Texas

Instruments desire to penetrate the PC market backing the 1980’s with a vastly inferior

product. They should have recognized that the technology had passed them by while

they were developing their PC and reconfigured it.

3) Suppose you were brought in as a consultant for the Bradley development during

the 1960s. What would been some of the warning signs of development problems

you could have observed?

One warning sign was the inability to select a primary mission for the vehicle. What was

the key role it was expected to play? As long as the Army flirted with multiple and

competing roles, they were not likely to develop a product that could adequately fulfill

any of them. Another warning sign was the poor testing that seemed designed to pass the

Bradley without any controversy. Clearly, this was a weapon system the Army wanted

regardless of what independent analysis would recognize.

4) Develop a strategy for managing the various stakeholders on the Bradley project.

In terms of its scope, are there middle ground compromises you can identify?

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

19

This question asks students to first identify the various stakeholders for the project (FMC

Corporation, the Army, the Army testing branch, Government oversight personnel, etc.).

They are then asked to identify how these stakeholder demands will conflict with each

other and what strategies they might undertake to address them, without violating the

needs of other stakeholders. This example works best if stakeholders are first identified,

they desires named, some prioritization of these desired is developed, and then students

are expected to develop strategies that will allow them to address one set of stakeholder

needs without violating the critical needs of other groups. Do they perceive the nature of

tradeoffs? This is a critical point to get across; namely, there may be no “ideal” strategy

but there are still methods for “satisficing” the needs of the various stakeholder groups.

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

20

MSProject EXERCISES

Using the information provided below, construct a simple WBS table for the project

example.

Project Outline – Remodeling an Appliance

I Research Phase

II Design and Engineering Phase

III Testing Phase

IV Manufacturing Phase

V Sales Phase

I Research Phase

A. Prepare product development proposal

1) Conduct competitive analysis

2) Review field sales reports

3) Conduct technological capabilities assessment

B. Develop focus group data

C. Conduct telephone surveys

D. Identify relevant specification improvements

II Design and Engineering Phase

A. Interface with Marketing staff

B. and so on

III Testing Phase

IV Manufacturing Phase

V Sales Phase

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

21

Solution:

Entering Tasks Using Custom WBS Codes

1. To view WBS codes, display the sheet view

2. Enter each activity on the MS Project task sheet

3. On the Project menu, point to WBS, and then click Define Code (See Figure 5.13)

Figure 5.13 – WBS Screen Shot

Microsoft product screen shot(s) reprinted with permission from Microsoft Corporation.

4. As you begin to enter each task and identify it as either a first-level, second-level,

or third-level heading, the WBS will demonstrate the organization of the project

(See Figure 5.14). Your final output should resemble the following:

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

22

Figure 5.14 – WBS Codes

Microsoft product screen shot(s) reprinted with permission from Microsoft Corporation.

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

23