Scope of Supply and Services

The scope of SALTEC covers the engineering activities from the very beginning, up to the commissioning of the new power line at the end of the entire project.

Consultancy services carried out by SALTEC can be offered.

Design freeze

Productsupply

Civilworks

Instal-lation

Documen-tation

Commis-sioning

The entire material which is needed for the project will be provided by SALTEC. For materials being supplied directly from special manufacturers, delivery controls will be executed by us in order to ensure the requested quality. For any HV parts SALTEC carries out the factory acceptance tests in the presence of our personnel exclusively. 

Product Supply

All HV materials, such as high voltage cables, terminations for outdoor, switchgear and transformer applications as well as HV joints with and without screen separation

Phase and ground wires with integrated optical fibres

Link boxes, bonding cables, optical fibre cables and accessories

DTS systems for temperature monitoring of cables and overhead lines

All auxiliary materials, e.g. for steel‐ and civil works, as well as the relevant parts for the power distribution at substations

Materials supplied by SALTEC

In front of a project the utility company needs to know which techniques and procedures which are optimal in order to transmit the required energy.SALTEC provides the full range of engineering and design works to offer the most efficient and economic solution. 

Design Freeze

Calculations (ampacity, statics)Drawings (components, designs)Feasibility studies, respecting the applicablelaws for the works on siteConsideration of national and internationalStandards (IEC 62067/60840)

Design FreezeStarting with the Engineering, so the technical part: 

Considering economic aspectsComparison between different techniquesLooking for a future‐oriented solution

Design Freezeup to the commercial part, which means:

Up to 500 kV, with a max. cross section of 3200 mm²

Single Core XLPE Cables

Up to 220 kV, with a max. cross section of 1000 mm²

Three Core XLPE Cables

Up to 500 kVTerminations (outdoor, switchgear, transformer), oil filled and dry typeJoints with anti corrosion protection housing or shrinkage sleeve

Accessories

For the civil works in the scope of a project a lot of coordination between the several parties is needed in advance as well as during the execution of the relevant works, in order to cover the full range of Project Management, e.g.: 

Civil Works

Civil Works

Fixing the route of the HV line, together with the customer and responsible authorities and/or agencies

Getting the permissions for the necessary accesses and digging works, both from public and from private property owners

Evaluation of any required material, such as concrete, steel etc.

QHSE (Quality/Health/Safety/Environment regulations) according to national and international PM Standards

Time Management of all running processes and involved companies in order to keep the overall time schedule for an on‐time‐commissioning of the new line

Execution of work will be carried out preferably by local subcontractors to SALTEC 

The project management contains the responsibility for this sector as well. 

St. Petersburg, first 330 kV cable in Russia21 km, 1200 mm², two circuits in parallel30 pcs. Joints, 18 pcs. TerminationsDecember 2006 –December 2007

Project Rzhevskaya

Moscow 220 kV78 km, 2000 mm², three circuits108 pcs. Joints, 24 pcs. Terminationsincl. VALCAPSeptember 2008Commissioning on 19.06.2011

Project Pavlovskaya

The installation works for any HV material will be executed by our own experienced and internationally certified personnel. 

The processes running in parallel are being coordinated by our Project Management, to keep the negative impacts between the several crafts as low as possible.

Installation

Providing the required working platforms and conditions for the ongoing processes/works

Availability of necessary equipment, tools, materials and personnel

Short termed reaction time in case of any arising, unforeseeable events and issues

Flexibility of installation staff concerning any influences from third parties

Installation of HV parts in a clean surrounding, in order to ensure the high quality standards needed

Installation

Moscow 220 kV3,0 km, 1200 mm², two circuits in parallel8 pcs. Joints, 7 pcs. TerminationsSeptember 2009

Project Ochakovo

St. Petersburg 330 kV + 110 kVCompletely inside substation13 km of 330 kV, 1600 mm² and 400 mm², 42 Terminationsincl. optical fibres(for 330 kV)6,5 km of 110 kV, 500 mm², 54 pcs. TerminationJuly 2009 – August 2012

Project Vostochnaya

110 kV City Cable5,64 km21 pcs. Joints, 8 pcs. Terminationsincl. optical fibresand VALCAPJuly 2011 –August 2011

Project Sofiyskaya

110 kV Single Core Cable11,8 km, three crosssections9 pcs. Joints, 32 pcs. TerminationsInstallation in 2014

Project Zavod Ilich

Documentation and Commissioning

At the end of the project the commissioning procedure needs to be prepared and executed afterwards. The relevant parties have to provide all necessary documentation in order to get the new HV line in service. This procedure will be initialized and monitored by SALTEC.

Documentation and Commissioning

Requesting and collecting all documents needed for the completion of the works, to be provided for the final customer / authorities / national grid company before and after commissioning

Preparing the site acceptance test (SAT) according to the valid standards, to be signed later by all responsible parties

Witnessing the tests on site before putting the new line under voltage

Handing over the complete as‐built‐report after the successful SAT

Coordination with international classification companies is common practice

for more details you are welcome with …