Scrum Level Up™ Assessment
for
Team ACME
Copyright and Use Restrictions
© Construx Software Builders, Inc. All rights reserved.
This report includes licensed content from Construx Software Builders, Inc. It is intended for educational purposes only. This content may be used by individuals solely for their own individual, personal use. This license does not allow for use or application of this content for corporate or other organizational purposes. This reporty may be freely reproduced and redistributed as long as it is reproduced and redistributed IN ITS ENTIRETY, including this copyright notice. COPYING SELECTED WORDING, DIAGRAMS, ANY PART OR PARTS OF THIS REPORT, OR ANY OTHER EXCERPTS IS EXPRESSLY PROHIBITED, regardless of whether the copying is on paper, electronic formats, internal or external websites, screen captures, or any other media.
Construx and Construx Software, are trademarks of Construx Software Builders, Inc. in the United States, other countries, or both. This report is for informational purposes only. This document is provided “As Is” with no warranties whatsoever, including any warranty of merchantability, noninfringement, fitness for any particular purpose, or any warranty otherwise arising out of any proposal, specification, or sample. Construx Software disclaims all liability relating to use of information in this paper.
3
Report Contents
Engagement Overview
State of Scrum Snapshot for Team ACME
Detailed Findings by Practice Area
Summary of Recommendations
Engagement Overview
5
Construx uses a structured process to conduct our Scrum Level Up™ assessment:
Understand the Team’s Current State. We learn the Scrum team’s current state with a set of structured but lightweight activities:
Conduct a brief online web survey with each team member about your current Scrum practices
Review existing Scrum and other project artifacts, including the Product Backlog, Definition of Done, and Sprint Burndown Charts
Interview the Scrum Master and Product Owner
Observe the Scrum events over a Sprint transition
Analyze and Assess. We evaluate the Scrum team, and compare it to a healthy Scrum team and an average Scrum team.
Report and Recommendations. Based on your current state, we have provided focused, targeted recommendations, which will help your Scrum team achieve a new level of effectiveness and performance.
Your findings and recommendations are based on our work with more than 500 Scrum teams in organizations world-wide.
Engagement Overview
6
Jenny Stuart, VP of Consulting
Jenny Stuart oversees Construx’s consulting services, focusing on proven software development best practices. Jenny has 20 years’ experience in process improvement, software testing, and quality assurance techniques. Her expertise in incorporating software development best practices has helped numerous companies dramatically improve their software development and quality assurance processes.
Jenny is an expert in quality practices, such as developing quality and test plans, and has a deep knowledge of software testing, process improvement, and quality assurance techniques. She is the author of numerous Construx client studies and Construx white papers. Jenny has a BSEE from the University of Washington. She is a member of the Computer Society of the IEEE, the Association for Computing Machinery, the American Society for Quality, and the Quality Assurance Institute. In 2000, she earned the highest score in the United States on QAI’s Certified Software Test Engineer (CSTE). She also has CSDP certification, is a Professional Scrum Master (PSM), and is a SAFe Program Consultant (SPC).
Scrum Level Up™ Lead Assessor Background
7
Product Owner: Jeff• Located in San Jose
Scrum Master: Sanjeev• Located in Seattle
Six members of the Development Team• 5 in Seattle • 1 in Boston
The ACME Team
8
A PowerPoint overview of the product
A subset of the team’s Product Backlog including
• 15 user stories with acceptance criteria and UI design guidance
• 8 defects
• 7 technical debt or technical items
The Definition of Done
The Definition of Ready
The Working Agreements
3 Sprint Backlog items from Sprint 22 including all tasks and other information
A screen shot of the current Sprint task board
Sprint Burndown Charts for the last three Sprints
Defect trend data from the last project and this project
Eight web survey results
Reviewed Materials
State of Scrum Snapshot
10
Overview of ACME’s Scrum Operation
The ACME team has a healthy Scrum adoption that is significantly better than average and healthy in nearly all respects.
We found all Scrum roles, events, and artifacts to be working well.
ACME’s mission going forward will be to strengthen an already-strong Scrum implementation, rather than to correct a deficient implementation.
11
Detailed Ratings of ACME’s Scrum OperationTeam Practice
Healthy Team
Average Team
Your Team
Gap Analysis Interpretation
Sprint Planning 7 4 6 Slight weakness
Used with mixed effectiveness; Better than average; Fairly healthy
Daily Scrum/Standup 7 6 9 Marked Strength
Used consistently and effectively; Much better than average; Very healthy
Sprint Review 7 4.5 9 Marked Strength
Used consistently and effectively; Much better than average; Very healthy
Sprint Retrospective 7 4 9 Marked Strength
Used consistently and effectively; Much better than average; Very healthy
Product Owner 7 2 8 StrengthUsed consistently and effectively; Much better than average; Very healthy
Scrum Master 7 4 8 StrengthUsed consistently and effectively; Much better than average; Very healthy
Cross-Functional, Self-Managing Development Team 7 6 8 Strength
Used consistently and effectively; Better than average; Very healthy
Product Backlog; Refinement 7 5.5 7 Mild strength Used consistently and effectively; Better than average; Healthy
Sprint Backlog 7 5.5 6 Slight weakness Used with mixed effectiveness; About average; Fairly healthy
12
Greatest Strength(s)Daily Scrum/StandupSprint ReviewSprint Retrospective
Greatest Weakness(es)Sprint Planning
Prioritizing Strengths and Weaknesses of ACME’s Scrum Operation
13
Team Perceptions of ACME’s Scrum Adoption (1 of 2)
Team PracticeConstrux
RatingLowest Self-
RatingHighest Self-
RatingAverage Self-
Rating
Sprint Planning 6 5 7 6
Daily Scrum/Standup 9 6 8 7
Sprint Review 9 8 9 8.5
Sprint Retrospective 9 9 9 9
Product Owner 8 8 9 8.5
Scrum Master 8 7 9 8
Cross-Functional, Self-Managing Development Team 8 6 9 7.5
Product Backlog; Refinement 7 5 7 6
Sprint Backlog 6 5 7 6
Overall Rating 7.8 6.6 8.2 7.4
14
Team Perceptions of ACME’s Scrum Adoption (2 of 2)
The team’s self-rating was biased slightly on the self-critical side
This pattern of a team being overly-self-critical is common among high performing teams; we regard it as healthy and do not recommend changing it
Detailed Findings by Practice Area
16
Sprint planning scored 6, which makes it a slight weakness Sprint planning was the most significant weakness observed in this
assessment (along with a related weakness in sprint backlog), but that is in the context of an otherwise strong implementation
Survey comments consistently stated that surprises occurred throughout the Sprint. During our observation of Sprint Planning, we found it rushed and that the team members did not feel confident in their plan
To improve in this area, we recommend the team have deeper discussions about what they need to do this Sprint as they develop their Sprint Backlog. Some additional task creation and decomposition would be valuable to ensure that discussion occurs
Sprint Planning
17
Daily Scrum/Standup scored 9, which makes it a marked strength We do not recommend any changes in this area, other than minor
refinements that will continue to be identified through the normal retrospective process
Daily Scrum/Standup
18
Sprint Review scored 9, which makes it a marked strength We do not recommend any changes in this area, other than minor
refinements that will continue to be identified through the normal retrospective process
Sprint Review
19
Sprint Retrospective scored 9, which makes it a marked strength We recommend the team explore bigger picture changes in the
retrospectives, as described on the next page
Sprint Retrospective
20
Members of the ACME team expressed concern that retrospectives were becoming stale. They have found and implemented all the low-hanging fruit changes.
We recommend that the ACME team establish a Big Hairy Audacious Goal (BHAG). Examples include decreasing build time by 75%, increasing velocity by 50%, or reducing customer reported defects by 30%.
The team can use the next retrospective to
• Establish a shared goal
• Determine how to measure progress towards the goal
• Select the first change the team will make and estimate what contribution they believe that change can make in two weeks
Retrospectives then focus on evaluating the impact and making decisions about what to try next until the team achieves its BHAG. The team can then establish a new goal.
Explore Bigger Picture Changes in the Retrospectives
21
Product Owner scored 8, which makes it a strength We do not recommend any changes in this area, other than minor
refinements that will continue to be identified through the normal retrospective process
Product Owner
22
Scrum Master scored 8, which makes it a strength We do not recommend any changes in this area, other than minor
refinements that will continue to be identified through the normal retrospective process
Scrum Master
23
Cross-Functional, Self-Managing Development Team scored 8, which makes it a strength
We do not recommend any changes in this area, other than minor refinements that will continue to be identified through the normal retrospective process
Cross-Functional, Self-Managing Development Team
24
Product Backlog; Refinement scored 8, which makes it a mild strength One major concern express by Jeff, the Product Owner, is the ACME team has
numerous stakeholders and the team sometimes feels they aren’t delivering what those stakeholders want and need
We recommend quantifying stakeholder goals, as described on the next few pages, to help focus the business and the team on value
Product Backlog; Refinement
25
We recommend that ACME capture and quantify the top three goals for their product. For example, one goal Jeff expressed was to Improve End User Satisfaction. Assuming this was a top goal across all stakeholders, ACME could then quantify it by establishing:
A scale: What is being measures / the units of measureA meter: How it is measured / how to place results of the scaleA target range: The range of acceptable outcomes (see next slide)
We recommend that Jeff interview the current stakeholders to understand their wants and needs. Sanjeev, the Scrum Master, and Jeff can then conduct a half day working session to prioritize and align everyone on the top three goals for the product in 2020.
Quantify the Stakeholders Goals (1 of 3)
26
We recommend that ACME capture the following target ranges for desired outcomes Minimum: The level necessary to avoid some form of failure Target: A level representing good success Outstanding: A desirable level that could be achieve if everything went perfectly
Quantify the Stakeholders Goals (2 of 3)
MinimumTarget
Outstanding
27
Example Quantified Goal
Quantify the Stakeholders Goals (3 of 3)
Improve User Satisfaction
Meter: Monthly User Satisfaction Survey
Scale: Net Promotor Score
Minimum: >=20 Outstanding: >=50Target: >=35
28
Sprint planning scored 6, which makes it a slight weakness Expanding the discussions occurring in Sprint Planning will help the team
have more confidence in their Sprint Backlog Quantifying the goals will help ensure the most valuable items are in the
Sprint Backlog
Sprint Backlog
Summary of Recommendations
30
The ACME team is performing well overall. Based on the team’s current state and its stated goals, we have recommended the following:
1. No changes in most areas, other than continuing refinements arising through the normal retrospective process
2. Expand the discussions occurring in Sprint Planning so that the team feels comfortable and confident with the Sprint plan
3. Explore Bigger Picture Changes in the Retrospectives 4. Quantify the Stakeholder’s Goals
Summary of Recommendations
32
Construx was founded by Code Complete author Steve McConnell to provide practical, evidence-based, real-world leadership to the software community
We have helped more than 1,000 Scrum teams in organizations world-wide
We believe that every software project can be successful We believe that developing the professional skills of
companies, teams, and individuals is the best way to make software projects more successful
Construx History & Focus
Construx Software is committed to helping individuals and organizations improve their software development practices.
For information about our training and consulting services, contact [email protected].
10900 NE 8th Street, Suite 1300Bellevue, WA 98004
+1.425.636.0100www.construx.com
Thank you