Solution EngineeringInternal Change Request Process
Date: 04/28/2015
PurposeThis transmittal describes the activities and steps to manage the Solution Engineering (SE) Internal Change Request Process.
Material ChangesThere is no change in this material.
Effect on Other DocumentsThis procedure does not impact any other document
AudienceThe Solution Engineering Internal Change Request Process is applicable to all SE resources, both government and contractor, who have a responsibility for requesting changes to Configuration Items managed by the Information Technology (IT) Change Control Board (CCB) and who have a responsibility for conducting Impact Assessments for Non-SE Change Requests upon request.
Effective Date This Process Description is effective upon signature.
Signature:
Acting Director, Solution Engineering
Title:
Solution EngineeringInternal Change Request
Process
Version: V0.20
04/28/2015Supersedes: N/A
1. Policy ExpectationsThe expectation is that all SE resources seeking to generate new Change Requests (CR)s, and performing impact analyses on external and internal CRs, will use this process.
2. Process Description
2.1 SE CR Process Flow Diagram
CTO:ES:SE:EPM-CR-PD-V0.20-04282015 Page 2 of 29
2.2 Process Flow1. Process Flow Control
If submitting a new SE CR, go to step 2
If responding to a request for an impact assessment, go to step 11
2. Conduct CR Pre-coordination with other SE Practice Groups for input and awareness
3. Complete the ITS CR Submission Form
4. Conduct Impact Assessment
If the CR is an SE CR, go to step 5
If the CR is a non-SE CR, go to step 12
5. Share CR impact assessment with all SE practice groups
6. Inform Non-SE Activities of SE intent to submit an SE CR and request feedback
NOTE: Non-SE contact is not obligated by this SE internal process to participate in any way
7. Receive and review Non-SE Activity feedback
8. Recommend submission of CR
If Yes, go to Step 9
If No, go to Process Exit
9. Submit CR, including impact assessment
10. Attend CCB
11. SE pre defined point of contact receives CR for impact assessment
12. Return SE impact assessment to requestor
If there is an SE impact go to step 10
If there is no SE impact proceed to process exit
CTO:ES:SE:EPM-CR-PD-V0.20-04282015 Page 3 of 29
3. Process Procedure
3.1 Roles and Responsibilities
Role Description Definition of ResponsibilitySE CR Submitter Responsibility:
Conduct the Pre-Coordination meeting Complete the ITS CR submission form Share CR Impact Assessment with SE Practice
Groups Submit CR
SE Pre-Defined Point of Contact Responsibility:
Receive non-SE CR for Impact Assessment Assign CR Analysts to perform Impact Assessment Return SE Impact Assessment to requestor
SE Pre-Coordination Analysis Member Responsibility:
Participate in the Pre-Coordination meeting
SE CR Analyst Responsibility:
Perform SE Impact Assessment
SE Practice Group Lead Responsibility:
Review SE CR Impact Assessment Concur or not with SE CR Impact Assessment
SE SME Representative Responsibility:
Attend CCB
SE Higher Authority Responsibility:
Review all SE CR artifacts Recommend SE CR for submission
CTO:ES:SE:EPM-CR-PD-V0.20-04282015 Page 4 of 29
3.2 CR Submission Procedure
3.2.1 Process Flow Control Procedure
Figure 1 – Process Flow Control
A1: Process Flow ControlSteps Roles
1. Submit a SE CR.
Go to Activity 2SE CR Submitter
2. Request that SE provide an SE Impact Assessment
Go to Activity 11n/a
CTO:ES:SE:EPM-CR-PD-V0.20-04282015 Page 5 of 29
3.2.2 Conduct Internal CR Pre-Coordination with all SE Practice Groups
Figure 2 – Conduct CR Internal Pre-Coordination with all SE Practice Groups
CTO:ES:SE:EPM-CR-PD-V0.20-04282015 Page 6 of 29
A2: Conduct CR Pre-Coordination with all SE Practice GroupsSteps Roles
1. Schedule and lead meeting with Pre-Coordination Analysis members.
Use the Appendix A Pre-Coordination Template/Checklist Determine the desired participation for the meeting
o Suggested participants include the following: SE Lead Engineer ITE Lead Engineer SE Practice Group Representatives SE Subject matter expert(s)
Schedule the meeting and invite all of the desired attendees.o Make the meeting available by conference call
Call the meeting to order when a quorum of essential personnel are present
Lead the Pre-Coordination meeting
Take meeting minutes or delegate as appropriate
Go to step 2
SE CR Submitter
2. Discuss the intent of the proposed change
Discuss the intent of the proposed change until its purpose is fully understood by all present.
Go to step 3
SE CR Submitter SE Pre-Coordination
Analysis Members
3. Confirm CR is on an IT CCB Configuration Item
Determine CCB management authority for the CI under consideration
Consult with IT CCB Chairman if CI ownership cannot be determined
If the CI under consideration is managed by the IT CCB:o Go to step 4.
If the CI under consideration is not managed by the IT CCB:o Stop
SE CR Submitter SE Pre-Coordination
Analysis Members
4. Determine Implementation status
If the proposed change has not been implemented, nor is it scheduled to be implemented:
o Go to step 6
If the proposed change is implemented, partially implemented, or scheduled to be implemented:
o Go to step 5
SE CR Submitter SE Pre-Coordination
Analysis Members
CTO:ES:SE:EPM-CR-PD-V0.20-04282015 Page 7 of 29
5. Determine the details of the implementation
Collect the following information:o Determine if an impact assessment has been performedo Identify the ITE implementation authorityo Identify the Production implementation authorityo Identify the implementation funding sourceo Identify available artifacts relating to this change o Identify which organizations are aware of the changeo Identify which CM or local process was used to implement the
changeo Determine if the change is recorded in the CMSo Determine if the change was tested in ITE and Productiono Determine which projects are using the changeo Determine which platforms host this changeo Determine the location of the changeo Determine if any SLAs or Service Contracts are affected by this
changeo Determine when the change was implementedo Determine if the change has been modified since its initial
deployment. If so, how?o Determine the reason for deviation from IRS CCM processes.o Determine the interfaces of this change. (i.e. DBs, APIs, etc.)o Determine if any ELC documents were modified as a result of this
change.
Go to step 6
SE CR Submitter SE Pre-Coordination
Analysis Members
6. Determine if the CR is associated with a Work Request (WR)
Determine the WR associated with this proposed change
o Go to step 8
If a WR cannot be identified that is associated with this change:o Go to step 7
SE CR Submitter SE Pre-Coordination
Analysis Members
7. Create a new WR
Consult the WR process to create a new WR that will be associated with this CR.
Identify and obtain concurrence from the WR authority (owner)
Go to step 8
SE CR Submitter
8. Determine if the WR owner concurs with the proposed CR
Inquire to the WR owner requesting CR/WR concurrence
If the WR owner does not concur:o Go to step 9
If the WR owner concurs:o Go to step 10
SE CR Submitter
CTO:ES:SE:EPM-CR-PD-V0.20-04282015 Page 8 of 29
9. Resolve CR/WR concurrence
Resolve concurrence with WR ownero Go to step 10
If concurrence cannot be resolved:o Consult Higher Authority
SE CR Submitter
10. Determine if the CR is Enterprise Architecture (EA) compliant
Consult the EA Enterprise Services Profile (ESP) to determine if the proposed change is EA compliant
If the proposed change is EA compliant:o Go to step 12
If the proposed change is not EA compliant:o Go to step 11
SE CR Submitter
11. Obtain EA compliance
Consult with EA to make them aware of the proposed change and allow them to provide guidance.
Submit a CR to IT CCB to obtain EA compliance for the proposed change to the EA ESP
Obtain approval disposition for the EA CR at the IT CCB
Go to step 12
SE CR Submitter
12. Construct the CR
Perform the following tasks:o Determine the correct CR titleo Determine the technical Point of Contacto Determine WR Point of Contacto Write a full narrative description of the proposed changeo Determine the funding sourceo Determine the Priority (Normal or High)
Provide all information to the SE CR Submitter
Go to step 13
SE CR Submitter SE Pre-Coordination
Analysis Members
13. Assign CR for Impact Assessment
Assign a SE Pre-Coordination member to perform the CR Impact Assessment with respect to SE
The CR Impact Assessment assignee will fulfill the SE CR Analyst role in Activity 4
Go to step 14
SE CR Submitter SE Pre-Coordination
Analysis Members
CTO:ES:SE:EPM-CR-PD-V0.20-04282015 Page 9 of 29
14. Record all Pre-Coordination artifacts in a publicly accessible version controlled repository
Store all Pre-Coordination artifacts in a pre-designated location on the SE Process Asset Libraryo Read/Write permissions for the SE CR Submittero Read permission for all others
Provide CR Pre-Coordination artifact location to all Pre-Coordination member participants
Go to Activity 3
SE CR Submitter
3.2.3 Complete the ITS CR Submission form
Figure 3 – Complete the ITS CR Submission form
A3: Complete the ITS CR Submission formSteps Roles
1. Obtain the ITS Configuration and Change Management (CCM) CR Submission form.
Download the current ITS CCM CR Submission form from the ITS CCM website.
Go to step 2
SE CR Submitter
2. Complete the ITS CCM CR Submission form using information gathered in Activity 2
Complete the ITS CCM CR Submission form
Record the results in the version controlled repository established in activity 2
Go to Activity 4
SE CR Submitter
CTO:ES:SE:EPM-CR-PD-V0.20-04282015 Page 10 of 29
3.2.4 Conduct Impact Assessment
Figure 4 – Conduct Impact Assessment
A4: Conduct Impact AssessmentSteps Roles
Flow Control by CR Source
If CR is an SE CR go to step 1
If CR is a Non-SE CR go to step 2
SE CR Submitter SE Pre-Determined
Point of Contact
1. Provide all CR Pre-Coordination artifacts required for the Impact Assessment.
Consolidate all relevant SE CR Pre-Coordination artifacts
Provide consolidated artifacts to the SE CR Analyst
Communicate the priority set by the pre-coordination board
o 10 working day turn around for Normal Priority
o 5 working day turn around for High Priority
SE CR Submitter
CTO:ES:SE:EPM-CR-PD-V0.20-04282015 Page 11 of 29
2. Provide all non-SE CR artifacts required for the Impact Assessment.
Consolidate all relative non-SE CR artifacts
Provide consolidated artifacts to the SE CR Analyst
Communicate the priority set by the pre-coordination board
o 10 working day turn around for Normal Priority
o 5 working day turn around for High Priority
SE Pre-Defined Point of Contact
3. Determine the impact of the CR on SE
Analyze the impact of the proposed change on the functions of SE
Use the Appendix B Impact Assessment Template/Checklist Include the following:
o Written narrative describing: Enterprise policies followed or deviated from Business case summary for the change
Advantages Disadvantages
Organizations affected Products affected Alternative Solutions Comparative analysis with existing solution (if the change
is an upgrade) Evaluation of proposed new technologies
Hardware Software Service
Skills analysis New skills required Skills no longer needed
Training required Location analysis
o Estimate cost to implement the changeo Estimate cost over time to operate and maintain the changeo Estimate man hours required to implement the changeo Estimate man hours required to operate and maintain the change
SE CR Analyst
4. Return Impact Assessment to requestor
Copy Impact Assessment into a single document using the ITS CR Impact Assessment form template of the ITS CR Submission form
If the proposed change is a non-SE CR:o Go to Activity 12
If the proposed change is a SE CR:o Go to step 5
SE CR Analyst
CTO:ES:SE:EPM-CR-PD-V0.20-04282015 Page 12 of 29
5. Record the Impact Assessment
Record the Impact Assessment together with the other CR artifacts in the version controlled repository
Go to Activity 5
SE CR Submitter
3.2.5 Share CR Impact Assessment with all SE Practice Groups
Figure 5 – Share CR Impact Assessment with all SE Practice Groups
A5: Share CR Impact Assessment with all SE Practice GroupsSteps Roles
1. Provide all CR artifacts including the Impact Assessment to SE Practice Groups for review.
Consolidate all CR artifacts including the Impact Assessment
Forward CR artifacts to the SE Practice Group Leads
Communicate the priority set by Activity 2 pre-coordination
o 10 working day turn around for Normal Priority
o 5 working day turn around for High Priority
SE CR Submitter
CTO:ES:SE:EPM-CR-PD-V0.20-04282015 Page 13 of 29
2. Review CR including Impact Assessment.
Receive the CR artifacts from the SE CR Submitter
Review the CR artifacts
SE Practice Group Lead
3. Determine concurrence with CR and Impact Assessment
If concurrence is determined:o Go to step 4
If non-concurrence is determined:o Go to step 5
SE Practice Group Lead
4. Record Practice Group concurrence in CR artifacts
Record concurrence together with the other CR artifacts in the version controlled repository
Go to Activity 6
SE CR Submitter
5. Record Practice Group non-concurrence in CR artifacts
Record non-concurrence together with the other CR artifacts in the version controlled repository
Go to Activity 2
SE CR Submitter
CTO:ES:SE:EPM-CR-PD-V0.20-04282015 Page 14 of 29
3.2.6 Inform Non-SE Activities of SE intent to Submit SE CR & Request Comments
Figure 6 – Inform Non-SE Activities of SE intent to Submit SE CR & Request Comments
A6: Inform Non-SE Activities of SE intent to Submit an SE CR & Request Comments
Steps Roles1. Consolidate all CR artifacts
Consolidate all SE CR artifacts including the SE impact assessment SE CR Submitter
CTO:ES:SE:EPM-CR-PD-V0.20-04282015 Page 15 of 29
2. Inform Non-SE Activities of SE intent to submit an SE CR and solicit comments
Communicate SE CR artifacts and request comments
Suggested Non-SE Activity participants include:
o EA Representative
o AD Representative
o EOPs Representative
o UNS Representative
SE CR Submitter
3. Review CR artifacts
Receive the request to review and comment
Review SE CR artifacts
NOTE: Non-SE contacts are not obligated by this SE internal process to participate in any way
Non-SE Pre-Coordination Contact
4. Provide review results and recommendations (if any) to requestor
Provide review results to the SE CR requestor
NOTE: Non-SE contacts are not obligated by this SE internal process to participate in any way
Non-SE Pre-Coordination Contact
5. Review Non-SE Activity review results
Receive the Non-SE review results
Review the Non-SE review results
SE CR Submitter
6. Consolidate Non-SE Activity artifacts with existing artifacts
Consolidate the Non-SE Activity artifacts together with the SE CR artifacts in the version controlled location established in Activity 2
Go to Activity 7
SE CR Submitter
CTO:ES:SE:EPM-CR-PD-V0.20-04282015 Page 16 of 29
3.2.7 Receive and Review Non-SE Activity Comments
Figure 7 – Receive and Review Non-SE Activity Comments
A7: Receive and Review Non-SE Activity CommentsSteps Roles
1. Provide review results, recommendations and comments (if any) to the SE CR requestor
Provide review results to the SE CR requestor
NOTE: Non-SE contacts are not obligated by this SE internal process to participate in any way
Non-SE Pre-Coordination Contact
2. Review Non-SE Activity review results
Review Non-SE Activity review results
Determine action(s) required
SE CR Submitter
CTO:ES:SE:EPM-CR-PD-V0.20-04282015 Page 17 of 29
3. Consolidate Non-SE Activity artifacts with existing SE CR artifacts
Consolidate Non-SE Activity artifacts with existing SE CR artifacts
If review results warrant re-iteration of the SE CR Pre-Coordination, go to Activity 2
If review results do not warrant additional action, go to step 8
SE CR Submitter
CTO:ES:SE:EPM-CR-PD-V0.20-04282015 Page 18 of 29
3.2.8 Recommend CR for Submission
Figure 8 – Recommend CR for Submission
A8: Recommend CR for SubmissionSteps Roles
1. Provide all CR artifacts to Higher Authority for recommendation prior to submission.
Consolidate all CR artifacts
Request Higher Authority recommendation for CR submission
SE CR Submitter
CTO:ES:SE:EPM-CR-PD-V0.20-04282015 Page 19 of 29
2. Recommend CR.
Review all CR artifacts
Determine CR recommendation:
Forward recommendation to SE CR Submitter
SE Higher Authority
3. Record recommendation in CR artifacts
Record recommendation together with the other CR artifacts in the version controlled repository
If the CR has been recommended:o Go to Activity 9
If the CR has not been recommended:o Stop
SE CR Submitter
3.2.9 Submit CR, including Impact Assessment
Figure 9 – Submit CR, including Impact Assessment
A9: Submit CR, including Impact Assessment
CTO:ES:SE:EPM-CR-PD-V0.20-04282015 Page 20 of 29
Steps Roles
1. Record all CR artifacts in the CR tool as a new SE CR.
Create a new SE CR in the CR tool
Attach all CR artifacts in the designated places
SE CR Submitter
2. Submit SE CR.
Submit the new SE CR
Inform all of the SE Pre-Coordination members and higher authority that the CR has been submitted and including references to view the CR and all artifacts.
Go to Activity 10
SE CR Submitter
CTO:ES:SE:EPM-CR-PD-V0.20-04282015 Page 21 of 29
3.2.10 Attend CCB
Figure 10 – Attend CCB
A10: Attend the CCBSteps Roles
1. Attend the appropriate CCB.
Attend the IT CCB meeting convened to disposition the SE CR
Attend the appropriate CCB meeting convened to disposition the Non-SE CR
SE SME Representative
2. Explain SE CR and SE Impact Assessment or the Non-SE impact assessment to the CCB.
If asked at the CCB meeting, explain all inquiries that the board members may have.
Stop
SE SME Representative
CTO:ES:SE:EPM-CR-PD-V0.20-04282015 Page 22 of 29
3.2.11 SE Pre-Defined Point of Contact receives non-SE CR for Impact Assessment
Figure 11 – SE Pre-Defined Point of Contact receives non-SE CR for Impact Assessment
A11: SE Pre-Defined Point of Contact receives non-SE CR for Impact Assessment
Steps Roles
1. Receive an Non-SE CR to analyze impact of CR on SE
Receive the Non-SE CR for Impact Assessment SE Pre-Defined Point
of Contact
2. Assign CR for Impact Assessment.
Assign a SE CR Analyst to perform the CR Impact Assessment with respect to SE
Go to Activity 4
SE Pre-Defined Point of Contact
CTO:ES:SE:EPM-CR-PD-V0.20-04282015 Page 23 of 29
3.2.12 Return SE Impact Assessment to CCB
Figure 12 – Return SE Impact Assessment to CCB
A12: Return SE Impact Assessment to CCBSteps Roles
1. Return completed non-SE CR Impact Assessment to requestor.
Review the completed non-SE CR Impact Assessment
Return the completed non-SE CR Impact Assessment to the requestor
SE Pre-Defined Point of Contact
2. Determine action to take if SE is impacted.
If SE is impacted:o Go to Activity 10
If SE is not impacted:o Stop
SE Pre-Defined Point of Contact
CTO:ES:SE:EPM-CR-PD-V0.20-04282015 Page 24 of 29
Appendix A. Pre-Coordination Template/Checklist
NOTE: Record the findings of the Pre-Coordination in a separate document. This information will be used to complete the MITS CM CR Form.
1. Determine the desired participation for the meetinga. Suggested participants include the following:
i. SE Lead Engineerii. ITE Lead Engineeriii. SE Practice Group Representativesiv. Subject matter expert(s)
2. Schedule the meeting and invite all of the desired attendees.a. Make the meeting available by conference call
3. Call the meeting to order when a quorum of essential personnel are present
4. Lead the Pre-Coordination meeting
5. Take meeting minutes or delegate as appropriate
6. Discuss the intent of the proposed change
a. Discuss the intent of the proposed change until its purpose is fully understood by all present.
7. Determine if the associated WR Primary Supplier is correctly identified
a. Identify the Primary Supplier in the WR that is associated with the proposed CR.
b. Verify that the Primary Supplier is correctly identified.
c. If the Primary Supplier is correct but not SE, then determine the correct CCBi. Forward CR to the correct CCB
d. If the Primary Supplier is incorrectly specified in the WR as SE:i. Advise WR authority to modify Primary Supplier
e. If the Primary Supplier is correctly identified in the WR as SE:i. Confirm CR is on an IT CCB Configuration Item
8. Confirm that he CR is on an IT CCB Configuration Item (CI)a. Determine CCB management authority for the CI under consideration
b. Consult with the IT CCB Chairman if CI ownership cannot be determined
9. Determine the state of implementation of the change.a. If the proposed change has been implemented, or is scheduled to be implemented:
CTO:ES:SE:EPM-CR-PD-V0.20-04282015 Page 25 of 29
i. Determine if an impact assessment has been performed
ii. Identify the ITE implementation authority
iii. Identify the Production implementation authority
iv. Identify the implementation funding source
v. Identify available artifacts relating to this change
vi. Identify which organizations are aware of the change
vii. Identify which CM or local process was used to implement the change
viii. Determine if the change is recorded in the CMS
ix. Determine if the change was tested in ITE and Production
x. Determine which projects are using the change
xi. Determine which platforms host this change
xii. Determine the location of the change
xiii. Determine if any SLAs or Service Contracts are affected by this change
xiv. Determine when the change was implemented
xv. Determine if the change has been modified since its initial deployment. If so, how?
xvi. Determine the reason for deviation from IRS CCM processes.
xvii. Determine the interfaces of this change. (i.e. DBs, APIs, etc.)
xviii. Determine if any ELC documents were modified as a result of this change.
10. Determine if the CR is associated with a WRa. Determine the WR associated with the proposed change
b. If a WR that is associated with the proposed change cannot be identified
i. Create a WR
1. Consult the WR process to create a new WR that will be associated with this CR
2. Identify and obtain concurrence from the WR authority (owner).
11. Determine if the WR owner concurs with the proposed CRa. Inquire to the WR owner requesting CR/WR concurrence
b. If the WR owner does not concur:i. Resolve CR/WR concurrence with WR owner
ii. If concurrence cannot be resolved
1. Consult higher authority
12. Determine if the proposed change is EA complianta. Consult the EA ESP to determine if the proposed change is EA compliant
b. If the proposed change is EA compliant:i. Continue
c. If the proposed change is not EA compliant:i. Obtain EA compliance:
CTO:ES:SE:EPM-CR-PD-V0.20-04282015 Page 26 of 29
1. Consult with EA to make them aware of the proposed change and allow them to provide guidance.
2. Submit a CR to IT CCB to obtain EA compliance for the proposed change
3. Obtain approval disposition for the EA CR
13. Construct the CRa. Perform the following tasks:
i. Determine the correct CR titleii. Determine the technical Point of Contactiii. Determine WR Point of Contactiv. Write a full narrative description of the proposed changev. Determine the funding sourcevi. Determine the Priority (Normal or High)
14. Assign the CR for Impact Assessmenta. Assign a SE Pre-Coordination member to perform the CR Impact Assessment with respect to
SE
b. Inform the Impact Analyst of the CR priority and schedule for completion
15. Record all Pre-Coordination artifacts in a publicly accessible version controlled repositorya. Store all Pre-Coordination artifacts in a pre-designated location on the SE Process Asset
Libraryi. Read/Write permissions for the SE CR Submitterii. Read permission for all others
b. Provide CR Pre-Coordination artifact location to all Pre-Coordination participants
CTO:ES:SE:EPM-CR-PD-V0.20-04282015 Page 27 of 29
Appendix B. Impact Assessment Template/Checklist
1. Determine the impact of the proposed change on SE.2. Using the ITS CR Assessment form template Include the following:
a. A written narrative of the change including:i. Enterprise policies followed or deviated fromii. Business case for the change
1. Advantages2. Disadvantages
iii. Organizations affectediv. Product affectedv. Alternative solutionsvi. Comparative analysis with existing solution (if the change is an
upgrade)vii. Evaluation of proposed new technologies
1. Hardware2. Software3. Service
viii. Skills analysis1. New skill required2. Skills no longer needed
ix. Training requiredx. Location analysis
b. Estimate the cost to implement the changec. Estimate the cost over time to operate and maintain the changed. Estimate man hours required to implement the changee. Estimate man hours required to operate and maintain the change
CTO:ES:SE:EPM-CR-PD-V0.20-04282015 Page 28 of 29