    Responsibilities and Authorities

    The position assumes full responsibility and authority in ensuring compliance of

    selected Contractors and Vendors with the engineering, procurement, construction

    and commissioning requirements of the project; including local and international

    codes and standards, safety and environmental laws, sound or establishedengineering practices and other provisions of the Contract Agreements or urchase

    !rders"

    #ajor rocesses

    roject $ngineering and %andling; $ngineering or &esign Analysis; $nvironmental,

    %ealth and 'afety (ssues (denti)cation and Analysis; Constructability (ssues

    (denti)cation an Analysis; roblem (denti)cation and 'olving; and (mprovement

    !pportunities (denti)cation rocesses"

    &etailed *unctions

    The 'ite $ngineer shall assist and get directions from the Technical 'upervisor in

    e+ecuting the following

    -" Review engineering designs or wor.s /applicable to his craft or )eld of

    e+pertise, e"g" civil mechanical, electrical, instrument and control system,

    process, safety, environmental, etc"0 of selected Contractors and con)rm

    their compliance with applicable local and international codes andstandards and sound or established engineering practices"1" &evelop, analy2e or resolve constructability, maintenance and operational

    issues during design or engineering stage of the project"3" $valuate proposed subcontractors and manufacturer of supplied

    equipment of main Contractor and recommend approval or disapproval"

    Conduct site visits as necessary"4" Review Contractors or Vendors Test procedures and witness *actory

    acceptance Tests for selected major equipment and facilities"5" Review Contractors construction methodologies for critical equipment and

    components including safety measures before start of construction" Verify

    compliance of Contractors and Vendors on agreed procedures duringconstruction"

    6" Verify if delivered or installed materials and equipment at site are per

    agreed quantities, quality and required speci)cations7 approved

    construction drawings"8" $valuate progress measurement reports of Contractors" Recommend

    approval or disapproval or changes on the reports"

  • 7/24/2019 SE-Mech'l

    2/2

    9" articipate during pre:commissioning and commissioning stages of the

    project as may be directed by the Technical 'upervisor including review of

    Contractors deliverables such as conduct of training; submission of

    operating and maintenance manuals, as built drawings, etc", conduct of

    operational tests, etc"

    " (nform the roject Team and recommend course of action on current andpotential issues that may have impact on cost, schedule, safety and

    quality of lant or roject"-