Seaborg Decommission James M. Craw Computational Systems Group Lead [email protected] NERSC User Group Meeting September 17, 2007

Upload: lorena-carr

Post on 18-Jan-2018

227 views

Category:

Documents


0 download

DESCRIPTION

NERSC User Group Meeting, September 17, Seaborg Arrives January 2001

TRANSCRIPT

Page 1: Seaborg Decommission James M. Craw Computational Systems Group Lead NERSC User Group Meeting September 17, 2007

Seaborg Decommission

James M. CrawComputational Systems Group Lead

[email protected]

NERSC User Group MeetingSeptember 17, 2007

Page 2: Seaborg Decommission James M. Craw Computational Systems Group Lead NERSC User Group Meeting September 17, 2007

NERSC User Group Meeting, September 17, 2007 2

Seaborg Highlights

Page 3: Seaborg Decommission James M. Craw Computational Systems Group Lead NERSC User Group Meeting September 17, 2007

NERSC User Group Meeting, September 17, 2007 3

Seaborg Arrives

January 2001

Page 4: Seaborg Decommission James M. Craw Computational Systems Group Lead NERSC User Group Meeting September 17, 2007

NERSC User Group Meeting, September 17, 2007 4

June 21, 2001 (N3)

• In the latest ranking of the world's 500 most powerful supercomputers, a 2,528-processor IBM RS/6000 SP system at the U. S. Department of Energy's Lawrence Berkeley National Laboratory is listed as the top unclassified supercomputer on Earth.

• Number 3 Overall.

Page 5: Seaborg Decommission James M. Craw Computational Systems Group Lead NERSC User Group Meeting September 17, 2007

NERSC User Group Meeting, September 17, 2007 5

November 1, 2002 (N3e)

• The U.S. Department of Energy's NERSC Center has signed a contract with IBM to double the size of NERSC's 3,328-processor RS/6000 SP supercomputer, creating a machine with a peak speed of 10 teraflop/s.

• NERSC made the decision to increase the capability of the existing system, rather than purchase an entirely new one. The new equipment to be installed in November with the 6,656-processor IBM system expected to become available to NERSC users by April 2003.

• This is the largest number of processors ever to be made available on an open production system.

Page 6: Seaborg Decommission James M. Craw Computational Systems Group Lead NERSC User Group Meeting September 17, 2007

NERSC User Group Meeting, September 17, 2007 6

March 10, 2003

• The NERSC Center, funded by the U.S. Department of Energy's Office of Science, put its 10 teraflop/s (10 trillion calculations per second) IBM POWER-based supercomputer into service last week.

• Providing researchers across the country with the most powerful computer for unclassified research in the United States.

Page 7: Seaborg Decommission James M. Craw Computational Systems Group Lead NERSC User Group Meeting September 17, 2007

NERSC User Group Meeting, September 17, 2007 7

Seaborg’s Retirement

Page 8: Seaborg Decommission James M. Craw Computational Systems Group Lead NERSC User Group Meeting September 17, 2007

NERSC User Group Meeting, September 17, 2007 8

Seaborg Decommission

Yes, Seaborg is really going away:• Users will be warned regularly and

reminded of the decommission schedule

• There will be no more scheduled maintenance for software or hardware

• Only Emergency maintenance(s) will be performed, if necessary (e.g., Security)

Page 9: Seaborg Decommission James M. Craw Computational Systems Group Lead NERSC User Group Meeting September 17, 2007

NERSC User Group Meeting, September 17, 2007 9

Seaborg Decommission

What’s Going On Today: • Normal 24 x 7 Operations• No Change In Service• Archiving of Inactive users >> HPSS• Opportunity for “Hero Runs” May Exist

Page 10: Seaborg Decommission James M. Craw Computational Systems Group Lead NERSC User Group Meeting September 17, 2007

NERSC User Group Meeting, September 17, 2007 10

Saving Your Seaborg Data

As part of the decommission process: • /home Directories Will be Backed Up and

Put Into User HPSS Accounts as a tar File • /scratch Will NOT be Backed Up• Save Your All Valuable /scratch Data to

HPSS• Help Us by Removing Files You Don’t

Need Archived From /home

Page 11: Seaborg Decommission James M. Craw Computational Systems Group Lead NERSC User Group Meeting September 17, 2007

NERSC User Group Meeting, September 17, 2007 11

Seaborg Decommission

Schedule:

• 01-Nov-2007 - No New User Accounts Created - USG Software Versions Frozen

• 31-Dec-2007 - End of IBM Contract Coverage (Hardware and Software)

• 08-Jan-2008 - End of Allocation Year (AY) All User Jobs Completed

Page 12: Seaborg Decommission James M. Craw Computational Systems Group Lead NERSC User Group Meeting September 17, 2007

NERSC User Group Meeting, September 17, 2007 12

Seaborg Decommission

Schedule (Continued):

• 09-Jan-2008 - Final User Archives to HPSS Started

• 15-Jan-2008 - Hardware Deinstallation Begins; 'Power Off'

• 15-Feb-2008 - Seaborg out of OSF & Excessed According to DOE Rules

Page 13: Seaborg Decommission James M. Craw Computational Systems Group Lead NERSC User Group Meeting September 17, 2007

NERSC User Group Meeting, September 17, 2007 13

Seaborg

January 2001 - January 2008