Page 1: Seattle Center City Streetcar Workshop

What Makes Streetcars Work? Nelson\Nygaard Consulting Associates

Seattle Center City Streetcar Workshop

July 20, 2007

Page 2: Seattle Center City Streetcar Workshop

What Makes Streetcars Work? Nelson\Nygaard Consulting Associates

What Makes Streetcars Work?

Modern Streetcar Applications

Page 3: Seattle Center City Streetcar Workshop

What Makes Streetcars Work? Nelson\Nygaard Consulting Associates

Project Goals• Understand key issues• Identify potential streetcar network and implementation priorities

• Understand that streetcars are only one mode in a major multi-modal system

• Realize that once a route is constructed it can not be altered

Page 4: Seattle Center City Streetcar Workshop

What Makes Streetcars Work? Nelson\Nygaard Consulting Associates

Transit Plan - Goal … Transit every 15 minutes … 18 hours a day … 7 days a week …

Page 5: Seattle Center City Streetcar Workshop

What Makes Streetcars Work? Nelson\Nygaard Consulting Associates

Existing Transit 2006

Page 6: Seattle Center City Streetcar Workshop

What Makes Streetcars Work? Nelson\Nygaard Consulting Associates

Next Phase

Page 7: Seattle Center City Streetcar Workshop

What Makes Streetcars Work? Nelson\Nygaard Consulting Associates

Seattle Connections 2030

Page 8: Seattle Center City Streetcar Workshop

What Makes Streetcars Work? Nelson\Nygaard Consulting Associates

2006 Next 2030

Page 9: Seattle Center City Streetcar Workshop

What Makes Streetcars Work? Nelson\Nygaard Consulting Associates

South Lake Union Streetcar

• Under construction

• Begins operation in fall 2007

• Local Improvement District funding

Page 10: Seattle Center City Streetcar Workshop

What Makes Streetcars Work? Nelson\Nygaard Consulting Associates

Actions to Build on• Center City Circulation Report -2003• Seattle Streetcar Network and Feasibility Analysis -2004

• Westlake Transportation Hub Study -2004

• Seattle Transit Plan -2005

Page 11: Seattle Center City Streetcar Workshop

What Makes Streetcars Work? Nelson\Nygaard Consulting Associates

Actions to Build On• Center City Action Strategy• Alaskan Way Viaduct and Seawall Replacement

• Sound Transit First Hill Transit Connections

• Streetcar Alliance

Page 12: Seattle Center City Streetcar Workshop

What Makes Streetcars Work? Nelson\Nygaard Consulting Associates

Why Consider More Streetcars in Seattle?

• Attracts up to 40% more riders than bus, all conditions held equal.

• New rail lines replacing buses doubled previous bus ridership.

• Attracts “choice” markets.

Page 13: Seattle Center City Streetcar Workshop

What Makes Streetcars Work? Nelson\Nygaard Consulting Associates

What Explains the Difference?Riders Perspective:• Predictable routes and stops

• More stability• Greater ride comfort• Electric – low noise and no fumes

• Nostalgia

Page 14: Seattle Center City Streetcar Workshop

What Makes Streetcars Work? Nelson\Nygaard Consulting Associates

What’s Different about Streetcars?

• Local circulation system• Covers shorter distances• Can operate in mixed traffic

• More frequent stops• Rapid and less costly construction

• Catalyzes pedestrian-friendly development

Page 15: Seattle Center City Streetcar Workshop

What Makes Streetcars Work? Nelson\Nygaard Consulting Associates

Factors Influencing Ridership• Intensity of land use• Mix of land use• Travel time• Frequency• Fares• Connectivity to transit network• Legibility and information• Comfort

Page 16: Seattle Center City Streetcar Workshop

What Makes Streetcars Work? Nelson\Nygaard Consulting Associates

Why Not Just Add Nice Buses?

Streetcars:• Organize development• Often generate private financing

• Attract tourists and occasional riders

• Offer “legibility”• Operate better in pedestrian environments.

Page 17: Seattle Center City Streetcar Workshop

What Makes Streetcars Work? Nelson\Nygaard Consulting Associates

Streetcars do have their drawbacks

• Less flexible• Less maneuverable• Higher maintenance• Once in place it has to succeed

• Higher capital investment

• Overhead wires

Page 18: Seattle Center City Streetcar Workshop

What Makes Streetcars Work? Nelson\Nygaard Consulting Associates

Main differences between streetcar and light rail

Characteristics Streetcar Light RailRight-of-Way Can operate in mixed

trafficMostly exclusive ROW

Stop Spacing Short, every few blocks Wide, often 1/2 mile to 1 mile or more

Vehicles Often shorter (~60 ft); lower capacity (~120 passengers/vehicle)

Longer vehicles (~90 ft); higher capacity (~180 passenger/vehicle)

Route Distance Usually short, less than 5 miles

Usually long, more than 10 miles

Functions / Markets

Supplement or replace local circulation

Regional, long-haul commuter service

Overhead Wire Usually single wire Catenary

Page 19: Seattle Center City Streetcar Workshop

What Makes Streetcars Work? Nelson\Nygaard Consulting Associates

But it’s a fine line…Streetcar line in Pittsburgh (1976)

Page 20: Seattle Center City Streetcar Workshop

What Makes Streetcars Work? Nelson\Nygaard Consulting Associates

But it’s a fine line…Same line using modern LRT vehicles (1999)

Required some track and power upgrades

Page 21: Seattle Center City Streetcar Workshop

What Makes Streetcars Work? Nelson\Nygaard Consulting Associates

Streetcar Vehicle Technologies

• Modern Vehicles– Portland, Tacoma, Toronto

• Restored Vintage Cars– Often PCC cars (San Francisco,

Philadelphia)– Nearly exhausted supply– Non-ADA accessible– Cost to acquire, transport and restore

• New “Replica” Cars– Built from blueprints of old cars

(Charlotte, Memphis)– Can be made ADA accessible

Page 22: Seattle Center City Streetcar Workshop

What Makes Streetcars Work? Nelson\Nygaard Consulting Associates

Advantages of Modern Streetcar Technology

• Lower maintenance• Low floor and ADA accessible

• Higher total capacity• Improved comfort and quieter

• Easier to acquire fleet

Page 23: Seattle Center City Streetcar Workshop

What Makes Streetcars Work? Nelson\Nygaard Consulting Associates

North American Streetcar Examples

Existing Systems (modern technology) Portland• One streetcar

line, serves as local circulation in downtown

• Promotes economic development

• Integrated with buses and LRT

Page 24: Seattle Center City Streetcar Workshop

What Makes Streetcars Work? Nelson\Nygaard Consulting Associates

North American Streetcar Examples

Existing Systems (modern technology) Tacoma• One streetcar

line • Provides local

circulation in downtown

• Designed to enhance economic development.

Page 25: Seattle Center City Streetcar Workshop

What Makes Streetcars Work? Nelson\Nygaard Consulting Associates

Toronto• 11 lines, 10

pass through downtown (both old and new technology)

• Integrated with buses and subway

North American Streetcar Examples

Existing Systems (modern technology)

Page 26: Seattle Center City Streetcar Workshop

What Makes Streetcars Work? Nelson\Nygaard Consulting Associates

North American Streetcar Examples

Existing Systems (heritage)Many examples• San Francisco• Philadelphia• Memphis• New Orleans• Little Rock• Tampa• Tucson• Dallas• Kenosha• Seattle• Charlotte• Others…

Tampa

Memphis

San Francisco “F” Line

Page 27: Seattle Center City Streetcar Workshop

What Makes Streetcars Work? Nelson\Nygaard Consulting Associates

Streetcar Systems Planned or Under Development

Cities considering streetcars:

• Madison• Spokane• Detroit• Sacramento• Vancouver, BC• Atlanta• Boston• Others…

Vancouver, BC

Page 28: Seattle Center City Streetcar Workshop

What Makes Streetcars Work? Nelson\Nygaard Consulting Associates

Streetcars as an Economic Engine

• Portland - more than $3B in economic development

• Public private investment

• Capture funding from new development/investments

Page 29: Seattle Center City Streetcar Workshop

What Makes Streetcars Work? Nelson\Nygaard Consulting Associates

Capturing the Economic Engine

Portland Streetcar After

• Property valuesincreased 40% on route

• Condos on route sell for$275-$350/sf

• 43% of employees use transit

Page 30: Seattle Center City Streetcar Workshop

What Makes Streetcars Work? Nelson\Nygaard Consulting Associates

Keys to a Successful Streetcar Corridor

• High frequency without LRT capacity demands

• Pedestrian- and transit-friendly• Short trips, local access needs and shorter stop spacing

• Corridor to serve a variety of markets • Lack of extreme congestion• Integration with broader transit network• Minimal utility conflicts• Geography

Page 31: Seattle Center City Streetcar Workshop

What Makes Streetcars Work? Nelson\Nygaard Consulting Associates

How to Integrate Streetcars with Existing Transit Services

• Let each system do what it does best!

• Ensure visible and legible connections

• Frequent service rather than timed connections

• Integrated fare media• High quality rider information and way-finding

Page 32: Seattle Center City Streetcar Workshop

What Makes Streetcars Work? Nelson\Nygaard Consulting Associates

How Much do Streetcar Lines Cost?

• Capital Costs– Estimates using current unit costs– Utility and other variable costs

• Operating Costs– Based on a realistic operating plan– Closely coordinated with King County

Metro– Validated against peer systems

Page 33: Seattle Center City Streetcar Workshop

What Makes Streetcars Work? Nelson\Nygaard Consulting Associates

Streetcar Costs• Operating Costs

– Portland experience: $3.7 million annual, $140/ revenue hour

• Capital Costs– Cost/mile: Portland ($23.7 to 26.3 million/mile)– Modern vehicles: $2.5 – $4.2 million / vehicle

(average $2.9 million)• What drives up the cost?

– Geography, turning movements, etc.– Utility relocation

Page 34: Seattle Center City Streetcar Workshop

What Makes Streetcars Work? Nelson\Nygaard Consulting Associates

Potential Funding Sources• Federal:

– New Starts/Small Starts• Focuses on streetcar, trolley and bus rapid

transit• Projects less than $75 million federal share• Total costs cannot exceed $250 million• Goal is expedited review process• Expect significant competition for funds

• State/Regional funding• City general funds• King County Metro • Tax increment financing• Parking revenues• Local improvement district• Endowment funds

Page 35: Seattle Center City Streetcar Workshop

What Makes Streetcars Work? Nelson\Nygaard Consulting Associates

Candidate CorridorsCenter City “Seattle Connections” routes are initial candidates for streetcar service. Today:• Criteria Evaluation• Mapping Exercise