secondary school @wilson construction workers parking during excavation and sheeting/ shoring will...

3
November 1, 2017 1 Completed and ongoing tasks: Construction trailers setup completed. Excavation and sheeting/shoring ongoing. Starting rebar work for footing and foundation. Construction activities next month: Continuing excavation. Temporary construction power will be installed. Below grade waterproofing will be installed. Tower crane will be erected. Concrete footings and foundation walls will be installed. Process related activities: Building Level Planning Committee meeting will be held in early December. Construction workers parking during excavation and sheeting/ shoring will be on-site. Secondary School @Wilson Community Newsletter (October 2017)

Upload: dolien

Post on 17-Mar-2018

223 views

Category:

Documents


3 download

TRANSCRIPT

November 1, 2017 1

Completed and ongoing tasks:

• Construction trailers setup completed.

• Excavation and sheeting/shoring ongoing.

• Starting rebar work for footing and foundation.

Construction activities next month:

• Continuing excavation.

• Temporary construction power will be installed.

• Below grade waterproofing will be installed.

• Tower crane will be erected.

• Concrete footings and foundation walls will be installed.

Process related activities:

• Building Level Planning Committee meeting will be held in early December.

• Construction workers parking during excavation and sheeting/ shoring will be on-site.

Secondary School @Wilson

Community Newsletter (October 2017)

November 1, 2017 2

Time capsule ceremony

Time capsule ceremony

Dewatering pump

November 1, 2017 3

Excavation for concrete pad at elevator tower

Pile 3D monitoring station