section 024119 - selective demolition 02-09 specifications.pdfconduct selective demolition so...

92
KCTCS System Office Renovation November 12, 2018 Copy Center Fit-up – Versailles, Kentucky EOP# 201732 SELECTIVE DEMOLITION 024119 - 1 SECTION 024119 - SELECTIVE DEMOLITION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section. 1.2 SUMMARY A. Section Includes: 1. Demolition and removal of selected portions of building or structure. 2. Demolition and removal of selected site elements. 3. Salvage of existing items to be reused or recycled. B. Related Requirements: 1. Section 011000 "Summary" for restrictions on use of the premises, Owner-occupancy requirements, and phasing requirements. 2. Section 015639 "Temporary Tree and Plant Protection" for temporary protection of existing trees and plants that are affected by selective demolition. 3. Section 017300 "Execution" for cutting and patching procedures. 4. Section 013516 "Alteration Project Procedures" for general protection and work procedures for alteration projects. 5. Section 311000 "Site Clearing" for site clearing and removal of above- and below-grade improvements not part of selective demolition. 1.3 DEFINITIONS A. Remove: Detach items from existing construction and dispose of them off-site unless indicated to be salvaged or reinstalled. B. Remove and Salvage: Detach items from existing construction, in a manner to prevent damage, and [deliver to Owner ready for reuse] [store]. C. Remove and Reinstall: Detach items from existing construction, in a manner to prevent damage, prepare for reuse, and reinstall where indicated. D. Existing to Remain: Leave existing items that are not to be removed and that are not otherwise indicated to be salvaged or reinstalled. E. Dismantle: To remove by disassembling or detaching an item from a surface, using gentle methods and equipment to prevent damage to the item and surfaces; disposing of items unless indicated to be salvaged or reinstalled.

Upload: others

Post on 21-Mar-2020

5 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

SELECTIVE DEMOLITION 024119 - 1

SECTION 024119 - SELECTIVE DEMOLITION

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Demolition and removal of selected portions of building or structure.2. Demolition and removal of selected site elements.3. Salvage of existing items to be reused or recycled.

B. Related Requirements:

1. Section 011000 "Summary" for restrictions on use of the premises, Owner-occupancy requirements, and phasing requirements.

2. Section 015639 "Temporary Tree and Plant Protection" for temporary protection of existing trees and plants that are affected by selective demolition.

3. Section 017300 "Execution" for cutting and patching procedures.4. Section 013516 "Alteration Project Procedures" for general protection and work

procedures for alteration projects.5. Section 311000 "Site Clearing" for site clearing and removal of above- and below-grade

improvements not part of selective demolition.

1.3 DEFINITIONS

A. Remove: Detach items from existing construction and dispose of them off-site unless indicated to be salvaged or reinstalled.

B. Remove and Salvage: Detach items from existing construction, in a manner to prevent damage, and [deliver to Owner ready for reuse] [store].

C. Remove and Reinstall: Detach items from existing construction, in a manner to prevent damage, prepare for reuse, and reinstall where indicated.

D. Existing to Remain: Leave existing items that are not to be removed and that are not otherwise indicated to be salvaged or reinstalled.

E. Dismantle: To remove by disassembling or detaching an item from a surface, using gentle methods and equipment to prevent damage to the item and surfaces; disposing of items unless indicated to be salvaged or reinstalled.

Page 2: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

SELECTIVE DEMOLITION 024119 - 2

1.4 MATERIALS OWNERSHIP

A. Unless otherwise indicated, demolition waste becomes property of Contractor.

B. Historic items, relics, antiques, and similar objects including, but not limited to, cornerstones and their contents, commemorative plaques and tablets, and other items of interest or value to Owner that may be uncovered during demolition remain the property of Owner.

1. Carefully salvage in a manner to prevent damage and promptly return to Owner.

1.5 PREINSTALLATION MEETINGS

A. Predemolition Conference: Conduct conference at [Project site] <Insert location>.

1. Inspect and discuss condition of construction to be selectively demolished.2. Review structural load limitations of existing structure.3. Review and finalize selective demolition schedule and verify availability of materials,

demolition personnel, equipment, and facilities needed to make progress and avoid delays.

4. Review requirements of work performed by other trades that rely on substrates exposed by selective demolition operations.

5. Review areas where existing construction is to remain and requires protection.

1.6 INFORMATIONAL SUBMITTALS

A. Qualification Data: For refrigerant recovery technician.

B. Engineering Survey: Submit engineering survey of condition of building.

C. Proposed Protection Measures: Submit report, including Drawings, that indicates the measures proposed for protecting individuals and property[, for environmental protection] [, for dust control] [and] [, for noise control]. Indicate proposed locations and construction of barriers.

D. Schedule of Selective Demolition Activities: Indicate the following:

1. Detailed sequence of selective demolition and removal work, with starting and ending dates for each activity. Ensure Owner's [building manager's] [and] [other tenants'] on-site operations are uninterrupted.

2. Interruption of utility services. Indicate how long utility services will be interrupted.3. Coordination for shutoff, capping, and continuation of utility services.4. Use of elevator and stairs.5. Coordination of Owner's continuing occupancy of portions of existing building and of

Owner's partial occupancy of completed Work.

E. Predemolition Photographs or Video: Show existing conditions of adjoining construction, including finish surfaces, that might be misconstrued as damage caused by demolition operations. Comply with Section 013233 "Photographic Documentation." Submit before Work begins.

F. Statement of Refrigerant Recovery: Signed by refrigerant recovery technician responsible for recovering refrigerant, stating that all refrigerant that was present was recovered and that recovery was performed according to EPA regulations. Include name and address of technician and date refrigerant was recovered.

rhinson
Rectangle
rhinson
Snapshot
Page 3: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

SELECTIVE DEMOLITION 024119 - 3

G. Warranties: Documentation indicating that existing warranties are still in effect after completion of selective demolition.

1.7 CLOSEOUT SUBMITTALS

A. Inventory: Submit a list of items that have been removed and salvaged.

1.8 QUALITY ASSURANCE

A. Refrigerant Recovery Technician Qualifications: Certified by an EPA-approved certification program.

1.9 FIELD CONDITIONS

A. Owner will occupy portions of building immediately adjacent to selective demolition area. Conduct selective demolition so Owner's operations will not be disrupted.

B. Conditions existing at time of inspection for bidding purpose will be maintained by Owner as far as practical.

1. Before selective demolition, Owner will remove the following items:

a. <Insert items to be removed by Owner>.

C. Notify Architect of discrepancies between existing conditions and Drawings before proceeding with selective demolition.

D. Hazardous Materials: It is not expected that hazardous materials will be encountered in the Work.

1. Hazardous materials will be removed by Owner before start of the Work.2. If suspected hazardous materials are encountered, do not disturb; immediately notify

Architect and Owner. Hazardous materials will be removed by Owner under a separate contract.

E. Hazardous Materials: Present in buildings and structures to be selectively demolished. A report on the presence of hazardous materials is on file for review and use. Examine report to become aware of locations where hazardous materials are present.

1. Hazardous material remediation is specified elsewhere in the Contract Documents.2. Do not disturb hazardous materials or items suspected of containing hazardous materials

except under procedures specified elsewhere in the Contract Documents.3. Owner will provide material safety data sheets for suspected hazardous materials that

are known to be present in buildings and structures to be selectively demolished because of building operations or processes performed there.

F. Historic Areas: Demolition and hauling equipment and other materials shall be of sizes that clear surfaces within historic spaces, areas, rooms, and openings, including temporary protection, by [12 inches (300 mm)] <Insert dimension> or more.

G. Storage or sale of removed items or materials on-site is not permitted.

rhinson
Rectangle
rhinson
Snapshot
Page 4: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

SELECTIVE DEMOLITION 024119 - 4

H. Utility Service: Maintain existing utilities indicated to remain in service and protect them against damage during selective demolition operations.

1. Maintain fire-protection facilities in service during selective demolition operations.

1.10 WARRANTY

A. Existing Warranties: Remove, replace, patch, and repair materials and surfaces cut or damaged during selective demolition, by methods and with materials and using approved contractors so as not to void existing warranties. Notify warrantor before proceeding. Existing warranties include the following:

1. <Insert warranted system>.

B. Notify warrantor on completion of selective demolition, and obtain documentation verifying that existing system has been inspected and warranty remains in effect. Submit documentation at Project closeout.

1.11 COORDINATION

A. Arrange selective demolition schedule so as not to interfere with Owner's operations.

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. Regulatory Requirements: Comply with governing EPA notification regulations before beginning selective demolition. Comply with hauling and disposal regulations of authorities having jurisdiction.

B. Standards: Comply with ASSE A10.6 and NFPA 241.

C. <Double click to insert sustainable design text for building reuse.>

PART 3 - EXECUTION

3.1 EXAMINATION

A. Verify that utilities have been disconnected and capped before starting selective demolition operations.

B. Review Project Record Documents of existing construction or other existing condition and hazardous material information provided by Owner. Owner does not guarantee that existing conditions are same as those indicated in Project Record Documents.

C. [Perform] [Engage a professional engineer to perform] an engineering survey of condition of building to determine whether removing any element might result in structural deficiency or unplanned collapse of any portion of structure or adjacent structures during selective building demolition operations.

rhinson
Rectangle
rhinson
Snapshot
Page 5: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

SELECTIVE DEMOLITION 024119 - 5

1. Perform surveys as the Work progresses to detect hazards resulting from selective demolition activities.

D. Steel Tendons: Locate tensioned steel tendons and include recommendations for de-tensioning.

E. Verify that hazardous materials have been remediated before proceeding with building demolition operations.

F. Survey of Existing Conditions: Record existing conditions by use of [measured drawings] [preconstruction photographs or video] [and] [templates].

1. Comply with requirements specified in Section 013233 "Photographic Documentation."2. Inventory and record the condition of items to be removed and salvaged. Provide

photographs or video of conditions that might be misconstrued as damage caused by salvage operations.

3. Before selective demolition or removal of existing building elements that will be reproduced or duplicated in final Work, make permanent record of measurements, materials, and construction details required to make exact reproduction.

3.2 PREPARATION

A. Refrigerant: Before starting demolition, remove refrigerant from mechanical equipment according to 40 CFR 82 and regulations of authorities having jurisdiction.

3.3 UTILITY SERVICES AND MECHANICAL/ELECTRICAL SYSTEMS

A. Existing Services/Systems to Remain: Maintain services/systems indicated to remain and protect them against damage.

B. Existing Services/Systems to Be Removed, Relocated, or Abandoned: Locate, identify, disconnect, and seal or cap off utility services and mechanical/electrical systems serving areas to be selectively demolished.

1. Owner will arrange to shut off indicated services/systems when requested by Contractor.2. Arrange to shut off utilities with utility companies.3. If services/systems are required to be removed, relocated, or abandoned, provide

temporary services/systems that bypass area of selective demolition and that maintain continuity of services/systems to other parts of building.

4. Disconnect, demolish, and remove fire-suppression systems, plumbing, and HVAC systems, equipment, and components indicated on Drawings to be removed.

a. Piping to Be Removed: Remove portion of piping indicated to be removed and cap or plug remaining piping with same or compatible piping material.

b. Piping to Be Abandoned in Place: Drain piping and cap or plug piping with same or compatible piping material and leave in place.

c. Equipment to Be Removed: Disconnect and cap services and remove equipment.d. Equipment to Be Removed and Reinstalled: Disconnect and cap services and

remove, clean, and store equipment; when appropriate, reinstall, reconnect, and make equipment operational.

e. Equipment to Be Removed and Salvaged: Disconnect and cap services and remove equipment and deliver to Owner.

f. Ducts to Be Removed: Remove portion of ducts indicated to be removed and plug remaining ducts with same or compatible ductwork material.

rhinson
Rectangle
rhinson
Snapshot
Page 6: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

SELECTIVE DEMOLITION 024119 - 6

g. Ducts to Be Abandoned in Place: Cap or plug ducts with same or compatible ductwork material and leave in place.

3.4 PROTECTION

A. Temporary Protection: Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain.

1. Provide protection to ensure safe passage of people around selective demolition area and to and from occupied portions of building.

2. Provide temporary weather protection, during interval between selective demolition of existing construction on exterior surfaces and new construction, to prevent water leakage and damage to structure and interior areas.

3. Protect walls, ceilings, floors, and other existing finish work that are to remain or that are exposed during selective demolition operations.

4. Cover and protect furniture, furnishings, and equipment that have not been removed.5. Comply with requirements for temporary enclosures, dust control, heating, and cooling

specified in Section 015000 "Temporary Facilities and Controls."

B. Temporary Shoring: Design, provide, and maintain shoring, bracing, and structural supports as required to preserve stability and prevent movement, settlement, or collapse of construction and finishes to remain, and to prevent unexpected or uncontrolled movement or collapse of construction being demolished.

1. Strengthen or add new supports when required during progress of selective demolition.

C. Remove temporary barricades and protections where hazards no longer exist.

3.5 SELECTIVE DEMOLITION, GENERAL

A. General: Demolish and remove existing construction only to the extent required by new construction and as indicated. Use methods required to complete the Work within limitations of governing regulations and as follows:

1. Proceed with selective demolition systematically, from higher to lower level. Complete selective demolition operations above each floor or tier before disturbing supporting members on the next lower level.

2. Neatly cut openings and holes plumb, square, and true to dimensions required. Use cutting methods least likely to damage construction to remain or adjoining construction. Use hand tools or small power tools designed for sawing or grinding, not hammering and chopping. Temporarily cover openings to remain.

3. Cut or drill from the exposed or finished side into concealed surfaces to avoid marring existing finished surfaces.

4. Do not use cutting torches until work area is cleared of flammable materials. At concealed spaces, such as duct and pipe interiors, verify condition and contents of hidden space before starting flame-cutting operations. Maintain portable fire-suppression devices during flame-cutting operations.

5. Maintain fire watch during and for at least <Insert number> hours after flame-cutting operations.

6. Maintain adequate ventilation when using cutting torches.7. Remove decayed, vermin-infested, or otherwise dangerous or unsuitable materials and

promptly dispose of off-site.

rhinson
Rectangle
rhinson
Snapshot
Page 7: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

SELECTIVE DEMOLITION 024119 - 7

8. Remove structural framing members and lower to ground by method suitable to avoid free fall and to prevent ground impact or dust generation.

9. Locate selective demolition equipment and remove debris and materials so as not to impose excessive loads on supporting walls, floors, or framing.

10. Dispose of demolished items and materials promptly.[ Comply with requirements in Section 017419 "Construction Waste Management and Disposal."]

B. Site Access and Temporary Controls: Conduct selective demolition and debris-removal operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.

C. Work in Historic Areas: Selective demolition may be performed only in areas of Project that are not designated as historic. In historic spaces, areas, and rooms, or on historic surfaces, the terms "demolish" or "remove" shall mean historic "removal" or "dismantling" as specified in Section 024296 "Historic Removal and Dismantling."

D. Removed and Salvaged Items:

1. Clean salvaged items.2. Pack or crate items after cleaning. Identify contents of containers.3. Store items in a secure area until delivery to Owner.4. Transport items to Owner's storage area [on-site] [off-site] [designated by Owner]

[indicated on Drawings].5. Protect items from damage during transport and storage.

E. Removed and Reinstalled Items:

1. Clean and repair items to functional condition adequate for intended reuse.2. Pack or crate items after cleaning and repairing. Identify contents of containers.3. Protect items from damage during transport and storage.4. Reinstall items in locations indicated. Comply with installation requirements for new

materials and equipment. Provide connections, supports, and miscellaneous materials necessary to make item functional for use indicated.

F. Existing Items to Remain: Protect construction indicated to remain against damage and soiling during selective demolition. When permitted by Architect, items may be removed to a suitable, protected storage location during selective demolition[ and cleaned] and reinstalled in their original locations after selective demolition operations are complete.

3.6 SELECTIVE DEMOLITION PROCEDURES FOR SPECIFIC MATERIALS

A. Concrete: Demolish in small sections. Using power-driven saw, cut concrete to a depth of at least 3/4 inch (19 mm) at junctures with construction to remain. Dislodge concrete from reinforcement at perimeter of areas being demolished, cut reinforcement, and then remove remainder of concrete. Neatly trim openings to dimensions indicated.

B. Concrete: Demolish in sections. Cut concrete full depth at junctures with construction to remain and at regular intervals using power-driven saw, and then remove concrete between saw cuts.

C. Masonry: Demolish in small sections. Cut masonry at junctures with construction to remain, using power-driven saw, and then remove masonry between saw cuts.

D. Concrete Slabs-on-Grade: Saw-cut perimeter of area to be demolished, and then break up and remove.

rhinson
Rectangle
rhinson
Snapshot
Page 8: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

SELECTIVE DEMOLITION 024119 - 8

E. Resilient Floor Coverings: Remove floor coverings and adhesive according to recommendations in RFCI's "Recommended Work Practices for the Removal of Resilient Floor Coverings."[ Do not use methods requiring solvent-based adhesive strippers.]

F. Roofing: Remove no more existing roofing than what can be covered in one day by new roofing and so that building interior remains watertight and weathertight. See Section <Insert Section number and title> for new roofing requirements.

1. Remove existing roof membrane, flashings, copings, and roof accessories.2. Remove existing roofing system down to substrate.

3.7 DISPOSAL OF DEMOLISHED MATERIALS

A. Remove demolition waste materials from Project site [and dispose of them in an EPA-approved construction and demolition waste landfill acceptable to authorities having jurisdiction.] [and recycle or dispose of them according to Section 017419 "Construction Waste Management and Disposal."]

1. Do not allow demolished materials to accumulate on-site.2. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces

and areas.3. Remove debris from elevated portions of building by chute, hoist, or other device that will

convey debris to grade level in a controlled descent.4. Comply with requirements specified in Section 017419 "Construction Waste Management

and Disposal."

B. Burning: Do not burn demolished materials.

3.8 CLEANING

A. Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Return adjacent areas to condition existing before selective demolition operations began.

3.9 SELECTIVE DEMOLITION SCHEDULE

A. Remove: <Insert description of items and construction to remove>.

B. Remove and Salvage: <Insert description of items to remove and salvage>.

C. Remove and Reinstall: <Insert description of items to remove and reinstall>.

D. Existing to Remain: <Insert description of items to remain>.

E. Dismantle: <Insert description of items to be removed>.

END OF SECTION 024119

rhinson
Rectangle
rhinson
Snapshot
Page 9: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation

Copy Center Fit-up – Versailles, Kentucky

November 12, 2018EOP#201732

CAST-IN-PLACE CONCRETE 033000 - 1

SECTION 033000 – CAST-IN-PLACE CONCRETE

PART 1 – GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section specifies cast-in-place concrete, including formwork, reinforcement, concrete materials, mixture design, placement procedures, and finishes. This section applies to concrete work shown on the structural drawings. See Division 32 for site concrete.

B. Cast-in-place concrete includes the following:

1. Slabs-on-grade.

C. Related Sections: The following Sections contain requirements that relate to this Section:

D. Coordination: Unless other satisfactory agreements are specifically entered into by contractors concerned, all miscellaneous iron and steel, sleeves, anchors, etc., required by work of other contractors, will be furnished and installed by such other contractors with the cooperation of this contractor.

1.3 DEFINITIONS

A. Cementitious Materials: Portland cement alone or in combination with one or more of the following: blended hydraulic cement, fly ash, slag cement, other pozzolans, and silica fume; materials subject to compliance with requirements.

B. W/C Ratio: The ratio by weight of water to cementitious materials.

1.4 ACTION SUBMITTALS

A. General: Furnish submittals in quantity, format, and other Conditions of the Contract and as specified in Division 1 of the Project Manual.

B. Design Mixtures: For each concrete mixture with laboratory test reports for the following data. Submit alternate design mixtures when characteristics of materials, Project conditions, weather, test results, or other circumstances warrant adjustments.

1. Method used to determine the proposed mix design (per ACI 301, Section 4).2. Gradation and quantity of fine and coarse aggregates.3. Proportions of all ingredients including all admixtures added either at the time of

batching or at the job site. Indicate amounts of mixing water to be withheld for later addition at Project site.

rhinson
Rectangle
rhinson
Snapshot
Page 10: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation

Copy Center Fit-up – Versailles, Kentucky

November 12, 2018EOP#201732

CAST-IN-PLACE CONCRETE 033000 - 2

4. Water/cement ratio and water/cementitious ratio.5. Slump – ASTM C143.6. Certification and test results of the total water soluble chloride ion content of the

design mix – FHWA RD-77 or AASHTO T 260-84.7. Air content of freshly mixed concrete by the pressure method, ASTM C231, or the

volumetric method, ASTM C173.8. Unit weight of concrete – ASTM C138.9. Strength at 7- and 28-days for structural concrete– ASTM C39. Document strength on

basis of previous field experience or trial mixtures, per ACI 301 Section 4. Submit strength test records, mix design materials, conditions, and proportions for concrete used for record of tests, standard calculation, and determination of required average compressive strength.

10. Strength at 7- and 28-days for polished concrete surfaces– ASTM C39. Document strength on basis of trial mixture (mandatory), per ACI 301 Section 4. Submit strength test records, mix design materials, conditions, and proportions for concrete used for record of tests, standard calculation, and determination of required average compressive strength.

11. Complete and include Structural Engineer’s standard mix design submittal form for each mix. A blank copy is included at the end of this section.

C. Steel Reinforcement Shop Drawings: Fabrication and placing drawings for reinforcement detailing, fabricating, bending, and placing concrete reinforcement. Comply with ACI 315 “Manual of Standard Practice for Detailing Reinforced Concrete Structures” showing bar sizes, lengths, material, grade, bar schedules, stirrup spacing, bent bar diagrams, bar arrangement, splices and laps, tie spacing, and supports for concrete reinforcement. Include special reinforcing required for openings through concrete structures.

1. Computer generated electronic structural construction document files (ACAD) will be made available to the Contractor. The Contractor will be required to sign the Engineer’s standard release of liability form and pay a handling fee of $50.00 per drawing prior to receiving the drawing files. Rules for use of said files shall be as defined in the CRSI “Code of Standard Practice” Sections 4.19 and 6.4.1.

2. Shop drawing resubmittals are reviewed for conformance with review marks only. Any changes or questions originating on a resubmittal shall be clearly clouded.

D. Product Data: For proprietary materials and items, including reinforcement, admixtures, vapor retarder, construction joint slip dowels, joint systems, curing compounds, and others if requested by Architect.

1.5 INFORMATIONAL SUBMITTALS

A. General: Furnish submittals in quantity, format, and other Conditions of the Contract and as specified in Division 1 of the Project Manual.

B. Laboratory test reports for concrete materials or material certificates in lieu of material laboratory test reports. Material certificates shall be signed by Manufacturer and Contractor, certifying that each material item complies with or exceeds specified requirements. Provide certification from admixture manufacturers that chloride content complies with specification requirements.

C. Survey of the as-built locations of anchor rods, foundation bolts, and other embedded items shall be submitted to the Architect, Engineer, and General Contractor.

D. Written notification that the concrete in the footings or other bearing support has attained, on the basis of an appropriate ASTM standard test method of field-cured samples, a minimum of 75% of the intended minimum compressive design strength.

rhinson
Rectangle
rhinson
Snapshot
Page 11: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation

Copy Center Fit-up – Versailles, Kentucky

November 12, 2018EOP#201732

CAST-IN-PLACE CONCRETE 033000 - 3

E. Floor Surface Flatness and Levelness Measurements: Submit record of all F-number tests, including a plan of the specific locations tested and the test results, to the Architect for their records.

1.6 QUALITY ASSURANCE

A. Codes and Standards: Comply with provisions of the following codes, specifications, and standards, except where more stringent requirements are shown or specified. Each contractor having reference to ACI Documents shall maintain copies of same on project site.

AMERICAN CONCRETE INSTITUTE

1. ACI 117-10 – Specifications for Tolerances for Concrete Construction and Materials.2. ACI 211.1-91 – Standard Practice for Selecting Proportions Normal, Heavyweight and

Mass Concrete (Reapproved 2009).3. ACI 301-10 – Specification for Structural Concrete.4. ACI 302.1R-04 – Guide for Concrete Floor and Slab Construction.5. ACI 304.2R-96 – Placing Concrete by Pumping Methods (Reapproved 2008).6. ACI 305R-10 – Guide to Hot Weather Concreting.7. ACI 306R-10 – Guide to Cold Weather Concreting.8. ACI 308R-01 – Guide to Curing Concrete (Reapproved 2008).9. ACI 309R-05 – Guide for Consolidation of Concrete.10. ACI 311.1R-07 – ACI Manual of Concrete Inspection.11. ACI 318-11 – Building Code Requirements for Structural Concrete and Commentary.12. SP-66 – ACI Detailing Manual.

CONCRETE REINFORCING STEEL INSTITUTE (CRSI):

1. CRSI – Manual of Standard Practice.2. CRSI 63 – Recommended Practice for Placing Reinforcing Bars.3. CRSI 65 – Recommended Practice for Placing Bar Nomenclature.

B. Qualifications of Workers: Use adequate numbers of skilled workers who are thoroughly trained and experienced in the necessary crafts and who are completely familiar with the specified requirements and the methods needed for proper execution of the work required by this Division.

C. Manufacturer Qualifications: A firm experienced in manufacturing ready-mixed concrete products and that complies with ASTM C 94 requirements for production facilities and equipment.

D. Contractor shall be responsible for conducting a survey of the as-built locations of anchor rods, foundation bolts, and other embedded items. Survey to include embed placement, bolt projection, and top of foundation elevation. Survey to be conducted by a Professional Land Surveyor.

1.7 DELIVERY, STORAGE, AND HANDLING

A. Deliver steel reinforcement and concrete to Project site in such quantities and at such times to ensure continuity of installation.

B. Store materials to permit easy access for inspection and identification. Keep steel reinforcement off ground by using pallets, platforms, dunnage, or other supports and spacers.

rhinson
Rectangle
rhinson
Snapshot
Page 12: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation

Copy Center Fit-up – Versailles, Kentucky

November 12, 2018EOP#201732

CAST-IN-PLACE CONCRETE 033000 - 4

C. Do not store materials on structure in a manner that might cause distortion, damage, or overload to members or supporting structures. Repair or replace damaged materials or structures as directed.

PART 2 - PRODUCTS

2.1 FORM MATERIALS

A. Forms for Unexposed, Rough-Formed Finish Concrete: Plywood, lumber, metal or another acceptable material. Provide lumber dressed on at least two edges and one side for tight fit.

B. Chamfer Strips: Non-staining dressed wood, metal, PVC, or rubber strips; ¾ by ¾ inch, minimum, and as shown on Drawings; in longest practical lengths.

C. Form-Release Agent: Commercially formulated form-release agent with a maximum volatile organic compounds (VOCs) not to exceed those allowable by jurisdictional regulations, that will not bond with, stain, or adversely affect concrete surfaces and will not impair subsequent treatments of concrete surfaces.

1. Formulate form-release agent with rust inhibitor for steel form-facing materials.

D. Form Joint Tape: Compressible foam tape; pressure sensitive; AAMA800, “Specification 810.1, Expanded Cellular Glazing Tape”; minimum ¼ inch thick.

E. Form Joint Sealant: Elastomeric sealant complying with ASTM C920, Type M or S, Grade NS, that adheres to form joint substrates.

F. Sealer: Penetrating, clear, polyurethane wood form sealer formulated to reduce absorption of bleed water and prevent migration of set-retarding chemicals from wood.

2.2 REINFORCING MATERIALS

A. Reinforcing Bars: ASTM A 615, Grade 60, deformed.

B. Welded Wire Fabric: ASTM A 1064, plain, fabricated from as-drawn steel wire into flat sheets.

C. Smooth Joint Dowel Bars: ASTM A36, plain-steel bars, cut true to length with ends square and free of burrs.

D. Bar Supports: Bolsters, chairs, spacers, and other devices for spacing, supporting, and fastening reinforcing bars in place. Manufacture bar supports from steel wire, plastic, or precast concrete according to CRSI's "Manual of Standard Practice," of greater compressive strength than concrete and as follows:

E. Fabric Supports: Chairs for spacing, supporting welded wire fabric in place. Use continuous wire chairs complying with CRSI specifications.

1. For slabs-on-grade, use supports with sand plates or horizontal runners where base material will not support chair legs.

2.3 CONCRETE MATERIALS

A. Source Limitations: Obtain each type or class of cementitious material of the same brand from the same manufacturer's plant, obtain aggregate from single source, and obtain admixtures from single source from single manufacturer.

rhinson
Rectangle
rhinson
Snapshot
Page 13: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation

Copy Center Fit-up – Versailles, Kentucky

November 12, 2018EOP#201732

CAST-IN-PLACE CONCRETE 033000 - 5

B. Cementitious Materials:

1. Portland Cement: ASTM C 150, Type I. High early strength (when specified), ASTM C150, Type III. One brand of cement shall be used throughout Project duration unless otherwise acceptable to Engineer.

2. Fly Ash: ASTM C 618, Class F or C, except maximum loss on ignition: 3%.

C. Normal-Weight Aggregates: ASTM C 33 Class 3S coarse aggregate or better, graded, and as specified. Provide aggregates from a single source for exposed concrete.

1. For exposed exterior surfaces, do not use fine or coarse aggregates that contain substances considered deleterious or that cause spalling or surface discoloration due to oxidation.

2. Fine Aggregate to be free of materials with deleterious reactivity to alkali in cement.

D. Water: ASTM C 94 and potable.

E. Chemical Admixtures: Certified by manufacturer to be compatible with other admixtures and that do not contribute water-soluble chloride ions exceeding those permitted in hardened concrete. Do not use calcium chloride or admixtures containing calcium chloride.

1. Water-Reducing Admixture: ASTM C 494, Type A.2. Retarding Admixture: ASTM C 494, Type B.3. Water-Reducing and Retarding Admixture: ASTM C 494, Type D.4. Water-Reducing and Accelerating Admixture: ASTM C 494, Type E.5. High-Range, Water-Reducing Admixture: ASTM C 494, Type F.6. High-Range, Water-Reducing and Retarding Admixture: ASTM C 494, Type G.7. Plasticizing and Retarding Admixture: ASTM C 1017, Type II.8. Air-Entraining Admixture: ASTM C 260.

2.4 RELATED MATERIALS

A. Anchor Rods, Bolts, Nuts, and Washers: As follows:

1. Non-High Strength Rods (Straight, Headed or Threaded) for heavy structural steel, PEMB, and precast concrete elements: ASTM F1554 Grade 36 and heavy hex carbon-steel nuts.

2. Plate Washers: ASTM A36.

B. Construction joint slip dowels: steel rod or plate in a plastic insert to allow contraction of the concrete while preventing vertical differential displacement.

1. Available Products: Subject to compliance with requirements, products that may be incorporated in the Work include, but are not limited to, the following:

a. #4x1’-6” long, Speed Dowel by Sika Greenstreak.b. ¼” plate, Diamond Dowel by PNA, Inc.c. ¼” plate, Speed Plate by Sika Greenstreak.

C. Sheet Vapor Retarder: Polyethylene sheet, ASTM D 4397, not less than 10 mils thick.

D. Bonding Agent: ASTM C 1059, Type II, nonredispersible, acrylic emulsion or styrene butadiene.

E. Epoxy Adhesive: ASTM C 881, two-component epoxy resin, capable of humid curing and bonding to damp surfaces, of class suitable for application temperature and of grade to suit Project requirements.

rhinson
Rectangle
rhinson
Snapshot
Page 14: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation

Copy Center Fit-up – Versailles, Kentucky

November 12, 2018EOP#201732

CAST-IN-PLACE CONCRETE 033000 - 6

1. Manufacturers: Subject to compliance with requirements, manufacturers offering products that may be incorporated in the Work include, but are not limited to, the following:

a. Dayton Superior.b. Euclid Chemical Company.c. BASF Corporation.d. W.R. Meadows, Inc.e. Sika Corporation.

F. Cartridge Injection Acrylic Adhesive (for reinforcing dowels): two-component material for use in concrete. Anchor to be approved for use with cracked concrete per AC308.

1. Acrylic resin adhesive, suitable for use on dry or damp surfaces. Available Products: Subject to compliance with requirements, products that may be incorporated in the Work include, but are not limited to, the following:

a. HIT HY 200 System, Hilti.b. AC 100 System, Powers.c. AT-XP System, Simpson/Strong-Tie.

2.5 CURING MATERIALS

A. Absorptive Cover: AASHTO M 182, Class 2, burlap cloth made from jute or kenaf, weighing approximately 9 oz./sq. yd. when dry.

B. Moisture-Retaining Cover: ASTM C 171, polyethylene film or white burlap-polyethylene sheet.

C. Water: Potable.

D. Evaporation Retarder: Waterborne, monomolecular film forming, manufactured for application to fresh concrete for temporary protection from rapid moisture loss.

1. Manufacturers: Subject to compliance with requirements, manufacturers offering products that may be incorporated in the Work include, but are not limited to, the following:

a. BASF Corporation.b. ChemMasters, Inc.c. Dayton Superior.d. Euclid Chemical Company.e. Kaufman Products, Inc.f. L&M Construction Chemicals, Inc.g. Lambert Corporation.h. Metalcrete Industries.i. Sika Corporation.j. SpecChem, LLC.k. W. R. Meadows, Inc.

E. Clear, Waterborne, Membrane-Forming Curing Compound: ASTM C 309, Type 1, Class B, 18 to 25 percent solids, nondissipating.

1. Manufacturers: Subject to compliance with requirements, manufacturers offering products that may be incorporated in the Work include, but are not limited to, the following:

rhinson
Rectangle
rhinson
Snapshot
Page 15: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation

Copy Center Fit-up – Versailles, Kentucky

November 12, 2018EOP#201732

CAST-IN-PLACE CONCRETE 033000 - 7

a. BASF Corporation.b. ChemMasters, Inc.c. Dayton Superior.d. Euclid Chemical Company.e. L&M Construction Chemicals, Inc.f. Lambert Corporation.g. Metalcrete Industries.h. SpecChem, LLC.i. W. R. Meadows, Inc.

2.6 PROPORTIONING AND DESIGNING MIXES

A. Prepare design mixes for each type and strength of concrete, proportioned on the basis of laboratory trial mixture or field data methods, or both, according to ACI 301. Use an independent testing agency for preparing and reporting proposed mixture designs based on laboratory trial mixtures. Trial batch and field experience tests shall have been performed within 12 months of submittal date. Use mix design submittal form included at the end of this section.

1. Do not use the same testing agency for field quality control testing.

B. Submit written reports to Architect of each proposed mix for each class of concrete at least 15 days prior to start of Work. Do not begin concrete production until proposed mix designs have been reviewed by Architect. The approved mix designs shall be used throughout this project unless changes are approved by the Architect/Engineer prior to use.

C. Cementitious Materials: Supplier shall coordinate surface treatment compatibility with cementitious materials. Limit percentage, by weight, of cementitious materials other than portland cement in concrete as follows:

1. Fly Ash: 20 percent for Type F or 25% for Type C.

D. Admixtures: Use admixtures according to manufacturer's written instructions.

1. Use water-reducing, high-range water-reducing, or plasticizing admixture in concrete as required for placement and workability and in all pumped concrete and concrete for slab on grade.

2. Use accelerating and retarding admixtures at Contractor’s discretion to control set time when required by extreme temperatures or humidity, or other adverse placement conditions. Use accelerating admixture in concrete slabs placed at ambient temperatures below 35 deg F.

E. The minimum compressive strength measured 28 days after placement (f’c), minimum cementitious content, slump, maximum water/cementitious content ratio (W/C), and air content of the concrete for each portion of the structure shall be as follows:

1. Class 1. Interior Slab on Grade and footings. Normal-weight concrete.

a. Minimum Compressive Strength: 4,000 psi.b. Minimum Cementitious Material: 505 lbs/cy.c. Maximum W/C Ratio: 0.48.d. Water Reducing Admixture: Mandatory.e. Slump Limit: Maximum 8 inches after adding water reducing admixture to 2-to-

3-inch slump concrete, plus or minus 1 inch.f. Air Content: Maximum 3 percent.

rhinson
Rectangle
rhinson
Snapshot
Page 16: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation

Copy Center Fit-up – Versailles, Kentucky

November 12, 2018EOP#201732

CAST-IN-PLACE CONCRETE 033000 - 8

2. Class 2. Exterior horizontal concrete exposed to weather or deicer chemicals, and exterior equipment bases. Normal-weight concrete.

a. Minimum Compressive Strength: 4,500 psi.b. Minimum Cementitious Material: 564 lbs/cy.c. Maximum W/C Ratio: 0.45.d. Water Reducing Admixture: Optional.e. Slump Limit: 4 inches or not more than 8 inches after adding admixture to 2-to-

3-inch slump concrete, plus or minus 1 inch.f. Air Content: 5.5 percent for 1 ½-inch maximum aggregate.

6.0 percent for 1-inch maximum aggregate.6.0 percent for ¾-inch maximum aggregate.7.0 percent for ½-inch maximum aggregate.

F. Adjustment to Concrete Mixes: Mix design adjustments may be requested by Contractor when characteristics of materials, job conditions, weather, test results, or other circumstances warrant, as accepted by Architect. Laboratory test data for revised mix design and strength results must be submitted to and accepted by Architect before using in Work.

2.7 FABRICATING REINFORCEMENT

A. Fabricate steel reinforcement according to CRSI's "Manual of Standard Practice."

2.8 CONCRETE MIXING

A. Ready-Mixed Concrete: Measure, batch, mix, and deliver concrete according to ASTM C 94, and furnish batch ticket information.

1. When air temperature is between 85 and 90 deg F, reduce mixing and delivery time from 1-1/2 hours to 75 minutes; when air temperature is above 90 deg F, reduce mixing and delivery time to 60 minutes.

B. Project-Site Mixing: Measure, batch, and mix concrete materials and concrete according to ASTM C 94. Mix concrete materials in appropriate drum-type batch machine mixer.

1. For mixer capacity of 1 cu. yd. or smaller, continue mixing at least 1-1/2 minutes, but not more than 5 minutes after ingredients are in mixer, before any part of batch is released.

2. For mixer capacity larger than 1 cu. yd., increase mixing time by 15 seconds for each additional 1 cu. yd..

3. Provide batch ticket for each batch discharged and used in the Work, indicating Project identification name and number, date, mixture type, mixture time, quantity, and amount of water added. Record approximate location of final deposit in structure.

PART 3 - EXECUTION

3.1 GENERAL

A. Coordinate the installation of joint materials, vapor retarder, and other related materials with placement of forms and reinforcing steel.

3.2 FORMWORK INSTALLATION

A. Design, erect, shore, brace, and maintain formwork, according to ACI 301, to support vertical, lateral, static, and dynamic loads, and construction loads that might be applied until concrete structure can support such loads.

rhinson
Rectangle
rhinson
Snapshot
Page 17: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation

Copy Center Fit-up – Versailles, Kentucky

November 12, 2018EOP#201732

CAST-IN-PLACE CONCRETE 033000 - 9

B. Construct formwork so concrete members and structures are of correct size, shape, lines, alignment, elevation, position, level, plumb, and dimension and indicated. Maintain formwork construction tolerances and surface irregularities within limits of ACI 117.

C. Limit concrete surface irregularities, designated by ACI 347 as abrupt or gradual, as follows:

1. Class A, 1/8 inch tolerances for smooth-formed concrete surfaces exposed to view.2. Class D tolerances for earth formed foundation elements. Tolerance applies as a

variation inward towards reinforcing only. No tolerance limit away from reinforcing applies.

3. Class C, ½ inch tolerances for other concrete surfaces.

D. Solidly butt joints and provide backup at joints to prevent cement paste from leaking.

E. Construct forms for easy removal without hammering or prying against concrete surfaces. Provide crush or wrecking plates where stripping may damage cast-concrete surfaces. Provide top forms for inclined surfaces where slope is too steep to place concrete with bottom forms only. Kerf wood inserts for forming keyways, reglets, recesses, and the like for easy removal.

F. Set edge forms, bulkheads, and intermediate screed strips for slabs to achieve required elevations and contours in finished surfaces. Provide and secure units to support screed strips using strike-off templates or compacting-type screeds.

G. Form offsets, sinkages, keyways, recesses, rustications, chamfers, blocking, screeds, bulkheads, and other features required in the Work. Chamfer exposed corners and edges at exterior corners and edges of permanently exposed concrete and as indicated, to produce uniform smooth, straight lines and tight edge joints.

H. Provisions for Other Trades: Provide openings in concrete formwork to accommodate work of other trades. Determine size and location of openings, recesses, and chases from trades providing such items. Accurately place and securely support items built into forms.

I. Earthen forms may be used for footings and foundation elements when ground is stable and capable of resisting erosion and fluid pressure of wet concrete without sloughing. All tolerances and clear covers shall be maintained. Excavation shall be clean of all loose soil and mud along bottom and sides.

J. Use selected materials to obtain required finishes.

K. Cleaning and Tightening: Thoroughly clean forms and adjacent surfaces to receive concrete. Remove chips, wood, sawdust, dirt, or other debris just before placing concrete. Retighten forms and bracing before placing concrete, as required, to prevent mortar leaks and maintain proper alignment.

L. Coat contact surfaces of forms with form-release agent, according to manufacturer's written instructions, before placing reinforcement.

1. Do not allow excess form-coating material to accumulate in forms or come into contact with in-place concrete surfaces against which fresh concrete will be placed.

2. Do not spray reinforcing with form oil.3. Coat steel forms with a nonstaining, rust-preventative material. Do not use rust-

stained steel form-facing material.

3.3 INSTALLING EMBEDDED ITEMS

rhinson
Rectangle
rhinson
Snapshot
Page 18: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation

Copy Center Fit-up – Versailles, Kentucky

November 12, 2018EOP#201732

CAST-IN-PLACE CONCRETE 033000 - 10

A. Place and secure anchorage devices, anchor rods, and other embedded items required for adjoining work that is attached to or supported by cast-in-place concrete. Use setting drawings, diagrams, templates, instructions, and directions furnished with items to be embedded.

1. Install anchor rods, accurately located, to elevations required and complying with tolerances in Section 7.5 of AISC 303. Column anchor rods shall be set in a rigid template and securely braced to formwork or ground prior to placing concrete. Anchor rods may not be “wet set” in plastic concrete.

2. Aluminum conduit shall not be installed in concrete.

3.4 STEEL REINFORCEMENT INSTALLATION

A. General: Comply with Concrete Reinforcing Steel Institute’s (CRSI) "Manual of Standard Practice" for fabricating, placing, and supporting reinforcement.

1. Do not cut or puncture vapor retarder. Repair damage and reseal vapor retarder before placing concrete.

B. Deliver reinforcement to job site bundled, tagged and marked. Use waterproof tags indicating bar size, length, and mark corresponding to placing drawings.

C. Clean reinforcement of loose rust and mill scale, earth, ice, and other materials that reduce or destroy bond with concrete.

D. When permitted, field bend bars cold, except during cold weather when moderate heating is necessary to avoid brittle failures.

E. Accurately position, support, and secure all bar reinforcement against displacement. Locate and support reinforcement with bar supports to maintain minimum coverages as indicated for concrete protection.

1. Arrange, space and securely tie bars and bar supports to hold reinforcement in position during concrete placement operations.

F. Install welded- wire fabric reinforcement in longest practicable lengths on fabric supports spaced to minimize sagging. Lap edges and ends of adjoining pieces at least one full mesh spacing. Offset laps of adjoining sheet widths to prevent continuous laps in either direction. Lace outermost cross wires of lace splices with wire to prevent lifting of the ends during concrete placement.

1. Chair welded wire fabric slab reinforcement with continuous chairs spaced a maximum of 32 inches on center. Provide additional chairs as required. Lift welded wire fabric back into position between chairs where depressed during concrete placement. Lifting welded wire fabric into position during concrete placement without the use of chairs is not permitted.

G. Set wire ties with ends directed into concrete, not toward exposed concrete surfaces.

H. Weld reinforcing bars and fabric, only where indicated, according to AWS D1.4. Do not tack weld crossing reinforcing bars.

3.5 JOINTS

A. General: Construct joints true to line with faces perpendicular to surface plane of concrete.

rhinson
Rectangle
rhinson
Snapshot
Page 19: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation

Copy Center Fit-up – Versailles, Kentucky

November 12, 2018EOP#201732

CAST-IN-PLACE CONCRETE 033000 - 11

B. Construction Joints in Reinforced Structure and Foundations: Locate and install construction joints so they do not impair strength or appearance of the structure, at locations indicated or otherwise as acceptable to Architect.

1. Place joints perpendicular to main reinforcement. Continue reinforcement across construction joints unless otherwise indicated. Do not continue reinforcement through sides of strip placements of slabs.

2. Use a bonding agent at locations where fresh concrete is placed against hardened or partially hardened concrete surfaces.

3. Use epoxy-bonding adhesive at locations where fresh concrete is placed against hardened or partially hardened concrete surfaces.

C. Contraction (Control) Joints in Slabs-on-Grade: Construct weakened-plane contraction joints, sectioning concrete into areas as indicated, and to a depth equal to at least one-fourth depth of concrete thickness as follows:

1. Sawed Joints: Form contraction joints with power saws equipped with shatterproof abrasive or diamond-rimmed blades. Cut 1/8-inch-wide joints into concrete when cutting action does not tear, abrade, or otherwise damage surface and before concrete develops random contraction cracks.

2. Contraction joints may be formed by saw cuts as soon as possible after slab finishing as may be safely done without dislodging aggregate.

3. If joint pattern is not shown, provide joints not exceeding 15 feet in either direction and located to conform to bay spacing wherever possible (at column centerlines, half bays, third bays).

4. Joint fillers and sealants are specified in Division 7 Section “Joint Sealants.”

3.6 VAPOR RETARDER INSTALLATION

A. Sheet vapor retarder: Place, protect, and repair sheet vapor retarder according to ASTM E 1643 and manufacturer's written instructions. Place sheeting in position with longest dimension parallel with direction of pour.

1. Extend film fully over slab area to the full perimeter of the slab. Turn film down to bottom of turn down slab.

a. Where obstructed by impediments (such as dowels or any other site condition requiring early termination of the vapor retarder). At the point of termination, seal vapor retarder to the footing, or slab itself. Use manufacturer’s recommended accessories for such non-standard terminations.

2. Lap joints 6 inches and seal with manufacturer’s recommended mastic or pressure- sensitive tape.

3. Apply seam tape to a clean and dry film only.

B. Seal around all penetrations (including all conduit and pipes) through film with manufacturer’s recommended mastic or pressure-sensitive tape. Cut slit around penetrations to place initial layer of film.

1. For small penetrations, tape film directly to the penetrating element.2. For penetrations larger than 2”, create collar for penetration of 12” wide by 1 ½ times

the penetration’s circumference with fingers cut half the width of the film. Wrap the collar around the penetration, tape the collar onto the strip of film, and tape the fingers at each edge/slit to the initial layer of film.

C. Avoid the use of non-permanent stakes driven through film. If non-permanent stakes are driven through film, repair and seal as recommended by film manufacturer.

rhinson
Rectangle
rhinson
Snapshot
Page 20: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation

Copy Center Fit-up – Versailles, Kentucky

November 12, 2018EOP#201732

CAST-IN-PLACE CONCRETE 033000 - 12

D. Repair damaged areas of film material of similar (or better) permeance, puncture resistance, and tensile strength.

3.7 CONCRETE PLACEMENT

A. Inspection: Before placing concrete, inspect and complete formwork installation, reinforcing steel, and items to be embedded or cast in. Notify other trades to permit installation of their work.

B. General: Comply with ACI 304, “Guide for Measuring, Mixing, Transporting, and Placing Concrete,” and as specified. Concrete delivery tickets shall show:

1. Batch number.2. Mix by number with cement content in pounds and maximum size aggregate.3. Admixtures.4. Air content.5. Slump.6. Time dispatched and discharged.7. Date.8. Contractor.9. Ready Mix Supplier.10. Project Name and Address.11. Volume of Concrete.

C. Do not add water to the concrete mix during delivery, at Project site, or during placement unless approved by the General Contractor’s representative, noted on the delivery ticket with the amount of water, and signed by the General Contractor’s representative. The maximum water/cement ratio of an approved mix design may not be exceeded.

1. When the ambient air temperature is between 80 and 90 degrees Fahrenheit, one (1) gallon of water per cubic yard of concrete may be added at the job site to compensate for water evaporation during transit.

2. When the ambient air temperature exceeds 90 degrees Fahrenheit, two (2) gallons of water per cubic yard of concrete may be added at the job site to compensate for water evaporation during transit.

3. Do not add water to concrete after adding high-range water-reducing admixtures to mixture.

D. Discharge concrete within 1 ½ hours after water has been added to the cement, unless a longer time has been authorized by the Architect/Engineer. During hot weather or other conditions contributing to a quick stiffening of the concrete, the Architect/Engineer may require discharge in less than 1 ½ hours.

E. Deposit concrete continuously in one layer or in horizontal layers of such thickness that no new concrete is placed on concrete that has hardened enough to cause seams or planes of weakness. If a section cannot be placed continuously, provide construction joints as indicated. Deposit concrete to avoid segregation. Do not allow concrete to drop more than 5 feet or from a height which allows concrete to fall against reinforcing.

1. Deposit concrete in forms in horizontal layers of depth not to exceed formwork design pressures and in a manner to avoid inclined construction joints. Where placement consists of several layers, place each layer while preceding layer is still plastic to avoid cold joints. Do not subject concrete to any procedure that will cause segregation. Deposit concrete as near as possible to the final position to avoid segregation.

rhinson
Rectangle
rhinson
Snapshot
Page 21: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation

Copy Center Fit-up – Versailles, Kentucky

November 12, 2018EOP#201732

CAST-IN-PLACE CONCRETE 033000 - 13

2. Consolidate placed concrete by mechanical vibrating equipment supplemented by hand-spading, rodding, or tamping. Use equipment and procedures for consolidation of concrete complying with ACI 301.

3. Do not use vibrators to transport concrete inside forms. Insert and withdraw vibrators vertically at uniformly spaced locations no farther than the visible effectiveness of the machine. Place vibrators to rapidly penetrate placed layer and at least 6 inches into preceding layer. Do not insert vibrators into lower layers of concrete that have begun to set. At each insertion, limit duration of vibration to time necessary to consolidate concrete and complete embedment of reinforcement and other embedded items without causing mix to segregate.

F. Deposit and consolidate concrete for floors and slabs in a continuous operation, within limits of construction joints, until placement of a panel or section is complete.

1. Consolidate concrete during placement operations so that concrete is thoroughly worked around reinforcement and other embedded items and into corners.

2. Maintain reinforcement in proper position on chairs during concrete placement.3. Screed slab surfaces with a straightedge and strike off to correct elevations.4. Slope surfaces uniformly to drains where required.5. Begin initial floating using bull floats or darbies to form a uniform and open-textured

surface plane, before excess bleedwater appears on the surface. Do not further disturb slab surfaces before starting finishing operations.

G. Cold-Weather Placement: When air temperature is expected to fall below 40 degrees Fahrenheit (4 deg C) within the first 72 hours after concrete placement, comply with provisions of ACI 306.1 and as follows. Protect concrete work from physical damage or reduced strength that could be caused by frost, freezing actions, or low temperatures.

1. When mean daily air temperature is expected to fall below 40 deg F (4 deg C) for more than three successive days after concrete placement, uniformly heat water and aggregates before mixing to obtain a concrete mixture temperature at point of placement as follows:

a. Not less than 55 deg F (13 deg C) or more than 75 deg F (24 deg C) for concrete sections less than 12 inches in the least dimension (width or thickness).

b. Not less than 50 deg F (10 deg C) or more than 70 deg F (21 deg C) for concrete sections 12 inches or greater in the least dimension (width or thickness).

2. Do not use frozen materials or materials containing ice or snow. Do not place concrete on frozen subgrade or on subgrade containing frozen materials.

3. Do not use calcium chloride, salt, or other materials containing antifreeze agents or chemical accelerators unless otherwise accepted in mix designs.

H. Hot-Weather Placement: When hot weather conditions exist that would impair quality and strength of concrete, place concrete complying with ACI 305.1 and as specified.

1. Cool ingredients before mixing to maintain concrete temperature at time of placement to below 90 deg F (32 deg C). Mixing water may be chilled or chopped ice may be used to control temperature, provided water equivalent of ice is calculated to total amount of mixing water. Using liquid nitrogen to cool concrete is Contractor’s option.

2. Cover reinforcing steel with water-soaked burlap if it becomes too hot, so that steel temperature will not exceed the ambient air temperature immediately before embedding in concrete.

3. Fog spray forms, reinforcing steel, and subgrade just before placing concrete. Keep subgrade moisture uniform without puddles or dry areas.

rhinson
Rectangle
rhinson
Snapshot
Page 22: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation

Copy Center Fit-up – Versailles, Kentucky

November 12, 2018EOP#201732

CAST-IN-PLACE CONCRETE 033000 - 14

4. Use water-reducing retarding admixture when required by high temperatures, low humidity, or other adverse placing conditions, as acceptable to Architect.

I. Pumping Concrete: Grout used to prime a pump shall not be placed in the forms of any concrete exposed to view in the final structure.

3.8 FINISHING FORMED SURFACES

A. Smooth-Formed Finish: Provide a smooth-formed finish on formed concrete surfaces exposed to view. This is an as-cast concrete surface obtained with selected form-facing material, arranged in an orderly and symmetrical manner with a minimum of seams. Repair and patch tie holes, honeycombing over ¼” in depth, and other defective areas. Remove fins and other projections exceeding 1/8” in height by rubbing down or grinding off until completely removed and smoothed.

B. Related Unformed Surfaces: At tops of walls, horizontal offsets, and similar unformed surfaces adjacent to formed surfaces, strike-off smooth and finish with a texture matching adjacent formed surfaces. Continue final surface treatment of formed surfaces uniformly across adjacent unformed surfaces unless otherwise indicated.

3.9 FINISHING FLOORS AND SLABS

A. General: Comply with ACI 302.1R recommendations for screeding, restraightening, and finishing operations for concrete surfaces. Do not wet concrete surfaces.

B. Trowel Finish: Apply a trowel finish to monolithic slab surfaces exposed to view.

1. After screeding, consolidating, and leveling concrete slabs, do not work surface until ready for floating. Begin floating, using float blades or float shoes only, when surface water has disappeared, or when concrete has stiffened sufficiently to permit operation of power-driven floats, or both. Consolidate surface with power-driven floats or by hand-floating if area is small or inaccessible to power units.

2. After floating, begin first trowel-finish operation using a power-driven trowel. Begin final troweling when surface produces a ringing sound as trowel is moved over surface. Consolidate concrete surface by final hand-troweling operation, free of trowel marks and uniform in texture and appearance. Grind smooth any surface defects that would telegraph through applied floor covering system.

Slabs on Grade and Formed Elevated Concrete Slabs (Shored Construction)

Composite Flatness F(F) Composite Levelness F(L) Typical Use

25 20 Slab on Grade

C. Nonslip Broom Finish: Apply a nonslip broom finish to exterior concrete platforms, steps, ramps, and elsewhere as indicated.

1. Immediately after float finishing, slightly roughen concrete surface by brooming with fiber-bristle broom perpendicular to main traffic route. Coordinate required final finish with Architect before application.

3.10 MISCELLANEOUS CONCRETE ITEMS

A. Filling In: Fill in holes and openings left in concrete structures for passage of work by other trades, unless otherwise shown or directed, after work of other trades is in place. Mix, place,

rhinson
Rectangle
rhinson
Snapshot
Page 23: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation

Copy Center Fit-up – Versailles, Kentucky

November 12, 2018EOP#201732

CAST-IN-PLACE CONCRETE 033000 - 15

and cure concrete as specified to blend with in-place construction. Provide other miscellaneous concrete filling shown or required to complete Work.

3.11 CONCRETE PROTECTING AND CURING

A. General: Protect freshly placed concrete from premature drying and excessive cold or hot temperatures.

B. For cold-weather protection during curing, comply with ACI 306.1 and the following:

1. All freshly placed concrete shall be kept from freezing for the following periods:

a. 3 days for all concrete with an air entraining admixture.b. 4 days for all concrete without an air entraining admixture.

2. A cumulative curing time of seven days at a minimum surface temperature of 50 degrees F (10 degrees C) shall be provided or until concrete has attained 75% of its design strength. This shall be followed by cooling of concrete in a gradual transition to surrounding conditions. The temperature drop during this period shall not be at a rate exceeding 2 degrees F per hour until the outside or surrounding temperature is reached.

3. When concrete is placed under conditions of cold weather concreting (defined as a period when the mean daily temperature drops below 40 degrees F for more than three successive days), take additional precautions as specified in “Cold Weather Concreting” by the American Concrete Institute (ACI Report 306) when placing, curing, monitoring and protecting the fresh concrete.

C. For hot-weather protection during curing, comply with ACI 301 and the following:

1. When concrete is placed under conditions of hot weather concreting, provide extra protection of the concrete against excessive placement temperatures and excessive drying throughout the placing and curing operations. Hot weather is defined as air temperature which exceeds 80 degrees F or any combination of high temperature, low humidity and/or high wind velocity which causes a rate of evaporation in excess of 0.2 pounds per square foot per hour as determined by Figure 2.1.5 of ACI Report 305. Hot weather curing is required if these conditions occur within a 24 hour period after completion of concrete placement.

2. Forms, reinforcing and the air shall be cooled by water fog spraying immediately before placing concrete.

3. Immediately following screeding, protect concrete by applying the specified evaporation retarder in accordance with the recommendations of the manufacturer.

D. Evaporation Retarder: Apply evaporation retarder to unformed concrete surfaces if hot, dry, or windy conditions cause moisture loss approaching 0.2 lb/sq. ft. x h before and during finishing operations. Apply according to manufacturer's written instructions after placing, screeding, and bull floating or darbying concrete, but before float finishing.

E. Unformed Surfaces: Begin curing immediately after finishing concrete. Cure unformed surfaces, including slabs, and other surfaces.

1. Cure interior and exterior slab surfaces exposed to deicing salts and slabs where the finish flooring is not compatible with curing compounds by Moisture Curing.

F. Cure concrete according to ACI 308.1, by the following method:

1. Curing and Sealing Compound: Apply uniformly to all slabs indicated in a continuous operation by power spray or roller according to manufacturer's written instructions

rhinson
Rectangle
rhinson
Snapshot
Page 24: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation

Copy Center Fit-up – Versailles, Kentucky

November 12, 2018EOP#201732

CAST-IN-PLACE CONCRETE 033000 - 16

(minimum coverage rate 400 sq. ft/gallon). Recoat areas subjected to heavy rainfall within three hours after initial application. Repeat process 24 hours later and apply a second coat (minimum coverage rate 450 sq. ft/gallon. Maintain continuity of coating and repair damage during curing period. Two coats are mandatory.

3.12 CONCRETE SURFACE REPAIRS

A. Defective Concrete: Repair and patch defective areas when approved by Architect. Remove and replace concrete that cannot be repaired and patched to Architect's approval.

B. Patching Mortar: Mix dry-pack patching mortar, consisting of 1 part portland cement to 2-1/2 parts fine aggregate passing a No. 16 sieve, and a 50:50 mixture of acrylic or styrene butadiene-based bonding admixture and water. Use only enough liquid as required for handling and placing.

C. Repairing Unformed Surfaces: Test unformed surfaces, such as slabs, for finish and verify surface tolerances specified for each surface. Correct low and high areas. Test surfaces sloped to drain for trueness of slope and smoothness; use a sloped template.

1. Repair formed surfaces containing defects. Surface defects include spalls, popouts, honeycombs, rock pockets, crazing and cracks in excess of 0.01 inch wide or that penetrate to reinforcement or completely through unreinforced sections regardless of width, and other objectionable conditions.

D. Perform structural repairs of concrete, subject to Architect's approval, using epoxy adhesive and patching mortar.

E. Repair methods not specified above may be used, subject to acceptance of Architect.

3.13 QUALITY CONTROL

A. The Owner will employ an independent testing and inspection agency which meets the requirements of ASTM E329 to perform inspections and tests and to prepare test reports. The agency will monitor concrete quality by means of site and laboratory tests. They will be authorized to reject plastic concrete not conforming to specifications. Failure to detect any defective materials shall not prevent later rejection when such defect is discovered, or obligate the Architect or Owner for final acceptance.

1. See Section 014110 – Structural Special Inspections for testing and inspection to be performed.

2. Test results will be reported in writing to the Architect, Engineer, ready-mix producer and General Contractor within 24 hours after tests.

3. Additional Tests: The testing agency will make additional tests of in-place concrete when test results indicate specified concrete strengths and other characteristics have not been attained in the structure, as directed by Architect.

B. Correct deficiencies in the Work that test reports and inspections indicate do not comply with the Contract Documents.

END OF SECTION 033000

rhinson
Rectangle
rhinson
Snapshot
Page 25: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

Water/Cementitious Ratio (W/C) = % (lbs. water /lbs. cementitious)

CONCRETE MIX DESIGN SUBMITTAL FORM

Project:

City, State:

General Contractor:

Concrete Contractor:

Mix Design Number:

Concrete Strength (Class):

Use (describe):

Design Mix Information

Based on Standard Deviation Analysis

Based on Trial Mix Laboratory Test Data

Check

one

Design Characteristics

Density pcf

Strength psi (28 days)

Air %

Slump inches

If trial mixes are used, the Mix Design is proportioned to achieve f’cr = f’c + 1200 psi

(1400 psi for strength higher than 5000 psi at 28 days)

Materials

Type SourceSpecific

Gravity

Weight

(lb.)

Absolute

Vol. (cu. ft.)

cement

flyash

silica fume

coarse aggregate

fine aggregate

water

other ( )

Total 27.0 cu. ft.

rhinson
Rectangle
rhinson
Snapshot
Page 26: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

Admixtures

ManufacturerDosage

(oz./cwt)

water reducer

air entraining agent

high range water reducer

non-corrosive accelerator

other ( )

Slump before high range water reducer = inches

Slump after high range water reducer = inches

Standard Deviation Analysis (field experience records)

Number of test cylinders evaluated:

k-factor:

Standard deviation (s):

Number of Tests k

15 1.16

20 1.08

25 1.03

≥30 1.00

Required avg. compressive strength (≤5000 psi: Max[f’c + 1.34ks, f’c + 2.33 ks – 500])

(>5000 psi: Max [f’c + 1.34ks, 0.9f’c + 2.33ks]):

Actual avg. compressive strength:

(refer to ACI 301 for standard deviation calculation – attach copies of laboratory test reports)

Trial Mix Laboratory Test Data

Mix #1 Mix #2 Mix #3

Age DateCompressive

StrengthDate

Compressive

StrengthDate

Compressive

Strength

7 days psi psi psi

7 days psi psi psi

28 days psi psi psi

28 days psi psi psi

28 days

averageNA psi NA psi NA psi

(refer to ACI 301 for trial mix procedure – attach copies of laboratory test reports)

Required Attachments

Coarse aggregate gradation report

Fine aggregate gradation report

Laboratory test reports (strength tests)

Admixture compatibility certification letters

Ready Mix Supplier

Please

check

Name and Address:

Phone: Miles from project: Date:

rhinson
Rectangle
rhinson
Snapshot
Page 27: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

CONCRETE UNIT MASONRY 042200 - 1

SECTION 042200 - CONCRETE UNIT MASONRY

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Concrete masonry units.2. Mortar and grout.3. Steel reinforcing bars.4. Masonry-joint reinforcement.5. Miscellaneous masonry accessories.6. Masonry-cell fill.

1.3 DEFINITIONS

A. CMU(s): Concrete masonry unit(s).

B. Reinforced Masonry: Masonry containing reinforcing steel in grouted cells.

1.4 ACTION SUBMITTALS

A. Product Data: For each type of product.

B. Shop Drawings: For the following:

1. Masonry Units: Show sizes, profiles, coursing, and locations of special shapes.2. Reinforcing Steel: Detail bending, lap lengths, and placement of unit masonry reinforcing

bars. Comply with ACI 315. Show elevations of reinforced walls.

C. Samples for Initial Selection:

1. Colored mortar.

D. Samples for Verification: For each type and color of the following:

1. Exposed CMUs.

1.5 INFORMATIONAL SUBMITTALS

A. Qualification Data: For testing agency.

rhinson
Rectangle
rhinson
Snapshot
Page 28: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

CONCRETE UNIT MASONRY 042200 - 2

B. Material Certificates: For each type and size of the following:

1. Masonry units.

a. Include material test reports substantiating compliance with requirements.b. For masonry units used in structural masonry, include data and calculations

establishing average net-area compressive strength of units.

2. Integral water repellant used in CMUs.3. Cementitious materials. Include name of manufacturer, brand name, and type.4. Mortar admixtures.5. Pre-blended, dry mortar mixes. Include description of type and proportions of ingredients.6. Grout mixes. Include description of type and proportions of ingredients.7. Reinforcing bars.8. Joint reinforcement.9. Anchors, ties, and metal accessories.

C. Mix Designs: For each type of mortar and grout. Include description of type and proportions of ingredients.

1. Include test reports for mortar mixes required to comply with property specification. Test according to ASTM C 109/C 109M for compressive strength, ASTM C 1506 for water retention, and ASTM C 91/C 91M for air content.

2. Include test reports, according to ASTM C 1019, for grout mixes required to comply with compressive strength requirement.

D. Statement of Compressive Strength of Masonry: For each combination of masonry unit type and mortar type, provide statement of average net-area compressive strength of masonry units, mortar type, and resulting net-area compressive strength of masonry determined according to TMS 602/ACI 530.1/ASCE 6.

E. Cold-Weather Procedures: Detailed description of methods, materials, and equipment to be used to comply with requirements.

1.6 QUALITY ASSURANCE

A. Testing Agency Qualifications: Qualified according to ASTM C 1093 for testing indicated.

1.7 DELIVERY, STORAGE, AND HANDLING

A. Store masonry units on elevated platforms in a dry location. If units are not stored in an enclosed location, cover tops and sides of stacks with waterproof sheeting, securely tied. If units become wet, do not install until they are dry.

B. Store cementitious materials on elevated platforms, under cover, and in a dry location. Do not use cementitious materials that have become damp.

C. Store aggregates where grading and other required characteristics can be maintained and contamination avoided.

D. Deliver pre-blended, dry mortar mix in moisture-resistant containers. Store pre-blended, dry mortar mix in delivery containers on elevated platforms in a dry location or in covered weatherproof dispensing silos.

rhinson
Rectangle
rhinson
Snapshot
Page 29: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

CONCRETE UNIT MASONRY 042200 - 3

E. Store masonry accessories, including metal items, to prevent corrosion and accumulation of dirt and oil.

1.8 FIELD CONDITIONS

A. Protection of Masonry: During construction, cover tops of walls, projections, and sills with waterproof sheeting at end of each day's work. Cover partially completed masonry when construction is not in progress.

1. Extend cover a minimum of 24 inches (600 mm) down both sides of walls, and hold cover securely in place.

B. Do not apply uniform floor or roof loads for at least 12 hours and concentrated loads for at least three days after building masonry walls or columns.

C. Stain Prevention: Prevent grout, mortar, and soil from staining the face of masonry to be left exposed or painted. Immediately remove grout, mortar, and soil that come in contact with such masonry.

1. Protect base of walls from rain-splashed mud and from mortar splatter by spreading coverings on ground and over wall surface.

2. Protect sills, ledges, and projections from mortar droppings.3. Protect surfaces of window and door frames, as well as similar products with painted and

integral finishes, from mortar droppings.4. Turn scaffold boards near the wall on edge at the end of each day to prevent rain from

splashing mortar and dirt onto completed masonry.

D. Cold-Weather Requirements: Do not use frozen materials or materials mixed or coated with ice or frost. Do not build on frozen substrates. Remove and replace unit masonry damaged by frost or by freezing conditions. Comply with cold-weather construction requirements contained in TMS 602/ACI 530.1/ASCE 6.

1. Cold-Weather Cleaning: Use liquid cleaning methods only when air temperature is 40 deg F (4 deg C) and higher and will remain so until masonry has dried, but not less than seven days after completing cleaning.

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Source Limitations for Masonry Units: Obtain exposed masonry units of a uniform texture and color, or a uniform blend within the ranges accepted for these characteristics, from single source from single manufacturer for each product required.

B. Source Limitations for Mortar Materials: Obtain mortar ingredients of a uniform quality, including color for exposed masonry, from single manufacturer for each cementitious component and from single source or producer for each aggregate.

rhinson
Rectangle
rhinson
Snapshot
Page 30: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

CONCRETE UNIT MASONRY 042200 - 4

2.2 PERFORMANCE REQUIREMENTS

A. Provide structural unit masonry that develops indicated net-area compressive strengths at 28 days.

1. Determine net-area compressive strength of masonry from average net-area compressive strengths of masonry units and mortar types (unit-strength method) according to TMS 602/ACI 530.1/ASCE 6.

2. Determine net-area compressive strength of masonry by testing masonry prisms according to ASTM C 1314.

2.3 UNIT MASONRY, GENERAL

A. Masonry Standard: Comply with TMS 602/ACI 530.1/ASCE 6 except as modified by requirements in the Contract Documents.

B. Defective Units: Referenced masonry unit standards may allow a certain percentage of units to contain chips, cracks, or other defects exceeding limits stated. Do not use units where such defects are exposed in the completed Work.

C. Fire-Resistance Ratings: Comply with requirements for fire-resistance-rated assembly designs indicated.

1. Where fire-resistance-rated construction is indicated, units shall be listed and labeled by a qualified testing agency acceptable to authorities having jurisdiction.

2.4 CONCRETE MASONRY UNITS

A. Shapes: Provide shapes indicated and as follows, with exposed surfaces matching exposed faces of adjacent units unless otherwise indicated.

1. Provide special shapes for lintels, corners, jambs, sashes, movement joints, headers, bonding, and other special conditions.

2. Provide square-edged units for outside corners and end of knee wall unless otherwise indicated.

B. CMUs: ASTM C 90.

1. Unit Compressive Strength: Provide units with minimum average net-area compressive strength of 2150 psi (14.8 MPa).

2. Density Classification: Lightweight.3. Size (Width): Manufactured to dimensions 3/8 inch (10 mm) less-than-nominal

dimensions.

2.5 MASONRY LINTELS

A. Masonry Lintels: Prefabricated or built-in-place masonry lintels made from bond beam CMUs matching adjacent CMUs in color, texture, and density classification, with reinforcing bars placed as indicated and filled with coarse grout. Cure precast lintels before handling and installing. Temporarily support built-in-place lintels until cured.

rhinson
Rectangle
rhinson
Snapshot
Page 31: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

CONCRETE UNIT MASONRY 042200 - 5

2.6 MORTAR AND GROUT MATERIALS

A. Portland Cement: ASTM C 150/C 150M, Type I or II, except Type III may be used for cold-weather construction. Provide natural color or white cement as required to produce mortar color indicated.

1. Alkali content shall not be more than 0.1 percent when tested according to ASTM C 114.

B. Hydrated Lime: ASTM C 207, Type S.

C. Portland Cement-Lime Mix: Packaged blend of portland cement and hydrated lime containing no other ingredients.

D. Masonry Cement: ASTM C 91/C 91M. Shall not be used for reinforced masonry construction

E. Mortar Cement: ASTM C 1329/C 1329M.

1. Products: Subject to compliance with requirements available products that may be incorporated into the Work include, but are not limited to, the following:

a. Lafarge North America Inc.; Lafarge mortar Cement

F. Aggregate for Mortar: ASTM C 144.

1. For mortar that is exposed to view, use washed aggregate consisting of natural sand or crushed stone.

2. For joints less than 1/4 inch (6 mm) thick, use aggregate graded with 100 percent passing the No. 16 (1.18-mm) sieve.

3. White-Mortar Aggregates: Natural white sand or crushed white stone.

G. Aggregate for Grout: ASTM C 404.

H. Epoxy Pointing Mortar: ASTM C 395, epoxy-resin-based material formulated for use as pointing mortar for glazed or pre-faced masonry units (and approved for such use by manufacturer of units); in color indicated or, if not otherwise indicated, as selected by Architect from manufacturer's colors.

I. Cold-Weather Admixture: Nonchloride, noncorrosive, accelerating admixture complying with ASTM C 494/C 494M, Type C, and recommended by manufacturer for use in masonry mortar of composition indicated.

1. Products: Subject to compliance with requirements, available products that may be incorporated into the Work include, but are not limited to, the following:

a. Euclid Chemical Company (The); Accelguard 80

b. Grace Construction Products, W.R. Grace & Co. – Conn.; Morset

c. Sonneborn Products, BASF Aktiengesellschaft; Trimix-NCA

J. Water: Potable.

2.7 REINFORCEMENT

A. Uncoated Steel Reinforcing Bars: ASTM A 615/A 615M or ASTM A 996/A 996M, Grade 60 (Grade 420).

rhinson
Rectangle
rhinson
Snapshot
Page 32: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

CONCRETE UNIT MASONRY 042200 - 6

B. Reinforcing Bar Positioners: Wire units designed to fit into mortar bed joints spanning masonry unit cells and to hold reinforcing bars in center of cells. Units are formed from 0.148-inch (3.77-mm) steel wire, hot-dip galvanized after fabrication. Provide units designed for number of bars indicated.

C. Masonry-Joint Reinforcement, General: Ladder type complying with ASTM A 951/A 951M.

1. Interior Walls: Hot-dip galvanized carbon steel.2. Exterior Walls: Hot-dip galvanized carbon steel.3. Wire Size for Side Rods: 0.148-inch (3.77-mm) diameter.4. Wire Size for Cross Rods: 0.148-inch (3.77-mm) diameter.5. Spacing of Cross Rods: Not more than 16 inches (407 mm) o.c.6. Provide in lengths of not less than 10 feet (3 m), with prefabricated corner and tee units.

2.8 TIES AND ANCHORS

A. General: Ties and anchors shall extend at least 1-1/2 inches (38 mm) into masonry but with at least a 5/8-inch (16-mm) cover on outside face.

B. Materials: Provide ties and anchors specified in this article that are made from materials that comply with the following unless otherwise indicated:

1. Hot-Dip Galvanized, Carbon-Steel Wire: ASTM A 82/A 82M, with ASTM A 153/A 153M, Class B-2 coating.

2. Galvanized-Steel Sheet: ASTM A 653/A 653M, Commercial Steel, G60 (Z180) zinc coating.

3. Steel Sheet, Galvanized after Fabrication: ASTM A 1008/A 1008M, Commercial Steel, with ASTM A 153/A 153M, Class B coating.

4. Steel Plates, Shapes, and Bars: ASTM A 36/A 36M.

C. Adjustable Anchors for Connecting to Structural Steel Framing: Provide anchors that allow vertical or horizontal adjustment but resist tension and compression forces perpendicular to plane of wall.

1. Anchor Section for Welding to Steel Frame: Crimped 1/4-inch- (6.35-mm-) diameter, hot-dip galvanized steel wire.

2. Tie Section: Triangular-shaped wire tie made from 0.187-inch- (4.76-mm-) diameter, hot-dip galvanized steel wire.

D. Adjustable Anchors for Connecting to Concrete: Provide anchors that allow vertical or horizontal adjustment but resist tension and compression forces perpendicular to plane of wall.

1. Connector Section: Dovetail tabs for inserting into dovetail slots in concrete and attached to tie section; formed from 0.060-inch- (1.52-mm-) thick steel sheet, galvanized after fabrication.

a. 0.064-inch- (1.63-mm-) thick, galvanized-steel sheet may be used at interior walls unless otherwise indicated.

2. Tie Section: Triangular-shaped wire tie made from 0.187-inch- (4.76-mm-) diameter, hot-dip galvanized steel wire.

3. Corrugated-Metal Ties: Metal strips not less than 7/8 inch (22 mm) wide with corrugations having a wavelength of 0.3 to 0.5 inch (7.6 to 12.7 mm) and an amplitude of 0.06 to 0.10 inch (1.5 to 2.5 mm) made from 0.060-inch- (1.52-mm-) thick steel sheet, galvanized after fabrication with dovetail tabs for inserting into dovetail slots in concrete.

rhinson
Rectangle
rhinson
Snapshot
Page 33: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

CONCRETE UNIT MASONRY 042200 - 7

a. 0.064-inch- (1.63-mm-) thick, galvanized sheet may be used at interior walls unless otherwise indicated.

E. Partition Top Anchors: 0.105-inch- (2.66-mm-) thick metal plate with a 3/8-inch- (9.5-mm-) diameter metal rod 6 inches (152 mm) long welded to plate and with closed-end plastic tube fitted over rod that allows rod to move in and out of tube. Fabricate from steel, hot-dip galvanized after fabrication.

F. Rigid Anchors: Fabricate from steel bars 1-1/2 inches (38 mm) wide by 1/4 inch (6.35 mm) thick by 24 inches (610 mm) long, with ends turned up 2 inches (51 mm) or with cross pins unless otherwise indicated.

1. Corrosion Protection: Hot-dip galvanized to comply with ASTM A 153/A 153M.

2.9 MISCELLANEOUS MASONRY ACCESSORIES

A. Compressible Filler: Pre-molded filler strips complying with ASTM D 1056, Grade 2A1; compressible up to 35 percent; of width and thickness indicated; formulated from neoprene.

B. Preformed Control-Joint Gaskets: Made from styrene-butadiene-rubber compound, complying with ASTM D 2000, Designation M2AA-805 and designed to fit standard sash block and to maintain lateral stability in masonry wall; size and configuration as indicated.

C. Bond-Breaker Strips: Asphalt-saturated felt complying with ASTM D 226/D 226M, Type I (No. 15 asphalt felt).

2.10 MASONRY-CELL FILL

A. Loose-Fill Insulation: Perlite complying with ASTM C 549, Type II (surface treated for water repellency and limited moisture absorption) or Type IV (surface treated for water repellency and to limit dust generation).

B. Lightweight-Aggregate Fill: ASTM C 331/C 331M.

2.11 MORTAR AND GROUT MIXES

A. General: Do not use admixtures, including pigments, air-entraining agents, accelerators, retarders, water-repellent agents, antifreeze compounds, or other admixtures unless otherwise indicated.

1. Do not use calcium chloride in mortar or grout.2. Use portland cement-lime masonry cement or mortar cement mortar unless otherwise

indicated.3. For reinforced masonry, use portland cement-lime masonry cement or mortar cement

mortar.4. Add cold-weather admixture (if used) at same rate for all mortar that will be exposed to

view, regardless of weather conditions, to ensure that mortar color is consistent.

B. Pre-blended, Dry Mortar Mix: Furnish dry mortar ingredients in form of a pre-blended mix. Measure quantities by weight to ensure accurate proportions, and thoroughly blend ingredients before delivering to Project site.

rhinson
Rectangle
rhinson
Snapshot
Page 34: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

CONCRETE UNIT MASONRY 042200 - 8

C. Mortar for Unit Masonry: Comply with ASTM C 270, Proportion Specification. Provide the following types of mortar for applications stated unless another type is indicated or needed to provide required compressive strength of masonry.

1. For masonry below grade or in contact with earth, use Type M.2. For reinforced masonry, use Type S.3. For mortar parge coats, use Type S or Type N.4. For interior non-load-bearing partitions, used Type N.

D. Grout for Unit Masonry: Comply with ASTM C 476.

1. Use grout of type indicated or, if not otherwise indicated, of type (fine or coarse) that will comply with TMS 602/ACI 530.1/ASCE 6 for dimensions of grout spaces and pour height.

2. Proportion grout in accordance with ASTM C 476, Table 1 or paragraph 4.2.2 for specified 28-day compressive strength indicated, but not less than 2000 psi (14 MPa).

3. Provide grout with a slump of 8 to 11 inches (200 to 280 mm) [10 to 11 inches (250 to 280 mm)] as measured according to ASTM C 143/C 143M.

E. Epoxy Pointing Mortar: Mix epoxy pointing mortar to comply with mortar manufacturer's written instructions.

1. Application: Use epoxy pointing mortar for exposed mortar joints with pre-faced CMUs.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine conditions, with Installer present, for compliance with requirements for installation tolerances and other conditions affecting performance of the Work.

1. For the record, prepare written report, endorsed by Installer, listing conditions detrimental to performance of the Work.

2. Verify that foundations are within tolerances specified.3. Verify that reinforcing dowels are properly placed.4. Verify that substrates are free of substances that would impair mortar bond.

B. Before installation, examine rough-in and built-in construction for piping systems to verify actual locations of piping.

C. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 INSTALLATION, GENERAL

A. Build chases and recesses to accommodate items specified in this and other Sections.

B. Leave openings for equipment to be installed before completing masonry. After installing equipment, complete masonry to match construction immediately adjacent to opening.

C. Use full-size units without cutting if possible. If cutting is required to provide a continuous pattern or to fit adjoining construction, cut units with motor-driven saws; provide clean, sharp, unchipped edges. Allow units to dry before laying unless wetting of units is specified. Install cut units with cut surfaces and, where possible, cut edges concealed.

rhinson
Rectangle
rhinson
Snapshot
Page 35: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

CONCRETE UNIT MASONRY 042200 - 9

3.3 TOLERANCES

A. Dimensions and Locations of Elements:

1. For dimensions in cross section or elevation, do not vary by more than plus 1/2 inch (12 mm) or minus 1/4 inch (6 mm).

2. For location of elements in plan, do not vary from that indicated by more than plus or minus 1/2 inch (12 mm).

3. For location of elements in elevation, do not vary from that indicated by more than plus or minus 1/4 inch (6 mm) in a story height or 1/2 inch (12 mm) total.

B. Lines and Levels:

1. For bed joints and top surfaces of bearing walls, do not vary from level by more than 1/4 inch in 10 feet (6 mm in 3 m), or 1/2-inch (12-mm) maximum.

2. For conspicuous horizontal lines, such as lintels, sills, parapets, and reveals, do not vary from level by more than 1/8 inch in 10 feet (3 mm in 3 m), 1/4 inch in 20 feet (6 mm in 6 m), or 1/2-inch (12-mm) maximum.

3. For vertical lines and surfaces do not vary from plumb by more than 1/4 inch in 10 feet (6 mm in 3 m), 3/8 inch in 20 feet (9 mm in 6 m), or 1/2-inch (12-mm) maximum.

4. For conspicuous vertical lines, such as external corners, door jambs, reveals, and expansion and control joints, do not vary from plumb by more than 1/8 inch in 10 feet (3 mm in 3 m), 1/4 inch in 20 feet (6 mm in 6 m), or 1/2-inch (12-mm) maximum.

5. For lines and surfaces, do not vary from straight by more than 1/4 inch in 10 feet (6 mm in 3 m), 3/8 inch in 20 feet (9 mm in 6 m), or 1/2-inch (12-mm) maximum.

6. For vertical alignment of exposed head joints, do not vary from plumb by more than 1/4 inch in 10 feet (6 mm in 3 m), or 1/2-inch (12-mm) maximum.

7. For faces of adjacent exposed masonry units, do not vary from flush alignment by more than 1/16 inch (1.5 mm).

C. Joints:

1. For bed joints, do not vary from thickness indicated by more than plus or minus 1/8 inch (3 mm), with a maximum thickness limited to 1/2 inch (12 mm).

2. For exposed bed joints, do not vary from bed-joint thickness of adjacent courses by more than 1/8 inch (3 mm).

3. For head and collar joints, do not vary from thickness indicated by more than plus 3/8 inch (9 mm) or minus 1/4 inch (6 mm).

4. For exposed head joints, do not vary from thickness indicated by more than plus or minus 1/8 inch (3 mm).

3.4 LAYING MASONRY WALLS

A. Lay out walls in advance for accurate spacing of surface bond patterns with uniform joint thicknesses and for accurate location of openings, movement-type joints, returns, and offsets. Avoid using less-than-half-size units, particularly at corners, jambs, and, where possible, at other locations.

B. Bond Pattern for Exposed Masonry: Unless otherwise indicated, lay exposed masonry in running bond; do not use units with less-than-nominal 4-inch (100-mm) horizontal face dimensions at corners or jambs.

rhinson
Rectangle
rhinson
Snapshot
Page 36: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

CONCRETE UNIT MASONRY 042200 - 10

C. Lay concealed masonry with all units in a wythe in running bond or bonded by lapping not less than 2 inches (50 mm). Bond and interlock each course of each wythe at corners. Do not use units with less-than-nominal 4-inch (100-mm) horizontal face dimensions at corners or jambs.

D. Stopping and Resuming Work: Stop work by stepping back units in each course from those in course below; do not tooth. When resuming work, clean masonry surfaces that are to receive mortar, remove loose masonry units and mortar, and wet brick if required before laying fresh masonry.

E. Built-in Work: As construction progresses, build in items specified in this and other Sections. Fill in solidly with masonry around built-in items.

F. Fill space between steel frames and masonry solidly with mortar unless otherwise indicated.

G. Where built-in items are to be embedded in cores of hollow masonry units, place a layer of metal lath, wire mesh, or plastic mesh in the joint below, and rod mortar or grout into core.

H. Fill cores in hollow CMUs with grout 24 inches (600 mm) under bearing plates, beams, lintels, posts, and similar items unless otherwise indicated.

I. Build non-load-bearing interior partitions full height of story to underside of solid floor or roof structure above unless otherwise indicated.

1. Install compressible filler in joint between top of partition and underside of structure above.

2. Fasten partition top anchors to structure above and build into top of partition. Grout cells of CMUs solidly around plastic tubes of anchors and push tubes down into grout to provide 1/2-inch (13-mm) clearance between end of anchor rod and end of tube. Space anchors 48 inches (1200 mm) o.c. unless otherwise indicated.

3. Wedge non-load-bearing partitions against structure above with small pieces of tile, slate, or metal. Fill joint with mortar after dead-load deflection of structure above approaches final position.

4. At fire-rated partitions, treat joint between top of partition and underside of structure above to comply with Section 078443 "Joint Firestopping."

3.5 MORTAR BEDDING AND JOINTING

A. Lay hollow CMUs as follows:

1. Bed face shells in mortar and make head joints of depth equal to bed joints.2. Bed webs in mortar in all courses of piers, columns, and pilasters.3. Bed webs in mortar in grouted masonry, including starting course on footings.4. Fully bed entire units, including areas under cells, at starting course on footings where

cells are not grouted.

B. Lay solid CMUs with completely filled bed and head joints; butter ends with sufficient mortar to fill head joints and shove into place. Do not deeply furrow bed joints or slush head joints.

C. Tool exposed joints slightly concave when thumbprint hard, using a jointer larger than joint thickness unless otherwise indicated.

rhinson
Rectangle
rhinson
Snapshot
Page 37: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

CONCRETE UNIT MASONRY 042200 - 11

3.6 MASONRY-JOINT REINFORCEMENT

A. General: Install entire length of longitudinal side rods in mortar with a minimum cover of 5/8 inch (16 mm) on exterior side of walls, 1/2 inch (13 mm) elsewhere. Lap reinforcement a minimum of 6 inches (150 mm).

1. Space reinforcement not more than 16 inches (406 mm) o.c.2. Provide reinforcement not more than 8 inches (203 mm) above and below wall openings

and extending 12 inches (305 mm) beyond openings in addition to continuous reinforcement.

B. Interrupt joint reinforcement at control and expansion joints unless otherwise indicated.

C. Provide continuity at wall intersections by using prefabricated T-shaped units.

D. Provide continuity at corners by using prefabricated L-shaped units.

E. Cut and bend reinforcing units as directed by manufacturer for continuity at corners, returns, offsets, column fireproofing, pipe enclosures, and other special conditions.

3.7 ANCHORING MASONRY TO STRUCTURAL STEEL AND CONCRETE

A. Anchor masonry to structural steel and concrete, where masonry abuts or faces structural steel or concrete, to comply with the following:

1. Provide an open space not less than 1/2 inch (13 mm) wide between masonry and structural steel or concrete unless otherwise indicated. Keep open space free of mortar and other rigid materials.

2. Anchor masonry with anchors embedded in masonry joints and attached to structure.3. Space anchors as indicated, but not more than 24 inches (610 mm) o.c. vertically and 36

inches (915 mm) o.c. horizontally.

3.8 CONTROL AND EXPANSION JOINTS

A. General: Install control- and expansion-joint materials in unit masonry as masonry progresses. Do not allow materials to span control and expansion joints without provision to allow for in-plane wall or partition movement.

B. Form control joints in concrete masonry using one of the following methods:

1. Fit bond-breaker strips into hollow contour in ends of CMUs on one side of control joint. Fill resultant core with grout, and rake out joints in exposed faces for application of sealant.

2. Install preformed control-joint gaskets designed to fit standard sash block.3. Install interlocking units designed for control joints. Install bond-breaker strips at joint.

Keep head joints free and clear of mortar, or rake out joint for application of sealant.4. Install temporary foam-plastic filler in head joints, and remove filler when unit masonry is

complete for application of sealant.

rhinson
Rectangle
rhinson
Snapshot
Page 38: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

CONCRETE UNIT MASONRY 042200 - 12

3.9 LINTELS

A. Provide masonry lintels where shown and where openings of more than 12 inches (305 mm) for brick-size units and 24 inches (610 mm) for block-size units are shown without structural steel or other supporting lintels.

B. Provide minimum bearing of 8 inches (200 mm) at each jamb unless otherwise indicated.

3.10 REINFORCED UNIT MASONRY INSTALLATION

A. Temporary Formwork and Shores: Construct formwork and shores as needed to support reinforced masonry elements during construction.

1. Construct formwork to provide shape, line, and dimensions of completed masonry as indicated. Make forms sufficiently tight to prevent leakage of mortar and grout. Brace, tie, and support forms to maintain position and shape during construction and curing of reinforced masonry.

2. Do not remove forms and shores until reinforced masonry members have hardened sufficiently to carry their own weight and other loads that may be placed on them during construction.

B. Placing Reinforcement: Comply with requirements in TMS 602/ACI 530.1/ASCE 6.

C. Grouting: Do not place grout until entire height of masonry to be grouted has attained enough strength to resist grout pressure.

1. Comply with requirements in TMS 602/ACI 530.1/ASCE 6 for cleanouts and for grout placement, including minimum grout space and maximum pour height.

2. Limit height of vertical grout pours to not more than 60 inches (1520 mm).

3.11 FIELD QUALITY CONTROL

A. Testing and Inspecting: Owner will engage special inspectors to perform tests and inspections and prepare reports. Allow inspectors access to scaffolding and work areas as needed to perform tests and inspections. Retesting of materials that fail to comply with specified requirements shall be done at Contractor's expense.

B. Testing Prior to Construction: One set of tests.

C. Testing Frequency: One set of tests for each 5000 sq. ft. (464 sq. m) of wall area or portion thereof.

D. Concrete Masonry Unit Test: For each type of unit provided, according to ASTM C 140 for compressive strength.

E. Mortar Aggregate Ratio Test (Proportion Specification): For each mix provided, according to ASTM C 780.

F. Grout Test (Compressive Strength): For each mix provided, according to ASTM C 1019.

G. Prism Test: For each type of construction provided, according to ASTM C 1314 at 7 days and at 28 days.

rhinson
Rectangle
rhinson
Snapshot
Page 39: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

CONCRETE UNIT MASONRY 042200 - 13

3.12 PARGING

A. Use a steel-trowel finish to produce a smooth, flat, dense surface with a maximum surface variation of 1/8 inch per foot (3 mm per 300 mm). Form a wash at top of parging and a cove at bottom.

B. Damp-cure parging for at least 24 hours and protect parging until cured.

3.13 REPAIRING, POINTING, AND CLEANING

A. Remove and replace masonry units that are loose, chipped, broken, stained, or otherwise damaged or that do not match adjoining units. Install new units to match adjoining units; install in fresh mortar, pointed to eliminate evidence of replacement.

B. Pointing: During the tooling of joints, enlarge voids and holes, except weep holes, and completely fill with mortar. Point up joints, including corners, openings, and adjacent construction, to provide a neat, uniform appearance. Prepare joints for sealant application, where indicated.

C. In-Progress Cleaning: Clean unit masonry as work progresses by dry brushing to remove mortar fins and smears before tooling joints.

D. Final Cleaning: After mortar is thoroughly set and cured, clean exposed masonry as follows:

1. Remove large mortar particles by hand with wooden paddles and nonmetallic scrape hoes or chisels.

2. Test cleaning methods on sample wall panel; leave one-half of panel uncleaned for comparison purposes. Obtain Architect's approval of sample cleaning before proceeding with cleaning of masonry.

3. Protect adjacent stone and non-masonry surfaces from contact with cleaner by covering them with liquid strippable masking agent or polyethylene film and waterproof masking tape.

4. Wet wall surfaces with water before applying cleaners; remove cleaners promptly by rinsing surfaces thoroughly with clear water.

5. Clean concrete masonry by applicable cleaning methods indicated in NCMA TEK 8-4A.

3.14 MASONRY WASTE DISPOSAL

A. Salvageable Materials: Unless otherwise indicated, excess masonry materials are Contractor's property. At completion of unit masonry work, remove from Project site.

B. Waste Disposal as Fill Material: Dispose of clean masonry waste, including excess or soil-contaminated sand, waste mortar, and broken masonry units, by crushing and mixing with fill material as fill is placed.

1. Crush masonry waste to less than 4 inches (100 mm) in each dimension.2. Mix masonry waste with at least two parts of specified fill material for each part of

masonry waste. Fill material is specified in Section 312000 "Earth Moving."3. Do not dispose of masonry waste as fill within 18 inches (450 mm) of finished grade.

C. Excess Masonry Waste: Remove excess clean masonry waste that cannot be used as fill, as described above or recycled, and other masonry waste, and legally dispose of off Owner's property.

END OF SECTION 042200

rhinson
Rectangle
rhinson
Snapshot
Page 40: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Room Fit-Up – Versailles, Kentucky EOP# 201732

FIRESTOPPING 078413 - 1

SECTION 078413 - FIRESTOPPING

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

1.3 Firestopping: Material or combination of materials used to retain integrity of fire-rated construction by maintaining an effective barrier against the spread of flame, smoke, and hot gases through penetrations in, or construction joints between, fire rated wall and floor assemblies.

1.4 PERFORMANCE REQUIREMENTS

A. Only tested firestop systems shall be used in specific locations as follows:

1. Penetrations for the passage of duct, cable, cable tray, conduit, piping, electrical busways and raceways through fire-rated vertical barriers (walls and partitions), horizontal barriers (floor/ceiling assemblies), and vertical service shaft walls and partitions.

2. Safing slot gaps between edge of floor slabs and curtain walls.3. Openings between structurally separate sections of wall or floors.4. Gaps between the top of walls and ceilings or roof assemblies.5. Expansion joints in walls and floors.6. Openings and penetrations in fire-rated partitions or walls containing fire doors.7. Openings around structural members which penetrate floors or walls.

B. General: For penetrations through the following fire-resistance-rated constructions, including both empty openings and openings containing penetrating items, provide through-penetration firestop systems that are produced and installed to resist spread of fire according to requirements indicated, resist passage of smoke and other gases, and maintain original fire-resistance rating of construction penetrated.

1. Fire-resistance-rated walls including fire walls, fire partitions, fire barriers and smoke barriers.

2. Fire-resistance-rated horizontal assemblies including floors, floor/ceiling assemblies and ceiling membranes of roof/ceiling assemblies.

C. Rated Systems: Provide through-penetration firestop systems with the following ratings determined per ASTM E 814 :

1. F-Rated Systems: Provide through-penetration firestop systems with F-ratings indicated, but not less than that equaling or exceeding fire-resistance rating of constructions penetrated.

2. T-Rated Systems: For the following conditions, provide through-penetration firestop systems with T-ratings indicated, as well as F-ratings, where systems protect penetrating items exposed to potential contact with adjacent materials in occupiable floor areas:

a. Penetrations located outside wall cavities.b. Penetrations located outside fire-resistance-rated shaft enclosures.

rhinson
Rectangle
rhinson
Snapshot
Page 41: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Room Fit-Up – Versailles, Kentucky EOP# 201732

FIRESTOPPING 078413 - 2

D. For through-penetration firestop systems exposed to view, traffic, moisture, and physical damage, provide products that, after curing, do not deteriorate when exposed to these conditions both during and after construction.

1. For piping penetrations for plumbing and wet-pipe sprinkler systems, provide moisture-resistant through-penetration firestop systems.

2. For floor penetrations with annular spaces exceeding 4 inches in width and exposed to possible loading and traffic, provide firestop systems capable of supporting floor loads involved, either by installing floor plates or by other means.

3. For penetrations involving insulated piping, provide through-penetration firestop systems not requiring removal of insulation.

E. For through-penetration firestop systems exposed to view, provide products with flame-spread and smoke-developed indexes of less than 25 and 450, respectively, as determined per ASTM E 84.

1.5 SUBMITTALS

A. Product Data: For each type of product indicated.

B. Shop Drawings: For each through-penetration, construction joint, edge of slab or curtain wall condition, openings between structurally separate sections of wall or floors, gaps between the top of walls and ceilings or roof assemblies and openings around structural members which penetrate floors and walls provide a firestop system, show each type of construction condition penetrated, relationships to adjoining construction and type of penetrating item. Include firestop design designation of qualified testing and inspecting agency that evidences compliance with requirements for each condition indicated.

1. Submit documentation, including illustrations, from a qualified testing and inspecting agency that is applicable to each through-penetration firestop system configuration for construction and penetrating items.

2. Where Project conditions require modification to a qualified testing and inspecting agency's illustration for a particular through-penetration firestop condition, submit illustration, with modifications marked, approved by through-penetration firestop system manufacturer's fire-protection engineer as an engineering judgment or equivalent fire-resistance-rated assembly.

C. Through-Penetration Firestop System Schedule: Indicate locations of each through-penetration firestop system, along with the following information:

1. Types of penetrating items.2. Types of constructions penetrated, including fire-resistance ratings and, where

applicable, thicknesses of construction penetrated.3. Through-penetration firestop systems for each location identified by firestop design

designation of qualified testing and inspecting agency.

D. Qualification Data: For Installer.

E. Product Test Reports: From a qualified testing agency indicating through-penetration firestop system complies with requirements, based on comprehensive testing of current products.

1.6 QUALITY ASSURANCE

A. Training: A manufacturer’s direct representative (not distributor or agent) shall be on-site during initial installation of firestop systems to train appropriate contractor personnel in proper selection

rhinson
Rectangle
rhinson
Snapshot
Page 42: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Room Fit-Up – Versailles, Kentucky EOP# 201732

FIRESTOPPING 078413 - 3

and installation procedures. This will be done per manufacturer’s written recommendations published in their literature and drawing details.

B. Installer Qualifications: A firm that has been approved by FMG according to FM 4991, UL approved Contractor or "Approval of Firestop Contractors."

C. Installer Qualifications: A firm experienced in installing through-penetration firestop systems similar in material, design, and extent to that indicated for this Project, whose work has resulted in construction with a record of successful performance. Qualifications include having the necessary experience, staff, and training to install manufacturer's products per specified requirements. Manufacturer's willingness to sell its through-penetration firestop system products to Contractor or to Installer engaged by Contractor does not in itself confer qualification on buyer.

D. Installation Responsibility: Assign installation of through-penetration firestop systems and fire-resistive joint systems in Project to a single qualified installer.

E. Source Limitations: Obtain through-penetration firestop systems, for each kind of penetration and construction condition indicated, through one source from a single manufacturer.

F. Firestop System installation must meet requirements of ASTM E 814, UL 1479 or UL 2079 tested assemblies that provide a fire rating equal to that of construction being penetrated.

G. Proposed firestop materials and methods shall conform to applicable governing codes having local jurisdiction.

H. Fire-Test-Response Characteristics: Provide through-penetration firestop systems that comply with the following requirements and those specified in Part 1 "Performance Requirements" Article:

1. Firestopping tests are performed by a qualified testing and inspecting agency. A qualified testing and inspecting agency is UL or another agency performing testing and follow-up inspection services for firestop systems acceptable to authorities having jurisdiction.

2. Through-penetration firestop systems are identical to those tested per testing standard referenced in "Part 1 Performance Requirements" Article. Provide rated systems complying with the following requirements:

a. Through-penetration firestop system products bear classification marking of qualified testing and inspecting agency.

b. Through-penetration firestop systems correspond to those indicated by reference to through-penetration firestop system designations listed by the following:

1) UL in its "Fire Resistance Directory."2) OPL in its "Directory of Listed Building Products, Materials, & Assemblies."3) ITS in its "Directory of Listed Products."

I. Preinstallation Conference: Conduct conference at Project site to comply with requirements in Division 01 Section "Project Management and Coordination."

1.7 DELIVERY, STORAGE, AND HANDLING

A. Deliver through-penetration firestop system products to Project site in original, unopened containers or packages with intact and legible manufacturers' labels identifying product and manufacturer, date of manufacture, lot number, shelf life if applicable, qualified testing and inspecting agency's classification marking applicable to Project, curing time, and mixing instructions for multi-component materials.

rhinson
Rectangle
rhinson
Snapshot
Page 43: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Room Fit-Up – Versailles, Kentucky EOP# 201732

FIRESTOPPING 078413 - 4

B. Store and handle materials for through-penetration firestop systems to prevent their deterioration or damage due to moisture, temperature changes, contaminants, or other causes.

1.8 PROJECT CONDITIONS

A. Environmental Limitations: Do not install firestop systems when ambient or substrate temperatures are outside limits permitted by firestop system manufacturers or when substrates are wet due to rain, frost, condensation, or other causes.

B. Ventilate through-penetration firestop systems per manufacturer's written instructions by natural means or, where this is inadequate, forced-air circulation.

1.9 COORDINATION

A. Coordinate construction of openings and penetrating items to ensure that through-penetration firestop systems are installed according to specified requirements.

B. Coordinate sizing of sleeves, openings, core-drilled holes, or cut openings to accommodate through-penetration firestop systems.

C. Notify Owner's inspecting agency at least seven days in advance of through-penetration firestop system installations; confirm dates and times on days preceding each series of installations.

D. Do not cover up through-penetration firestop system installations that will become concealed behind other construction until each installation has been examined by Owner's inspecting agency and building inspector, if required by authorities having jurisdiction.

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Available Products: Subject to compliance with requirements, through-penetration firestop systems that may be incorporated into the Work include those systems indicated in the Through-Penetration Firestop System Basis of Design Products schedule at the end of Part 3 that are produced by, but are not limited to, the following manufacturers:

1. Hilti, Inc. A/D Fire Protection Systems Inc.2. RectorSeal Corporation (The).3. 3M; Fire Protection Products Division.

2.2 FIRESTOPPING, GENERAL

A. Compatibility: Provide through-penetration firestop systems that are compatible with one another; with the substrates forming openings; and with the items, if any, penetrating through-penetration firestop systems, under conditions of service and application, as demonstrated by through-penetration firestop system manufacturer based on testing and field experience.

B. Accessories: Provide components for each through-penetration firestop system that are needed to install fill materials and to comply with Part 1 "Performance Requirements" Article. Use only components specified by through-penetration firestop system manufacturer and approved by qualified testing and inspecting agency for firestop systems indicated. Accessories include, but are not limited to, the following items:

rhinson
Rectangle
rhinson
Snapshot
Page 44: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Room Fit-Up – Versailles, Kentucky EOP# 201732

FIRESTOPPING 078413 - 5

1. Permanent forming/damming/backing materials, including the following:

a. Slag-/rock-wool-fiber insulation.b. Sealants used in combination with other forming/damming/backing materials to

prevent leakage of fill materials in liquid state.c. Fire-rated form board.d. Fillers for sealants.

2. Temporary forming materials.3. Substrate primers.4. Collars.5. Steel sleeves.

2.3 FILL MATERIALS

A. General: Provide firestop systems containing the types of fill materials indicated in the Firestop System Schedule at the end of Part 3 by referencing the types of materials described in this Article. Fill materials are those referred to in directories of referenced testing and inspecting agencies as "fill," "void," or "cavity" materials.

1. Color of through-penetration and construction joint firestop materials shall be RED.

B. Cast-in-Place Firestop Devices: Factory-assembled devices for use in cast-in-place concrete floors and consisting of an outer metallic sleeve lined with an intumescent strip, a radial extended flange attached to one end of the sleeve for fastening to concrete formwork, and a neoprene gasket.

C. Latex Sealants: Single-component latex formulations that after cure do not re-emulsify during exposure to moisture.

D. Firestop Devices: Factory-assembled collars formed from galvanized steel and lined with intumescent material sized to fit specific diameter of penetrant.

E. Intumescent Composite Sheets: Rigid panels consisting of aluminum-foil-faced elastomeric sheet bonded to galvanized steel sheet.

F. Intumescent Putties: Non-hardening dielectric, water-resistant putties containing no solvents, inorganic fibers, or silicone compounds.

G. Intumescent Wrap Strips: Single-component intumescent elastomeric sheets with aluminum foil on one side.

H. Mortars: Prepackaged dry mixes consisting of a blend of inorganic binders, hydraulic cement, fillers, and lightweight aggregate formulated for mixing with water at Project site to form a non-shrinking, homogeneous mortar.

I. Pillows/Bags: Reusable heat-expanding pillows/bags consisting of glass-fiber cloth cases filled with a combination of mineral-fiber, water-insoluble expansion agents, and fire-retardant additives.

J. Silicone Foams: Multicomponent, silicone-based liquid elastomers that, when mixed, expand and cure in place to produce a flexible, non-shrinking foam.

K. Silicone Sealants: Single-component, silicone-based, neutral-curing elastomeric sealants of grade indicated below:

rhinson
Rectangle
rhinson
Snapshot
Page 45: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Room Fit-Up – Versailles, Kentucky EOP# 201732

FIRESTOPPING 078413 - 6

1. Grade: Pourable (self-leveling) formulation for openings in floors and other horizontal surfaces, and non-sag formulation for openings in vertical and other surfaces requiring a non-slumping, gunnable sealant, unless indicated firestop system limits use to non-sag grade for both opening conditions.

2. Grade for Horizontal Surfaces: Pourable (self-leveling) formulation for openings in floors and other horizontal surfaces.

3. Grade for Vertical Surfaces: Non-sag formulation for openings in vertical and other surfaces.

2.4 MIXING

A. For those products requiring mixing before application, comply with through-penetration firestop system manufacturer's written instructions for accurate proportioning of materials, water (if required), type of mixing equipment, selection of mixer speeds, mixing containers, mixing time, and other items or procedures needed to produce products of uniform quality with optimum performance characteristics for application indicated.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine substrates and conditions, with Installer present, for compliance with requirements for opening configurations, penetrating items, substrates, and other conditions affecting performance of work.

1. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 PREPARATION

A. Surface Cleaning: Clean out openings immediately before installing through-penetration firestop systems to comply with firestop system manufacturer's written instructions and with the following requirements:

1. Remove from surfaces of opening substrates and from penetrating items foreign materials that could interfere with adhesion of through-penetration firestop systems.

2. Clean opening substrates and penetrating items to produce clean, sound surfaces capable of developing optimum bond with through-penetration firestop systems. Remove loose particles remaining from cleaning operation.

3. Remove laitance and form-release agents from concrete.

B. Priming: Prime substrates where recommended in writing by through-penetration firestop system manufacturer using that manufacturer's recommended products and methods. Confine primers to areas of bond; do not allow spillage and migration onto exposed surfaces.

C. Masking Tape: Use masking tape to prevent through-penetration firestop systems from contacting adjoining surfaces that will remain exposed on completion of Work and that would otherwise be permanently stained or damaged by such contact or by cleaning methods used to remove smears from firestop system materials. Remove tape as soon as possible without disturbing firestop system's seal with substrates.

rhinson
Rectangle
rhinson
Snapshot
Page 46: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Room Fit-Up – Versailles, Kentucky EOP# 201732

FIRESTOPPING 078413 - 7

3.3 FIRESTOP SYSTEM INSTALLATION

A. Regulatory Requirements: Install firestop materials in accordance with UL Fire Resistance Directory or Omega Point Laboratories Directory.

B. Manufacturer's Instructions: Comply with manufacturer's instructions for installation of through-penetration and construction joint materials.

1. Seal all holes or voids made by penetrations to ensure an air and water resistant seal.

2. Consult with mechanical engineer, project manager, and damper manufacturer prior to installation of UL firestop systems that might hamper the performance of fire dampers as it pertains to duct work.

3. Protect materials from damage on surfaces subjected to traffic.

C. General: Install through-penetration firestop systems to comply with Part 1 "Performance Requirements" Article and with firestop system manufacturer's written installation instructions and published drawings for products and applications indicated.

D. Install forming/damming/backing materials and other accessories of types required to support fill materials during their application and in the position needed to produce cross-sectional shapes and depths required to achieve fire ratings indicated.

1. After installing fill materials and allowing them to fully cure, remove combustible forming materials and other accessories not indicated as permanent components of firestop systems.

E. Install fill materials for firestop systems by proven techniques to produce the following results:

1. Fill voids and cavities formed by openings, forming materials, accessories, and penetrating items as required to achieve fire-resistance ratings indicated.

2. Apply materials so they contact and adhere to substrates formed by openings and penetrating items.

3. For fill materials that will remain exposed after completing Work, finish to produce smooth, uniform surfaces that are flush with adjoining finishes.

3.4 IDENTIFICATION

A. Identify through-penetration firestop systems with preprinted metal or plastic labels. Attach labels permanently to surfaces adjacent to and within 6 inches of edge of the firestop systems so that labels will be visible to anyone seeking to remove penetrating items or firestop systems. Use mechanical fasteners for metal labels. For plastic labels, use self-adhering type with adhesives capable of permanently bonding labels to surfaces on which labels are placed and, in combination with label material, will result in partial destruction of label if removal is attempted. Include the following information on labels:

1. The words "Warning - Through-Penetration Firestop System - Do Not Disturb. Notify Building Management of Any Damage."

2. Contractor's name, address, and phone number.3. Through-penetration firestop system designation of applicable testing and inspecting

agency.4. Date of installation.5. Through-penetration firestop system manufacturer's name.6. Installer's name.

rhinson
Rectangle
rhinson
Snapshot
Page 47: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Room Fit-Up – Versailles, Kentucky EOP# 201732

FIRESTOPPING 078413 - 8

3.5 FIELD QUALITY CONTROL

A. Inspecting Agency: Owner will engage a qualified, independent inspecting agency to inspect through-penetration firestops. Independent inspecting agency shall comply with ASTM E 2174 requirements including those related to qualifications, conducting inspections, and preparing test reports.

B. Where deficiencies are found, repair or replace through-penetration firestop systems so they comply with requirements.

C. Proceed with enclosing through-penetration firestop systems with other construction only after inspection reports are issued and firestop installations comply with requirements.

3.6 CLEANING AND PROTECTING

A. Clean off excess fill materials adjacent to openings as Work progresses by methods and with cleaning materials that are approved in writing by through-penetration firestop system manufacturers and that do not damage materials in which openings occur.

B. Provide final protection and maintain conditions during and after installation that ensure that through-penetration firestop systems are without damage or deterioration at time of Substantial Completion. If, despite such protection, damage or deterioration occurs, cut out and remove damaged or deteriorated through-penetration firestop systems immediately and install new materials to produce systems complying with specified requirements.

3.7 FIRESTOP SYSTEM BASIS OF DESIGN PRODUCTS

A. Basis-of-Design Product: Establishes the significant qualities related to type, function, dimension, in-service performance, physical properties, appearance, and other characteristics for purposes of evaluating comparable products of other named manufacturers. Subject to compliance with requirements, and approval by the Architect, other manufacturer’s products may be incorporated into the Work.

B. Use only firestop products that have been UL 1479, ASTM E 814 or UL 2079 tested for specific fire-rated construction conditions conforming to construction assembly type, penetrating item type, annular space requirements, and fire-rating involved for each separate instance.

C. Cast-in place firestop devices for use with noncombustible and combustible pipes (closed and open systems), conduit, and cable bundles penetrating concrete floors, the following Basis of Design products are acceptable:

1. Hilti CP 680-P Cast-In Place Firestop Device

a. Add Aerator adaptor when used in conjunction with aerator (“sovent”) system.

2. Hilti CP 681 Tub Box Kit for use with tub installations.3. Hilti CP 680-M Cast-In Place Firestop Device for use with noncombustible

penetrants.4. Hilti CP 653 Speed Sleeve for use with cable penetrations.5. Hilti CFS-DID Firestop Drop-In Device for use with noncombustible and

combustible penetrants.

D. Sealants, caulking materials, or foams for use with non-combustible items including steel pipe, copper pipe, rigid steel conduit and electrical metallic tubing (EMT), the following Basis of Design products are acceptable:

rhinson
Rectangle
rhinson
Snapshot
Page 48: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Room Fit-Up – Versailles, Kentucky EOP# 201732

FIRESTOPPING 078413 - 9

1. Hilti FS-ONE Intumescent Firestop Sealant2. Hilti CP 604 Self-leveling Firestop Sealant3. Hilti CP 620 Fire Foam4. Hilti CP 606 Flexible Firestop Sealant5. Hilti CP 601s Elastomeric Firestop Sealant

E. Sealants or caulking materials for use with sheet metal ducts, the following Basis of Design products are acceptable:

1. Hilti CP 601s Elastomeric Firestop Sealant2. Hilti CP 606 Flexible Firestop Sealant3. Hilti FS-ONE Intumescent Firestop Sealant

F. Sealants, caulking or spray materials for use with fire-rated construction joints and other gaps, the following Basis of Design products are acceptable:

1. Hilti CP 672 or CP 672 FC Speed Spray2. Hilti CP 601s Elastomeric Firestop Sealant3. Hilti CP 606 Flexible Firestop Sealant4. Hilti CP 604 Self-leveling Firestop Sealant5. Hilti CFS-SP WB Firestop Joint Spray

G. Pre-formed mineral wool designed to fit flutes of metal profile deck and gap between top of wall and metal profile deck; as a backer for spray material. The following Basis of Design products are acceptable:

1. Hilti CP 777 Speed Plugs2. Hilti CP 767 Speed Strips

H. Intumescent sealants, caulking materials for use with combustible items (penetrants consumed by high heat and flame) including insulated metal pipe, PVC jacketed, flexible cable or cable bundles and plastic pipe, the following Basis of Design products are acceptable:

1. Hilti FS-ONE Intumescent Firestop Sealant

I. Foams, intumescent sealants, or caulking materials for use with flexible cable or cable bundles, the following Basis of Design products are acceptable:

1. Hilti FS-ONE Intumescent Firestop Sealant2. Hilti CP 620 Fire Foam3. Hilti CP 601s Elastomeric Firestop Sealant4. Hilti CP 606 Flexible Firestop Sealant

J. Non-curing, re-penetrable intumescent putty or foam materials for use with flexible cable or cable bundles, the following Basis of Design products are acceptable:

1. Hilti CP 618 Firestop Putty Stick2. Hilti CP 658T Firestop Plug

K. Wall opening protective materials for use with U.L. listed metallic and specified nonmetallic outlet boxes, the following Basis of Design products are acceptable:

1. Hilti CP 617 Firestop Putty Pad

L. Firestop collar or wrap devices attached to assembly around combustible plastic pipe (closed and open piping systems), the following Basis of Design products are acceptable:

rhinson
Rectangle
rhinson
Snapshot
Page 49: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Room Fit-Up – Versailles, Kentucky EOP# 201732

FIRESTOPPING 078413 - 10

1. Hilti CP 643N Firestop Collar2. Hilti CP 644 Firestop Collar3. Hilti CP 645/648 Wrap Strips

M. Materials used for large openings and complex penetrations made to accommodate cable trays and bundles, multiple steel and copper pipes, electrical busways in raceways, the following Basis of Design products are acceptable:

1. Hilti CP 637 Firestop Mortar2. Hilti FS 657 FIRE BLOCK3. Hilti CP 620 Fire Foam4. Hilti CP 675T Firestop Board

N. Non curing, re-penetrable materials used for large size/complex penetrations made to accommodate cable trays and bundles, multiple steel and copper pipes, electrical busways in raceways, the following Basis of Design products are acceptable:

1. Hilti FS 657 FIRE BLOCK2. Hilti CP 675T Firestop Board

O. Sealants or caulking materials used for openings between structurally separate sections of wall and floors, the following Basis of Design products are acceptable:

1. Hilti CP 672 Speed Spray2. Hilti CP 601s Elastomeric Firestop Sealant3. Hilti CP 606 Flexible Firestop Sealant

4. Hilti CP 604 Self-Leveling Firestop Sealant5. Hilti CFS-SP WB Firestop Joint Spray

P. For blank openings made in fire-rated wall or floor assemblies, where future penetration of pipes, conduits, or cables is expected, the following Basis of Design products are acceptable:

1. Hilti CP653 SPEED SLEEVE2. Hilti FS 657 FIRE BLOCK3. Hilti CP 658T Firestop Plug

Q. Provide a firestop system with a "F" Rating as determined by UL 1479 or ASTM E814 which is equal to the time rating of construction being penetrated.

R. Provide a firestop system with an Assembly Rating as determined by UL 2079 which is equal to the time rating of construction joint assembly.

THROUGH-PENETRATION FIRESTOP SYSTEM SCHEDULE

rhinson
Rectangle
rhinson
Snapshot
Page 50: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Room Fit-Up – Versailles, Kentucky EOP# 201732

FIRESTOPPING 078413 - 11

END OF SECTION 078413

rhinson
Rectangle
rhinson
Snapshot
Page 51: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

JOINT SEALANTS 079200 - 1

SECTION 079200 - JOINT SEALANTS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section includes joint sealants for the following applications, including those specified by reference to this Section:

1. Interior joints in the following vertical surfaces and horizontal non-traffic surfaces:

a. Control and expansion joints on exposed interior surfaces of exterior walls.b. Perimeter joints between interior wall surfaces and frames of interior doors and

windows.c. Other joints as indicated.

2. Interior joints in the following horizontal traffic surfaces:

a. Isolation joints in cast-in-place concrete slabs.b. Other joints as indicated.

3. All other joints greater than or equal to 0.125 inches in width.

1.3 PERFORMANCE REQUIREMENTS

A. Provide elastomeric joint sealants that establish and maintain watertight and airtight continuous joint seals without staining or deteriorating joint substrates.

B. Provide joint sealants for interior applications that establish and maintain airtight and water-resistant continuous joint seals without staining or deteriorating joint substrates.

1.4 SUBMITTALS

A. Product Data: For each joint-sealant product indicated.

B. Samples for Initial Selection: Manufacturer's color charts consisting of strips of cured sealants showing the full range of colors available for each product exposed to view.

C. Samples for Verification: For each type and color of joint sealant required, provide Samples with joint sealants in 1/2-inch- wide joints formed between two 6-inch- long strips of material matching the appearance of exposed surfaces adjacent to joint sealants.

D. Product Certificates: For each type of joint sealant and accessory, signed by product manufacturer.

rhinson
Rectangle
rhinson
Snapshot
Page 52: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

JOINT SEALANTS 079200 - 2

E. Qualification Data: For Installer.

F. Pre-construction Field Test Reports: Indicate which sealants and joint preparation methods resulted in optimum adhesion to joint substrates based on preconstruction testing specified in "Quality Assurance" Article.

G. Compatibility and Adhesion Test Reports: From sealant manufacturer, indicating the following:

1. Materials forming joint substrates and joint-sealant backings have been tested for compatibility and adhesion with joint sealants.

2. Interpretation of test results and written recommendations for primers and substrate preparation needed for adhesion.

H. Field Test Report Log: For each elastomeric sealant application.

I. Product Test Reports: Based on comprehensive testing of product formulations performed by a qualified testing agency, indicating that sealants comply with requirements.

J. Warranties: Special warranties specified in this Section.

1.5 QUALITY ASSURANCE

A. Installer Qualifications: Manufacturer's authorized Installer who is approved or licensed for installation of elastomeric sealants required for this Project.

B. Source Limitations: Obtain each type of joint sealant through one source from a single manufacturer.

C. Pre-construction Compatibility and Adhesion Testing: Submit to joint-sealant manufacturers, for testing indicated below, samples of materials that will contact or affect joint sealants.

1. Use manufacturer's standard test method to determine whether priming and other specific joint preparation techniques are required to obtain rapid, optimum adhesion of joint sealants to joint substrates.

2. Submit not fewer than eight pieces of each type of material, including joint substrates, shims, joint-sealant backings, secondary seals, and miscellaneous materials.

3. Schedule sufficient time for testing and analyzing results to prevent delaying the Work.4. For materials failing tests, obtain joint-sealant manufacturer's written instructions for

corrective measures including use of specially formulated primers.5. Testing will not be required if joint-sealant manufacturers submit joint preparation data

that are based on previous testing of current sealant products for adhesion to, and compatibility with, joint substrates and other materials matching those submitted.

D. Product Testing: Obtain test results for "Product Test Reports" Paragraph in "Submittals" Article from a qualified testing agency based on testing current sealant formulations within a 36-month period preceding the Notice to Proceed with the Work.

1. Testing Agency Qualifications: An independent testing agency qualified according to ASTM C 1021 to conduct the testing indicated, as documented according to ASTM E 548.

2. Test elastomeric joint sealants for compliance with requirements specified by reference to ASTM C 920, and where applicable, to other standard test methods.

3. Test other joint sealants for compliance with requirements indicated by referencing standard specifications and test methods.

rhinson
Rectangle
rhinson
Snapshot
Page 53: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

JOINT SEALANTS 079200 - 3

1.6 PROJECT CONDITIONS

A. Do not proceed with installation of joint sealants under the following conditions:

1. When ambient and substrate temperature conditions are outside limits permitted by joint-sealant manufacturer.

2. When joint substrates are wet.3. Where joint widths are less than those allowed by joint-sealant manufacturer for

applications indicated.4. Contaminants capable of interfering with adhesion have not yet been removed from joint

substrates.

1.7 WARRANTY

A. Special Installer's Warranty: Installer's standard form in which Installer agrees to repair or replace elastomeric joint sealants that do not comply with performance and other requirements specified in this Section within specified warranty period.

1. Warranty Period: Two years from date of Substantial Completion.

B. Special Manufacturer's Warranty: Manufacturer's standard form in which elastomeric sealant manufacturer agrees to furnish elastomeric joint sealants to repair or replace those that do not comply with performance and other requirements specified in this Section within specified warranty period.

1. Warranty Period: 20 years from date of Substantial Completion.

C. Special warranties specified in this Article exclude deterioration or failure of elastomeric joint sealants from the following:

1. Movement of the structure resulting in stresses on the sealant exceeding sealant manufacturer's written specifications for sealant elongation and compression caused by structural settlement or errors attributable to design or construction.

2. Disintegration of joint substrates from natural causes exceeding design specifications.3. Mechanical damage caused by individuals, tools, or other outside agents.4. Changes in sealant appearance caused by accumulation of dirt or other atmospheric

contaminants.

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Available Products: Subject to compliance with requirements, products that may be incorporated into the Work include, but are not limited to, products listed in other Part 2 articles.

2.2 MATERIALS, GENERAL

A. Compatibility: Provide joint sealants, backings, and other related materials that are compatible with one another and with joint substrates under conditions of service and application, as demonstrated by sealant manufacturer, based on testing and field experience.

rhinson
Rectangle
rhinson
Snapshot
Page 54: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

JOINT SEALANTS 079200 - 4

B. Colors of Exposed Joint Sealants: Provide manufacturers full range of standard colors for Architect selection.

2.3 ELASTOMERIC JOINT SEALANTS

A. Elastomeric Sealants: Comply with ASTM C 920 and other requirements indicated for each liquid-applied chemically curing sealant specified, including those referencing ASTM C 920 classifications for type, grade, class, and uses related to exposure and joint substrates.

B. Stain-Test-Response Characteristics: Where elastomeric sealants are specified to be non-staining to porous substrates, provide products that have undergone testing according to ASTM C 1248 and have not stained porous joint substrates indicated for Project.

C. Single-Component Neutral- and Basic-Curing Silicone Sealant:

1. Available Products:

a. Dow Corning Corporation; 790 at Application A.b. Dow Corning Corporation; 795 at Application B.c. Tremco; Spectrem 3 at Application A.d. Tremco; Spectrem 2 at Application B.e. Pecora Corporation; 890 at Application A.f. Pecora Corporation; 895 at Application B.

2. Type and Grade: S (single component) and NS (non-sag).3. Class: 50.4. Use Related to Exposure: NT (non-traffic).5. Uses Related to Joint Substrates: M, G, A and O.6. Stain-Test-Response Characteristics: Non-staining to porous substrates per

ASTM C 1248.7. Ultra low-modulus non-acid-curing silicone sealant shall include 20-year warranty against

staining of adjacent porous substrates.8. Application A

a. Aluminum Storefront System

9. Application B

a. Glass and glazing.

D. Single-Component Mildew-Resistant Neutral-Curing Silicone Sealant:

1. Available Products:

a. Pecora Corporation; 898.b. Tremco; Tremsil 600 White.

2. Type and Grade: S (single component) and NS (non-sag).3. Class: 25.4. Use Related to Exposure: NT (non-traffic).5. Uses Related to Joint Substrates: G, A and O.6. Applications: Ceramic tile and other non-porous substrates that are subject to in-service

exposures of high humidity.

E. Multi-component Non-sag Urethane Sealant:

rhinson
Rectangle
rhinson
Snapshot
Page 55: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

JOINT SEALANTS 079200 - 5

1. Available Products:

a. Pecora Corporation; Dynatrol II.b. Tremco; Dymeric 511.c. Tremco; Vulkem 922.

2. Type and Grade: M (multicomponent) and NS (non-sag).3. Class: 50.4. Uses Related to Exposure: NT (non-traffic) and T (traffic).5. Uses Related to Joint Substrates: M, A and O.6. Applications: Use for expansion joints in paving, walks and curbs.

F. Multicomponent Pourable Urethane Sealant:

1. Available Products:

a. Pecora Corporation; Urexpan NR-200.b. Tremco; THC-900.c. Tremco; Vulkem 245.

2. Type and Grade: M (multi-component) and P (pourable).3. Class: 25.4. Use Related to Exposure: T (traffic).5. Uses Related to Joint Substrates: M, A, and O.6. Applications: Use for horizontal expansion joints in paving and walks,.

G. Single-Component Nonsag Urethane Sealant:

1. Available Products:

a. Sika Corporation, Inc.; Sikaflex - 1a.b. Sonneborn, Division of ChemRex Inc.; NP 1.c. Tremco; Vulkem 116.

2. Type and Grade: S (single component) and NS (nonsag).3. Class: 25.4. Uses Related to Exposure: T (traffic) and NT (nontraffic).5. Uses Related to Joint Substrates: M, A, and O.6. Applications: Use for expansion joints in paving, walks and curbs.

2.4 LATEX JOINT SEALANTS

A. Latex Sealant: Comply with ASTM C 834, Type P, Grade NF.

B. Available Products:

1. Pecora Corporation; AC-20+.2. Tremco; Tremflex 834.

C. Applications: Caulking of Interior joints between dissimilar materials.

rhinson
Rectangle
rhinson
Snapshot
Page 56: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

JOINT SEALANTS 079200 - 6

2.5 JOINT-SEALANT BACKING

A. General: Provide sealant backings of material and type that are non-staining; are compatible with joint substrates, sealants, primers, and other joint fillers; and are approved for applications indicated by sealant manufacturer based on field experience and laboratory testing.

B. Cylindrical Sealant Backings: ASTM C 1330, Type C (closed-cell material with a surface skin), and of size and density to control sealant depth and otherwise contribute to producing optimum sealant performance:

C. Bond-Breaker Tape: Polyethylene tape or other plastic tape recommended by sealant manufacturer for preventing sealant from adhering to rigid, inflexible joint-filler materials or joint surfaces at back of joint where such adhesion would result in sealant failure. Provide self-adhesive tape where applicable.

2.6 MISCELLANEOUS MATERIALS

A. Primer: Material recommended by joint-sealant manufacturer where required for adhesion of sealant to joint substrates indicated, as determined from preconstruction joint-sealant-substrate tests and field tests.

B. Cleaners for Nonporous Surfaces: Chemical cleaners acceptable to manufacturers of sealants and sealant backing materials, free of oily residues or other substances capable of staining or harming joint substrates and adjacent nonporous surfaces in any way, and formulated to promote optimum adhesion of sealants to joint substrates.

C. Masking Tape: Non-staining, nonabsorbent material compatible with joint sealants and surfaces adjacent to joints.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine joints indicated to receive joint sealants, with Installer present, for compliance with requirements for joint configuration, installation tolerances, and other conditions affecting joint-sealant performance.

B. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 PREPARATION

A. Surface Cleaning of Joints: Clean out joints immediately before installing joint sealants to comply with joint-sealant manufacturer's written instructions and the following requirements:

1. Remove all foreign material from joint substrates that could interfere with adhesion of joint sealant, including dust, paints (except for permanent, protective coatings tested and approved for sealant adhesion and compatibility by sealant manufacturer), old joint sealants, oil, grease, waterproofing, water repellents, water, surface dirt, and frost.

2. Clean porous joint substrate surfaces by brushing, grinding, blast cleaning, mechanical abrading, or a combination of these methods to produce a clean, sound substrate capable of developing optimum bond with joint sealants. Remove loose particles

rhinson
Rectangle
rhinson
Snapshot
Page 57: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

JOINT SEALANTS 079200 - 7

remaining after cleaning operations above by vacuuming or blowing out joints with oil-free compressed air. Porous joint substrates include the following:

a. Concrete.b. Masonry.

3. Remove laitance and form-release agents from concrete.4. Clean nonporous surfaces with chemical cleaners or other means that do not stain, harm

substrates, or leave residues capable of interfering with adhesion of joint sealants. Nonporous joint substrates include the following:

a. Metal.

B. Joint Priming: Prime joint substrates, where recommended in writing by joint-sealant manufacturer, based on preconstruction joint-sealant-substrate tests or prior experience. Apply primer to comply with joint-sealant manufacturer's written instructions. Confine primers to areas of joint-sealant bond; do not allow spillage or migration onto adjoining surfaces.

C. Masking Tape: Use masking tape where required to prevent contact of sealant with adjoining surfaces that otherwise would be permanently stained or damaged by such contact or by cleaning methods required to remove sealant smears. Remove tape immediately after tooling without disturbing joint seal.

3.3 INSTALLATION OF JOINT SEALANTS

A. General: Comply with joint-sealant manufacturer's written installation instructions for products and applications indicated, unless more stringent requirements apply.

B. Where Required: Any joint with a nominal width of 0.125 inches or wider shall receive joint sealant appropriate for location and use of materials forming the joint.

C. Sealant Installation Standard: Comply with recommendations in ASTM C 1193 for use of joint sealants as applicable to materials, applications, and conditions indicated.

D. Install sealant backings of type indicated to support sealants during application and at position required to produce cross-sectional shapes and depths of installed sealants relative to joint widths that allow optimum sealant movement capability.

1. Do not leave gaps between ends of sealant backings.2. Do not stretch, twist, puncture, or tear sealant backings.3. Remove absorbent sealant backings that have become wet before sealant application

and replace them with dry materials.

E. Install bond-breaker tape behind sealants where sealant backings are not used between sealants and backs of joints.

F. Install sealants using proven techniques that comply with the following and at the same time backings are installed:

1. Place sealants so they directly contact and fully wet joint substrates.2. Completely fill recesses in each joint configuration.3. Produce uniform, cross-sectional shapes and depths relative to joint widths that allow

optimum sealant movement capability.

rhinson
Rectangle
rhinson
Snapshot
Page 58: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

JOINT SEALANTS 079200 - 8

G. Tooling of Non-sag Sealants: Immediately after sealant application and before skinning or curing begins, tool sealants according to requirements specified below to form smooth, uniform beads of configuration indicated; to eliminate air pockets; and to ensure contact and adhesion of sealant with sides of joint.

1. Remove excess sealant from surfaces adjacent to joints.2. Use tooling agents that are approved in writing by sealant manufacturer and that do not

discolor sealants or adjacent surfaces.3. Provide concave joint configuration per Figure 5A in ASTM C 1193, unless otherwise

indicated.

3.4 CLEANING

A. Clean off excess sealant or sealant smears adjacent to joints as the Work progresses by methods and with cleaning materials approved in writing by manufacturers of joint sealants and of products in which joints occur.

3.5 PROTECTION

A. Protect joint sealants during and after curing period from contact with contaminating substances and from damage resulting from construction operations or other causes so sealants are without deterioration or damage at time of Substantial Completion. If, despite such protection, damage or deterioration occurs, cut out and remove damaged or deteriorated joint sealants immediately so installations with repaired areas are indistinguishable from original work.

END OF SECTION 079200

rhinson
Rectangle
rhinson
Snapshot
Page 59: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

HOLLOW METAL DOORS AND FRAMES 081113 - 1

SECTION 081113 - HOLLOW METAL DOORS AND FRAMES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes:

1. Interior standard steel doors and frames.

1.3 DEFINITIONS

A. Minimum Thickness: Minimum thickness of base metal without coatings according to NAAMM-HMMA 803 or SDI A250.8.

1.4 COORDINATION

A. Coordinate anchorage installation for hollow-metal frames. Furnish setting drawings, templates, and directions for installing anchorages, including sleeves, concrete inserts, anchor bolts, and items with integral anchors. Deliver such items to Project site in time for installation.

B. Coordinate requirements for installation of door hardware, electrified door hardware, and access control and security systems.

1.5 ACTION SUBMITTALS

A. Product Data: For each type of product.

1. Include construction details, material descriptions, core descriptions and finishes.

B. Shop Drawings: Include the following:

1. Elevations of each door type.2. Details of doors, including vertical- and horizontal-edge details and metal thicknesses.3. Frame details for each frame type, including dimensioned profiles and metal thicknesses.4. Locations of reinforcement and preparations for hardware.5. Details of each different wall opening condition.6. Details of anchorages, joints, field splices, and connections.7. Details of accessories.

C. Product Schedule: For hollow-metal doors and frames, prepared by or under the supervision of supplier, using same reference numbers for details and openings as those on Drawings. Coordinate with final door hardware schedule.

rhinson
Rectangle
rhinson
Snapshot
Page 60: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

HOLLOW METAL DOORS AND FRAMES 081113 - 2

1.6 INFORMATIONAL SUBMITTALS

A. Product Test Reports: For each type of hollow-metal door and frame assembly, for tests performed by a qualified testing agency.

1.7 DELIVERY, STORAGE, AND HANDLING

A. Deliver hollow-metal doors and frames palletized, packaged, or crated to provide protection during transit and Project-site storage. Do not use non-vented plastic.

1. Provide additional protection to prevent damage to factory-finished units.

B. Deliver welded frames with two removable spreader bars across bottom of frames, tack welded to jambs and mullions.

C. Store hollow-metal doors and frames vertically under cover at Project site with head up. Place on minimum 4-inch- (102-mm-) high wood blocking. Provide minimum 1/4-inch (6-mm) space between each stacked door to permit air circulation.

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may incorporated into the Work include, but not limited to, the following:

1. Ceco Door Products; an Assa Abloy Group company2. Curries Company; As Assa Abloy Group Company3. Fleming Door Products Ltd.; an Assa Abloy Group Company

2.2 INTERIOR STANDARD STEEL DOORS AND FRAMES

A. Construct hollow-metal doors and frames to comply with standards indicated for materials, fabrication, hardware locations, hardware reinforcement, tolerances, and clearances, and as specified.

B. Standard-Duty Doors and Frames: SDI A250.8, Level 1; SDI A250.4, Level C. At locations indicated on the drawings.

1. Doors: Basis of Design: Curries Company (CU): 707 Series.

a. Type: As indicated on the drawings.b. Thickness: 1-3/4 inches (44.5 mm).c. Face: Uncoated steel sheet, minimum thickness of 0.032 inch (0.8 mm).d. Edge Construction: Model 1, Full Flush.e. Edge Bevel: Bevel lock and hinge edges 1/8 inch in 2 inches (3.2 mm in 51 mm).f. Core: Manufacturer's standard Kraft-paper honeycomb or one-piece Polystyrene

core, securely bonded to both faces.

rhinson
Rectangle
rhinson
Snapshot
Page 61: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

HOLLOW METAL DOORS AND FRAMES 081113 - 3

2. Frames: Basis of Design: Curries Company (CU) – M Series (Masonry)

a. Materials: Uncoated steel sheet, minimum thickness of 0.042 inch (1.0 mm).b. Construction: Full profile welded.

3. Exposed Finish: Prime.

2.3 FRAME ANCHORS

A. Jamb Anchors:

1. Type: Anchors of minimum size and type required by applicable door and frame standard, and suitable for performance level indicated.

2. Quantity: Minimum of three anchors per jamb, with one additional anchor for frames with no floor anchor. Provide one additional anchor for each 24 inches (610 mm) of frame height above 7 feet (2.1 m).

3. Post-installed Expansion Anchor: Minimum 3/8-inch- (9.5-mm-) diameter bolts with expansion shields or inserts, with manufacturer's standard pipe spacer.

B. Floor Anchors: Provide floor anchors for each jamb and mullion that extends to floor.

C. Floor Anchors for Concrete Slabs with Underlayment: Adjustable-type anchors with extension clips, allowing not less than 2-inch (51-mm) height adjustment. Terminate bottom of frames at top of underlayment.

D. Material: ASTM A 879/A 879M, Commercial Steel (CS), 04Z (12G) coating designation; mill phosphatized.

1. For anchors built into exterior walls, steel sheet complying with ASTM A 1008/A 1008M or ASTM A 1011/A 1011M; hot-dip galvanized according to ASTM A 153/A 153M, Class B.

2.4 MATERIALS

A. Cold-Rolled Steel Sheet: ASTM A 1008/A 1008M, Commercial Steel (CS), Type B; suitable for exposed applications.

B. Inserts, Bolts, and Fasteners: Hot-dip galvanized according to ASTM A 153/A 153M.

2.5 FABRICATION

A. Hollow-Metal Frames: Fabricate in one piece except where handling and shipping limitations require multiple sections. Where frames are fabricated in sections, provide alignment plates or angles at each joint, fabricated of metal of same or greater thickness as frames.

1. Provide countersunk, flat- or oval-head exposed screws and bolts for exposed fasteners unless otherwise indicated.

2. Door Silencers: Except on weather-stripped frames, drill stops to receive door silencers as follows. Keep holes clear during construction.

a. Single-Door Frames: Drill stop in strike jamb to receive three door silencers.b. Double-Door Frames: Drill stop in head jamb to receive two door silencers.

rhinson
Rectangle
rhinson
Snapshot
Page 62: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

HOLLOW METAL DOORS AND FRAMES 081113 - 4

B. Hardware Preparation: Factory prepare hollow-metal doors and frames to receive templated mortised hardware, and electrical wiring; include cutouts, reinforcement, mortising, drilling, and tapping according to SDI A250.6, the Door Hardware Schedule, and templates.

1. Reinforce doors and frames to receive non-templated, mortised, and surface-mounted door hardware.

2. Comply with BHMA A156.115 for preparing hollow-metal doors and frames for hardware.

2.6 STEEL FINISHES

A. Prime Finish: Clean, pretreat, and apply manufacturer's standard primer.

1. Shop Primer: Manufacturer's standard, fast-curing, lead- and chromate-free primer complying with SDI A250.10; recommended by primer manufacturer for substrate; compatible with substrate and field-applied coatings despite prolonged exposure.

PART 3 - EXECUTION

3.1 PREPARATION

A. Remove welded-in shipping spreaders installed at factory. Restore exposed finish by grinding, filling, and dressing, as required to make repaired area smooth, flush, and invisible on exposed faces. Touch up factory-applied finishes where spreaders are removed.

B. Drill and tap doors and frames to receive non-templated, mortised, and surface-mounted door hardware.

3.2 INSTALLATION

A. General: Install hollow-metal doors and frames plumb, rigid, properly aligned, and securely fastened in place. Comply with approved Shop Drawings and with manufacturer's written instructions.

B. Hollow-Metal Frames: Comply with SDI A250.11.

1. Set frames accurately in position; plumbed, aligned, and braced securely until permanent anchors are set. After wall construction is complete, remove temporary braces without damage to completed Work.

a. Where frames are fabricated in sections, field splice at approved locations by welding face joint continuously; grind, fill, dress, and make splice smooth, flush, and invisible on exposed faces. Touch-up finishes.

2. Floor Anchors: Secure with post-installed expansion anchors.

a. Floor anchors may be set with power-actuated fasteners instead of post-installed expansion anchors if so indicated and approved on Shop Drawings.

3. Masonry Walls: Coordinate installation of frames to allow for solidly filling space between frames and masonry with grout or mortar.

4. Installation Tolerances: Adjust hollow-metal frames to the following tolerances:

rhinson
Rectangle
rhinson
Snapshot
Page 63: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

HOLLOW METAL DOORS AND FRAMES 081113 - 5

a. Squareness: Plus or minus 1/16 inch (1.6 mm), measured at door rabbet on a line 90 degrees from jamb perpendicular to frame head.

b. Alignment: Plus or minus 1/16 inch (1.6 mm), measured at jambs on a horizontal line parallel to plane of wall.

c. Twist: Plus or minus 1/16 inch (1.6 mm), measured at opposite face corners of jambs on parallel lines, and perpendicular to plane of wall.

d. Plumbness: Plus or minus 1/16 inch (1.6 mm), measured at jambs at floor.

C. Hollow-Metal Doors: Fit and adjust hollow-metal doors accurately in frames, within clearances specified below.

1. Non-Fire-Rated Steel Doors: Comply with SDI A250.8.

3.3 CLEANING AND TOUCHUP

A. Prime-Coat Touchup: Immediately after erection, sand smooth rusted or damaged areas of prime coat and apply touchup of compatible air-drying, rust-inhibitive primer.

B. Touchup Painting: Cleaning and touchup painting of abraded areas of paint are specified in painting Sections.

END OF SECTION 081113

rhinson
Rectangle
rhinson
Snapshot
Page 64: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

NON-STRUCTURAL METAL FRAMING 092216 - 1

SECTION 092216 - NON-STRUCTURAL METAL FRAMING

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Non-load-bearing steel framing systems for interior partitions.

1.3 ACTION SUBMITTALS

A. Product Data: For each type of product.

1.4 INFORMATIONAL SUBMITTALS

A. Product Certificates: For each type of code-compliance certification for studs and tracks.

1.5 QUALITY ASSURANCE

A. Code-Compliance Certification of Studs and Tracks: Provide documentation that framing members are certified according to the product-certification program of the Certified Steel Stud Association.

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. Fire-Test-Response Characteristics: For fire-resistance-rated assemblies that incorporate non-load-bearing steel framing, provide materials and construction identical to those tested in assembly indicated, according to ASTM E 119 by an independent testing agency.

B. STC-Rated Assemblies: For STC-rated assemblies, provide materials and construction identical to those tested in assembly indicated on Drawings, according to ASTM E 90 and classified according to ASTM E 413 by an independent testing agency.

2.2 FRAMING SYSTEMS

A. Framing Members, General: Comply with ASTM C 754 for conditions indicated.

rhinson
Rectangle
rhinson
Snapshot
Page 65: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

NON-STRUCTURAL METAL FRAMING 092216 - 2

1. Steel Sheet Components: Comply with ASTM C 645 requirements for metal unless otherwise indicated.

2. Protective Coating: ASTM A 653/A 653M, G40 (Z120), hot-dip galvanized unless otherwise indicated.

B. Studs and Tracks: ASTM C 645.

1. Steel Studs and Tracks:

a. Minimum Base-Metal Thickness: 20 gauge.b. Depth: As indicated on Drawings.

C. Hat-Shaped, Rigid Furring Channels: ASTM C 645.

1. Minimum Base-Metal Thickness: 0.0179 inch.2. Depth: As indicated on Drawings.

2.3 AUXILIARY MATERIALS

A. General: Provide auxiliary materials that comply with referenced installation standards.

1. Fasteners for Steel Framing: Of type, material, size, corrosion resistance, holding power, and other properties required to fasten steel members to substrates.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine areas and substrates, with Installer present, and including welded hollow-metal frames, cast-in anchors, and structural framing, for compliance with requirements and other conditions affecting performance of the Work.

B. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 INSTALLATION, GENERAL

A. Installation Standard: ASTM C 754.

1. Gypsum Board Assemblies: Also comply with requirements in ASTM C 840 that apply to framing installation.

B. Install framing and accessories plumb, square, and true to line, with connections securely fastened.

C. Install supplementary framing, and blocking to support fixtures, equipment services, heavy trim, grab bars, toilet accessories, furnishings, or similar construction.

D. Install bracing at terminations in assemblies.

E. Do not bridge building control and expansion joints with non-load-bearing steel framing members. Frame both sides of joints independently.

rhinson
Rectangle
rhinson
Snapshot
Page 66: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

NON-STRUCTURAL METAL FRAMING 092216 - 3

3.3 INSTALLING FRAMED ASSEMBLIES

A. Install framing system components according to spacings indicated, but not greater than spacings required by referenced installation standards for assembly types.

1. Single-Layer Application: 16 inches (406 mm) o.c. unless otherwise indicated.

B. Where studs are installed directly against exterior masonry walls or dissimilar metals at exterior walls, install isolation strip between studs and exterior wall.

C. Install studs so flanges within framing system point in same direction.

D. Install tracks at floors and overhead supports. Extend framing full height to structural supports or substrates above suspended ceilings except where partitions are indicated to terminate at suspended ceilings. Continue framing around ducts that penetrate partitions above ceiling.

E. Direct Furring:1. Attach to concrete or masonry with stub nails, screws designed for masonry attachment,

or powder-driven fasteners spaced 24 inches (610 mm) o.c.

F. Installation Tolerance: Install each framing member so fastening surfaces vary not more than 1/8 inch (3 mm) from the plane formed by faces of adjacent framing.

END OF SECTION 092216

rhinson
Rectangle
rhinson
Snapshot
Page 67: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

GYPSUM BOARD 092900 - 1

SECTION 092900 - GYPSUM BOARD

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Interior gypsum board.

B. Related Requirements:

1. Section 092216 "Non-Structural Metal Framing" for non-structural steel framing and suspension systems that support gypsum board panels.

1.3 ACTION SUBMITTALS

A. Product Data: For each type of product.

1.4 DELIVERY, STORAGE AND HANDLING

A. Store materials inside under cover and keep them dry and protected against weather, condensation, direct sunlight, construction traffic, and other potential causes of damage. Stack panels flat and supported on risers on a flat platform to prevent sagging.

1.5 FIELD CONDITIONS

A. Environmental Limitations: Comply with ASTM C 840 requirements or gypsum board manufacturer's written instructions, whichever are more stringent.

B. Do not install paper-faced gypsum panels until installation areas are enclosed and conditioned.

C. Do not install panels that are wet, moisture damaged, and mold damaged.

1. Indications that panels are wet or moisture damaged include, but are not limited to, discoloration, sagging, or irregular shape.

2. Indications that panels are mold damaged include, but are not limited to, fuzzy or splotchy surface contamination and discoloration.

PART 2 - PRODUCTS

A. <Double click to insert sustainable design text for low-emitting ceilings and walls.>

rhinson
Rectangle
rhinson
Snapshot
Page 68: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

GYPSUM BOARD 092900 - 2

2.2 GYPSUM BOARD, GENERAL

A. Size: Provide maximum lengths and widths available that will minimize joints in each area and that correspond with support system indicated.

2.3 INTERIOR GYPSUM BOARD

A. Gypsum Wallboard: ASTM C 1396/C 1396M.

1. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:

a. American Gypsumb. CertainTeed Groupc. National Gypsum Companyd. USG Corporation

2. Thickness: 5/8 inch (15.9 mm).

3. Long Edges: Tapered.

2.4 TRIM ACCESSORIES

A. Interior Trim: ASTM C 1047.

1. Material: Galvanized or aluminum-coated steel sheet, rolled zinc, plastic, or paper-faced galvanized-steel sheet.

2. Shapes:

a. Cornerbead.b. Bullnose bead.c. LC-Bead: J-shaped; exposed long flange receives joint compound.d. L-Bead: L-shaped; exposed long flange receives joint compound.e. U-Bead: J-shaped; exposed short flange does not receive joint compound.f. Expansion (control) joint.

2.5 JOINT TREATMENT MATERIALS

A. General: Comply with ASTM C 475/C 475M.

B. Joint Tape:

1. Interior Gypsum Board: Paper.

C. Joint Compound for Interior Gypsum Board: For each coat, use formulation that is compatible with other compounds applied on previous or for successive coats.

1. Prefilling: At open joints and damaged surface areas, use setting-type taping compound.2. Embedding and First Coat: For embedding tape and first coat on joints, fasteners, and

trim flanges, use setting-type taping compound.

a. Use setting-type compound for installing paper-faced metal trim accessories.

rhinson
Rectangle
rhinson
Snapshot
Page 69: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

GYPSUM BOARD 092900 - 3

3. Fill Coat: For second coat, use setting-type, sandable topping compound.4. Finish Coat: For third coat, use setting-type, sandable topping compound.5. Skim Coat: For final coat of Level 5 finish, use setting-type, sandable topping compound.

2.6 AUXILIARY MATERIALS

A. General: Provide auxiliary materials that comply with referenced installation standards and manufacturer's written instructions.

B. Laminating Adhesive: Adhesive or joint compound recommended for directly adhering gypsum panels to continuous substrate.

1. Laminating adhesive shall have a VOC contect of 50g/L or less when calculated according to 40 CFR 59, Subpart D (EPA Method 24).

C. Steel Drill Screws: ASTM C 1002 unless otherwise indicated.

1. Use screws complying with ASTM C 954 for fastening panels to steel members from 0.033 to 0.112 inch (0.84 to 2.84 mm) thick.

2. For fastening cementitious backer units, use screws of type and size recommended by panel manufacturer.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine areas and substrates including welded hollow-metal frames and support framing, with Installer present, for compliance with requirements and other conditions affecting performance of the Work.

B. Examine panels before installation. Reject panels that are wet, moisture damaged, and mold damaged.

C. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 APPLYING AND FINISHING PANELS, GENERAL

A. Comply with ASTM C 840.

B. Install panels with face side out. Butt panels together for a light contact at edges and ends with not more than 1/16 inch (1.5 mm) of open space between panels. Do not force into place.

C. Locate edge and end joints over supports, except in ceiling applications where intermediate supports or gypsum board back-blocking is provided behind end joints. Do not place tapered edges against cut edges or ends. Stagger vertical joints on opposite sides of partitions. Do not make joints other than control joints at corners of framed openings.

D. Form control and expansion joints with space between edges of adjoining gypsum panels.

E. Cover both faces of support framing with gypsum panels in concealed spaces (above ceilings, etc.), except in chases braced internally.

rhinson
Rectangle
rhinson
Snapshot
Page 70: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

GYPSUM BOARD 092900 - 4

1. Unless concealed application is indicated or required for sound, fire, air, or smoke ratings, coverage may be accomplished with scraps of not less than 8 sq. ft. (0.7 sq. m) in area.

2. Fit gypsum panels around ducts, pipes, and conduits.3. Where partitions intersect structural members projecting below underside of floor/roof

slabs and decks, cut gypsum panels to fit profile formed by structural members; allow 1/4- to 3/8-inch- (6.4- to 9.5-mm-) wide joints to install sealant.

F. Isolate perimeter of gypsum board applied to non-load-bearing partitions at structural abutments. Provide 1/4- to 1/2-inch- (6.4- to 12.7-mm-) wide spaces at these locations and trim edges with edge trim where edges of panels are exposed. Seal joints between edges and abutting structural surfaces with acoustical sealant.

G. Attachment to Steel Framing: Attach panels so leading edge or end of each panel is attached to open (unsupported) edges of stud flanges first.

3.3 APPLYING INTERIOR GYPSUM BOARD

A. Install interior gypsum board in the following locations:

1. Wallboard Type: As indicated on Drawings.

B. Single-Layer Application:

1. On partitions/walls, apply gypsum panels horizontally (perpendicular to framing) unless otherwise indicated or required by fire-resistance-rated assembly, and minimize end joints.

a. Stagger abutting end joints not less than one framing member in alternate courses of panels.

b. At stairwells and other high walls, install panels horizontally unless otherwise indicated or required by fire-resistance-rated assembly.

2. Fastening Methods: Apply gypsum panels to supports with steel drill screws.

3.4 INSTALLING TRIM ACCESSORIES

A. General: For trim with back flanges intended for fasteners, attach to framing with same fasteners used for panels. Otherwise, attach trim according to manufacturer's written instructions.

B. Control Joints: Install control joints according to ASTM C 840 and in specific locations approved by Architect for visual effect.

C. Interior Trim: Install in the following locations:

1. Cornerbead: Use at outside corners.2. Bullnose Bead: Use at outside corners.3. LC-Bead: Use at exposed panel edges.

rhinson
Rectangle
rhinson
Snapshot
Page 71: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

GYPSUM BOARD 092900 - 5

3.5 FINISHING GYPSUM BOARD

A. General: Treat gypsum board joints, interior angles, edge trim, control joints, penetrations, fastener heads, surface defects, and elsewhere as required to prepare gypsum board surfaces for decoration. Promptly remove residual joint compound from adjacent surfaces.

B. Prefill open joints and damaged surface areas.

C. Apply joint tape over gypsum board joints, except for trim products specifically indicated as not intended to receive tape.

D. Gypsum Board Finish Levels: Finish panels to levels indicated below and according to ASTM C 840:

1. Level 4: At panel surfaces that will be exposed to view unless otherwise indicated.

a. Primer and its application to surfaces are specified in Section 099123 "Interior Painting."

3.6 PROTECTION

A. Protect adjacent surfaces from drywall compound and promptly remove from floors and other non-drywall surfaces. Repair surfaces stained, marred, or otherwise damaged during drywall application.

B. Protect installed products from damage from weather, condensation, direct sunlight, construction, and other causes during remainder of the construction period.

C. Remove and replace panels that are wet, moisture damaged, and mold damaged.

1. Indications that panels are wet or moisture damaged include, but are not limited to, discoloration, sagging, or irregular shape.

2. Indications that panels are mold damaged include, but are not limited to, fuzzy or splotchy surface contamination and discoloration.

END OF SECTION 092900

rhinson
Rectangle
rhinson
Snapshot
Page 72: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

ACOUSTICAL PANEL CEILINGS 095113 - 1

SECTION 095113 - ACOUSTICAL PANEL CEILINGS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes acoustical panels and exposed suspension systems for interior ceilings.

B. Products furnished, but not installed under this Section, include anchors, clips, and other ceiling attachment devices to be cast in concrete.

1.3 ACTION SUBMITTALS

A. Product Data: For each type of product.

B. Source Limitations: Obtain each type of acoustical ceiling panel and supporting suspension system from single source from single manufacturer.

1.4 INFORMATIONAL SUBMITTALS

A. Qualification Data: For testing agency.

B. Product Test Reports: For each acoustical panel ceiling, for tests performed by a qualified testing agency.

C. Evaluation Reports: For each acoustical panel ceiling suspension system, from ICC-ES.

D. Field quality-control reports.

1.5 CLOSEOUT SUBMITTALS

A. Maintenance Data: For finishes to include in maintenance manuals.

1.6 MAINTENANCE MATERIAL SUBMITTALS

A. Furnish extra materials that match products installed and that are packaged with protective covering for storage and identified with labels describing contents.

1. Acoustical Ceiling Units: Full-size panels equal to 2 percent of quantity installed.2. Suspension-System Components: Quantity of each exposed component equal to 2

percent of quantity installed.3. Hold-Down Clips: Equal to 2 percent of quantity installed.

rhinson
Rectangle
rhinson
Snapshot
Page 73: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

ACOUSTICAL PANEL CEILINGS 095113 - 2

4. Impact Clips: Equal to 2 percent of quantity installed.

1.7 DELIVERY, STORAGE, AND HANDLING

A. Deliver acoustical panels, suspension-system components, and accessories to Project site and store them in a fully enclosed, conditioned space where they will be protected against damage from moisture, humidity, temperature extremes, direct sunlight, surface contamination, and other causes.

B. Before installing acoustical panels, permit them to reach room temperature and a stabilized moisture content.

1.8 FIELD CONDITIONS

A. Environmental Limitations: Do not install acoustical panel ceilings until spaces are enclosed and weathertight, wet-work in spaces is complete and dry, work above ceilings is complete, and ambient temperature and humidity conditions are maintained at the levels indicated for Project when occupied for its intended use.

1. Pressurized Plenums: Operate ventilation system for not less than 48 hours before beginning acoustical panel ceiling installation.

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Source Limitations: Obtain each type of acoustical ceiling panel and its supporting suspension system from single source from single manufacturer.

2.2 PERFORMANCE REQUIREMENTS

A. Surface-Burning Characteristics: Comply with ASTM E 84; testing by a qualified testing agency. Identify products with appropriate markings of applicable testing agency.

1. Flame-Spread Index: Class according to ASTM E 1264.2. Smoke-Developed Index: 50 or less.

2.3 ACOUSTICAL PANELS.

A. Basis of Design Product: Subject to compliance with requirements, provide Armstrong Ultima, Model #: 1901 or comparable product by one of the following:

1. USG Interiors, Inc.; Subsidiary of USG Corporation.2. CertainTeed Corp.

B. Acoustical Panel Standard: Provide manufacturer's standard panels according to ASTM E 1264 and designated by type, form, pattern, acoustical rating, and light reflectance unless otherwise indicated.

rhinson
Rectangle
rhinson
Snapshot
Page 74: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

ACOUSTICAL PANEL CEILINGS 095113 - 3

C. Classification: Provide panels as follows:

1. Type and Form: Type IV, Form 2, Pattern E, Fire Class A

D. Color: White.

E. Light Reflectance (LR): Not less than 0.90.

F. Ceiling Attenuation Class (CAC): Not less than 35.

G. Noise Reduction Coefficient (NRC): Not less than 0.75.

H. Edge/Joint Detail: Beveled Tegular.

I. Thickness: 3/4 inch (19 mm).

J. Modular Size: 24 by 24 inches (610 by 610 mm).

K. Antimicrobial Treatment: Manufacturer's standard broad spectrum, antimicrobial formulation that inhibits fungus, mold, mildew, and gram-positive and gram-negative bacteria and showing no mold, mildew, or bacterial growth when tested according to ASTM D 3273, ASTM D 3274, or ASTM G 21 and evaluated according to ASTM D 3274 or ASTM G 21.

2.4 METAL SUSPENSION SYSTEM

A. Basis of Design Product: Provide Armstrong 15/16” Prelude XL.

B. Metal Suspension-System Standard: Provide manufacturer's standard, direct-hung, metal suspension system and accessories according to ASTM C 635/C 635M and designated by type, structural classification, and finish indicated.

C. Wide-Face, Capped, Double-Web, Steel Suspension System: Main and cross runners roll formed from cold-rolled steel sheet; prepainted, electrolytically zinc coated, or hot-dip galvanized, G30 (Z90) coating designation; with prefinished 15/16-inch- (24-mm-) wide metal caps on flanges.

1. Structural Classification: Intermediate-duty system.2. End Condition of Cross Runners: Override (stepped) type.3. Face Design: Flat, flush.4. Cap Material: Cold-rolled steel.5. Cap Finish: Painted white.

2.5 ACCESSORIES

A. Attachment Devices: Size for five times the design load indicated in ASTM C 635/C 635M, Table 1, "Direct Hung," unless otherwise indicated. Comply with seismic design requirements.

1. Anchors in Concrete: Anchors of type and material indicated below, with holes or loops for attaching hangers of type indicated and with capability to sustain, without failure, a

rhinson
Rectangle
rhinson
Snapshot
Page 75: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

ACOUSTICAL PANEL CEILINGS 095113 - 4

load equal to five times that imposed by ceiling construction, as determined by testing according to ASTM E 488/E 488M or ASTM E 1512 as applicable, conducted by a qualified testing and inspecting agency.

a. Type: Post-installed expansion anchors.b. Corrosion Protection: Carbon-steel components zinc plated according to

ASTM B 633, Class SC 1 (mild) service condition.c. Corrosion Protection: Stainless-steel components complying with ASTM F 593 and

ASTM F 594, Group 1 Alloy 304 or 316.d. Corrosion Protection: Components fabricated from nickel-copper-alloy rods

complying with ASTM B 164 for UNS No. N04400 alloy.

2. Power-Actuated Fasteners in Concrete: Fastener system of type suitable for application indicated, fabricated from corrosion-resistant materials, with clips or other accessory devices for attaching hangers of type indicated and with capability to sustain, without failure, a load equal to [10] <Insert safety factor> times that imposed by ceiling construction, as determined by testing according to ASTM E 1190, conducted by a qualified testing and inspecting agency.

B. Wire Hangers, Braces, and Ties: Provide wires as follows:

1. Zinc-Coated, Carbon-Steel Wire: ASTM A 641/A 641M, Class 1 zinc coating, soft temper.2. Size: Wire diameter sufficient for its stress at three times hanger design load

(ASTM C 635/C 635M, Table 1, "Direct Hung") will be less than yield stress of wire, but not less than 0.106-inch- (2.69-mm-) diameter wire.

C. Hanger Rods: Mild steel, zinc coated or protected with rust-inhibitive paint.

D. Flat Hangers: Mild steel, zinc coated or protected with rust-inhibitive paint.

E. Angle Hangers: Angles with legs not less than 7/8 inch (22 mm) wide; formed with 0.04-inch- (1-mm-) thick, galvanized-steel sheet complying with ASTM A 653/A 653M, G90 (Z275) coating designation; with bolted connections and 5/16-inch- (8-mm-) diameter bolts.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine substrates, areas, and conditions, including structural framing to which acoustical panel ceilings attach or abut, with Installer present, for compliance with requirements specified in this and other Sections that affect ceiling installation and anchorage and with requirements for installation tolerances and other conditions affecting performance of acoustical panel ceilings.

B. Examine acoustical panels before installation. Reject acoustical panels that are wet, moisture damaged, or mold damaged.

C. Proceed with installation only after unsatisfactory conditions have been corrected.

rhinson
Rectangle
rhinson
Snapshot
Page 76: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

ACOUSTICAL PANEL CEILINGS 095113 - 5

3.2 PREPARATION

A. Measure each ceiling area and establish layout of acoustical panels to balance border widths at opposite edges of each ceiling. Avoid using less-than-half-width panels at borders unless otherwise indicated, and comply with layout shown on reflected ceiling plans.

B. Layout openings for penetrations centered on the penetrating items.

3.3 INSTALLATION

A. Install acoustical panel ceilings according to ASTM C 636/C 636M and manufacturer's written instructions.

B. Suspend ceiling hangers from building's structural members and as follows:

1. Install hangers plumb and free from contact with insulation or other objects within ceiling plenum that are not part of supporting structure or of ceiling suspension system.

2. Splay hangers only where required to miss obstructions; offset resulting horizontal forces by bracing, counter-splaying, or other equally effective means.

3. Where width of ducts and other construction within ceiling plenum produces hanger spacings that interfere with location of hangers at spacings required to support standard suspension-system members, install supplemental suspension members and hangers in form of trapezes or equivalent devices.

4. Secure wire hangers to ceiling-suspension members and to supports above with a minimum of three tight turns. Connect hangers directly to structure or to inserts, eye screws, or other devices that are secure and appropriate for substrate and that will not deteriorate or otherwise fail due to age, corrosion, or elevated temperatures.

5. Secure flat, angle, channel, and rod hangers to structure, including intermediate framing members, by attaching to inserts, eye screws, or other devices that are secure and appropriate for both the structure to which hangers are attached and the type of hanger involved. Install hangers in a manner that will not cause them to deteriorate or fail due to age, corrosion, or elevated temperatures.

6. Do not support ceilings directly from permanent metal forms or floor deck. Fasten hangers to cast-in-place hanger inserts, postinstalled mechanical or adhesive anchors, or power-actuated fasteners that extend through forms into concrete.

7. When steel framing does not permit installation of hanger wires at spacing required, install carrying channels or other supplemental support for attachment of hanger wires.

8. Do not attach hangers to steel deck tabs.9. Do not attach hangers to steel roof deck. Attach hangers to structural members.10. Space hangers not more than 48 inches (1200 mm) o.c. along each member supported

directly from hangers unless otherwise indicated; provide hangers not more than 8 inches (200 mm) from ends of each member.

11. Size supplemental suspension members and hangers to support ceiling loads within performance limits established by referenced standards.

C. Secure bracing wires to ceiling suspension members and to supports with a minimum of four tight turns. Suspend bracing from building's structural members as required for hangers, without attaching to permanent metal forms, steel deck, or steel deck tabs. Fasten bracing wires into concrete with cast-in-place or post-installed anchors.

D. Install edge moldings and trim of type indicated at perimeter of acoustical ceiling area and where necessary to conceal edges of acoustical panels.

rhinson
Rectangle
rhinson
Snapshot
Page 77: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

ACOUSTICAL PANEL CEILINGS 095113 - 6

1. Apply acoustical sealant in a continuous ribbon concealed on back of vertical legs of moldings before they are installed.

2. Screw attach moldings to substrate at intervals not more than 16 inches (400 mm) o.c. and not more than 3 inches (75 mm) from ends. Miter corners accurately and connect securely.

3. Do not use exposed fasteners, including pop rivets, on moldings and trim.

E. Install suspension-system runners so they are square and securely interlocked with one another. Remove and replace dented, bent, or kinked members.

F. Install acoustical panels with undamaged edges and fit accurately into suspension-system runners and edge moldings. Scribe and cut panels at borders and penetrations to provide precise fit.

1. Arrange directionally patterned acoustical panels as follows:

a. As indicated on reflected ceiling plans.b. Install panels with pattern running in one direction parallel to [long] [short] axis of

space.c. Install panels in a basket-weave pattern.

2. For reveal-edged panels on suspension-system runners, install panels with bottom of reveal in firm contact with top surface of runner flanges.

3. Paint cut edges of panel remaining exposed after installation; match color of exposed panel surfaces using coating recommended in writing for this purpose by acoustical panel manufacturer.

3.4 ERECTION TOLERANCES

A. Suspended Ceilings: Install main and cross runners level to a tolerance of 1/8 inch in 12 feet (3 mm in 3.6 m), non-cumulative.

B. Moldings and Trim: Install moldings and trim to substrate and level with ceiling suspension system to a tolerance of 1/8 inch in 12 feet (3 mm in 3.6 m), non-cumulative.

3.5 CLEANING

A. Clean exposed surfaces of acoustical panel ceilings, including trim, edge moldings, and suspension-system members. Comply with manufacturer's written instructions for cleaning and touchup of minor finish damage.

B. Remove and replace ceiling components that cannot be successfully cleaned and repaired to permanently eliminate evidence of damage.

END OF SECTION 095113

rhinson
Rectangle
rhinson
Snapshot
Page 78: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

RESILIENT BASE AND ACCESSORIES 096513 - 1

SECTION 096513 - RESILIENT BASE AND ACCESSORIES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Thermoset-rubber base.

1.3 ACTION SUBMITTALS

A. Product Data: For each type of product.

B. Samples for Initial Selection: For each type of product indicated.

1.4 MAINTENANCE MATERIAL SUBMITTALS

A. Furnish extra materials that match products installed and that are packaged with protective covering for storage and identified with labels describing contents.

1. Furnish not less than 10 linear feet (3 linear m) for every 500 linear feet (150 linear m) or fraction thereof, of each type, color, pattern, and size of resilient product installed.

1.5 DELIVERY, STORAGE, AND HANDLING

A. Store resilient products and installation materials in dry spaces protected from the weather, with ambient temperatures maintained within range recommended by manufacturer, but not less than 50 deg F (10 deg C) or more than 90 deg F (32 deg C).

1.6 FIELD CONDITIONS

A. Maintain ambient temperatures within range recommended by manufacturer, but not less than 70 deg F (21 deg C) or more than 95 deg F (35 deg C), in spaces to receive resilient products during the following periods:

1. 48 hours before installation.2. During installation.3. 48 hours after installation.

rhinson
Rectangle
rhinson
Snapshot
Page 79: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

RESILIENT BASE AND ACCESSORIES 096513 - 2

B. After installation and until Substantial Completion, maintain ambient temperatures within range recommended by manufacturer, but not less than 55 deg F (13 deg C) or more than 95 deg F (35 deg C).

C. Install resilient products after other finishing operations, including painting, have been completed.

PART 2 - PRODUCTS

2.1 THERMOSET-RUBBER BASE

A. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that many be incorporated into the Work include, but are not limited to, the following:

1. Armstrong World Industries, Inc.2. Fexco.3. Johnsonite (Tarkett)4. Roppe Corporation, USA

B. Product Standard: ASTM F 1861, Type TS (rubber, vulcanized thermoset), Group I (solid, homogeneous).

1. Style and Location: Basis of Design Product: Johnsonite, 48 Grey WB ColorMatch

a. Style B, Cove: Provide in areas with resilient floor coverings.

C. Thickness: 0.125 inch (3.2 mm).

D. Height: 4 inches (102 mm).

E. Lengths: Coils in manufacturer's standard length.

F. Outside Corners: Job formed.

G. Inside Corners: Job formed.

H. Colors: 48 Grey WB ColorMatch.

2.2 RUBBER MOLDING ACCESSORY

A. <Double click here to find, evaluate, and insert list of manufacturers and products.>

B. Description:

1. Rubber cap for cove carpet 2. Cap for cove resilient floor covering 3. Carpet edge for glue-down applications 4. Nosing for carpet 5. Nosing for resilient floor covering 6. Reducer strip for resilient floor covering 7. Joiner for tile and carpet transition strips.

C. Profile and Dimensions: Confirm with Architect.

rhinson
Rectangle
rhinson
Snapshot
Page 80: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

RESILIENT BASE AND ACCESSORIES 096513 - 3

D. Locations: Provide rubber molding accessories in areas indicated.

E. Colors and Patterns: As selected by Architect from full range of industry colors.

2.3 INSTALLATION MATERIALS

A. Trowelable Leveling and Patching Compounds: Latex-modified, portland-cement-based or blended hydraulic-cement-based formulation provided or approved by resilient-product manufacturer for applications indicated.

B. Adhesives: Water-resistant type recommended by resilient-product manufacturer for resilient products and substrate conditions indicated.

1. Adhesives shall have a VOC content of 50g/L or less.

2. Adhesives shall comply with the testing and product requirements of the California Department of Public Health’s “standard Method for the Testing and Evaluation of Volatile Organic Chemical Emissions from Indoor Sources Using Environmental Chambers.”

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine substrates, with Installer present, for compliance with requirements for maximum moisture content and other conditions affecting performance of the Work.

1. Verify that finishes of substrates comply with tolerances and other requirements specified in other Sections and that substrates are free of cracks, ridges, depressions, scale, and foreign deposits that might interfere with adhesion of resilient products.

B. Proceed with installation only after unsatisfactory conditions have been corrected.

1. Installation of resilient products indicates acceptance of surfaces and conditions.

3.2 PREPARATION

A. Prepare substrates according to manufacturer's written instructions to ensure adhesion of resilient products.

B. Fill cracks, holes, and depressions in substrates with trowelable leveling and patching compound; remove bumps and ridges to produce a uniform and smooth substrate.

C. Do not install resilient products until materials are the same temperature as space where they are to be installed.

1. At least 48 hours in advance of installation, move resilient products and installation materials into spaces where they will be installed.

D. Immediately before installation, sweep and vacuum clean substrates to be covered by resilient products.

rhinson
Rectangle
rhinson
Snapshot
Page 81: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

RESILIENT BASE AND ACCESSORIES 096513 - 4

3.3 RESILIENT BASE INSTALLATION

A. Comply with manufacturer's written instructions for installing resilient base.

B. Apply resilient base to walls, columns, pilasters, casework and cabinets in toe spaces, and other permanent fixtures in rooms and areas where base is required.

C. Install resilient base in lengths as long as practical without gaps at seams and with tops of adjacent pieces aligned.

D. Tightly adhere resilient base to substrate throughout length of each piece, with base in continuous contact with horizontal and vertical substrates.

E. Do not stretch resilient base during installation.

F. On masonry surfaces or other similar irregular substrates, fill voids along top edge of resilient base with manufacturer's recommended adhesive filler material.

G. Job-Formed Corners:

1. Outside Corners: Use straight pieces of maximum lengths possible and form with returns not less than 12 inches in length.

a. Form without producing discoloration (whitening) at bends.

2. Inside Corners: Use straight pieces of maximum lengths possible and form with returns not less than 12 inches in length.

a. Miter corners to minimize open joints.

3.4 RESILIENT ACCESSORY INSTALLATION

A. Comply with manufacturer's written instructions for installing resilient accessories.

B. Resilient Molding Accessories: Butt to adjacent materials and tightly adhere to substrates throughout length of each piece. Install reducer strips at edges of floor covering that would otherwise be exposed.

3.5 CLEANING AND PROTECTION

A. Comply with manufacturer's written instructions for cleaning and protecting resilient products.

B. Perform the following operations immediately after completing resilient-product installation:

1. Remove adhesive and other blemishes from surfaces.2. Sweep and vacuum horizontal surfaces thoroughly.3. Damp-mop horizontal surfaces to remove marks and soil.

C. Protect resilient products from mars, marks, indentations, and other damage from construction operations and placement of equipment and fixtures during remainder of construction period.

D. Floor Polish: Remove soil, adhesive, and blemishes from resilient stair treads before applying liquid floor polish.

1. Apply three coat(s).

E. Cover resilient products subject to wear and foot traffic until Substantial Completion.

END OF SECTION 096513

rhinson
Rectangle
rhinson
Snapshot
Page 82: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

RESILIENT ATHLETIC FLOORING 096566 - 1

SECTION 096566 - RESILIENT ATHLETIC FLOORING (ANTI-FATIGUE SHEET FLOORING)

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Sheet vinyl flooring.

B. Related Requirements:

1. Section 096513 "Resilient Base and Accessories" for wall base and accessories installed with resilient athletic flooring.

1.3 ACTION SUBMITTALS

A. Product Data: For each type of product.

B. Shop Drawings: Show installation details and locations of the following:

1. Seam locations for sheet flooring.

C. Samples for Verification: For each type, color, and pattern of flooring specified, 6-inch- (150-mm-) square in size and of same thickness and material indicated for the Work.

1. Seam Samples: For each vinyl sheet flooring color and pattern required; with seam running lengthwise and in center of 6-by-9-inch (150-by-230-mm) Sample applied to a rigid backing and prepared by Installer for this Project.

1.4 INFORMATIONAL SUBMITTALS

A. Qualification Data: For sheet vinyl flooring Installer.

1.5 CLOSEOUT SUBMITTALS

A. Maintenance Data: For resilient athletic flooring to include in maintenance manuals.

1.6 MAINTENANCE MATERIAL SUBMITTALS

A. Furnish extra materials that match products installed and that are packaged with protective covering for storage and identified with labels describing contents.

rhinson
Rectangle
rhinson
Snapshot
Page 83: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

RESILIENT ATHLETIC FLOORING 096566 - 2

1. Sheet Flooring: Furnish full-width rolls of not less than 10 linear feet (3 linear m) for each 500 linear feet (150 linear m) or fraction thereof, of each type, color, and pattern of flooring installed.

1.7 QUALITY ASSURANCE

A. Sheet Vinyl Flooring Installer Qualifications: An experienced installer who has completed sheet vinyl flooring installations using seaming methods indicated for this Project and similar in material, design, and extent to that indicated for this Project; who is acceptable to manufacturer; and whose work has resulted in installations with a record of successful in-service performance.

1.8 DELIVERY, STORAGE, AND HANDLING

A. Deliver materials in original packages and containers, with seals unbroken, bearing manufacturer's labels indicating brand name and directions for storing.

B. Store materials to prevent deterioration.

1. Store rolls upright.

1.9 FIELD CONDITIONS

A. Adhesively Applied Products:

1. Maintain temperatures during installation within range recommended in writing by manufacturer, but not less than 70 deg F (21 deg C) or more than 95 deg F (35 deg C), in spaces to receive flooring 48 hours before installation, during installation, and 48 hours after installation unless longer period is recommended in writing by manufacturer.

2. After post-installation period, maintain temperatures within range recommended in writing by manufacturer, but not less than 55 deg F (13 deg C) or more than 95 deg F (35 deg C) Insert temperature.

3. Close spaces to traffic during flooring installation.4. Close spaces to traffic for 48 hours after flooring installation unless manufacturer

recommends longer period in writing.

B. Install flooring after other finishing operations, including painting, have been completed.

PART 2 - PRODUCTS

2.1 SHEET VINYL FLOORING

A. Heterogeneous Vinyl Resilient Athletic Sheet Flooring: 1. Heterogeneous Vinyl Resilient Athletic Sheet Flooring with the following physical

characteristics:a. Complies with requirements for ASTM F 1303 Standard Specification for Sheet

Vinyl Sheet Floor Covering With Backing, Type I Grade 1, Class C.b. Constructed with a .028" (0.7 mm) thick urethane coated clear wear layer.c. Roll/Sheet Width: 6' 6" (2 m).d. Wear layer/Overall thickness: .197" (5.0 mm).e. ASTM D 2047, Standard Test Method for Static Coefficient of Friction of Polish-

Coated Flooring or 0.6 or greater.

rhinson
Rectangle
rhinson
Snapshot
Page 84: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

RESILIENT ATHLETIC FLOORING 096566 - 3

f. ASTM F 970, Standard Test Method for Static Load Limit – 175 PSI.g. ASTM E 648, Standard Test method for Critical Radiant Flux of 0.45 watts/cm2 or

greater, Class I.h. Johnsonite offers a RESTART reclamation program for returning jobsite scrapi. Vinyl Athletic Sheet contains 22% pre-consumer recycled contentj. 100% Recyclablek. Phthalate-freel. SCS FloorScore® Certified and meets California Specifications Section 01250m. Johnsonite facilities are ISO 9001 and ISO 14001 Certifiedn. LEED contributions for Vinyl Athletic Flooring include MR2; MR4; EQ4.3

2. DESIGN PRODUCT: Sports and Multi-functional floor by Johnsonitea. Model: Training TRN-Rb. Color: 8009 Grey CGc. Weld Rod: 1287183, 28 Medium Grey CG*

2.2 ACCESSORIES

A. Trowelable Leveling and Patching Compound: Latex-modified, hydraulic-cement-based formulation approved by flooring manufacturer.

B. Adhesives: As recommended by Johnsonite to meet site conditions.1. Heterogeneous Vinyl Resilient Athletic Sheet Flooring.

a. Johnsonite #925 Resilient Flooring Adhesive.b. Johnsonite #975 Two-Part Urethane Adhesive.c. Johnsonite 150 SpraySmart Adhesive

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine substrates, with Installer present, for compliance with requirements for installation tolerances, moisture content, and other conditions affecting performance of the Work.

1. Verify that finishes of substrates comply with tolerances and other requirements specified in other Sections and that substrates are free of cracks, ridges, depressions, scale, and foreign deposits that might interfere with adhesion of resilient products.

B. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 PREPARATION

A. Prepare substrates according to manufacturer's written instructions to ensure adhesion of flooring.

B. Concrete Substrates: Prepare according to ASTM F 710.

1. Verify that substrates are dry and free of curing compounds, sealers, and hardeners.2. Alkalinity Testing: Perform pH testing according to ASTM F 710. Proceed with installation

only if pH readings are not less than 7.0 and not greater than 9.0.

rhinson
Rectangle
rhinson
Snapshot
Page 85: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

RESILIENT ATHLETIC FLOORING 096566 - 4

3. Moisture Testing: Perform tests so that each test area does not exceed [200 sq. ft. (18.6 sq. m)] [1000 sq. ft. (304.8 sq. m)] <Insert area>, and perform no fewer than three tests in each installation area and with test areas evenly spaced in installation areas.

a. Anhydrous Calcium Chloride Test: ASTM F 1869. Proceed with installation only after substrates have maximum moisture-vapor-emission rate of 5 lb of water/1000 sq. ft. in 24 hours.

b. Relative Humidity Test: Using in-situ probes, ASTM F 2170. Proceed with installation only after substrates have a maximum 75 percent relative humidity level measurement.

C. Remove substrate coatings and other substances that are incompatible with adhesives and that contain soap, wax, oil, or silicone, using mechanical methods recommended in writing by manufacturer. Do not use solvents.

D. Use trowelable leveling and patching compound to fill cracks, holes, and depressions in substrates.

E. Move flooring and installation materials into spaces where they will be installed at least 48 hours in advance of installation unless manufacturer recommends a longer period in writing.

1. Do not install flooring until it is the same temperature as space where it is to be installed.

F. Sweep and vacuum clean substrates to be covered by flooring immediately before installation. After cleaning, examine substrates for moisture, alkaline salts, carbonation, and dust. Proceed with installation only after unsatisfactory conditions have been corrected.

3.3 FLOORING INSTALLATION, GENERAL

A. Comply with manufacturer's written installation instructions.

B. Scribe, cut, and fit flooring to butt neatly and tightly to vertical surfaces, equipment anchors, floor outlets, and other interruptions of floor surface.

C. Extend flooring into toe spaces, door reveals, closets, and similar openings unless otherwise indicated.

D. Maintain reference markers, holes, and openings that are in place or marked for future cutting by repeating subfloor markings on flooring. Use nonpermanent, nonstaining marking device.

3.4 SHEET FLOORING INSTALLATION

1. Install with Johnsonite adhesive specified for the site conditions and follow adhesive label for proper use.

2. Install rolls in sequential order following roll numbers on the labels.3. Reverse sheets unless instructed otherwise in Johnsonite Installation Instructions.4. Roll the flooring in both directions using a 100 pound three-section roller.5. Resilient Athletic Vinyl Sheet Flooring must be heat welded.6. Johnsonite Resilient Vinyl Sheet Flooring may be flash coved.

a. Use Johnsonite CFS-00-A Cove Filler Strip.b. Net fit flooring material into the appropriate Johnsonite cove cap.

B. 5

rhinson
Rectangle
rhinson
Snapshot
Page 86: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

RESILIENT ATHLETIC FLOORING 096566 - 5

3.5 CLEANING AND PROTECTION

A. Perform the following operations immediately after completing flooring installation:

1. Remove adhesive and other blemishes from flooring surfaces.2. Sweep and vacuum flooring thoroughly.3. Damp-mop flooring to remove marks and soil after time period recommended in writing

by manufacturer.

B. Protect flooring from mars, marks, indentations, and other damage from construction operations and placement of equipment and fixtures during remainder of construction period. Use protection methods recommended in writing by manufacturer.

1. Do not move heavy and sharp objects directly over flooring. Protect flooring with plywood or hardboard panels to prevent damage from storing or moving objects over flooring.

2. No traffic for 24 hours after installation.3. No heavy traffic, rolling loads, or furniture placement for 72 hours after installation.

C. Wait 72 hours after installation before performing initial cleaning

END OF SECTION 096566

rhinson
Rectangle
rhinson
Snapshot
Page 87: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

INTERIOR PAINTING 099123 - 1

SECTION 099123 - INTERIOR PAINTING

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes surface preparation and the application of paint systems on the following interior substrates:

1. Concrete masonry units (CMUs).2. Steel and iron.3. Galvanized metal.4. Gypsum board.

1.3 DEFINITIONS

A. MPI Gloss Level 1: Not more than five units at 60 degrees and 10 units at 85 degrees, according to ASTM D 523.

B. MPI Gloss Level 2: Not more than 10 units at 60 degrees and 10 to 35 units at 85 degrees, according to ASTM D 523.

C. MPI Gloss Level 3: 10 to 25 units at 60 degrees and 10 to 35 units at 85 degrees, according to ASTM D 523.

D. MPI Gloss Level 4: 20 to 35 units at 60 degrees and not less than 35 units at 85 degrees, according to ASTM D 523.

E. MPI Gloss Level 5: 35 to 70 units at 60 degrees, according to ASTM D 523.

F. MPI Gloss Level 6: 70 to 85 units at 60 degrees, according to ASTM D 523.

G. MPI Gloss Level 7: More than 85 units at 60 degrees, according to ASTM D 523.

1.4 ACTION SUBMITTALS

A. Product Data: For each type of product. Include preparation requirements and application instructions.

1. Include Printout of current "MPI Approved Products List" for each product category specified, with the proposed product highlighted.

2. Indicate VOC content.

rhinson
Rectangle
rhinson
Snapshot
Page 88: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

INTERIOR PAINTING 099123 - 2

B. Product List: Cross-reference to paint system and locations of application areas. Use same designations indicated on Drawings and in schedules. Include color designations.

1.5 MAINTENANCE MATERIAL SUBMITTALS

A. Furnish extra materials that match products installed and that are packaged with protective covering for storage and identified with labels describing contents.

1. Paint: 5 percent, but not less than 1 gal. (3.8 L) of each material and color applied.

1.6 DELIVERY, STORAGE, AND HANDLING

A. Store materials not in use in tightly covered containers in well-ventilated areas with ambient temperatures continuously maintained at not less than 45 deg F (7 deg C).

1. Maintain containers in clean condition, free of foreign materials and residue.2. Remove rags and waste from storage areas daily.

1.7 FIELD CONDITIONS

A. Apply paints only when temperature of surfaces to be painted and ambient air temperatures are between 50 and 95 deg F (10 and 35 deg C).

B. Do not apply paints when relative humidity exceeds 85 percent; at temperatures less than 5 deg F (3 deg C) above the dew point; or to damp or wet surfaces.

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:

1. Behr Process Corporation.2. Benjamin Moore & Co.3. Coronado Paint.4. ICI Paints.5. Kelly-Moore Paints.6. PPG Architectural Finishes, Inc.7. Pratt & Lambert.

8. Sherwin-Williams Company (The). BASIS OF DESIGN PRODUCT.

2.2 PAINT, GENERAL

A. MPI Standards: Products shall comply with MPI standards indicated and shall be listed in its "MPI Approved Products Lists."

B. Material Compatibility:

rhinson
Rectangle
rhinson
Snapshot
Page 89: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

INTERIOR PAINTING 099123 - 3

1. Materials for use within each paint system shall be compatible with one another and substrates indicated, under conditions of service and application as demonstrated by manufacturer, based on testing and field experience.

2. For each coat in a paint system, products shall be recommended in writing by topcoat manufacturers for use in paint system and on substrate indicated.

C. VOC Content: Products shall comply with VOC limits of authorities having jurisdiction.

1. Flat Paints and Coatings: 50 g/L.2. Nonflat Paints and Coatings: 150 g/L.3. Dry-Fog Coatings: 400 g/L.4. Primers, Sealers, and Undercoaters: 200 g/L.5. Anticorrosive and Antirust Paints Applied to Ferrous Metals: 250 g/L.6. Zinc-Rich Industrial Maintenance Primers: 340 g/L.7. Pretreatment Wash Primers: 420 g/L.8. Floor Coatings: 100 g/L.9. Shellacs, Clear: 730 g/L.10. Shellacs, Pigmented: 550 g/L.

D. Low-Emitting Materials: Interior paints and coatings shall comply with the testing and product requirements of the California Department of Health Services' "Standard Practice for the Testing of Volatile Organic Emissions from Various Sources Using Small-Scale Environmental Chambers."

E. Colors: PT-1 = SW 6140 Moderate White.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine substrates and conditions, with Applicator present, for compliance with requirements for maximum moisture content and other conditions affecting performance of the Work.

B. Maximum Moisture Content of Substrates: When measured with an electronic moisture meter as follows:

1. Concrete: 12 percent.2. Masonry (Clay and CMUs): 12 percent.3. Gypsum Board: 12 percent.

C. Gypsum Board Substrates: Verify that finishing compound is sanded smooth.

D. Verify suitability of substrates, including surface conditions and compatibility, with existing finishes and primers.

E. Proceed with coating application only after unsatisfactory conditions have been corrected.

1. Application of coating indicates acceptance of surfaces and conditions.

rhinson
Rectangle
rhinson
Snapshot
Page 90: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

INTERIOR PAINTING 099123 - 4

3.2 PREPARATION

A. Comply with manufacturer's written instructions and recommendations in "MPI Architectural Painting Specification Manual" applicable to substrates and paint systems indicated.

B. Remove hardware, covers, plates, and similar items already in place that are removable and are not to be painted. If removal is impractical or impossible because of size or weight of item, provide surface-applied protection before surface preparation and painting.

1. After completing painting operations, use workers skilled in the trades involved to reinstall items that were removed. Remove surface-applied protection if any.

C. Clean substrates of substances that could impair bond of paints, including dust, dirt, oil, grease, and incompatible paints and encapsulants.

1. Remove incompatible primers and reprime substrate with compatible primers or apply tie coat as required to produce paint systems indicated.

D. Masonry Substrates: Remove efflorescence and chalk. Do not paint surfaces if moisture content or alkalinity of surfaces or mortar joints exceeds that permitted in manufacturer's written instructions.

E. Steel Substrates: Remove rust, loose mill scale, and shop primer, if any. Clean using methods recommended in writing by paint manufacturer[.] [ but not less than the following:]

1. SSPC-SP 2.2. SSPC-SP 3.3. SSPC-SP 7/NACE No. 4.4. SSPC-SP 11.

F. Galvanized-Metal Substrates: Remove grease and oil residue from galvanized sheet metal by mechanical methods to produce clean, lightly etched surfaces that promote adhesion of subsequently applied paints.

3.3 APPLICATION

A. Apply paints according to manufacturer's written instructions and to recommendations in "MPI Manual."

1. Use applicators and techniques suited for paint and substrate indicated.2. Paint surfaces behind movable equipment and furniture same as similar exposed

surfaces. Before final installation, paint surfaces behind permanently fixed equipment or furniture with prime coat only.

3. Paint front and backsides of access panels, removable or hinged covers, and similar hinged items to match exposed surfaces.

4. Do not paint over labels of independent testing agencies or equipment name, identification, performance rating, or nomenclature plates.

5. Primers specified in painting schedules may be omitted on items that are factory primed or factory finished if acceptable to topcoat manufacturers.

B. Tint each undercoat a lighter shade to facilitate identification of each coat if multiple coats of same material are to be applied. Tint undercoats to match color of topcoat, but provide sufficient difference in shade of undercoats to distinguish each separate coat.

rhinson
Rectangle
rhinson
Snapshot
Page 91: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

INTERIOR PAINTING 099123 - 5

C. If undercoats or other conditions show through topcoat, apply additional coats until cured film has a uniform paint finish, color, and appearance.

D. Apply paints to produce surface films without cloudiness, spotting, holidays, laps, brush marks, roller tracking, runs, sags, ropiness, or other surface imperfections. Cut in sharp lines and color breaks.

E. Painting Fire Suppression, Plumbing, HVAC, Electrical, Communication, and Electronic Safety and Security Work:

1. Paint the following work where exposed in occupied spaces:

a. Equipment, including panelboards.b. Uninsulated metal piping.c. Uninsulated plastic piping.d. Pipe hangers and supports.e. Metal conduit.f. Plastic conduit.g. Duct, equipment, and pipe insulation having cotton or canvas insulation covering

or other paintable jacket material.h. Other items as directed by Architect.

2. Paint portions of internal surfaces of metal ducts, without liner, behind air inlets and outlets that are visible from occupied spaces.

3.4 FIELD QUALITY CONTROL

A. Dry Film Thickness Testing: Owner may engage the services of a qualified testing and inspecting agency to inspect and test paint for dry film thickness.

1. Contractor shall touch up and restore painted surfaces damaged by testing.2. If test results show that dry film thickness of applied paint does not comply with paint

manufacturer's written recommendations, Contractor shall pay for testing and apply additional coats as needed to provide dry film thickness that complies with paint manufacturer's written recommendations.

3.5 CLEANING AND PROTECTION

A. At end of each workday, remove rubbish, empty cans, rags, and other discarded materials from Project site.

B. After completing paint application, clean spattered surfaces. Remove spattered paints by washing, scraping, or other methods. Do not scratch or damage adjacent finished surfaces.

C. Protect work of other trades against damage from paint application. Correct damage to work of other trades by cleaning, repairing, replacing, and refinishing, as approved by Architect, and leave in an undamaged condition.

D. At completion of construction activities of other trades, touch up and restore damaged or defaced painted surfaces.

rhinson
Rectangle
rhinson
Snapshot
Page 92: SECTION 024119 - SELECTIVE DEMOLITION 02-09 Specifications.pdfConduct selective demolition so Owner's operations will not be disrupted. B. Conditions existing at time of inspection

KCTCS System Office Renovation November 12, 2018Copy Center Fit-up – Versailles, Kentucky EOP# 201732

INTERIOR PAINTING 099123 - 6

3.6 INTERIOR PAINTING SCHEDULE

A. CMU Substrates:

1. Institutional Low-Odor/VOC Latex System:

a. Block Filler: Block filler, latex, interior/exterior, MPI #4.b. Intermediate Coat: Latex, interior, institutional low odor/VOC, matching topcoat.c. Topcoat: Latex, interior, institutional low odor/VOC, (Gloss Level 3), MPI #145.

B. Steel Substrates:

1. Institutional Low-Odor/VOC Latex System:

a. Prime Coat: Primer, rust-inhibitive, water based MPI #107.b. Intermediate Coat: Latex, interior, institutional low odor/VOC, matching topcoat.c. Topcoat: Latex, interior, institutional low odor/VOC, semi-gloss (Gloss

Level 5), MPI #147.

C. Galvanized-Metal Substrates:

1. Water-Based Dry-Fall System:

a. Prime Coat: Dry fall, water based, for galvanized steel, flat (Gloss Level 1), MPI #133.

b. Topcoat: Dry fall, water based, for galvanized steel, flat (Gloss Level 1), MPI #133.

2. Institutional Low-Odor/VOC Latex System:

a. Prime Coat: Primer, galvanized, water based, MPI #134.b. Intermediate Coat: Latex, interior, institutional low odor/VOC, matching topcoat.c. Topcoat: Latex, interior, institutional low odor/VOC, (Gloss Level 3), MPI #145.

D. Gypsum Board Substrates:

1. Institutional Low-Odor/VOC Latex System:

a. Prime Coat: Primer sealer, interior, institutional low odor/VOC, MPI #149.b. Intermediate Coat: Latex, interior, institutional low odor/VOC, matching topcoat.c. Topcoat: Latex, interior, institutional low odor/VOC, (Gloss Level 3), MPI #145.

END OF SECTION 099123

rhinson
Rectangle
rhinson
Snapshot