Sediment Transport Analysis and Creek Restoration- Field Experiences 4 th Hydromodification Seminar & Workshop – Sediment Management and Modeling November, 21, 2013 1

Upload: others

Post on 15-Aug-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Sediment transport 2013...Guadalupe River at Alamaden Gage 23B (45, 240) Guadalupe River d/s of Hwy 101 (98, 320) Creeku/sof Drive:(2.5,45) Adobe Creek u/s of West Edith Road (7, 54)

Sediment Transport Analysis and Creek Restoration- Field Experiences

4th Hydromodification Seminar & Workshop –Sediment Management and ModelingNovember, 21, 2013

1

Page 2: Sediment transport 2013...Guadalupe River at Alamaden Gage 23B (45, 240) Guadalupe River d/s of Hwy 101 (98, 320) Creeku/sof Drive:(2.5,45) Adobe Creek u/s of West Edith Road (7, 54)

2

Topics

Santa Clara County HMP program Stable channel design SCVWD regional bankfull curves Channel stability analysis

Page 3: Sediment transport 2013...Guadalupe River at Alamaden Gage 23B (45, 240) Guadalupe River d/s of Hwy 101 (98, 320) Creeku/sof Drive:(2.5,45) Adobe Creek u/s of West Edith Road (7, 54)

Urbanized Watersheds

3Santa Clara Valley Water District

Page 4: Sediment transport 2013...Guadalupe River at Alamaden Gage 23B (45, 240) Guadalupe River d/s of Hwy 101 (98, 320) Creeku/sof Drive:(2.5,45) Adobe Creek u/s of West Edith Road (7, 54)

Effects of hydrology by Urbanization Less infiltration / evapotranspiration More surface runoff (increased volume) Runoff leaves the site faster (increased peak flows) Runoff occurs more often (increased frequency) More runoff conveyed directly to creek

Page 5: Sediment transport 2013...Guadalupe River at Alamaden Gage 23B (45, 240) Guadalupe River d/s of Hwy 101 (98, 320) Creeku/sof Drive:(2.5,45) Adobe Creek u/s of West Edith Road (7, 54)

Thompson Creek Undermining outfall structure

Page 6: Sediment transport 2013...Guadalupe River at Alamaden Gage 23B (45, 240) Guadalupe River d/s of Hwy 101 (98, 320) Creeku/sof Drive:(2.5,45) Adobe Creek u/s of West Edith Road (7, 54)

Incising channel bed on Yerba Buena Creek

Page 7: Sediment transport 2013...Guadalupe River at Alamaden Gage 23B (45, 240) Guadalupe River d/s of Hwy 101 (98, 320) Creeku/sof Drive:(2.5,45) Adobe Creek u/s of West Edith Road (7, 54)

Unurbanized Stable Stream

Page 8: Sediment transport 2013...Guadalupe River at Alamaden Gage 23B (45, 240) Guadalupe River d/s of Hwy 101 (98, 320) Creeku/sof Drive:(2.5,45) Adobe Creek u/s of West Edith Road (7, 54)

GUADALUPE RIVER

tu101

§̈¦680

tu17

§̈¦880

§̈¦280

tu82

tu273

tu35

tu84

tu101

tu87tu65

COYOTE CREEKtu85

CoyoteGuadalupe

San TomasStevens

Baylands

San Francisquito

Calabazas

Adobe

Lower Penitencia

Permanente

Matadero/Barron

Dumbarton South

Sunnyvale West

Sunnyvale East

³

San Felipe Road

White Road

Aborn Road

Quimby Road

THOMPSON CREEK

FLINT CREEK

NORWOOD CREEK

LOWER SILVER CREEK

SOUTH BABB CREEK

FOWLER CREEK

MIGUELITA CREEK

EVERGREEN CREEK

QUIMBY CREEK

RUBY CREEK

YERBA BUENA CREEK

CRIBARI CREEK

³

ROSS CREEK

LONE HILLCREEK

EAST ROSSCREEK

Subwatersheds Assessed under HMP

Ross Creek

Thompson Creek

San Tomas

Slide courtesy of Geosyntec Consultants

Page 9: Sediment transport 2013...Guadalupe River at Alamaden Gage 23B (45, 240) Guadalupe River d/s of Hwy 101 (98, 320) Creeku/sof Drive:(2.5,45) Adobe Creek u/s of West Edith Road (7, 54)

Velocity, Shear Stress and Excess Total Work (W) based on Flow-Duration Histogram

Stream Flow Exerts Shear Stress on Bed and Bank

c Critical Shear Stress of bed or weakest layer of bank at cross-sectionLower of the two values applies; if weak layer not at bottom c = cbank + gShbank

Range of Geomorphically Significant flows

Characteristics of Bed and Bank

Materials

c b

tvWen

icb

1

c

Mid-stream velocity observed over a durationv t Which is a time period in histogramn = number of separate flow bins in the flow duration histogram, e =1 for computations shown

ghSb

gDwscc )(

D is D50 (median particle size) of bed material, c* is the dimensionless shear stress = 0.047(Julien 2002), s and w are sand/gravel and water

Page 10: Sediment transport 2013...Guadalupe River at Alamaden Gage 23B (45, 240) Guadalupe River d/s of Hwy 101 (98, 320) Creeku/sof Drive:(2.5,45) Adobe Creek u/s of West Edith Road (7, 54)

Increase Critical Shear Stress to Reduce Erosive Work Done (Wi)

Post-Urban Buildout

Pre-Urban

Work Done is computed for each flow bin in flow duration histogram;

50-year continuous record of runoff, cfs computed from the rainfall record

Work done by each flow bin

c

Flow, cfs

The sum of work done, W, for all n flow bins is computed as cumulative work

icbi tvW 5.1)( EP=Wexisting/Wpre-urban

Page 11: Sediment transport 2013...Guadalupe River at Alamaden Gage 23B (45, 240) Guadalupe River d/s of Hwy 101 (98, 320) Creeku/sof Drive:(2.5,45) Adobe Creek u/s of West Edith Road (7, 54)

11

Stable Channel Design Procedure

1. Determine bankfull cross-sectional geometry2. Develop equilibrium slope via. sediment transport

modeling (SAM or HEC-6)3. Identify hardpoints in project reach4. Layout cross-section and profile and, if necessary,

locations of grade control structures 5. Design surface protection

Page 12: Sediment transport 2013...Guadalupe River at Alamaden Gage 23B (45, 240) Guadalupe River d/s of Hwy 101 (98, 320) Creeku/sof Drive:(2.5,45) Adobe Creek u/s of West Edith Road (7, 54)

Remnant of Pre-urbanization channel geometry

12Santa Clara Valley Water District

Page 13: Sediment transport 2013...Guadalupe River at Alamaden Gage 23B (45, 240) Guadalupe River d/s of Hwy 101 (98, 320) Creeku/sof Drive:(2.5,45) Adobe Creek u/s of West Edith Road (7, 54)

13

THBF TOE

BF Width

BF Depth

BF = bankfull

BF bench or BF floodplain

width

TH = Thalwag

Bankfull Channel Measurement

2H:1V bank slope2H:1V bank slopefor bankfull channel

Note how bankfullchannel is formedwithin stable floodconveyance channel

Top of bank

Page 14: Sediment transport 2013...Guadalupe River at Alamaden Gage 23B (45, 240) Guadalupe River d/s of Hwy 101 (98, 320) Creeku/sof Drive:(2.5,45) Adobe Creek u/s of West Edith Road (7, 54)

14

Guadalupe River at Almaden Expressway

Page 15: Sediment transport 2013...Guadalupe River at Alamaden Gage 23B (45, 240) Guadalupe River d/s of Hwy 101 (98, 320) Creeku/sof Drive:(2.5,45) Adobe Creek u/s of West Edith Road (7, 54)

Bankfull and Floodplain

Santa Clara Valley Water District 15

Entrenchment Ratio = ratio of channel width at 2xbankfull depth to bankfull depthBottom shear stress = RS

Page 16: Sediment transport 2013...Guadalupe River at Alamaden Gage 23B (45, 240) Guadalupe River d/s of Hwy 101 (98, 320) Creeku/sof Drive:(2.5,45) Adobe Creek u/s of West Edith Road (7, 54)

Bankfull Effect on Bottom Shear

Santa Clara Valley Water District 16

012345678

0 2 4 6 8

T/Tb

f

Q/Qbf

Bottom Shear Stress vs. Flow For Various Floodplain Widths

1.62.5

3.55.3

7.3

9.3

Entrenchment Ratio

Page 17: Sediment transport 2013...Guadalupe River at Alamaden Gage 23B (45, 240) Guadalupe River d/s of Hwy 101 (98, 320) Creeku/sof Drive:(2.5,45) Adobe Creek u/s of West Edith Road (7, 54)

Effective Flow Calculation

17Santa Clara Valley Water District

Page 18: Sediment transport 2013...Guadalupe River at Alamaden Gage 23B (45, 240) Guadalupe River d/s of Hwy 101 (98, 320) Creeku/sof Drive:(2.5,45) Adobe Creek u/s of West Edith Road (7, 54)

Effective Flow Calculation ResultsGauge Station

Available Gauge Data

Drainage Area (sq mi)

Effective Flow (cfs)

Sediment Transported

Exceedance Frequency (Return Period)

Los Gatos Creek at Lark Ave

1992‐2007 6 (44)* 50 45% 94% (1.1)

Ross Creek at Cherry Ave

1956‐2007 10 100‐200 54% 95‐99% (1‐1.1)

San Francisquito Creek at Stanford

1987‐2007 37 200‐500 66% 86‐95% (1.1‐1.2)

Guadalupe River at Almaden

1970‐2004 45 (70)*  700 55% 78‐86% (1.2‐1.3)

Guadalupe River at Saint John

1987‐2003 88 (150)*  900 60% 88% (1.1)

Calabazas Creek at Lawrence

1972‐2004 12 250‐350 54% 93‐97% (1‐1.1)

Matadero Creek at Palo Alto

1987‐2007 27 270 50% 80% (1.3)

18Santa Clara Valley Water District

(    )* denotes drainage area including the areas upstream of the reservoir

Page 19: Sediment transport 2013...Guadalupe River at Alamaden Gage 23B (45, 240) Guadalupe River d/s of Hwy 101 (98, 320) Creeku/sof Drive:(2.5,45) Adobe Creek u/s of West Edith Road (7, 54)

Drainage Area vs. Bankfull X-sec

Calabazas Creek u/s of Regnart Creek (7.6, 57)

Guadalupe River  at Alamaden Gage 23B (45, 240)

Guadalupe River  d/s of Hwy 101 (98, 320)

Calabazas Creek u/s of  Comer Drive: (2.5 ,45)

Adobe Creek  u/s of West Edith Road (7, 54)

Guadalupe River at Reach 6 (67, 226)

Guadalupe River at St. John (88, 200)

1

10

100

1000

0.1 1 10 100 1000 10000

Ban

kful

lCro

ss-s

ectio

nal A

rea

(squ

are

feet

)

Drainage Area (square miles)

A B

A. San Francisco Bay Region, Dunne and Leopold 1978B. Waterways Restoration Institute, 1999

SCVWD Data

19Santa Clara Valley Water District

Page 20: Sediment transport 2013...Guadalupe River at Alamaden Gage 23B (45, 240) Guadalupe River d/s of Hwy 101 (98, 320) Creeku/sof Drive:(2.5,45) Adobe Creek u/s of West Edith Road (7, 54)

Santa Clara Valley Water District 20

Calabazas Creek u/s of Regnart Creek (7.6, 190)

Guadalupe River  at Alamaden Gage 23B (45,  750)

Guadalupe River  d/s of Hwy 101 (98, 1000)

Calabazas Creek at  Comer Drive: (2.5 ,180)

Adobe Creek  at West Edith Road (7, 280)

Guadalupe River at Reach 6 (67, 800)

Guadalupe River at St. John (88, 900)

Los Gatos Creek atLark Ave (6, 50)

Ross Creek at Cherry Ave (10, 150)

San Francisquito Creek atStanford (37, 350)

Matadero Creek at Palo Alto (27, 270)

y = 49.285x0.6247R² = 0.7072

1

10

100

1000

10000

1 10 100 1000

Ban

kful

lDis

char

ge (c

fs)

Drainage Area (square miles)

Bankfull Discharge as a function of Drainage Area

SCVWD Data

Page 21: Sediment transport 2013...Guadalupe River at Alamaden Gage 23B (45, 240) Guadalupe River d/s of Hwy 101 (98, 320) Creeku/sof Drive:(2.5,45) Adobe Creek u/s of West Edith Road (7, 54)

Comer Debris Basin Dam Removal

Debris basin behind dam has silted in Reduced Passage under Comer Dr. Br. Increased Flooding Potential

Remove Comer Dam

Design stable channel

Page 22: Sediment transport 2013...Guadalupe River at Alamaden Gage 23B (45, 240) Guadalupe River d/s of Hwy 101 (98, 320) Creeku/sof Drive:(2.5,45) Adobe Creek u/s of West Edith Road (7, 54)

Comer Debris Basin

22

Page 23: Sediment transport 2013...Guadalupe River at Alamaden Gage 23B (45, 240) Guadalupe River d/s of Hwy 101 (98, 320) Creeku/sof Drive:(2.5,45) Adobe Creek u/s of West Edith Road (7, 54)

Reference Reach

23

Page 24: Sediment transport 2013...Guadalupe River at Alamaden Gage 23B (45, 240) Guadalupe River d/s of Hwy 101 (98, 320) Creeku/sof Drive:(2.5,45) Adobe Creek u/s of West Edith Road (7, 54)

Step 1. Design Stable Cross Section

•Locate stable reach near project area

•Measure bankfull channel dimensions and floodplain slope in field

•Average measurements

•Develop prototypical bankfull channel

•Fit into existing channel by varying floodplain width

Page 25: Sediment transport 2013...Guadalupe River at Alamaden Gage 23B (45, 240) Guadalupe River d/s of Hwy 101 (98, 320) Creeku/sof Drive:(2.5,45) Adobe Creek u/s of West Edith Road (7, 54)

Step 2. Estimate Stable Channel Slope

Page 26: Sediment transport 2013...Guadalupe River at Alamaden Gage 23B (45, 240) Guadalupe River d/s of Hwy 101 (98, 320) Creeku/sof Drive:(2.5,45) Adobe Creek u/s of West Edith Road (7, 54)

Use SAM to compute Qs: Iteration #1

Bed Slope (ft/ft) Qs at bankfull flow (tons/day)

U/S Reach 1.26% 1969

Design Reach 1.25% 3110

D/S Reach 0.9% 2308

Page 27: Sediment transport 2013...Guadalupe River at Alamaden Gage 23B (45, 240) Guadalupe River d/s of Hwy 101 (98, 320) Creeku/sof Drive:(2.5,45) Adobe Creek u/s of West Edith Road (7, 54)

Iteration #2Qs in design reach too large Reduce slope

Bed Slope (ft/ft)

Qs at bankfull flow (tons/day)

U/S Reach 1.26% 1969

Design Reach 1% 2411

D/S Reach 0.9% 2308

Page 28: Sediment transport 2013...Guadalupe River at Alamaden Gage 23B (45, 240) Guadalupe River d/s of Hwy 101 (98, 320) Creeku/sof Drive:(2.5,45) Adobe Creek u/s of West Edith Road (7, 54)

Iteration #3: Qs in design reach between Qs u/s and d/s: DONE !!!

Bed Slope (ft/ft)

Qs at bankfull flow (tons/day)

U/S Reach 1.26% 1969

Design Reach 0.9% 2103

D/S Reach 0.9% 2308

Page 29: Sediment transport 2013...Guadalupe River at Alamaden Gage 23B (45, 240) Guadalupe River d/s of Hwy 101 (98, 320) Creeku/sof Drive:(2.5,45) Adobe Creek u/s of West Edith Road (7, 54)

29

4. Layout cross-section & profile

Determine need for grade control

Design grade control structures (chapter 8, hydraulic design manual)

Layout plan and profile (workshop in Mar 07)

Page 30: Sediment transport 2013...Guadalupe River at Alamaden Gage 23B (45, 240) Guadalupe River d/s of Hwy 101 (98, 320) Creeku/sof Drive:(2.5,45) Adobe Creek u/s of West Edith Road (7, 54)

30

5. Design surface protection

Although equilibrium slope provides sediment balance, there is continuous sediment deposition and erosion taking place

Surface armor concept – armor will occur if Dcritical ≤ D90 and the D90 materials will cover bed surface

Surface cover should be compatible with flow regime To be described in sediment transport workshop

Page 31: Sediment transport 2013...Guadalupe River at Alamaden Gage 23B (45, 240) Guadalupe River d/s of Hwy 101 (98, 320) Creeku/sof Drive:(2.5,45) Adobe Creek u/s of West Edith Road (7, 54)

31

Page 32: Sediment transport 2013...Guadalupe River at Alamaden Gage 23B (45, 240) Guadalupe River d/s of Hwy 101 (98, 320) Creeku/sof Drive:(2.5,45) Adobe Creek u/s of West Edith Road (7, 54)

Calabazas Creek Degradation

Page 33: Sediment transport 2013...Guadalupe River at Alamaden Gage 23B (45, 240) Guadalupe River d/s of Hwy 101 (98, 320) Creeku/sof Drive:(2.5,45) Adobe Creek u/s of West Edith Road (7, 54)

Calabazas Creek Degradation

Page 34: Sediment transport 2013...Guadalupe River at Alamaden Gage 23B (45, 240) Guadalupe River d/s of Hwy 101 (98, 320) Creeku/sof Drive:(2.5,45) Adobe Creek u/s of West Edith Road (7, 54)

HEC-6 Sediment Transport Analysis

Page 35: Sediment transport 2013...Guadalupe River at Alamaden Gage 23B (45, 240) Guadalupe River d/s of Hwy 101 (98, 320) Creeku/sof Drive:(2.5,45) Adobe Creek u/s of West Edith Road (7, 54)

HEC-6 Results for Post Weir Construction

Thalweg Comparison

Homestead

120

122

124

126

128

130

132

134

136

138

140

31000 31500 32000 32500 33000 33500 34000

Cross Section Number

Elev

atio

n (f

t, N

GVD

29)

As-Built (10-01-1998)

HEC6 (10-1-2004)

Concrete Channels

Street Crossing

Deposition - 2009

Page 36: Sediment transport 2013...Guadalupe River at Alamaden Gage 23B (45, 240) Guadalupe River d/s of Hwy 101 (98, 320) Creeku/sof Drive:(2.5,45) Adobe Creek u/s of West Edith Road (7, 54)

Weir Construction

Page 37: Sediment transport 2013...Guadalupe River at Alamaden Gage 23B (45, 240) Guadalupe River d/s of Hwy 101 (98, 320) Creeku/sof Drive:(2.5,45) Adobe Creek u/s of West Edith Road (7, 54)

37

Page 38: Sediment transport 2013...Guadalupe River at Alamaden Gage 23B (45, 240) Guadalupe River d/s of Hwy 101 (98, 320) Creeku/sof Drive:(2.5,45) Adobe Creek u/s of West Edith Road (7, 54)

38

Conclusion

Understand meaning and origin of geomorphologic parameters

Focus on applicable parameters and incorporate into design

SCVWD channel modification designs include field data collection and sediment transport modeling

Emphasize on long term stability

Page 39: Sediment transport 2013...Guadalupe River at Alamaden Gage 23B (45, 240) Guadalupe River d/s of Hwy 101 (98, 320) Creeku/sof Drive:(2.5,45) Adobe Creek u/s of West Edith Road (7, 54)

Thanks for Listening!