See Opening Checklist on the Website for a Detail View
The Basics of Opening a Hotel
![Page 2: See Opening Checklist on the Website for a Detail View The Basics of Opening a Hotel](https://reader036.vdocuments.net/reader036/viewer/2022082710/56649e8f5503460f94b9325d/html5/thumbnails/2.jpg)
The arThe General Manager(GM) or Operations Project Manager (OPM) should :t and science of opening a hotelReview the blueprints and specifications for the
entire buildingAssist in creation of model roomDevelop pre-opening staff planDevelop and manage pre-opening budgetDevelop operational supplies and equipment
budgetOversee the purchase, delivery and installation of
supplies and equipment
![Page 3: See Opening Checklist on the Website for a Detail View The Basics of Opening a Hotel](https://reader036.vdocuments.net/reader036/viewer/2022082710/56649e8f5503460f94b9325d/html5/thumbnails/3.jpg)
Blueprints:To ensure good flow for guests, staff and goodsConsider the location of:
car parkbellhop bag storage areahousekeeper’s closetRestaurants and cafes / kitchens
![Page 4: See Opening Checklist on the Website for a Detail View The Basics of Opening a Hotel](https://reader036.vdocuments.net/reader036/viewer/2022082710/56649e8f5503460f94b9325d/html5/thumbnails/4.jpg)
Pre-Opening Staff Plan:Draw up an organization chart with all positionsDraw up spreadsheet consisting of
Position titlesStart datesPay ratesBonus and allowancesBenefits
![Page 5: See Opening Checklist on the Website for a Detail View The Basics of Opening a Hotel](https://reader036.vdocuments.net/reader036/viewer/2022082710/56649e8f5503460f94b9325d/html5/thumbnails/5.jpg)
Labor costs 40%(taken from pre-opening staff plan)
Sales and marketing efforts 40%(advertising and promotion, contracts, public relations, and travelling to see clients)
Miscellaneous 20%(office space before moving, utilities, recruitment and selection costs, licenses etc)
Pre-Opening Budget:
![Page 6: See Opening Checklist on the Website for a Detail View The Basics of Opening a Hotel](https://reader036.vdocuments.net/reader036/viewer/2022082710/56649e8f5503460f94b9325d/html5/thumbnails/6.jpg)
$8000 to $10000 per room for 4 or 5 star hotelMay exceed 2500 items (more for full service
resort, less for in city business hotel)Include:
Front office and lobby items Guest room itemsFood and beverage (F&B) itemsBanquet itemsKitchen itemsAdministrative office itemsStaff uniform
Operational Supplies and Equipment: