selected problems solution - summer 1433-34h
DESCRIPTION
OrganizacionTRANSCRIPT
King Saud University GE 404 Engineering Management
Civil Engineering Department Selected Problems Solution Summer semester 1433/ 1434H
1
Question 1 A small project activities and related information are given in table
(1).
a) Develop the AOA, AON, TSN
b) Calculate ES,LS,LS, AND LF and Find the critical path using
AON network
c) Find Gantt chart for each
d) Consider calendar date, the project starts Saturday, first of the
month and Friday is holiday. Draw the bar chart and
determine the project finish date and needed working days
e) Considering the constraints of ZZBD 3,2, FSCF 2, SSFG 4, SFEG 3; Determine:
i. Network data of forward and backward calculations and Total Float (TF)
ii. Critical path of the network. How it is differ from question 3b?
f) Develop load diagram of the resource, and find
i. average daily requirement;
ii. Critical Index
iii. Effectiveness value
iv. use Burgess Algorithm to level resource
Solution
a) AOA AON
a) TSN
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
A,2
B,5 D,10 E,3 G,8
C,1 F,6
Table (1)
Activity Immediate
predecessor(s)
Time,
days
Man-
power Equipment
A - 2 2 E1
B - 5 3 E1
C - 1 1 E2
D B 10 3 E2
E A, D 3 4 E3
F C 6 5 E4
G E, F 8 3 E5
1
2
3
4
6
5
7 8
A, 2
B, 5
C, 1
E, 3
D, 10
F, 6 G, 8
A
,
START B
,
C
,
D
,
E
,
F,
6
G
,
King Saud University GE 404 Engineering Management
Civil Engineering Department Selected Problems Solution Summer semester 1433/ 1434H
2
b) AON and critical path [carry calculation]
c) Gantt chart T 01 02 03 04 05 06 07 08 09 10 11 12 13 13 15 16 17 18 19 20 21 22 23 24 24 26
B B
D D
E E
G G
A A A
C C C
F F F
d) Calendar schedule July
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
B
D D D
E
G G
A
C
F F
Activity A B C D E F G
Free Float 13 0 11 0 0 11 0
Total Float 13 0 11 0 0 11 0
A
0 2
13 2 15
C
0 1
11 1 12
B
0 5
0 5 5
D
5 1
5 1 1
G
18 26
18 8 26
E
15 18
15 3 18
F
1 7
12 6 18
0 0
0 0 0
START
L
S
E
S
CRITICAL
King Saud University GE 404 Engineering Management
Civil Engineering Department Selected Problems Solution Summer semester 1433/ 1434H
3
e) Solution with constraint (lag times)
Forward pass:----------------------------------------------------------------------------------------------
Activity A: ESA=0; EFA= ESA+DA=0+2=2; -------------------------------------------------------------------------------
Activity B: ESB=0; EFB= ESB+DB=0+5=5; -------------------------------------------------------------------------------
Activity C: ESC=0; EFC= ESC+DC=0+1=1; -------------------------------------------------------------------------------
Activity D: ESD=ESB+SSBD=0+3=3 OR EFB+FFBD-DD=5+2-10=0 Then ESD=3; EFD= ESD+DD=3+10=13--
Activity E: ESE=13; EFE= ESE+DE=13+3=16----------------------------------------------------------------------------
Activity F: ESF=EFC+FSCF=1+2=3; EFF= ESF+DF=3+6=9-----------------------------------------------------------
Activity G: ESG=ESE+SFEG-DG=13+4-8=9 OR ESF+SSFG=3+4=7 Then ESG=9; EFG= ESG+DG=9+8=17----
Backward pass: --------------------------------------------------------------------------------------------
Activity G: LFG= EFG =17; LSG= LFG - DG =17-8=9; ------------------------------------------------------------------
Activity F: LFF=LSG-SSFG+DF =9-4+6=11; LSF= LFF – DF =11-6=5------------------------------------------------
Activity E: LFE=LFG-SFEG+DE =17-4+3=16; LSE= LFE – DE =16-3=13--------------------------------------------
Activity D: LFD=13; LSD= LFD – DD =13-10=3; -------------------------------------------------------------------------
Activity C: LFC= LFF-FSCF = 10-2=8; LSC= LFC – DC=8-1=7--------------------------------------------------------
Activity B: LFB=LSD-SSBD+DB=3-3+5=5 OR LFD-FFBD=13-2=11 Then LFB=5; LSB= LFB – DB =5-5=0-----
Activity A: LFA=13; LSA= LFA – DA =13-2=11; --------------------------------------------------------------------
Activity A B C D E F G
Free Float 11 0 7 0 0 2 0
Total Float 11 0 7 0 0 2 0
A
0 2
11 2 13
C
0 1
7 1 8
B
0 5
0 5 5
D
3 13
3 10 13
G
9 17
9 8 17
E
13 16
13 3 16
F
3 9
5 6 11
0 0
0 0 0
START
jjj
jiji
jiji
iji
iji
ij
DESEF
DSFES
DFFEF
SSES
FSEF
allMaxES
SSFORWARD PA
]2[
Time Initial
)(]1[
iii
iijj
iijj
ijj
ijj
ji
DLFLS
DSFLF
DSSLS
FFLF
FSLS
e
allMinLF
ASSBACKWARD P
]4[
Tim Terminal
)(]3[
King Saud University GE 404 Engineering Management
Civil Engineering Department Selected Problems Solution Summer semester 1433/ 1434H
4
f) Resource and leveling
TI 01 02 03 04 05 06 07 08 09 10 11 12 13 13 15 16 17 18 19 20 21 22 23 24 24 26
B- B
D- D
E- E
G- G
A- A
C- C
F- F
T 01 02 03 04 05 06 07 08 09 10 11 12 13 13 15 16 17 18 19 20 21 22 23 24 24 26
B B
D D
E E
G G
A A
C C
F F
TI 01
02 03
04
05
06 07 08 09 10 11 12 13 13 15 16 17 18 19 20 21 22 23 24 24 26
R 6 10 8 8 8 8 8 3 3 3 3 3 3 3 3 4 4 4 3 3 3 3 3 3 3 3
ΣR
6 16 24
32
40
48 56 59 62 65 68 71 74 77 80 84 88 92 95 98 101
104
107
110
113
116
R2 36
100
64
64
64
64 64 9 9 9 9 9 9 9 9 16 16 16 9 9 9 9 9 9 9 9
Σ R2 648
TI 01
02
03
04
05
06
07
08
09
10
11
12
13
13 15 16
17
18
19
20
21 22 23 24 24 26
R 3 3 3 3 3 3 3 3 3 3 3 4 8 10 10 9 9 9 3 3 3 3 3 3 3 3
ΣR
3 6 9 12
15
18
21
24
27
30
33
37
45
55 65 74
83
92
95
98
101
104
107
110
113
116
R2 9 9 9 9 9 9 9 9 9 9 9 16
64
100
100
81
81
81
9 9 9 9 9 9 9 9
Σ R2 694
0
2
4
6
8
10
12
0 5 10 15 20 25 30
No
. of
Re
sou
rce
s (M
en
)
Time, Day
0
20
40
60
80
100
120
140
0 10 20 30
Acc
um
alat
ive
Re
sou
rce
(m
an)
Time, Days
E
S
CRITICAL
L
S
CRITICAL
ES
T
LS
T
ES
T
LS
T
Figure 2 man power requirement Figure 1 Man Load histogram (Earliest & Latest
Start
King Saud University GE 404 Engineering Management
Civil Engineering Department Selected Problems Solution Summer semester 1433/ 1434H
5
Analysis
𝐴𝑣𝑒𝑟𝑎𝑔𝑒 𝑑𝑎𝑖𝑙𝑦 𝑟𝑒𝑞𝑢𝑖𝑟𝑒𝑚𝑒𝑛𝑡, 𝐷𝑟 =𝑇𝑜𝑡𝑎𝑙 𝑚𝑒𝑛 (∑ 𝑅)
𝑝𝑟𝑜𝑗𝑒𝑐𝑡 𝑑𝑢𝑟𝑎𝑡𝑖𝑜𝑛 (𝐷)=
116
26= 𝟒. 𝟒𝟔𝟐
𝐸𝑓𝑓𝑒𝑐𝑡𝑖𝑣𝑒𝑛𝑒𝑠𝑠 = 𝐷𝑟2 ∗ 𝐷 = (4.462)2 ∗ 26 = 𝟓𝟏𝟕. 𝟓𝟒
𝐸𝑆𝑇 𝐶𝑟𝑖𝑡𝑖𝑐𝑎𝑙𝑖𝑡𝑦 𝐼𝑛𝑑𝑒𝑥 =√6482
26= 0.98
𝐿𝑆𝑇 𝐶𝑟𝑖𝑡𝑖𝑐𝑎𝑙𝑖𝑡𝑦 𝑖𝑛𝑑𝑒𝑥 =√6942
26= 1.013
Load leveled
TI 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 24 26
B- B
D- D
E- E
G- G
A- A
C- C
F- F
𝐶𝑟𝑖𝑡𝑖𝑐𝑎𝑙𝑖𝑡𝑦 𝑖𝑛𝑑𝑒𝑥 = √624
26
2
= 0.961
TI 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 24 26
R 3 3 3 3 3 3 5 5 4 8 8 8 8 8 8 4 4 4 3 3 3 3 3 3 3 3
ΣR 3 6 9 12 15 18 23 28 32 40 48 56 64 72 80 84 88 92 95 98 101 104 107 110 113 116
R2 9 9 9 9 9 9 25 25 16 64 64 64 64 64 64 16 16 16 9 9 9 9 9 9 9 9
Σ R2 624
0
2
4
6
8
10
12
0 5 10 15 20 25 30
No
. of
Re
sou
rce
s (M
en
)
Time, Day
CRITICAL
ES
T
LS
T
LEVELING
Figure 3 Load Histograms
King Saud University GE 404 Engineering Management
Civil Engineering Department Selected Problems Solution Summer semester 1433/ 1434H
6
Question 2 A small project activities and related information are given in table.
1. Develop the AOA, AON, TSN
2. Calculate network times and Find the critical path using AON network
3. Find Gantt charts
4. Considering the constraints of ZZAD 3,2, SFDF 2, FSFH 2, SSGI 2; ZZHI 2,1Determine:
a. Network data of forward and backward calculations and Total Float (TF)
b. Critical path of the network.
5. Develop load diagram of the resource, and find
a. average daily requirement;
b. Critical Index
c. Effectiveness value
d. use Burgess Algorithm to level resource
Solution Q1 -1-
A,4
C,4
D,7
B,4
K,10
F, 6
E, 7
END H, 14
G, 7
J, 15
I, 14
ZZAD 3,2
SFDF 2
FSFH 2
SSGI 2
ZZHI 2,1
AON network
5 9
6
A, 4 2 4
3 7
8 D, 7
B, 4
1
C, 4
E, 7
F, 6
K, 10
G, 7
J, 15
1
0
1
1
H, 14 1
2
I, 14
AOA network
King Saud University GE 404 Engineering Management
Civil Engineering Department Selected Problems Solution Summer semester 1433/ 1434H
7
1 2 3 4 5 6 7 8 9 1
0
1
1
1
2
1
3
1
4
1
5
1
6
1
7
1
8
1
9
2
0
2
1
2
2
2
3
2
4
2
5
2
6
2
7
2
8
2
9
3
0
3
1
3
2
3
3
3
4
3
5
3
6
2
7
3
8
3
9
4
0
4
1
4
2
4
3
4
4
4
5
Solution Q1 -2-
Critical Path activities: A-D-F-H-I
Project duration Time =45 weeks
A
0 0 4
0 4 4
B
4 3 8
7 4 11
C
4 27 8
31 4 35
D
4 0 11
4 7 11
K
8 17 18
35 10 45
E
11 6 18
17 7 24
G
18 6 25
24 7 31
J
8 22 23
30 15 45
H
17 0 31
17 14 31
F
11 0 17
11 6 17
I
31 0 45
31 14 45
Act
ES TF LS
LS D LF
CR@CS
END
45 0 45
45 0 45
TSN network
B, 4
A, 4
C, 4
D, 7
J, 15
F, 6 H, 14 I, 14
E, 7 G, 7
K, 10
King Saud University GE 404 Engineering Management
Civil Engineering Department Selected Problems Solution Summer semester 1433/ 1434H
8
Solution Q1 -3-
1 2 3 4 5 6 7 8 9 10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
27
38
39
40
41
42
43
44
45
A
D
F
H
I
B
J
E
G
C
K
1 2 3 4 5 6 7 8 9 10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
27
38
39
40
41
42
43
44
45
A
D
F
H
I
B
J
E
G
C
K
Solution Q1 -4 Solution with constraint Forward pass: Activity A: ESA=0; EFA= ESA+DA=0+4=4;
Activity B: ESB=4; EFB= ESB+DB=4+4=8;
Activity C: ESC=4; EFC= ESC+DC=4+4=8;
Activity D: ESD=ESA+SSAD=0+3=3 OR EFA+FFAD-DD=4+2-7=0
Then ESD=3; EFD= ESD+DD=3+7=10;
Activity E: ESE= EFD =10; EFE= ESE+DE=10+7=17;
Activity F: ESF=ESD+SFDF-DF=3+2-6=0 OR EFB= 8;
Then ESF=8; EFF= ESF+DF=8+6=14;
Activity J: ESJ= EFB= 8; EFJ= ESJ+DJ=8+15=23;
Activity G: ESG= EFE=17; EFG= ESG+DG=17+7=24;
Activity K: ESK= EFC=8; EFK= ESK+DK=8+10=18;
Activity H: ESH=EFF+FSFH=14+2=16; EFF= ESF+DF=16+14=30;
Activity I: ESI=ESH+SSHI=16+2=18 OR EFH+FFHI-DI=30+1-14=17 OR ESG+SSGI=17+2=19
Then ESI=19; EFI= ESI+DI=19+14=33;
EST GANTT CHART
LST GANTT CHART
jjj
jiji
jiji
iji
iji
ij
DESEF
DSFES
DFFEF
SSES
FSEF
allMaxES
SSFORWARD PA
]2[
Time Initial
)(]1[
King Saud University GE 404 Engineering Management
Civil Engineering Department Selected Problems Solution Summer semester 1433/ 1434H
9
Backward pass:
Activity I: LFI= EFI =33; LSI= LFI – DI =33-14=19;
Activity J: LFJ= EFI =33; LSJ= LFJ – DJ =33-15=18;
Activity K: LFK= EFK=33; LSK= LFK- DK =33-10=23;
Activity H: LFH=LSI-SSHI+DH=19-2+14=31 OR LFI-FFHI=33-1=32
Then LFH=31; LSH= LFH– DH =31-14=17
Activity G: LFG=LSI-SSGI+DG =19-2+7=24; LSG= LFG– DG =24-7=17
Activity F: LFF= LSH-FSFH = 17-2=15; LSF= LFF– DF=15-6=9
Activity E: LFE= LSG =17; LSE= LFE- DE=17-7=10;
Activity C: LFC= LSG =17; LSC= LFC- DC=17-4=13;
Activity B: LFB= LSF =9; LSB= LFB- DB=9-4=5;
Activity E: LFD=LFE-SFDE+DD=17-2+7=22; OR LFD = LSE=10;
Then LFD=10; LSD=LFE – DE =10-7=3
Activity H: LFA=LSD-SSAD+DA=3-3+4=4 OR LFD-FFAD=10-2=8 OR LSJ=18 OR LSC=13
Then LFA=4; LSA= LFA– DA =4-4=0
Critical Path activities: A-D-E-G-I
Project duration Time =33 weeks
A
0 0 4
0 4 4
B
4 1 8
5 4 9
C
4 9 8
13 4 17
D
3 0 10
3 7 10
K
8 15 18
23 10 33
E
10 0 17
10 7 17
G
17 0 24
17 7 24
J
8 10 23
18 15 33
H
16 1 30
17 14 31
F
8 0 14
9 6 15
I
19 0 33
19 14 33
Act
ES TF LS
LS D LF
CR@CS
END
33 0 33
33 0 33
ZZAD 3, 2 SFDF 2
FSFH 2
SSGI 2
ZZHI 2, 1
iii
iijj
iijj
ijj
ijj
ji
DLFLS
DSFLF
DSSLS
FFLF
FSLS
e
allMinLF
ASSBACKWARD P
]4[
Tim Terminal
)(]3[
King Saud University GE 404 Engineering Management
Civil Engineering Department Selected Problems Solution Summer semester 1433/ 1434H
10
Solution Q1 -5-
1 2 3 4 5 6 7 8 9 1
0
1
1
1
2
1
3
1
4
1
5
1
6
1
7
1
8
1
9
2
0
2
1
2
2
2
3
2
4
2
5
2
6
2
7
2
8
2
9
3
0
3
1
3
2
3
3
3
4
3
5
3
6
2
7
3
8
3
9
4
0
4
1
4
2
4
3
4
4
4
5
A 4 4 4 4
D 3 3 3 3 3 3 3
F 4 4 4 4 4 4
H 5 5 5 5 5 5 5 5 5 5 5 5 5 5
I 5 5 5 5 5 5 5 5 5 5 5 5 5 5
B 2 2 2 2
J 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
E 5 5 5 5 5 5 5
G 4 4 4 4 4 4 4
C 3 3 3 3
K 2 2 2 2 2 2 2 2 2 2
1 2 3 4 5 6 7 8 9 1
0
1
1
1
2
1
3
1
4
1
5
1
6
1
7
1
8
1
9
2
0
2
1
2
2
2
3
2
4
2
5
2
6
2
7
2
8
2
9
3
0
3
1
3
2
3
3
3
4
3
5
3
6
2
7
3
8
3
9
4
0
4
1
4
2
4
3
4
4
4
5
A 4 4 4 4
D 3 3 3 3 3 3 3
F 4 4 4 4 4 4
H 5 5 5 5 5 5 5 5 5 5 5 5 5 5
I 5 5 5 5 5 5 5 5 5 5 5 5 5 5
B 2 2 2 2
J 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
E 5 5 5 5 5 5 5
G 4 4 4 4 4 4 4
C 3 3 3 3
K 2 2 2 2 2 2 2 2 2 2
∑ R2 3295
∑ R2 3101
EST GANTT CHART
LST GANTT CHART
R 4 4 4 4 8 8 8 8 8 8 8 14 14 14 14 14 14 15 12 12 12 12 12 9 9 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
∑R 4 8 12 16 24 32 40 48 56 64 72 86 100 114 128 142 156 171 183 195 207 219 231 240 249 254 259 264 269 274 279 284 289 294 299 304 309 314 319 324 329 334 339 344 349
R2 16 16 16 16 64 64 64 64 64 64 64 196 196 196 196 196 196 225 144 144 144 144 144 81 81 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25
∑ R2
16 32 48 64 128 192 256 320 384 448 512 708 904 1100 1296 1492 1688 1913 2057 2201 2345 2489 2633 2714 2795 2820 2845 2870 2895 2920 2945 2970 2995 3020 3045 3070 3095 3120 3145 3170 3195 3220 3245 3270 3295
R 4 4 4 4 3 3 3 5 5 5 5 4 4 4 4 4 4 10 10 10 10 10 10 10 9 9 9 9 9 9 12 11 11 11 11 10 10 10 10 10 10 10 10 10 10
∑R 4 8 12 16 19 22 25 30 35 40 45 49 53 57 61 65 69 79 89 99 109 119 129 139 148 157 166 175 184 193 205 216 227 238 249 259 269 279 289 299 309 319 329 339 349
R2 16 16 16 16 9 9 9 25 25 25 25 16 16 16 16 16 16 100 100 100 100 100 100 100 81 81 81 81 81 81 144 121 121 121 121 100 100 100 100 100 100 100 100 100 100
∑ R2
16 32 48 64 73 82 91 116 141 166 191 207 223 239 255 271 287 387 487 587 687 787 887 987 1068 1149 1230 1311 1392 1473 1617 1738 1859 1980 2101 2201 2301 2401 2501 2601 2701 2801 2901 3001 3101
King Saud University GE 404 Engineering Management
Civil Engineering Department Selected Problems Solution Summer semester 1433/ 1434H
11
Question 8 Consider the time-scaled network given below.
a) Draw the corresponding AON network showing each activity four timings and total float.
b) For Developed load diagram of the resource for EST below, find
i. Average daily requirement
ii. Effectiveness value
iii. Critical Index
c) Perform the resource leveling in order to keep the resource uniform with resource constraint of 5 and find
i. Average daily requirement
ii. Effectiveness value
iii. Critical Index
d) Comment on the budget costing before and after leveling of resources, Period, week 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Resources, R 5 5 5 5 7 7 5 6 6 8 5 5 5 5 5 5 5 2 2 5 5 3 3
Budget, Cs,
1000SR 2 2 2 3 4 4 3.5 3 3 4 3 3 3 3 4 4 4 2.5 2.5 2.5 2.5 2 2
a) AON
Critical Path activities: A-C-F-I-K
Project duration Time =23 weeks
D
2@1000SR
K
3@2000SR
H
3@1500SR
I
2@2500SR
F
3@2000SR
E
3@1000SR
C
3@2500SR
B
2@500SR
A
5@2000SR
G
2@1000SR
J
2@500SR
E
7 8 10
15 3 18
0
C
3 0 7
3 4 7
B
3 9 6
12 3 15
D
3 3 6
6 3 9
F
7 0 14
7 7 14
I
14 0 19
14 5 19
0 0 3
0 3 3
A
G
6 3 11
9 5 14
K
19 0 23
19 4 23
H
14 4 17
18 3 21
2
J
19 2 21
21 2 23
END
23 0 23
23 0 23
King Saud University GE 404 Engineering Management
Civil Engineering Department Selected Problems Solution Summer semester 1433/ 1434H
12
b) Load diagrams
Period, week 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Resources, R 5 5 5 7 7 7 5 8 8 8 5 3 3 3 5 5 5 2 2 5 5 3 3
Budget, Cs,
1000SR 2 2 2 4 4 4 4.5 4 4 4 3 2 2 2 4 4 4 2.5 2.5 2.5 2.5 2 2
week 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23
R 5 5 5 5 7 7 5 6 6 8 5 5 5 5 5 5 5 2 2 5 5 3 3
ΣR 5 10 15 22 29 36 41 49 57 65 70 73 76 79 84 89 94 96 98 103 108 111 114
R2 25 25 25 49 49 49 25 64 64 64 25 9 9 9 25 25 25 4 4 25 25 9 9
ΣR2 642
Analysis 𝐴𝑣𝑒𝑟𝑎𝑔𝑒 𝑑𝑎𝑖𝑙𝑦 𝑟𝑒𝑞𝑢𝑖𝑟𝑒𝑚𝑒𝑛𝑡, 𝐷𝑟
=𝑇𝑜𝑡𝑎𝑙 𝑚𝑒𝑛 (∑ 𝑅)
𝑝𝑟𝑜𝑗𝑒𝑐𝑡 𝑑𝑢𝑟𝑎𝑡𝑖𝑜𝑛 (𝐷)=
114
23= 𝟒. 𝟗𝟓𝟕
𝐸𝑓𝑓𝑒𝑐𝑡𝑖𝑣𝑒𝑛𝑒𝑠𝑠 = 𝐷𝑟2 ∗ 𝐷 = (4.957)2 ∗ 23
= 𝟓𝟔𝟓. 𝟏𝟓𝟑 = ∑ 𝑹𝑬𝟐
𝐸𝑆𝑇 𝐶𝑟𝑖𝑡𝑖𝑐𝑎𝑙𝑖𝑡𝑦 𝐼𝑛𝑑𝑒𝑥 =∑ 𝑹𝑨
𝟐
∑ 𝑹𝑬𝟐
=642
565.153= 𝟏. 𝟏𝟑𝟔
Comments
1- Load histogram shows resource variations
through the time.
2- The average resources required to be leveled is
>= 5
3- available resources only 5 at any time, then
Hence, when available resource is 5; Then,
𝐸𝑓𝑓𝑒𝑐𝑡𝑖𝑣𝑒𝑛𝑒𝑠𝑠 = 𝐷𝑟2 ∗ 𝐷 = (5)2 ∗ 23 = 𝟓𝟕𝟓 = ∑ 𝑹𝑬𝟐
𝐸𝑆𝑇 𝐶𝑟𝑖𝑡𝑖𝑐𝑎𝑙𝑖𝑡𝑦 𝐼𝑛𝑑𝑒𝑥 =𝟒. 𝟗𝟓𝟕
𝟓= 𝟎. 𝟗𝟗𝟏
D
2@1000SR
K
3@2000SR
H
3@1500SR
I
2@2500SR
F
3@2000SR
E
3@1000SR
C
3@2500S
B
2@500SR
A
5@2000
G
2@1000SR
J
2@500SR
0
2
4
6
8
10
0 10 20 30
No
. of
Rec
ou
rses
Project Duration
King Saud University GE 404 Engineering Management
Civil Engineering Department Selected Problems Solution Summer semester 1433/ 1434H
13
c) Resource leveling
Arrange according LST (A, C, D, B, F, G, E , I, H, K, J)
EAS
OSS
A 5 5 5
C 3 3 3 3
D 2 2 2
B 2 2 2
F 3 3 3 3 3 3 3
G 2 2 2 2 2
E 3 3 3
I 2 2 2 2 2
H 3 3 3
K 3 3 3 3
J 2 2
WEEK 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
- - - 2 2 2 2 3 3 2 2 2 2 2 2 2 2 3 3 2 2 2 2 2
R 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 3 5 5 3 3
ΣR 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 98 103 108 111 114
R2 5 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 9 25 25 9 9
ΣR2= 532
Analysis
𝐴𝑣𝑒𝑟𝑎𝑔𝑒 𝑑𝑎𝑖𝑙𝑦 𝑟𝑒𝑞𝑢𝑖𝑟𝑒𝑚𝑒𝑛𝑡, 𝐷𝑟 =𝑇𝑜𝑡𝑎𝑙 𝑚𝑒𝑛 (∑ 𝑅)
𝑝𝑟𝑜𝑗𝑒𝑐𝑡 𝑑𝑢𝑟𝑎𝑡𝑖𝑜𝑛 (𝐷)=
114
24= 𝟒. 𝟕𝟓
𝐸𝑓𝑓𝑒𝑐𝑡𝑖𝑣𝑒𝑛𝑒𝑠𝑠 = 𝐷𝑟2 ∗ 𝐷 = (4.75)2 ∗ 24 = 𝟓𝟒𝟏. 𝟓 = ∑ 𝑹𝑬𝟐
𝐸𝑆𝑇 𝐶𝑟𝑖𝑡𝑖𝑐𝑎𝑙𝑖𝑡𝑦 𝐼𝑛𝑑𝑒𝑥 =𝟒. 𝟕𝟓
𝟓= 𝟎. 𝟗𝟒
0
2
4
6
8
10
0 5 10 15 20 25
No
. of
Res
ou
rces
Project Duration, week
R (without resource limit) R (with resource limit=5)
King Saud University GE 404 Engineering Management
Civil Engineering Department Selected Problems Solution Summer semester 1433/ 1434H
14
Comments
1- Load histogram shows resource variations reduced by leveling through the time.
d) Budgeted Cost
Week 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Budget, Cs 1000SR (Without resource level)
2 2 2 4 4 4 4.5 4 4 4 3 2 2 2 4 4 4 2.5 2.5 2.5 2.5 2 2
Cumulative Cs 2 4 6 9 13 17 20.5 23.5 26.5 30.5 33.5 36.5 39.5 42.5 46.5 50.5 54.5 57 59.5 62 64.5 66.5 68.5
Budget, Cs 1000SR (With resource level=5)
2 2 2 4 4 4 4.5 4 4 4 3 2 2 2 4 4 4 2.5 2.5 2.5 2.5 2 2 2
Cumulative Cs 2 4 6 9.5 13 16.5 19.5 22 24.5 27.5 30.5 33.5 36.5 39.5 43 46.5 50 54 58 59.5 62 64.5 66.5 68.5
Comment:
Since the duration is extended when resources is limited to 5, this is resulted in small reduction of budgeted cost
over periods.
Figure 4 Cumulative Budgeted Cost
0
10
20
30
40
50
60
70
0 5 10 15 20 25
Cu
mu
lati
ve b
ud
get
ed c
ost
, 1o
oo
SR
Project Duration, week
CumulativeCs1000SR(Withoutresource level)
Cumulative Cs1000SR(Withresource level=5)
King Saud University GE 404 Engineering Management
Civil Engineering Department Selected Problems Solution Summer semester 1433/ 1434H
15
Question 12 (Crushing)
Development of a new version of software is
considered by a software company. The activities
necessary for completion of the project are given
in the following table (1)
(a) What is the project completion date?
(b) What is the total cost required to completing
this project on normal time?
(c) If it is required to reduce the completion time
by one week, which activity should be
crashed? , and how much will this increase the total cost increase?
(d) What is the maximum time that can be crashed? How much would cost increase?
Solution (a) Project completion time 16
(Critical Path Activities A–D–G)
(b) Total cost on normal duration time =Σ normal cost of activities = $12,300
(c) Crash one week
Find cost slope Crash activity (D) by one week at extra cost of $75 (d) Maximum time to be crashed
Activities Predecessor(s) Tome, weeks Cost, $
Normal Crash Normal Crash
A - 4 3 2000 2600
B - 2 1 2200 2800
C - 3 3 500 500
D A 8 4 2300 2600
E B 6 3 900 1200
F C 3 2 3000 4200
G D, E 4 2 1400 2000
Activity
(X) Normal Time – Crash Time
(Y) Crash $–Normal $
Cost Slope=(Y/X);
$/time
A 1 600 600 B 1 600 600 C 0 0 — D 4 300 75 E 3 300 100 F 1 1,200 1,200 G 2 600 300
Activity Crash Cost
D 4 $300
G 2 600
A 1 600
E 1 100
7 weeks $1,600
A,
4
START B,
2
C,
3
E,
6
D,
8
F,
3
G,
4
END
King Saud University GE 404 Engineering Management
Civil Engineering Department Selected Problems Solution Summer semester 1433/ 1434H
16
Question 13 (financing) Consider data for a small project given in Table below. Revenue is paid to the contractor every 6 months
according to completed quantities of work. Assume that markup is 10% of total project cost and is uniformly
distributed over the work.
Assume also that work of each activity is uniformly distributed over its duration.
a. Draw on a scale the project cumulative cost and revenue curves according to ES timings.
b. Draw on the diagram produced in a) above effect of receipt of 10% of total revenue as an advance
payment. This payment will be deducted from each periodic revenue by the same percentage.
Solution
1-
Project completion time 30 ; (Critical Path Activities A–C–D)
2- Activity Cost distribution
TIME 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30
A-20 C-60 D-50
B-60
ACC. COST
0040 0080 0120 0160 0200 0240 0480 0720 0960 1080 1200 1320 1420 1520 1620
3- Revenue calculation
4- Total payment = 1620*(1+0.1) x 1000=(1620+162) x 1000 =1782 x 1000
Advanced payment = 0.1*1782 x 1000 =178.2 x 1000
Revenue every 6 months =
Activity Predecessor(s) Duration, Months Monthly cost, SR1000
A - 12 20
B A 6 60
C A 12 60
D B,C 6 50
Month R= Revenue =(Cost*1.1),
1000 SR Adj. Revenue = 0.9 R, 1000
SR Cumulative Revenue,
1000 SR
0 178.2
6 120(1.1)=132 118.8 118.8+178.2=297.0
12 240(1.1)=264 237.6 237.6+178.2=415.8
18 960(1.1)=1056 950.4 950.4+178.2=1128.6
24 1320(1.1)=1452 1306.8 1306.8+178.2=1485.0
30 1620(1.1)=1782 1603.8 1603.8+178.2=1782.0
A,
12
B,
6
C,
12
D,
6
King Saud University GE 404 Engineering Management
Civil Engineering Department Selected Problems Solution Summer semester 1433/ 1434H
17
5- Graph presentations
Figure 5 Cumulative Cash Flow
0
200
400
600
800
1000
1200
1400
1600
1800
0 5 10 15 20 25 30
Pro
ject
Cas
h, 1
00
0 S
R
Project Duration, weeks
Cash out= Cost
Adj. Revenue
Revenue
-700
-500
-300
-100
100
300
0 10 20 30
Cas
h, 1
00
0 S
R
Project Duration, weeks
Adj. Revenue
Revenue
Figure 6 Net Cash Flow
King Saud University GE 404 Engineering Management
Civil Engineering Department Selected Problems Solution Summer semester 1433/ 1434H
18
Question17 (project control) A small engineering project has budgeted cost of each activity as shown
in Table (15a). The budgeted cost of each activity is assumed to be
uniformly distributed over its duration. Project status at the end of the 15th
day, is given the table (15b). The actual cost of work performed (ACWP)
at the end of day 15 = 20200 SR
Calculate the CV, SV, CPI, SPI, and % overrun (underrun); BAC, EAC;
comment on progress of works.
Solution
Using Equations
BCWS (SR) =20,200
BCWP (SR) = 4000 + 6000 (0.6) + 2000 + 8000(0.8) + 7000 + 6000 (0.8) = 27,800
ACWP (SR) = 4200 + 3000 + 1600 + 5000 + 7200 + 4200 = 25,200
CV (SR) = BCWP – ACWP = 27800-25200=+2600 Over Budget
SV (SR) = BCWP – BCWS = 27,800-20,200=+7,600 Ahead of the schedule
BAC (SR) = 4000 + 6000 + 2000 + 8000 + 7000 + 6000 +9000 + 4000 = 46,000
EAC (SR) = (ACWP/ BCWP) × BAC = (25,200/27,800)*46,000= 41,697.84
ETC (SR) = EAC – ACWP =41,697.84-25,200= 16,497.84
% overrun or underrun = (ACWP-BCWP)/BCWP =(25,200-27,800)/ 27,800= -9.35% underrun
Comment: 1- Expenses are less than estimated and project is under control.
Table (1b) Project status
Activity % completed Expense to date,
1000 SR
A 100 4.2
B 60 3.0
C 100 1.6
D 80 5.0
E 100 7.2
F 80 4.2
G 0 0
H 0 0
Total 25.2
Table (1a). Activity budgeted cost
Activity A B C D E F G H
Budgeted cost (SR) 4000 6000 2000 8000 7000 6000 9000 4000
Project Cost Control
Activity Budgeted (scheduled) Cost,
1000 SR
To date value (Over /Under) Run
Cost, 1000 SR % completed Estimated Cost,
1000 SR Expense to date,
1000 SR
A 4 100 4*1.0=4 4.2 +0.2
B 6 60 6*0.6=3.6 3.0 -0.6
C 2 100 2 1.6 -0.4
D 8 80 8*0.8= 6.4 5.0 -1.4
E 7 100 7 7.2 +0.2
F 6 80 6*0.8=4.8 4.2 -0.6
G 9 0 0 0 0
H 4 0 0 0 0
Total 46 BCWP = 27.8 ACWP = 25.2 -2.4 (under-Run)
King Saud University GE 404 Engineering Management
Civil Engineering Department Selected Problems Solution Summer semester 1433/ 1434H
19
Question18 (Crashing & project control) Table (15) gives the work activities of a project and its related data.
Table (16a) project activity data
Activity Predecessor (s)
Normal Schedule Crashed Schedule
Time, week
Cost, 10,000 SR
Time, week
Cost, 10,000 SR
A - 4 2.0 2 5.0
B - 6 3.0 3 9.0
C A 4 4.5 2 10.0
D A, B 6 2.5 4 10.0
E D 2 0.5 1 1.0
F E 13 13.0 8 25.0
G E 1 1.5 1 1.5
H C, G 20 6.0 10 23.5
I F 9 7.0 5 16.0
Total 40.0 101.0
a) Determine EST, LST, TF schedule for each work activity at normal activity duration.
b) Determine a minimum schedule to complete the project within 26 weeks, what will be the required budget?
c) Consider that the project is scheduled according earliest time schedule for normal activity duration, only
246,000 SR has been spent and the project status as shown in table (3b). Determine the project is ahead or
behind schedule and the amount it is over or under budget. Suggest corrective actions in case that the project
is behind schedule or over budget.
Solution (a)
Critical Path activities: B-D-E-F-I
Project duration Time =36 Weeks
Table (16b) Project status
Activity % completed Expense to date,
10,000 SR
A 100 2.6
B 100 5.0
C 100 3.0
D 100 5.0
E 100 0.7
F 40 5.6
G 100 0.7
H 25 2.0
I 0 0
Total 24.6
B, 6 F, 13 D, 6
A, 4 C, 4
E, 2
FINIS
H, 20
G, 1
AON network
I, 9
STAR
King Saud University GE 404 Engineering Management
Civil Engineering Department Selected Problems Solution Summer semester 1433/ 1434H
20
Solution (b) Crashing
Activity Predecessor (s) X=(Normal –Crash)
Time, week
Y=(Normal –crash)
Cost, 10,000 SR
Cost Slope =Y/X,
10,000 SR
A - 2 3.0 1.5
B - 3 6.0 2.0
C A 2 5.5 2.75
D A, B 2 7.5 3.75
E D 1 0.5 0.5
F E 5 12.0 2.4
G E - - -
H C, G 10 17.5 1.75
I F 4 9 2.25
Cycle #
Activity to Shorten
Can Be Shortened
Week Shortened
Cost per week, 10,000 SR
Cost for Cycle, 10,000 SR
Project Duration
New activity duration time, week
0 36
1 E 1 1 0.5 0.5 35 1
2 B, A 3, 2 3, 1 2, 1.5 6+1.5=7.5 32 3, 3
3 I, H 4, 10 4, 3 2.25, 1.75 9+5.25=14.25 28 5, 17
4 D 2 2 3.75 7.5 4
Total extra cost paid, 10,000SR 29.75
Project budget,10,000 SR 40+29.75=69.75
Time Schedule analysis for Project normal activity duration
Activity Predecessor (s) Normal Time, week
Forward pass Backward pass Slack, (LS_ES)= TF
On Critical Path ES LS LS LF
A - 4 0 4 2 6 2
B - 6 0 6 0 6 0 yes
C A 4 4 8 12 16 8
D A, B 6 6 12 6 12 0 yes
E D 2 12 14 12 14 0 yes
F E 13 14 27 14 27 0 yes
G E 1 14 15 15 16 1
H C, G 20 15 35 16 36 1
I F 9 27 36 27 36 0 yes
Time Schedule analysis for Project after crashing
Activity Predecessor (s) Activity
Time, week
Forward pass Backward pass Slack, (LS_ES)= TF
On Critical Path ES LS LS LF
A - 3 0 3 0 3 0 yes
B - 3 0 3 0 3 0 yes
C A 4 3 7 5 9 2
D A, B 4 3 7 3 7 0 yes
E D 1 7 8 7 8 0 yes
F E 13 8 21 8 21 0 yes
G E 1 8 9 8 9 0 yes
H C, G 17 9 26 9 26 0 yes
I F 5 21 26 21 26 0 yes
King Saud University GE 404 Engineering Management
Civil Engineering Department Selected Problems Solution Summer semester 1433/ 1434H
21
Critical Activities; A, B, D, E, F, G, H, I
Project Duration =26 WEEKS –
Number OF Critical path = 4
Budget =697,500 SR
Solution (c) Project control project cost control Report
Activity Predecessor
(s)
Normal Schedule To date values
Time, week
Cost (scheduled), 10,000 SR
% completed
Cost (estimated), 10,000 SR
Expense to date, 10,000 SR
Cost overrun/underrun,10,000SR
A - 4 2.0 100 2.0 2.6 +0.6
B - 6 3.0 100 3.0 5.0 +2.0
C A 4 4.5 100 4.5 3.0 -1.5
D A, B 6 2.5 100 2.5 5.0 +2.5
E D 2 0.5 100 0.5 0.7 +0.2
F E 13 13.0 40 13*0.4=5.2 5.6 +.4
G E 1 1.5 100 1.5 0.7 -0.8
H C, G 20 6.0 25 6*0.25=1.5 2.0 +.5
I F 9 7.0 0 7*0=0 0 0
Total 40.0 BCWP = 20.7 ACWP = 24.6 Over-run = +3.9
OR BCWS (SR) =24.6 x 104
BCWP (SR) = (2 + 3 + 4.5 + 2.5 + 0.5 + 13*0.4+ 1.5 + 6*0.25) = 20.7 x 104
ACWP (SR) = (2.6 + 5 + 3 + 5 + 0.7 + 5.6 + 0.7 + 2) = 24.6 x 104
CV (SR) = BCWP – ACWP = 20.7 x 104-24.6 x 104=-3.9 x 104 under Budget
SV (SR) = BCWP – BCWS = 20.7 x 104-24.6 x 104 =-3.9 x 104 behind the schedule
BAC (SR) = (2 + 3 + 4.5 + 2.5 + 0.5 + 13+1.5 + 6 + 7) = 40 x 104
EAC (SR) = (ACWP/ BCWP) × BAC = (24.6 x 104 /20.7 x 104)* 40 x 104= 47.54 x 104
ETC (SR) = EAC – ACWP =47.54 x 104-24.6 x 104 = 22.94 x 104
% overrun or underrun = (ACWP-BCWP)/BCWP =(24.6 x 104 -20.7 x 104)/ 20.7 x 104= 18.84% Over-run
Comments:
1- The project is found to be behind schedule / experiencing cost over-run.
2- The experienced cost over-run or delay is lost causes due to not meeting project deadlines or budgets.
3- Action should be taken for cost saving, (a) in case the project behind schedule, expediting some activity
at extra cost may be possible; (b) in case over budget, non-critical activities are evaluated for cost saving.,
(c) in case of fund reduction causing delay, evaluating project duration time is evaluated and may require
to be extended.