Seymour Capilano Filtration Project

Seymour Capilano Twin Tunnels

June 4, 2010

Goran Oljaca P.Eng.

Page 2: Seymour Capilano Filtration Project Seymour Capilano Twin Tunnels June 4, 2010 Goran Oljaca P.Eng

Seymour Capilano Filtration Plant& Twin Tunnels

Page 3: Seymour Capilano Filtration Project Seymour Capilano Twin Tunnels June 4, 2010 Goran Oljaca P.Eng

Seymour Capilano Filtration Plant

Page 4: Seymour Capilano Filtration Project Seymour Capilano Twin Tunnels June 4, 2010 Goran Oljaca P.Eng

Pump station

Pipeline corridor

Energy Recovery Facility

Twin Tunnels

portals site

Capilano

Page 5: Seymour Capilano Filtration Project Seymour Capilano Twin Tunnels June 4, 2010 Goran Oljaca P.Eng

Pump Station

Page 6: Seymour Capilano Filtration Project Seymour Capilano Twin Tunnels June 4, 2010 Goran Oljaca P.Eng

Inside the Break Head Tank

Page 7: Seymour Capilano Filtration Project Seymour Capilano Twin Tunnels June 4, 2010 Goran Oljaca P.Eng

• Filtration Plant– 1800 ML/d (20.8 m3/s) capacity

• Capilano Pump Station– 1080 Ml/d (12.5 m3/s)– 16,000 HP (12,000 KW)

• Break Head Tank / Energy Recovery Facility– Facility Flow range 0 – 12.5 m3/s– Turbine flow range 3 – 7.5 m3/s– PRV flow range (each) 0 – 12.5 m3/s– Generating capacity 1.7 MW– Annual Energy Generated 9500 MW.h

Page 8: Seymour Capilano Filtration Project Seymour Capilano Twin Tunnels June 4, 2010 Goran Oljaca P.Eng
Page 9: Seymour Capilano Filtration Project Seymour Capilano Twin Tunnels June 4, 2010 Goran Oljaca P.Eng

Twin Tunnel Progress

Page 10: Seymour Capilano Filtration Project Seymour Capilano Twin Tunnels June 4, 2010 Goran Oljaca P.Eng

Twin Tunnels

Treated Water Tunnel

Untreated Water Tunnel

Page 11: Seymour Capilano Filtration Project Seymour Capilano Twin Tunnels June 4, 2010 Goran Oljaca P.Eng

Gantry Crane Over Seymour Access Shaft

Page 12: Seymour Capilano Filtration Project Seymour Capilano Twin Tunnels June 4, 2010 Goran Oljaca P.Eng

Top of Seymour Tunnel Shaft

May 1, 2006

Page 13: Seymour Capilano Filtration Project Seymour Capilano Twin Tunnels June 4, 2010 Goran Oljaca P.Eng

Seymour Shaft

Page 14: Seymour Capilano Filtration Project Seymour Capilano Twin Tunnels June 4, 2010 Goran Oljaca P.Eng

Looking into the ‘tail tunnel’

Page 15: Seymour Capilano Filtration Project Seymour Capilano Twin Tunnels June 4, 2010 Goran Oljaca P.Eng

Seymour Shaft Base Entrance to Twin Tunnels

Page 16: Seymour Capilano Filtration Project Seymour Capilano Twin Tunnels June 4, 2010 Goran Oljaca P.Eng

Seymour Shaft Base

Page 17: Seymour Capilano Filtration Project Seymour Capilano Twin Tunnels June 4, 2010 Goran Oljaca P.Eng
Page 18: Seymour Capilano Filtration Project Seymour Capilano Twin Tunnels June 4, 2010 Goran Oljaca P.Eng

Muck Bucket

Page 19: Seymour Capilano Filtration Project Seymour Capilano Twin Tunnels June 4, 2010 Goran Oljaca P.Eng

Tunnel Boring Machine

Page 20: Seymour Capilano Filtration Project Seymour Capilano Twin Tunnels June 4, 2010 Goran Oljaca P.Eng

Untreated (Raw) Water Tunnel

October 6, 2009

Page 21: Seymour Capilano Filtration Project Seymour Capilano Twin Tunnels June 4, 2010 Goran Oljaca P.Eng

Reinforcing mesh and rock bolts

Page 22: Seymour Capilano Filtration Project Seymour Capilano Twin Tunnels June 4, 2010 Goran Oljaca P.Eng

Treated Water Tunnel

Sept. 1, 2009

Page 23: Seymour Capilano Filtration Project Seymour Capilano Twin Tunnels June 4, 2010 Goran Oljaca P.Eng

Treated Water Tunnel

Page 24: Seymour Capilano Filtration Project Seymour Capilano Twin Tunnels June 4, 2010 Goran Oljaca P.Eng

Untreated Water Tunnel

Page 25: Seymour Capilano Filtration Project Seymour Capilano Twin Tunnels June 4, 2010 Goran Oljaca P.Eng

Untreated Water TunnelClass 5 Support

Page 26: Seymour Capilano Filtration Project Seymour Capilano Twin Tunnels June 4, 2010 Goran Oljaca P.Eng

Shotcrete Installation

Page 27: Seymour Capilano Filtration Project Seymour Capilano Twin Tunnels June 4, 2010 Goran Oljaca P.Eng

Pump Station

Page 28: Seymour Capilano Filtration Project Seymour Capilano Twin Tunnels June 4, 2010 Goran Oljaca P.Eng

Discharge WaterQuality

Page 29: Seymour Capilano Filtration Project Seymour Capilano Twin Tunnels June 4, 2010 Goran Oljaca P.Eng
Page 30: Seymour Capilano Filtration Project Seymour Capilano Twin Tunnels June 4, 2010 Goran Oljaca P.Eng

Pond 3

Page 31: Seymour Capilano Filtration Project Seymour Capilano Twin Tunnels June 4, 2010 Goran Oljaca P.Eng

Capilano Shaft Site

Twin Tunnels Portals Site

Page 32: Seymour Capilano Filtration Project Seymour Capilano Twin Tunnels June 4, 2010 Goran Oljaca P.Eng

Capilano Raise Bore

Page 33: Seymour Capilano Filtration Project Seymour Capilano Twin Tunnels June 4, 2010 Goran Oljaca P.Eng

Reaming

Cleveland Dam Spillway

Raise-bore operation

Pumping

Station

250m to residence

270m deep shafts

Twin Tunnels

Page 34: Seymour Capilano Filtration Project Seymour Capilano Twin Tunnels June 4, 2010 Goran Oljaca P.Eng

Liner Storage

Page 35: Seymour Capilano Filtration Project Seymour Capilano Twin Tunnels June 4, 2010 Goran Oljaca P.Eng

Install Shaft Steel Liner

Page 36: Seymour Capilano Filtration Project Seymour Capilano Twin Tunnels June 4, 2010 Goran Oljaca P.Eng

Temporary Silos for Grouting

Temporary Silos

10 m

2 m

Page 37: Seymour Capilano Filtration Project Seymour Capilano Twin Tunnels June 4, 2010 Goran Oljaca P.Eng

Public Impacts and Mitigation Measures

• Truck traffic

• Noise

• Vibrations

• Air quality

• Landscaping and restoration

Page 38: Seymour Capilano Filtration Project Seymour Capilano Twin Tunnels June 4, 2010 Goran Oljaca P.Eng

Questions?