sgtech europe 2017 - smart grid forums · abb red670 (21p/21n/87l) synaptec distributed sensors w...

15
1 www.spenergynetworks.co.uk Cristina Fundulea Future Intelligent Transmission Network Substation (FITNESS) 28 th March 2017 SGTech Europe 2017

Upload: others

Post on 16-May-2020

5 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: SGTech Europe 2017 - Smart Grid Forums · ABB RED670 (21P/21N/87L) Synaptec Distributed Sensors w ABB MU (CT & VT) Circuit 1 GE NCIT-CT/VT Circuit 1 GE MU (CT & VT) Circuit 2 ABB

1www.spenergynetworks.co.uk

Cristina Fundulea

Future Intelligent Transmission

Network Substation (FITNESS)

28th March 2017

SGTech Europe 2017

Page 2: SGTech Europe 2017 - Smart Grid Forums · ABB RED670 (21P/21N/87L) Synaptec Distributed Sensors w ABB MU (CT & VT) Circuit 1 GE NCIT-CT/VT Circuit 1 GE MU (CT & VT) Circuit 2 ABB

2www.spenergynetworks.co.uk Future Intelligent Transmission Network Substation

(FITNESS)

• Overview project FITNESS

• Business benefits and drivers

• Optimising architecture design for long term

• Overcoming the technical challenges when implementing the process

bus:

• Reliability

• Time synchronisation between devices

• Cyber-security

• Measurement accuracy

• Confidence in the solution

Topics covered

Page 3: SGTech Europe 2017 - Smart Grid Forums · ABB RED670 (21P/21N/87L) Synaptec Distributed Sensors w ABB MU (CT & VT) Circuit 1 GE NCIT-CT/VT Circuit 1 GE MU (CT & VT) Circuit 2 ABB

3www.spenergynetworks.co.uk

FITNESS Overview

Future Intelligent Transmission Network Substation (FITNESS) is a flagship innovation collaboration project awarded by the UK regulator, Ofgem, to accelerate the progression to 61850-based transmission network substations, and:

Predicted benefits to GB customers by 2050:Faster deployment and improving network availability:

£260m-£592m savings in constraint payments

Reduced cabling and substation footprint:

£572m-£858m savings in substation costs

Major benefits are expected to include:• A reduction in substation costs,• improved system access, • reduced network constraints.

• Demonstrate a multi-vendor fully interoperable digital substation solution - deploying standardised and fully Integrated substation protection, monitoring and control system based on the IEC61850-9-2 standard.

• Reduce environmental impact of substations

• Enhance substation safety

• Enable increased flexibility and greater controllability in substations

Substation

hardware

Academia &

research

Future Intelligent Transmission Network Substation

(FITNESS)

Page 4: SGTech Europe 2017 - Smart Grid Forums · ABB RED670 (21P/21N/87L) Synaptec Distributed Sensors w ABB MU (CT & VT) Circuit 1 GE NCIT-CT/VT Circuit 1 GE MU (CT & VT) Circuit 2 ABB

4www.spenergynetworks.co.uk

FITNESS Overview

Future Intelligent Transmission Network Substation

(FITNESS)

Jan 2016 – March 2020 to:

• design and demonstrate full IEC 61850 operation and interoperation

• educate and inform the industry (including internal) of the technology

• uncover and overcome issues with the interpretation of the standard

• work with IEC Working Group to develop standard as necessary

Sep-16 WP1 Substation Design Complete

Sep-17 WP2 Off-line trials completeNov-18 WP5 Digital Substation training complete for install

Aug-18 WP2 Substation Bay#1 – live operation startsSep-18 WP3 Information exchange & application demoSep-18 WP3 Flexible control infrastructure demonstrationAug-19 WP2 Substation Bay#2 – live operation startsMar-20 Close down

Page 5: SGTech Europe 2017 - Smart Grid Forums · ABB RED670 (21P/21N/87L) Synaptec Distributed Sensors w ABB MU (CT & VT) Circuit 1 GE NCIT-CT/VT Circuit 1 GE MU (CT & VT) Circuit 2 ABB

5www.spenergynetworks.co.uk

Benefits and business drivers

• SPEN innovation strategy

• Short-term and long-term gains:– Reduced substation costs &

reduced network constraints

– Improved system access

Targeted areas of improvement and optimisation in conventional design

15% 10% 10-30% 80% 10%Future Intelligent Transmission Network Substation

(FITNESS)

Page 6: SGTech Europe 2017 - Smart Grid Forums · ABB RED670 (21P/21N/87L) Synaptec Distributed Sensors w ABB MU (CT & VT) Circuit 1 GE NCIT-CT/VT Circuit 1 GE MU (CT & VT) Circuit 2 ABB

6www.spenergynetworks.co.uk

Architecture & Connectivity

HSR PRP

Station

Bay

Process

Future Intelligent Transmission Network Substation

(FITNESS)

Page 7: SGTech Europe 2017 - Smart Grid Forums · ABB RED670 (21P/21N/87L) Synaptec Distributed Sensors w ABB MU (CT & VT) Circuit 1 GE NCIT-CT/VT Circuit 1 GE MU (CT & VT) Circuit 2 ABB

7www.spenergynetworks.co.ukFuture Intelligent Transmission Network Substation

(FITNESS)

Multi-Vendor Interoperability

Multi-vendor interoperability:

✓ Between ABB IEDs and GE merging units;

✓ Between GE IEDs and ABB merging units;

✓ Between ABB/GE merging units and SYNAPTEC

Interrogator;

✓ Between ABB IEDs and GE Substation Automation

System;

✓ Between ABB IEDs and GE SCUs (for protection trips);

✓ Between GE IEDs and ABB SCUs (for protection trips).

End to end integration of substation and central

system applications, to increase visibility and situational

awareness.

Bus architecture for measured sampled values (SV)

published to all secondary devices

• Distributed optical sensing

• Non-conventional voltage transformers (NCVTs)

First demonstration of NCITs as single unified data source

to replace separate transformers for protection,

measurement and power quality (PQ);

Greatly improved access to information sources without

CT/VT connections;

FITNESS focus

Interoperability

across SB & PB

Page 8: SGTech Europe 2017 - Smart Grid Forums · ABB RED670 (21P/21N/87L) Synaptec Distributed Sensors w ABB MU (CT & VT) Circuit 1 GE NCIT-CT/VT Circuit 1 GE MU (CT & VT) Circuit 2 ABB

8www.spenergynetworks.co.uk

Proof of interoperability

Future Intelligent Transmission Network Substation

(FITNESS)

Multi-Vendor Interoperability (2)

GE P546

(21P/21N/87L)

ABB RED670

(21P/21N/87L)

Synaptec

Distributed Sensors

Wis

haw

ABB MU

(CT & VT)Circuit 1

GE NCIT-CT/VT Circuit 1

GE MU

(CT & VT)Circuit 2

ABB NCIT-CT

& CVTCircuit 2

Synaptec NCIT

Distributed SensorCircuit 1 & Circuit 2

New

arth

ill Conventional

CT & CVTCircuit 1 Circuit 1

Conventional

CT (no CVT available)

Circuit 2,

87L only

Circuit 2,

87L only

Page 9: SGTech Europe 2017 - Smart Grid Forums · ABB RED670 (21P/21N/87L) Synaptec Distributed Sensors w ABB MU (CT & VT) Circuit 1 GE NCIT-CT/VT Circuit 1 GE MU (CT & VT) Circuit 2 ABB

9www.spenergynetworks.co.ukFuture Intelligent Transmission Network Substation

(FITNESS)

Process Bus Architecture

• Piloting new technologies affecting key aspect of network operation -

Protection and Control

• Purpose to determine optimum architecture

• Performance, Redundancy / reliability, maintenance, and, scalability

• IEC61850 standard does not specify what kind of redundancy is required

• ABB and GE have different preferred PB architectures:

• Parallel Redundancy Protocol (PRP)

• High-availability Seamless Redundancy (HSR)

• Technical assessment and Life-Cycle Analysis to determine chosen

architecture

• Most significant challenge is to instil sufficient confidence across the

business that benefits are both attainable and sustainable and can be

achieved without degrading system reliability and security.

Page 10: SGTech Europe 2017 - Smart Grid Forums · ABB RED670 (21P/21N/87L) Synaptec Distributed Sensors w ABB MU (CT & VT) Circuit 1 GE NCIT-CT/VT Circuit 1 GE MU (CT & VT) Circuit 2 ABB

10www.spenergynetworks.co.uk

Process Bus: ABB and GE Preferred Architectures

PRPHSRDual-ring

Not

segregated

from SB

Dual LANs

Segregated

from SB

Future Intelligent Transmission Network Substation

(FITNESS)

Page 11: SGTech Europe 2017 - Smart Grid Forums · ABB RED670 (21P/21N/87L) Synaptec Distributed Sensors w ABB MU (CT & VT) Circuit 1 GE NCIT-CT/VT Circuit 1 GE MU (CT & VT) Circuit 2 ABB

11www.spenergynetworks.co.uk

Primary objective is to overcome technical challenges and

bring technology and practices to BaU.

A technological leap from Single Function IEDs to Integrated C&P:

1. Reliability

– Examine and validate performance, Operational / maintenance

2. Time synchronisation between devices

– Highly dependant on GPS systems, state of existing comms infrastructure

3. Cyber-security

– Masses of digital data, integration with existing IT systems

4. Measurement accuracy

– Non-conventional instrument Transformers deployed, time synch errors

Future Intelligent Transmission Network Substation

(FITNESS)

Technical Challenges

Page 12: SGTech Europe 2017 - Smart Grid Forums · ABB RED670 (21P/21N/87L) Synaptec Distributed Sensors w ABB MU (CT & VT) Circuit 1 GE NCIT-CT/VT Circuit 1 GE MU (CT & VT) Circuit 2 ABB

12www.spenergynetworks.co.uk

Time Synchronisation is vital to ensure the substation devices properly

synchronise events and data acquisition

• The method of time synchronisation can be either direct (GPS, 1PPS,

IRIG-B) or synchronisation over LAN (distributed time synchronisation).

• LAN synchronisation can be applied on the existing Ethernet network to

distribute synchronisation information without the need for a dedicated

cabling infrastructure (more cost effective)

• FITNESS:

• uses IEEE 1588 Precision Time Protocol (PTP) - power profile, and dual Grand Master Clock with “Best Master Clock”

• switches (at both SB and PB) and IEDs must be able to act as Transparent Clocks (TC) and as Boundary Clock (BC) respectively

Future Intelligent Transmission Network Substation

(FITNESS)

Technical Challenges

Page 13: SGTech Europe 2017 - Smart Grid Forums · ABB RED670 (21P/21N/87L) Synaptec Distributed Sensors w ABB MU (CT & VT) Circuit 1 GE NCIT-CT/VT Circuit 1 GE MU (CT & VT) Circuit 2 ABB

13www.spenergynetworks.co.uk

Previous 61850 demonstration trialled in 2015/16

– Experienced difficulties of implementing IEC 61850 with added complexity of using propriety configuration tool

However, business remains committed to explore the benefits of

employing 61850

Internal stakeholder engagement to identify specific concerns:

– Key questions from Protection Engineer Manager:

• Can we rely on multicast SVs?

• How can we provide reliable time synchronisation?

• Can we rely on simulation tools to robustly prove functionality?

• How do we manage the evolution of the standard and integrate new IEDs?

• What is the engineering process? How will SPT deliver future projects?

Future Intelligent Transmission Network Substation

(FITNESS)

Technical Challenges

Page 14: SGTech Europe 2017 - Smart Grid Forums · ABB RED670 (21P/21N/87L) Synaptec Distributed Sensors w ABB MU (CT & VT) Circuit 1 GE NCIT-CT/VT Circuit 1 GE MU (CT & VT) Circuit 2 ABB

14www.spenergynetworks.co.uk

How we are addressing the technical challenges?

• Assessment of both HSR and PRP architectures with support from independent parties - Christoph Brunner (IT4Power) & Haiyu Li (University of Manchester).

• Full solution complement testing and training at HV testing facility prior to deployment

• Establish and educate engineers on testing procedures to support process bus implementation

Future Intelligent Transmission Network Substation

(FITNESS)

Technical Challenges

Page 15: SGTech Europe 2017 - Smart Grid Forums · ABB RED670 (21P/21N/87L) Synaptec Distributed Sensors w ABB MU (CT & VT) Circuit 1 GE NCIT-CT/VT Circuit 1 GE MU (CT & VT) Circuit 2 ABB

Thank you

Cristina Fundulea

[email protected]