sh_exmp sheet pile

Upload: suntoyo-saja

Post on 23-Feb-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/24/2019 Sh_exmp Sheet Pile

    1/17

    Civi lTech Software SHORING EXAMPLES 1

    EXAMPLE 1DESIGN OF CANTILEVERED WALL, GRANULAR SOIL

    Introduction:A sheet pile wall is required to support a 12 excavation. The soil is uniform as shown in the

    figure. To take into account the friction between the wall and the soil, we use friction angle =

    /2. Please note this value is applied only for passive pressure. Use factor of safety = 1.5 forpassive pressure.

    Question:What is the embedment and maximum bending moment in the pile?

    Calculation:Active pressure above cut:

    = 35, Ka = 0.27, @ 12, P1=Ka(12) = (0.27)(125)(12) = 0.405 KsfActive pressure below cut:Below the cut, use pressure slope input.

    The pressure slope Pa = Ka= (0.027)(125) = 0.034 KcfPassive pressure below cut:

    Soil friction = 35, wall friction = /2, Kp = 6.74 (NAVFAC or Epres program)

    The pressure slope Pp = Kp/F.S. = (6.74)(125)/1.50 = 0.56 KcfRunning Program:

    A short result for input and output is presented.NOTE: 1 spacing for the sheet pile

    Results:The program shows that the minimum embedment is 9.3 and the pile length is 21.3. Themaximum moment in the pile is 17 Kip-ft /ft. The maximum moment is at 15.9 from the groundsurface.

    H = 12

    Y0.56 kcf1

    P1 = 0.405 ksf

    0.034 kcf

    1

    Dredge Line

    = 125 pcf

    = 35o

    = /2 (only for passive)X

    EXAMPLE 1

  • 7/24/2019 Sh_exmp Sheet Pile

    2/17

    Civi lTech Software SHORING EXAMPLES 2

    EXAMPLE 2Alternative Input for Example 1

    Introduction:The conditions are the same as example 1. In example 2, we use an alternative input to checkthe versatility of the program. Instead of inputting both active and passive pressures below the

    cut, we input the net passive pressure below the cut. The net passive pressure is equal to Pp-Pa.

    Question:What is the embedment and maximum bending moment in pile?

    Calculation:Active pressure above cut: Same as Example 1.Net pressure below cut:

    Active pressure slope is

    Pa = Ka= (0.27)(125) = 0.034 KcfPassive pressure slope is

    Pp = Kp/F.S. = (6.74)(125) /1.5 = 0.56 KcfNet passive pressure slope is

    Pn = Pp - Pa = 0.56 - 0.034 = 0.526 KcfThe point of zero pressure is

    e = P1/Pn = 0.405/0.526 = 0.77Running Program:

    Input two active pressures in driving pressure input:One is from x = 0 to x = 12. Another is from x = 12 to x = 12 + 0.77There is no active pressure input below dredge line.The passive pressure starts Y = 0.77, with a net slope = 0.526 Kcf

    Results:The same as example 1.

    Alternative:Another alternative input is also presented in attached file, example 2A. In this input, the net

    passive pressure slope, 0.526 Kcf is directly inputted from Y = 0 with starting pressure of -0.405Ksf. In this way, the calculation of zero pressure point, e, can be omitted.

  • 7/24/2019 Sh_exmp Sheet Pile

    3/17

    Civi lTech Software SHORING EXAMPLES 3

    H = 12

    Y

    0.526 kcf

    1

    P1 = 0.405 ksf

    = 125 pcf

    = 35o

    =/2 (only for passive)X

    EXAMPLE 2

    e

    Y = 0.77

    H = 12

    P5 = 1.752

    P2 = 0.618

    2 = 130 pcf

    2 = 35o

    = /2

    EXAMPLE 3

    1 = 125 pcf

    1 = 30o

    = /2

    SOIL 1

    SOIL 2

    SURCHARGE, Ps = 0.24

    P4 =

    0.4

    1

    0.58

    P1 = 0.495

    P3 = 0.52615

    10

    1

    0.041

    1

    0.035

    1.2

  • 7/24/2019 Sh_exmp Sheet Pile

    4/17

    Civi lTech Software SHORING EXAMPLES 4

    EXAMPLE 3DESIGN OF SHEET PILE WALL WITH TWO SOIL AND SURCHARGE

    LOAD

    Introduction:

    A sheet pile wall is required to support 12 excavation. F.S. = 1.5 is required for passivepressure. Soil conditions are shown in the figure. The surcharge load will be in a separatediagram.

    Question: What is the embedment and maximum bending moment in pile?

    Calculation:Active pressure above cut:

    1=30, Ka =0.33, P1= Ka(12) = (0.33)(125)(12) = 0.495 KsfActive pressure below cut:

    pressure slope, Pa = Ka= (0.33)(125) = 0.041 Kcf

    P2= Ka(15) = (0.33)(125)(15) = 0.618 Ksf

    2= 35, Ka = 0.27, pressure slope Pa = Ka= (0.27)(130) = 0.035 Kcf

    P3= Ka(15) = (0.27)(130)(15) = 0.526 Ksf

    Passive pressure below cut: 1= 30, = 1/2, Kp = 4.8 (NAVFAC or Epres program)

    pressure slope, Pp = Kp/F.S. = (4.8)(125) /1.5 = 0.4 KcfP4= Pp(3) = 0.4(3) = 1.2 Ksf

    2= 35, = 2/2, Kp = 6.74 (NAVFAC or Epres program)

    pressure slope, Pp = Kp/F.S.= (6.74)(130) /1.5 = (6.74)(130) /1.5 = 0.584 KcfP5= Pp(3) = 0.584(3) = 1.752 Ksf

    Running Program:Use 1 spacing for the sheet pile and 0.24 Ksf for surcharge load.

    Results:The program shows that the minimum embedment is 13.3 and the pile length is 25. Themaximum moment in the pile is 53.3 K-ft/ft at 17.7 from the ground surface.

  • 7/24/2019 Sh_exmp Sheet Pile

    5/17

    Civi lTech Software SHORING EXAMPLES 5

    EXAMPLE 4DESIGN OF SHEET PILE WALL WITH COHESIVE SOIL AND

    SURCHARGE LOAD

    Introduction :

    In this example, the surcharge load is merged with the active pressure. It also can be separatedas example 3. Soil 2 below cut line is a cohesive material with cohesion = 500 pcf (F.S.included).

    Question: What is the embedment and maximum bending moment in the pile?

    Calculation:Active pressure above cut:

    1=30, Ka = 0.33, @ 0, P1= Ka q = (0.33)(300) = 0.1 Ksf.

    P2= Ka (q + H) = 0.33 (300 + 122.5 x 12) = 0.485 KsfPassive pressure below cut:

    2= 0, Ka = 0, @ 12, P3= 4c - v = 4(500) - (q + 1H) = 2000 - [300 + 122.5(12)] = 0.23Ksf

    Running Program:For passive pressure input, use Top Pres.= 0.23 and Pres. Slope = 0

    Results:The program shows that the minimum embedment is 41.58 and the pile length is 53.58. Themaximum moment in the pile is 43.2 Kip-ft/ft at 27.3 from the ground surface.

    H = 12

    P3 = 0.23

    P2 = 0.485

    2 = 110 pcf

    2 = 0Cu = 500 psf

    EXAMPLE 4

    1 = 122.5 pcf1 = 30

    o

    =0Cu = 0

    SOIL 1 (LOOSE SAND)

    SOIL 2 (MED. CLAY)

    P1 = 0.1

    q = 300psf

  • 7/24/2019 Sh_exmp Sheet Pile

    6/17

    Civi lTech Software SHORING EXAMPLES 6

    EXAMPLE 5DESIGN OF SHEET PILE WALL WITH DIFFERENTIAL WATER LEVELS

    Introduction:The water level is higher outside of the excavation base. Seepage is allowed to flow through thebottom of the pile. The water pressures of both sides are equal, therefore, the net pressure is

    zero at the bottom of the pile.Question: What is the embedment and maximum bending moment in the pile?

    Calculation:Active pressure above cut:

    = 35, Ka = 0.27, @ 5, P1= Ka(5) = (0.27)(125)(5) = 0.17 Ksf@ 12, P2= (0.27)(125 - 62.4)(12 - 5) + P1= 0.287 Ksf

    Active pressure below cut:

    Pa = Ka = (0.27)(125 - 62.4) = 0.017 KsfPassive pressure below cut:

    = 35, Kp = 6.74, @ = /2, P1=0

    Pp = Kp/F.S. = (6.74)(62.6) /1.5 = 0.281 KsfRunning Program:

    Due to seepage, the net water pressure = 0 at the embedment bottom. Because theembedment depth is unknown, the value can be set 999 to let the program find embedment.(See Chapter 5).

    Results:The program shows that the minimum embedment is 16.8 and the pile length is 28.8. Themaximum moment in the pile is 38.9 Kip-ft/ft at 20 from the ground surface.

    1 = 125 pcf

    1 = 35o

    =/2 (Only for passive)H = 12Water @ 5Seepage @ bottomF. S. = 1.5

    0.2811

    Pw = 0.43

    0.017

    1 The depth is unknown,input 999 in program

    H = 12

    EXAMPLE 5

    5P1 = 0.17

    P2 = 0.28712

  • 7/24/2019 Sh_exmp Sheet Pile

    7/17

    Civi lTech Software SHORING EXAMPLES 7

    EXAMPLE 6DESIGN OF ANCHORED SHEET PILE WALL WITH THE SAME WATER

    LEVEL

    Introduction:

    This example has a 36 deep excavation to which tieback anchors are applied. The water levelsare the same inside and outside of the excavation. Two layers of soil are presented in theexample.

    Question: What is the embedment, anchor force, and maximum bending moment in the pile?

    Calculation:Active pressure above cut:

    1= 34, Ka = 0.28, @ 10, P1= Ka(10) = 0.308 Ksf

    @ 36, P2= P1+ Ka(36-10) = P1+ (0.28)(60)(26) = 0.745 KsfActive pressure below cut:

    2= 34.5, Ka = 0.26, @ 36, P3= Ka[(10) + (26)] = 1.26 [110(10) + 60(26)]= 0.692 Ksf

    Passive pressure below cut:

    2= 34.5, Kp = 6.63, Pp = KpPn = Pp - Pa = (6.63 - 0.26)(65) = 0.414 KsfRunning Program:

    Try input anchor level at 9 from the ground surface.Results:

    The program shows that the minimum embedment is 7.5 and the pile length is 43.5. Themaximum moment in the pile is 68.7 Kip-ft/ft at 26 from the ground surface. The brace force =8.8 K/ft.

    SAND BACK FILL

    = 110 = 60 pcf

    = 34o

    = 0Ka = 0.28

    T

    0.4141

    H = 36

    EXAMPLE 6

    10P1=0.308

    P2=0.745

    P3=0.692

    MEDIUM SAND

    = 65 pcf

    Kp = 6.63

    = 34.5o

    /= 0.4

    Ka = 0.26Kp - Ka = 6.37

    9

  • 7/24/2019 Sh_exmp Sheet Pile

    8/17

    Civi lTech Software SHORING EXAMPLES 8

    EXAMPLE 7DESIGN OF ANCHORED SOLDIER PILE WALL WITH LAGGING

    Introduction: A soldier pile wall is used in this example with one tieback anchor applied for each pile.

    Question: What is the embedment, anchor force, and maximum bending moment in the pile?

    Calculation:Active pressure above cut:

    = 30, Ka = 0.33, @ 12, P1= Ka(12) = 0.485 KsfPassive pressure below cut:

    C = 700 psf, = 0, Ka = 0, @ 12, P2= 4c - v = 4(700) - (122.5)(12) = 1.33 KsfRunning Program:

    Try an anchor level = 5 from the pile top.Results:

    The program shows that the minimum embedment is 1.3 and the pile length is 13.3. Themaximum moment in the pile is 13.2 Kip-ft/ft at 9.3 from the ground surface. Horizontal tiebackforce is 10.6 Kips per pile.

    EXAMPLE 7

    H = 12

    P2 = 1.33

    P1 = 0.485

    2 = 110 pcf

    2 = 0Cu = 700 psf

    1 = 122.5 pcf

    1 = 30o

    =0Cu = 0Ka = 0.33

    LOOSE SAND

    MED. CLAY

    Lagging spacing = 6

    T5

    Pile Dia. = 2

  • 7/24/2019 Sh_exmp Sheet Pile

    9/17

    Civi lTech Software SHORING EXAMPLES 9

    EXAMPLE 8DESIGN OF SHEET PILE WALL WITH TIEBACK ANCHOR

    Introduction:This example has a limited surcharge load. The surcharge pressure from the Lpres program is0.42 Ksf as shown in the figure. The water pressure is similar to the condition in example 5.

    Question: What is the embedment, anchor force, and maximum bending moment in the pile?

    Calculation:Surcharge:Ps = 0.42 KsfWater pressure:

    Pw = w (16 - 8) = (62.4)(8) = 0.499 KsfActive pressure:

    P1= Ka(8) = (0.27)(125)(8) = 0.27 Ksf

    P2= P1+Ka= P1+ (0.27)(125 - 62.4)(7) = 0.388 Ksf

    Pa = Kp= (0.27)(125-62.4) = 0.017 KcfPassive pressure: starting 2 below dredge line

    P3= Kp[(1) +w (1)] = 8.95 [125 + 62.4] = 1.26 Ksf

    Pp = Kp = (8.95)(125 - 62.4) = 0.56 KcfRunning Program:

    Use 999 for the unknown depth. (See Example 5)Results:

    The program shows that the minimum embedment is 5 and the pile length is 20. Themaximum moment in the pile is 17.3 Kip-ft/ft at 12.5 from the ground surface. T = 8.2 Kips.

    T

    0.561

    H = 15

    EXAMPLE 8

    10

    P1 = 0.27

    P2 = 0.39

    P3 =1.26

    = 62.6 pcf

    = 125 pcf

    = 35o

    = /2

    5

    1718

    q

    Ps = 0.42

    8

    16

    Pw = 0.4990.017

    1

    The depth is unknown,input 999 in program

  • 7/24/2019 Sh_exmp Sheet Pile

    10/17

    Civi lTech Software SHORING EXAMPLES 10

    EXAMPLE 9DESIGN OF COFFERDAM WITH TWO BRACES

    Introduction : A cofferdam is designed for a bridge pier excavation. Two braces are used herein.

    Question: What is the embedment, brace force, and maximum bending moment in the pile?

    Calculation:

    Surcharge:Ps = 0.42 KsfWater pressure:

    Pw = w (16 - 8) = (62.4)(8) = 0.499 KsfActive pressure:

    P1= Ka(8) = (0.27)(125)(8) = 0.27 Ksf

    P2= P1+Ka= P1+ (0.27)(125 - 62.4)(7) = 0.388 Ksf

    Pa= Kp= (0.27)(125-62.4) = 0.017 KcfPassive pressure: starting 2 below dredge line

    P3= Kp[(1) + w (1)] =8.95 [125 + 62.4] = 1.26 Ksf

    Pp = Kp= (8.95)(125 - 62.4) = 0.56 KcfRunning Program:

    The condition is the same as in example 8. The maximum movement is significantly reduceddue to two levels of bracing.

    Results:The program shows that the minimum embedment is 4.2 and the pile length is 19.2. Themaximum moment in the pile is 7.8 Kip-ft/ft at 14.1 from the ground surface. T1= 5.3 Kips/ ftand T2=2.9 Kips/ ft.

    T1

    0.51

    H = 15

    EXAMPLE 9

    P1 = 0.27

    P2 = 0.39

    P3 =1.26

    = 62.6 pcf

    = 125 pcf

    = 35o

    = /2

    1718

    q

    Ps = 0.42

    8

    16

    0.01

    1

    T2

    16

    10

    The depth is unknown,input 999 in program

    10

    5

    Pw = 0.499

    Pw = 0

  • 7/24/2019 Sh_exmp Sheet Pile

    11/17

    Civi lTech Software SHORING EXAMPLES 11

    EXAMPLE 10DESIGN OF COFFERDAM WITH THREE BRACES

    Introduction:A cofferdam is designed to support an excavation for a bridge pier. Due to a railroad 6 from thewall, surcharge pressure of 0.42 Ksf is applied. No seepage is allowed below the pile bottom.

    The water pressures at both sides are not equal. The outside pressure is higher than inside.After subtraction of the inside pressure, the net hydraulic pressure is constant below 36.

    Question: What is the embedment, brace force, and maximum bending moment in the pile?

    Calculation:Active pressure above cut:

    = 35, Ka = 0.27, @ 8, P1= Ka(8) = (0.27)(125)(8) = 0.27 Ksf

    @ 35, P2= Ka(35 - 8) + P1= (0.27)(62.6)(27) + 0.27 = 0.724 KsfWater pressure:@ 36, Pw = (36 - 8)(62.4) = 1.747 KsfSurcharge load: (from Lpres program)from 0 to 10, Ps = 0.42 Ksfat 36, Ps = 0

    Active pressure below cut:active pressure slope: Pa = Ka = (0.27)(62.6) = 0.017 KcfNet water pressure:Pw = 1.747 Ksf constantPassive pressure below cut:

    = 35, = /2, Kp = 8.95

    @ 37, P3= Kp(2) = 8.95(62.6)(2) = 0.843 Ksf

    passive pressure slope: Pp = Kp= 8.95(62.6) = 0.56 KcfRunning Program:

    The soil below the excavation base is disturbed. Therefore the passive pressure of the top 2soil below the dredge line is ignored. The input pressure diagram is shown as follows.

    Results:The program shows that the minimum embedment is 8.5 and the pile length is 43.5. Themaximum moment in the pile is 32.4 Kip-ft/ft at 25.2 from the ground surface. T1= 13.6 Kips/ft, T2= 12.6 Kips/ ft, and T3= 16.1 Kips/ ft.

  • 7/24/2019 Sh_exmp Sheet Pile

    12/17

    Civi lTech Software SHORING EXAMPLES 12

    T1

    0.561

    H = 35

    EXAMPLE 10

    P1 = 0.27

    P2 = 0.46

    P3 =1.26

    = 62.6 pcf

    = 125 pcf

    = 35o

    = /2

    37

    36

    Surcharge q

    Ps = 0.42

    8

    36

    Pw = 1.7470.017

    1

    T2

    36

    10

    19

    10

    T331

    Cancel out

  • 7/24/2019 Sh_exmp Sheet Pile

    13/17

    Civi lTech Software SHORING EXAMPLES 13

    EXAMPLE 11DESIGN OF TIEBACK WALL

    Introduction:The tieback wall has an 8 spacing of soldier pile supported by timber lagging (3 x 12). Theactive pressure diagram is a trapezoid. The surcharge load of 2 of soil is added to the active

    diagram. The soldier pile has a 2 diameter shaft. Below the dredge line, the active pressure isacting on one diameter. The passive pressure is acting on two diameters of pile due to thearching effect.

    Question: What is the embedment, tieback force, and maximum bending moment in the pile?

    Calculation:The soil report of this project requires 20(H + 2) for active pressure and ignoring the top 2 ofpassive pressure. The passive resistance is 400 pcf including F.S.

    Above base 8 spacingActive pressure P2 = P3 = 20(H + 2) = 20(30 + 2) = 0.64 Ksf

    Below baseActive pressure P4 = 30(Z + 2) = 30(30 + 2) = 0.96 Ksf

    Active pressure slope Pa = 0.03 KcfActing 1 diameter of pile. Diameter of pile = 2.

    Passive pressure slope Pp = 0.4 KcfActing 2 diameter of pile. Diameter of pile = 2.

    Running Program:Use 3 pressure programs to input the active pressure

    Results:The program shows that the minimum embedment is 6.7 and the pile length is 36.7. Themaximum moment in the pile is 49.7 Kip-ft at 27.1 from the ground surface. T 1= 44.7Kips, T2= 45.1Kips, T3= 42.9Kips.

    P4 = 0.96

    Acting 2 Dia. of Pile = 4 Acting 1 Dia. Of Pile = 2

    0.41

    H = 30

    EXAMPLE 11

    P1 = 0.04

    0.4.Y

    Surcharge = 2 (Height of Soil)

    P2 = 0.64

    1

    32

    0.2 H = 6

    Lagging Spacing = 8

    0.03 X + 2

    P3 = 0.640.2 H = 6

    22

    14

    5.5

    22

    T1

    T2

    T3

  • 7/24/2019 Sh_exmp Sheet Pile

    14/17

    Civi lTech Software SHORING EXAMPLES 14

    EXAMPLE 12DESIGN OF ANCHORED AND RACKING BRACED WALL

    Introduction:The original design using one level of tieback is not adequate to support the wall. An additionalraking brace is added to help the stability of the wall.

    Question: What is the embedment, brace force, and maximum bending moment in the pile?

    Calculation:Active pressure above exc. 20(H) = 20(30) = 0.6 Ksf Acting 8Active below exc. 30(Y) = 30(30) = 0.6 Ksf Acting 2 (diameter of pile)Passive below exc. 400Y Acting 4 (2 diameter of pile)Diameter of pile = 2 Lagging spacing = 8Surcharge as shown Ps = 0.36

    Running Program:The program only calculates the horizontal bracing force. The user has to calculate the verticalforce and the total force based on the horizontal force calculations.

    Results:The program shows that the minimum embedment is 5.8 and the pile length is 35.8. Themaximum moment in the pile is 128.6 Kip-ft at 24 from the ground surface. T 1= 61.3 Kips, T2=

    71.1 Kips. The force is in brace = 50 /Sin 45= 70.7 Kips.

    0.4

    1

    H = 30

    EXAMPLE 12

    P1 = 0.6

    Ps = 0.36

    0.0675

    Surcharge

    P2 = 0.6

    0.03

    1

    36

    0.2 H = 6

    Lagging Spacing = 8

    45o

    P3 = 0.9

    0.2 H = 6

    30

    6

    17

    4

    T2

    T1

  • 7/24/2019 Sh_exmp Sheet Pile

    15/17

    Civi lTech Software SHORING EXAMPLES 15

    EXAMPLE 13DESIGN OF BRACED CUT WITHOUT EMBEDMENT

    Introduction :For trench excavation, sometimes the supporting system only uses steel plates, swale, andbraces. The steel plates do not penetrate into the ground. The program also can solve these

    types of problems. The program also can be applied for trench box excavation for pipelines.This example uses three level of braces for a 20 cut. To check the stability problem, the heaveprogram can be used.

    Question: What is the bracing force?

    Calculation:

    Active pressure: = 30 Ka = 0.33

    P1= 0.65 KaH = (0.65)(0.33)(120) 20 = 0.51 KsfRunning Program:

    In the program output on page 2, check the bottom which will indicate the shoring wall withoutbracing.

    Results:Brace @ 3.7 T1 = 2.64k/ ft

    Brace @ 10 T2 = 2.87k/ ftBrace @ 16.3 T3 = 2.64k/ ftMaximum moment in plate: 2 Kip-ft/ft

    EXAMPLE 13

    P1= 0.51

    0.2 H = 4

    = 120pcf = 30

    o

    0.2 H = 4

    H = 20

  • 7/24/2019 Sh_exmp Sheet Pile

    16/17

    Civi lTech Software SHORING EXAMPLES 16

    EXAMPLE 14DESIGN OF SHEET PILE WALL, POUR SEAL AT BOTTOM

    Introduction:Sometimes the bottom of the excavation is sealed to prevent water and heave. In this case, twoways can be used for inputting the concrete seal. 1) Use a brace at the level of the seal. Note:

    the depth of the brace cannot be equal to the depth of the excavation. 0.5 to 1.0 is requiredabove the excavation level as the input of this example. 2) In the passive pressure input, use alarge value of Pres. Top and Pres. Slope. However, if the value is too large, the program cannotfunction. Trial and error is required.

    Question: What is the embedment and maximum bending moment in the pile?

    Calculation:Active: P1= 650 psf

    Water: Pw= w(25 - 10) = 62.4 (15) = 936psfPassive: Pp = 300 pcfConcrete seal was poured at bottom of excavation, then dewater to excavation base.Sheet pile spacing (width) = 1

    Running Program:

    Results:The program shows that the minimum embedment is 3.7 and the pile length is 28.7. Themaximum moment in pile is 11.7 Kip-ft/ft at 18 from the ground surface. T1=5.8 Kips/ ft,T2=5.8 Kips/ ft, and T3=4.2 Kips/ ft. T3 is the concrete seal. If the seal is 2 thick, thecompression stress is 175 psi.

    T1

    0.3

    1

    25

    EXAMPLE 14

    CONCRETE SEAL, 2 THICK

    P1= 0.65

    10

    Cancel out

    Pw = 0.936

    T2

    T3

    4

    12

    24

  • 7/24/2019 Sh_exmp Sheet Pile

    17/17

    Civi lTech Software SHORING EXAMPLES 17

    EXAMPLE 15DESIGN OF DEEP EXCAVATION USING MULTI-TIEBACK WALL

    Introduction:This is a real project in Seattle area. The excavation is 60 below ground. The lagging spacing is6. 7 levels of tiebacks are used. Vertical spacings of tiebacks need to be adjusted for a

    minimum moment in piles and smaller reaction force in tieback. The program proves easy inputinterface, so the user can change the depth of each tieback and run the program several timesto get an optimum result.

    Question: What is the embedment, tieback force and maximum bending moment in the pile?

    Calculation:

    Active: Above Base P1 = 0.65 KaH = (0.65)(0.28)(125)(60) = 1.365 ksf

    Below Base P2 = KaH = (0.28)(125)(60)= 2.1 ksf

    Pa = Ka= (0.28)(125) = 0.035 kcf

    Passive: Below Base Pp = Kp= 6.74 (130) = 0.876 kcf

    Surcharge 0-10, Ps1 = 0.64 ksf; >10, Ps2 = 0.24 ksfRunning Program:

    Results:The output results are shown in the following:

    = 125 pcf

    = 34o

    ka = 0.28

    13.3

    0.8761

    H = 60

    EXAMPLE 15

    Lagging Spacing = 6

    P1= 1.365

    0.035

    Ps2 = 0.24

    Ps1= 0.64

    50

    = 130 pcf

    = 35o

    =/2kp = 6.74

    42.6

    5.5

    35.3

    20.6

    28.0

    2

    Acting 2 Dia. of pile = 4. Acting 1 Dia. of pile = 2

    Surcharge

    48

    12

    P2 = 2.1

    701