shield wire

Upload: anane-ntoso

Post on 06-Apr-2018

220 views

Category:

Documents


1 download

TRANSCRIPT

  • 8/3/2019 Shield Wire

    1/36

    THE SHIELD WIRE POWER SCHEME(SWS)

    EXPECTATIONS

  • 8/3/2019 Shield Wire

    2/36

    THE SHIELD WIRE POWER SCHEME(SWS)

    Learning Objectives:By the end of this Program, theparticipants should be able to;

    1. Describe accurately using schematics,the 4 Shield Wire Power DistributionSchemes (SWS).

    2. Identify specifically the type of schemeadopted for various SW communities inthe NED operational areas.

  • 8/3/2019 Shield Wire

    3/36

    Learning Objectives, contd:3. Identify all major components used in

    the SWS and their functions.

    4. Identify all potential dangers associatedwith the operation of the scheme andhow to mitigate them during operations

    and maintenance.5. Adopt Shield Wire Equipment on

    Conventional Schemes and vice versa.

    6. Operate and maintain Safely the SWSs.

    THE SHIELD WIRE POWER SCHEME(SWS)

  • 8/3/2019 Shield Wire

    4/36

    What is the Shield Wire Power Scheme?

    The technique of using the Sky/ShieldWire to transmit power for distribution of3-phase and single-phase power tosmaller communities along the High

    Voltage Transmission Lines in VRA.

    THE SHIELD WIRE POWER SCHEME(SWS)

  • 8/3/2019 Shield Wire

    5/36

    THE SKY/SHIELD WIRE

    What is a Shield Wire and how is ashield wire normally connected?

    What are the uses of Shield Wires?

    Protection of Power Lines againstLightning discharges

    Mechanical Protection for Fibre OpticCables for Communication and SCADASystems.

    Insulated at the Towers to carr Power

    http://hyperlink%20pictures/SkyWire%20Presentation.ppthttp://hyperlink%20pictures/SkyWire%20Presentation.ppt
  • 8/3/2019 Shield Wire

    6/36

    THE CONCEPT OF SWSSky/Shield wires are insulated at Towers and

    energised at the substations nearest to thecommunities to be served. They are:

    Insulated for medium voltage operation.

    Energised at 20-34kV from HV/MV sub-station. Supplies loads using earth return current.

    Supply loads by means of distribution transformersbranched between the shield wires or wire(s) and

    ground. Still performs power line protection with appropriate

    Arcing Horns.

    With no additional environmental impact.

    http://hyperlink%20pictures/Insulated%20Skywire%20Presentation.ppthttp://hyperlink%20pictures/Arcing%20Horns%20Presentation.ppthttp://hyperlink%20pictures/Arcing%20Horns%20Presentation.ppthttp://hyperlink%20pictures/Arcing%20Horns%20Presentation.ppthttp://hyperlink%20pictures/Insulated%20Skywire%20Presentation.ppt
  • 8/3/2019 Shield Wire

    7/36

    The History The citizens of small communities living near HV

    transmission lines who had no supply made it a

    Corporate Social Responsibility and PublicRelations issue for VRA.

    VRA invited Prof. Iliceto in early 1980s to makeinnovative proposals for a Low Cost solution to

    serve the settlements near its 161kVtransmission lines.

    BACKGROUND AND MOTIVATIONOF SWS

    http://cost%20consideration.ppt/http://cost%20consideration.ppt/
  • 8/3/2019 Shield Wire

    8/36

    Shield Wire Scheme (SWS) is proposed &implemented on the Cape Coast TakoradiTransmission Line

    The cost of SWS is only a fraction of standard MVline.

    The operational performance of the SWS in termsof outage frequency and time is better than normal.

    BACKGROUND AND MOTIVATIONOF SWS

  • 8/3/2019 Shield Wire

    9/36

    Savings and Benefits

    Installation Costs are lower because: Common usage of conductors & grounding rods.

    Does not add to the power line right-of-way.

    Operational Performance is better as: Outage rates are low & permanent faults are rare.

    Low medium voltage losses due to conductor size.

    Maintenance burden is extremely low.

    Other Benefits.

    Community protection of the transmission line.

  • 8/3/2019 Shield Wire

    10/36

    Cost Comparison:MV vrs SWS

    Insulators Insulators

    Steel

    Lattice

    Towers

    Survey &

    Civil Works

    Conductors

    Accessories

    0

    5,000

    10,000

    15,000

    20,000

    25,000

    30,000

    MV Line SWS

    US$perkm

  • 8/3/2019 Shield Wire

    11/36

    MV Line SWS Comment

    Acquisition of Right-of-Way Variable - Depends on local conditions.

    Survey &

    Civil Works4,500 -

    Steel Lattice Towers 7,500 750 Increase in erection only

    Conductors 10,000 -

    Insulators 2,500 3,000

    Accessories 500 -

    Total Cost per kilometer 25,000 3,750 Saving = 85%

    Typical Construction Cost of 34.5 kV line in US $ per km)

  • 8/3/2019 Shield Wire

    12/36

    The massive extension of the HV grid to thenorth in the late 80s presented anopportunity to deploy SWS on the new lines.

    SWS cost is only 15% of equivalent MV line.Yet its operational performance is superior. SWS is now proven technology which

    supplies settlements within a 20km corridor

    of the transmission line at very reasonablecost. Adopted in many African countries and

    beyond.

    TRANSFER OF SUCCESS

  • 8/3/2019 Shield Wire

    13/36

    THE SWS DEVELOPED

    Currently four schemes developed are asshown A, B, C and D in Fig 1 below which are:

    SWSA - Single-Phase Earth-Return Scheme

    SWSB - Single-Phase Metallic-Return Scheme

    SWSC - V (Open Delta) Scheme

    SWSD - 3-Phase () Scheme.

  • 8/3/2019 Shield Wire

    14/36

  • 8/3/2019 Shield Wire

    15/36

    SWS A (in Fig. 1) Single-Phase Earth-Return Schemefeasible for HV line protected by one shield wire.

    I61/34.5/11kV

    Tm

    I61/34.5/11kV

    Tm

    http://hyperlink%20pictures/Towers%20Presentation.ppthttp://hyperlink%20pictures/Towers%20Presentation.ppt
  • 8/3/2019 Shield Wire

    16/36

    SWS B (in Fig. 1) Single-Phase Metallic-ReturnScheme feasible for HV line protected by Two shield

    wires.

    I61/34.5/11kV

    Tm

    http://hyperlink%20pictures/Towers%20Presentation.ppthttp://hyperlink%20pictures/Towers%20Presentation.ppthttp://hyperlink%20pictures/Towers%20Presentation.ppthttp://hyperlink%20pictures/Towers%20Presentation.ppthttp://hyperlink%20pictures/Towers%20Presentation.ppthttp://hyperlink%20pictures/Towers%20Presentation.ppt
  • 8/3/2019 Shield Wire

    17/36

    SWS C (in Fig. 1) The V (Open-Delta) Schemefeasible for HV line protected by Two shield wires.

    They can supply limited amount of 3-phase loads.

    161/34.5 /11kV

    Tm

    http://hyperlink%20pictures/V%20Scheme%20Trafo%20Presentation.ppthttp://hyperlink%20pictures/V%20Scheme%20Trafo%20Presentation.ppthttp://hyperlink%20pictures/V%20Scheme%20Trafo%20Presentation.ppthttp://hyperlink%20pictures/V%20Scheme%20Trafo%20Presentation.ppthttp://hyperlink%20pictures/V%20Scheme%20Trafo%20Presentation.ppt
  • 8/3/2019 Shield Wire

    18/36

    SWS D (in Fig. 1) The (Delta) Scheme feasible forHV line protected by Two shield wires.

    They can supply 100% 3-phase loads.

    I61/34.5/11kV

    Tm

    http://hyperlink%20pictures/D%20Scheme%20Trafo%20Presentation.ppthttp://hyperlink%20pictures/D%20Scheme%20Trafo%20Presentation.ppthttp://hyperlink%20pictures/D%20Scheme%20Trafo%20Presentation.ppthttp://hyperlink%20pictures/D%20Scheme%20Trafo%20Presentation.ppthttp://hyperlink%20pictures/D%20Scheme%20Trafo%20Presentation.ppthttp://hyperlink%20pictures/D%20Scheme%20Trafo%20Presentation.ppt
  • 8/3/2019 Shield Wire

    19/36

    THE APPLICATION

    SWS in NED AreasFig. 6Table 1

    http://hyperlink%20pictures/FIG%206.dochttp://hyperlink%20pictures/Table%201.dochttp://hyperlink%20pictures/Table%201.dochttp://hyperlink%20pictures/FIG%206.doc
  • 8/3/2019 Shield Wire

    20/36

    Single Phase Earth Return (In Fig. 1 A).

    3-phase Earth Return (In Fig. 1 C & D) by usingthe earth return as the 3rd phase conductor, a 3-

    phase MV line is realised (D in Fig. 1)

    Fig. 2 shows the typical independent multipleearthing systems for the earth return of current and

    for safety of MV and LV networks.

    In the HV/MV substations supplying the SWS, thestation ground mat is used for earth return of

    current.

    THE EARTH RETURN OF CURRENT

  • 8/3/2019 Shield Wire

    21/36

    EARTHING OF MV AND LV NETWORKS

    Fig 2

  • 8/3/2019 Shield Wire

    22/36

    EARTHING OF MV AND LV NETWORKS

    Fig. 2 shows the typical independent multiple

    earthing system for the earth return of current andfor safety of MV and LV networks.MV Earth Return is achieved by burying andconnecting a bare conductor between the 161kV

    steel pylon and the 34.5kV take off steel pylon orthe 161kV pylon and a ground/earth electrodeunder the wooden pole serve as the ground for thesystem.The Earth-Return wire is connected to thisground and multiple grounded to the general massof earth at every 2 wooden poles interval for the

    20kV/30kV transmission.

  • 8/3/2019 Shield Wire

    23/36

    EARTHING OF MV AND LV NETWORKS

    At the MV/LV Transformer Station 3

    independent Grounding systems areprovided (Ref. Distribution NetworkEarthing Arrangement Drawing No

    A/EAR/01 07) which are:

    1.MV Grounding System2.Surge/Lightning Arrestor Grounding System

    3.LV Neutral/Grounding System

  • 8/3/2019 Shield Wire

    24/36

    EARTHING OF MV AND LV NETWORKS

    1.MV Grounding System: This comprises ofMV Multiple grounded Earth return

    Conductor

    The Transformer MV Ground TerminalThe Metalworks (Non Current carrying parts)

    of the Substation

    Earth Electrode

  • 8/3/2019 Shield Wire

    25/36

    EARTHING OF MV AND LV NETWORKS

    2. Surge/Lightning Arrestors Grounding

    System. This comprises of:

    The Ground Terminal of the Surge Arrestors

    Ground /Earthing Lead

    Ground Electrode.

    The Two electrodes are buried at the MV/LVtransformer station three meters deep, and atleast four meters away from each other.

  • 8/3/2019 Shield Wire

    26/36

    EARTHING OF MV AND LV NETWORKS

    3. LV Neutral/Grounding System:Consists of:

    The Neutral/Grounding Feeder Wire

    The Transformer Neutral/Ground TerminalMultiple rods along the LV feeders at 4 pole

    intervals.

    Transformer LV neutral electrode buried onepole span away from the MV/LV station.

  • 8/3/2019 Shield Wire

    27/36

    Scheme A - Single Phase Earth Return

    The Shield Wire Line (SWL) = 34.5kV/3=19.92kV or 20kV.The Transformer HV Side = 34.5kV/3=19.92kV or 20kV.The Transformer LV Side:=240V phase toGround, 480V phase to phase

    Scheme B - Single Phase Metal Return.The Shield Wire Line (SWL) = 34.5kV.The Transformer HV Side: = 34.5kV.The Transformer LV Side:= 240V phase to

    Ground, 480V phase to phase.

    VOLTAGE LEVELS OF THE SWS

  • 8/3/2019 Shield Wire

    28/36

    Scheme C The V Scheme (3-phase Open Delta)The Shield Wire Line (SWL) = 34.5kV.The Transformer HV Side: = 34.5kV, phase to phase,20kV phase to ground

    The Transformer LV Side: 240V phase to Ground, 415Vphase to phase

    Scheme D - 3-phase Close Delta SWL (In Fig. 1 D).The Shield Wire Line (SWL). = 30kV

    The Transformer HV Side: 30kV, phase to phase, 30kVphase to groundThe Transformer LV Side: 433V, phase to phase, 240Vphase to ground

    VOLTAGE LEVELS OF THE SWS

  • 8/3/2019 Shield Wire

    29/36

    Questions:1.Explain the differences between the SWS

    Transformers and Conventional MV/LV

    Transformers.

    2.Can a Shield Wire Transformer be used ona Conventional MV Network? Explain

    3.Can a Conventional MV/LV Transformerbe used on a Shield Wire MV/LV Network?

    Explain.

    VOLTAGE LEVELS OF THE SWS

  • 8/3/2019 Shield Wire

    30/36

    Insulators used on SWLs are either3-String for 20kV Lines and 4-Stringfor 30kV Lines.

    Surge/ Lightning Arrestors 48kVand 60kV

    VOLTAGE LEVELS OF THE SWS

    MTCE & TESTING OF SWS

  • 8/3/2019 Shield Wire

    31/36

    Inspection,Maintenance,Testing procedure and,

    Calculation of results forConventional Transformers apply toSWS Transformers as well. (check

    Nameplate Information)

    MTCE & TESTING OF SWSTRANSFORMERS

  • 8/3/2019 Shield Wire

    32/36

    Energised StateVoltage LevelsLimit of Approach

    Isolated StateCapacitorsInduced Voltages

    SAFETY CONSIDERATIONS

    COMPONENTS OF THE SWS AND THEIR

  • 8/3/2019 Shield Wire

    33/36

    The Main Transformer (HV/MV)Feeder Circuit BreakersInterposing TransformerCompensating Resistor-Reactor

    Grounding SwitchThe Shield/Sky WiresInsulatorsInsulator Arcing HornsCapacitorsSurge/ Lightning ArrestorsThe Distribution Transformers (MV/LV)

    Grounded Neutral

    COMPONENTS OF THE SWS AND THEIRFUNCTIONS

  • 8/3/2019 Shield Wire

    34/36

  • 8/3/2019 Shield Wire

    35/36

    TAP

    POSITIONPRIMARY

    VOLTAGE SECONDARY VOLTAGE1. 21,0002. 20,5003. 20,000 250 0- 2504. 19,5005.

    19,000

    TRANSFORMER TAP CHANGING

  • 8/3/2019 Shield Wire

    36/36

    Points for ConsiderationThere is only one Voltage available at terminals

    of Transformer.(Check Incoming Voltage to knowTap to be connected to.)Tap Voltages are to be considered as number ofTurns (V is proportional T ie connect more voltageto where more turns are.)

    Primary Voltage Per Turn is equal to SecondaryVoltage per Turn (V/Tp = V/Ts or N1/N2 = V1/V2i.e. Secondary Voltage is inversely proportional to

    P i T )

    TRANSFORMER TAP CHANGING