siemens tip application manual part 3 for high-rise buildings

44
Application Manual – Planning of a High-rise Building Answers for industry. Totally Integrated Power

Upload: ykt3

Post on 10-May-2017

261 views

Category:

Documents


15 download

TRANSCRIPT

Page 1: Siemens TIP Application Manual Part 3 for High-rise Buildings

Application Manual – Planning of a High-rise Building

Answers for industry.

Totally Integrated Power

Page 2: Siemens TIP Application Manual Part 3 for High-rise Buildings
Page 3: Siemens TIP Application Manual Part 3 for High-rise Buildings

Introduction

The demands placed on a modern high-rise building are constantly

increasing. A high level of safety, flexibility throughout the entire

life cycle, a low level of environmental pollution, the integration of

renewable energies and low costs are common demands nowadays

that already have to be taken into consideration during the planning

of a high-rise building. A special challenge is the coordination of the

individual installations. The main installations are, for example, heat-

ing, ventilation, air conditioning and refrigeration, fire protection,

protection against burglary, building control system and power distri-

bution. In modern planning, the demands on a high-rise building are

not simply split up among the individual installations, but have to be

coordinated. An optimum solution is created from the networking of

the individual requirements. This manual provides an overview of the

most important installations in a high-rise building and describes the

planning of the power distribution as an example.

Page 4: Siemens TIP Application Manual Part 3 for High-rise Buildings

Contents

1 Planning Tasks when Erecting a High-rise Office Building . . . . . . . . . . . . . . . . . . . . . 5

1.1 Total Building Solutions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6

1.2 Building Automation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6

1.3 Fire Protection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7

1.4 Alarm and Evacuation Systems . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7

1.5 Fire Extinguishing Systems . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7

1.6 Planned Security . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8

1.7 Robbery and Burglar Alarm Systems . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8

1.7.1 Electronic Robbery and Burglar Alarm Systems . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9

1.7.2 Video Surveillance Systems . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9

1.7.3 Time Management and Access Control Systems . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9

1.8 Automated Room Control . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10

1.9 Power Management . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10

1.10 Power Distribution . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11

2 Planning of the Power Distribution – Design Example . . . . . . . . . . . . . . . . . . . . . . . 13

2.1 Specifications (Excerpt from the Project Description) . . . . . . . . . . . . . . . . . . . . . . . . . . . 14

2.1.1 General Specifications . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14

2.1.2 Specifications for the Floors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15

2.1.3 Specifications for the Occupied Areas . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15

2.2 Power Demand Estimate . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17

2.3 Schematic Power Supply Concept . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18

2.4 Detailed Power Demand Calculation (Installed Capacity) . . . . . . . . . . . . . . . . . . . . . . . . 20

2.5 Power Distribution Components . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24

2.5.1 General Power Supply (GPS) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24

2.5.2 Standby Power Supply . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26

2.5.3 Further Components and Installations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27

2.6 Power System Considerations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28

2.6.1 Power Supply Systems according to the Type of Connection to Ground . . . . . . . . . . . . 28

2.6.2 Selectivity in Low-Voltage Systems . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29

2.7 The Main Components of the Power Distribution System in Detail . . . . . . . . . . . . . . . . 30

2.8 Performance Specification of Power Distribution (Excerpt) . . . . . . . . . . . . . . . . . . . . . . 38

Your Siemens Contact Partners . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 41

Contacts for Special Interests . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 41

Trademarks, Imprint . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 42

Page 5: Siemens TIP Application Manual Part 3 for High-rise Buildings

Planning Tasks when Erecting a High-rise Office Building

Chapter 1

Page 6: Siemens TIP Application Manual Part 3 for High-rise Buildings

6 Totally Integrated Power by Siemens

1 Planning Tasks when Erecting a High-rise Offi ce Building

zones, entire floors and the complete building, even across groups of distributed buildings and campuses.

Buildings are responsible for around 40% of the world’s power consumption. With Directive 2002/91/EC, Energy Performance of Buildings Directive, EPBD, the European Union is trying to improve the energy efficiency of proper-ties. Amongst the most important measures specified are the creation of an energy certificate for buildings (or energy ‘passport’) and the determination of minimum requirements for buildings.

The components of the building automation systems are evaluated with regard to their effect on the energy con-sumption of buildings with the new standard EN 15232, “Energy Performance of Buildings – Effects of the Building Automation and the Building Management”.

In accordance with the new standard, building automation systems (BAS) are divided into four different performance classes (Fig. 1-1).

Class D corresponds to BAS systems that are not energy-efficient; buildings with such systems have to be modernized, new buildings may not be equipped with these systems.

Class C corresponds to the average BAS system requirements currently in use.

Class B designates BAS systems that have been developed further, with better functionality than ‘standard’.

Class A applies to highly efficient BAS systems.

The greatest potential for the optimization of a project is during the planning phase. At this stage, the course is set for additional costs and cost increases which may incur during the erection and subsequent use of the building. Compared to conventional planning, integrated planning continually improves the cost-benefit ratio. When tackling complex tasks, integrated planning takes the synergies of coordinated, intelligent, integrated systems and products from a single supplier into account and implements them in cost-effective solutions. Interfacing and elaborate har-monization of different systems and products becomes obsolete.

1.1 Total Building Solutions

Total Building Solutions establish a balance between the requirements for safety and security of people and prop-erty and the desire for ease-of-use and problem-free oper-ation. The result is a highly automated, intelligent build-ing, designed for the entire life cycle of the property. In its requirements and structures, the Total Building Solution refers to the Technical Building Management (TBM) disci-plines.

These customized solutions comprise:

A central building control system

Security and personnel control systems

Control of heating, ventilation, air conditioning and refrigeration

Automated room and zone controls

Power distribution

Fire protection

Protection against burglary and intrusion

Access control

Surveillance systems (CCTV and video)

Lighting systems

Integration of third-party systems

Display of alarms and building data

1.2 Building Automation

Building automation means the comprehensive solutions and services required in the open-loop and closed-loop control of the heating, ventilation, air conditioning, light-ing and blinds as well as the integration of the power distribution to selected building services elements. Build-ing automation can be applied to individual rooms and

Fig. 1-1: Performance classes of the building automation systems according to EN 1523

Page 7: Siemens TIP Application Manual Part 3 for High-rise Buildings

7Totally Integrated Power by Siemens

This new standard also contains procedures for the calcula-tion of energy performance by means of user profiles for various complex building types:

Offices, hotels

Classrooms

Auditoriums

Restaurants

Retail centers

Hospitals

Combinations of these standard elements provide clear specifications of how to achieve a certain performance class.

1.3 Fire Protection

Fire requires an initial ignition and then oxygen to keep burning. Therefore, wherever people live and work, there is always a danger of fire. Constructional measures alone are not sufficient to prevent the initial ignition turning into a real fire. For this reason, effective fire protection is essential. Effective fire protection is in place when the following two conditions are satisfied. Firstly, the fire must be detected quickly and clearly and signaled. And secondly, the correct measures must be implemented as quickly as possible. This is the only way to avoid direct fire and conse-quential damage or at least to keep this to a minimum.

Optimally coordinated fire detection, alarm, evacuation and fire extinguishing systems are more effective than separate solutions. The fire protection system can also be easily integrated with a management system in a larger security concept with intrusion protection, access control and video surveillance. This results in the creation of a comprehensive hazard management. Integration in the building control system and the associated intelligent interaction result in a more effective protection of people, property and the environment.

The fire detection system

Intelligent, high-speed evaluation models of advanced fire detection systems such as the SINTESO detectors with ASA (advanced signal analysis) technology enable smoke and fire to be detected immediately and clearly, no matter how difficult the environmental conditions. These detectors can be programmed optimally for the conditions at the loca-tion of use.

The alarm and evacuation system

The effectiveness of clear and unequivocal communication during a crisis situation is also of prime importance in the fire protection. An electro-acoustical or speech-controlled alarm and evacuation system has proven to be the best solution in all cases. Unique fire alarm signals, reassuring behavior rules and clear instructions help to avoid panic breaking out.

The fire extinguishing system

Each application requires a suitable extinguisher. Whether powder, wet, foam or a combination of these extinguishing systems: a fire extinguishing strategy that has been worked out individually and tailor-made not only protects your building, but also the environment when a fire breaks out.

1.4 Alarm and Evacuation Systems

The right information at the right time, at the right place! The ideal equipment for this is an electro-acoustical emer-gency alarm system with speech commands. It enables quick, sensible responses thus providing optimum safety. Rapid evacuation saves lives.

In addition to the prompt detection of the fire, quick and orderly evacuation of the building is of prime importance to save lives. Especially with regard to the changed court rulings on compensation claims, the evacuation is playing an increasingly important role. In tall buildings such as hotels, banks or administration buildings, or in buildings with a large number of visitors such as shopping centers, universities and cinemas, efficient evacuation is of prime importance. The following general rule applies: the faster the evacuation, the greater the chance of survival. How-ever, it is most important that panic does not break out amongst the users or residents of the building. This is best achieved with reassuring information and clear instruc-tions.

It is therefore best when a fire alarm occurs that spoken messages are used for the evacuation. Spoken instructions via loudspeakers are clear, they are understood and fol-lowed. This greatly increases the chances for people to save themselves. For this reason, speech-controlled alarm systems are an ideal complement to fire alarm systems in all buildings.

1.5 Fire Extinguishing Systems

Time as a safety factor: An important element in fire prevention is the time between fire detection and interven-tion. The shorter this time that be kept, the less the imme-diate damage and the consequential damage.

Intervention at an early stage: A fire extinguishing system cannot prevent a fire starting. However, with prompt detection, it can extinguish a fire when it is still small. Especially in buildings where there are special risks (expensive property, high downtime costs, etc.), this is of invaluable, existential importance.

The basis for this is quick and clear detection so that fire sources are detected and located immediately. Depending on the situation, the correct intervention is started at the right time.

Page 8: Siemens TIP Application Manual Part 3 for High-rise Buildings

8 Totally Integrated Power by Siemens

Successful extinguishing of the fire: As an automatic fire extinguishing system represents the optimum initial inter-vention method in most cases, Siemens supplies a coordi-nated range of extinguishing systems. Adapted to the respective field of application (risk and target of protec-tion), each of these systems provides optimum protection. The comprehensive range of extinguishing equipment also ensures that the quickest and best effect is achieved, suited to the situation in each special case (Fig. 1-2).

1.6 Planned Security

There is a great potential for risk – terrorism and extrem-ism, environmental catastrophes, fire, robbery, burglary and spying, theft and vandalism. These risks have to be identified and analyzed and the appropriate security con-cepts have to be developed (Fig. 1-3).

Prevention, intervention and rescue measures can be implemented for many of these risks within the framework of the legal standards and guidelines. The aim is to make the future more secure through defined risk management. This means investment for companies, but also benefits: transparency, confidence of members of staff and business partners, improvement in the company image, increase of the credit ranking and clarity about the risk situation.

Risk identificationDefinition of value-added areas

Consideration of the macro environment

Analysis of weak points

Risk determination

Analysis of effects

Risk assessment According to effect and probability

Quantitative evaluations

Representation of a risk portfolio

Risk measures Organizational measures, e.g. a crisis management organization

Technical measures such as the introduction of security equipment and systems

Risk controlling

In addition to activities that are your personal responsibil-ity, Siemens also offers “extended services” – a wide range of services that support a holistic risk control for the prop-erty or building.

1.7 Robbery and Burglar Alarm Systems

The necessity to protect people, property and other values against violence and theft was never as great as at present. The subject of security is increasingly becoming an impor-tant economic factor. Therefore, reasonable provisions for the protection of people, the safeguarding of property or irreplaceable objects of value are especially important. Modern risk management takes account of these points.

Four security aspects

Naivety and carelessness help burglars just as much as inadequate security measures. Therefore, protection must be both passive and active: passive through mechanical protection equipment and active with an electronic alarm system. The additional observance of simple security rules and the necessary everyday prudence are another signifi-cant contribution to minimize the risk. Optimum protection of people and buildings is based on the following four pillars:

1. Prudence as free-of-charge protection2. Mechanical protection equipment as the first line of

defense3. Electronic robbery and burglar alarm systems for the

reliable detection of dangers4. Forwarding of alarms for the immediate notification of

personnel providing assistance

Fig. 1-2: Stages during a fire

Fig. 1-3: Risk management

Page 9: Siemens TIP Application Manual Part 3 for High-rise Buildings

9Totally Integrated Power by Siemens

1.7.1 Electronic Robbery and Burglar Alarm Systems

The crucial question is: is an alarm system decisive for risk management? The following factors must be taken into consideration when answering this question:

Origin of the risks: are these only external risks, e.g. through intruders, or do they also occur within the building, e.g. through employees or visitors?

Objects of value on the property (cash, jewelry and works of art, high-quality production goods and systems, sensitive data, etc.)?

The location of the object to be protected: busy or quiet area?

Risk of vandalism: what does the social environment look like?

Danger of extremism: is there a danger of specific acts of sabotage?

The consequences of burglaries, such as operational down-times, the loss of customer data and the possible resulting damage, must also be taken into consideration. The deci-sive benefit of an alarm system is the protection against the established risks and the minimization or total preven-tion of injury to people or damage to property. This is only possible with the aid of an active security system that immediately sets off an alarm in an emergency situation and also notifies the offices providing assistance.

An electronic system has decisive advantages compared to purely mechanical protection measures. For example, it already detects the first attempt at a break-in and immedi-ately notifies the required security staff. This is not the case with purely mechanical building protection. If not detected, a burglar could make any number of attempts to overcome the mechanical protection measures. If you also consider that mechanical protection measures often can-not be used with modern building components, such as glass doors or special lightweight construction elements, then an active security system is frequently the only alter-native.

We recommend a sensible mixture of mechanical and electronic protection. The more time it takes to break in, the more time the notified security team has to intervene. The burglar also has much less time in the building, which can significantly reduce the possible damage.

1.7.2 Video Surveillance Systems

In sophisticated security concepts, the video system pro-vides the visual basis for decisions and plays a central role – in addition to the real-time monitoring of critical areas – in the identification of persons with the aid of biometric processes, and in the detection of dangers.

Mobile video systems

Whether for the monitoring of external installations, live coordination of service personnel or the management of

mobile business activities, the high-speed availability of data and images is a task performed by mobile multimedia monitoring systems. Numerous detectors and cameras are grouped around a mobile digital system that can store multimedia information and quickly pass this on via mod-ern communication networks.

Stationary digital room surveillance

Stationary systems are used for specific room surveillance using the existing IT infrastructures. These systems detect changes and monitor various alarm zones. If an alarm is triggered, the video sequences are recorded digitally and forwarded to higher-level management systems.

Recording of alarm situations

Video surveillance not only detects incidents, but docu-ments the entire process when an incident occurs – from the recording of the video images, the transmission and storage of this information, the initiation of automatic measures through to the centralized data evaluation and archiving.

Video control centers

The communication between the video system and the control center is performed using TCP/IP via any Ethernet, ATM or TN network structure. In conjunction with a Video Web Client, operation, control and access is possible from anywhere in the world.

1.7.3 Time Management and Access Control Systems

Last not least, the future of a company is also a question of the security technology and therefore, the right technol-ogy for access control. The aim is to qualify access authori-zation and at the same time flexibly adapt the authentica-tion of persons to the individual corporate requirements, as well as to be able to individually configure access rights both geographically and chronologically.

The above requirements can only be resolved with the aid of modern systems for access control. Therefore, open system solutions with flexible networks are required. They are only configured under consideration of the intended use of the building and the organization involved. Its special structures and the specific workflows also have an effect. Factors such as the size of the company, the num-ber of people, doors, elevator and access gate control as well as additional functions also have to be taken into account.

Future-oriented solutions include not only the linking of business management applications, but also the integra-tion of other security systems. When linked to the building management systems, the information can also be opti-mally used under energy performance aspects.

Page 10: Siemens TIP Application Manual Part 3 for High-rise Buildings

10 Totally Integrated Power by Siemens

1.8 Automated Room Control

Modern automated room control concepts provide inte-grated solutions for the air conditioning, lighting and blinds control as an important precondition for the well-being and performance capability of those using the room. Switches and regulators in various designs, which satisfy individual requirements and architectural demands, are available for the operation of all room functions.

Communicative systems should be used that satisfy the requirements of EN 15232 for a Class A building. Open communication protocols such as LON or KNX/EIB in accor-dance with EN 50090 satisfy this requirement. A further advantage of such systems is the ease they can be ex-tended with or flexibly adapted for various types of use.

1.9 Power Management

High supply and operational reliability and flexible use are the key factors of every modern power distribution. With the energy costs making up a greater share of the total operating costs of the building, optimization of the operat-ing costs through an ecological and economically efficient optimization of the energy and energy costs is an abso-lutely essential goal, which already has to be taken into consideration during the planning.

Only when all the components of the power distribution system have been optimally matched, is it possible to

guarantee a reliable and profitable power distribution, which is beneficial throughout the entire life cycle of the building. A power management system has the following objectives:

Continuous monitoring:

Automatic, time-related recording, monitoring and archiving of status and measurement data, power consumers

Increase in the transparency through visualization of the power flow/consumption within the building, from the point of supply to the final load circuit

Analysis of the energy values:

Analyses of the energy data/flow and provision for further processes

Identification of potential for improvement and savings for the purpose of energy cost optimization

Correct allocation of the energy consumption quanti-ties and costs according to utilization and consumer

Technical and organizational measures:

Optimization and reduction of the energy consumption and costs

Support for purposeful diagnostics and maintenance

In order to sustain the energy performance of a building permanently at a high level, accompanying services are required during the operational phase in order to con-tinuously adapt automation strategies to the changes in use.

Fig. 1-4: Operational view of the power distribution

Page 11: Siemens TIP Application Manual Part 3 for High-rise Buildings

11Totally Integrated Power by Siemens

Power management system

The power management system is based on the opera-tional level in a building, focusing on power supply and includes the functional layers:

Acquisition for status analysis and measurements

Processing level for the data acquisition (Fig. 1-4)

Operator control and monitoring with visualization, archiving, reports, control of switchgear, status monitoring / measuring points

In order to command of optimum purchase/consumption quantities records during the utilization phase, the required measuring points and the power distribution components to be monitored must be planned and configured at an early stage. Specific room assignments and the fact that this can change must be taken into account.

The following outlines some of the reasons for the imple-mentation of a power management system:

Quick and simple online overview of the states of the power flow/consumption in the building

Validity check of the recorded values, avoidance of reading errors

Optimization of the purchasing contracts adjusted to the individual consumption shares

More precise specification and more economical power consumption through exact knowledge of the demand profile

Transparency of costs in the energy sector

Benchmarking

1.10 Power Distribution

Nowadays the investment costs are of prime importance when planning power supply systems. But the operating and energy costs should not be neglected either, as they can have a sustained effect on the overall cost balance over the period of utilization.

The electrical planning engineers therefore have the respon-sibility of designing power supply systems with operational reliability and energy performance in mind. Their service ren-dered must correspond to the generally accepted rules of good practice. This means that various implementing regula-tions, administrative regulations, relevant standards (IEC, EN, DIN), general legal building test certificates and the general legal building approvals must be taken into account during the planning phase, not only for a specific installation but across all installations involved.

Support for these increasingly complex tasks during planning is provided by solution approaches such as Totally Integrated Power (TIP), which facilitates the plan-ning tasks with integrated solutions and efficient engi-neering tools.

Standards and regulations

When planning and erecting buildings, many standards, regulations and guidelines must be observed and complied with in addition to the explicit specifications made by the building and plant operator (e.g. factory regulations) and the responsible power distribution network operator. These standards and regulations vary from country to country and depend on the location of the building.

Power demand

With regard to the power supply, the most important task is the estimation of the required power. In order to attain a high level of efficiency, the components should work with a utilization of 70–80% of the maximum power: undersiz-ing causes malfunctions, while oversizing results in excess costs.

Network structure and supply sources

The network structure is determined by the requirements resulting from the building’s use. In line with the specifica-tions made by the installation company and the intended use of the building, the required power must be distributed between different sources of supply. If redundancy is a system requirement, an additional reserve must be consid-ered in the planning.

Besides the demand to be met by the general power supply (GPS), the power quantity required from a safe and reliable source of supply must also be estimated. This power de-mand is divided between the redundant power supply (RPS) and the uninterruptible power supply (UPS). The redundant power supply (RPS) is also operated via the second system input from the UPS as a standby system when the general power supply has failed. In addition, the power requirements of safety equipment (DIN VDE 0100-710, DIN VDE 0100-718) to be supplied by the safety power supply system (SPS) must be considered. The di-mensioning of the individual components results from the estimate of the power quantities required and their alloca-tion to different sources of supply.

Electric utilities rooms

Besides the correct dimensioning of the components, another essential planning aspect is the specification of the size and location of the utilities rooms required for the power supply. The dimensions of these utilities rooms depend on the dimensions of the components required and the relevant safety regulations.

Boundary conditions such as room ventilation, ceiling loads and access ways for moving items must also be taken into consideration when drawing up room and building plans. Over-dimensioned rooms reduce the economic efficiency of a building (room utilization). Under-dimen-sioned rooms may hinder the implementation of a certain technical solution or, at least force the use of expensive custom solutions for the technology applied.

Page 12: Siemens TIP Application Manual Part 3 for High-rise Buildings
Page 13: Siemens TIP Application Manual Part 3 for High-rise Buildings

Planning of the Power Distribution – Design Example

Chapter 2

Page 14: Siemens TIP Application Manual Part 3 for High-rise Buildings

14 Totally Integrated Power by Siemens

2 Planning of the Power Distribution – Design Example

The dimensioning software SIMARIS design provides assis-tance for the dimensioning process. The result of the dimensioning process is the specification of the switching and protective devices as a function of the individual connection distances. When all the components of the power distribution system have been planned, this plan-ning must be incorporated in the tender specification.

2.1 Specifi cations (Excerpt from the Project Description)

For a high-rise office building with shopping arcade in Berlin, Germany, the power supply has to be planned for a 10-story building (12 floors) with a floor area of approx. 25 m x 60 m.

There is a car park for customers in front of the building, the access way to the parking garage (levels -1 to -3 for employees) and a fountain (80 m x 20 m). (Fig. 2-1)

Real floor area approx. 1350 m2 (14 levels + technical equipment on roof level).

Floor heights of levels 00 to +10: 4 m, levels -1 to -3: 3 m

The valid rules and regulations have to be observed.

2.1.1 General Specifi cations

The level of building installations, equipment and furnish-ing should represent an average standard of innovation and comfort.

Emphasis should be placed on energy savings. Single-room control and presence signaling should be provided.

A fire alarm system, video surveillance of the traffic routes, the parking garage, the shopping arcade and the outside area as well as an access control system have to be planned.

The building has external shutters.

The media supply is via two utilities hubs that contain the elevators, staircases, electrical distribution boards, ventila-tion and other media.

Within the levels, the supply routing is in the ceiling.

The power distribution in a high-rise office building is considered in this chapter from the first planning steps to the creation of the specifications of work and services. The required planning steps are shown and explained using an example.

The specifications of the owner/developer with regard to the use of the building must be implemented when plan-ning the power distribution. The supply concept is created taking into account the rules and regulations valid for the building location. The main components are then dimen-sioned. Depending on the supply concept, the consump-tion for the general power supply (GPS), the safety power supply (SPS) and the uninterruptible power supply (UPS) must be determined separately. The expected separate consumptions must be weighted with the associated simultaneity factor (SF) and added up.

The technical data of the components results from the determined energy consumption. The architect can derive important information for the required space and access ways from the technical data and the requirements set by the owner/developer. In addition to the component dimen-sions, pressure relief and ventilation are also important for the correct dimensioning of the rooms.

The power distribution system is then dimensioned in the next planning step. Dimensioning is the rating of all the equipment and components that are to be used within the electrical network. Protection against overload, short-circuit and electric shock as well as the static/dynamic voltage drop and the static/dynamic selectivity are taken into consideration.

Fig. 2-1: Top view of the estate and the building

Page 15: Siemens TIP Application Manual Part 3 for High-rise Buildings

15Totally Integrated Power by Siemens

2.1.2 Specifi cations for the Floors

Level 00: The following stores and businesses have been planned for level 00: bakery, travel agency, bank, dry cleaners and jeweler.

The power consumption is to be assigned to the individual stores.

On level 00 there is also a doctor, a day nursery, the mail center as well as the reception, the control center and the fire alarm center.

Levels +1 to +9: The PC workplaces with telephone and communication network are on levels +1 to +9. The workplaces have individual lighting and general lighting (daylight-dependent) The IT server room is on level +5.

Level +10: Executive floor with conference rooms and briefing rooms as well as a kitchen (120 m2) and cafeteria (750 m2).

Levels -1 to -3: Underground car park including control system; 10% of parking lots reserved for women.

Outside area with decorative lighting.

2.1.3 Specifi cations for the Occupied Areas

Office areas (levels +1 to +10): General: fire alarm system

Suspended ceiling with integrated lighting

Installation systems in window sill / workplace floor-ceiling column

PC workplace, telephone, communication network (printer …)

Individual lighting and general lighting, dimmed depending on daylight

Individual room control (ventilation, air conditioning)

Presence signaling (office hours)

External shutter control

Communication routes (all levels): General: video surveillance, fire alarm system

Suspended ceiling with integrated lighting

Stores (level 00): General: video surveillance, fire alarm system

Bakery (2/3 salesroom and 1/3 backrooms)

Travel agency (2/3 salesroom and 1/3 storeroom, kitchen / lavatories)

Bank (2/3 salesroom and 1/3 storeroom / safe / lavatories), security system

Dry cleaner’s (1/3 salesroom and 2/3 backrooms)

Jeweler (2/3 salesroom and 1/3 backrooms), security system

Underground parking garage (levels -1 to -3): General: video surveillance, access control, fire alarm system

Car park control system

Surface-mounted lighting, parking lots reserved for women (10%)

Utilities rooms (levels -1, 00, 5, roof): General: video surveillance, fire alarm system

Medium-voltage switchgear: false floor

Transformers

Low-voltage switchgear: false floor

Diesel backup system

Battery system

UPS system

Refrigeration technology

Ventilation

Sprinkler system

Conference rooms, presentation (level +10): General: fire alarm system

Video conference, presentation system (beamer …)

Telephone, communication network (printer …)

Sanitary facilities (all levels): General: fire alarm system

Storage area (all levels): General: fire alarm system

Fig. 2-2: Ground plan of a model office, double workplace

Page 16: Siemens TIP Application Manual Part 3 for High-rise Buildings

16 Totally Integrated Power by Siemens

IT server room (level +5): General: video surveillance, access control, fire alarm system

Kitchen / cafeteria (level +10): General: video surveillance, fire alarm system

Utilities hubs (all levels): General: video surveillance, fire alarm system

Elevators:

2 x passenger elevators

1 x restaurant/freight elevator

Staircase

Electrical installations: distribution cabinet room (GPS/SPS), rising main busbars

Ventilation, air conditioning, media

Garbage/refuse: 30 m2

Mail center (level 00): General: video surveillance, fire alarm system

Doctor (level 00): General: access control, fire alarm system

1 x waiting room: 18 m2

2 x changing rooms: each 2 m2

2 x consulting rooms: each 15 m2

1 x archive room: 10 m2

1 x laboratory: 12 m2

2 x lavatory: each 9 m2

1 x hallway/reception: 18 m2

Recreation area / kitchenette (all levels): General: fire alarm system

Reception / control center /fire alarm center (level 00): General: video surveillance, access control, fire alarm system

Day nursery (level 00): General: fire alarm system

Sleeping area: 20 m2

Play area: 25 m2

Creativity area: 40 m2

Kitchen: 6 m2

Lavatories: 2 x 9 m2

Changing room / cloakroom: 6 m2

Outside area: General: video surveillance

Lighting: decorative

Fig. 2-3: Ground plan of the utilities hubs

Page 17: Siemens TIP Application Manual Part 3 for High-rise Buildings

17Totally Integrated Power by Siemens

2.2 Power Demand Estimate

Approach: based on W/m2, according to the Application Manual, Basic Data and Preliminary Planning, Chapter 3 Determination and Division of Power Demand.

Parking garage / utilities areas (incl. roof area)

Basement levels -1 to -3 with 1,350 m2 each + utilities areas ca. 210 m2 (areas between utilities hubs), assumed average power demand: 10 W/m2

Calculation: (3 x 1,350 m2 + 210 m2) x 10 W/m2 = 42,600 W

Shopping center / bank

Ground level 00 with 1,350 m2, assumed average power demand: 60 W/m2

Calculation: 1 x 1,350 m2 x 60 W/m2 = 81,000 W

Offices

Levels +1 to +10 with 1,350 m2 each, assumed average power demand: 50 W/m2

Calculation: 10 x 1,350 m2 x 50 W/m2 = 675,000 W

Refrigeration / ventilation

11 levels with 1,350 m2 each, assumed average power demand: 60 W/m2.

Calculation: 11 x 1,350 m2 x 60 W/m2 = 891,000 W

Total power demand

approx. sum: 1,690 kW

Required transformer output

The established total power demand determines the re-quired transformer output. The determination is based on a cos phi = 0.85 and a transformer load level of 70%.

Calculation: 1,690 kW / (0.7 x 0.85) = 2,840 kVA

Building use Average power demand 1)

Simultaneity factor 2)

Comments

Bank 40 – 70 W/m2 0.6

Library 20 – 40 W/m2 0.6

Office 30 – 50 W/m2 0.6

Shopping center 30 – 60 W/m2 0.6

Hotel 30 – 60 W/m2 0.6

Department store 30 – 60 W/m2 0.6

Small hospital (40–80 beds)

250 – 400 W/m2 0.6

Hospital (200–500 beds)

50 – 80 W/m2 0.6 ca. 2,000 W per bed

Warehouse (no cooling)

2 – 20 W/m2 0.6

Cold store 500 – 1,500 W/m2 0.6 Upper values for deep-freeze store

Apartment complex (without night storage/continuous-flow water heater)

10 – 30 W/m2 0.6

Museum 60 – 80 W/m2 0.6

Parking garage 3 – 10 W/m2 0.6

Production plant 30 – 80 W/m2 0.6

Data center 500 – 2,000 W/m2 1.0

School 10 – 30 W/m2 0.6

Gym hall 15 – 30 W/m2 0.6

Stadium (40,000–80,000 seats)

70 – 120 W/seat 0.6

Old people’s home 15 – 30 W/m2 0.6

Greenhouse (artifical lighting)

250 – 500 W/m2

1) The values specified here are guidelines for demand estimation and cannot substitute precise power demand analysis.2) The simultaneity factor (SF) is a guideline for preliminary planning and must be adapted for individual projects.

Fig. 2-4: Average power demand for buildings according to their type of use

Page 18: Siemens TIP Application Manual Part 3 for High-rise Buildings

18 Totally Integrated Power by Siemens

2.3 Schematic Power Supply Concept

The following aspects should be taken into consideration when designing electric power distribution systems:

Operational simplification due to clear and straightforward network configuration

Low cost for power losses, e.g. by medium-voltage network-side power transmission to the load centers

High reliability of supply and a high degree of operational safety for the plant even in the event of faulted items of equipment (standby power, selectivity, i.e. fault-discriminating system protection, and high availability)

Easy adjustment to changing load and operating conditions

Low operating costs thanks to maintenance-friendly equipment

Sufficient power transmission capacity of equipment both under normal and fault operating conditions

Good power supply quality, i.e. low voltage fluctuations owing to load fluctuations at a sufficient level of voltage symmetry and low harmonic content in the voltage

Compliance with applicable standards and project-related rules for special installations

Please also refer to the Application Manual, Basic Data and Preliminary Planning, Chapter 4 Power Distribution Plan-ning in Commercial, Institutional and Industrial Buildings, high-rise building type 3.

Fig. 2-5: Schematic power supply concept for a high-rise building

Page 19: Siemens TIP Application Manual Part 3 for High-rise Buildings

19Totally Integrated Power by Siemens

Building type High-rise building

Number of floors 10 to 20

Ground area / total area 1,000 m2 / ≤ 20,000 m2

Segmentation of power required

80% utilized area20% side area

Power required ≥ 1,500 kW; for 2 MW or higher, a relocation of the transformers should be considered even if the number of floors is less than 10

Supply types 100% total power from the public grid10–30% of total power for safety power supply (SPS)5–20% of total power for uninterruptible power supply (UPS)

Power system protection Selectivity is aimed at

Special requirements Good electromagnetic compatibilityHigh safety of supply and operation

Feature Our solution Advantage Your benefit

Network configurationSmax = 1,800 kVAcos phi = 0.85Floors: 20

Splitting into two supply sections

2 transformer modules with (2 + 1) x 630 kVA Ukr = 6%, i.e. Ik ≤ 45 kA

Short LV cables, low power losses, reduction of fire load

Economical, eased fire protection

Voltage stability, lighter design

Optimized voltage quality, economical

Redundant supply unit:– Generator 800 kVA (30%)

(the smaller the generator, the greater the short-circuit current must be compared to the nominal current)

– UPS: 400 kVA (15%)

Supply of important consumers on all floors in the event of a fault, e.g. during power failure of the public grid

Increased safety of supply

Safety power supply Safety power supply acc. to DIN VDE 0108 Part 718

Supply of sensitive or important consumers

Uninterruptible power supply during power failure of the public grid

Radial network Transparent structure Easy operation and fault localization

Medium-voltage supply station

SF6 gas-insulated Small switchgear station, independent of climate

Minimized space requirements for utilities room; no maintenance

Transformer GEAFOL cast-resin with reduced losses

Low fire load, indoor installation

Economical

Low-voltage main distribution

SIVACON with central grounding point –> splitting of PEN in PE and N to the TN-S system (4-pole switches in the feeding lines and at the changeover point)

EMC-friendly power system Protection of telecommunications equipment from interference (e.g. lower transmission rates for communication lines)

Wiring / main route

Cables Central measurements of current, voltage, power, e.g. for billing, centrally per floor in LVMD

Central data processing

Fig. 2-6: Proposal for concept finding

Page 20: Siemens TIP Application Manual Part 3 for High-rise Buildings

20 Totally Integrated Power by Siemens

Lighting:

In accordance with the Application Manual, Part 2 Draft Planning, Appendix A6 “Table of Nominal Illuminance” and Section 9.2.3 Light between the Priorities of Energy Effi-ciency and Light Quality.

Lighting of offices / kitchen:

For a rated illuminance of 500 lx and a ceiling height of 3 m, an installed capacity of 30 W/m2 is assumed.

Lighting of individual stores:

For a rated illuminance of 300 lx and a ceiling height of 3 m, an installed capacity of 17 W/m2 is assumed.

Lighting of traffic areas / utilities / parking lots:

For a rated illuminance of 100 lx and a ceiling height of 3 m, an installed capacity of 6 W/m2 is assumed.

Lighting of cafeteria / lavatories:

For a rated illuminance of 200 lx and a ceiling height of 3 m, an installed capacity of 11 W/m2 is assumed.

Other areas:

For a rated illuminance of 200 lx and a ceiling height of 3 m, an installed capacity of 11 W/m2 is assumed.

Other loads: Office, 2-person workplace, power outlets 0.8 kW

Office, 6-person workplace, power outlets 2.4 kW

Elevators for 3 floors 9 kW

Sprinkler pump 30 kW

Central battery 8 kW

Fan-assisted oven, bakery 10 kW

Kitchen/restaurant 40 kW

Kitchenettes on every floor; 11 floors at 3 kW 33 kW

Lavatory, hand-dryers, 20 units at 2 kW 40 kW

IT server room 55 kW

Gas extinguishing system 3 kW

Kitchen 150 kW

Ventilation, air conditioning, 80 W/m2

(office area, 10 levels at 1,350 m2) 1,080 kW

Elevators 22.3 kW

Smoke extraction, 2 x 10 kW 20 kW

Gutter heating 70 kW

Other loads (photocopiers, small equipment …) ca. 10 kW per level 110 kW

Type of indoor area or activity Nominal illuminance En (lx) Comments

1. General areas

1.1 Traffic zones in storerooms 50

1.2 Storage areas

1.2.1 Storage areas for similar or large-unit goods 50

1.2.2 Storage areas with search requirements for non-similar storage goods 100

1.2.3 Storage areas with reading requirements 200

1.3 Automatic high-rack warehouse

1.3.1 Corridors 2

1.3.2 Operator station 200

1.4 Dispatch center 200

1.5 Recreational, sanitary and medical care facilities

1.5.1 Canteens 200 Atmospheric lighting, possibly incandescent lamps

1.5.2 Other recreational rooms and resting areas 100

1.5.3 Rooms for physical exercise 300

1.5.4 Changing rooms 100

1.5.5 Washing rooms 100 Possibly additional illumination of mirrors

1.5.6 Lavatories 100

1.5.7 Medical rooms, rooms for first aid and medical care 500

1.6 Building services, utilities

Fig. 2-7: Table of nominal illuminance (continued)

2.4 Detailed Power Demand Calculation (Installed Capacity)

Page 21: Siemens TIP Application Manual Part 3 for High-rise Buildings

21Totally Integrated Power by Siemens

Type of indoor area or activity Nominal illuminance En (lx) Comments

1.6.1 Machine rooms 100

1.6.2 Power supply and distribution 100

1.6.3 Telex, post room 500

1.6.4 Telephone operator 30

2. Traffic routes inside buildings

2.1 For people 50

2.2 For people and vehicles 100 Adjustment of nominal illuminance to adjacent areas: En1 ≥ 0.1 En2 where:En1 = En of the traffic routesEn2 = En of adjacent areas

2.3 Stairs, moving escalators and inclined traffic routes 100

2.4 Loading platforms 100

2.5 Automatic conveyor systems or belts in the vicinity of traffic routes 100

2.6 Gateway areas

2.6.1 For day shift (min. 400 lx) 2 x En

2.6.2 For night shift 0.5 En to 0.2 En

3. Offices and similar rooms

3.1 Office rooms with daylight-oriented workplaces only in the immediate vicinity of windows

300 Workplace-oriented general lighting, at the workplace at least 0.8 En

3.2 Office rooms 500

3.3 Open-plan offices – high level of reflection – medium reflection

7501,000

High levels of reflexion: ceilings with min. 0.7, walls/partitions min. 0.5. Single-user lamps useful.

3.4 Technical drawing 750 En referred to a typical position of the drawing board of 70 ° towards the horizontal plane; in the center 1.2 m high

3.5 Conference and meeting rooms 300

3.6 Reception rooms 10

3.7 Areas with access to the public 200

3.8 Areas for data processing 500

16 Wholesale and retail trades

16.1 Shops 300

16.2 Cashier’ s desks 500

Fig. 2-7: Table of nominal illuminance (continued)

Nominal illuminance (lx)

Installed power/base area of the room (W/m2)

Lights approx. 2 m above the area to be illuminated

Lights approx. 3 m above the area to be illuminated

Lights approx. 4 m above the area to be illuminated

1,000 50 60 64

750 38 45 48

500 25 30 32

300 15 17 19

200 10 11 13

Fig. 2-8: Nominal illuminance subject to the installed power/m2 when using fluorescent lamps

Page 22: Siemens TIP Application Manual Part 3 for High-rise Buildings

22 Totally Integrated Power by Siemens

Resulting power demand:

General power supply (GPS)

Required transformer output 2,754 kVASelected transformer capacity (4 x 800 kVA) 3,200 kVA

Safety power supply (SPS)

Required generator output 766 kVASelected generator capacity 800 kVA

Area Lighting Loads of which supplied by:

Level Room assignment Description

No. of items

Room (m2)

Total (m2)

Illum.(lx)

Power (W/m2)

Power total (W)

SF* Power eff. (W)

Description Power(W)

SF* Power eff. (W)

SPS (W)

UPS (W)

-3 Parking lots 60 11 660 100 6 3,960 0.6 2,376 Lifting gear 3,000 0.3 900 900

and Utilities hub 2 56 112 100 6 672 0.6 403 Power outlets 2,000 0.2 400

-2 Traffic area 578 100 6 3,468 0.6 2,081 Other 5,000 0.3 1,500

-1 Parking lots 40 11 440 100 6 2,640 0.6 1,584 Lifting gear 3,000 0.3 900 900

Utilities hub 2 56 112 100 6 672 0.6 403 Power outlets 2,000 0.2 400

Sprinkler center 1 60 60 100 6 360 0.6 216 Sprinkler pump 30,000 1 30,000 30,000

Diesel unit / SPS 1 50 50 100 6 300 0.6 180 Central battery 8,000 1 8,000 8,000

Medium voltage 1 20 20 100 6 120 0.1 12 Other 5,000 0.3 1,500 500

Low voltage 1 40 40 100 6 240 0.1 24

Transformers 2 8 16 100 6 96 0.1 10

Traffic area 628 100 6 3,768 0.6 2,261

00 Shops and stores

Bakery 1 50 50 300 17 850 0.8 680 Fan-assisted oven 10,000 0.3 3,000

Travel agency 1 50 50 300 17 850 0.8 680 Power outlets 35,000 0.6 21,000 2,000

Bank 1 200 200 300 17 3,400 0.8 2,720Video, office equipment

10,000 0.3 3,000

Jeweler 1 50 50 300 17 850 0.8 680Kitchen / restaurant

40,000 0.6 24,000

Dry-cleaner’s 1 30 30 300 17 510 0.8 408 Hand-dryers 4,000 0.2 800

Restaurant 1 70 70 200 11 770 0.8 616 Kitchenettes 3,000 0.3 900

Lavatories 4 9 36 200 11 396 0.6 238 Laboratory 2,000 0.6 1,200 1,200

Storeroom 2 30 60 200 11 660 0.3 198Control system, reception ...

3,000 1 3,000

Utilities hub 2 56 112 100 6 672 0.1 67 Other 10,000 0.3 3,000 1,000

Garbage/refuse 1 50 50 100 6 300 0.1 30

Mail center 1 25 25 500 30 750 0.8 600

Doctor‘s practice 1 120 120 300 17 2,040 0.8 1,632

Rec, area / kitchenette

1 14 14 200 11 154 0.3 46

Reception 1 40 40 500 30 1,200 0.8 960

Control center 1 15 15 500 30 450 0.6 270

Fire alarm / communic,

1 12 12 100 6 72 0.1 7

Day nursery 1 115 115 200 11 1,265 0.8 1,012

Traffic area 301 100 6 1,806 0.6 1,084

+1 Offices

to 2-person

workplace40 20 800 500 30 24,000 0.8 19,200 Power outlets 36,800 0.8 29,440 28,800

+46-person

workplace2 50 100 500 30 3,000 0.8 2,400 Hand-dryers 4,000 0.2 800

Utilities hub 2 56 112 100 6 672 0.1 67 Kitchenettes 3,000 0.3 900

Rec, area / kitchenette

2 14 28 200 11 308 0.3 92 Other 10,000 0.3 3,000 1,000

Copier / storage area

4 6 24 100 6 144 0.3 43

Lavatories 4 9 36 200 11 396 0.6 238

Traffic area 250 100 6 1,500 0.6 900

+5 Offices

2-person workplace

38 20 760 500 30 22,800 0.8 18,240 Power outlets 36,800 0.8 29,440 28,800

6-person workplace

2 50 100 500 30 3,000 0.8 2,400 Hand-dryers 4,000 0.2 800

Utilities hub 2 56 112 100 6 672 0.1 67 Kitchenettes 3,000 0.3 900

IT server room 1 40 40 500 30 1,200 0.8 960 IT server room 55,000 0.8 44,000 55,000 55,000

Fig. 2-9: Summary of power demand (continued)

Page 23: Siemens TIP Application Manual Part 3 for High-rise Buildings

23Totally Integrated Power by Siemens

Uninterruptible power supply (UPS)

Required output 92 kVASelected capacity 100 kVA

Area Lighting Loads of which supplied by:

Level Room assignment Description

No. of items

Room (m2)

Total (m2)

Illum.(lx)

Power (W/m2)

Power total (W)

SF* Power eff. (W)

Description Power(W)

SF* Power eff. (W)

SPS (W)

UPS (W)

Rec, area / kitchenette

2 14 28 200 11 1,200 0.3 360Gas extinguishing system

3,000 1 3,000 3,000

Copier / storage area

4 6 24 100 6 308 0.6 185 Other 10,000 0.3 3,000 1,000

Lavatories 4 9 36 200 11 144 0.6 86

Traffic area 250 100 6 396 0.6 238

+6 Offices

to2-person

workplace40 20 800 500 30 24,000 0.8 19,200 Power outlets 36,800 0.8 29,440 28,800

+96-person

workplace2 50 100 500 30 3,000 0.8 2,400 Hand-dryers 4,000 0.2 800

Utilities hub 2 56 112 100 6 672 0.1 67 Kitchenettes 3,000 0.3 900

Rec, area / kitchenette

2 14 28 200 11 308 0.3 92 Other 10,000 0.3 3,000 1,000

Copier / storage area

4 6 24 100 6 144 0.3 43

Lavatories 4 9 36 200 11 396 0.6 238

Traffic area 250 100 6 1,500 0.6 900

+10 Offices

Workplace (Executive)

2 40 80 500 30 2,400 0.8 1,920 Power outlets 10,000 0.8 8,000 8,000

Workplace (Team Assistant)

2 25 50 500 30 1,500 0.8 1,200 Hand-dryers 4,000 0.2 800

Conference room 1 50 50 500 30 1,500 0.4 600 Kitchenettes 3,000 0.3 900 900

Presentation /meeting area

1 150 150 500 30 4,500 0.4 1,800 Kitchen 150,000 0.6 90,000 3,000

Marketing 1 60 60 500 30 1,800 0.8 1,440 Cafeteria 8,000 0.6 4,800 1,000

2-person workplace

4 20 80 500 30 2,400 0.8 1,920 Other 10,000 0.3 3,000 1,000

6-person workplace

2 50 100 500 30 3,000 0.8 2,400

Restaurant

Kitchen 1 50 50 500 30 1,500 0.6 900

Cafetria 1 200 200 200 11 2,200 0.6 1,320

Hospitality 1 30 30 200 11 330 0.6 198

Utilities hub 2 56 112 100 6 672 0.1 67

Rec, area / kitchenette

1 14 14 200 11 154 0.3 46

Copier / storage area

2 6 12 100 6 72 0.3 22

Lavatories 4 9 36 200 11 396 0.6 238

Traffic area 326 100 6 1,956 0.6 1,174

Roof Utilities hub 2 56 112 100 6 672 0.1 67Ventilation / air conditioning …

1,080,000 0.7 756,000 5,000

Utilities center 1 160 160 100 6 960 0.1 96 Elevators 22,300 1 22,300 22,300

MV station 1 8 8 100 6 48 0.1 5 Power outlets 3,000 0.3 900

LV station 1 20 20 100 6 120 0.1 12 Gutter heating 70,000 0.3 21,000 21,000

Transformers 2 4 8 100 6 48 0.1 5 Smoke extraction 20,000 1 20,000 20,000

Other 10,000 0.3 3,000 2,000

Total area 19,224 Total lighting 247,826 Total loads 1,391,260 455,800 55,000

Corresponding to a generator/transformer/UPS output in kVA (load level = 70%. cos phi 0.85):

416,514 2,338,252 766,050 92,437

GPS: total transformer capacity (kVA) 2,754,766

SPS: total generator capacity (kVA) 766,050

* SF = Simultaneity factor UPS: total UPS capacity (kVA) 92,437

Fig. 2-9: Summary of power demand (continued)

Page 24: Siemens TIP Application Manual Part 3 for High-rise Buildings

24 Totally Integrated Power by Siemens

2.5 Power Distribution Components

In the general power supply (GPS), components are fed by load transfer from the medium-voltage system (max. 52 kV) using distribution transformers.

For the standby power supply system, power sources are selected according to the permissible interruption time.

Generators for safety power supply (SPS)

Uninterruptible power supply (UPS) as a static UPS, consisting of a rectifier/inverter unit and battery

2.5.1 General Power Supply (GPS)To be determined by project specifications, or else the Application Manual, Basic Data and Preliminary Planning, Section 5.2 Distribution Transformers.

Medium-voltage switchgear

A gas-insulated medium-voltage switchgear as utilities substation at level -1, and as a substation on the rooftop.

See Application Manual, Basic Data and Preliminary Plan-ning, Section 5.1 Medium-Voltage Switchgear.

Note on product selection:

The gas-insulated Siemens 8DH10 switchgear

requires approx. 30% to 50% less space (depending on the voltage level) compared to air-insulated switchgear

requires no maintenance for life

is highly available, as it requires no maintenance

is not susceptible to environmental and climatic impact,

as all live parts are immersed in gas

permits fast system expansions and panel replacements thanks to its modular design

provides a high degree of operator safety, as the switchgear is encapsulated and arc-fault-tested

requires only small pressure relief openings to provide for accidental arcs, as the pressure increase is only approx. 30% compared to air-insulated switchgear technology

Distribution transformers

Four cast-resin dry-type transformers with 800 kVA each:

2 cast-resin dry-type transformers at level -1

2 cast-resin dry-type transformers on the rooftop

See Application Manual, Basic Data and Preliminary Plan-ning, Section 5.2 Distribution Transformers.

Note on product selection:

Siemens GEAFOL cast-resin dry-type transformers

can be used in any climate (persistent to humidity and tropical conditions, high and low temperatures)

place the lowest requirements on water protection and fire prevention (special rooms, oil tub etc. become obsolete)

require no insulating liquid

emit low noise

are hardly flammable and self-extinguishing

can be recycled

require only a small space for installation

provide up to 50% performance increase when cross-flow fans are installed

Fig. 2-10: 8DH10 medium-voltage switchgear Fig. 2-11: GEAFOL cast-resin dry-type transformer

Page 25: Siemens TIP Application Manual Part 3 for High-rise Buildings

25Totally Integrated Power by Siemens

require no maintenance

are cost-effective thanks to aluminum instead of copper windings

Low-voltage main distribution

A type-tested switchgear assembly (TTA) in compliance with IEC 60439-1, with extended testing of behavior in the event of an accidental arc, as low-voltage main distribution system, installed at basement level -1 and on the rooftop.

See Application Manual, Basic Data and Preliminary Plan-ning, Section 5.3 Low-Voltage Main Distribution.

Note on product selection:

Siemens SIVACON low-voltage switchgear

provides the utmost of plant safety owing to type-tested assemblies

is space saving with an installation area of 400 mm x 500 mm or above

offers a choice as to busbar position (top/rear)

enables cable/busbar connection from the top, bottom or rear

allows a combination of different mounting techniques within one panel

has a switch-test and disconnection position with closed door while maintaining the same degree of protection (max. IP54)

ensures maximum operator safety thanks to an arc-fault-proof locking system

allows flexible adjustments of its inner compartmentalization to customer needs

has a uniform operator interface for all withdrawable units

has a universal hinge for ease of subsequent changes of the door opening (left/right)

has a high-efficiency ventilation system that provides maintenance advantages

presents a high-quality industrial design for seamless integration in modern room concepts

boasts of a worldwide network of SIVACON licensed manufacturing partners that ensure service and system availability

Busbar trunking systems

A busbar trunking system to connect the low-voltage main distribution system to the transformers and for power transmission as rising mains line in the utilities hubs.

See Application Manual, Basic Data and Preliminary Plan-ning, Section 5.4 Busbar Trunking Systems.

Note on product selection:

SENTRON busbar trunking systems by Siemens

have a 20% lower fire load than cables

are easy to install and extend, as they don’t require any sophisticated support constructions

are EMC-friendly

have a low weight (aluminum conductors)

are cost-effective (aluminum instead of copper conductors)

allow straightforward routing of power lines

are comparable to short-circuit-proof cabling; no additional precautions required

provide a high degree of operational safety

are part of the seamless power distribution concept by Siemens, constituting a type-tested unit (transformer/LVMD, LVMD/SD)

Fig. 2-12: SIVACON S8 low-voltage switchgear Fig. 2-13: SENTRON busbar trunking systems

Page 26: Siemens TIP Application Manual Part 3 for High-rise Buildings

26 Totally Integrated Power by Siemens

Subdistribution systems and distribution boards

To ensure reliable power supply of all consumer equip-ment, appropriate subdistribution systems should be provided. Relevant standards, such as IEC 60364-30 and IEC 60364-4-51, must be complied with.

Note on product selection: TTA from end to end (transformer and busbar to LVMD, LVMD, busbar for power distribution, Siemens ALPHA subdistribution boards).

Product range covering all distribution boards from 63 A to 630 A.

The ALPHA SELECT software tool enables fast and easy configuration of the distribution boards (www.siemens.com/alpha-select).

See Application Manual, Draft Planning, Chapter 8 Subdis-tribution Systems.

2.5.2 Standby Power Supply

The standby power supply consists of the safety power supply system (SPS) and the uninterruptible power supply system (UPS).

Generator for safety power supply

To provide for necessary life safety equipment, such as emergency lighting, elevators for firefighters, etc., a diesel generator as standby power supply unit (t ≤ 15 s) is installed in a container on the rooftop; selected rating 800 kVA.

Manufacturer: MTU

See Application Manual, Basic Data and Preliminary Plan-ning, Section 5.7 Standby Power Supply.

Uninterruptible power supply

The requirements of the system integration in accordance with Totally Integrated Power must be satisfied by an (input-side) frequency- and voltage-independent load supply through double-transformer UPS devices (so-called online devices with double-conversion operation). In this context, the distributed use of plug-in devices can be excluded from the planning.

A CE marking in accordance with Directive 73/23/EEC for low-voltage systems and 89/336/EEC for electromagnetic compatibility is required for the operation of UPS devices within the European Community. These regulations have been included in the international standards for safety requirements (IEC 62040-1-1 for operation in easily acces-sible rooms and IEC 62040-1-2 for operation in locked service rooms) as well as in the EMC requirements (IEC 62040-2).

The UPS is installed at level 5 with a rating of 100 kVA (central arrangement in the vicinity of the main consumer (IT). IEC 62040-3 has been considered for rating the UPS. A central, static UPS system with a separate batteries room was chosen; selected rating 100 kVA.

Model: static UPS, consisting of a rectifier/inverter unit and battery

Manufacturer: Masterguard

See Application Manual, Basic Data and Preliminary Plan-ning, Section 5.6 Uninterruptible Power Supply.

Fig. 2-14: ALPHA 160-DIN wall-mounted distribution board

Fig. 2-15: ALPHA 630-DIN floor-mounted distribution board

Page 27: Siemens TIP Application Manual Part 3 for High-rise Buildings

27Totally Integrated Power by Siemens

2.5.3 Further Components and Installations

Automated room control

A building management system is included in the planning to provide integrated room control functions (constant light control, presence signaling, shading, room climate control …).

Manufacturer/type: Siemens / instabus KNX/EIB

For details on the integrated room control functions of Siemens instabus KNX/EIB, please refer to the Application Manual, Draft Planning, Section 10.2 Building Manage-ment System.

Note:

Excerpt from the tender specification:

The following contract items are to be delivered and per-formed as a fully operative KNX/EIB building management system.

All power and control cords required for installation, in-cluding their necessary wiring systems, must be included in the respective tender sections.

The supplier should specify and verify the following by proof:

1. ETS3 license number: ...........................................

2. Reference systems (a minimum of two in the same size as the planned installation):System 1: …………………………….............................System 2: …………………………….............................

3. Proof of certification of the company or staff member from an authorized KNX/EIB training center.

Alternatively, a KNX/EIB service provider may be named. Appropriate proof of certification must also be included.

The following basic requirements are placed on the bus:

1. Sound communication according to KNX/EIB standard (EN 50090 and following DIN VDE 0829), twisted wires with a wire diameter of 0.8 mm.

2. Safe isolation from the power network.

3. Bus cables whose wires have a joint enclosure. As a minimum requirement, the bus cables must be rated for the same test voltage between conductor and cable surface, that also applies to power cables.

Bus cable labeled: YCY 2 x 2 x 0.8 mm², normal design, HCH 2 x 2 x 0.8 mm², halogen-free design. First wire pair for signal transmission and power supply, second wire pair as reserve.

If conventional switch and pushbutton inserts are used, it must be ensured that the rockers can be snapped into the frame as a unit.

To ease installation work for positioning the switch, and in order to compensate for wall clearances, the rockers must be furnished with elongated guide pins and the installation devices with flexible contact lever guides.

The calculation of unit prices must include delivery, instal-lation ready for service, addressing, parameterization, testing and switching works, machine-operated labeling, share of documentation, including handing over of project parameterization on CD-ROM, all additional services, small parts and fixtures, terminals and wiring shares, data bus-bars, bus terminals, and scaffolding up to 3 m.

Leading product: Siemens Switch range: DELTA line,Titanium white

Safety lighting

A safety lighting system consists of the following compo-nents: safety power source, distributors, monitoring de-vices, cabling, luminaires and rescue signs.

Model: CEAG

See Application Manual, Draft Planning, Section 10.4 Safety Lighting Systems.

Note:

Emergency lighting control can be performed by using KNX/EIB and DALI. In this context it is important that the controllers and bus systems for the electrical safety instal-lations be independent of the controllers and bus systems of the building management system. For this purpose, electronic control gear (ECG) with a DALI interface is used in the safety luminaires.

Elevators

Elevators must be chosen with an appropriate load capac-ity for the conveyance of people.

Model: OTIS

See Application Manual, Draft Planning, Section 9.3 Eleva-tor Systems.

Page 28: Siemens TIP Application Manual Part 3 for High-rise Buildings

28 Totally Integrated Power by Siemens

The type of connection to ground of the medium-voltage or low-voltage power system should be selected carefully, as it is crucial for the extent of protective measures to be taken. At the low-voltage side, it also determines the system’s electromagnetic compatibility.

Selected power supply system: TN-S system

See Application Manual, Draft Planning, Section 2.1.2 Power Supply Systems according to the Type of Connection to Ground.

Note on product selection:

Power systems in which electromagnetic interference plays an important part should preferably be configured as TN-S systems immediately downstream of the point of supply. Later, it will mean a comparatively high expense to turn ex-isting TN-C or TN-C/S systems into EMC-compatible sys-tems. The state of the art for TN systems is an EMC-suited design as TN-S system.

Characteristics TN-C TN-C/S TN-S IT system TT system

1 2 3 1 2 3 1 2 3 1 2 3 1 2 3

Low cost of investment

Little expense for system extensions

Any switchgear/protective technology can be used

Ground fault detection can be implemented

Fault currents and impedance conditions in the system can be calculated

Stability of the grounding system

High degree of operational safety

High degree of protection

High degree of shock hazard protection

High degree of fire safety

Automatic disconnection for protection purposes can be implemented

EMC-friendly

Equipment functions maintained in case of 1st ground or enclosure fault

Fault localization during system operation

Reduction of system downtimes by controlled disconnection

1 = true, 2 = conditionally true, 3 = not true

Fig. 2-16: Exemplary quality rating dependent on the power supply system according to its type of connection to ground

2.6 Power System Considerations

2.6.1 Power Supply Systems according to the Type of Connection to Ground

Page 29: Siemens TIP Application Manual Part 3 for High-rise Buildings

29Totally Integrated Power by Siemens

2.6.2 Selectivity in Low-Voltage Systems

Proof of selectivity is required in IEC 60364-7-710 / DIN VDE 100-710 and DIN VDE 0100-718.

See Application Manual, Draft Planning, Section 2.5 Selec-tivity in Low-Voltage Systems.

According to IEC 60947-2, Appendix A, and VDE 660-101, the determination or verification of the desired type of selectivity is divided in two time ranges.

Time range ≥ 100 ms:

The time range above 100 ms can be analyzed by a com-parison of characteristic curves in the L- or S-range. Toler-ances, required protective settings, curve representation in identical scales etc. are to be observed.

Time range < 100 ms:

The standard requires selectivity in this time range to be verified by testing. Due to the fact that the time and cost expense involved is very high, when different devices are used in the power distribution system, selectivity limits can often be obtained from renowned equipment manufactur-

ers only. This is why in practice, let-through currents are often compared to the operating or pick-up currents or, the let-through currents of the protective devices are com-pared to each other.

The prerequisite being that the relevant data is available from the equipment manufacturer and that it is analyzed thoroughly.

In this project, the selectivity was calculated with the aid of the TÜV-certified SIMARIS design dimensioning soft-ware. Components were selected and dimensioned using SIMARIS design.

Note:

A network calculation should always be performed prior to any performance description, forming a basis thereof. Any problems resulting from a wrong device selection/combi-nation/arrangement will thus be detected at an early stage.

Furthermore, a network calculation provides a record of planning reliability with regard to cable cross sections, voltage drop, observance of conditions for disconnection from supply, and the grading distances of protective de-vices.

Fig. 2-17: Example of a system configuration using SIMARIS design 4.1 basic

Page 30: Siemens TIP Application Manual Part 3 for High-rise Buildings

30 Totally Integrated Power by Siemens

2.7 The Main Components of Power Distribution in Detail

Medium voltage

The medium-voltage switchgear was configured using the Profix 8 DH10 configuration software (www.siemens.com/profix).

1 item of switchgear (load transfer from power supply network operators) comprising of:

2 items of load transfer via switch-disconnector including

1 item Cable panel (RK) for wall installation, as transfer or feeder panel, consisting of a switch-discon-nector with manually operated snap-action drive, as three-position switch, with the switch positions “ON-OFF-GROUND” and capacitive voltage indicator, 230 V motorized drive, resis-tance to accidental arcs up to 20 kA

1 item of load transfer via circuit-breaker including

1 item Circuit-breaker panel (CB) for wall installation, as transfer or feeder panel, consisting of a circuit-breaker with manually operated snap-action drive, 1 f-release, 1 auxiliary switch 2NO+2NC+2CO contacts, operating cycle counter and “switch tripped” signaling, plus a switch-disconnector with manually operated snap-action drive, as three-position switch, with the switch positions “ON-OFF-GROUND” and capacitive voltage indicator, as well as a low-voltage cubicle (height 600 mm) with universal terminal bar. Extension for auxiliary switch of the circuit-breaker to 7NO+4NC+2CO contacts. Standard protection system: SIPROTEC 7SJ63 communi-

cation-capable (PROFIBUS), including the necessary current/voltage transformers / trans-ducers and system-related accessories ( con-trol fuse, contactors).

1 item of measuring equipment, designed and equipped as follows

1 item Measuring panel, air-insulated (ME 1), for wall installation, as metering panel for power con-sumption billing, with screwed door (front cover), consisting of a 850 mm wide panel, including mounting and wiring of a maximum of 3 current transformers and 3 voltage transform-ers to be provided by the customer. Busbar grounding via ball connection bolt, 3 grounding fix points at the busbar in the air-insulated metering panel via a ball connection bolt 25 mm

3 items 1-pole cast-resin voltage transformer depending on the voltage level: 24/12 kV 4MR1, 20/10 kV/root3 to 100 or 110 V/root3, 20 VA Class 0.2 / 50 VA Class 0.5. In case of load transfer from power supply network operator: current transformer designed acc. to the network opera-tor’s technical supply conditions.

3 x 1 item Cast-resin current transformer 4MA7 max. 24 kV/16 kA 12 kV/20 kA, 10 VA, 1FS5 or 10P10 selectable from 60 A to 600 A, /1A or /5 A, without approval. In case of load transfer from power supply network operator: current trans-former designed acc. to the network operator’s technical supply conditions.

1 item Resistance to accidental arcs up to 20 kA

1 item Miniature circuit-breaker for voltage transformer g with auxiliary switch

1 item 3VU protective switch for voltage transformer, rated current 3 A, with auxiliary contact switch 1NO+1NC

4 transformer outgoing feeders/feeders via circuit-breakers, designed and equipped as follows

1 item Circuit-breaker panel (CB) for wall installation, as transfer or feeder panel, consisting of a circuit-breaker with manually operated snap-action drive, 1 f-release, 1 auxiliary switch 2NO+2NC+2CO contacts, operating cycle coun-ter and “switch tripped” signaling, plus a switch-disconnector with manually operated snap-action drive, as three-position switch, with the switch positions “ON-OFF-GROUND” and capaci-tive voltage indicator, as well as a low-voltage cubicle (height 600 mm) with universal terminal bar. Motorized drives and protective devices are to be powered by the customer’s own UPS.

1 item Standard protection system: SIPROTEC 7SJ63 communication-capable (PROFIBUS), including the necessary current/voltage transform-

Fig. 2-18: Model configuration of the medium-voltage switchgear using Profix 8DH10

Page 31: Siemens TIP Application Manual Part 3 for High-rise Buildings

31Totally Integrated Power by Siemens

ers / transducers and system-related accessories (control fuse, contactors …).

1 item Resistance to accidental arcs up to 20 kA, 1 s in compliance with DIN VDE 0670-6, IEC 298 with Appendix AA, PEHLA Guideline No.4, Criteria 1 to 6

1 item Miniature circuit-breaker (MCB) for motorized drive or control circuit with auxiliary switch, 230 V AC or DC

1 item Miniature circuit-breaker for voltage transformer g with auxiliary switch

1 item 3VU protective switch for voltage transformer, rated current 3 A, with auxiliary contact switch 1NO+1NC

Transformer

4 items of transformers in cast-resin design with foil winding

Transformer with aluminum foil winding, cast-resin design

Rating: 800 kVA

High voltage: 10 kV, AC50/LI95 (Standard)

Low voltage: 0.400 kV

Impedance voltage: Uz = 6%

Losses: reduced losses

Vector group: Dyn5

Connections: HV and LV connections at the top

Volt switchover option f. HV terminals: No

HV taps: ± 5%

Frequency: 50 Hz

Ambient temperature: 104.00 °F

Degree of protection: IP00, indoor installation

Surface: Normal painting

Degree of protection: IP20

Casing size for degree of protection: 4

Fire protection class: F1

Behavior in the event of fire: Low flammability, self-extinguishing

Test voltage / partial discharge: 2 x Un, discharge < 5 pC

Grounding stud with 25 mm diameter at HV and LV side, temperature sensor for warnings, temperature sensor for tripping, tripping device (230 V AC, 50-60 Hz), 2 sensor loops can be connected, incl. transformer bedding (rail, vibration damper …). Grounding switch 20 kV with rod-ding / angle transmission and handle, necessary control/fusing, cable routes / cable clamping rails and equipotential bonding bar 30 x 10 mm, with six M12 connection bolts.

Manufacturer/type: Siemens/GEAFOL 4GB

4 items of transformers casing for GEAFOL 4GB

Casing for stand-alone installation of GEAFOL cast-resin transformers in electrical operating areas, designed for indoor (IP20) installation.

Busbar trunking system (connection of transformer/LVMD)

Busbar trunking systems must conform to the following technical data as a minimum requirement:

Rated operating current Ie: 1,600/1,250 A

Rated operating voltage Ue: 400 V AC

Degree of protection: IP34

System configuration TN-C system

Voltage drop default: 6%

Ambient temperature: -5 °C / +40 °C

Rated operating current Ie: 1,600 A (horizontal)

Rated operating voltage Ue: 1,000 V AC

Rated short-time withstand current Icw: 80 kA/1 s

Rated peak withstand current Ipk: 176 kA

Number of conductors: 4

Conductor material: aluminum

Surface treatment of busbar: nickel- and tin-plated

Conductor cross section: 706 mm2

PE conductor cross section: 706 mm2

Color of casing: RAL 7035

Casing dimensions: W x H: 240 mm x 180 mm

The busbar trunking system is to be delivered as a com-plete unit including the required connecting and terminat-ing material matching the project-specific system opera-tion. Listed unit prices must also include all costs for project planning, documentation, the coordination of the trunking route with other work contractors/installations and the measurements of system modules to be taken, as well as fastening material and drawing up the final inspec-tion documents.

Besides the quantities listed below, the floor plans and sectional drawings of the entire system are to be consid-ered for project planning and drawing up a tender specifi-cation.

Manufacturer/type: Siemens, SIVACON LDA 342

50 m Trunking units as running meter for 1,600/ 1,250 A without tap-off points for horizontal/vertical installation, including single-bolted connection and fastening brackets. Expansion joints are integrated in the trunking unit. The connections between the individual trunking units must be keyed so that they are mechani-cally secured against reverse polarization.

4 items Transformer connection for the above described busbar trunking system. Rated operating current Ie: 1,600/1,250 A, transformer type: Siemens, GEAFOL 800 kVA.

4 items Connection of the low-voltage main distribution for the above described running meter of busbar trunking system. Rated operating current Ie: 1,600/1,250 A, LVMD type: SIVACON.

Page 32: Siemens TIP Application Manual Part 3 for High-rise Buildings

32 Totally Integrated Power by Siemens

20 items Directional change pieces for above described running meter of busbar trunking system for directional changes of 90°.

4 items Fire protection S90, built into the busbar for routing it through fire wall or fireproof ceiling. Tested acc. to DIN 4102-9, with fire resistance class S90.

Low-voltage main distribution (LVMD)

1 item LV main distribution system (Level -1 and sub-station in the attic). As double-front station (GPS), depth 1,000 mm and single-front station (SPS) depth 600 mm. Delivery, moving into place, mounting and installation ready for service. Instruction of operator personnel.

Comprising:

Plant component for general power supply (double-front station)

4 items Transformer supply (T1 to T4) with air circuit-breaker (ACB), width 800 mm, depth 500 mm, height 2200 mm. The circuit-breaker panel shall be offered as a complete unit with all panel and busbar parts and the following equipment:

1 item SENTRON 3WL circuit-breaker for alternating current in withdrawable unit design, DIN VDE 0660-101, rated insulation voltage 1,000 V AC, 3-pole, time-discriminating grading possible, with guide frame.Rated current: In = 2,000 ARated operational voltage: Ue = 690 V AC, 50/60 HzRated service short-circuit breaking capacity Ics = 65 kA = Icu at 415 V ACPermissible ambient temperature: -25 °C … +70 °CNo derating at an ambient temperature of max. +55 °CDegree of protection IP20Mechanical reclosing lock-out, mechanical switch-on readiness indicator with signaling switch (1NO), auxiliary switch with 2NO and 2NC, replaceable contacts.Temperature monitoring integrated in the switch (measuring points: switch environment, main contacts, electronics in the tripping mod-ule), measured values are supplied to superior control system by means of a COM module, fan control for the LV switchgear. Manual operation and motorized drive with mechanical and electric impulse. Rated operational voltage: Us = 230 V AC with electronic overcurrent release “LSIN”, ETU45Setting current of overload release is indepen-dent of external voltage: Ir = 40 to 100% of In in

5% incrementsManufacturer/type: Siemens/SENTRON L

1 item Multi-functional measuring instrument to be integrated into switchboard with PROFIBUS-DP interface, built-in device 96 mm x 96 mm for the acquisition, direct display and transmission of power system parameters of a low-voltage power distribution system to a central data recording unit. Manufacturer/type: Siemens/SENTRON PAC3200 DP

1 item Coupling panel (T1/T2) with ACB, width 800 mm, depth 500 mm, height 2,200 mm. The circuit-breaker panel shall be offered as a complete unit with all panel and busbar parts and the following equipment:

1 item SENTRON 3WL circuit-breaker for alternating voltage in withdrawable-unit design, DIN VDE 0660-101Rated insulation voltage: 1,000 V AC, 3-pole, time-discriminating grading, with guide frame.Rated current: In = 2000 ARated operational voltage: Ue = 690 V AC, 50/60 Hz Rated service short-circuit breaking capacity Ics = 65 kA = Icu at 415 V AC Permissible ambient temperature: -25 °C to +70 °CNo derating at an ambient temperature of max. +55 °CDegree of protection IP20 Mechanical reclosing lock-out, mechanical switch-on readiness indicator with signaling switch (1NO) auxiliary switch with 2NO and 2NC replaceable contacts.Temperature monitoring integrated in the switch (measuring points: switch environment, main contacts, electronics in the tripping module), measured values are supplied to superior control system by means of a COM module, fan control for the LV switchgear. Manual operation and motorized drive with mechanical and electric impulse.Rated operational voltage: Ue = 230 V AC with electronic overcurrent release “LSIN”, ETU45 independent of external voltage.Setting current of overload release: Ir = 40 to 100% of In in 5% incrementsManufacturer/type: Siemens/SENTRON 3WL

1 item Multi-functional measuring instrument to be integrated into switchboard with PROFIBUS-DP interface, built-in device 96 mm x 96 mm for the acquisition, direct display and transmission of power system parameters of a low-voltage power distribution system to a central data recording unit. Manufacturer/type: Siemens/SENTRON PAC3200 DP

Page 33: Siemens TIP Application Manual Part 3 for High-rise Buildings

33Totally Integrated Power by Siemens

5 items Feeder panel (busbar in utilities hub 1 and 2, HVAC, and safety supply coupling panel) with ACB, width 600 mm (SPS 800 mm), depth 500 mm, height 2,200 mm. The circuit-breaker panel shall be offered as a complete unit with all panel and busbar parts and the following equip-ment:

1 item SENTRON 3WL circuit-breaker for alternating current in withdrawable unit design, DIN VDE 0660-101.Rated insulation voltage 1,000 V AC, 3-pole, time-discriminating grading possible, with guide frame.Rated current: In = 2000 A Rated operational voltage: Ue = 690 V AC, 50/60 Hz Rated service short-circuit breaking capacity Ics = 65 kA = Icu at 415 V AC Permissible ambient temperature: -25 °C to +70 °CNo derating at an ambient temperature of max. +55 °CDegree of protection IP20 Mechanical reclosing lock-out, mechanical switch-on readiness indicator with signaling switch (1NO), auxiliary switch with 2NO and 2NC, replaceable contacts.Temperature monitoring integrated in the switch (measuring points: switch environment, main contacts, electronics in the tripping mod-ule), measured values are supplied to superior control system by means of a COM module, fan control for the LV switchgear. Manual operation and motorized drive with mechanical and electric impulse.Rated operational voltage: Ue = 230 V AC with electronic overcurrent release “LSIN”, ETU45independent of external voltageSetting current of overload release: Ir = 40 to 100% of In in 5% incrementsManufacturer/type: Siemens/SENTRON 3WL

1 item Multi-functional measuring instrument to be integrated into switchboard with PROFIBUS-DP interface, built-in device 96 mm x 96 mm for the acquisition, direct display and transmission of power system parameters of a low-voltage power distribution system to a central data recording unit. Manufacturer/type: Siemens/SENTRON PAC3200 DP

4 items Compensation unit with dry-type capacitors and filter circuit with main busbar.Width 800 mm, depth 500 mm, height 2,200 mm. The feeder panel shall be offered as a complete unit with all panel and busbar parts and the following equipment: In compliance with IEC 439-1; EN 60439-1; DIN VDE 0660-500 for switchgear

IEC 831; EN 60831; DIN VDE 0560-41 for capacitors. compatibility level Class 2 in com-pliance with IEC 1000-2-4.Reactive power controller to be mounted into panel door with digital display; current trans-former connection …/1A and …/5 A; measured voltage 200 V – 700 V AC, 50/60 Hz; supply voltage 230 V AC, 50/60 Hz ±15%; 6 controller outputs; fault signaling contact; RS232 PC interface.Controller module consisting of: Module sheet Circuit-breaker for protection of control voltage Fan unitTemperature controller

Capacitor module consisting of:Module sheetLV HRC fuse-switch-disconnectorLV HRC fuse-linkDischarge reactor / resistorMKK power capacitors with round windings, built into aluminum can, self-healing plastic dielectric, N2 as impregnating agent, a pres-sure relief device, power loss < 0.5 W/kvar, measured at the connection terminals, or < 0.3 W/kvar in the dielectric, service life minimum 100,000 h, permissible overload of 1.5 x IN5 items of MKK capacitors 50 kvar Capacitor switching contactor with auxiliary contacts.Choking: Reactor with iron core suitable for fundamental and harmonic currents, with linear inductivity up to 1.7 (7%) times the reactor current rating Ieff with temperature switch for insulation class T40/HType: 4RF17: (p = 7%) Reactive-power control unit for central reactive power compensation in networks with a pro-portion > 20% of non-linear loads in the total load and a high self-generation of harmonic oscillations to prevent resonance between capacitors and network inductivities.With filtering of harmonic contents of the 5th order up to approx. 30% With filtering of harmonic contents of the 7th order up to approx. 15%With sufficient blocking of sound frequencies > 250 Hz

6 items Feeder panel of LV HRC in-line disconnectors,width 1,000 mm, depth 500 mm, height 2,200 mm. The feeder panel shall be offered as a complete unit with all panel and busbar parts and the following equipment:

4 items In-line fuse switch disconnectors, Size 00, with high-speed closing, M8 stud terminal, double interruption, DIN VDE 0660, IEC 947LV HRC fuses with center indicator without

Page 34: Siemens TIP Application Manual Part 3 for High-rise Buildings

34 Totally Integrated Power by Siemens

weakened ceramics. Type: 3NA7Rated operational voltage: Ue = 690 V AC, 50/60 HzRated current: Ith = 160 ARated short-circuit current: 50 kA 3-pole transformer set, Class 1, X/1A, 2.5 VAManufacturer/type: Siemens/SENTRON 3NJ6

4 items In-line fuse switch disconnectors, Size 1, with high-speed closing, M12 stud terminal, double interruption, DIN VDE 0660, IEC 947LV HRC fuses with center indicator without weakened ceramics. Type: SENTRON 3NA7Rated operational voltage: Ue = 690 V AC, 50/60 HzRated current: In = 250 ARated short-circuit current: 50 kA3-pole transformer set, Class 1, X/1A, 2.5 VAManufacturer/type: Siemens/SENTRON 3NJ6

3 items In-line fuse switch disconnectors, Size 3, with high-speed closing, M12 stud terminal, double interruption, DIN VDE 0660, IEC 947LV HRC fuses with center indicator without weakened ceramics. Type: 3NA7Rated operational voltage: Ue = 690 V AC, 50/60 HzRated current: Ith = 630 ARated short-circuit current: 50 kA 3-pole transformer set, Class 1, X/1A, 2.5 VAManufacturer/type: Siemens/SENTRON 3NJ6

3 items Metering panel for LV HRC in-line switch-discon-nectors, width 400 mm, depth 500 mm, height 2200 mm. The following equipment must be provided from ONE manufacturer! Mixing different OEM prod-ucts is not permitted. The metering panel shall be offered completely wired and with following equipment:

22 items Multi-functional measuring instrument for panel mounting with PROFIBUS-DP interface, built-in device 96 mm x 96 mm for the acquisition, direct display and transmission of power system parameters of a low-voltage power distribution system to a central data recording unit. Manufacturer/type: Siemens/SENTRON PAC3200 DP

Plant component for safety power supply (single-front station)

1 item Generator supply with air circuit-breaker (ACB), width 800 mm, depth 600 mm, height 2,200 mm. The circuit-breaker panel shall be offered as a complete unit with all panel and busbar parts and the following equipment:

1 item SENTRON 3WL circuit-breaker for alternating current in withdrawable unit design, DIN VDE 0660-101, time-discriminating grading possible, with guide frame.

Rated current: In = 2,000 ARated operational voltage: Ue = 690 V AC, 50/60 Hz Rated service short-circuit breaking capacity Ics = 65 kA = Icu at 415 V AC Permissible ambient temperature: -25 °C to +70 °CNo derating at ambient temperatures up to +55 °CDegree of protection IP20 Mechanical reclosing lock-out, mechanical switch-on readiness indicator with signaling switch (1NO), auxiliary switch with 2NO and 2NC, replaceable contacts.Temperature monitoring integrated in the switch (measuring points: switch environment, main contacts, electronics in the tripping mod-ule), measured values are supplied to superior control system by means of a COM module, fan control for the LV switchgear.With electronic tripping unit ”LSIN” , ETU 45Manufacturer/type: Siemens/SENTRON 3WL

1 item Multi-functional measuring instrument for panel mounting with PROFIBUS-DP interface, built-in device 96 mm x 96 mm for the acquisition, direct display and transmission of power system parameters of a low-voltage power distribution system to a central data recording unit. Manufacturer/type: Siemens/SENTRON PAC3200 DP

1 item Undervoltage protection, 230/400 V, 3-pole, 2 CO contacts Type: 5TT3

3 items Feeder panel (busbar in utilities hub 1 and 2, and general supply coupling panel) with ACB, width 600 mm (SPS 800 mm), depth 500 mm, height 2,200 mm. The circuit-breaker panel shall be offered as a complete unit with all panel and busbar parts and the following equipment:

1 item SENTRON 3WL circuit-breaker for alternating current in withdrawable unit design, DIN VDE 0660-101, rated insulation voltage Ui = 1,000 V AC, 3-pole, time-discriminating grading possible, with guide frame.Rated current: In = 2,000 ARated operational voltage: Ue = 690 V AC, 50/60 Hz Rated service short-circuit breaking capacity Ics = 65 kA = Icu at 415 V AC Permissible ambient temperature: -25 °C to +70 °CNo derating at an ambient temperature of max. +55 °CDegree of protection IP20 Mechanical reclosing lock-out, mechanical switch-on readiness indicator with signaling switch (1NO), auxiliary switch with 2NO and 2NC, replaceable contacts.

Page 35: Siemens TIP Application Manual Part 3 for High-rise Buildings

35Totally Integrated Power by Siemens

Temperature monitoring integrated in the switch (measuring points: switch environment, main contacts, electronics in the tripping mod-ule), measured values are supplied to superior control system by means of a COM module, fan control for the LV switchgear.With electronic tripping unit ”LSIN” , ETU 45Manufacturer/type: Siemens/SENTRON 3WL

1 item Multi-functional measuring instrument for panel mounting with PROFIBUS-DP interface, built-in device 96 mm x 96 mm for the acquisition, direct display and transmission of power system parameters of a low-voltage power distribution system to a central data recording unit. Manufacturer/type: Siemens/SENTRON PAC3200 DP

1 item Undervoltage protection, 230/400 V, 3-pole, 2 CO contacts Type: 5TT3

2 items Feeder panel for LV HRC in-line switch-discon-nectorswidth 1,000 mm, depth 600 mm, height 2,200 mm. The feeder panel shall be offered as a complete unit with all panel and busbar parts and the following equipment:

4 items In-line fuse switch disconnectors, Size 00, with high-speed closing, M8 stud terminal, double interruption, DIN VDE 0660, IEC 947.LV HRC fuses with center indicator without weakened ceramics. Type: 3NA7Rated operational voltage: Ue = 690 V AC, 50/60 HzRated current: In = 160 ARated short-circuit current: 50 kA3-pole transformer set, Class 1, X/1A, 2.5 VAManufacturer/type: Siemens/SENTRON 3NJ6

4 items In-line fuse switch disconnectors, Size 1, with high-speed closing, M12 stud terminal, double interruption, DIN VDE 0660, IEC 947.LV HRC fuses with center indicator without weakened ceramics. Type: 3NA7Rated operational voltage: Ue = 690 V AC, 50/60 HzRated current: In = 250 ARated short-circuit current: 50 kA3-pole transformer set, Class 1, X/1A, 2.5 VAManufacturer/type: Siemens/SENTRON 3NJ6

3 items In-line fuse switch disconnectors, Size 3, with high-speed closing, M12 stud terminal, double interruption, IEC 947, DIN VDE 0660.LV HRC fuses with center indicator without weakened ceramics. Type: 3NA7Rated operational voltage: Ue = 690 V AC, 50/60 HzRated current: Ith = 630 A

Rated short-circuit current: 50 kA 3-pole transformer set, Class 1, X/1A, 2.5 VAManufacturer/type: Siemens/SENTRON 3NJ6

2 items Metering panel for LV HRC in-line switch-discon-nectors, width 400 mm, depth 600 mm, height 2200 mm. The metering panel shall be offered completely wired and with following equipment:

11 items Multi-functional measuring instrument for panel mounting with PROFIBUS-DP interface, built-in device 96 mm x 96 mm for the acquisition, direct display and transmission of power system parameters of a low-voltage power distribution system to a central data recording unit. Manufacturer/type: Siemens/SENTRON PAC3200 DP

Power management

1 item Power management systemThe above described power supply system must be equipped with a power management system. The leading product is Siemens.

Measurements/transmission from the switchgear rooms / panels:

In each of the switchgear rooms or in process, measured values and status will be collected via communication-capable circuit-breakers, multi-functional measuring instru-ments or distributed I/Os and transmitted to a programma-ble logic controller (SIMATIC S7) via PROFIBUS-DP or direct interfacing. This controller must be designed with the capacity to generate mean values of measurements, per-form message acquisitions, and store measured values and messages temporarily. If communication to the operator control and monitoring level has broken down, energy data are buffered, so that they can be transmitted when the connection is reestablished.

Central control room – visualization on a PC:

The server shall be installed in a central room. The server communicates with all PLC units (SIMATIC S7) in the switchgear rooms via an OWG ring circuit, it serves for display of all information rendered from the switchgear rooms, for measured value, message and load manage-ment parameterization as well as for data archiving. Client applications on distributed workstations access this server. In a control center the current status of power distribution is displayed. Besides electricity, other energy types, such as gas, compressed air, district heating etc., may also be integrated. Energy quantities, limit violations, individual measured values and switch positions are displayed inform of graphics. Electrical switches can be remote-controlled directly from the operator interface. All switching opera-tions, whether initiated from the control center or directly on site, as well as limit violations of measured values are recorded with date and time and archived. This informa-tion is either visualized as text message or graphically as

Page 36: Siemens TIP Application Manual Part 3 for High-rise Buildings

36 Totally Integrated Power by Siemens

switching cycle diagram. Measured value acquisition is performed continuously and compressed and archived as mean values in adjustable increments of 1 to 60 minutes. Values are displayed graphically as load curves. All archived data are available for analysis, export and reporting. A cost management function is available as to map the cost center structure, energy types, consumption values, costs and billing rates. Power distribution is visualized by means of hierarchically structured process images. A plant over-view functions as start screen to access the individual plant component images. Messages and faults/malfunctions can be displayed in the respective component images or in a specific diagnostic image. In addition, there are curve diagrams and tables/statistics.

Status and measured value acquisition

Integration of all operating states / measured values of the following plant components:

Medium-voltage switchgear

Distribution transformers

Low-voltage main distribution systems

Subdistribution systems

UPS

Standby power supply

Additional components for communication

For networking the different components of the power management system and for communication with other components, the following equipment should be consid-ered:

Industrial Ethernet LAN Switch SCALANCE X208

Profibus repeater

Modbus gateway (transformer / diesel generator)

Distribution board max. 160 A

Distribution board for surface-mounting with recessed mounting frame,

Height 950 mm, width 550 mm, depth 140 mm, TTA acc. to DIN EN 60439-1 (VDE 0660-500) and DIN EN 60439-3 (DIN VDE 0660-504)

Quick-assembly kits in full cabinet height

Assembly kits for switches and installation equipment

Molded-plastic covers with quick-acting locks

Modular system: distribution board as a complete unit

Rated current: 160 A

Rated voltage: 690 V AC

Degree of protection: IP43

Safety class 2

Mounting rail center spacing: 125/150 mm

Material: sheet steel, electroplated and powder-coated

Color: light gray RAL 7035 AP

Door to be hinged from the left or right; door opening angle 170°

Delivery: complete case with door / double door and espagnolette lock

One cable entry opening with flange at top and bottom per panel width, with integrated slabs for mounting assembly kits.

Manufacturer/type: Siemens/ALPHA 160-DIN

15 items equipped with:

6 items Circuit-breaker, 1-pole 16 A, C, 10 kA, 1NO+1NC, type 5SY

3 items Circuit-breaker, 3-pole 16 A, C, 10 kA, 1NO+1NC, type 5SY

1 item Circuit-breaker, 3-pole 32 A, C, 10 kA, 1NO+1NC, type 5SY

2 items Circuit-breaker, 1-pole 16 A, B, 10 kA, 1NO+1NC, type 5SY

6 items Residual-current-operated circuit-breaker (RCCB), 2-pole, 25 A /30 mA, type 5SM1

3 items RCCB, 4-pole, 25 A /30 mA, type 5SM1

3 items RCCB, 4-pole, 63 A /30 mA, type 5SM1

1 item Switch, 3-pole, 230 V, 160 A, type 5TE1

3 items MINIZED switch-disconnector, 3-pole, max. 63 A, type 5SG7

1 item Overvoltage protection, 4-pole, consisting of a lightning current arrester (1/B) and surge ar-rester (2/C)

Page 37: Siemens TIP Application Manual Part 3 for High-rise Buildings

37Totally Integrated Power by Siemens

Distribution board max. 630 A (utilities hubs for GPS and SPS)

Distribution board in floor-mounted design

Height 1950 mm, width 750 mm, depth 320 mmTTA acc. to DIN EN 60439-1 (VDE 0660-500) and DIN EN 60439-3 (DIN VDE 0660-504)

Quick-assembly kits in full cabinet height (SMB)

Assembly kits for switches and installation equipment

Molded-plastic covers with quick-acting locks

Modular system: distribution board as a complete unit

Rated current: 630 A

Rated voltage: 690 V AC

Degree of protection: IP43

Safety class 1

Mounting rail center spacing: 150 mm

Material: sheet steel, electroplated and powder-coated

Color: light gray RAL 7035

Door to be hinged from the left or right; door opening angle 170°

Delivery: Complete case with door / double door and espagnolette lock

One cable entry opening with flange at top and bottom per panel width, with integrated slabs for mounting assembly kits.

Manufacturer/type: Siemens/ALPHA 630-DIN

22 items (GPS) equipped with:

12 items Circuit-breaker, 1-pole 16 A, C, 15 kA, 1NO+1NC, type 5SY

6 items Circuit-breaker, 3-pole 16 A, C, 15 kA, 1NO+1NC, type 5SY

2 items Circuit-breaker, 3-pole 32 A, C, 15 kA, 1NO+1NC, type 5SY

24 items Circuit-breaker, 1-pole 16 A, B, 15 kA, 1NO+1NC, type 5SY

20 items Circuit-breaker, 1-pole 16 A, B, 15 kA, 1NO+1NC, type 5SY

24 items RCCB, 2-pole, 25 A /30 mA, type 5SM1

8 items RCCB, 4-pole, 25 A /30 mA, type 5SM1

2 items RCCB, 4-pole, 63 A /30 mA, type 5SM1

1 item Molded-case circuit-breaker (MCCB), 3-pole, 230 V, 400 A, type SENTRON 3VL

2 items MINIZED switch-disconnector, 3-pole, max. 63 A, type 5SG7

1 item Overvoltage protection, 4-pole, consisting of a lightning current arrester (1/B) and surge ar-rester (1/C)

22 items (SPS) equipped with:

6 items Circuit-breaker, 1-pole 16 A, C, 15 kA, 1NO+1NC, type 5SY

1 item Circuit-breaker, 3-pole 16 A, C, 15 kA, 1NO+1NC, type 5SY

1 item Circuit-breaker, 3-pole 32 A, C, 15 kA, 1NO+1NC, type 5SY

12 items Circuit-breaker, 1-pole 16 A, B, 15 kA, 1NO+1NC, type 5SY

12 items Circuit-breaker, 1-pole 16 A, B, 15 kA, 1NO+1NC, type 5SY

30 items RCCB, 2-pole, 25 A /30 mA, type 5SM1

2 items RCCB, 4-pole, 25 A /30 mA, type 5SM1

2 items RCCB, 4-pole, 63 A /30 mA, type 5SM1

1 item MCCB, 3-pole, 230 V, 400 A, type SENTRON 3VL

2 items MINIZED switch-disconnector, 3-pole, max. 63 A, type 5SG7

1 item Overvoltage protection, 4-pole, consisting of a lightning current arrester (1/B) and surge arrester (1/C)

Page 38: Siemens TIP Application Manual Part 3 for High-rise Buildings

38 Totally Integrated Power by Siemens

2.8 Performance Specifi cation of Power Distribution (Excerpt)

The following specification of work and services describes the power supply from the medium-voltage level (rated voltage 10 kV) to the final circuit.

A medium-voltage switchgear plant is to be erected ac-cording to the supply conditions imposed by the responsi-ble power distribution network operator.

In order to build a fully selective power system, specifica-tions made by the network operator in terms of grading times must be observed.

Medium voltage is fed into the system by means of ring-main cables.

The switchgear for medium-voltage transfer is to be deliv-ered as a 6-panel, gas-insulated (SF6) station (ring, ring, metering, CB load transfer, 2 x CB transformer outgoing feeder). It must be possible to extend the station by one feeder panel without redesigning work being involved and within a time frame of a few hours.

The medium-voltage substation consists of 3 panels (feed-in via disconnectors, 2 x CB transformer outgoing feeder)

The transformers are to be designed as low-loss cast-resin transformers with a performance enhancement option by using tangential fans (50%).

The LVMD system, the busbars and the system of trans-former/busbar/LVMD is to be implemented as a type-tested assembly (TTA).

All feeder and coupling switches are to be delivered as air circuit-breakers(ACB) in identical current ratings with guide frame and LSIN releases. The rated current of the release block must be adapted to requirements by means of a rating plug (without replacing the measuring transducer set).

Feeders with LV HRC fuses must be measured in 3 phases and their power consumption must be allocated to the appropriate cost centers by employing a power manage-ment system.

Meters for these load circuits shall be placed in such a way that they can clearly be allocated to the respective load circuit.

The compensation unit is to be supplied as a choked system.

General pre-conditions

All works are to be announced and registered approx. 4 weeks prior to their start and must be agreed upon with the user/construction management/customer. The speci-fied switchgear dimensions are maximum dimensions. They are binding. Prior to delivery, the contractor shall

take measurements of local conditions (openings and doors for moving the switchgear in, frame dimensions of switchgear, possible transportation units, weights, routes …) in coordination with the construction manage-ment. The delivery of switchgear components shall also cover all costs required for testing and acceptance (power supply network operator, experts..) and additional ser-vices.

The leading products are binding.

The protective devices put out to tender are matched to one another regarding their short-circuit behavior / charac-teristic curves / shutdown behavior. For this reason, all installation devices must be procured from one supplier. Protective technology, reliability of supply as well as any possible power feedback into the system in case of an existing standby power network is to be agreed with the network operator / public testing and inspection authori-ties, Association of Property Insurers etc. Any works out-side this industry, if not explicitly mentioned herein, are not part of this performance specification. For the duration of constructions, the contractor shall name a responsible contact person for every work contract section /installation who shall be in charge of coordination and clarification of questions. Participation in construction-related meetings is compulsory. If the contractor employs subcontractors, they shall be named in the tender. The contractor provides coordination, responsibility for and representation of his subcontractors (construction-related meetings, workflow, schedules …). The contractor, and not his subcontractors, shall be the sole point of contact and partner in negotia-tions for the customer.

Schedule

To ensure erection and mounting procedures running on schedule, the contractor must adjust his capacities to the specific mounting situation. Based upon the corner dates listed below, the contractor is required to draw up a de-tailed time schedule which describes the precise erection and mounting procedures. The contractor must proactively lead all coordinating talks required in this context with the various developer representatives, representatives of public authorities and any other performing companies involved in the construction process. The detailed time schedule must be handed over to the developer’s represen-tative 4 weeks after the contract has been awarded, at the latest. The time schedule becomes part of the contract and must strictly be complied with. This time schedule must be actively managed during construction, and, if necessary, adjusted to a changed situation in good cooperation with the parties involved.

Proof of selectivity (medium-voltage utilities substation to final circuit)

Computational proof for the selected protective devices and cable cross sections including an assessment of selec-tivity for the entire supply network (MV branch circuit to

Page 39: Siemens TIP Application Manual Part 3 for High-rise Buildings

39Totally Integrated Power by Siemens

final circuit) including energy balance for all of the con-nected loads (switchgear cabinets for the different supply subsections, e.g. electrical installations, heating, ventila-tion, air conditioning, lighting …).

Data on network configuration (1-pole single-line dia-grams), cable lengths and load data are provided by the construction management.

The outgoing feeder terminals of the above mentioned main distribution boards will be regarded as the interface for selectivity assessment.

Relevant power supply system data shall be handed over to the third-party works suppliers in writing. The point of reference is the feeder terminal to the distribution boards for the different supply subsections.

The proof of selectivity, being the fundamental basis of the implementation planning for mounting the electrical installation, shall be handed in, at the latest, when the implementation plans of the main switchgear are submit-ted for the purpose of obtaining a mounting permit. This proof must include the following:

Energy balance in form of a table

1-pole single-line diagram with device parameters (for power sources, protective devices, cable routes)

1-pole single-line diagram with load flow and voltage drop representation for each circuit

1-pole single-line diagram with representation of the minimum and maximum short-circuit loads

I2t characteristic curve diagrams of all circuit-breakers and the largest LV HRC outgoing fuses for each switchgear station and network(these curves must show the circuit-breaker parameters that have actually been set)

A table of all protective devices including setting ranges and set values (will also be used for subsequent commissioning documentation)

This proof must be produced using an approved, certified IT tool.

Manufacturer/IT tool: Siemens/SIMARIS design

Note:

See Application Manual, Draft Planning, Section 8.3 Selec-tivity and Back-up Protection.

A network calculation should always be performed prior to any performance specification, forming a basis thereof. Any problems resulting from a wrong device selection/combination/arrangement will thus be detected at an early stage.

Furthermore, a network calculation provides a record of planning reliability with regard to cable cross sections, voltage drop, observance of conditions for disconnection

from supply, and the grading distances of protective de-vices.

Selectivity is required on the basis of the following stan-dards, regulations and recommendations:

DIN VDE 0100-718 “Erection of low-voltage installations – Requirements for special installations or locations – Part 718: Installations for gathering of people“ (previously DIN VDE 0108)

DIN VDE 0100-710 “Erection of low-voltage installations – Requirements for special installations or locations – Part 710: Medical locations“ (previously DIN VDE 0107)

Safety Rule of the Nuclear Safety Standards Commission (KTA 3705) Switchgear, Transformers and Distribution Networks for the Electrical Power Supply of the Safety System in Nuclear Power Plants

Increasing (global) customer demand for switchgear with a high degree of supply reliability

Medium-voltage switchgear

In accordance with the Application Manual, Basic Data and Preliminary Planning, Section 5.1 and Part 2 of the Applica-tion Manual, Draft Planning, Section 3.4 Medium-Voltage Switchgear.

An up-to-date template for the tender specification text can be obtained on the Internet at: www.siemens.com/tip/consultant

Note: Pressure calculation for internal faults

This proof is sometimes a mandatory requirement stipu-lated by the power utility.

A calculation gives information regarding pressures pro-duced in case of accidental arcs and provides the resulting dimensions of openings in the shell necessary for pressure relief (which is important when the switchgear room should be located somewhere inside the building, because pressure relief openings would then be problematic).

In accordance with Application Manual, Basic Data and Preliminary Planning, Section 5.1.3 Pressure Development in Switchgear Rooms.

Transformers and accessories

In accordance with the Application Manual, Basic Data and Preliminary Planning, Section 5.2 Distribution Transformers and Part 2 of the Application Manual, Draft Planning, Chapter 4 Transformers.

An up-to-date template for the tender specification text can be obtained on the Internet at: www.siemens.com/tip/consultant

Page 40: Siemens TIP Application Manual Part 3 for High-rise Buildings

40 Totally Integrated Power by Siemens

Busbar trunking system (connection of transformer/LVMD)

In accordance with the Application Manual, Basic Data and Preliminary Planning, Section 5.4 Busbar Trunking Systems and Part 2 of the Application Manual, Draft Planning, Chapter 7 Busbar Trunking Systems, Cables and Wires.

Note:

Excerpt from the tender specification text:

Busbar trunking systems must be delivered and mounted as a system tested from end to end (connection of trans-former/busbar/LVMD), as “type-tested low-voltage switch-gear assembly – TTA” ready for connection.

An up-to-date template for the tender specification text can be obtained on the Internet at: www.siemens.com/tip/consultant

Low-voltage switchgear

In accordance with the Application Manual, Basic Data and Preliminary Planning, Section 5.3 Low-Voltage Main Distri-bution and Part 2 of the Application Manual, Draft Plan-ning, Chapter 6 Low-Voltage Switchgear.

Note:

The reactive power compensation unit is part of the low-voltage switchgear and shall be put out to tender under the same subsection.

An up-to-date template for the tender specification text can be obtained on the Internet at: www.siemens.com/tip/consultant

Busbar trunking system (rising mains line in the utilities hubs (GPS/SPS)

In accordance with the Application Manual, Basic Data and Preliminary Planning, Section 5.4 Busbar Trunking Systems and Part 2 of the Application Manual, Draft Planning, Chapter 7 Busbar Trunking Systems, Cables and Wires.

Note:

Excerpt from the tender specification:

The busbar trunking system is to be delivered as a com-plete unit including the required connecting and terminat-ing material matching the project-specific system opera-tion.

Listed unit prices must also include all costs for project planning, documentation, the coordination of the trunking route with other work contractors/installations and the measurements of system modules to be taken, as well as fastening material and drawing up the final inspection doc-uments.

Besides the quantities listed below, the floor plans and sectional drawings of the entire system are to be consid-ered for project planning and drawing up a tender specifi-cation.

An up-to-date template for the tender specification text can be obtained on the Internet at: www.siemens.com/tip/consultant

Distribution boards

In accordance with the Application Manual, Basic Data and Preliminary Planning, Section 5.5 Subdistribution Systems and Part 2 of the Application Manual, Draft Planning, Section 8.4 Small Distribution Boards and Wall- or Floor-Mounted Distribution Boards.

Distribution boards are divided as follows:

Distribution boards up to 160 A

Distribution boards up to 630 A

Standby power supply

In accordance with the Application Manual, Basic Data and Preliminary Planning, Section 5.7 Standby Power Supply and Part 2 of the Application M anual, Draft Planning, Section 6.4 Container Solutions.

Note:

Container solutions

are space saving

their assembly is independent of the building construction progress

they are quickly rigged up

they are an all-in-one solution which has solved all interfacing problems (little harmonization with the building shell required)

they are economical, in particular as a “rooftop version” (short exhaust gas piping, low noise pollution …)

they can be easily maintained, or replaced, if necessary.

Uninterruptible power supply (UPS)

In accordance with the Application Manual, Basic Data and Preliminary Planning, Section 5.6 Uninterruptible Power Supply (UPS) and Part 2 of the Application Manual, Draft Planning, Section 5.2 Basis for the Use of UPS.

An up-to-date template for the tender specification text can be obtained on the Internet at: www.siemens.com/tip/consultant.

Page 41: Siemens TIP Application Manual Part 3 for High-rise Buildings

41Totally Integrated Power by Siemens

Your Siemens Contact Partners

Consultant Support

AustriaLeopold HolzhackerSiemensstraße 92ZIP 1211ViennaPhone: +43 5 1707-23330E-mail: [email protected]

ChinaChristophe de Maistre7, Wangjing Zhonghuan NanluZIP 100102BeijingPhone: +86 10 6476 5780E-mail: [email protected]

ItalyPaolo ParmaVia Piero e Alberto Pirelli, 10ZIP 20126MilanPhone: +39 02 243-62952E-mail: [email protected]

NetherlandsWalter van AkenPrinses Beatrixlaan 800ZIP 2595Den HaagPhone: +31 70 333-1598E-mail: [email protected]

PortugalAnabela CorreiaRua Imraos Siemens, 1ZIP 2720-093AmadoraPhone: +351 21 417-8648E-mail: [email protected]

RussiaAndrej BirjukowUl. Letnikovskaya, 11/10ZIP 115114MoscowPhone: +7 495 [email protected]

SpainPedro Jose Iglesia PerezRonda de Europa, 5 – Tres CantosZIP 28760MadridPhone: +34 91 514-7110E-mail: [email protected]

SwitzerlandMartin LinigerFreilagerstrasse 28ZIP 8047ZurichPhone: +41 585 560 028E-mail: [email protected]

TurkeyCahit AtayYakacik Cad. No. 111, KartalZIP 34870IstanbulPhone: +90 216 459 3182E-mail: [email protected]

UKHoward JohnSir William Siemens HousePrincess RoadZIP M20 2 URManchesterPhone: +44 161 446-6400E-mail: [email protected]

USAWilliam Reid215 Southport Drive, Suite 900ZIP 27560Morrisville, NCPhone: +1 919 468 2320E-mail: [email protected]

Elevators, escalators, moving walkways

OTIS GmbH & Co. OHGOtisstraße 33D-13507 BerlinPhone: +49 30 4304-1600 Fax: +49 30 4304-2585

Lighting systems

Siteco Beleuchtungstechnik GmbHTechnical SupportGeorg-Simon-Ohm-Straße 50 D-83301 Traunreut/Obb.Phone: +49 8669 33-844Fax: +49 8669 33-540E-mail: [email protected] www.siteco.de or www.siteco.com

Safety lighting

CEAG Notlichtsysteme GmbHSenator-Schwartz-Ring 26 D-59494 SoestPhone: +49 2921 69-0www.ceag.de

Cables

U.I. Lapp GmbHSchulze-Delitzsch-Straße 25D-70565 StuttgartPhone:+49 711 7838-01www.lapplabel.de

Uninterruptible power supply

MASTERGUARD GmbHP.O. Box 2620D-91014 ErlangenFax: +49 9131 6300-300www.masterguard.deInfoline (workdays 9 a.m. to 5 p.m.)Phone: 0180 5323751E-mail: [email protected]

Contacts for Special Interests

Page 42: Siemens TIP Application Manual Part 3 for High-rise Buildings

42 Totally Integrated Power by Siemens

Trademarks

ALPHA SELECT®, DIAZED®, GEAFOL®, instabus® EIB, MINIZED®, SENTRON®, SIMATIC®, SIMARIS design®, SIPROTEC®, SIVACON®are registered trademarks of Siemens AG.

Totally Integrated Power™ is a trademark of Siemens AG.

PROFIBUS®is a registered trademark of PROFIBUS Nutzerorganisation e.V. (PNO).

The omission of any specific reference with regard to trade-marks, brand names, technical solutions, etc., does not imply that they are not protected by patent.

Imprint

Totally Integrated PowerApplication Manual –Planning of a High-rise Building

Published bySiemens AGIndustry SectorIndustry AutomationPostfach 48 4890327 Nuremberg, Germany

EditorRalf Willeke, Siemens AG, Industry Sector IA CD TIP

Publishing HousePublicis KommunikationsAgentur GmbH, GWANägelsbachstr. 3391052 Erlangen, Germany

PrintHofmann Infocom AGEmmericher Straße 1090411 Nuremberg, Germany

© 2008 Siemens AktiengesellschaftBerlin and MunichAlle rights reserved. All data and circuit examples without engagement.Subject to change without prior notice.

Page 43: Siemens TIP Application Manual Part 3 for High-rise Buildings

43Totally Integrated Power by Siemens

Page 44: Siemens TIP Application Manual Part 3 for High-rise Buildings

The information provided in this manual contains merely general descriptions or characteristics of performance which in case of actual use do not always apply as described or which may change as a result of further development of the products. An obligation to provide the respective characteristics shall only exist if expressly agreed in the terms of contract.

All product designations may be trademarks or product names of Siemens AG or supplier companies whose use by third parties for their own purposes could violate the rights of the owners.

www.siemens.com/tip

Subject to change without prior notice 03/08 Order No. E20001-A170-M104-X-7600Dispo 276122100/8281 XX04.52.8.03 HB 03082.0Printed in Germany © Siemens AG 2008

Siemens AGIndustry SectorLow-Voltage Controls and DistributionP.O. Box 48 4890327 NUREMBERGGERMANY

Get more information

More about Totally Integrated Power in the internet :www.siemens.com/tip