    ASSIGNMENT NO: 30

    COURSE NO: NCP 30

    COURSE TITLE: SITE ORGANISATION AND

    MANAGEMENT

    ASSIGNMENT NO: NINE

    DATE OF DESPATCH:

    LAST DATE OF RECEIPT:

    ASSIGNMENT:

    Your company has been awarded a prestigious contract of building 500 M length

    pre-stressed concrete bridge on a national highway crossing the major river. Due to

    cultivation on both sides of highway, very restricted space of only 100 m in width

    and 300 m in length is available on both sides of highway.

    To mobilize the site, your management has asked you to house 350 t of cement,300 t of steel, 2 size II crawler-tractor dozer, one mobile crane, one JCB, ten

    dumpers. Labour force of 100 men in addition to site office complete with

    communication set up.

    Discuss your plan to organize the site, draw layout sketch showing all details. Wind

    direction is from west to east and bridge direction is east to west.

  • 8/3/2019 Site ion

    2/19

    Site Organization and Management

    With the integration of above analyzed situation and main Project bar chart, analyze

    the work heads / Sections and staff requirement for each section according to job

    responsibilities.

    Site Organization Chart as per Annexure 1

    Sections

    Planning

    Execution

    Administration, Accounts

    Store

    Safety

    Quality Control

    Job Responsibilities

    Planning Section

    Prepare Detailed Project schedule with reference to contractual periods. Take

    approval from HQ and Client.

    In depth study of contract documents, specifications and drawings.

  • 8/3/2019 Site ion

    3/19

    Take out Quantities of different activities based on available drawings

    Prepare Work Methodology of different activities based on Specification,

    drawings and site situations

    Analyze requirement of labours based on type of work, quantities and project

    schedule. Labour requirement contains skilled, semi skilled, unskilled and

    specialized agencies

    Analyze requirement of plan and machines based on quantities and project

    schedule.

    Analyze requirement of basic materials and specialized materials based on

    drawings quantities and project schedule.

    Prepare Monthly, weekly, daily planning of activities.

    Major resources / Plant allocation based of work.

    Prepare daily, weekly, and monthly progress reports.

    Prepare Monthly and yearly project budgets.

    Invites suppliers quotations for different materials negotiate with concerns

    vendors and finalized after concurrence of top management. Generally

    certain limits are abided by HQ to give such power for sanctioning up to the

    limit, beyond that it comes in higher management authorities.

    Invites sub contractors' quotations for different works, negotiate with

    concerns vendors and finalized after concurrence of top management.

    Maintain records of clients / consultants correspondence, Hindrances records

  • 8/3/2019 Site ion

    4/19

    Suppliers and sub contractors quotations with their negotiations, and

    comparative statements.

    Prepare client bill, its' checking with client representative, follow up for

    payments.

    Prepare sub contractors labor bills based on site measurement available from

    execution teams.

    Reconciliation of subcontractors vs client measurement, materials

    reconciliation.

    Updating and monitoring of project schedule /bar charts.

    Check and prepare list of items, which are to be execute as per drawings but

    not available original contracts. Get approval for such activities before start

    of execution; put extra claims for such items.

    Administration -

    This section acts its multifunctional vital role for whole project. This section is

    directly / indirectly connected with each site personnel, labours, vendors. Mainly

    this Section is divided in following sub sections. Generally in this section operating

    personnel common are same and integrated with other sections.

    1. Administration / Human Resource

    2. Accounts -

    3. Time office.

  • 8/3/2019 Site ion

    5/19

    Administration / Human Resource:

    Enlisted below is a brief job descriptions related to this section.

    Maintain daily monthly attendance records of company staff and forward to

    HO .

    Maintain leave records of staff.

    Avail Welfare facilities to staff as per company's predefining norms.

    Staff accommodation facilities.

    Staff conveyance facilities.

    Staff transferred details, staff requirement details

    Arrange internal/ external communication systems, like telephones, wireless,

    mobile phones, etc..

    Preparation of staff salary and other perks

    Maintain site amenities such as site office, office furniture, toilets, news

    papers, books and reception

    Arrangement of site level functions and celebrations

    Public relations with respect to the site level

    Maintain the relation with local police, leaders, unions etc..

    Arrange deployment of local staffs as per the site requirements with

    approvals of the project manager

  • 8/3/2019 Site ion

    6/19

  • 8/3/2019 Site ion

    7/19

    Check details of purchase order and work order before making payment to

    check the deduction made according to rules / terms and conditions

    Forward all transaction details to HQ

    Forward bills with MRN details for material ordered from HQ

    Monitor the working capital involved the project

    Prepare monthly cost statement for cost incurred till date

    Time office

    Prepare and maintain daily labour records and inform same to project

    manager

    Daily site visit for labour strength verification

    Prepare monthly labour records

    Prepare wage statement and make the payment after scrutinizing by

    accounts and administration dept.

    Prepare PF calculation and submit in required PF forms to PF dept

    Maintain wages records as per statutory requirements

    Maintain all labour reports as per govt rules and regulations

  • 8/3/2019 Site ion

    8/19

    Allocate labour colony to workers and maintain room allotment records,

    which contains room occupants name, address and belongs to which sub

    contractor

    Maintain labour colony safe clean and healthy

    Prevent consumption of alcohol in the colony

    Store

    This section is a core project which supplies the requirement of each activity in each

    department / sections. Material cost itself is largest component of the total cost of

    the project. Store incharge should be fully aware of the stocks of the material he

    ahs in the store and must able to lay hand on it when there is a demand store

    personnel deals not merely with materials but people from different sources. He has

    to deal with not only with colleagues of the material management department like

    HQ/RO purchase department, accounts, but also with outsiders like suppliers

    transport agencies, users, etc.. He should develop good relation with all concern.

    This section involved numerous actions. Some of that are listed bellows

    Standard codification and classification of various materials.

    Maintain Requisition form from ~ to be submitted by the consumer center to

    inventory controls

    Advice note to the purchase; from inventory to the purchase with copy to

    the accounts.

  • 8/3/2019 Site ion

    9/19

    Inviting Quotations for supply of materials and transportation. This action will

    also involve planning department for material rate and quantity verification.

    Scrutiny of quotation, comparative statements and preparing purchase order

    for any Local purchase item, (This action does not come under the store

    sections, generally separate purchase department at HQ level maintain the

    matters.)

    issue materials as per indent

    Maintain records regarding the receipt, issue and balance

    Prepare Monthly inventory and indenting quantity and cost

    Prepare monthly stock statements

    Maintain Safety Stock of essential materials at all time

    Proper Housekeeping in store as well as outside open stock yard

    Always keep separate perishables and non-perishables item stock and record

    it separately

    Safety

    This is also a part of site administration but now a day it becomes an essential for

    all projects.

    To maintain site safety for overall project duration. So, High standards of safety

    should be an objective pursued in the same way and as much vigor as other

  • 8/3/2019 Site ion

    10/19

    management objectives. Its always accident and illness means additional costs and

    perhaps disruption of contract.

    Here I had separated safety as a different department / section with its own

    individual identity.

    For this some of measures, which are necessary, are mentioned below.

    ** Effective Communication:

    Communicate effectively with work force on accident prevention is often the key to

    successful approach to safety. Internal site wireless system is more effective.

    ** Record Keeping:

    Keeping of records of type of accident.

    Keep daily safe man-hours working

    Analyze accident causes and its preventive actions.

    Analyze most frequent occurring Incidents I accidents

    Work out site safety cost U

    Safety related training records

    Improve awareness for safety to workers and staff.

  • 8/3/2019 Site ion

    11/19

    **Motivation of Work Force

    Organize safety programmes, bonus, and incentive for workers or gangs with

    best nil accident performance records.

    Use Safety equipments.

    Make sure that safety equipment is available when and where it is needed,

    insist that it always used, and take disciplinary action against workers who

    refuse or frequently forget to use the equipment.

    PPE (Personnel Protective Equipments) are must for all workers and staff.

    Such as, Helmet, Safety shoes, Safety Belts for working beyond 2.00 m

    height. Life jackets for working inside water lodged area.

    Plant and machinery Section:

    Now a days Plant and machinery / equipments are playing vital role to achieve

    targets in time and cost measures with separate identity of each equipment with

    specific activities. This section contains elaborate activities; some of those are short

    listed here.

    lts main objective will be minimizing break down of any equipment.

    Attend break down equipment immediately and restart it within short

    duration.

  • 8/3/2019 Site ion

    12/19

    Regular periodic service of each equipment, this will in upkeep the machinery

    and increase life and productivity

    Determine performance of each machinery,

    Check and maintain Logbook for each equipment

    Maintain repairs and maintenances cost separately

    Maintain Machine History report.

    Update licenses and insurance and its renewal.

    Maintain Records of Purchase, Hired, and owned equipments.

    Keep separate Depreciation of own equipment,

    Determine Total Plant cost for the month.

    Fuel consumption on plants and its reconciliation.

    Follow for inventory of spares and consumables.

    Maintain workshop, its equipments and frequent needed spares readily

    available.

    Compare cost of hired and own equipment in coordination with planning.

    Quality Control:

    Control gives confirmations regarding to all activities with required standard.

    lt gives standards for construction methodology, material testing before its

    use, product testing after commencement of any activities etc. We can say

  • 8/3/2019 Site ion

    13/19

    Quality Control refers to the technical process that gather, examine, analyze

    and report the projects progress and conformance with % the performance

    requirements.

    Main Basic Elements for Q C. Actions:

    Setting up of standards and specifications

    Evaluating materials process and outputs through appropriate tests,

    inspection

    Appraising failures to these standards and acting when standards are not

    being adhered

    Planning improvements in the standards and specifications

    Quality control functions:

    Development of specifications

    Interaction with project designers

    Reliability and developments testing

    Process capability studies

    QC of incoming materials.

    Vendor of QC and Vendor development.

    Quality planning for control of construction process

    Inspection and testing during construction.

  • 8/3/2019 Site ion

    14/19

    Interaction with service engineers.

    Records and Procedures;

    QC record accumulation procedure

    Document control procedure I

    ln built drawing control procedure

    Non-conformance control procedure.

    Execution Team:

    Execution teams have a vital role not only for site but for companies overall

    establishment. These all are the frontline asset of company whom we call

    Execution staffs.

    Job responsibility;

    Prepare working strategy according to available drawings and specifications.

    Finalize the Methodology of each activity with concern to quality,

    specilicationf and safety.

    Determine the Quantities required for the work, prepare schedule of

    material requirement according to drawing and bar chart

    Raise the Material Requisition and take approval from sitemanagement.

    Check the quality of materials as per required quality norms.

    Give details of daily progress reports to planning section.

  • 8/3/2019 Site ion

    15/19

    Prepare sub contractors measurement and give it to planning section for

    preparation of labor bills.

    Prepare monthly reconciliation for sub contractor work done and material

    quantity.

    Keep record of chargeable materials given to sub - contractor.

    Keep drawing available records its revisions, changes according to revisions.

    Inform project manager and planning section for any new items which are

    not mentioned in contracts BOQ schedule.

    Maintain the safety and quality standards as prescribed in specifications and

    contracts.

    Site lay out plan

    Due to cultivation on both sides of highway, very restricted space of 100X300 M is

    available on both side of highway so plan the site layout as per annexure -2. The

    considerations for planning the layout are as discussed bellow

    Plot No 1

    Labour camp :

    Capacity -120 nos

  • 8/3/2019 Site ion

    16/19

    Size of one room -9X3 m (Portable cabin)

    Nos of room- 36 nos

    Nos of person in one room 4 nos.

    Portable cabins use for toilet 8 nos

    Total Nos of toilets 24 nos (16 Bath + 16 Vt/C)

    Location of toilets Toilets are placed on east side of the plot because wind

    direction is from west to east so that it should not spoil the climate inside the labour

    camp due to bad smell coming out from sanitary block.

    Recreation and Dinning Recreation and Dining hall of size 9X27 M is provided

    between the labour accomodation for labours

    Ventilation circulation space Proper ventilation and circulation space is provided

    for all rooms of labour accommodation to maintain healthy and hygienic

    environment

    Plant, Machinery, Vehicle yard and workshop

    Plant machinery and vehicle yard is planned as shown in annexure-2, which will

    accommodate 10 nos. of dumpers, crawler, mobile crane, JCB and other equipment.

    For movement of these equipment proper roads are provided.

    Workshop of size 40X40 m for maintenance and repair of all above equipment are

    provide inside the plant, machinery & vehicle yard

  • 8/3/2019 Site ion

    17/19

    Two nos (one for labour camp St one for PMV yard) of entrance gate are provided to

    this plot with two security post

    Plot no 2

    Site office

    Site offices will be of portable cabin of size 9x3M which will accommodate all staff

    shown in organization chart. Site office will be located on west side of plot no.2 as

    shown in attached annexure-.2 which will nearest to construction site for effective

    monitoring & execution.

    Covered car parking for 30 nos of car is provided for staff cars 8. for visitors car

    between the site offices.

    Steel yard

    Size 40X25m

    Capacity 3000 MT

    Location Near the store & site office to keep proper watch on material transfer

    from the yard.

    Store

    Size - 40X25m

    Capacity For small miscellaneous material

  • 8/3/2019 Site ion

    18/19

    Location ln between steel yard & cement godown.

    Cement yard

    Size 25X25m

    Capacity 350 MT `

    Location Near the store & concrete batching plant area.

    Mobilization

    Take approval of site plan from higher authorities with proposed estimate.

    Obtain the approval of local authorities if requires as per contractual conditions.

    Also take clients concern for the temporary structures.

    Start clearance of area of site for the work as well as for the site office and labour

    camp.

    Mobilization of staff as per planning schedule prepared as per Annexure-3 given.

    Work out the quantities required for mobilization work as well as main work.

    Invite different quotations for different items and works.

    Prepare comparative statements for rate approval and analyze the matters work,

    time for supply for completion of work Give work orders accordingly for construction

    of temporary structures as well as main works preparatory related works.

    Determine requirement of Plant and equipment required for the works.

  • 8/3/2019 Site ion

    19/19

    Prepare schedule of Plant and machinery requirement as per Annexure3

    accordingly make inquiry for availability of plants in companys other sites or

    surplus

    Prepare rate analysis for hired plants Invites Quotation for hiring of equipment.

    JCB, Crawler, Tractor Dozer, Dumpers. Finalize the vendors based on prepared

    comparative statements and applicable different conditions.

    Search queries nearby the work site, their production capacity, arrangement of

    suppliers from quarries, determine logistics for transportation, Rate analysis for

    supply, negotiation with vendors and finalization of suppliers. Give Purchase order

    accordingly

    Deploy some departmental staff form local source as per requirement of particular

    section head with proper justification. Also record of performance of such staff.