Digital Gantry Signs Re-loaction
at Perth Airport
S&L Digital SignageS&L Digital Signage
C A S E S T U D Y
S&L Digital SignageS&L Digital Signage
C A S E S T U D Y
Offering a turnkey solution enables clients to all “Operatives Tickets” the “Plant Hire
select from any combination of our digital Companies”;
signage services to create a premium, large • Installation of relocated gantry's completed
format billboard and advertising solutions. as night works to minimise disruption to
The APN Digital gantry signs needed to be airport users;
relocated from Brierley Ave to Airport Drive at • Removal of and reinstatement of the digital
Perth Airport. This was a light engineering hardware - consisting of the tiles on the two
project involving the movement of two large gantry signs – including recommissioning.
scale digital gantry signs – they didn't need
moving far but the complexity of the project The unique challenges of this project related in
was such that multiple high risk services part to the Airport environment which is a 24/7
needed to be co-ordinated to ensure smooth operation and performing major works on the
sailing on this project. main entry/exit road into and out of the
Airport required precision timing with limited
The key turnkey elements of this works room for error.
included:
Our workshop team manufactured the various
• Design & Engineering of each unique elements of the metal works such as rio cages
element of the project including bolt cages, rio and base plates. These followed stringent
cages, base plates, excavation, footings and Engineering guidelines with post installation
the sign super-structures; certifications. Our shop drawings paid careful
• Engineering and manufacture of the signs attention to the need to create items that
columns to extend the gantry leg dimensions could be transported and lifted into place on
by xx mm; site within the parameters of a busy road
• Three phase power cables (supplied by environment.
others) run into pits at the base of each
footing, on the outer footings; Involvement of traffic management to manage
• Lift Plans & Works Movement Plans project the high risk nature of working in a high
managed to precise timings during the night at volume, time critical environment, was
off-peak times at the Airport; essential.
• OH&S & SWMS documents including
“Plant Certificates of Fitness” for all plant and
Our turnkey solution includes:
• Content
• Hardware
• Design & Engineering
• Digital Care
• Software
• Hosting
• Manufacture
• Permits & Traffic Mngt
• Project Management
• Installation
• Maintenance
S&L Digital SignageS&L Digital Signage
C A S E S T U D Y
To discuss your own digital signage strategyplease don’t hesitate to get in touch.