slide set 7 pwc mark hughes
DESCRIPTION
Kosova Lignite Power Investors Conference January 2010 • Immediate development of the Sibovc Lignite Field to supply existing plant and KRPP • Private sector participation in Kosova B January 2010 Slide 2 PricewaterhouseCoopers LLP Kosovo Lignite Power KRPP 1 Kosova B Kosova A Sibovc Key: Transaction components January 2010 Slide 3 PricewaterhouseCoopers LLP Kosovo Lignite PowerTRANSCRIPT
PricewaterhouseCoopers LLPJanuary 2010
Slide 2Kosovo Lignite Power
Transaction structureComponents
A. Construction of a new electric power generation plant, ‘Kosova e Re Power Plant’ (“KRPP”)- Estimated installed initial capacity of 500 MW- Possibility of expanding up to 1000 MW- Limited associated interconnection facilities
B. Immediate development of the Sibovc Lignite Field to supply existing plant and KRPP
C. Private sector participation in Kosova B
PricewaterhouseCoopers LLPJanuary 2010
Slide 3Kosovo Lignite Power
Transaction structureComponents
Sibovc
Kosova A
Kosova B
KRPP 1
DiSCo Domestic Market
Regional MarketKRPP2 Option
Key: Transaction components
PricewaterhouseCoopers LLPJanuary 2010
Slide 4Kosovo Lignite Power
Transaction structureComponents
Sibovc
Kosova A
Kosova B
KRPP 1
DiSCo Domestic Market
Regional MarketKRPP2 Option
Key: Transaction components
LSA
LSA
LSA
PPA
PPA
LSA
PricewaterhouseCoopers LLPJanuary 2010
Slide 5Kosovo Lignite Power
GenCoGenCo
MineCo & GenCo
MineCo
Sibovc
Kosova B
KR
PP 1
KR
PP
2 Option
• 2 companies but one consortium bid• No pre-determined corporate structure, but must work to ensure
efficient project delivery and operation
GoK
GoK
PricewaterhouseCoopers LLPJanuary 2010
Slide 6Kosovo Lignite Power
Main transaction agreements
MineCo GenCoKosovo B1
Kosovo B2
KRPP
DiSCo
Kosovo ALSA
LSA
LSA
PPA1
PPA2
Power
PPA3
PricewaterhouseCoopers LLPJanuary 2010
Slide 7Kosovo Lignite Power
Transaction structureMineCo: Sibovc lignite field
• Asset / staff / truck & shovel contract transfer• Transfer of existing Sibovc SW mining licence• Exclusive rights to mining development of Sibovc lignite field• GoK contribution: e.g. Bucket Wheel Excavators, Sibovc SW overburden
removal spend• MineCo will not assume pre-existing environmental / social liabilities• Access to Bardh mine for overburden disposal (MineCo responsible for
safe operation of spoil heaps and contribution to rehabilitation)• Duration of concession (40 years from KRPP COD)
PricewaterhouseCoopers LLPJanuary 2010
Slide 8Kosovo Lignite Power
Transaction structureMineCo: Contractual & pricing arrangements
• LSAs – non-discriminatory pricing across generation customers, supply to Kosovo A, B, KRPP 1 and other potential generators serving the domestic market
• Mining tonnage concession a function of licensed generation• 5, 10 or 15 year levellized price per tonne; regulated/indexed price
afterwards (for remaining 25-35 years)• Will schedule meetings with interested parties to receive indicative market
feedback prior to Draft RfP
PricewaterhouseCoopers LLPJanuary 2010
Slide 9Kosovo Lignite Power
Transaction structureKosova e Re Power Plant (KRPP)
• Commitment to construct new plant with estimated installed capacity of 500MW for domestic consumption (KRPP 1)
• Long-term PPA with Distribution & Supply company (DiSCo)
• On site of Kosovo B power plant
• To fulfill all EU-mandated environmental requirements and to achieve efficiencies in excess of 38%
• Proposed option to extend by further 500MW (KRPP 2)
PricewaterhouseCoopers LLPJanuary 2010
Slide 10Kosovo Lignite Power
KRPP contractual framework
Licences
O&M Agreement
Water Supply Agreement
Ash Disposal Agreement
Lignite Supply
Agreement
Power purchase
agreement
Connection Agreement
Financing
KRPP
PricewaterhouseCoopers LLPJanuary 2010
Slide 11Kosovo Lignite Power
Transaction structureKRPP – unit size
• Trade-off between supercritical favourable efficiency / emissions and commercial / technical viability in context of domestic and regional market
• Willing to listen to indicative market feedback prior to Draft RfP• Draft RfP will include specific required contracted operating and technical
characteristics- Rated capacity (MW)- Minimum heat rate, thermal efficiency in excess of 38%- CO2 and other emissions performance (EU Standards)- CCS ready
PricewaterhouseCoopers LLPJanuary 2010
Slide 12Kosovo Lignite Power
Transaction structureKRPP – offtake arrangements
• Long term PPA with Licensed Distribution and Supply business- Capacity up to 500MW- Duration – 20 years (circa)
• Kosovo Government support agreement with World Bank PRG / MIGA support- Support framework to extend beyond DiSCo privatisation
PricewaterhouseCoopers LLPJanuary 2010
Slide 13Kosovo Lignite Power
Transaction structureKRPP – site for construction
• Existing water supply from Iber-Lepenc canal
• Existing transmission connections, require expansion
• Site-sharing synergies with Kosovo B
• Existing ash-disposal pipeline connection to Mirash mine
Kosovo B 1 & 2
KRPPAsh Pile
New CoalYard
To mine
PricewaterhouseCoopers LLPJanuary 2010
Slide 14Kosovo Lignite Power
Transaction structureKRPP – Typical IPP PPA structure
KRPPCapital
repayment & return
Tax
Fuel
0
10
20
30
40
50
60
70
Ave
rage
pow
er p
rice
of P
PA (€
/MW
h 20
09 p
rices
)
Capital repayment & return Operations & Maintenance costTax Fuel
Variable Operations & Maintenance
cost
“Availability charge” €/MW
“Energy charge” €/MWh
Fixed Operations & Maintenance
cost
PricewaterhouseCoopers LLPJanuary 2010
Slide 15Kosovo Lignite Power
Transaction structureKosova B
• Long-term PPA with DiSCo with pre-determined Availability payments and competitively bid energy price (inclusive of LSA price)
• Long-term LSA with MineCo
• Immediate revenue source to GenCo
• Contribution of B assets by GoK in return for equity interest in GenCo
• Rehabilitation of plant to extend life to ensure EU-compliance and to provide domestic security of supply
• Offtake arrangements through PPA with provision for rehabilitation expenditure; step-up in Availability payments for expenditure approved by ERO
• Clearly identified assets, including facilities, PPA and generation licence
• Existing skilled workforce
PricewaterhouseCoopers LLPJanuary 2010
Slide 16Kosovo Lignite Power
What does a bid look like: preliminary views
• Bid price for KRPP Availability and Energy (including bid price LSA)• Bid price for Kosovo B1 and B2 Energy (pre-rehabilitation, including bid
price LSA)- pre-determined Availability payment and minimum Energy conversion
efficiency• Bid price LSA for Kosovo A• Pre-determined government stake
PricewaterhouseCoopers LLPJanuary 2010
Slide 17Kosovo Lignite Power
Bid evaluation criteria
For a given project volume / structure, bidders will be evaluated on:
• Lowest total cost of power supplied from KRPP
• Lowest cost of energy supplied from Kosovo B, pre-rehabilitation
• Lowest cost of lignite supplied to Kosovo A
NPV of 20 years’ capacity charge + energy charge * demand
NPV of [20] years’ energy charge * demand
NPV of Lignite price * Kosovo A demand until decommissioning
PricewaterhouseCoopers LLPJanuary 2010
Slide 18Kosovo Lignite Power
How to win this transaction
• Pre-qualify!• Engineer a successful bid
- Efficient Lignite mining plan and efficient operation- Efficient and effective KRPP construction plan for early and compliant
commercial operation- Realisation of operational synergies with B1 & B2- Efficient and effective B1 & B2 operation- Optimum cost of capital- Integrating value synergies from trading with regional markets through
successful development of KRPP 2 option