WP 1 – Definition of requirements and system analysis
Brussels, February 1st, 2017
Overview
Final Review Meeting 1 Feb 17
• Status: Completed(100%)• Length: 12 Months (From M1 to M12)• Leader: MHG
WP1. Objectives
Final Review Meeting 1 Feb 17
• Identify the users and specifically their needs and requirements• Define processes • Detail the data and metadata model covering the use of SLOPE• Define the hardware, equipment, sensors and mobile devices• Define the user Interface requirements• Define the system architecture to be used• Define the technical requirements
WP1. Tasks
Final Review Meeting 1 Feb 17
•Task 1.1 - Users and System requirements – ITENE• Partners: GRAPHITECH, CNR, COAST, MHG, BOKU, FLY, GRE, TRE
• Task 1.2 Hardware and equipment definition – GRAPHITECH• Partners: CNR, COAST, MHG, BOKU, FLY, GRE, ITENE
• Task 1.3 Human Machine Interface (HMI) definition – GRAPHITECH• Partners: MHG, GRE, TRE, ITENE
• Task 1.4 Mountainous Forest inventory data model definition – CNR• Partners: GRAPHITECH, COAST, MHG, BOKU, FLY, GRE, TRE
• Task 1.5 - System Architecture - MHG• Partners: GRAPHITECH, FLY, TRE, ITENE
Final Review Meeting 1 Feb 17
T 1.1 Users and System requirements
Length: 3 Months (From M1 to M3)Partners: ITENE, GRAPHITECH, CNR, COAST, MHG, BOKU, FLY, GRE, TREOutput: D.1.01 Users Requirements ReportStatus: Deliverable submitted
Define users and system requirements : • Defines users and user groups and functionalities• Gathers information about user requirements to guide further
development of the SLOPE Forest Information System (FIS)• Total: 23 questionnaires created and documented. Locations: Austria,
Italy (Trento), Finland, Ireland
T1.1 User group specifications
Functions and user groups mapped
Final Review Meeting 1 Feb 17
Final Review Meeting 1 Feb 17
T 1.2 Hardware and equipment definition
Length: 3 Months (From M1 to M3)Partners: GraphiTech, CNR, COAST, MHG, BOKU, FLY, GRE, ITENEOutput: D.1.04 Technical Requirements ReportStatus: Deliverable submitted
Define the Hardware and Software equipment: • Defines tools to collect forest information before harvesting• Defines tools to collect timber information during the harvesting• Defines tools for resources tracking
Final Review Meeting 1 Feb 17
T1.2 Hardware specificationsIdentify for each workflow step:
• Instruments• Tools• Hardware• Data types
Final Review Meeting 1 Feb 17
T 1.3 Human Machine Interface (HMI) definition
Length: 3 Months (From M2 to M4)Partners: GraphiTech, MHG, GRE, TRE, ITENEOutput: D.1.02 Human Machine InterfaceStatus: Deliverable submitted
Define the user interface for the whole SLOPE system: • Defines user interface needs• Defines web user interface requirements• Defines in-vehicle and on-field devices interfaces• Specifies all user interfaces that will be in slope platform
Final Review Meeting 1 Feb 17
T1.3 UI specifications
Desktop
Mobile In-vehicle
Final Review Meeting 1 Feb 17
T 1.4 Mountainous Forest inventory data model definition
Length: 4 Months (From M2 to M6)Partners: CNR, GRAPHITECH, COAST, MHG, BOKU, FLY, GRE, TREOutput: D.1.03 Data and metadata model reportStatus: Deliverable submitted
Define data and metadata model for the FIS: • Defines data and metadata model requirements that will be
implemented in T5.1• Describes data format standards to be used• Defines datasets and input sources for database population
Final Review Meeting 1 Feb 17
T 1.4 Data specificationsTABLE A1: FOREST
Final Review Meeting 1 Feb 17
T 1.5 System Architecture
Length: 11 Months (From M2 to M12)Partners: MHG, GraphiTech, FLY, TRE, ITENEOutput: D.1.05 System architecture specificationsStatus: Deliverable submitted
Design the technology specification of the system architecture:• Specify applications and technologies to be used• Specify design principles• Design model and interfaces for application integrations in
different integration levels• Design deployment platform
T1.5 Architecture overview
Final Review Meeting 1 Feb 17
T1.5 Component diagram
Final Review Meeting 1 Feb 17
WP1 Deliverable submissions
01 02 03 04 05 06 07 08 09 10
ITENE:Task 1.1: D1.01Users Requirements Report
Technical meeting in
Mikkeli
GRAPHITECH:Task 1.3: D1.02HumanMachine Interface
MHG:Task 1.5: D1.05System ArchitectureSpecifications
Final Review Meeting 1 Feb 17
CNR:Task 1.4: D1.03Data and Meta Data modelReport
GRAPHITECH :Task 1.2: D1.04TechnicalRequirementsReport
Final Review Meeting 1 Feb 17
WP1 Summary• All deliverables can be found from 04_Final_Deliverables folder on Dropbox• All deliverables finalized correctly
• Some problems on start of the project:• One partner (Kesla) left from consortium. Kesla was Task 1.2 leader and
contributor in many WP1 tasks.• Some feedback and communication delays on first 6 months
• Objectives reached:• Specifies user groups and user requirements• Specifies tools and hardware to use• Specifies user interface guidelines• Specifies data model and used standards• Specifies technology and scalable SOA based system architecture for the
SLOPE FIS development
Open Discussion
Final Review Meeting 1 Feb 17
Final Review Meeting 1 Feb 17
Contact info
Veli-Matti Plosila [email protected]
Seppo Huurinainen [email protected]
Thank you for your attention