small hydro overview

Upload: saptharishi-manikandan

Post on 14-Apr-2018

222 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/27/2019 Small Hydro Overview

    1/98

    Great Lakes Institute of Energy Management and ResearchPlanning, Policy Regulatory andoperational Aspects ofSmall Hydro

    Dr. P. SaxenaDirectorMINISTRY OF NEW AND RENEWABLE ENERGY21st March,2012

  • 7/27/2019 Small Hydro Overview

    2/98

    Out Line of Presentation

    Indian Energy Scenario

    Over all Renewable Energy Development in India

    and 12th Plan Projections

    Hydro Power Policy and Regulations in India

    Classification, Planning and operational aspectsof Small Hydro

  • 7/27/2019 Small Hydro Overview

    3/98

    THE CHALLENGE

    Developing countries are facing formidable

    challenges in meetings its energy needs and

    providing adequate energy ofdesired quality in a

    sustainable manner and at

    reasonable costs.

  • 7/27/2019 Small Hydro Overview

    4/98

    INDIAN ENERGY SCENARIO

  • 7/27/2019 Small Hydro Overview

    5/98

    India

    India has a geographical area of about

    3.28 million sq. km.

    1.21 billion population

    28 States and 7 Union Territories with 640

    districts

    About 30% of Indias population lives in 7742

    towns and 70% in about 0.608 million villages.

  • 7/27/2019 Small Hydro Overview

    6/98

    Rural population - about 800 million

    Total villages - 610,000

    Unelectrified villages - 95,000

    Unelectrified households - 45% total

    56% rural

    INDIA-SOME FACTS

  • 7/27/2019 Small Hydro Overview

    7/98

    TOTAL INSTALLED CAPACITY 1,90,766 MW

    GROSS GENERATION 850 BUs

    PER CAPITA CONSUMPTION 733 kwh/ Annum

    ENERGY SHORTAGE about 8.2 %

    PEAKING SHORTAGE about 10.5 %

    INDIAN POWER SCENARIO

  • 7/27/2019 Small Hydro Overview

    8/98

    Indian Power Sector at a Glance

    Thermal

    1,04,816

    Hydro

    38,848

    Gas

    17,742

    Renewable

    23379

    Nuclear

    4780

    As on 29.2. 2012

    Source: CEA

    Total installed capacity : 1,90,766 MW

    Renewable contributes 23379 MW12 %

    If we take large hydro under RE32%

  • 7/27/2019 Small Hydro Overview

    9/98

    Electricity demand growing @ 8% annually

    Capacity addition of about 100,000 MW requiredin the next 10 years

    Challenge is to meet the energy needs in asustainable manner

    POWER GROWTH PERSPECTIVE

  • 7/27/2019 Small Hydro Overview

    10/98

    PROPOSED CAPACITY ADDITION 20 22

    Total 1,00,000 MW

  • 7/27/2019 Small Hydro Overview

    11/98

    Renewable Power Potential

    S. No. Resource Estimated Potential(In MWeq.)

    1. Wind Power 49,000

    2. Small Hydro Power (up to 25 MW) 15,000

    3. Bio-Power:Agro-Residues 17,000

    Cogeneration - Bagasse 5,000

    Waste to Energy:

    - Municipal Solid Waste to Energy

    - Industrial Waste to Energy

    2,600

    1,280

    Sub-Total 89,880

    4 Solar Energy >100,000

    30-50 MW/ sq. km.

    Total >1,89,880

  • 7/27/2019 Small Hydro Overview

    12/98

    12

    Plan wise Renewable Power GrowthBeginning

    of10th Plan(MW)

    1.4.2002

    Beginning

    of11th Plan(MW)

    1.4.2007

    Target

    11th

    Plan

    (MW)

    11th plan

    Achvmnt.till 31.12.11(MW)

    Cumulative

    Achvmnt.up to 31.12.11(MW)

    Wind 1,628 7,092 9,000 8,598 16,078

    SmallHydro

    1,434 1,976 1,400 1,322 3,252

    Bio power 389 1,184 1,780 1,841 3,123.79

    Solar 2 3 200** 115 189.98

    Total 3,453 10,255 12,380 11,876 22,643.90

    106% growth during 11th Plan

  • 7/27/2019 Small Hydro Overview

    13/98

    Indian Renewable Energy at a Glance

    As on 29.2. 2012

    Source: CEA

  • 7/27/2019 Small Hydro Overview

    14/98

    14

    12th Plan ProjectionsInstalled Capacities in MW

    Source Likely Installedcapacity by end of

    11th Plan

    31.3.2012

    Capacity additionTarget for 12th

    Plan

    (2012-17)

    Target installedcapacity at the end

    of 12th Plan

    % of Potentiallikely to be

    harnessed at the

    end of 12th Plan

    Wind power16,300

    15,000 31,300 64%

    Small Hydro 3,390 2,100 5,500 37%

    Biomass Power1,125

    500 1,700 11%

    Bagasse

    Cogeneration

    1,866

    1,400 3,20064%

    Waste to Power104 500

    600 22%

    Solar Power 21510,000

    10,200 10%

    TOTAL 23,000 29,500 52,500 28%

  • 7/27/2019 Small Hydro Overview

    15/98

    The Government aim is that 10-12 percent of thegrid interactive power generation installed capacity

    should come from renewables

    Deployment of renewable power during the 11thPlan has made it the second largest source after

    conventional power.

    A target of 14,000 MW capacity addition has been

    achieved during the 11th Plan.

    GRID INTERACTIVE RENEWABLE POWER

    3

  • 7/27/2019 Small Hydro Overview

    16/98

    16

    Wind Power

    Potential : 49,000 MW

    Achievement : 15,683 MW

    11th Plan Target/ Achievement: 9,000 MW/ 7,897 MW

    Deployment target 12th Plan : 15,000 MW.

    Strategy:

    Accelerated depreciation to go away

    GBI scheme to be reviewed after 11th Plan and continued

    for 12th Plan for up to 4,000 MW capacity projects.

    Wind Resource activities to be substantially increased.

    Evacuation infrastructure to be developed.

    Separate RPO for wind. Enforce RPO. Make REC work.

    Work towards competitive bidding.

  • 7/27/2019 Small Hydro Overview

    17/98

    17

    Small Hydro Power

    Potential : 15000 MW

    Achievement : 3198 MW (as on 31.10. 11)

    11th Plan Target/ Achievement: 1400 MW / 1178 MW

    Deployment target 12th Plan : 2100 MW.

    Strategy:

    Private sector participation

    Performance based incentivisation for State sector / NE

    Small plants to get higher support.

  • 7/27/2019 Small Hydro Overview

    18/98

    18

    Biomass Power

    Potential : 17000 MW

    Achievement : 1097 MW

    11th Plan Target/ Achievement: 500 MW/ 567 MW

    Deployment target 12th Plan : 500 MW.

    Strategy:

    Promotion of small capacity biomass projects with

    biomass linkage and captive plantations.

  • 7/27/2019 Small Hydro Overview

    19/98

    19

    Bagasse Cogeneration

    Potential : 5000 MW

    Achievement : 1854 MW

    11th Plan Target/ Achievement: 1200 MW/ 1155 MW

    Deployment target 12th Plan : 1400 MW.

    Strategy:

    Promotion of BOOT/BOLT model in cooperative sectorsugar mills.

    Promotion of optimum cogeneration potential in small sizesugar mills (

  • 7/27/2019 Small Hydro Overview

    20/98

    20

    Solar Energy and Solar Mission

    Potential : 20-50 MW/ sq. km

    Achievement : 120 MW

    Over 18 lakh SPV Systems installed / distributed

    11th Plan Target : 1100 MW

    (incl. 2013)

    Target for 12th Plan : 4000 MW.

    Target for 13th Plan : 15000 MW.

  • 7/27/2019 Small Hydro Overview

    21/98

    HYDRO POWER

    21

    Hydropower is a renewable, non-polluting and

    environmentally benign source of energy.

    It is perhaps the oldest renewable energy techniquefor electricity generation.

    It represents inflation free energy with matured

    technology characterized by highest prime moverefficiency and spectacular operational flexibility.

  • 7/27/2019 Small Hydro Overview

    22/98

    Hydro Resource in India

    Hydro potential in India is about 150,000 MW

    Small Hydro Potential is over 15,000MW

    Ministry of Power deals with large hydro projects

    MNRE is responsible for small hydro up to 25 MW

    Water is a State Government subject

    Hydropower installed capacity: 38,848 MW

    Small hydro installed capacity: 3,342 MW

  • 7/27/2019 Small Hydro Overview

    23/98

    INDUS RIVER

    GANGA RIVER

    NEPAL

    BHUTAN

    BANGLA

    DESH

    BRAHMAPUTRA

    RIVER SYSTEM

    CENTRAL INDIAN

    RIVER SYSTEM

    EAST FLOWING

    RIVER SYSTEM

    WEST FLOWING

    RIVER SYSTEM

    SHARAVATHI

    KUTTIYADI

    PERIYAR

    CAUVERY

    PENNER

    KRISHNA

    GODAVARI

    TAPI

    NARM

    ADA

    MAHI

    BANA

    S

    SABARM

    ATI

    CHAMBAL

    BETW

    A

    MAHANADI

    DAMODARSONR

    SUBERN

    REKHA

    BAITA

    RNI

    BRAHMANI

    BARAKB

    RAHM

    APUT

    RATISTA

    C H I N A

    ( T I B E T )

    KAMENG

    SUBANSIRI

    LUHIT

    DIBANG

    GANGA

    DELHI

    YAMUNA

    SUTL

    EJ

    BEASR

    AVI

    CHENABJHELUM

    INDUS

    INDU

    S DIHANG

    SYSTEM

    SYSTEM

    GANGA

    880 920960

    680 720360

    320

    280

    240

    200

    760

    800 840

    MYANMAR

    MAJOR RIVER SYSTEMS OF INDIA

  • 7/27/2019 Small Hydro Overview

    24/98

    Hydropower Definition & Applications

    MW

    Micro0.1

    25

    0

    3

    15

    1

    Mini

    Small

    Large

    Distributed Generation/ grid-sales/ DG-RE

    systems with grid-support/ Off-grid RE

    Grid-Sale/ REC/ Captive/ Third party sales

    Inter/ Intra State grid Sale/ Merchant Sale

    Classification of Small Hydro (Size wise)

    Pico - < 5 kW

    Micro - > 5 kW and upto 100 kW

    Mini - > 100 kW and upto 2 MW

    Small - > 2 MW and upto 25 MW

    Classification of Small Hydro (Head wise):

    Ultra Low - < 3 mtrs

    Low 3 mtrs and upto 30 mtrs

    Medium Between 30 and 75 mtrs

    High > 75 metres and above

  • 7/27/2019 Small Hydro Overview

    25/98

    HYDROPOWER DEVELOPMENT

    Sl.

    No.

    States Central Sector State Sector Private sector Total

    No. MW No MW No. MW No. MW

    1. Himachal Pradesh 2 816 7 892 6 749 15 2457

    2. Jammu & Kashmir 4 2450 4 1473 0 0 8 3923

    3. Uttarakhand 12 4374 7 1655 5 829 24 6858

    4. Punjab 0 0 1 168 1 75 2 243

    5. Madhya Pradesh 3 166 0 0 0 0 3 1666. Andhra Pradesh 0 0 3 1560 0 0 3 1560

    7. Kerala 0 0 6 373 0 0 6 373

    8. Karnataka 0 0 2 400 0 0 2 400

    9. West Bengal 1 120 2 66 0 0 3 186

    10. Sikkim 1 520 0 0 10 1935 11 2455

    11. Arunachal Pradesh 3 1610 0 0 23 7969 26 9579

    12. Assam 0 0 1 150 0 0 1 150

    13. Manipur 2 1566 0 0 0 0 2 1566

    14. Tamil Nadu 0 0 1 500 0 0 1 500

    15. Meghalaya 0 0 1 54 1 450 2 504

    16. Total 28 11,622 35 7291 46 12,007 109 30,920

    12th Plan Target for Hydro Power Generation

  • 7/27/2019 Small Hydro Overview

    26/98

    HYDROPOWER CLASSIFICATION

    Pico 5 kW & below

    Micro 100 kW & below

    Mini 2000 kW & below

    Small 25000 kW & below

    Medium 100,000 kW & below

    Large above 100,000 kW

    Indian hydro is 115 year old.

    First hydro in Darjeeling 1897.

    Biggest capacity today is Naptha Jhakri Hydroproject of 1500 MW in Himachal Pradesh

  • 7/27/2019 Small Hydro Overview

    27/98

    Private sector participation in the renewables started

    in early 90s

    MNES issued guidelines in 1993-94 for purchase ofpower from renewables, wheeling, banking etc.

    Selected states announced policies for private sectorparticipation

    Most of the SEBs reorganized and regulators came inexistence.

    Electricity Act Announced in 2003

    PRE ELECTRICITY ACT 2003

  • 7/27/2019 Small Hydro Overview

    28/98

    Hydro policy was announced in1998 and revised in Nov.2008.

    Small hydro needs to be promoted.

    Projects above 100 MW to be allotted by States through tariff

    based bidding only.

    Projects below 100 MW can be allotted through MOU route.

    Hydro projects to be allotted by States in a transparent manner.

    Projects costing more than Rs. 2500 crore require CEA

    concurrence.

    Regu lat ions in Hydro Secto r

  • 7/27/2019 Small Hydro Overview

    29/98

    SMALL HYDRO POWER

    29

    It is recognized that small hydro power projects can

    play a significant role in meeting energy requirements

    in remote and hilly areas where extension of grid is

    uneconomical.

    Small hydro can contribute in capacity addition of

    hydropower in short time frame.

  • 7/27/2019 Small Hydro Overview

    30/98

    Electricity Act in 2003

    National Electricity Policy in 2005

    Tariff Policy in 2006

    POST- ELECTRICITY ACT 2003

  • 7/27/2019 Small Hydro Overview

    31/98

    Salient features of Electricity Act - 2003

    Laws relating to Generation, Transmission,

    Distribution, Trading and use of Electricity

    Facilitates De-regulation of the Power Sector

    Permits Private-Sector Participation

    Identifies the Regulatory Framework

    Creates the Regulatory Authorities

    Establishes PGCIL as the Grid Operator

  • 7/27/2019 Small Hydro Overview

    32/98

    Salient features of Electricity Act - 2003

    Recognized the role of Renewable Energy for supply of

    Power to Utility Grid / Stand-alone System

    Preferential Tariff and Quota for Renewable Energy

    Section 86(1): SERC to specify a percentage of electricity

    to be purchased from renewables by a

    distribution licensee.

  • 7/27/2019 Small Hydro Overview

    33/98

    The National Electricity Policy aims at:

    Access to electricity available for all households in thenext five years.

    Availability of Power- Demand to be fully met by 2012.

    Supply of Reliable and Quality Power.

    Per capita availability of electricity to increased to over1000 units by 2012.

    Minimum lifeline consumption of 1 unit/household/day by2012.

    THE NATIONAL ELECTRICITY POLICY

  • 7/27/2019 Small Hydro Overview

    34/98

    About Renewables Section 2.2.20 & 5.12

    Feasible potential of non-conventional energy resourcesneeds to be exploited

    With a view to increase share of renewables, efforts willbe made to encourage private sector participation

    through suitable promotional measures.

    SERCs to provide suitable measures for connectivity withgrid and sale of electricity to any person , and promoteco-generation

    THE NATIONAL ELECTRICITY POLICY

  • 7/27/2019 Small Hydro Overview

    35/98

  • 7/27/2019 Small Hydro Overview

    36/98

  • 7/27/2019 Small Hydro Overview

    37/98

    TECHNOLOGY SPECIFIC PARAMETER FOR SHPCERC Regulation 2009Capital Cost The normative capital cost for SHP during first year of control period(FY 2009-10) shall be as follows:Region project size capital cost

    (Rs. Lac/MW)Himachal Pradesh Below 5 MW 700Uttarakhand andNE States 5 MW to 25 MW 630Other States Below 5 MW 5505 MW to 25 MW 500

  • 7/27/2019 Small Hydro Overview

    38/98

    TECHNOLOGY SPECIFIC PARAMETER FOR SMALLHYDRO PROJECTS (SHP)Capacity Utilization Factor (CUF) CUF shall be 45% for SHP located in HimachalPradesh, Uttarakhand and North Easter States For other States CUF shall be 30%

    Normative CUF is net of free power to the home state if any, and anyquantum of free power if committed by the developer over and above thenormative CUF shall not be factored into the tariffAuxilliary consumption Normal Auxilliary Consumption for SHP shall be 1.0%

  • 7/27/2019 Small Hydro Overview

    39/98

    TECHNOLOGY SPECIFIC PARAMETER FOR SMALLHYDRO PROJECTS (SHP)Operation and Maintenance Expenses Normative O&M expenses for the first year of control period(FY 2009-10) Region project size capital cost

    (Rs. Lac/MW)Himachal Pradesh Below 5 MW 21Uttarakhand andNE States 5 MW to 25 MW 15Other States Below 5 MW 175 MW to 25 MW 12

    Normative O&M expenses shall be escalated at the rate of 5.72%per annum for the tariff period for the purpose of determinationof levellised tariff.

  • 7/27/2019 Small Hydro Overview

    40/98

    GOI POLICY ON HYDROPOWER DEVELOPMENT

    Projects held up for environment and forest clearance,

    concerned State Govt./developer to get the timely E&Fclearances.

    1% of free power with a matching 1% support from Stategovernment for local area development to the affected local

    population.

    Problems such as local agitation (law & order), landacquisition etc. need be resolved by concerned State

    Government.

    Project developer to seek long term open access by indicatingat least region(s) in which they intend to supply their powerto enable development of transmission system.

  • 7/27/2019 Small Hydro Overview

    41/98

    SHP Planning and Layouts

    41

    Pl i SHP

  • 7/27/2019 Small Hydro Overview

    42/98

    Planning - SHP

    For a systematic, time bound, duly shared between

    Government, Social and Private Sectors, master planare required.

    It is an inventory of all possible sites.

    Provides priority or ranking for speed development.

    Provides cluster approach.

    Provides financial requirement.

    Provides grid network strengthening.

  • 7/27/2019 Small Hydro Overview

    43/98

    Assessment of SHP potential of existing irrigation dams and

    canals.

    Assessment of potential as run off river schemes

    Assessment of potential sites for rural electrification.

    Compilation of the above mentioned activities with

    prioritization of identified SHP sites.

    Creating of spatial database using Geographic InformationSystems (GIS) for the state incorporating various themes

    including identified SHP sites.

    Master Plan

    R f Ri SHP Sit

  • 7/27/2019 Small Hydro Overview

    44/98

    Run-of-River SHP Sites

    Run-of-river (ROR) hydropower implies that there is

    no (or minimal) storage reservoir.

    The instantaneous flows that are passed through the

    powerhouse are essentially the flows that occur in

    the stream at the intake and flows downstream of

    the powerhouse are virtually identical to pre-

    development flows.

    Run-of-river facilities use low dams to provide

    limited storage of water at most daily pondage.

    In a run-off river SHP scheme, through a diversion

    structure water is diverted to water conductor

    system to the powerhouse.

  • 7/27/2019 Small Hydro Overview

    45/98

  • 7/27/2019 Small Hydro Overview

    46/98

    T t ti L t F R R S h (R SHP)

  • 7/27/2019 Small Hydro Overview

    47/98

    Tentative Layout For RoR Scheme(Rampur SHP)

  • 7/27/2019 Small Hydro Overview

    48/98

  • 7/27/2019 Small Hydro Overview

    49/98

    Dam Toe SHP Sites

  • 7/27/2019 Small Hydro Overview

    50/98

    Dam Toe SHP Sites The dam provides the means to regulate the flow of water, and

    can add to the height of the source of water thereby

    effectively increasing the head (H).

    Reservoir created by the dam may store and regulate stream

    flows to make them more timely for power production, and toserve other purposes for water resource development.

    Powerhouse is located at the toe of the dam and it utilizes thedischarge release through sluice primarily meant for irrigation

    and the head available (water level difference between

    upstream and downstream of reservoir) for power generation.

  • 7/27/2019 Small Hydro Overview

    51/98

  • 7/27/2019 Small Hydro Overview

    52/98

  • 7/27/2019 Small Hydro Overview

    53/98

  • 7/27/2019 Small Hydro Overview

    54/98

  • 7/27/2019 Small Hydro Overview

    55/98

    Layouts

    T f H d

  • 7/27/2019 Small Hydro Overview

    56/98

    Types of Hydropower

    Run of River:

    Run of river hydropower development

  • 7/27/2019 Small Hydro Overview

    57/98

  • 7/27/2019 Small Hydro Overview

    58/98

  • 7/27/2019 Small Hydro Overview

    59/98

    Using existing facilities:

    Typical Arrangement of canal fall small hydropower

    development

  • 7/27/2019 Small Hydro Overview

    60/98

  • 7/27/2019 Small Hydro Overview

    61/98

    Reservoir

    Based HydropowerDevelopment

  • 7/27/2019 Small Hydro Overview

    62/98

  • 7/27/2019 Small Hydro Overview

    63/98

  • 7/27/2019 Small Hydro Overview

    64/98

  • 7/27/2019 Small Hydro Overview

    65/98

  • 7/27/2019 Small Hydro Overview

    66/98

  • 7/27/2019 Small Hydro Overview

    67/98

  • 7/27/2019 Small Hydro Overview

    68/98

  • 7/27/2019 Small Hydro Overview

    69/98

  • 7/27/2019 Small Hydro Overview

    70/98

  • 7/27/2019 Small Hydro Overview

    71/98

  • 7/27/2019 Small Hydro Overview

    72/98

  • 7/27/2019 Small Hydro Overview

    73/98

  • 7/27/2019 Small Hydro Overview

    74/98

  • 7/27/2019 Small Hydro Overview

    75/98

  • 7/27/2019 Small Hydro Overview

    76/98

    Dam toe project in MP

  • 7/27/2019 Small Hydro Overview

    77/98

    St t i P t ti l d A hi t

  • 7/27/2019 Small Hydro Overview

    78/98

    State-wise Potential and Achievement

    State Sites(Nos.) Potential(MW)

    Achievement

    (MW)

    Andhra Pradesh 497 560 192.63

    Arunachal Pradesh 566 1333 78.83

    Assam 119 238 31.11

    Bihar 95 213 59.80

    Chhatisgarh 184 993 19.050

    Goa 6 6.5 0.050

    Gujarat 292 196 15.600

    Haryana 33 110 70.100

    Himachal Pradesh 536 2268 440.96

    State-wise Potential and Achievement

  • 7/27/2019 Small Hydro Overview

    79/98

    State wise Potential and Achievement

    State Sites

    (Nos.)

    Potential

    (MW)

    Achievement

    (MW)

    Jammu & Kashmir 246 1417 130.59

    Jharkhand 103 208 4.050

    Karnataka 309 2029 856.25

    Kerala 245 704 141.67

    Madhya Pradesh 2 99 803 86.16

    Maharashtra 255 732 279.92

    Manipur 114 109 5.450

    Meghalaya 101 229 31.030

    Mizoram 75 166 36.470

    Nagaland 99 196 28.670

    State-wise Potential and Achievement

  • 7/27/2019 Small Hydro Overview

    80/98

    State Sites

    (Nos.)

    Potential

    (MW)

    Achievement

    (MW)

    Orissa 222 295 64.30

    Punjab 237 393 154.50

    Rajasthan 66 57 23.85

    Sikkim 91 265 52.11

    Tamil Nadu 197 659 103.05

    Tripura 13 46 16.01

    Uttar Pradesh 251 460 25.10

    Uttaranchal 444 1577 146.82

    West Bengal 203 396 98.40

    A&N Island 7 8 5.250

    Total 5,718 15,384 3197.79

    Focus States

  • 7/27/2019 Small Hydro Overview

    81/98

    Focus States

    Karnataka

    Himachal Pradesh

    Andhra Pradesh

    Uttarakhand

    Kerala

    Maharashtra

    Chattisgarh

    Arunachal Pradesh

    SHP Programme

  • 7/27/2019 Small Hydro Overview

    82/98

    SHP Programme The MNRE has been providing financial support / subsidy for

    following activities to develop the SHP sector :

    Resource Assessment, Detailed Survey & Investigation, DPR

    Preparation and perspective plan for States

    Capital Subsidy to State Sector Projects

    Subsidy for Commercial Projects

    Renovation & Modernization of old SHP projects (State Sector)

    Micro Hydel &Water Mills

    Capacity building

    PRIVATE SECTOR INITIATIVES

  • 7/27/2019 Small Hydro Overview

    83/98

    PRIVATE SECTOR INITIATIVES

    Worlds largest SHP development programmethrough private sector participation

    Policies for private sector participation forSHP development announced by 23 States

    Over 8500 MW capacity SHP sites offered/allotted to private sector for their development

  • 7/27/2019 Small Hydro Overview

    84/98

    PRIVATE SECTOR INITIATIVES299 SHP projects aggregating 1528 MW

    commissioned by the private sector.

    Karnataka 743.70 MW

    Andhra Pradesh 106.03 MW

    Himachal Pradesh 296.10 MW

    Maharashtra 85.00 MW

    Uttaranchal 49.50 MW

    Punjab 29.25 MWWest Bangal 6.45 MW

    Orissa 32.0 MW

    Tariff Pol icy in Top Ten SHP Potent ial States

  • 7/27/2019 Small Hydro Overview

    85/98

    State Wheeling Banking TP Sale Buy-back and

    Annual

    Escalation

    H.P. 2% of energy

    generated

    Permitted with

    additional

    charges

    Not permitted Rs. 2.50/ kWh

    Uttaranchal To be determined by

    ERCU; 10%

    Free if soled to UPCL

    or rural distribution

    2 Months

    monetised at

    average pooled

    price

    Permitted to

    HT consumer,

    rural areas,

    out side State

    14% IRR

    Jammu &

    Kashmir

    10% now, to be

    decided

    by SCRC. No charges

    for sale to PDD or

    local grid

    Permitted for 2

    months

    Permitted

    HT

    consumers

    Negotiable

    Karnataka 20% of energy

    generation

    1 year Rs. 2.90/ kWh in

    the first year

    Maharashtra Permitted with no

    charges

    for first 3 years and

    1% after that

    Permitted Permitted Rs. 2.84/ kWh in

    the first year; AE

    Rs. 0,03 per unit

    /year till 10 years

  • 7/27/2019 Small Hydro Overview

    86/98

  • 7/27/2019 Small Hydro Overview

    87/98

    Project Development Cycle Case of HP Allotmentof Sites

  • 7/27/2019 Small Hydro Overview

    88/98

    of SitesIdentification

    of Site

    Development ofPFRHPSEB/

    Consultant/DeveloperHIMURJA

    Developer

    self identified

    Notification ofSite Allotment

    HIMURJA Website

    Local and NationalNews Papers

    Clearance FromIPH / Power Dept

    Investigation by

    Developer of Site

    Head & DischargeInvestigationEconomic Viability andBroad Site Planning

    Development &

    Submission of

    Application/Bid

    Evaluation ofApplication/

    Bid by HIMURJA

    Technical

    30%`Financial60%`

    Interview10%`

    Allotment ofProject

    Letter of Intent

    MoUProjectDevelopment

    Agreement

    Project Allocation

    Clearances Gram

    Panchayat and Wild Life

    Within 30 Days of

    allotment

    Preparation of

    Detailed Project Report

    Major Delays

    Delays often happen here due toambiguity in policy, political transitions orchange in management at the SNA

    In case of HP, allotment is still to be madefor sites notified in 2008

    Delays

    As theutility may not

    give priority to

    the task

    Go/ No Go Clearance

    Doubling of effort

    Developer makes PFR again

    before biddingThese projects limit planning for

    evacuation

    Responsibility of

    HIMURJA

    (SNA)Has to

    be done by

    Developer

    Project Development Cycle Case ofHP Clearances, Project Construction and

    C i i i Delay No need for

  • 7/27/2019 Small Hydro Overview

    89/98

    Commissioning

    Development ofDPR

    Developer/Consultant

    Broad DPRPreparation- Consultant

    DetailedEngineering

    6 Months to1 Year

    1to 2 Years

    DPR forwarded toHIMURJA for TEC

    Clearance TEC forwardedto HPSEB

    TEC Clearancefrom HPSEB

    3-4 Months

    Request to StateGovernment for signingof IA (Implementation

    Agreement)

    1-2 Months

    ImplementationAgreement

    Punjab also has a

    Tripartite agreement

    between developer,

    PEDA & irrigation

    department

    Clearances

    PPA, LandSection 118 (in HP) &FisheriesForest & PCBIrrigation & Water resourcesIndustrial licensingLabour permits

    Utility approval for inter connectionLocal government level approvalUsage of explosive for excavation

    Land

    Acquisition (Forest,

    Private, Panchayatand Govt)

    FinancialClosure

    Appointment ofEPC ContractorsCivil & EME

    ProjectConstruction

    ProjectCommissioning

    Major Delays in forest &

    land acquisition

    DelayLow priority

    for HPSEB

    DelayNo need for

    sending DPR through

    HIMURJA

    Coordination delays between civil and EME Contractors Need for

    integrated service providers these are usually more expensive but

    commissioning takes place earlier

    Delay - Development of access infrastructure roads to project

    site, use of cable based trolley systems for conveying material tofore bay tank, weir, penstock

    Restrictions from forest department on cutting of trees

    DelayState government usuallytakes its own sweet time

    Getting equity for 1st

    time developers an

    issue

  • 7/27/2019 Small Hydro Overview

    90/98

    EQUIPMENT MANUFACTURING STATUS

  • 7/27/2019 Small Hydro Overview

    91/98

    EQUIPMENT MANUFACTURING STATUS India has a wide base of manufacturers of equipment for hydro

    power projects.

    State-of-the-art equipment are available indigenously.

    15 manufacturers produce almost the entire range and type of

    hydropower equipment.

    Most of the worlds leading equipment manufacturers have theirfactory and or offices in India.

    There are about 5 manufactures that are producing micro hydroand watermill equipment.

    PERFORMANCE TESTING OF SHP STATIONS

  • 7/27/2019 Small Hydro Overview

    92/98

    The small hydro project when commissioned is required to betested for its performance by AHEC, IIT Roorkee.

    The capital subsidy is released after project attaining thefollowing:

    Overall performance of the station should be satisfactory.

    Plant equipment should conform to Indian/International standards.

    Weighted average efficiency of generating units should, with certainexceptions, be at least 75%.

    Project should have attained 80% of projected generation for a minimum

    of 3 months at a stretch.

    However it is not mandatory condition for performance testing forlarge hydropower projects

    ESTABLISHMENT OF R&D HYDRAULIC

    TURBINE LABORATORY

  • 7/27/2019 Small Hydro Overview

    93/98

    TURBINE LABORATORY

    R&D hydro turbine Laboratory of International

    level being established at AHEC IIT Roorkee turbine-model testing,

    research & development (R&D),

    human resource development (HRD) verification of designs,

    generation of design data,

    design validation through CFD analysis,

    Witnessing tests on turbines/pumps in field Laboratory is expected to be fully functional by the

    end of year 2012.

    STANDARDS FOR SMALL HYDRO

  • 7/27/2019 Small Hydro Overview

    94/98

    SHP needs to be made profitable and a long-term investmentopportunity, while ensuring quality and reliability of the power.

    To make SHP cost effective and reliable, standards, guidelines andmanuals are required covering entire range of SHP activities.

    Necessity of the standards/guidelines and manuals strongly felt bydevelopers, manufactures, consultants, regulators and others.

    Government of India has initiated preparation of about 30 standards

    for SHP and are expected to be ready by the year 2011.

  • 7/27/2019 Small Hydro Overview

    95/98

  • 7/27/2019 Small Hydro Overview

    96/98

  • 7/27/2019 Small Hydro Overview

    97/98

  • 7/27/2019 Small Hydro Overview

    98/98