smg
TRANSCRIPT
Influential Factors in the Outsourcing DecisionIncreased manufacturing and operating costs of spreader production at the Temecula plant have
influenced the decision to consider relocating production to China to increase profit margin. After
thoroughly analyzing the present and future logistical and financial risks of both the Temecula and
China plants, the team determined that Scotts Miracle-Gro should maintain spreader operations at the
Temecula plant. The following quantitative and qualitative analyses support the team’s conclusion.
Quantitative Factors & Sensitivity AnalysisWhen evaluating the decision to outsource production, the team analyzed the total quantitative
costs of the supply chain (Figure 1). Production, SG&A, and initial investment costs have a significant
impact on the decision to outsource the Scotts Miracle Grow spreader from Temecula to China.
Quantitative factors evaluated in the analysis include total costs for transportation, labor, raw materials,
electricity, management, overhead (startup, molds), and the initial investment. Detailed Net Present
Value (NPV) analyses are shown in Figure 2 for Temecula and Figure 3 for China. Upon conducting
the impact of the ten-year analysis, the quantitative factors that have the most significant impact on total
cost between operations in China and Temecula are transportation and labor costs.
Raw materials and electricity costs both have minor impacts on total cost of operations in both
China and Temecula. The estimated $1.4 million in savings (figure 3) at the Temecula plant has a
minimal impact on total cost of operations. The same applies to the effect of electricity costs on the total
cost of operations in both China and Temecula. The Temecula plant would cost an estimated $9 million
(figure 3) more for electricity operations and thus, along with raw material costs, both factors do not
make a significant impact.
Management, overhead, and investment costs mildly affected the decision for operations and
averaged around $15 million. Both overhead and management costs favored operations in China (figure
3), while investment costs were cheaper in Temecula due to the established operations. Lastly, labor
costs had the third largest impact on total cost favoring operations in China by almost $55 million. With
1
the number of workers remaining the same in both operations, it is evident that the cheaper labor rates
(18 times less than Temecula) in China are a significant advantage.
There are inherent risks and uncertainties in some of the factors that financially impact the
decision to outsource to China. Changes in Transportation and Labor costs can affect the total landed
costs of the product. Figure 4 and Figure 5 illustrates that an increase in transportation costs from 3% to
9.4% per year, shifts the financial drivers to favor Temecula over China. A detailed transportation cost
sensitivity analysis is graphically illustrated in Figure 6. On the other hand, productivity at the
Temecula plant needs to increase by 16.2% annually as shown in Figure 7 and Figure 8 and hourly labor
cost in China requires an unprecedented increase of 39.5% annually to financially prefer Temecula over
China (Figure 9 and Figure 10). Transportation costs had the most significant impact on maintaining
operations at the Temecula facility. Freight charges accounted for over $90 million in additional
charges by outsourcing production to China. This expense is almost double the benefit of labor costs
and thus plays an instrumental part in maintaining production in the Temecula facility.
Qualitative Factors Influencing the Outsourcing DecisionAlthough many of Scotts’ outsourcing analysis factors are highly measurable in nature, some are
harder to quantify than others. According to Chopra’s review of Supplier Scoring and Assessment (p.
428), replenishment lead time greatly affects the amount of safety stock held in inventory to account for
potential deviations in the supply chain. Scotts’ option to source the spreader to China increases lead
time an additional eight weeks, which generates not only $460,000 in safety stock, but also leads to a
continuum of other challenges. Increased lead time translates to greater potential for delayed shipments,
which damages the supplier’s on-time performance ratings and consequently causes Scotts to hold even
more safety stock while accruing holding costs.
Supply inflexibility is another consideration in the Chinese outsourcing option. Chinese suppliers
would likely impose a minimum batch size requirement, which leaves little room to respond to intense
swings in demand with smaller, more frequent deliveries. Larger batches also greatly increase cycle
2
inventory, associated holding costs, and risk. Given larger lot sizes, the potential for poor quality
production tremendously increases costs from replacement orders coupled with long lead time, rework,
and finally customer dissatisfaction in the form of missed sales. Supplier viability depends on
sustainability in the form of quality and reliability, thus an accepted level of quality deterioration for
cost savings tradeoff may eventually inhibit the supplier’s sustainability.
The most visible tradeoff with the China option is decreased manufacturing and labor costs
versus increased inbound transportation costs at Temecula. However, the lack of information
coordination capabilities expressed by Chinese manufacturers accentuates freight costs associated with
lack of visibility and the bullwhip effect, which minimizes the optimism outlook. Lastly, if the Chinese
government allows the Yuan to float or begins charging taxes and duties on agricultural products, costs
in China would soar. Heavy financial hedging would protect Scott from general fluctuations but would
not be a sufficient strategy to evade the inevitable.
Outline & Recommendations The team recommends that Scotts should not outsource the manufacturing capabilities to a
contractor in China. Scotts would offer up a core piece of the business (as well as all of the technical
knowledge and possibly even the “In Mold” machinery) to a contracted source. Labor rate forecasts in
China are on the rise for the next decade. The potential exists that once the operation is fully functional,
the cost of labor may no longer be a significant advantage and the unpredictability of the Chinese laws
can still result in a disadvantage to Scotts. Output from the Chinese facility predictions are lower than in
Temecula, as the employees in China would experience a learning curve coupled with low productivity
rates. As previously mentioned, Scotts will make the tradeoff of responsiveness for cost-savings, which
consequently increases safety stock and working capital costs.
In conclusion, the justification for outsourcing production to China looks very appealing in the
analysis, but there needs to be a balance between cost reduction and the other challenges that arise from
using overseas contract manufacturers.
3
Figure 1 – Summary Sheet
Temecula AnalysisYEAR 0 YEAR 1 YEAR2 YEAR 3 YEAR 4 YEAR 5 YEAR 6 YEAR 7 YEAR 8 YEAR 9 YEAR 10 Total
Total Cost $17,562,750 $17,288,907 $17,026,784 $16,531,368 $16,296,679 $16,072,730 $16,075,843 $16,082,082 $16,091,420 $16,103,832 $16,119,297 $181,251,69115% Discount Rate 1.0000 0.8696 0.7561 0.6575 0.5718 0.4972 0.4323 0.3759 0.3269 0.2843 0.2472NPV $17,562,750 $15,033,832 $12,874,695 $10,869,643 $9,317,679 $7,990,987 $6,950,031 $6,045,850 $5,260,314 $4,577,714 $3,984,444 $100,467,939Total NPV $100,467,939
China AnalysisTotal Cost $19,466,742 $12,340,613 $12,624,736 $12,919,439 $13,225,061 $13,941,953 $13,870,484 $14,211,035 $14,564,005 $14,929,806 $15,708,870 $157,802,744
15% Discount Rate 1.0000 0.8696 0.7561 0.6575 0.5718 0.4972 0.4323 0.3759 0.3269 0.2843 0.2472NPV $19,466,742 $10,730,967 $9,546,115 $8,494,741 $7,561,471 $6,931,615 $5,996,593 $5,342,454 $4,760,999 $4,243,983 $3,882,992 $86,958,673
Total NPV $86,958,673
Raw Material Labor Electricity Lease Management Overhead Freight Safety Stock InvestmentTemecula ($1,420,679) $62,014,061 $16,100,688 $33,000,000 $18,815,401 $34,434,425 $12,807,796 $0 $5,500,000
China $0 $3,896,102 $7,387,529 $2,200,000 $4,515,696 $14,387,997 $102,462,366 $5,060,000 $17,893,054Difference* $1,420,679 ($58,117,959) ($8,713,159) ($30,800,000) ($14,299,705) ($20,046,428) $89,654,570 $5,060,000 $12,393,054
* Note: Black indicates money saved by staying in Temecula
Temecula China$109,694,070 $13,483,631$66,057,621 $126,426,059$5,500,000 $17,893,054
$181,251,691 $157,802,744* Note: Black indicates money saved by staying in Temecula
S,G and A Cost $60,368,437Investment Cost $12,393,054
Total ($23,448,948)
COMPARISON OF NET PRESENT VALUES
SPECIFIC COST BREAKDOWN OVER THE TEN YEAR PERIOD
TOTAL COST COMPARISON OVER THE 10 YEAR PERIODDifference*
Cost of Goods ($96,210,439)
4
Figure 2 - Cash Flow and NPV Calculations for Temecula
Year: 0 1 2 3 4 5 6 7 8 9 10
PRODUCTION COSTS
Raw Materials
Current savings from use of regrind ($100,000)
Annual increase in savings due to regrind usage 5% 5% 5% 5% 5% 5% 5% 5% 5% 5%
Cost savings from use of regrind ($100,000) ($105,000) ($110,250) ($115,763) ($121,551) ($127,628) ($134,010) ($140,710) ($147,746) ($155,133) ($162,889)
Hourly Labor Costs
Current Avg. hourly rate $16.25
Annual increase % 3% 3% 3% 3% 3% 3% 3% 3% 3% 3%
Avg. hourly labor rate $16.25 $16.74 $17.24 $17.76 $18.29 $18.84 $19.40 $19.99 $20.59 $21.20 $21.84
Current no. of workers 195
Annual productivity increase 6% 6% 6% 6% 6% 3% 3% 3% 3% 3%
Number of hourly workers 195 183 172 162 152 143 139 135 131 127 123
Total annual hourly labor cost $6,337,500 $6,135,968 $5,940,844 $5,751,925 $5,569,014 $5,391,919 $5,387,066 $5,382,218 $5,377,374 $5,372,534 $5,367,699
Electricity Costs 4.00% <--annual growth rate
Avg. KwH rate $0.1600 $0.1664 $0.1731 $0.1800 $0.1872 $0.1947 $0.2025 $0.2105 $0.2190 $0.2277 $0.2368
Surcharge (per KwH) $0.025 $0.025 $0.025 $0.000 $0.000 $0.000 $0.000 $0.000 $0.000 $0.000 $0.000
Annual power usage (KwH) 8,000,000 7,840,000 7,683,200 7,529,536 7,378,945 7,231,366 7,086,739 6,945,004 6,806,104 6,669,982 6,536,582
Total annual electricity cost $1,480,000 $1,500,576 $1,521,704 $1,355,153 $1,381,172 $1,407,690 $1,434,718 $1,462,264 $1,490,340 $1,518,954 $1,548,118
Lease $3,000,000 $3,000,000 $3,000,000 $3,000,000 $3,000,000 $3,000,000 $3,000,000 $3,000,000 $3,000,000 $3,000,000 $3,000,000
TOTAL PRODUCTION COSTS $10,717,500 $10,531,544 $10,352,298 $9,991,315 $9,828,635 $9,671,981 $9,687,774 $9,703,772 $9,719,968 $9,736,356 $9,752,928
SG&A COSTS
Management Costs
Current Average annual rate $125,000
Annual increase % 0% 3% 3% 3% 3% 3% 3% 3% 3% 3% 3%
Avg. annual pay labor rate $125,000 $128,750 $132,613 $136,591 $140,689 $144,909 $149,257 $153,734 $158,346 $163,097 $167,990
Current no. of workers 16
Annual productivity increase 6% 6% 6% 6% 6% 3% 3% 3% 3% 3%
Number of salaried managers 16 15 14 13 12 12 11 10 10 9 9
Total annual management labor cost $2,000,000 $1,936,400 $1,874,822 $1,815,203 $1,757,480 $1,701,592 $1,647,481 $1,595,091 $1,544,367 $1,495,257 $1,447,707
Overhead Costs
Corporate Allocation $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000
30% allocation of direct costs $2,345,250 $2,290,963 $2,238,764 $2,132,123 $2,085,056 $2,039,883 $2,046,535 $2,053,345 $2,060,314 $2,067,447 $2,074,745
CM Profit $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Total annual OH costs $3,345,250 $3,290,963 $3,238,764 $3,132,123 $3,085,056 $3,039,883 $3,046,535 $3,053,345 $3,060,314 $3,067,447 $3,074,745
Freight Rate % 0.03
Freight $1,000,000 $1,030,000 $1,060,900 $1,092,727 $1,125,509 $1,159,274 $1,194,052 $1,229,874 $1,266,770 $1,304,773 $1,343,916
Safety Stock $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
TOTAL SG&A COSTS $6,345,250 $6,257,363 $6,174,487 $6,040,053 $5,968,044 $5,900,749 $5,888,069 $5,878,310 $5,871,452 $5,867,476 $5,866,369
INVESTMENTS
Annual Capital Outlays $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000
Start Up Costs $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Additional Scott People To Manage CM $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Additional Scott Travel $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Molds $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
TOTAL INVESTMENTS $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000
Total Costs $17,562,750 $17,288,907 $17,026,784 $16,531,368 $16,296,679 $16,072,730 $16,075,843 $16,082,082 $16,091,420 $16,103,832 $16,119,297Discout Factor @ 15% 1.0 0.8696 0.7561 0.6575 0.5718 0.4972 0.4323 0.3759 0.3269 0.2843 0.2472
NPV $17,562,750 $15,033,832 $12,874,695 $10,869,643 $9,317,679 $7,990,987 $6,950,031 $6,045,850 $5,260,314 $4,577,714 $3,984,44410 YR NPV $100,467,939
Only hourly wage employees counted (i.e. direct labor personal and temporary workers)
(Productivity assumed to increase at 6% for the first 5 years and then at 3% for the last 5 years)
(Assuming a 5 day work week, 8 hours/day and a 50 week year)
(Productivity assumed to increase at 6% for the first 5 years and then at 3% for the last 5 years)
5
Figure 3 - Cash Flow and NPV Calculations for ChinaYear: 0 1 2 3 4 5 6 7 8 9 10
PRODUCTION COSTS
Raw Materials
Current savings from use of regrind $0
Annual increase in savings due to regrind usage 5% 5% 5% 5% 5% 5% 5% 5% 5% 5%
Cost savings from use of regrind $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Hourly Labor Costs
Current Avg. hourly rate $0.91
Annual increase % 0% 2% 2% 2% 2% 2% 2% 2% 2% 2% 2%
Avg. hourly labor rate $0.91 $0.93 $0.95 $0.97 $0.99 $1.00 $1.02 $1.05 $1.07 $1.09 $1.11
Current no. of workers 195
Annual productivity increase 2% 2% 2% 2% 2% 2% 2% 2% 2% 2%
Number of hourly workers 195 191 187 184 180 176 173 169 166 163 159
Total annual hourly labor cost $354,900 $354,758 $354,616 $354,474 $354,333 $354,191 $354,049 $353,907 $353,766 $353,624 $353,483
Electricity Costs 5.00% <--annual growth rate
Avg. KwH rate $0.0650 $0.0683 $0.0717 $0.0752 $0.0790 $0.0830 $0.0871 $0.0915 $0.0960 $0.1008 $0.1059
Surcharge (per KwH) $0.000 $0.000 $0.000 $0.000 $0.000 $0.000 $0.000 $0.000 $0.000 $0.000 $0.000
Annual power usage (KwH) 8,000,000 8,000,000 8,000,000 8,000,000 8,000,000 8,000,000 8,000,000 8,000,000 8,000,000 8,000,000 8,000,000
Total annual electricity cost $520,000 $546,000 $573,300 $601,965 $632,063 $663,666 $696,850 $731,692 $768,277 $806,691 $847,025
Lease $200,000 $200,000 $200,000 $200,000 $200,000 $200,000 $200,000 $200,000 $200,000 $200,000 $200,000
TOTAL PRODUCTION COSTS $1,074,900 $1,100,758 $1,127,916 $1,156,439 $1,186,396 $1,217,857 $1,250,899 $1,285,600 $1,322,043 $1,360,315 $1,400,508
SG&A COSTS
Management Costs
Current Average annual rate $30,000
Annual increase % 0% 3% 3% 3% 3% 3% 3% 3% 3% 3% 3%
Avg. annual pay labor rate $30,000 $30,900 $31,827 $32,782 $33,765 $34,778 $35,822 $36,896 $38,003 $39,143 $40,317
Current no. of workers 16
Annual productivity increase 6% 6% 6% 6% 6% 3% 3% 3% 3% 3%
Number of salaried managers 16 15 14 13 12 12 11 10 10 9 9
Total annual management labor cost $480,000 $464,736 $449,957 $435,649 $421,795 $408,382 $395,395 $382,822 $370,648 $358,862 $347,450
Overhead Costs
Corporate Allocation $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000
50% allocation of direct costs $177,450 $177,379 $177,308 $177,237 $177,166 $177,095 $177,025 $176,954 $176,883 $176,812 $176,741
CM Profit 8% $124,392 $125,240 $126,230 $127,367 $128,655 $130,099 $131,704 $133,474 $135,415 $137,534 $139,837
Total annual OH costs $1,301,842 $1,302,619 $1,303,538 $1,304,604 $1,305,822 $1,307,195 $1,308,728 $1,310,427 $1,312,298 $1,314,346 $1,316,578
Freight Rate % 0.03
Freight $8,000,000 $8,240,000 $8,487,200 $8,741,816 $9,004,070 $9,274,193 $9,552,418 $9,838,991 $10,134,161 $10,438,185 $10,751,331
Safety Stock $460,000 $460,000 $460,000 $460,000 $460,000 $460,000 $460,000 $460,000 $460,000 $460,000 $460,000
TOTAL SG&A COSTS $10,241,842 $10,467,355 $10,700,695 $10,942,069 $11,191,687 $11,449,769 $11,716,542 $11,992,240 $12,277,107 $12,571,393 $12,875,359
INVESTMENTS
Annual Capital Outlays $300,000 $300,000 $300,000 $300,000 $300,000 $300,000 $300,000 $300,000 $300,000 $300,000 $300,000
Start Up Costs $1,000,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Additional Scott People To Manage CM $250,000 $262,500 $275,625 $289,406 $303,877 $319,070 $335,024 $351,775 $369,364 $387,832 $407,224
Additional Scott Travel $200,000 $210,000 $220,500 $231,525 $243,101 $255,256 $268,019 $281,420 $295,491 $310,266 $325,779
Molds $400,000 $0 $0 $0 $0 $400,000 $0 $0 $0 $0 $400,000
Buyback Lease Option $6,000,000
TOTAL INVESTMENTS $8,150,000 $772,500 $796,125 $820,931 $846,978 $1,274,327 $903,043 $933,195 $964,855 $998,098 $1,433,003
Total Costs $19,466,742 $12,340,613 $12,624,736 $12,919,439 $13,225,061 $13,941,953 $13,870,484 $14,211,035 $14,564,005 $14,929,806 $15,708,870Discount Rate @ 15% 1.00 0.8696 0.7561 0.6575 0.5718 0.4972 0.4323 0.3759 0.3269 0.2843 0.2472NPV $19,466,742 $10,730,967 $9,546,115 $8,494,741 $7,561,471 $6,931,615 $5,996,593 $5,342,454 $4,760,999 $4,243,983 $3,882,992
10 YR NPV $86,958,673
(Productivity assumed to increase at 6% for the first 5 years and then at 3% for the last 5 years)
Only hourly wage employees counted (i.e. direct labor personal and temporary workers)
(Productivity assumed to increase at 2% annually.)
(Assuming a 5 day work week, 8 hours/day and a 50 week year)
6
Figure 4 – NPV Calculations for Temecula with Transportation Cost Annual Increase of 9.4%Year: 0 1 2 3 4 5 6 7 8 9 10
PRODUCTION COSTS
Raw Materials
Current savings from use of regrind ($100,000)
Annual increase in savings due to regrind usage 5% 5% 5% 5% 5% 5% 5% 5% 5% 5%
Cost savings from use of regrind ($100,000) ($105,000) ($110,250) ($115,763) ($121,551) ($127,628) ($134,010) ($140,710) ($147,746) ($155,133) ($162,889)
Hourly Labor Costs
Current Avg. hourly rate $16.25
Annual increase % 3% 3% 3% 3% 3% 3% 3% 3% 3% 3%
Avg. hourly labor rate $16.25 $16.74 $17.24 $17.76 $18.29 $18.84 $19.40 $19.99 $20.59 $21.20 $21.84
Current no. of workers 195
Annual productivity increase 6% 6% 6% 6% 6% 3% 3% 3% 3% 3%
Number of hourly workers 195 183 172 162 152 143 139 135 131 127 123
Total annual hourly labor cost $6,337,500 $6,135,968 $5,940,844 $5,751,925 $5,569,014 $5,391,919 $5,387,066 $5,382,218 $5,377,374 $5,372,534 $5,367,699
Electricity Costs 4.00% <--annual growth rate
Avg. KwH rate $0.1600 $0.1664 $0.1731 $0.1800 $0.1872 $0.1947 $0.2025 $0.2105 $0.2190 $0.2277 $0.2368
Surcharge (per KwH) $0.025 $0.025 $0.025 $0.000 $0.000 $0.000 $0.000 $0.000 $0.000 $0.000 $0.000
Annual power usage (KwH) 8,000,000 7,840,000 7,683,200 7,529,536 7,378,945 7,231,366 7,086,739 6,945,004 6,806,104 6,669,982 6,536,582
Total annual electricity cost $1,480,000 $1,500,576 $1,521,704 $1,355,153 $1,381,172 $1,407,690 $1,434,718 $1,462,264 $1,490,340 $1,518,954 $1,548,118
Lease $3,000,000 $3,000,000 $3,000,000 $3,000,000 $3,000,000 $3,000,000 $3,000,000 $3,000,000 $3,000,000 $3,000,000 $3,000,000
TOTAL PRODUCTION COSTS $10,717,500 $10,531,544 $10,352,298 $9,991,315 $9,828,635 $9,671,981 $9,687,774 $9,703,772 $9,719,968 $9,736,356 $9,752,928
SG&A COSTS
Management Costs
Current Average annual rate $125,000
Annual increase % 0% 3% 3% 3% 3% 3% 3% 3% 3% 3% 3%
Avg. annual pay labor rate $125,000 $128,750 $132,613 $136,591 $140,689 $144,909 $149,257 $153,734 $158,346 $163,097 $167,990
Current no. of workers 16
Annual productivity increase 6% 6% 6% 6% 6% 3% 3% 3% 3% 3%
Number of salaried managers 16 15 14 13 12 12 11 10 10 9 9
Total annual management labor cost $2,000,000 $1,936,400 $1,874,822 $1,815,203 $1,757,480 $1,701,592 $1,647,481 $1,595,091 $1,544,367 $1,495,257 $1,447,707
Overhead Costs
Corporate Allocation $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000
30% allocation of direct costs $2,345,250 $2,290,963 $2,238,764 $2,132,123 $2,085,056 $2,039,883 $2,046,535 $2,053,345 $2,060,314 $2,067,447 $2,074,745
CM Profit $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Total annual OH costs $3,345,250 $3,290,963 $3,238,764 $3,132,123 $3,085,056 $3,039,883 $3,046,535 $3,053,345 $3,060,314 $3,067,447 $3,074,745
Freight Rate % 0.03
Freight $1,000,000 $1,094,000 $1,196,836 $1,309,339 $1,432,416 $1,567,064 $1,714,368 $1,875,518 $2,051,817 $2,244,688 $2,455,688
Safety Stock $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
TOTAL SG&A COSTS $6,345,250 $6,321,363 $6,310,423 $6,256,665 $6,274,952 $6,308,538 $6,408,384 $6,523,954 $6,656,498 $6,807,391 $6,978,141
INVESTMENTS
Annual Capital Outlays $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000
Start Up Costs $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Additional Scott People To Manage CM $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Additional Scott Travel $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Molds $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
TOTAL INVESTMENTS $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000
Total Costs $17,562,750 $17,352,907 $17,162,720 $16,747,980 $16,603,586 $16,480,519 $16,596,158 $16,727,726 $16,876,466 $17,043,746 $17,231,069Discout Factor @ 15% 1.0 0.8696 0.7561 0.6575 0.5718 0.4972 0.4323 0.3759 0.3269 0.2843 0.2472NPV $17,562,750 $15,089,484 $12,977,482 $11,012,069 $9,493,154 $8,193,731 $7,174,977 $6,288,572 $5,516,947 $4,844,896 $4,259,257
10 YR NPV $102,413,319
Only hourly wage employees counted (i.e. direct labor personal and temporary workers)
(Productivity assumed to increase at 6% for the first 5 years and then at 3% for the last 5 years)
(Assuming a 5 day work week, 8 hours/day and a 50 week year)
(Productivity assumed to increase at 6% for the first 5 years and then at 3% for the last 5 years)
7
Figure 5 – NPV Calculations for China with Transportation Cost Annual Increase of 9.4%
Year: 0 1 2 3 4 5 6 7 8 9 10
PRODUCTION COSTS
Raw Materials
Current savings from use of regrind $0
Annual increase in savings due to regrind usage 5% 5% 5% 5% 5% 5% 5% 5% 5% 5%
Cost savings from use of regrind $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Hourly Labor Costs
Current Avg. hourly rate $0.91
Annual increase % 0% 2% 2% 2% 2% 2% 2% 2% 2% 2% 2%
Avg. hourly labor rate $0.91 $0.93 $0.95 $0.97 $0.99 $1.00 $1.02 $1.05 $1.07 $1.09 $1.11
Current no. of workers 195
Annual productivity increase 2% 2% 2% 2% 2% 2% 2% 2% 2% 2%
Number of hourly workers 195 191 187 184 180 176 173 169 166 163 159
Total annual hourly labor cost $354,900 $354,758 $354,616 $354,474 $354,333 $354,191 $354,049 $353,907 $353,766 $353,624 $353,483
Electricity Costs 5.00% <--annual growth rate
Avg. KwH rate $0.0650 $0.0683 $0.0717 $0.0752 $0.0790 $0.0830 $0.0871 $0.0915 $0.0960 $0.1008 $0.1059
Surcharge (per KwH) $0.000 $0.000 $0.000 $0.000 $0.000 $0.000 $0.000 $0.000 $0.000 $0.000 $0.000
Annual power usage (KwH) 8,000,000 8,000,000 8,000,000 8,000,000 8,000,000 8,000,000 8,000,000 8,000,000 8,000,000 8,000,000 8,000,000
Total annual electricity cost $520,000 $546,000 $573,300 $601,965 $632,063 $663,666 $696,850 $731,692 $768,277 $806,691 $847,025
Lease $200,000 $200,000 $200,000 $200,000 $200,000 $200,000 $200,000 $200,000 $200,000 $200,000 $200,000
TOTAL PRODUCTION COSTS $1,074,900 $1,100,758 $1,127,916 $1,156,439 $1,186,396 $1,217,857 $1,250,899 $1,285,600 $1,322,043 $1,360,315 $1,400,508
SG&A COSTS
Management Costs
Current Average annual rate $30,000
Annual increase % 0% 3% 3% 3% 3% 3% 3% 3% 3% 3% 3%
Avg. annual pay labor rate $30,000 $30,900 $31,827 $32,782 $33,765 $34,778 $35,822 $36,896 $38,003 $39,143 $40,317
Current no. of workers 16
Annual productivity increase 6% 6% 6% 6% 6% 3% 3% 3% 3% 3%
Number of salaried managers 16 15 14 13 12 12 11 10 10 9 9
Total annual management labor cost $480,000 $464,736 $449,957 $435,649 $421,795 $408,382 $395,395 $382,822 $370,648 $358,862 $347,450
Overhead Costs
Corporate Allocation $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000
50% allocation of direct costs $177,450 $177,379 $177,308 $177,237 $177,166 $177,095 $177,025 $176,954 $176,883 $176,812 $176,741
CM Profit 8% $124,392 $125,240 $126,230 $127,367 $128,655 $130,099 $131,704 $133,474 $135,415 $137,534 $139,837
Total annual OH costs $1,301,842 $1,302,619 $1,303,538 $1,304,604 $1,305,822 $1,307,195 $1,308,728 $1,310,427 $1,312,298 $1,314,346 $1,316,578
Freight Rate % 0.03Freight $8,000,000 $8,752,000 $9,574,688 $10,474,709 $11,459,331 $12,536,508 $13,714,940 $15,004,145 $16,414,534 $17,957,500 $19,645,505
Safety Stock $460,000 $460,000 $460,000 $460,000 $460,000 $460,000 $460,000 $460,000 $460,000 $460,000 $460,000
TOTAL SG&A COSTS $10,241,842 $10,979,355 $11,788,183 $12,674,962 $13,646,948 $14,712,085 $15,879,064 $17,157,394 $18,557,481 $20,090,708 $21,769,533
INVESTMENTS
Annual Capital Outlays $300,000 $300,000 $300,000 $300,000 $300,000 $300,000 $300,000 $300,000 $300,000 $300,000 $300,000
Start Up Costs $1,000,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Additional Scott People To Manage CM $250,000 $262,500 $275,625 $289,406 $303,877 $319,070 $335,024 $351,775 $369,364 $387,832 $407,224
Additional Scott Travel $200,000 $210,000 $220,500 $231,525 $243,101 $255,256 $268,019 $281,420 $295,491 $310,266 $325,779
Molds $400,000 $0 $0 $0 $0 $400,000 $0 $0 $0 $0 $400,000
Buyback Lease Option $6,000,000
TOTAL INVESTMENTS $8,150,000 $772,500 $796,125 $820,931 $846,978 $1,274,327 $903,043 $933,195 $964,855 $998,098 $1,433,003
Total Costs $19,466,742 $12,852,613 $13,712,224 $14,652,332 $15,680,321 $17,204,269 $18,033,006 $19,376,189 $20,844,378 $22,449,121 $24,603,044Discount Rate @ 15% 1.00 0.8696 0.7561 0.6575 0.5718 0.4972 0.4323 0.3759 0.3269 0.2843 0.2472NPV $19,466,742 $11,176,185 $10,368,412 $9,634,146 $8,965,275 $8,553,562 $7,796,166 $7,284,227 $6,814,064 $6,381,441 $6,081,496
10 YR NPV $102,521,717
Only hourly wage employees counted (i.e. direct labor personal and temporary workers)
(Productivity assumed to increase at 2% annually.)
(Assuming a 5 day work week, 8 hours/day and a 50 week year)
(Productivity assumed to increase at 6% for the first 5 years and then at 3% for the last 5 years)
8
Figure 6 –Transportation Costs Sensitivity (Graph)
TEMECULA CHINA-5% 98,782,957$ 73,478,821$ -4% 98,958,251$ 74,881,169$ -3% 99,142,553$ 76,355,588$ -2% 99,336,371$ 77,906,131$ -1% 99,540,239$ 79,537,073$ 0% 99,754,719$ 81,252,918$ 1% 99,980,407$ 83,058,417$ 2% 100,217,927$ 84,958,577$ 3% 100,467,939$ 86,958,673$ 4% 100,731,137$ 89,064,260$ 5% 101,008,253$ 91,281,190$ 6% 101,300,058$ 93,615,625$ 7% 101,607,360$ 96,074,048$ 8% 101,931,015$ 98,663,283$ 9% 102,271,918$ 101,390,510$
10% 102,631,014$ 104,263,279$ 11% 103,009,296$ 107,289,529$ 12% 103,407,805$ 110,477,607$ 13% 103,827,640$ 113,836,284$ 14% 104,269,952$ 117,374,778$ 15% 104,735,951$ 121,102,769$
10 YR NPVFreight Cost Change (%)
$-
$20,000,000
$40,000,000
$60,000,000
$80,000,000
$100,000,000
$120,000,000
$140,000,000
-5% -4% -3% -2% -1% 0% 1% 2% 3% 4% 5% 6% 7% 8% 9% 10% 11% 12% 13% 14% 15%
10 YR NPV
Freight Cost Change
Transportation Cost Sensitivity Analysis
10 YR NPV TEMECULA
10 YR NPV CHINA
9.4% Freight increase per year
9
Figure 7 NPV Calculations for Temecula with Productivity Annual Increase of 16.2%Year: 0 1 2 3 4 5 6 7 8 9 10
PRODUCTION COSTS
Raw Materials
Current savings from use of regrind ($100,000)
Annual increase in savings due to regrind usage 5% 5% 5% 5% 5% 5% 5% 5% 5% 5%
Cost savings from use of regrind ($100,000) ($105,000) ($110,250) ($115,763) ($121,551) ($127,628) ($134,010) ($140,710) ($147,746) ($155,133) ($162,889)
Hourly Labor Costs
Current Avg. hourly rate $16.25
Annual increase % 3% 3% 3% 3% 3% 3% 3% 3% 3% 3%
Avg. hourly labor rate $16.25 $16.74 $17.24 $17.76 $18.29 $18.84 $19.40 $19.99 $20.59 $21.20 $21.84
Current no. of workers 195
Annual productivity increase 16.2% 16.2% 16.2% 16.2% 16.2% 16.2% 16.2% 16.2% 16.2% 16.2%
Number of hourly workers 195 163 137 115 96 81 68 57 47 40 33
Total annual hourly labor cost $6,337,500 $5,470,150 $4,721,505 $4,075,320 $3,517,572 $3,036,157 $2,620,628 $2,261,969 $1,952,396 $1,685,191 $1,454,556
Electricity Costs 4.00% <--annual growth rate
Avg. KwH rate $0.1600 $0.1664 $0.1731 $0.1800 $0.1872 $0.1947 $0.2025 $0.2105 $0.2190 $0.2277 $0.2368
Surcharge (per KwH) $0.025 $0.025 $0.025 $0.000 $0.000 $0.000 $0.000 $0.000 $0.000 $0.000 $0.000
Annual power usage (KwH) 8,000,000 7,840,000 7,683,200 7,529,536 7,378,945 7,231,366 7,086,739 6,945,004 6,806,104 6,669,982 6,536,582
Total annual electricity cost $1,480,000 $1,500,576 $1,521,704 $1,355,153 $1,381,172 $1,407,690 $1,434,718 $1,462,264 $1,490,340 $1,518,954 $1,548,118
Lease $3,000,000 $3,000,000 $3,000,000 $3,000,000 $3,000,000 $3,000,000 $3,000,000 $3,000,000 $3,000,000 $3,000,000 $3,000,000
TOTAL PRODUCTION COSTS $10,717,500 $9,865,726 $9,132,959 $8,314,710 $7,777,193 $7,316,219 $6,921,336 $6,583,523 $6,294,990 $6,049,013 $5,839,785
SG&A COSTS
Management Costs
Current Average annual rate $125,000
Annual increase % 0% 3% 3% 3% 3% 3% 3% 3% 3% 3% 3%
Avg. annual pay labor rate $125,000 $128,750 $132,613 $136,591 $140,689 $144,909 $149,257 $153,734 $158,346 $163,097 $167,990
Current no. of workers 16
Annual productivity increase 6% 6% 6% 6% 6% 3% 3% 3% 3% 3%
Number of salaried managers 16 15 14 13 12 12 11 10 10 9 9
Total annual management labor cost $2,000,000 $1,936,400 $1,874,822 $1,815,203 $1,757,480 $1,701,592 $1,647,481 $1,595,091 $1,544,367 $1,495,257 $1,447,707
Overhead Costs
Corporate Allocation $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000
30% allocation of direct costs $2,345,250 $2,091,218 $1,872,963 $1,629,142 $1,469,623 $1,333,154 $1,216,604 $1,117,270 $1,032,821 $961,244 $900,802
CM Profit $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Total annual OH costs $3,345,250 $3,091,218 $2,872,963 $2,629,142 $2,469,623 $2,333,154 $2,216,604 $2,117,270 $2,032,821 $1,961,244 $1,900,802
Freight Rate % 0.03
Freight $1,000,000 $1,030,000 $1,060,900 $1,092,727 $1,125,509 $1,159,274 $1,194,052 $1,229,874 $1,266,770 $1,304,773 $1,343,916
Safety Stock $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
TOTAL SG&A COSTS $6,345,250 $6,057,618 $5,808,685 $5,537,072 $5,352,611 $5,194,020 $5,058,137 $4,942,235 $4,843,958 $4,761,273 $4,692,426
INVESTMENTS
Annual Capital Outlays $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000
Start Up Costs $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Additional Scott People To Manage CM $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Additional Scott Travel $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Molds $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
TOTAL INVESTMENTS $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000 $500,000
Total Costs $17,562,750 $16,423,343 $15,441,644 $14,351,782 $13,629,804 $13,010,239 $12,479,474 $12,025,759 $11,638,948 $11,310,286 $11,032,211Discout Factor @ 15% 1.0 0.8696 0.7561 0.6575 0.5718 0.4972 0.4323 0.3759 0.3269 0.2843 0.2472
NPV $17,562,750 $14,281,168 $11,676,101 $9,436,530 $7,792,885 $6,468,388 $5,395,221 $4,520,928 $3,804,793 $3,215,089 $2,726,99410 YR NPV $86,880,847
Only hourly wage employees counted (i.e. direct labor personal and temporary workers)
(Productivity assumed to increase at 6% for the first 5 years and then at 3% for the last 5 years)
(Assuming a 5 day work week, 8 hours/day and a 50 week year)
(Productivity assumed to increase at 6% for the first 5 years and then at 3% for the last 5 years)
10
Figure 8 –Temecula Productivity Sensitivity (Graph)
TEMECULA CHINA0% 110,721,881$ 86,958,673$ 1% 108,601,919$ 86,958,673$ 2% 106,590,968$ 86,958,673$ 3% 104,683,104$ 86,958,673$ 4% 102,872,716$ 86,958,673$ 5% 101,154,487$ 86,958,673$ 6% 99,523,383$ 86,958,673$ 7% 97,974,636$ 86,958,673$ 8% 96,503,733$ 86,958,673$ 9% 95,106,404$ 86,958,673$
10% 93,778,607$ 86,958,673$ 11% 92,516,520$ 86,958,673$ 12% 91,316,530$ 86,958,673$ 13% 90,175,219$ 86,958,673$ 14% 89,089,357$ 86,958,673$ 15% 88,055,891$ 86,958,673$ 16% 87,071,938$ 86,958,673$ 17% 86,134,774$ 86,958,673$ 18% 85,241,827$ 86,958,673$ 19% 84,390,667$ 86,958,673$ 20% 83,579,002$ 86,958,673$
10 YR NPVTemecula Annual Productivity Change (%)
$-
$20,000,000
$40,000,000
$60,000,000
$80,000,000
$100,000,000
$120,000,000
0% 1% 2% 3% 4% 5% 6% 7% 8% 9% 10% 11% 12% 13% 14% 15% 16% 17% 18% 19% 20%
10 YR NPV
Temecula Productivity Change
Temecula Productivity Sensitivity Analysis
10 YR NPV TEMECULA
10 YR NPV CHINA
16.2% Productivity increase per year
11
Figure 9 NPV Calculations for China with Hourly Labor Cost Annual Increase of 39.5%Year: 0 1 2 3 4 5 6 7 8 9 10
PRODUCTION COSTS
Raw Materials
Current savings from use of regrind $0
Annual increase in savings due to regrind usage 5% 5% 5% 5% 5% 5% 5% 5% 5% 5%
Cost savings from use of regrind $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Hourly Labor Costs
Current Avg. hourly rate $0.91
Annual increase % 0% 39.5% 39.5% 39.5% 39.5% 39.5% 39.5% 39.5% 39.5% 39.5% 39.5%
Avg. hourly labor rate $0.91 $1.27 $1.77 $2.47 $3.45 $4.81 $6.71 $9.36 $13.05 $18.21 $25.40
Current no. of workers 195
Annual productivity increase 2% 2% 2% 2% 2% 2% 2% 2% 2% 2%
Number of hourly workers 195 191 187 184 180 176 173 169 166 163 159
Total annual hourly labor cost $354,900 $485,184 $663,295 $906,790 $1,239,673 $1,694,757 $2,316,902 $3,167,437 $4,330,203 $5,919,821 $8,092,987
Electricity Costs 5.00% <--annual growth rate
Avg. KwH rate $0.0650 $0.0683 $0.0717 $0.0752 $0.0790 $0.0830 $0.0871 $0.0915 $0.0960 $0.1008 $0.1059
Surcharge (per KwH) $0.000 $0.000 $0.000 $0.000 $0.000 $0.000 $0.000 $0.000 $0.000 $0.000 $0.000
Annual power usage (KwH) 8,000,000 8,000,000 8,000,000 8,000,000 8,000,000 8,000,000 8,000,000 8,000,000 8,000,000 8,000,000 8,000,000
Total annual electricity cost $520,000 $546,000 $573,300 $601,965 $632,063 $663,666 $696,850 $731,692 $768,277 $806,691 $847,025
Lease $200,000 $200,000 $200,000 $200,000 $200,000 $200,000 $200,000 $200,000 $200,000 $200,000 $200,000
TOTAL PRODUCTION COSTS $1,074,900 $1,231,184 $1,436,595 $1,708,755 $2,071,736 $2,558,423 $3,213,752 $4,099,129 $5,298,480 $6,926,511 $9,140,012
SG&A COSTS
Management Costs
Current Average annual rate $30,000
Annual increase % 0% 3% 3% 3% 3% 3% 3% 3% 3% 3% 3%
Avg. annual pay labor rate $30,000 $30,900 $31,827 $32,782 $33,765 $34,778 $35,822 $36,896 $38,003 $39,143 $40,317
Current no. of workers 16
Annual productivity increase 6% 6% 6% 6% 6% 3% 3% 3% 3% 3%
Number of salaried managers 16 15 14 13 12 12 11 10 10 9 9
Total annual management labor cost $480,000 $464,736 $449,957 $435,649 $421,795 $408,382 $395,395 $382,822 $370,648 $358,862 $347,450
Overhead Costs
Corporate Allocation $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000
50% allocation of direct costs $177,450 $242,592 $331,647 $453,395 $619,836 $847,378 $1,158,451 $1,583,718 $2,165,102 $2,959,910 $4,046,493
CM Profit 8% $124,392 $135,674 $150,924 $171,552 $199,483 $237,344 $288,732 $358,556 $453,530 $582,830 $758,997
Total annual OH costs $1,301,842 $1,378,265 $1,482,572 $1,624,947 $1,819,319 $2,084,723 $2,447,183 $2,942,275 $3,618,632 $4,542,740 $5,805,490
Freight Rate % 0.03
Freight $8,000,000 $8,240,000 $8,487,200 $8,741,816 $9,004,070 $9,274,193 $9,552,418 $9,838,991 $10,134,161 $10,438,185 $10,751,331
Safety Stock $460,000 $460,000 $460,000 $460,000 $460,000 $460,000 $460,000 $460,000 $460,000 $460,000 $460,000
TOTAL SG&A COSTS $10,241,842 $10,543,001 $10,879,729 $11,262,412 $11,705,185 $12,227,298 $12,854,997 $13,624,087 $14,583,441 $15,799,787 $17,364,271
INVESTMENTS
Annual Capital Outlays $300,000 $300,000 $300,000 $300,000 $300,000 $300,000 $300,000 $300,000 $300,000 $300,000 $300,000
Start Up Costs $1,000,000 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
Additional Scott People To Manage CM $250,000 $262,500 $275,625 $289,406 $303,877 $319,070 $335,024 $351,775 $369,364 $387,832 $407,224
Additional Scott Travel $200,000 $210,000 $220,500 $231,525 $243,101 $255,256 $268,019 $281,420 $295,491 $310,266 $325,779
Molds $400,000 $0 $0 $0 $0 $400,000 $0 $0 $0 $0 $400,000
Buyback Lease Option $6,000,000
TOTAL INVESTMENTS $8,150,000 $772,500 $796,125 $820,931 $846,978 $1,274,327 $903,043 $933,195 $964,855 $998,098 $1,433,003
Total Costs $19,466,742 $12,546,685 $13,112,449 $13,792,099 $14,623,899 $16,060,048 $16,971,792 $18,656,412 $20,846,775 $23,724,396 $27,937,286Discount Rate @ 15% 1.00 0.8696 0.7561 0.6575 0.5718 0.4972 0.4323 0.3759 0.3269 0.2843 0.2472NPV $19,466,742 $10,910,161 $9,914,895 $9,068,529 $8,361,262 $7,984,682 $7,337,374 $7,013,636 $6,814,848 $6,743,954 $6,905,670
10 YR NPV $100,521,752
Only hourly wage employees counted (i.e. direct labor personal and temporary workers)
(Productivity assumed to increase at 2% annually.)
(Assuming a 5 day work week, 8 hours/day and a 50 week year)
(Productivity assumed to increase at 6% for the first 5 years and then at 3% for the last 5 years)
12
Figure 10 – China Hourly Labor Cost Sensitivity (Graph)
TEMECULA CHINA0% 100,467,939$ 86,729,016$ 3% 100,467,939$ 87,082,378$ 6% 100,467,939$ 87,493,006$ 9% 100,467,939$ 87,970,776$
12% 100,467,939$ 88,527,175$ 15% 100,467,939$ 89,175,540$ 18% 100,467,939$ 89,931,321$ 21% 100,467,939$ 90,812,373$ 24% 100,467,939$ 91,839,289$ 27% 100,467,939$ 93,035,768$ 30% 100,467,939$ 94,429,021$ 33% 100,467,939$ 96,050,229$ 36% 100,467,939$ 97,935,046$ 39% 100,467,939$ 100,124,153$ 42% 100,467,939$ 102,663,878$ 45% 100,467,939$ 105,606,869$ 48% 100,467,939$ 109,012,846$ 51% 100,467,939$ 112,949,412$
China Hourly Labor Cost Change (%) 10 YR NPV
$-
$20,000,000
$40,000,000
$60,000,000
$80,000,000
$100,000,000
$120,000,000
0% 3% 6% 9% 12% 15% 18% 21% 24% 27% 30% 33% 36% 39% 42% 45% 48% 51%
10 YR NPV
China Hourly Labor Cost Change
China Labor Cost Sensitivity Analysis
10 YR NPV TEMECULA
10 YR NPV CHINA
39.5% Labor cost increase per year
13