socialist republic of vietnam ministry of agriculture … · viet nam managing natural hazards...
TRANSCRIPT
SOCIALIST REPUBLIC OF VIETNAM
MINISTRY OF AGRICULTURE AND RURAL DEVELOPMENT (MARD)
CENTRAL PROJECT OFFICE (CPO)
VIETNAM MANAGING NATURAL HAZARDS PROJECT
(VN-Haz)
(ESMF)
March - 2012
E2993 v15 P
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
ed
Preface
This document is called the Environment and Social Management Framework (ESMF) for the
Viet Nam Managing Natural Hazards Project (Vn-Haz/WB5) (the Project). It is developed to
guide the Central Project Management Office (CPMO) and the subproject implementers in
screening future subprojects/subprojects to be implemented during the second phase for
environment and social impacts, the relevant environmental assessment documents that need
to be prepared and the corresponding mitigating measures as well as the implementation
arrangements and capacity building, among others. It also includes an exclusion list whereby
subprojects that pose adverse impacts on natural habitats and forest will be excluded from
project financing. The ESMF was developed as a standalone document to satisfy WB’s
safeguard requirements on Environmental Assessment (OP/BP 4.01), Indigenous Peoples
(OP/BP 4.10), Involuntary Resettlement (OP/BP 4.12), Safety of Dams (OP/BP 4.37);
Physical Cultural Resources (OP/BP 4.11), and Projects on International Waterways (OP/BP
7.50). It is also connected to other safeguard policy documents namely the Ethnic Minorities
Policy Framework (EMPF), the Resettlement Policy Framework (RPF), the Dam Safety
Framework (DSF) as well as the safeguard action plans for the subprojects namely the
Resettlement Action Plans (RAPs), the Ethnic Minority Development Plans (EMDPs), the
Dam Safety Report (DSR), and the Environmental Management Plans (EMPs), including the
Environmental Code of Practices (ECOPs). The ESMF will be applied to all the subprojects to
be financed under the Project.
The Central Project Management Office (CPMO), which was established within the Central
Projects Office (CPO) of the Ministry of Agriculture and Rural Development (MARD), will
be responsible for the overall implementation of the Project including the implementation of
the ESMF. The Provincial Project Management Unit (PPMU) established at the provincial
Department of Agriculture and Rural Development (DARD) in each of the ten provinces is
responsible for preparation and implementation of the mitigation measures as described in the
subproject specific RAP, EMDP, and/or EMP/ECOP in consistency with this ESMF. The
subproject specific RAP, EMDP, and EMP, including DSR as needed, would be subject to the
review and clearance by the Bank before implementation.
Environmental and Social Management Framework (ESMF) Viet Nam Managing Natural Hazards Project (Vn-Haz/WB5)
ii
Table of contents
Preface ......................................................................................................................................... i
Abbreviations ............................................................................................................................. v
Executive Summary .................................................................................................................... 1
Section I: Introduction ................................................................................................................ 3
Section II. Project Description ................................................................................................... 4
Section III. Legal and Policy Frameworks ............................................................................... 15
3.1. Government Policy on Natural Disaster Management ....................................................... 15 3.2. Government Laws and Regulations ...................................................................................... 15 3.3. Application of World Bank Safeguard Policies .................................................................... 17
Section IV: Summary of Impacts and Mitigation Measures .................................................... 20
4.1. Potential Positive Impacts ...................................................................................................... 20 4.2. Potential Negative Impacts and Mitigation Measures ........................................................ 21 4.3 Potential Cumulative Impacts and Enhancement Opportunities ....................................... 24
Section V. ESMF Process for the Subprojects ......................................................................... 25
5.1. Objective and Approach ......................................................................................................... 25 5.2. Safeguard Screening and Impact Assessment (Step 1&2) ............................................... 25 5.3. Development of Mitigation Measures and Public Consultation (Step 3) ......................... 27 5.4. Information Disclosure and WB Safeguard Clearance (Step 4) ....................................... 31 5.5. Implementation, Supervision, Monitoring, and Reporting (Step 5) .................................. 31
Section VI. Mitigation Measures for Other Project Activities ................................................. 34
Section VII. Implementation Arrangement and Budget .......................................................... 35
7.1. Roles and Responsibilities ..................................................................................................... 35 7.2. Reporting Arrangement........................................................................................................... 36 7.3. Safeguard Training and Capacity Building .......................................................................... 36 7.4. Budget Allocation ..................................................................................................................... 37
Annex 1: Location of River Basins and List of Potential Subprojects ..................................... 38
Annex 2: Standard Environmental Code of Practices (ECOP) for the Subprojects ................ 46
I. Introduction ........................................................................................................................... 48
II. Relevant World Bank’s Safeguard Policies and Government’s Regulations ..................... 48 III. Responsibilities .......................................................................................................................... 49 IV. General Provisions .................................................................................................................... 50 4.1 Contract Specific Environmental Plan (CSEP) ..................................................................... 50 4.2 Non-compliance Reporting Procedures ................................................................................ 51 4.3 Liaising with Authorities and the Public ................................................................................. 51 4.5 Mitigation Objectives and Special Considerations ............................................................... 52 4.6 Implementation of “Chance Find” Procedures...................................................................... 52 4.7 Prohibitions ................................................................................................................................ 53
V. Management of Construction ............................................................................................. 53
5.1 Management of Construction Sites ........................................................................................ 54 5.2 Management of Environmental Quality ................................................................................. 56 5.3 Management of Work Camp ................................................................................................... 60 5.4 Management of Stockpiles, Quarries, and Borrow Pits ...................................................... 61
Environmental and Social Management Framework (ESMF) Viet Nam Managing Natural Hazards Project (Vn-Haz/WB5)
iii
5.5 Management of Dredging ........................................................................................................ 61 5.6. Monitoring of Potential Impacts ............................................................................................. 62
Annex 3: Scope for an EMP Preparation ................................................................................. 63
I. EMP Outline .................................................................................................................................. 63 II. Consultation and Information Disclosure ................................................................................. 64 III. Preparation of a DMDP ............................................................................................................. 65 IV. Preparation of a study for coastal erosion ............................................................................. 66
Annex 4: Simple Environmental Code of Practices (ECOP) for Small Works ....................... 67
I. General provisions ....................................................................................................................... 67 II. Good Environmental and Housekeeping Practices ............................................................... 67 III. Prohibitions ................................................................................................................................. 69 IV. “Chance find” Procedures ........................................................................................................ 69
Annex 5. Safeguard Screening and Key Impacts of Component 4 Subprojects ....................... 70
Annex 6. Summary of Potential Impacts, Mitigating Measures; Monitoring, and Responsible
agencies ..................................................................................................................................... 81
References…………………………………………………………………………………….75
Environmental and Social Management Framework (ESMF) Viet Nam Managing Natural Hazards Project (Vn-Haz/WB5)
iv
LIST OF TABLES AND FIGURES
Table 2.1: List of proposed first year subprojects under Component 4 ................................... 14
Table 4.1: Impacts due to land acquisition and relocations of first year Component 4
subprojects ................................................................................................................................ 22
Figure 5.1 – Schematic Flowchart for Safeguard Actions for Components 4 Subprojects ...... 32
Table 5.1: Technical Guideline for Safeguard Screening and Actions for Component 4
Subprojects ............................................................................................................................... 33
Table 7.1: Institutional responsibilities for the Project and Subproject ................................... 35
Figure A1.1. River basins and provinces related to WB5 Project ............................................ 38
Table A1.1: List of the first year subprojects (5 provinces, 5 basins) ...................................... 39
Table A1.3: Classification of subprojects under Component 4 by type of works .................... 42
Table A1.4: Number of subprojects under Component 4 by provinces ................................... 43
Table A1.6: List of List of Dams Proposed Under the Project…………………………….....45
Table A1.7: List of the activities to be implemented under Component 3 .... Error! Bookmark
not defined.
Table A5.1: Results of Safeguard Screening for the First Year Component 4 Subprojects..... 71
Table A5.2: Potential Negative Impacts of the First Year Component 4 Subprojects: Chị cập
nhật lại số liệu theo email a. Tuấn gửi ngày 21-10-2011. ........................................................ 73
Table A5.3: Results of Preliminary Safeguard Screening for potential subprojects for the
follow-on years by provinces ................................................................................................... 76
Table A6.1. Potential Environmental and Social Impacts, Mitigating Measures; Monitoring,
and Responsible agencies ......................................................................................................... 81
Environmental and Social Management Framework (ESMF) Viet Nam Managing Natural Hazards Project (Vn-Haz/WB5)
v
Abbreviations CAFSCP Commune Annual Flood and Storm Control Plan
CBDRM Community-Based Disaster Risk Management
CCCC Commune CBDRM Coordination Committee
CCFSC Central Committee for Flood and Storm Control
CDPM Community Disaster Prevention Management
CFSC Committee for Flood and Storm Control (at Province, District and
Commune levels)
CPC Commune People's Committee
CPMO Central Project Management Office
CPO Central Project Office of MARD
CSC Construction Supervising Consultant
CSEP Contract Specific Environmental Plan
DARD Department of Agriculture and Rural Development
DMC Disaster Risk Management Committee
DMDP Dredge Materials Disposal Plan
DoNRE Department of Natural Resources and Environment
DPC District People's Committee
DRM Disaster Risk Management
DSF Dam Safety Framework
DSR Dam Safety Report
EA Environmental Assessment
EIA Environmental Impact Assessment
ECOP Environmental Code of Practices
EMC Environmental Management Consultant
EMDP Ethnic Minority Development Plan
EMP Environment Management Plan
EMPF Ethnic Minority Policy Framework
EPC Environment Protection Commitment
ESMF Environment and Social Management Framework
ESU Environment and Social Unit
GoV Government of Vietnam
HH Household
MARD Ministry of Agriculture and Rural Development
MoNRE Ministry of Natural Resources and Environment
NRDMP National Risk and Disaster Management Project
OP Operation Policy of World Bank
PPC Provincial People’s Committee
PPMU Provincial Project Management Unit
QCVN National Technical Regulations
RAP Resettlement Action Plan
RPF Resettlement Policy Framework
TCVN National Environmental Standards
UXO Unexploded Ordnance
WB World Bank
Executive Summary
1. Project Development Objective and Components: The development objective of the
Project is to increase the resilience of the people and economic assets to natural hazards in
selected river basins of the project provinces within the overall framework of the Vietnam’s
National Disaster Prevention, Response and Mitigation Strategy Towards 2020. The Project
consists of the following components: (i) Strengthening Disaster Risk Management
Institutions, Information Systems and Planning to promote technical capacities and
implement policies, plans, guidelines, databases related to disaster prevention, response
and mitigation; (ii) Strengthening Weather Forecasting and Early Warning Systems to
improve national integration of hydrometeorology services and the delivery of locally
relevant early warning and weather information services; (iii) Community-Based Disaster
Risk Management to make vulnerable communes more disaster-resilient; (iv) Priority
Disaster Risk Mitigation Investments to mitigate risks posed by storms, floods, landslides
and drought, including river and sea dykes and embankments, safe harbors, dam safety,
rescue roads and reservoirs; and (v) Project Management to deliver sound project
coordination, financing and procurement, as well as ensure timely reporting and lesson
learning.
2. World Bank’s safeguard policy: The Project has been assigned as category “B” and
WB clearance of the mitigation measures is required. The Project has to comply with the
following safeguard policies: Environmental Assessment (OP/BP 4.01); Involuntary
Resettlement (OP/BP 4.12); Indigenous Peoples (OP/BP 4.10); Safety of Dams (OP/BP 4.37);
Physical Cultural Resources (OP/BP 4.11); and Projects on International Waterways (OP/BP
7.50). Public Consultation and Information Disclosure of safeguard documents as well as full
compliance with GOV regulations will also be required. To assess the potential impacts an
Environmental Assessment (EA) and a Social Study were carried out. The EA concluded that
the Project will not affect critical natural habitats/protected areas and/or involve forest
logging/production but may involve relocation of graves.
3. Project impacts: The overall impacts will be positive. The negative impacts will be
due to activities to be carried out under Component 4, especially those related to: (i) Land
acquisition and resettlement of local people including ethnic people and (ii) Site clearance and
construction which could temporary increase levels of dust and other air pollution, noise,
vibration, water pollution, local traffic volume, safety risk, and other impacts on local
residents and businesses. These impacts however will be small to moderate, localized and
temporary, and can be mitigated through good construction management and practices with
close supervision of contractors by field/site engineers and in consultation with local
authorities and local residents. To mitigate these impacts a standard Environmental Code of
Practices (ECOP) has been developed and it will be included in the bidding and contract
documents for the Component 4 subprojects. There are UXO risks during construction but
this risk is considered moderate and could be mitigated through an UXO examination and
clearance (as needed) prior to commencing civil works. There are also risks during operation
if the infrastructures are not properly designed and/or maintained adequately and/or sluices
are not properly operated, but these risks are also considered moderate and could be mitigated
through proper design, close consultation among stakeholders, and the capacity building
activities to be carried out under Components 1, 2, and 3. Risk related to coastal erosion could
be mitigated through proper design of coastal structure and consultation with nearby local
authorities and communities.
Environmental and Social Management Framework (ESMF) Viet Nam Managing Natural Hazards Project (Vn-Haz/WB5)
2
4. Potential negative impacts of the activities to be carried out under Components 1, 2, 3
will be limited to those related to small works/infrastructure such as renovation/construction
of office/building, community shelters, elevated road path, small bridges and/or two-story
concrete school building for evacuation purpose during emergency cases. These impacts can
be mitigated through the participatory planning process and/or the application of good
construction practices. A simple ECOP has also been developed and it will be applied to
bidding and/or construction contracts.
5. The Environmental and Social Management Framework (ESMF). Given that the
subprojects will be implemented in phases an ESMF has been prepared to ensure that the
subprojects and activities to be financed under the Project would not create adverse impacts
on the local environment and local communities and the residual and/or unavoidable impacts
will be adequately mitigated in line with the WB’s safeguard policy. The ESMF describes
criteria for safeguard screening and identification of impacts; basic principles for development
of mitigation measures; requirements for WB safeguard clearance; and implementation,
supervision, monitoring, and reporting. The ESMF also provides guidelines for preparation of
an EMP for a subproject, including actions to facilitate effective implementation of the EMP,
institutional arrangement, safeguard training and capacity building, and budget allocation and
source of funds. Below provides a brief summary of the ESMF process while details are
provided in Section V.
Safeguard Screening and Identification of Impacts. All the Component 4 subprojects
will undergo the safeguard screening process to determine the nature and scale of the
potential negative impacts. An exclusion list has been developed to screen and exclude
subprojects that potentially adversely affect areas of biological importance, conversion
of site with valuable landscape, removal of objects with historical/religious
appreciation, or encroachment on mangrove forest regardless of the size.
Development of Mitigation Measures and Public Consultation. Data collection will be
carried out to develop mitigation measures including conducting public consultation as
needed.
EMPs, EMDPs, and RAPs Preparation and Clearance. PPMUs will be responsible for
preparing EMPs, EMDPs, and RAPs with assistance from international and/or national
technical specialists. CPMO will be responsible for the review and ensuring the
compliance with ESMF, RPF and EMPF.
6. Implementation, Supervision, Monitoring, and Reporting. This will be in line with the
overall institutional arrangement of the Project.
7. The CPMO set up by MARD, which is responsible for the overall implementation of
the project, will be responsible for the implementation of the ESMF, RPF and EMPF while
PPMUs who is responsible for project implementation at the local level will also be
responsible for implementation of safeguard measures at the subproject level. Cost for the
preparation of the subproject safeguard documents and implementation of safeguards policies
will be included in the Project cost. Safeguard training will be provided.
Environmental and Social Management Framework (ESMF) Viet Nam Managing Natural Hazards Project (Vn-Haz/WB5)
3
Section I: Introduction
8. The development objective of the Vietnam-Managing Natural Hazards Project (the
Project) is to support the implementation of the National Disaster Prevention, Response and
Mitigation Strategy by increasing the resilience of people and assets to natural hazards in
selected major river basins in Central Vietnam. The Project activities will be implemented
through five components over a five-year period (2012-2017). The Project will involve both
structural and non-structural measures including institutional capacity building. The Project
description and areas are provided in Section II.
); and (f)
Projects on International Waterways (OP/BP 7.50). Other policies such as Natural Habitats
(OP/BP 4.04), Forests (OP/BP 4.36), Pest Management (OP/BP 4.09), and Project in Disputed
Areas (OP/BP 7.60) are not triggered since all the subprojects are not located in the critical natural
habitats and/or degrade any natural habitats or affect ecological health and quality of forests
and/or the people who are depending on them.
10. To be in line with WB’s safeguard policy on Environemtnal Assessment (OP/BP
4.01), an Environmental Assessment (EA) and a social study were carried out for the Project.
Given that the scope of Component 3 activities which will be limited to increasing awareness
and capacity building of local communities and renovations and/or construction of small
office buildings, the EA concluded that (i) key potential negative impacts of the Project (both
social and environmental) will be due to the implementation of Component 4 subprojects; and
(ii) an Environmental and Social Management Framework (ESMF) should be prepared to
ensure that the subprojects and activities to be financed under the Project would not create
adverse impacts on the local environment and local communities and the residual and/or
unavoidable impacts will be adequately mitigated in line with the WB’s safeguard policy. In
this context the ESMF has been prepared as a standalone document and the ESMF process
will be applied to the Component 4 subprojects. A Dam Safety Framework (DSF) has also
been prepared to be aplied to the subproject involving dam safety. To mitigate the potential
negative impacts of activities to be implemented under Components 1, 2, 3 that involve small
civil works, a simple Environmental Code of Practice (ECOP) has been prepared and it will
be included in bidding and contract documents.
11. Section II briefly outlines the Project description while more details can be found in
the Project Appraisal Document (PAD). Section III outlines the legal and policy framework
related to the safeguard policies, while Section IV summarizes the potential impacts and key
mitigation measures for the Project. Section V describes the ESMF process for the
Component 4 subproject comprising safeguard screening, impact assessment, safeguard
documentation and clearance, and safeguard implementation, supervision, and monitoring
while Section VI describes measures for other activities. The social safeguard documents
comprising the Resettlement Policy Framework (RPF) and the Ethnic Minority Policy
Framework (EMPF) for the Project and the Resettlement Action Plans (RAPs) and Ethnic
Minority Development Plans (EMDPs) of the first year subprojects have been prepared
separately and submitted to the Bank. The safeguard screening and preparation of EMPs,
RAPs, and EMDPs for the future subprojects will be carried out during implementation.
Environmental and Social Management Framework (ESMF) Viet Nam Managing Natural Hazards Project (Vn-Haz/WB5)
4
Section II. Project Description
(a) Project Components
12. The project consists of five components, namely Component 1: Strengthening DRM
Institutions, Information Systems and Planning; (2) Strengthening Weather Forecasting and
Early Warning Systems; (3) Community-Based Disaster Risk Management; (4) Priority
Disaster Risk Mitigation Investments; and (5) Project Management.
Component 1: Strengthening Disaster Risk Management Institutions, Information
Systems and Planning (US$ 7.0 million).
13. The specific objective of Component 1 is to strengthen institutional and technical
capacities at national, provincial and local level on disaster risk management (DRM) in order
to better plan and mitigate hazard risks, thereby reducing potential loss of life, damage to
property, and economic disruption. The institutional strengthening will be in line with the
priorities outlined in the National Strategy for Natural Disaster Prevention, Response and
Mitigation to 2020 its national Action Plan and draft DRM law, which serves as the
overarching document for the Government's approach to disaster management and MARD’s
Institutional Vision for 2020.
14. The component will focus on the institutional mechanisms relevant to national,
provincial and local levels as well as regional scale for hydromet services. The DRM
institutions of 10 provinces of Central Vietnam (Thanh Hoa, Nghe An, Ha Tinh, Quang Binh,
Quang Tri, Da Nang, Quang Nam, Quang Ngai, Binh Dinh and Ninh Thuan) will be covered
with an renewed focus on a river basin approach.
15. Component 1 will have three sub-components: (i) Strengthening DRM institutions, (ii)
Improvement of the DRM information systems, and (iii) Support for the integration of DRM
in river basin Planning.
16. Under the first sub-component, Strengthening DRM Institutions, the project will
provide relevant support to implement the National Platform on Disaster Preparedness,
Prevention and Mitigation and Adaptation to Climate Change. This activity aims to facilitate
inter-ministerial coordination meetings, policy dialogue and knowledge-sharing mechanisms
between the government ministries, development partners, academic institutions, NGOs and
private sector. One of the outputs of this activity will be to develop an on-line web-based
knowledge sharing portal on Disaster Risk Management (DRM) and Climate Change
Adaptation (CCA) at national level. The sub-component will also review and update DRM
codes, standards and technical manuals for water resources management at river basin level.
Technical assistance will be given for a study on the feasibility of financing mechanisms for
DRM.
17. The sub-component will support the establishment of 8 Provincial Disaster
Management Centers (PDMCs) in the project target provinces (except in Quang Ngai and Da
Nang where PDMCs already exist). This would include renovation of office facilities and
basic equipments. Before establishing PDMCs, a detailed study on the performance of
existing PDMCs and standing office of PCFSC will be conducted in order to propose the most
relevant PDMC model. The experience and lessons learned from the existing PDMCs and
river basin approach adopted in this project will be considered while establishing PDMCs in
eight provinces.
Environmental and Social Management Framework (ESMF) Viet Nam Managing Natural Hazards Project (Vn-Haz/WB5)
5
18. The sub-component will strengthen DRM technical capacity of government agencies
at different levels. This will require an update of training needs assessment of national and
provincial level agencies involved in DRM work which was done by the on-going Bank-
financed NDRMP, and subsequent training would cover all aspects of DRM such as risk,
vulnerability assessments, preparedness, search and rescue, and response. The National level
Disaster Management Centre (DMC), which is mandated to offer CBDRM training to
provincial and district level staff, will be supported with technical assistance to improve
training content. Technical expertise on CBDRM will be strengthened at the provincial and
lower levels following a Training of Trainers (ToT) approach, using an experienced local
consultancy firm to conduct the trainings. The national DMC would provide supervision,
technical guidance and monitoring of these trainings.
19. The CBDRM training curriculum will integrate on-going capacity development related
to Community Based Adaptation (CBA). This activity is closely related to component 3
(CBDRM), and ToT training would cover all 10 provinces. The ToT training will target
provincial level staff, and after the training, these staff would participate together with other
experts in providing similar trainings to selected district and commune (component 3) level
staff. It is proposed to conduct CBDRM trainings in each of the 28 districts selected under
component 3. This sub-component will also support international training on DRM and study
tours.
20. The second sub-component, Improvement of the DRM information Systems, will
support DRM databases, spatial interpretation tools, and dam/reservoir safety information
systems. Strengthening existing DRM databases and information systems include update
and addition of indicators such as hazards, vulnerability, risks, livelihood groups, data on
damage and loss, socio-economic information and post disaster interventions. MARD’s
current information collection procedures will be improved and linked to the proposed
information systems. In addition, links will be established to existing socio-economic
database of General Statistics Office (GSO) of Vietnam. Interactivity of the databases is
expected to be enhanced by strengthening query and quality checking procedures. This
activity will help to harmonize all existing DRM databases and provide access to agencies
involved in DRM related work.
21. A database on smaller dams/reservoirs held by MARD is currently not available at the
provincial level. There are at least three different management layers of reservoirs (provincial,
district and commune level), and lack of coordination and information exchange weakens the
reservoir operation and disaster preparedness. Improved coordination and sharing of
information can promote better management of these reservoirs and protect lives and
livelihood assets. The project will support: (i) an inventory of existing medium and small
scale reservoirs, their safety standards, operational procedures; (ii) development of a software
that can be applied at national and provincial level; (iii) development of guidelines for safety
of medium and small reservoir/dam operations in 10 provinces, and (iv) a training program on
how to use the database, software and on guidelines for safety of medium and small reservoir
operations to provincial and district staff.
22. The third sub-component, Support for the Integration of DRM in River Basin
Planning, will help integrate DRM into river basin management. In particular, the sub-
component would support: (a) data collection and assessment of exposure, risks and
vulnerability at the basin scale, (b) identification of vulnerable areas, and possible structural
and non-structural measures to mitigate the natural disaster risks. The sub-component will
cover all river basins in the 10 project provinces to be supported under the project, and take
place in two phases: a study phase and the preparation of the river basin plan itself.
Environmental and Social Management Framework (ESMF) Viet Nam Managing Natural Hazards Project (Vn-Haz/WB5)
6
23. The study phase will assess the main DRM problems in the river basins (such as
environmental degradation, soil erosion, drought, landslides, sedimentation, solid waste
management, water quality, flood impacts); the climate change impacts on the major river
basins; flood mapping combining existing hazard and vulnerability maps prepared under
NDRMP project with new data sets; an institutional analysis; and an inventory of existing
plans (land use, provincial disaster management plans, agriculture, transport). The DRM
priorities and basin risk maps would then be integrated into river basin plans.
24. At present, nine out of ten provinces have prepared Integrated DRM Plans (IDRMs)
under the Bank-funded NDRMP project. At the same time, the National Target Programme on
Climate Change requests provinces to prepare provincial plans on adaptation to climate
change. Given that there are similarities with respect to actions under DRM and CCA and that
promoting two similar plans may add complexity for the provincial authorities, there is a need
to integrate CCA into DRM action plans aiming to address short term priorities, but at the
same time with long-term perspectives. This activity will promote a joint action plan for CCA
and DRM in 10 provinces based on lessons and experiences from IDRMP exercise and
updated comprehensive vulnerability and risk analysis.
25. Finally, the sub-component will provide training on the use of hydrological models
and GIS tools to DRM staff at provincial level and will be closely linked to component 2 of
the project. This activity will promote use of existing data on land use, vulnerabilities and risk
maps from NDRMP project combined with satellite imageries for preparation of flood maps
in eight river basins (Ma, Ca, Vu Gia-Thu Bon, Tra Khuc Tra Bong, Kone Ha Thanh, Thach
Han, Gianh, Cai Phan Rang). These flood maps will contribute to preparation of river basin
plans and joint action plans for DRM and CCA described above. Technical specialists from
the sub-Department for Water Resources and Flood and Storm Control within the provincial
DARD, MARD’s Water Resources Directorate and Faculty of Hydrology in Water Resources
University (WRU) will be trained on modeling, use of satellite maps and GIS.
Component 2: Strengthening Weather Forecasting and Early Warning Systems ($30.0
million)
26. The objectives of component 2 are to strengthen hydrometeorological services,
weather forecasting and early warning systems for disaster preparedness at all levels and to
improve delivery of locally relevant early warning products and services. Particular emphasis
will be given to strengthening the integration of the existing and planned hydro-met
components in the country. Two sub-components will be implemented: (i) Designing and
implementing an integrated national hydromet forecasting and early warning system and end-
to-end applications at the regional and provincial level; and (ii) Strengthening hydromet
observation and monitoring network, computer hardware and ICT infrastructure.
27. Sub-Component 2.1 Technical Assistance for development and implementation of an
integrated National Hydromet forecasting and EW System and end-to-end applications ($6
million): This sub-component will cover the technical assistance to design a nation-wide
integrated system and to provide overall guidance and implementation support. This will
include the preparation of hydrometeorological implementation plans for the national and
central region and the design of a nation-wide communication system. Priorities to be
addressed include (i) Analysing institutional frameworks, staff capacity requirements and
Preparation of Concept of Operation; (ii) providing technical advice on software, forecasting
models, instruments, computer architecture and data processing; (iii) Instrument
specifications, ensuring inter-operability of the observation networks and contract
performance monitoring; and (iv) providing support for the development and testing of a
sustainable hydromet business model. An Integrator will be hired at the beginning of the
Environmental and Social Management Framework (ESMF) Viet Nam Managing Natural Hazards Project (Vn-Haz/WB5)
7
project to develop a detailed framework and to support and monitor the implementation of the
integrated system.
28. Technical support will be provided for the maintenance and operation of hard- and
software of weather forecasting and early warning systems according to the developed
concept of operation. The national level strengthening will ensure better integration of the
planned improvements (observation, forecasting and communication infrastructures) proposed
for three regional hydrometeorological centers (north-central, mid-central, and southern)
under sub-component 2.2. Synergies and collaboration will be sought with other proposed and
existing investment programs, including the Government-funded MONRE investment
program and donor-funded programs such as the Italian ODA program phase I & II, the
Mekong River Commission’s-HYCOS, the USAID support and the Japan International
Cooperation Agency (JICA) assistance.
29. An overall training strategy will be developed to improve the technical capacity at
national, regional and provincial levels based on user information needs and institutional
analysis. The objectives of the training are to maintain the hard- and software, use the weather
and hydrological models and analyse model outputs (down-scaling), and prepare quality
forecast products and early warning information. The capacity development programs will
include training on weather forecasting, drought monitoring, storm surge prediction, seasonal
climate prediction and assessment of climate change impacts. Improvement of forecast
models and other software include high resolution non-hydrostatic Numerical Weather
Prediction (NWP) models, topography and land use database, ensemble multi-scale weather
forecast models for short range forecasts, hydrological and hydraulic models for flood
forecasting and flash flood warning, integration of radar data (existing) for hydraulic models
and development of techniques for quantitative precipitation estimate from radar and visual
display and analysis system.
30. User interaction, climate data and information sharing will be strengthened by
establishing a national user forum (linked to a national platform supported under component
1). This sub-component includes study tours and on-the-job training for managers.
Strengthening of end-to-end application includes user training on interpretation of early
warning products for provincial departments, district staff and communities for better
informed decisions. Three regional hydro-met centers (north-central, mid-central and
southern) are included.
31. Sub-Component 2.2. Strengthening hydro-met observation and monitoring network,
computer hardware and ICT infrastructure ($20 million): This sub-component will support
the establishment of multi-hazard early warning systems, including the installation of
automated hydro-meteorological observing networks and communication systems through
provision of equipment and relevant training.
32. Major priorities to be addressed include: (i) Upgrading ICT infrastructure and
computer hardware at national, regional and provincial NHMS centers, (ii) modernization of
hydromet observation and monitoring infrastructure in north-central, mid-central and southern
regional centers; and (iii) improvement of technical capacity to maintain instruments,
including observation, data transfer and communication between provincial, regional and
national hydro-met centers. Installation of computer systems and forecast interpretation tools
such as GIS mapping facility to deliver rapid location-specific forecasts are included. Three
regional hydro-met centers (north-central, mid-central and southern) are included under this
Environmental and Social Management Framework (ESMF) Viet Nam Managing Natural Hazards Project (Vn-Haz/WB5)
8
sub-component1This sub-project would be implemented in the two phases: (a) Phase 1
(southern region) to complete the initiative taken by the NDRMP, and (b) Phase 2 (national
and central region).
33. Major investments include High Performamce Computer (HPC) hardware and
operating software, service development and technical support for the national center,
upgradation of computer hardwares and operating softwares, service development and
technical support for the provincial centres; modernization and upgrading of existing
meteorological stations and automatic weather stations, upgrading to SMS automated rain
gauge networks, automatic water level and rain gauge stations, integrated discharge and
suspended sediment, water level and rainfall measuring devices and boats for discharge and
velocity measurements. This sub-component covers upgrading of communication networks to
connect provincial and regional centres with the national centre and setting up a LAN and
other communication networks in three regional centres, together with a reliable backup
system. Real time status of major and important reservoirs will be included within the LAN
communication network for development of flood forecasting services. Upgrading of
equipment and networks will be closely coordinated with ODA activities to avoid potential
duplication and overlaps.
34. The sub-component will include support for the southern regional hydromet centre.
This support will facilitate an upgrade of meteorological instruments and an enhancement of
the hydrological monitoring along the Mekong river. The support in question will focus on the
design and establishment of an automated hydrologic network and on defining clear operating
procedures for the network. The modernization will cover automatic weather stations, river
discharge measurements devices, suspended sediment measurement, sounding depth
measurement device, automatic water level recorders and flood measurement poles; and
calibration and evaluation of flood danger/alarm levels. It will also help complete the
renovation/construction of office buildings for five provincial centres and other fire fighting
and early warning equipments. Training and capacity development activities include operation
and maintenance of automatic weather stations, maintenance of water level and rain
measurement devices and maintenance of discharge and water depth measurement
instruments.
Component 3: Community-Based Disaster Risk Management ($22.0 million)
36. This component will build on the successful pilot experiences in community-based
disaster preparedness including safer commune planning and risk management awareness
under the current Bank-financed NDRMP project. It also introduces new design features,
including river basin approaches, cluster approaches, interactive Management Information
System (MIS) with commune reporting by cell phone and private sector-commune
partnerships.
37. The objective of this component is to help implement the GoV’s national CBDRM
strategy (Decision 1002/QD-TTg). As a result this component, approximately 100 communes
will be better prepared for natural disaster events.
38. The selection of communes will be carried using a clustering approach which will
ensure that the communes selected are those benefiting from the larger scale infrastructure
investments supported under Component 4. This integration, following a river basin approach,
will maximize and better sustain the impacts from the larger scale DRM investments as well
1 The priority (i) on “modernization of measurement/monitoring infrastructure and data transfer” will be excluded
for mid-central region as this has already been covered by ODA assistance to the Regional Hydro-Meteorological Centre located in Da Nang.
Environmental and Social Management Framework (ESMF) Viet Nam Managing Natural Hazards Project (Vn-Haz/WB5)
9
as the commune level engagement. Under the first phase of the DRM investments, 27
communes have been identified for support (see Table 1). The identification of the remaining
communes will be conducted after project inception. The abovementioned objective will be
achieved through two sub-components: (i) Commune Institutional Strengthening and (ii)
CBDRM Investments.
Table 1. The List of Proposed Commune for Phase 1 CBDRM Activities
No Province District Commune River basin
1 Thanh Hoa Yen Dinh Yen Thinh Ma river
2 Dinh Hoa Ma river
3 Dinh Thanh Ma river
4 Dinh Cong Ma river
5 Dinh Binh Ma river
6 Dinh Tuong Ma river
7 Yen Tam Ma river
8 Yen Giang Ma river
9 Thieu Hoa Thieu Thanh Ma river
10 Tho Xuan Xuan Vinh Ma river
11 Ha Tinh Cam Xuyen Cam Phuc Rac River
12 Cam Long/
Thien Cam town Rac River
13 Cam Nhuong Rac River
14 Cam Thang Rac River
15 Quang Nam Duy Xuyen Duy Phu Thu Bon river
16 Duy Thu Thu Bon river
17 Duy Tan Thu Bon river
18 Duy Hoo Thu Bon river
19 Binh Dinh Tuy Phuoc Phuoc Hoa Kon river
20 Phuoc Hiep Kon river
21 Phuoc Quang Kon river
22 Phuoc Loc Kon river
23 Phuoc Thuan Ha Thanh river
24 An Nhon Nhon An Kon river
25 Nhon Phong Kon river
26 Nhơo Hau Kon river
27 Nhon Khanh Ha Thanh river
28 Nhon Hung Ha Thanh river
39. Commune Institutional Strengthening ($2.0 million). This sub-component aims to
develop the capacity of participating commune-level stakeholders and agencies2 to plan and
engage in a broad range of risk reduction measures encompassing “pre-, during- and post-
disaster” activities. Gender equality and integration will be ensured through these capacity
development initiatives, as too will be the focus on vulnerable groups. Main activities
include:
Strengthening of commune-level flood and storm risks management procedure. This
activity will help commune-based institutions to prepare a commune-annual flood and
storm risks management plan (CAFSCP) on yearly basis. 3
The plan will improve early
warning and support the Communal Committee for Flood and Storm Control (CFSC)
2 Commune-level stakeholders and agencies in this document refer to not only government
agencies, institutions, political parties and interest groups, but also other private organizations and citizens.
3 This activity would build on existing manuals such as CCFSC Manual/Handbook, the “four on the
spots’ motto” and CCFSC “Emergency response and early recovery guidelines”.
Environmental and Social Management Framework (ESMF) Viet Nam Managing Natural Hazards Project (Vn-Haz/WB5)
10
and its counterparts to understand responsibilities during pre- and post-disaster
activities.
Training for commune-based institution leaders. The project will provide training to
improve capacity of CFSC, CBDRM facilitators and other commune-level stakeholders
and agencies (see Appendix 1 for details of training).
Development of inter-communal support platforms. This activity will develop an inter-
communal support platform where leaders of the CFSCs and commune-based
institutions conduct exchange visits to plan co-operation for pre- and post-disaster
activities, including joint evacuation exercises, post-disaster clean up and relief
operations.
Community Resilient Planning: Each participating commune will: (i) identify its
vulnerability through a participatory risk assessment; (ii) prepare and update commune-
level annual flood and storm control plans (CAFSCP) based on the risk assessment;
and (iii) integrate the CAFSCP into commune socio-economic development plans.
Private sector-commune partnerships. This project seeks to develop enterprise-
community collaboration for enhancing commune resilience to disasters and thereby
support the Government’s development objectives under the National Community-
Based DRM Program and the National Program of Developing New Rural Areas, both
of which highlight private sector engagement as a key requisite for successful
implementation.
40. CBDRM Investments ($18.0 million). This sub-component will fund CBDRM
activities identified in the updated CAFSCPs. Risk reduction measures will include non-
structural and structural measures determined through the VCA and CAFSCP and driven by
the needs of the local communities, which would include representatives of most vulnerable
in the communes.
Non-structural measures: Activities will include evacuation drills, public
awareness raising, communications/early warning systems, provision of small
equipment such as small boats, pumps, and first aid kits. Activities will be
followed by participatory workshops to review the results and document the
lessons learned in the CAFSCP.
Structural measures: The project would support the participating communes to
construct small-scale physical structural measures in a hazard-resilient manner.
These would include multi-purpose shelters, evacuation roads, bridges, river bank
rehabilitation, retention ponds as well as reforestations and other structures
identified by the target communes. The project will also provide support to prepare
plans and designs for such prevention measures and plans for the management,
operation and maintenance of each structural measure built. The CPC would be
responsible for monitoring and reporting on the progress and quality of
construction as well as for preparing and implementing operational and
maintenance guidelines.
41. Monitoring and Evaluation of CBDRM. As a part of the project-wide M&E
framework, the project will set up a CBDRM monitoring system that will be both
participatory and also use a web-based Management Information System (MIS) at national
and sub-national levels. The system will record the performance of each commune in close to
real time. Key performance information on the status of project implementation will be
available to authorized users at national and provincial level.
Environmental and Social Management Framework (ESMF) Viet Nam Managing Natural Hazards Project (Vn-Haz/WB5)
11
Component 4: Priority Disaster Risk Mitigation Investments ($104.7m)
42. A river basin approach will be used to identify and prioritize major DRM investments
(subprojects) within the four selected river basins in the Central Region. The structural
measures will mitigate risks posed by storms, floods, landslides and drought, including river
and sea dykes/ embankments, safe harbors, rescue roads and bridges, and reservoirs. The
Government strategy on reservoirs for disaster management objective would mainly be
focusing on rehabilitation of selected existing dams and reservoirs to improve their safety.
The rehabilitation would involve safety measures such as lowering and/or expansion of
existing spillway or building addition spillway, additional backfill with better compaction of
the main dam and its auxiliary apparatus, termite treatment, grouting, and installation of
safety monitoring devices.
43. Based on the Integrated DRM Plans (IDRMPs) developed under the on-going Bank-
financed NDRMP project in all 12 project provinces using hydraulic modeling technology
piloted in the three provinces of Thanh Hoa, Quang Tri and Quang Nam. These plans provide
number of priority infrastructure investments within the context of disaster risk management
and climate change adaptation for long-term benefits. These plans have been reviewed and
endorsed by MARD and the provincial authorities.
44. Experience learned from the on-going Bank-financed NDRMP project proved that an
investment of approximately UD$ 12 million protecting 12 communes with population of
64,000 and 5,271 hectares of rice land. A dam safety investment with budget of US$ 6 million
protected 8 communes living downstream 80,960 population and about 4,500 hectares of
agricultural land. Similarly an amount of US$ 2.5 million to build a safe harbor in one of the
province in the Central Coast that helped protect about 1,500 small fishing boats to evacuate
during the typhoons season of the last and this year. This proves that priority infrastructure
investments are crucial to protect livelihood and economic assets of local people who are
living in the disaster-prone areas. This is also confirmed in the Government’s strategy on
DRM prevention and mitigation.
45. Phase 1 Investments: These will include the high priority specified in the approved
IDRMPs, and are most advanced in term of preparation including technical engineering,
economic/financial, social safeguards aspects. A maximum of two such ‘subprojects’ would
be implemented per one province over the course of the first two years of the project
depending on the readiness of preparation of subprojects. Greater priority would be given to
those subprojects that incorporate a river basin approach, and have complementary
investments under other components clustered nearby. Six subprojects have been confirmed
as ready for inclusion in Phase 1 spanning in 5 provinces, including four dyke or embankment
upgrading, one bridge with connecting rescue roads, and one reservoir upgrade. These are:
(i) 42 km. of a river dyke system in a tributary of Ma river basin in Thanh Hoa province
(ii) 7 km. of river bank protection and 3 km. of rescue roads and 100 m and a birdge in Ca
river basin in Nghe An (2 subprojects)
(iii)11.5 km of Phuc-Long-Nhuong Sea-dyke improvement in Ha Tinh province, prepared
by the current NDRMP project
(iv) Dam safety improvement in Vu Gia-Thu Bon river basin in Quang Nam province
(v) 4 km. of River embankment erosion protection in Kon river basin in Binh Dinh
province
46. Phase 2 Investments: These investments would include other high priority physical
investments that need further detailed preparation work after project start-up, and that together
Environmental and Social Management Framework (ESMF) Viet Nam Managing Natural Hazards Project (Vn-Haz/WB5)
12
with Phase 1 investments fall under within the cost ceilings indicated above. Provinces would
undertake detailed technical, social, environmental and economic design work over the course
of year 1 and 2 and submit these for approval by MARD and no objection by the World Bank
for execution in years 3, 4 and 5. 28 other subprojects are shortlisted for inclusion in Phase 2
including 11 dyke, embankment and weir repair, 3 roads/bridges, 2 harbors and 9 reservoir
subprojects. The harbor works would involve some dredging of sea sand, construction of
breakwater structure, buoys and anchoring system for fishing boats to hire during flood and
typhoon events. Reservoir works would be mainly on rehabilitation a stated earlier. Details of
phase 2 proposed by provinces are in Annex 1.
Component 5: Project Management ($3.8m)
47. The objective of this component is to deliver sound project coordination, financing
and procurement, as well as ensure timely reporting and lesson learning. This component
provides financial support for those project implementing entities in MARD and MONRE
responsible for project coordination, financial management and procurement, as well as
ensuring compliance with relevant safeguards and fiduciary policies. It would provide
incremental operating cost for implementing agencies at all levels in managing the
implementation of the project.
48. Strengthening of both national and provincial implementation capacity of the project
will include provision of office renovation, equipment facilities and vehicles, external
monitoring on fiduciary and safeguards, internal audit and control, operating expenses and
training. The component will also support the establishment of an effective M&E system for
the project and applicable to the broader DRM sector including tracking the implementation
of the National DRM Strategy. The system will monitor the performance of the various
implementing partners at national and local level and the achievement of project deliverables
as defined in the results framework and detailed M&E design. An independent baseline and
final evaluation will be funded.
49. The detailed design will be prepared by international technical assistance in the first
six months of project implementation. Funding is provided for an independent baseline to take
place between appraisal and project effectiveness, and final evaluation in Year 5. The
estimated cost includes contribution from the Government, such as personnel, office space,
and utilities both at the central and provincial level.
(b) The Project Area and the Subprojects 50. The project area will cover the central part of Vietnam, spanning 8 river basins and
involving ten provinces including Thanh Hoa, Nghe An, Ha Tinh, Quang Binh, Quang Tri,
Danang, Quang Nam, Quang Ngai, Binh Dinh, and Ninh Thuan. Priority investments would
be given to the following four major river basins: Ma River basin in Thanh Hoa, Ca River
basin in Nghe An and Ha Tinh provinces; Thach Han River Basin in Quang Tri province; and
Vu Gia-Thu Bon in Da Nang and Quang Nam provinces. These river basins are located
entirely within Vietnam, except the upper part of Ca River which is located in Lao People’s
Democratic Republic (PDR), and Ma River which originates in Vietnam but runs through Lao
PDR before coming back to Vietnam territory. Of the 513 km long and 27,200 km² catchment
of the Ca River, 361 km and 17,730 km² are located in Vietnam. Other four river basins (with
less number of subprojects) include Ha Vang-Rac River basin in Ha Tinh province, Tra Khuc-
Ve-Tra Bong River basin in Quang Ngai province, Kone River basin in Binh Dinh province,
and Dinh River basin in Ninh Thuan.
Environmental and Social Management Framework (ESMF) Viet Nam Managing Natural Hazards Project (Vn-Haz/WB5)
13
51. Below briefly summarizes the background related to the natural disaster risks in the
four major river basins (Ma, Ca, Thach Han, and Vu Gia-Thu Bon) while more details are
provided in the EA (see location maps in Annex 1).
- Topography: Narrow land, descending from the West (highlands) to the East (coastal
lowlands), divided by dense river networks and mountain ranges extending to the sea.
The plain area is divided into three strips, the coastal strip including sand dunes,
lagoons, coves and gulfs, the middle lowland areas, and the alluvial plain.
- River bank and coastal erosion: River bank erosion and river sedimentation happen in
most of the rivers, causing a relatively high content of TSS (total suspended solids) in
the rivers. Coastal erosion also occurs in many areas along the coast.
- Surface water hydrology: Ma River is short and steep with rapid flows; Flow varies
greatly causing water shortage in the dry season and floods in rainy season with one
flood peak a year. Ca River is originated from Laos and is narrow in the upstream,
widening towards downstream and with two flood peaks a year. Vu Gia-Thu Bon flow
has two separate seasons; the flood season often begins from half a month to a month
later than the rainy season, and often not stable. Thach Han high slope typography
creates straight flows from the highlands to the lowlands, easily causing floods in the
rainy season and drought in the dry season; The flow varies in different months with a
big difference between the highest and lowest flows, causing a prolonged flood
season.
- Infrastructure: In the urban areas, the infrastructure is quite good. In rural areas, the
infrastructure is still poor, especially the rural road systems which haven’t met the
needs for transportation and rescue in heavy rains or floods. There are some
community projects at the commune level which are quite small and scattered.
- Agriculture and aquaculture: The main agriculture form is cultivation of rice and
other edible crops, cultivation and catching of aquatic products which are heavily
dependent on nature variables. Therefore, poor crops and/or considerable damage
often occur when there are floods and storms.
- Community floods: Rural health services haven’t been well-equipped. Epidemics and
environmental pollution often occur after floods due to a lack of proper sewage
systems. During and after floods or storms, floodwater spreads waste from toilets,
causing epidemics and environmental pollution.
- Natural disaster risks: The areas often suffer from storms, floods, flash floods, heat
waves, droughts, etc. Floods and inundations in the Central region usually occur on
large scale, simultaneously in several provinces, sometimes cover the entire region
(such as in 1999, 2003, 2009, 2010). Floods occur in the region more frequently and
more fiercely, causing human casualties, property damage, and soil and water
pollution. Flash floods occur in the headwaters in Ha Tinh, Quang Binh, Quang Nam,
Da Nang, Quang Ngai. Storms and tropical low pressure occur more regularly and
intensely. Heat waves often develop in lowlands such as the coastal plain and river
valleys. In river valleys, hot weather occurs at greater length and intensity.
52. In terms of subprojects, about 34 subprojects have been proposed for Component 4
involving rehabilitation, upgrading, and/or construction of existing dykes/embankments,
rescue roads/bridge, dams/reservoirs, and/or river mouth infrastructure (such as safe fishing
boat harbours). Annex 1 (Table A1.1 – A1.6) provides brief description of the proposed
subprojects.
Environmental and Social Management Framework (ESMF) Viet Nam Managing Natural Hazards Project (Vn-Haz/WB5)
14
53. Activities proposed under Component 3 of capacity building include: supporting for
the establishment or activities of CDPMs at provincial, district and commune levels and
providing training and communication, awareness raising and capacity strengthening
activities on natural disaster prevention at community levels in select communes (Annex 1,
Table A1.7). There are some proposed construction works of small-scale building and
renovating CDPMs such as disaster prevention storages and public houses, etc. where the
simple ECOP will be applied.
(c) The First year subprojects
54. Six subprojects have been proposed for the first year implementation under
Component 4 (Table 2.1) and RAPs, EMDPs, and EMPs for the subprojects have been
prepared and submitted for WB review.
Table 2.1: List of proposed first year subprojects under Component 4
No Sub-Projects River
basins Investment Items
Remarks
I. Thanh Hoa
1
Maintain, upgrade and treat
the key parts of the left
dyke of Cau Chay river
(section from K0-K42),
Yen Dinh district
Ma
river
upgrade 42 km dyke site;
Repair, upgrade and renew
structures on the site; build
more rescue roads
EIA approved by Thanh
Hoa PPC by its Decision
No. 3709/ QD-UBND
dated 11/11/2011
II. Nghe An
2
Bridge combining with
overflow connecting
Rescue roads, Nghi Loc
and Vinh city
Ca
river
65 m bridge combining
with overflow and 1 Km
road and a drain sluice
with B=7.5m
EPC will be prepared and
approved before project
implementation
3 Upgrade dyke site of
Luong Yen Khai Ca
river Line, widen, stabilize the
surface 2.87Km
EIA approved by Nghe An
PPC in its Decision No.
5689/ QD-UBND dated
23/12/2011
III. Ha Tinh
4 Upgrade dyke site Phuc
Long Nhuong, Cam Xuyen
district
Ha
Vang -
Rac
river
Upgrade dyke site of 11.41
km; Renew 21 drainage
sluices crossing the dyke;
build 12 road sites
combining with dyke
rescue with the total length
of 8.974 km
EIA approved by Ha Tinh
PPC in its Decision No.
3954/ QD-UBND dated
14/12/2011
VII. Quang Nam
5 Repair, upgrade Thạch Ban
reservoir, Duy Xuyen
district
Thu
Bon
river
Main dam, overflow,
intake gate, management
house and road
EIA approved by Quang
Nam PPC in its Decision
No. 576/ QD-UBND dated
24/2/2012
X. Binh Dinh
6
Upgrade anti-erosion
embankment of Kone
river for safety, An Nhon
and Tuy Phuoc districts
Kone
river
Upgrade for anti-erosion
for 4 dike sections with a
total length of 5.8 km
EIA approved by Binh
Dinh PPC in its Decision
No. 3044/QD-UBND
dated 29/12/2011
Environmental and Social Management Framework (ESMF) Viet Nam Managing Natural Hazards Project (Vn-Haz/WB5)
15
Section III. Legal and Policy Frameworks
3.1. Government Policy on Natural Disaster Management
55. Natural disaster management. On 16 July 2007, the GOV approved the “National
Strategy for Natural Disaster Prevention, Response and Mitigation to 2020”. Accordingly,
Ministry of Agriculture and Rural Development (MARD) is the standing agency and to
cooperate with relevant agencies to support the Government in executing state management in
the field of disaster management. The overall goal of the Strategy is to “Mobilize all resources
to effectively implement disaster prevention, response and mitigation from now up to 2020 in
order to minimize losses of human life and properties, damage of natural resources and
cultural heritages, and the degradation of environment, contributing significantly to ensure the
country sustainable development, national defense and security”. To achieve this goal, tasks
and measures are laid out as follow: (1) Consolidate the system of laws, policies and
mechanisms; (2) Consolidate organizational structure; (3) Human resources development and
social mobilization, (4) Financial resources; (5) Community awareness raising; (6) Ensure
safety for dyke, reservoir and dam systems; (7) Enhance the search and rescue capacities; and
(8) Promote international cooperation and integration.
56. For the Project areas, natural disaster prevention and mitigation tasks and measures in
the strategy include:
(i) North Central Region: Radically prevent floods, and take initiatives in preventing and
responding to storm, drought and storm surge, for which the following solutions must
be taken in places in the same time: making flood control plannings for river systems,
reviewing and adjusting dyke system plannings as bases for activities of dyke
construction, upgrading, protection, and management; strengthening of underdyke
structures; treatment of weak dyke foundation; and reinforcing dyke surface for rural
traffic, etc.
(ii) Central Coast and the Eastern South: the approach applied for the areas is
"Proactiveness in disaster prevention, and adaptation for development", for which
following solutions are considered as priorities: planning residential, industrial and
tourism areas; planning and constructing disaster prevention and mitigation structures,
and transportation infrastructures to ensure flood resilience and drainability; shifting
crops and animal husbandry; strengthening dykes, building reservoirs and
embankment structures, and increasing forestation; building storm shelters for boats
and ships; establishing and upgrading coastal communication stations for typhoon, sea
rise and tsunami warning.
3.2. Government Laws and Regulations
3.2.1 EIA regulations
57. The Law on Environmental Protection (2005) sets out regulations on strategic
environmental assessment, environmental impact assessment and environmental protection
commitment of development activities. Environmental impact assessment report is developed
at the same time as investment project preparation (feasibility study). Time of preparation,
submission and approval of reports are detailed in Term 2, Article 13 of Circular 26/2011/TT-
BTNMT. The project’s type for the environmental assessment is carried out based on the list
of project types in Annex I and Annex II of Decree 29/2011/ND-CP.
Environmental and Social Management Framework (ESMF) Viet Nam Managing Natural Hazards Project (Vn-Haz/WB5)
16
58. Environmental Impact Assessment (EIA). Articles from 12 to 28 in Chapter 3 of
Decree 29/2011/NĐ-CP provide detailed regulations on the preparation, appraisal and
approval of an EIA report, inclduing a detailed description of technical and management
solutions to address negative impacts and environemtnal monitoring program. According to
this Decree, the subprojects under the Project that require an EIA approval are included in
Annex II of the Decree.
59. Environmental Protection Commitment (EPC). Article 29 to 36 in Chapter 4 of Decree
No. 29/2011/NĐ-CP identifies scope of the EPC requirements, including the review and
approval process and responsibilities of the project owners and agencies in charge of the EPC
preparation, description of pollution mitigation measures, environmental monitoring
programs, and committment to comply with environmental standards.
3.2.2. Pollution control and other regulations
60. Other related regulations:
Regarding construction: Law on Construction No. 16/2003/QH11 and some Decrees such
as the Decree No.12/2009/ND-CP dated 10th February 2009 on managing construction and
investment projects and Decree No. 209/2004/ND-CP dated 16th December 2004 on
managing the quality of construction projects.
Regarding planning, land acquisition and resettlement: Law on Land No.13/2003/QH11
dated 26th
November 2003; Decree No. 197/2004/ND-CP on compensation, support and
resettlement when the State acquires land; Circular No. 116/2004/TT-BTC on instruction
on executing the Decree No.197/2004/ND-CP, etc.
Regarding disaster management: Law on Dykes No. 79/2006/QH11 dated 29 Nov 2006,
Ordinance No. 32/2001/PL-UBTVQH10 dated 04 April 2001 on the exploitation and
protection of irrigation works, Decree detailing some of the Flood Prevention and
Response Ordinance No. 08/2006/NĐ-CP dated 16 Jan 2006, etc.
Regarding dam safety: The Decree No. 72/ND-CP dated 07/05/2007 of the Government's
dam safety management clearly provides provisions for dam construction, dam
management and state management on dam safety. The Decree distinguishes between
small and large dams. Small dams are normally less than 15 meters in height. Large dams
are 15 meters or more in height and/or create a reservoir having a capacity above 3,000,000
m3. Dam owners must have detail plans for water regulation, sluice and related works
operation, dam safety and hydrological monitoring/ inspection, dam maintenance and
protection, dam rescue, dam safety reporting, flood and inundation prevention in the
downstream. All plans must be carried out strictly. MARD is responsible for the state
management of reservoirs and dams nationwide. The Directorate of Water Resources under
MARD assists MARD to implement the function of state management on safety of
reservoirs. The Ministry of Industry and Trade is responsible for the state management of
hydroelectric dam safety. Provincial People's Committees (PPCs) are responsible for the
state management function on reservoir safety in their provinces. PPCs assign the
Department of Agriculture and Rural Development to implement this function.
Other related areas: Law on Forest Development and Protection No. 29/2004/QH11, Law
on Labor dated 23 June 1994, Law on Cultural Heritage No. 28/2001/QH10, Law on Water
Resources No. 8/1998/QH10.
Environmental and Social Management Framework (ESMF) Viet Nam Managing Natural Hazards Project (Vn-Haz/WB5)
17
Vietnamese Environment Standards: National technical regulations on quality of drinking
water QCVN01:2009/BYT; National technical regulations on quality of domestic water
QCVN02:2009/BYT; National technical regulations on quality of surface water
QCVN08:2008/BTNMT; National technical regulations on quality of groundwater
QCVN09:2008/BTNMT; National technical regulations on quality of coastal water
QCVN10:2008/BTNMT; Air quality – Standards for ambient air quality
QCVN05:2009/BTNMT; Air quality – Maximum allowable concentration of hazardous
substances in the ambient air QCVN06:2009/BTNMT.
Dam design standards for flood cycle: 500 to 1000 years for dam grade I; 200 years for dam
grade II; 100 years for dam grade III; 67 years for dam grade IV; and 50 years for dam grade V.
3.3. Application of World Bank Safeguard Policies
61. Out of the ten safeguard policies of the World Bank, six policies are triggered by this
Project: Environmental Assessment (OP/BP 4.01); Safety of Dams (OP/BP 4.37); Indigenous
Peoples (OP/BP 4.10); Involuntary Resettlement (OP/BP 4.12); Physical Cultural Resources
(OP/BP 4.11); and Projects on International Waterways (OP/BP 7.50). Key objectives of the
policies are briefly summarized in Table 3.1 below. In addition, the World Bank Group’s
Environment Health and Safety Guidelines will also be referred to.
Table 3.1: Relevant WB’s Safeguard Policies
Policy Objective
OP 4.01
Environmental
Assessment
To ensure the environmental and social soundness and sustainability of
investment projects.
To provide decision makers with information on potential
environmental and social impacts related to the project.
To enhance the transparency and participation of affected communities
into the decision making process.
OP/BP 4.11
Physical
Cultural
Resources
The policy aims to avoid, or mitigate, adverse impacts on cultural
resources which are important as sources of valuable historical and
scientific information, as assets for economic and social development,
and as integral parts of a people's cultural identity and practices,
including graves and graveyards. The policy provide guideline to ensure
that (a) Physical cultural resources are identified and protected in the
project and (b) National legislations on Physical Cultural Resources
Protection are fully complied with.
OP 4.10
Indigenous
Peoples
To ensure that ethnic peoples: (a) Receive full respect for their dignity,
human rights, and cultural uniqueness; (b) Do not suffer adverse
effects during the development process; (c) Receive culturally
compatible social and economic benefits; and (d) Benefit from
consultation and participatory processes.
OP 4.12
Involuntary
Resettlement
To ensure that the following policies will be applied: (a) Avoid or
minimize involuntary resettlement and impacts on economic activities,
including loss of livelihoods; (b) Provide transparent compensation
procedures during involuntary taking of land and other assets; (c)
Provide sufficient investment resources to enable the persons displaced
by the project to share in project benefits (implemented through the
Environmental and Social Management Framework (ESMF) Viet Nam Managing Natural Hazards Project (Vn-Haz/WB5)
18
62. Other policies such as Natural Habitats (OP 4.04), Forests (OP 4.36), Pest
Management (OP 4.09), and Projects in Disputed Areas (7.60) are not triggered since all the
subprojects: i) are not located in the critical natural habitats and/or would not degrade any
natural habitats or affect ecological health and quality of forests and/or the people who are
depending on them; ii) would not involve procurement of pesticides, pesticide application
equipment, and would not affect pest management; and iii) are not situated in any disputed
area with any neighboring countries.
63. To comply with these policies, the following safeguard documents have been prepared
for the Project:
(a) An Environmental Assessment (EA) assessing the overall impacts of the project as a
whole, including the first year subprojects, and possible follow-on year subprojects. A
social assessment was also carried out for the Project.
(b) An Environmental and Social Safeguard Framework (ESMF), including a standard
Environmental Code of Practices (ECOP) for civil works to be carried out under
Component 4 and actions related to dam safety and subprojects related to dredging and
upgrading of fishing boat harbors, and a simple ECOP to be applied to the activities to
be implemented under Components 1, 2, 3 that are related to small civil works.
(c) A Dam Safety Framework (DSF), outlining the policy requirements for ensuring
safety of dams to be rehabilitated and/or upgrading including a technical guideline for
preparation of Dam Safety Report (DSR) and a sample table of content. The DSF will
be applied to all the subproject involving dams.
(d) An Ethnic Minority Policy Framework (EMPF); and
(e) A Resettlement Policy Framework (RPF).
64. In addition, preparation of the following subproject specific documents will be
required: Environmental Management Plan (EMPs); Resettlement Action Plan (RAPs); and
Ethnic Minority Development Plan (EMDPs). EMPs, RAPs, and EMDPs for the six first year
subprojects have been prepared.
Resettlement Action Plan); (d) Restore and improve the standards of
living of persons affected by the project; and (e) Provide prompt and
effective compensation at full replacement cost for losses of assets
attributable directly to the project. Development of Resettlement Plan
and mitigation measures must be carried out based on consultation with
affected populations and participatory approaches.
OP 4.37
Safety of
Dams
To ensure that dam safety issues are adequately addressed, especially
for high and/or risky dams; The policy applied to new dams, existing
dams, and/or dams under construction that are related to infrastructure
to be financed by WB.
OP 7.50
Projects on
International
Waterways
To ensure that the projects neither affect the effective use and protection
of international waterways, nor the relationship between the Bank and
the borrower and between nations sharing the same waterway.
Environmental and Social Management Framework (ESMF) Viet Nam Managing Natural Hazards Project (Vn-Haz/WB5)
19
65. Public consultation: During the preparation of the EA, ESMF, DSF, and EMPs for
the first year subprojects, two public consultations were conducted: one in June-July 2011 and
the other in September 2011. Participants included farmer and fisherman households directly
or indirectly affected by the projects, local authorities, central and local state agencies, and
mass organizations, etc. Opinions and concerns provided during the consultation were taken
into account in the preparation of the EA, ESMF, DSF, and EMPs. Most of the provinces and
communities in the Project area showed enthusiasm in supporting the implementation of the
Project and wished that the Project would be carried out as soon as possible.
Environmental and Social Management Framework (ESMF) Viet Nam Managing Natural Hazards Project (Vn-Haz/WB5)
20
Section IV: Summary of Impacts and Mitigation Measures
66. Overview. The EA conducted for the Project concluded that the overall impacts of
the Project will be positive since an improved infrastructure under Component 4 will
increase effectiveness of local infrastructure capacity to prevent and/or rescue impacts due
to natural hazard, and thus create positive impacts at provincial and river basin levels. The
potential negative impacts will be limited to the subproject sites, temporary, and can be
mitigated. Implementation of Component 3 will increase capacity of local government and
communities to address natural disaster issues while activities under Component 1 will
strengthen policy, planning and coordination capacity at central and river basin level.
Details are highlighted below.
4.1. Potential Positive Impacts
67. General benefits: The Project would have potential positive impacts in strengthening
national, provincial, and local capacities for natural disaster prevention, preparedness, and
mitigation. The Project is fully in line with the target of the National Strategy for Natural
Disaster Prevention, Response and Mitigation to 2020, the National Strategy on Environment
Protection to 2010 and Direction to 2020, and regional master planning. Key benefits include:
Reduction of human losses and property damage: According to the RPF report, the
Project will protect approximately 900,000 people (more than 210,000 households) from
annual floods and droughts, including people of 5 ethnic groups: Muong, Thai, Co Tu,
H’re and Cham. The Project would also help maintain the trust of people in the
Communist Party and the Government, making them feel secured to focus on production
and settling down their lives.
Facilitation for socio-economic development: According to the social assessment report,
the Project would protect approximately 50,000 ha of production lands from floods and
droughts each year. As the result, it would increase agricultural productivity, increase
incomes and livelihoods opportunities, and people’s lives in the areas affected by natural
disasters to recover faster. Moreover, the subprojects would enhance trading activities
between communes, districts and provinces, possibly create more jobs for local residents,
and help to develop the local infrastructure and a better investment environment to attract
investors. The socio-economic development, in turn, would increase the human capacity
and material resources for natural disaster response and post-disaster recovery of the
communities.
Raising community awareness and natural disaster risk management capacity of different
levels: Through the Project activities, local people would increase their awareness in
natural disaster risks as well as community-based DRM capacity. Raising the community
awareness on natural disaster prevention and response would help the residents and the
communities change their attitudes and behaviours in their response to climate change,
especially towards the environment, including: use and protection of forest resources
(watershed and protective forests), water resources, dikes, and dams; proactive response to
natural disasters, mobilization of internal resources to rescue and support each other in
disaster events and post-disaster reconstruction.
Improvement in quality of living environment: The rivers in the Central region are narrow
and steep. This characteristic forms a relatively high river flow in the flood season, which
results in river bank erosion happening more frequently. The river bank erosion process is
the result of increased content of suspended solids in the river water and it can largely
Environmental and Social Management Framework (ESMF) Viet Nam Managing Natural Hazards Project (Vn-Haz/WB5)
21
affect domestic water quality of the riverside residents. The subproject group of upgrading
river revetments would reduce the river bank erosion process, which will help improve the
river water quality, especially in terms of suspended solids parameter. Besides, the Project
activities would reduce the inundation currently occurring every year in the Central
provinces or damage caused to fishing boats at river mouth areas. Preventing natural
disaster would be an effective way in reducing the environmental degradation happening
after storms and floods, and increasing the local residents’ habitat quality because after
flood events. It would help improve domestic water supply sources during and after
floods, reduce diseases (such as red eye sores, skin diseases, diarrhea, etc.), and limit
environmental landscape degradation (with wastes, mud, dead animals and plants,
offensive smell, etc.).
4.2. Potential Negative Impacts and Mitigation Measures
68. In the river basins of the Project area there are 8 physical cultural sites and 10 nature
reserves, protected areas, or protection forests. However, all of the subprojects are not located
within or nearby those sites. It is thus concluded that the Project would not cause any impacts
on the physical cultural resources and natural habitats and/or forests. There will be no
construction of new dam, major sea dykes nor major sea sluices and/or big-scale bridges
which may pose major environmental concerns beyond B environmental category as defined
by WB safeguard policy. These conditions will be explicitly defined during the eligible
screening of safeguard (Section 5.2).
4.2.1 Impacts of Component 4 Subprojects
69. Key potential negative impacts of the Project (both social and environmental) will be
due to the implementation of Component 4 subproject, especially those related to: (i) Land
acquisition and resettlement of local people including ethnic people and (ii) Site clearance and
construction which could temporary increase levels of dust and other air pollution, noise,
vibration, water pollution, local traffic volume, safety risk, and other impacts on local
residents and businesses. The impacts however will be small to moderate, localized, and
temporary, and can be mitigated. There are UXO risks during construction and other risks
during operation if the infrastructures are not properly designed and/or maintained adequately
and/or sluices are not properly operated. These risks however are considered moderate and
could be mitigated.
70. Below briefly describes the key negative impacts and need for mitigation measures.
(a) Impacts due to land acquisition, relocation, and ethnic groups
Land acquisition and relocation. Land acquisitions will be required mostly for upgrading
of existing dykes, dams, roads, overflow bridges, fishing boat shelters, sluices, and
construction of small rescue roads. The impacts are considered significant and efforts will
have to be made to avoid/reduce the need for land acquisition and/or relations, and if
unavoidable, the affected people will be adequately compensated in line with the Bank
safeguard policy. A RPF has been developed in close consultation with local agencies and
affected people, and specific policy and procedures has been finalized, including those
related to grave relocation. RAPs for the first year subprojects have also be prepared,
including compensation and grave relocation. Table 4.1 summarizes the level of impacts
due to the first year subprojects.
Environmental and Social Management Framework (ESMF) Viet Nam Managing Natural Hazards Project (Vn-Haz/WB5)
22
Relocation of graves. During the preparation of the six subprojects, twenty two graves
were identified affected. Relocation of graves would be carried out by households whose
graves are affected (as a practice in Vietnam). Rituals for relocation of graves may be
different among Kinh, and ethnic minority peoples. Affected households will receive
compensation payment to conduct the relocation on their own. Payment to the grave
relocation includes costs of excavation, relocation, reburial, purchasing land for reburial
(if any), and all other reasonable costs associated with necessary rituals by the local
practice. Local ritual means relocation of graves will be carried out in accordance with
local cultural practices, taking into account cultural preferences which are typical for each
ethnic group. When graves of ethnic minorities are affected, grave relocation rituals
adopted will be documented in respective Ethic Minority Development Plan (EMDPs)
based on the consultation with affected ethnic minority peoples during project
implementation. Where graveyard - owned collectively by ethnic groups, are affected,
appropriate consultation with affected groups will be conducted during social assessment
under respective subproject to work out solutions acceptable to affected ethnic minorities.
Relocation of graves will be done satisfactorily to the affected households prior to the
commencement of construction.
Ethnic Minorities. The Project will involve ethnic minority and an EMPF has been
prepared in line with the WB policy. EMDPs for the first year subprojects have been
prepared.
Table 4.1: Impacts due to land acquisition and relocations of first year Component 4
subprojects
Total
affected
HH
Permanent
land (m2)
Temporary
land (m2)
Remarks No. of
grave
relocation
I. Thanh Hoa 1. Maintain, upgrade and treat the
key parts of the left dyke of Cau
Chay river (section from K0-K42),
Yen Dinh district
781 147,337 537,673
42,000 m
dyke; 11
communes
in 1 district
3
II. Nghe An 2. Bridge combining with overflow
connecting Rescue roads, Nghi Loc
and Vinh city 5 0 200
1,020 m; 2
commune,
2 districts 0
3. Upgrade dyke site of Luong Yen
Khai 83 13,300 0
2,870 m
dyke; 2
communes,
1 district
0
III. Ha Tinh
4. Upgrade dyke site Phuc Long
Nhuong, Cam Xuyen district 335 91,402 0
11,000 m;
4
communes,
1 district
1
IV. Quang Nam
5. Repair, upgrade Thach Ban
reservoir, Duy Xuyen district 7 0 20,000
1
communes,
1 district 0
V. Binh Dinh
6. Upgrade anti-erosion 73 9,156 1,037 5,700 m; 4 18
Environmental and Social Management Framework (ESMF) Viet Nam Managing Natural Hazards Project (Vn-Haz/WB5)
23
embankment of Kone river for
safety, An Nhon and Tuy Phuoc
districts
communes,
2 districts
Total 1,284 261,195 558,910 22
(b) UXO risk.
71. Safety risk related to UXO is considered moderate since most of the subprojects will
involve existing infrastructure with very limited number of new construction (some small
rescue roads). However, UXO risk assessment will be conducted for all the subproject sites
and UXO clearance (if needed) will be carried out by qualified agencies. Construction
activities will not be allowed prior to UXO clearance.
(a) Impacts during site clearance and construction stage
72. The EA assessed the impact according to type of civil works as follows:
rehabilitation/upgrading of existing dykes, embankments, and overflow bridges,
upgrading/construction of rescue roads, rehabilitation/upgrading of existing dams/reservoir,
and dredging and/or construction of river mouth infrastructure (i.e. rehabilitation of fishing
boat harbors and/or river mouth erosion protection). The assessment concluded that the
potential negative impacts of these activities will be moderate, localized, temporary, and can
be mitigated through the application of good construction and management practices and with
close supervision of contractor performance by field engineers and in close consultation with
local communities. The impacts of the first year subprojects will be limited to an increase in
dust, noise, vibration, waste generation, traffic hindrance, public safety, and exploitation of
construction materials (soil, gravel, rocks, etc.). Increased turbidity resulting from dredging at
the river mouth and rehabilitation of fishing boat harbor, which has been proposed for the
follow-on years, however may create negative impacts on nearby water uses along the coast
(such as recreation and coastal aquaculture), but these impacts are most likely to be localized
and temporary and close monitoring and immediate suspension of the construction works in
case of the abnormality would be adequate. These issues will be addressed during the
preparation of the EIA and EMPs for these subprojects.
73. For the subprojects involve river mouth dredging and construction of coastal
infrastructure that could change flow of the near shore current and/or sediment transport, a
quick study will be made during the preparation of the EIA/EMP of the subprojects to assess
the risks of coastal erosion in nearby area. Consultation and active participation of local
communities will be the key elements during the development of the mitigation measures. For
dredging, preparation of a Dredge Material Disposal Plan (DMDP) should be considered. The
DMDP will provide information on amount and characteristic of dredge materials especially
those related to organic content and heavy metals as well as the dredging methods,
transportation, and disposal areas such that it will minimize potential impacts on the nearby
land/water uses along the coast.
74. The contractor will be responsible for mitigating these impacts. Damage will be
repaired, fixed, and/or paid for as appropriate by the contractors. After completion of
construction, the contractor will be required to complete or rehabilitate the construction site to
bring it back to the prior construction situation. These requirements will be included as part of
Environmental and Social Management Framework (ESMF) Viet Nam Managing Natural Hazards Project (Vn-Haz/WB5)
24
the construction contract with appropriate mitigation cost and they will be specified in the
bidding documents and be informed during the bidding process.
75. In this context, a standard Environmental Code of Practices (ECOP) has been prepared
describing specific requirements to be carried out by contractor and scope of the ECOP is
provided in Annex 2 and briefly described in Section V. Monitoring of environmental quality
during construction can be useful in ensuring adequacy of the mitigation measures being
implemented by contractor. However, the monitoring parameters, locations, and timing
should be designed in line with the subproject activities, locations, and nearby water uses.
The EMP will clearly define the need for environmental quality monitoring with specific
locations, monitoring parameters, frequency, and an estimated cost.
(e) Impacts during operation phase
76. The potential negative impact during operation of Component 4 subprojects would be
limited to the potential risks related to: (a) failure of dams, dyke, and/or rescue roads and
potential land/water use conflicts during sluice operation and local floods and (b) possible
impacts on coastal erosion in nearby area due to construction of new structure that could change
flow pattern of nearshore current and/or sediment transport. Mitgation measures will be
necessary and actions below will be undertaken during the preparation of the EIA and EMP.
4.2.2 Impacts of Other Project Activities
77. The potential negative impacts of other Project activities will be limited to small
works/infrastructure such as renovation/construction of office/building, community shelters,
elevated road path, small bridges and/or two-story concrete school building for evacuation
purpose during emergency cases. These impacts can be mitigated through the participatory
planning process and/or the application of good construction practices (see Section VI).
4.3 Potential Cumulative Impacts and Enhancement Opportunities
78. In general, the EA found no major cumulative negative impacts resulting from the
Project, as the proposed investments are limited to rehabilitation and upgrading of existing
dams, dykes, reservoirs, and roads, etc. and therefore does not create any cumulative impacts
Environmental and Social Management Framework (ESMF) Viet Nam Managing Natural Hazards Project (Vn-Haz/WB5)
25
on local environment and/or local people. In fact, the proposed investment in repair and
upgrading of dams, dykes, reservoirs, and rescue roads are critical for reducing damage due to
natural hazards. Supporting local community through the community-based program
(Component 3) will increase awareness and capacity of local communities to be responsive to
the natural hazards, and thus considered as a means to mitigate the potential risks due to
operation failure of dams, dykes, reservoirs, and rescue roads to be implemented under the
Component 4 subprojects. During the preparation of an EIA/EMP for the subprojects, local
communities with risks will be identified and assistance on capacity building will be provided
following the CBDRM principle and a separate budget has been provided as part of the bloc
grant to be implemented under Component 3.
Section V. ESMF Process for the Subprojects
5.1. Objective and Approach
79. The ESMF will be applied only to the Component 4 subprojects. The main objective
of the ESMF is to ensure that the subprojects and activities to be finance under the Project
would not create adverse impacts on the local environment and local communities and the
residual and/or unavoidable impacts will be adequately mitigated in line with the WB’s
safeguard policy. Based on the potential negative impacts and mitigation measures described
in Section IV, the ESMF process for Component 4 subprojects has been designed to comprise
5 key steps: (1) Eligibility screening, (2) Technical screening and identification of key
impacts and documentation, (3) Development of mitigation measures and public consultation,
(4) Information disclosure and WB safeguard clearance, and (5) Implementation, monitoring,
and reporting. The first year Component 4 subprojects have gone through the first three steps
and specific mitigation plans (RAPs, EMDPs, and EMPs//DSRs) have been prepared and
these documents will be submitted to WB for public disclosure and clearance. The safeguard
screening, impact assessment, and preparation of safeguard documents for all the second and
follow-on year subprojects will be carried out during the Project implementation and the
safeguard documents (RAPs, EMDPs, and EMPs, including dam safety report as needed) will
be submitted for WB clearance before their approval and implementation.
80. Figure 5.1 and Table 5.1 identifies criteria and actions to be undertaken during the
ESMF process and they are briefly discussed in Section 5.2 below.
5.2. Safeguard Screening and Impact Assessment (Step 1and2)
(a) Eligibility screening (Step 1)
81. To avoid adverse social and environmental impacts which cannot be adequately
mitigated by the Project, an initial screening would be carried out to identify subprojects
which may cause serious impacts which would not be easily mitigated with the project’s
current set of safeguard instruments, and therefore not eligible for the Project financing.
There will be no construction of new dams, new major sea dykes/sluices, and/or big-scale
bridges which may pose major or significant irreversible environmental impacts that would be
equivalent to a Category A as described in World Bank safeguard guidelines. The subprojects
that can create significant loss or damage to physical cultural resources, including sites having
archeological (prehistoric), paleontological, historical, religious, cultural and/or unique
natural values will not be eligible for Project.
Environmental and Social Management Framework (ESMF) Viet Nam Managing Natural Hazards Project (Vn-Haz/WB5)
26
82. To avoid potential adverse potential socio-environmental impacts on areas of critical
importance such as national parks, biological conservation areas, protected forests or areas of
historical values, subprojects under the Vn-Haz will be screened for their environmental
eligibility. The subprojects that potentially adversely affect areas of biological importance,
conversion of site with valuable landscape, removal of objects with historical/religious
appreciation, or encroachment on mangrove forest regardless of the size will be excluded
from the Project financing.
83. The criteria for exclusion of subprojects have been developed with reference to Annex
III of Decree No.29/2011/ND-CP (listing the projects subject to appraisal by MONRE) as
detailed below:
i) Subprojects that use land of national parks, natural reserves, world heritage,
historical/cultural sites, nationally protected landscapes, biosphere conservation
sites;
ii) Subprojects that cause conversion of natural forests including mangrove forests,
watershed protection forests, waves/wind shield forests, etc;
iii) Subprojects that cause sea encroachment of 20 ha or more;
iv) Subprojects that cause conversion of two-crop rice field land of 20 ha or more
with high productivity;
v) Subprojects having project sites in more than one province.
vi) If access/rescue roads are needed, the alignment for each of these roads must be
determined to avoid critical habitats and such as national parks, natural reserves,
world heritage, historical/cultural sites, nationally protected landscapes,
biosphere conservation sites.
84. During the eligibility screening, careful selection of the possible subprojects should be
made considering the above-mentioned criteria. Once the subprojects are selected, the
applicable Bank safeguard policies should be determined for each subproject identified.
(b) Technical screening and assessment of potential impacts (Step 2)
85. For activities which are eligible for the Project financing, a technical screening will be
carried out to identify key potential impacts of the subproject. Table 5.1 identifies criteria for
safeguard actions and documents necessary for WB clearance and they can be briefly
summarized below:
Social impacts screening and assessment. The subproject will be screened for the nature
and extent of potential negative impacts on local people related to land acquisition,
resettlement, land donation, relocation of graves, and/or involvement with ethnic minority.
If the impacts exist, RAPs and/or EMDPs will be prepared in line with the Resettlement
Policy Framework (RPF) and/or the Ethnic Minority Policy Framework (EMPF) which
has been developed for the Project. During the preparation of RAPs and EMDPs,
consultation with affected population, local authorities, local communities, and interested
mass organizations and/or NGOs will be required. Due attention should also be given to
address the issues related to gender, ethnic minority, and other disadvantage groups,
especially when they are likely to be affected by the natural disaster. Relation of graves
will be in line with the WB policy on PCR. Relocation of graves will be carried out based
on the principle of replacement cost and in accordance with local cultural practices, taking
into account cultural preferences which are typical for each ethnic group as set out in the
RAPs and EMDPs. WB approval of the RAPs and EMDPs will be mandatory.
Environmental and Social Management Framework (ESMF) Viet Nam Managing Natural Hazards Project (Vn-Haz/WB5)
27
Environmental impacts screening and assessment. Key potential negative impacts on local
environment and local community will mainly occur during construction and operation
phases. Scope and extent of the impacts during construction, however would depend on
type and nature of civil works and locations of the subprojects. The subproject will
therefore be screened for the extent of the potential impacts on air/noise/vibration;
land/soil/water; solid wastes; natural habitats/fisheries/aquatic life; livelihoods and local
resident disturbance; and other aspects such as local floods, public safety/UXO risks, off-
site impacts, etc. The level of impacts to be assigned should be as follows: None (N) – no
impact; Low (L) – Small works, minor impacts, localized, reversible, temporary; Medium
(M) – Small works in coastal/sensitive areas, medium scale works with moderate impacts
of which most are reversible, reducible and manageable, localized, temporary; High (H) –
Medium scale works in coastal/sensitive area, large scale works with significant impacts
(socially and/or environmentally) of which some are irreversible and require
compensation. Both M and H impacts need development and implementation of
mitigation measures, monitoring program, and adequate institutional capacity on
safeguard and this will be used as the basis for development of an EIA/EMP for the
subproject. Data collection, field survey, and consultation with local communities and
affected population will be carried out. Technical guidelines for the preparation of an
EMP are provided in Section 5.3 below. If an EIA or EPC for the subproject is required by
the Government’s EIA regulations, appropriate actions and documents will be prepared
accordingly.
5.3. Development of Mitigation Measures and Public Consultation (Step 3)
5.3.1 Preparation of an EMP and public consultation
86. Environmental Management Plan (EMP). Appropriate mitigation measures should be
identified according to the nature and extent of the potential negative impacts. Given that
guidelines for preparation of RAP, EMDP, and DSR will be prepared separately; this section
focuses on the preparation of an EMP describing the basic principles and activities to be
carried out to mitigate the potential negative impacts. The EMP will briefly describe the
subproject description; environmental and social background of the subproject area, including
a good map showing locations of the subproject and site specific activities and/or process as
appropriate; the potential impacts and proposed mitigation measures; and the implementation
and monitoring arrangement and budget. Public consultation is to be carried out as part of the
EMP preparation. For each subproject, the EMP will clearly define actions to assess and
mitigate UXO risks as well as to mitigate potential impacts during site clearance and
construction and to reduce the risks during operation. At a minimum the EMP will include the
standard ECOP and actions identified in Section 4.2, including environmental monitoring
program. Annex 3 provides a sample content of the EMP as well as technical guidelines for
EMP preparation, consultation and information disclosure, preparation of DMDP, and a quick
assessment of potential impacts on coastal erosion.
87. To ensure effective implementation of the EMP, the following actions will be carried
out during the implementation of the Project:
(a) During feasibility study and conceptual design
Environmental and Social Management Framework (ESMF) Viet Nam Managing Natural Hazards Project (Vn-Haz/WB5)
28
To mitigate the potential risks during operation that are related to: (a) failure of dams,
dykes, and/or rescue roads and potential land/water use conflicts during sluice
operation and local floods and (b) possible impacts on coastal erosion in nearby area
as identified in Section 4.2, the following principles will be considered and applied
during the preparation of the EMP:
– For the subproject involving dam rehabilitation and/or upgrading, the DSF will be
strictly followed. For large and high hazard dams (see definition in DSF),
submission of a Dam Safety Report (DSR) to the WB will be required. A capacity
building building program on large and high hazard dam should be described in
the DSR. Scope of the DSR is provided in DSF. The safeguard screening excludes
the financing of a new dam.
– For the subproject involving dyke safety and operation of sluices, the potential
impacts due to dyke safety and operation of sluices will be mitigated by providing
training and capacity building following the CBDRM approach and a budget has
been provided as part of the EMP.
– For the subprojects involving river mouth dredging and construction of river
mouth infrastructure that could change flow of the near shore current and/or
sediment transport, a quick study will be made to assess the risks of coastal erosion
in nearby area. Consultation and active participation of local communities will be
the key elements during the development of the mitigation measures. For dredging,
preparation of a Dredge Material Disposal Plan (DMDP) should be considered.
The DMDP will provide information on amount and characteristics of dredge
materials especially those related to organic content and heavy metals as well as
the dredging methods, transportation, and disposal areas such that it will minimize
potential impacts on the nearby land/water uses along the coast.
(b) During detailed design and preparation of bidding and contract documents
To mitigate the impacts during site clearance and construction, the following activities
will be carried out by PPMU:
– Include specific mitigation measures described in the EMP into the detailed design
as appropriate. For dredging, preparation of a DMDP may be necessary. For large
and high hazard dams a dam safety report will be submitted to WB.
– In preparing the bidding and contract documents, include the standard ECOPs
(Annex 2) in the bidding and contract documents and make an effort to ensure that
the contractors are aware of the safeguard obligation and commit to comply. The
ECOP comprises five sections: (I) objective and application, (II) brief description
of policies and regulations, (III) roles and responsibilities of key parties (project
owner and contractor), (IV) general provisions, and (V) construction management.
The general provisions section prescribes the need for preparation of a Contract
Specific Environmental Management Plan (CSEP), the non-compliance reporting
procedures, the liaising with authorities and the public, the community relations,
the mitigation objectives and special considerations, the implementation of
“Chance Find” procedures, and prohibitions while the construction management
section prescribes the general management of construction sites, the management
Environmental and Social Management Framework (ESMF) Viet Nam Managing Natural Hazards Project (Vn-Haz/WB5)
29
of environmental quality from sources (i.e. control of water pollution, air pollution,
waste generation, traffic and transportation, etc.), and the management of work
camps, quarries/borrow pits, dredging, and monitoring of environmental quality.
The contractor will be required to prepare the CSEP which is to be approved by
the Construction Supervising Consultant (CSC) before starting construction. The
CSEP will also include a monitoring plan for air, noise/vibration, soil
erosion/sedimentation, and water quality during construction. Cost for mitigating
the impacts during construction must be included as part of the Project cost. The
supervision and/or field engineers will be responsible for supervision and
monitoring of safeguard performance of contractor and this responsibility will be
included in the TOR for field engineers.
– Ensure that all safeguard activities and documentation have been completed and
disclosed.
– Secure Government approval of the EIA/EPC for the subprojects as required by
the Government regulations. The subproject EMPs should be submitted to the
relevant authority for review and comment.
– Relocation of graves will be done satisfactorily to the affected households prior to
the commencement of construction in accordance with the related RAPs and
EMDPs.
(c) During Construction stage
PPMU will assign the Construction Supervising Consultant (CSC) and/or field engineer to
be responsible for supervision of safeguard performance of contractor on a daily basis.
CSC and/or field engineers will carry out, but not limited to, the following tasks:
– Before the launch of the construction, confirm that (a) all compensation for land
and facilities are provided and relocation and/or land acquisition/donation has been
completed; (b) the subproject EIA and/or mitigation measures for specific site are
approved by Government; and (c) the above-mentioned environmental plan have
been approved by concerned parties.
– During construction, closely supervise the implementation of safeguard measures
throughout the construction period.
– At the completion of the construction, confirm the compliance with the agreed
environmental plan and inspect any damages incurred by the contractor. If
necessary, prepare an order to compensate/restore the construction sites as
specified in the contracts. Contractor safeguard performance will be included in
the subproject progress report.
The contractor will recruit a group of national consultants (the Environmental Contractor)
to assist in the planning and implementation of safeguard measures to be carried out by
the contractor, including preparation of the Contract Specific Environmental Plan (CSEP)
and communication with local authorities and local communities. In particular, the
Environmental Contractor will carry out but not limited to the following tasks:
Environmental and Social Management Framework (ESMF) Viet Nam Managing Natural Hazards Project (Vn-Haz/WB5)
30
– Prepare a CSEP in compliance with the ECOP before launch of the construction
given due attention to reduce potential negative impacts on safety of resident and
general public, dust/noise suppression, waste management, and traffic congestion.
Efforts should be made to identify sensitive areas that may be affected by and/or
issues that may arise from the construction activities due to large number of local
population and/or important use of land and water.
– During construction stage, monitor the compliance with the agreed environmental
plan, and maintain close consultation with the community residents, and
information disclosure and timely responsive to any possible complaints from
residents and general public throughout the construction duration.
– At the completion of the construction, confirm the compliance with the agreed
environmental plan and inspect any damages incurred to be paid by the contractor,
including preparation of an order to compensate/restore the construction sites as
specified in the contracts.
– Prepare a periodical report to the contractor and the subproject owners as agreed in
the CSEP.
– Assist the CPMO/ESU/CEMC in conducting periodic monitoring of safeguard
performance of construction contractors.
5.3.2 Preparation of an environmental monitoring program
88. Water quality monitoring: Water quality monitoring is considered an important
mitigation measure for the Component 4 subproject. However, the monitoring plan (locations,
parameters, and frequency) should be strategically considered to ensure cost effectiveness of
the measures. Basic water quality monitoring should be designed to protect water users as
well as to facilitate effective operation of water resources management. Water quality
monitoring during construction is the responsibility of the contractor. The contractor’s
environmental consultant will monitor the water quality (including sampling and analysis) in
construction areas and report to the Provincial Project Management Unit (PPMU). It is
anticipated that the water quality parameters to be monitored by the contractor at a minimum
will include pH, total suspended solids (TSS), dissolved oxygen (DO), and coliform bacteria
while selective analysis of heavy metals should be made as required by DMDP. The PPMU’s
PEMC to review the contractor’s water quality monitoring data, and if necessary, collect
independently its own water quality data. The contractor will be required to take actions to
avoid and/or mitigate impacts on water users during dredging and rehabilitation of bridges
and this requirement has been included in the standard ECOP. It is anticipated that the
subprojects related to dredging and upgrading of fishing boat harbors will require a more
comprehensive monitoring of water quality during construction as well as operation stage.
89. The same monitoring approach can be applied to all monitoring parameters if the
impacts on local residents and/or water users are likely to be significant and/or there are
complaints (such as when/where the works is carried out in urban area or near sensitive spot
and/or might adversely impacts other water user. Monitoring during operation is not
anticipated.
Environmental and Social Management Framework (ESMF) Viet Nam Managing Natural Hazards Project (Vn-Haz/WB5)
31
5.4. Information Disclosure and WB Safeguard Clearance (Step 4)
90. Before commencement of implementation of a subproject, the subproject EMP will
be submitted to the WB for disclosure in the Bank InfoShop and WB safeguard clearance.
Public disclosure of the EMP in the country and the project areas will also be required.
91. Government’s approval. If the subproject requires Government approval according to
the EIA and/or other regulations, the subproject owner will prepare and submit the report as
required by the Government and secure their approvals and clearances. An English summary
of the EIA as well as the approval conditions will be provided to the Bank for information.
The EIA report and approval condition will also be disclosed to the public.
5.5. Implementation, Supervision, Monitoring, and Reporting (Step 5)
92. Subproject level: During Project implementation, the subproject owner (PPMUs)
responsible for each subproject will be responsible for ensuring effective implementation of
safeguard measures (RAPs, EMDPs, EMPs/ECOP, DSRs, water quality monitoring etc.) in
close consultation with local authorities and local communities. PPMU will assign at least one
full time staff (as the safeguard focal point) to be responsible for forging effective
implementation of RAP, EMDP, EMP/DSR of the subproject. During construction, PPMU
will assign the Construction Supervising Consultant (CSC) and/or field engineer to be
responsibility for monitoring and supervision of contractor performance on a daily basis. The
results will be part of the subproject progress report and the safeguard focal point will be
responsible for ensuring proper documentation of safeguard activities. PPMU will also be
assisted by qualified Provincial Environmental Management Consultants (PEMC) and the
environmental staff in the implementation of the EMP, including training of field engineers
and supervision of contractor environmental performance.
93. Project level: The Central Project Management Office (CPMO) who has been
assigned to take the lead in overseeing and monitoring of the implementation of subproject
will periodically supervise and monitor the safeguard implementation performance and
include the progress/results in the Project progress report. CPMO will set up an
Environmental and Social Unit (ESU) responsible for forging effective and timely
implementation of safeguard activities and assign one senior staff and at least one full time
safeguard staff to be responsible for managing and monitoring of the environmental and social
impacts of the subproject throughout the Project period. Main responsibility of the ESU will
include, but not limited to, (a) forging compliance, including supervision and monitoring, of
all environment and social aspects; (b) representing the subproject owner for all matters
related to the project safeguards; and (c) be responsible for overall coordination of the
subproject EMP implementation. Information regarding the safeguard measures and
performance should be periodically disclosed to the public. A Cental Environmental
Management Consultant (CEMC) will be hired to assist ESU in performing it tasks.
94. The WB will conduct regular safeguard supervision, monitoring, and post review both
at the subproject and Project levels.
Environmental and Social Management Framework (ESMF) Viet Nam Managing Natural Hazards Project (Vn-Haz/WB5)
32
Figure 5.1 – Schematic Flowchart for Safeguard Actions for Components 3 and 4 Subprojects
CPMO conduct initial screening to determine the environmental category
of subprojects (Step 1)
Involve civil works that could
generate potential negative impacts
under Component 4: PPMU
prepare EIA/EPC as required by
GoV regulations. If the subproject
involves dam, DSF will be
followed (Step 3)
Pass: CPMO identifies potential negative impacts (environment
and social), mitigation measures and/or next actions–using the
checklist forms, discuss the results with local government and/or
communities –Apply criteria described in Table 5.1 (Step 2)
CPMO monitor/report safeguard implementation/performance in the project
progress report; WB will periodically review and monitor the results/reports
(Step 5)
PPMUs prepare EMPs in line with
ESMF, including ECOP, dam
safety report (DSR) and/or water
quality monitoring as needed; the
EMPs will be submitted for WB
clearance. Public consultation will
be part of the EMP preparation. If
UXO risk exists, the EMP will also
include measures to mitigate the
risk.
(Step 4)
Small civil works
under Component
3 with small
impacts and no
EIA/EPC is
required (Step 3)
Fail:
The Project will
not fund the
proposed
activities
Involve
ethnic
peoples:
PPMU
prepare
EMDP (Step
3)
Involve land
acquisition,
relocation, and/or
compensation:
PPMU prepare RAP
(Step 3)
PPMUs use the
ECOP for small
civil work in the
ESMF and include
them in the bidding
and contract
documents (Step 4)
PPMUs prepare
RAP in line with
RPF, including
consultation with
affected population.
Compensation must
be paid before the
civil works could
begin (Step 4)
PPMUs
prepare an
EMDP in
line with the
EMPF
(Step 4)
PPMUs, assisted by Construction Supervising Consultant (CSC) and/or field engineer monitor and
supervise contractor performance and report the results periodically to CPMO; Information disclosure
should be conducted periodically (Step 5)
Table 5.1: Technical Guideline for Safeguard Screening and Actions for Component 4
Subprojects
Potential negative
impacts Required mitigation actions
(If Yes) Requir
ed
docum
ent
Remarks
(1) Permanent or
temporary loss of land or
resources for any
families,
Identify the amount and nature of land
required, owner, and/or other issues and
prepare a RAP to provide compensation
and/or assistance following the RPF.
RAP Prior consultation
with WB, proper
documentation, and
Post review by WB
may be necessary.
(2) Likely to involve
ethnic minorities and/or
adversely affect ethnic
groups
Carry out social assessment process through
free, prior, and informed consultations and
prepare an EMDP in accordance with
guidance in the EMPF. The project will
support increasing awareness of affected
population, in respective languages of ethnic
minority groups, about the Grievance
Redress mechanisms, and building capacity
of those involved in the existing Grievance
Redress mechanism on the required tasks,
including dealing with or mediating
complaints from individual and/or ethnic
groups, recording and reporting, and
monitoring proposed resolutions.
EMDP Prior consultation
with WB, proper
documentation, and
Post review by WB
may be necessary.
(3) Likely to have
artifacts or remains
found during excavation
works, and physical
relocation of graves.
Physical relocation of graves is likely. If this
is the case follows the procedure described in
the RPF;
A standard “Chance Find” Procedure
included in the ECOP will be incorporated in
the subproject EMP.
RAP
EMP
Preparation of
procedures to
address when local
grave is encountered
has been included in
the RPF.
Contractor will
apply the chance
finds procedure (4) Likely to involve
UXO risk? If identified at the feasibility stage, include
the clause in the EMP. The procedures would
include: contact responsible agencies and
complete the clearance before conducting
construction activities. The subproject will
be required to provide a UXO clearance
certificate before undertaking site clearance
and/or construction.
EMP PPMU will be
responsible for
contacting the
concerned agencies
and obtain clearance
to secure safety of
the project area
(5) Involve civil works
which can generate air,
noise, and/or water
pollution, soil erosion,
public health risks,
and/or impacts on
downstream and/or
nearby water uses during
site clearance and
construction.
Include the standard ECOP into bidding and
contract documents and ensure that
Construction Supervising Consultant (CSC)
and/or field engineer closely monitor
performance of contractor.
EMP PPMU will ensure
that the ECOP is
included in the
contract and the
CSC responsibility
to supervise the
contractors is
included in the
TOR.
Environmental and Social Management Framework (ESMF) Viet Nam Natural Hazards Management Project (Vn-Haz/WB5)
34
(6) Involve dredging
and/or possible
contamination of soil
and water quality from
the disposal of dredged
materials during
construction
Prepare a Dredge Materials Disposal Plan
(DMDP) during the preparation of the
EIA/EMP and/or detailed design.
Compliance with the DMDP has been
included in the standard ECOP.
EMP Technical guidelines
are provided in
Annex 3
(7) Involve risk related
to safety of dams
Apply DSF and include the mitigation
measures as part of the EMP: For a large and
high hazard dams prepare a dam safety report
(DSR) as described in the DSF.
Identify local community with high risk and
provide capacity building as part of the
Component 3 implementation.
EMP
/DSF PPMU/CPMO will
ensure that this is
the case
(8) Likely to cause
land/water use conflicts
due to dyke safety and/or
sluice operation
Identify areas/local community with high
risks and provide capacity building as part of
the Component 3 implementation.
EMP PPMU/CPMO will
ensure that this is
the case
(9) Likely to create
coastal erosion nearby
during operation.
Conduct a review for potential erosion in
nearby area and identify areas/local
community with high risks and provide
capacity building as part of the Component 3
implementation.
EMP PPMU/CPMOwill
ensure that this is
the case
Section VI. Mitigation Measures for Other Project Activities
95. As mentioned in Section IV that the potential negative impacts of these activities will
be limited to small civil works and the potential impacts can be mitigated through the
participatory planning process and/or the application of good construction practices. In this
context, a simple ECOP comprising Prohibitions; “Chance Find” procedures, and Good
Environmental and Housekeeping practices has also been developed (Annex 4) and it will be
applied to all the bidding and/or contract documents of all the activities to be implemented
under the Project, excluding those related to the subproject. Efforts will be made to integrate
the knowledge on environment and social safeguard into the planning process and capacity
building to be implemented under Components 1, 2, 3 as appropriate.
96. The agencies responsible for implementation of the activities (i.e. PPMUs of DARD
for Component1 and 3 and the Project Management Unit (PMU) of MONRE for Component
2) will (a) ensure that the simple ECOP is included in the bidding and contract documents
and it is effectively implemented by contractor, (b) integrate safeguard knowledge and
consideration into the planning and capacity building process, and (c) report the safeguard
performance in the component progress report.
Environmental and Social Management Framework (ESMF) Viet Nam Natural Hazards Management Project (Vn-Haz/WB5)
35
Section VII. Implementation Arrangement and Budget
7.1. Roles and Responsibilities
97. The implementation arrangement will follow the Project implementation arrangement.
Specifically for Component 4 subprojects, CPMO/CEMC, PPMUs/CSC, the Department of
Natural Resources and Environmental at provincial level (DoNRE), and the provincial
Peoples’ Committee (PPCs), and representative from mass organization and/or local
community are the key parties responsible for implementation of safeguard measures
including the ESMF and EMPs (see Table 7.1). The Contractors are responsible for
implementing mitigation measures and the mitigation costs will be part of the contract. The
CSC is responsible for assisting PPMU in supervision and monitoring the day-to-day
implementation of mitigation measures undertaken by the contractor while the CEMC is
responsible for assisting CPMO through it ESU in managing the safeguard implementation
including monitoring of EMP performance and environmental quality. For other activities the
agencies responsible for Components 1, 2, 3 will be responsible for implementation of the
safeguard measures described in Section VI.
Table 7.1: Institutional responsibilities for the Project and Subproject
Community/agencies Responsibilities
CPMO
- Periodically monitor performance of the subproject and include the
safeguard performance in the project progress report and be the overall
contact point with the World Bank.
- A Central Environmental Management Consultant (CEMC) at the central
level will be hired to assist ESU in performing it tasks
PPMU
- As the subproject owner, PPMU is responsible for implementation of the all
the EMP activities to be carried out under the Project, including fostering
effective coordination and cooperation between contractor, local authorities,
and local communities during construction phase. PPMU will be assisted by
a team of qualified consultants (CSC and PEMC), the environmental staff,
and/or field engineer.
Environmental staff
and Provincial
Environmental
Management
Consultant (PEMC)
- Assist PPMU in the implementation of the EMP, including training of field
engineers and supervision of contractor monitoring and water quality
monitoring.
CSC and/or Field
engineer
- Assist PPMU in the routine supervision of contractor performance in line
with the ECOP, including reporting and maintain close coordination with
local community.
Contractor
- Take actions to mitigate all potential negative impacts in line with the
objective described in the ECOP - Actively communicate with local residents and take actions to prevent
disturbance during construction. - Ensure that at least a staff is assigned to monitor EMP compliance during
the preconstruction and construction periods.
- Ensure all the construction activities having sufficient documents from the
Environmental and Social Management Framework (ESMF) Viet Nam Natural Hazards Management Project (Vn-Haz/WB5)
36
related organization.
- Ensure that all staff and workers understand the procedure and their tasks in
the environmental management program. - Report to the PPMU on any difficulties and their solutions
- Report to local authority and PPMU if environmental accidents occur and
coordinate with agencies and keys stakeholders to resolve these issues
Local community
Community: According to Vietnamese practice, the community has the right
and responsibility to routinely monitor environmental performance during
construction to ensure that their rights and safety are adequately protected
and that the mitigation measures are effectively implemented by contractors
and the PPMU. In case of unexpected problems, they will report to
CSC/PPMU.
Women Union and
other mass
organizations
- These organizations could play a role as a bridge between the PPC/DPC,
communities, contractors, and PPMU by assisting in community
monitoring, - Mobilizing communities participation in the subproject, providing training
to communities, and
- Participating in solving environmental problems if any.
Province and District People’s
Committees
(PPCs/DPCs)
- Oversee the implementation of the subproject under the recommendations of
the DONRE and the PPMU to ensure compliance of Government policy and
regulations
Provincial DONREs
- DONRE represents the MONRE for environmental management. It is
responsible for monitoring the compliance with the Government
environmental requirements.
7.2. Reporting Arrangement
98. The safeguard performance will be included in the subproject and Project progress
reports. PPMU with assistance from the CSC and PEMC will include safeguard
performance at subproject level to CPMO periodically. At the project level, CPMO assisted
by CEMC will prepare safeguard performance report twice per year for submission to the
World Bank describing the Project progress and compliance with the ESMF and other
safeguard requirements.
7.3. Safeguard Training and Capacity Building
99. Although most of the Project provinces have been involved in the implementation of
WB safeguard under the on-going WB funded projects, knowledge and expereince on WB
safeguard requirements as well as of environment and and social issues remain limited.
Given that most of the key mitgation measures are good engineering practices, the
safeguard training should focus on increasing knowledge on (a) safeguard policy and
procedures to implement the safeguard instruments (RAP/RPF, EMDP/EMPF, EMP/ESMF,
DSR/DSF) designed for the Project and subproject (b) specific training on supervision and
monitoring of contractor perforamnce, including forms and reporting process, and (c)
general knowledge on good construction practices for reducing potential impacts on local
environment and safety aspects.
Environmental and Social Management Framework (ESMF) Viet Nam Natural Hazards Management Project (Vn-Haz/WB5)
37
100. Given the number of the subprojects and its nature/locations, it is anticipated that at
least 4 safeguard training courses should be provided during the first 3 years of the project
implementation. The training should first focus on the knowledge, policies, and procedures
related to land acquisition and resettlement and involvement of ethnic minority and/or other
social aspect so that RAP implementation could be completed before construction start. All
key staff responsible for the activities should particapate in the training. The supervision of
contractor training should be conducted at least 1 month before the construction. The key
participants should include PPMU staff and its consultants (CSC), and representatives from
local agencies, local communities, and/or mass organizations, responsible for supervison of
contractor.
7.4. Budget Allocation
101. To support effective implementation of safeguard, the Project budget has been
allocated as follows:
Feasibility Studies and Safeguard Documents for the second and follow-on year
subprojects. About 1.5 percent of the estimated civil works cost is appropriated to support
the preparation of the detailed feasibility studies (including economic analysis) and
safeguard document preparation (RAP, EMP/DSR, and EMDP) for the follow-on
Component 4 subprojects. The PPMUs will carry out the feasibility studies and safeguard
documents preparation with the assistance of national consulting firms/institutions
financed by the counterpart, whereas the CPMO will review and carry out quality control
with the assistance of international experts funded by the Bank.
Detailed Design and Construction Supervision. The Government has appropriated
approximately US$2.00 million to finance the preparation of the detailed design for the
follow-on Component 4 subprojects and to carry out technical supervision for the civil works
which will also be responsible for monitoring of safeguard. The funds would support the
recruitment of national consulting firms which will assist the PPMUs in carry out the tasks.
Environment Management Plan and Monitoring. About US$250,000 will support the
environmental management plan and monitoring for the potential impacts possibly
resulting from the proposed investment under the project, including training and capacity
building for the affected local communities following the CBDRM. The detailed scope
and frequency of the monitoring is described in the EMP prepared for each subprojects.
The monitoring would be carried out by a team of national consultant to be recruited by
CPMO. A report would be prepared by the CPMO with the assistance of national
consultants financed by the Bank for each subproject every year.
Social Safeguard Monitoring. US$250,000 will support the monitoring the
implementation of the social safeguards, namely RAP and EMDP. The monitoring would
be carried out by a team of independent experts recruited by the CPMO. The monitoring
report would be prepared for each subproject every year.
Land Appropriation. About 15 percent of the total estimated cost of civil works under
Component 4 has been appropriated to be used for the appropriation of the land necessary
to implement the civil works for the subprojects. The cost for the land appropriation
would be exclusively financed by the Government, and this amount would be adjusted
when the RAP is prepared for each subproject.
Environmental and Social Management Framework (ESMF) Viet Nam Natural Hazards Management Project (Vn-Haz/WB5)
38
Annex 1: Location of River Basins and List of Potential Subprojects
Figure A1.1. River basins and provinces related to WB5 Project
Environmental and Social Management Framework (ESMF) Viet Nam Natural Hazards Management Project (Vn-Haz/WB5)
39
Table A1.1: List of the first year subprojects (5 provinces, 5 basins)
No. Sub-Projects River basins
Total
(Bill.
VND)
IDA
fund
(Bill.
VND)
Type of
works
River
basins
I. Thanh Hoa
1 Maintain, upgrade and treat the
key parts of the left dyke of
Cau Chay river (section from
K0-K42), Yen Dinh district
Ma river
263 240 Dyke/road Ma
River
II. Nghe An
2 Bridge combining with
overflow connecting Rescue
roads, Nghi Loc and Vinh city Ca river
53 45 Dyke/road Ca River
3 Upgrade dyke site of Luong
Yen Khai Ca river
29 27 Dyke/road Ca River
III. Ha Tinh
4
Upgrade dyke site Phuc Long
Nhuong, Cam Xuyen district Ha Vang-Rac river
191 180 Dyke/road Ha
Vang-
Rac
River
VII. Quang Nam
5 Repair, upgrade Thạch Ban
reservoir, Duy Xuyen district Thu Bon river
92 86 Dam Thu Bon
River
X. Binh Dinh
6 Upgrade anti-erosion
embankment of Kone river
for safety, An Nhon and Tuy
Phuoc districts
Kone river
53 47 Dyke/road Kone
River
Sub-Projects River basins 681 625
Table A1.2: List of potential subprojects for the follow-on years by provinces
No.
Name of subproject Investment Items Total
(Bil.
VND)
IDA
fund
(Bil.V
ND)
Type of
works River
basins
Total 9 provinces 1,487 1,294
I. Thanh Hoa 0 0
II. Nghe An 268 235
1 Repair, Upgrade, ensure
safety for reservoirs Ban
Muong, Cho Quan, Xop
Thap, Khe Lau, Khe Lang,
Lach Buoi
Earthen dam; overflow;
intake gate and
management house 70 62
Dam Ca
River
2 Rescued road of Hung
Nguyen district (including
Hung Lam, Hung Nhan,
Line, widen, stabilize the
road surface 23.5 Km 20 17
Dyke/road Ca
River
Environmental and Social Management Framework (ESMF) Viet Nam Natural Hazards Management Project (Vn-Haz/WB5)
40
Hng Xuan, Hung Chau)
3 Embankment protecting Ca
River, acrossing Dinh Son,
district Anh Son. 2 km embankment
50 45
Dyke/road Ca
River
4 Embankment protecting Ca
River, acrossing Linh Son,
district Anh Son. 2 km embankment
40 36
Dyke/road Ca
River
5 Rescued road of Do
Luong district (including
Thai Son, Minh Son
communes)
Line, widen, stabilize the
road surface 12 km 10 8
Dyke/road Ca
River
6 Upgrade dyke Vach Bac,
district Yen Thanh 9km dike
64 55 Dyke/road Ca
River 7 Rescued road connecting
national road 46 to Thanh
Luong - Nam Hung.
Line, widen, stabilize the
road surface 11.5 km 14 12
Dyke/road Ca
River
III. Ha Tinh 88 60
8
Dredging, treating jet to
Cua Sot shelter, Loc Ha
district
Dredge a jet with 4 km
length; build 300 m
embankment, treat flow; 2
km rescued roads, 1.5 km
embankment protecting
harbors and flood shelters 88 60
Coastal
structure Ca
River
IV. Quang Binh 150 128
9 Fishing boat harbor in Nhat
Le river basin Boats anchoring
structures; anti-wave dike 150 128 Coastal
structure Gianh
River V. Quang Tri 122 111
10 Upgrade Trieu Thuong
reservoirs 1 and 2
Upgrade main damp, flood
overflow, intake gate
under damp 38 34
Dam Thach
Han
River 11 Repair and upgrade
Hydraulic Structures:
Viet Yen – Vinh Phuoc
Upgrade sluice and sluice
gate 15 14
Dam Thach
Han
River 12
Upgrade Phuoc Mon
reservoir, Hai Le commune
Upgrade main dam, flood
overflow, sluice under
dam 14 13
Dam Thach
Han
River 13 Emergency anti- erosion
embankment for Nai Cuu –
Trieu Dong commune –
Trieu Phong district
Build 1.02 km river
embankment 16 14
Dyke/road Thach
Han
River
14 Embankment for Trieu Do
commune – Trieu Phong
district
Build 2.24 km river
embankment 24 22
Dyke/road Thach
Han
River 15 Emergency anti-erosion
embankment for Trieu Tai
commune – Trieu Phong
district
Build 1km river
embankment 15 14
Dyke/road Thach
Han
River
VI. Da Nang 245 221
16 Upgrade ensure safety for
Hoa Trung reservoir
(i) Widen main overflow
(ii) Reinforce main dam
(iii) Equipments and 85 77
Dam Vu Gia-
Thu
Bon
Environmental and Social Management Framework (ESMF) Viet Nam Natural Hazards Management Project (Vn-Haz/WB5)
41
management house
(iv) Upgrade rescued road
and overflood bridge 17
Upgrade, widen flood drain
for An Trach weir
(i) Replace 12 old valvet
gates by 12 flat valvet
gates operating by
electricity
(ii) Widen 2 more drain
section
(iii) Reinforce, upgrade
absorption yard
(iv) Equip controlling
system
(v) Repair Ha Thanh dam 60 54
Dam Vu Gia-
Thu
Bon
18
Upgrade ensure safety for
4 reservoirs: Truoc Dong,
Truong Loan, Hoc Khe, Ho
Cau
(i) Upgrade main dam
(ii) Upgrade & widen
main overflow
(iii) Widen auxiliary
overflow
(iv) Repair intake gate
(v) Reinforce rescued &
management roads 80 72
Dam Vu Gia-
Thu
Bon
19
Upgrade ensure safety for
2 small reservoirs: Dong
Treo and Ho Thung
(i) Upgrade main dam
(ii) Widen, reinforce main
overflow
(iii) Repair auxiliary
overflow
(iv) Repair intake gate 20 18
Dam Vu Gia-
Thu
Bon
VII. Quang Nam 178 161
20 Repair, upgrade Khe Tan
reservoir, Dai Loc district
Main dam, overflow,
intake gate, management
house and road 66 58
Dam Vu Gia
River
21 Build anti-erosion
embankment for Thu Bon
river, Phu Da area, Duy
Xuyen district
Embankment’s body and
foot made of concrete
slabs, length 1.5 km 33 31
Dyke/road Thu
Bon
River
22 Repair, upgrade Chan Son
reservoir, Dai Loc district
Main dam, overflow,
intake gate, management
house and road, electricity
system 21 20
Dam Vu Gia
River
23 Build river embankment
for Tan Binh village, Dien
Trung commune, Dien Ban
district
Embankment’s body and
foot made of concrete
slabs, length 1.5 km 33 31
Dyke/road Thu
Bon
River
24 Build anti-landslide
embankment for Bau Sau
river, in the down-stream
of Bau Nit weir, Dien Ban
district
Embankment’s body made
of precast concrete, its foot
made of Ferro-concrete
M200, length 1 km 25 21
Dyke/road Thu
Bon
River
VIII. Quang Ngai 190 171
25 Duc Loi dam Headwork dam
50 45 Dam Ve
River
Environmental and Social Management Framework (ESMF) Viet Nam Natural Hazards Management Project (Vn-Haz/WB5)
42
26
Fishing boat harbor and
My A sea gates (phase 2)
Lengthen 180 m South
dike Nam, 160 m North
dike Bac to the level of
+6.0 m; Lengthen anti-
sand dike, flood
prevention for more than
120 m, crest level of +3.2
m. Dredge and widen jet
to 60 m. Logistic fishing
structure, shelters for
fishermen and technical
structures 140 126
Coastal
structure Ve
River
IX. Binh Dinh 90 81
27
Upgrade, repair overflow
bridges of rescued road
Dong Tuy Phuoc – An
Nhon – Phu Cat
Upgrade 8 overflow
bridges of road DT640:
Bridge # 15 in Huynh Mai;
Km14+310; Km14+760;
Km15+820; Km16+620;
Km17+080; Km17+865;
and Bau Sao overflow
bridge on road DT636A 90 81
Dyke/road Kone
River
X. Ninh Thuan 156 126
28
Upgrade dyke at the north
of Dinh river
Upgrade the whole dike
site to protect Phan Rang –
Thap Cham city
combining with traffic,
length of 11.1 Km 156 126
Dyke/road Dinh
River
Table A1.3: Classification of subprojects under Component 4 by type of works
[(1) Upgrading river dikes and revetments; (2) Upgrading rescue roads/bridge; (3) Upgrading
dams and reservoirs; and (4) Dredging of river mouth and upgrading of habors for fishing boats]
Type of works No. of
Subprojects Main activities
(1) Upgrading
river dikes and
revetments,
including roads
and bridges
14
Upgrading: Raising and widening cross-section, reinforcing dike
surface (combined with traffic way function), construction of wave-
prevention walls on the dike surface, dike slope embankments;
construction of under dyke sluices; construction of premises for the
dike management and flood and storm prevention and control unit on
the dike, construction of rescue roads, construction of pumping stations
to the river; Revetment: Reinforcing river banks mainly with slope revetments
(ashlars or rock gabions aranged in reinforced concrete frames (pile
up or excavate earth to form slope design before reinforcing));
construction of reinforced concrete wave-prevention walls on the
revetment surface; construction of management and operation roads
combined with transport ways on top of the revetments; construction of
drainages to the river. (2) Upgrading
rescue
roads/bridge 5
Raising and widening cross-section, stabilize surface to facilitate
rescue activities; construction of sluices accross the roads, construction
of traffic bridges combined with overflow dam;
Environmental and Social Management Framework (ESMF) Viet Nam Natural Hazards Management Project (Vn-Haz/WB5)
43
(3) Upgrading
dams and
reservoirs,
including
upgrading and
widening flood
drain for An
Trach weir
12
raising and widening cross-section, reinforcing dam surface (combined
with traffic road function and reservoir management and operation
function); Construction of wave-prevention walls on the dam surface;
reinforcing upstream slope, plantting grass on downstream slope;
supplement or repairing drainage structures, new construction or
reparing/upgrading flood drain; new construction or
reparing/upgrading sluices; construction of head management house;
new construction of management and operation roads, reparing and
upgrading irrigation canals; Replacing 12 old valvet gates by 12 flat valvet gates operating by
electricity to gain control in operation of flood drain, Widening 2
more drain section two sides of the weir to increase flood drain
capacity (due to climate change, flood flow has increased);
Reinforcing absorption yard and basin, Reparing the weir, Equiping
automatic control system. (4) Coastal
structure (river
mouth
dredging, safe
habors for
fishing boats)
3
Dredging passages to ensure safe water-line for ships to enter ports to
avoid storms; construction of flow control embankments;
construction of rescue roads, construction of dyke protection port and
surrounding; construction of technical infrastructure for anchorages;
construction of mooring posts;
Total 34
Table A1.4: Number of subprojects under Component 4 by provinces
Province
I.
Thanh
Hoa
II.
Nghe
An
III.
Ha
Tinh
IV.
Quang
Binh
V.
Quang
Tri
VI.
Da
Nang
VII.
Quang
Nam
VIII.
Quang
Ngai
IX.
Binh
Dinh
X.
Ninh
Thuan Total
No. of
subprojects
under
Component 4
1 9 2 1 6 4 6 2 2 1 34
Table A1.5: Number of subprojects proposed under component 4 by river basins (9)
River basins Ma Ca
Ha
Vang-
Rac
Gianh
River Thach
Han
Vu
Gia-
Thu
Bon
Vu
Gia-
Thu
Bon
Tra
Khuc-
Tra
Bong
Kone
River
Dinh
River Total
No. of
subprojects
under
Component 4
1 9 2 1 6 4 6 2 2 1 34
Environmental and Social Management Framework (ESMF) Viet Nam Natural Hazards Management Project (Vn-Haz/WB5)
44
Table A1.6: List of Dams Proposed Under the Project
Subproj
ect
Name of
Dam
Province /
District
River-
basin
Built
Year
Widt
h
(m)
Lengt
h
(m)
Heigh
t
(m)
Volum
e
(millio
n m3)
Population
Downstrea
m
Purposes of Dams
Remark
Sub 1 Thạch Ban
Reservoir
Quang Nam
/ Duy
Xuyen
Thach
Han
1984 6 776 20 9.84 13615 Agriculture / Flood
Cntrl / Drought Mgt
Phase 1
Sub 2 Bản Muỗng,
Reservoir
Nghệ
An/Quy
Hop
Cả 1971 5 120 23 3.14 5344 Agriculture / Flood
Cntrl
Phase 2
Chọ Quan
Reservoir
Nghệ
An/Anh Son
Cả 1990 5 205 13.2 3.1 967 Agriculture / Flood
Cntrl
Phase 2
Xốp Thập
Reservoir
Nghệ
An/Ky Son
Cả 2000 5 50 7 0.16 1531 Agriculture / Flood
Cntrl , /supply water
for 350 households
Phase 2
Khe Lau Nghê
Cả 1978 6 308.32 13.49 2.133 5,010
Agriculture / Flood
Cntrl , /supply water
for 140 ha crops
Phase 2
Khe Lang Nghê An/Nghi Lô c
Cả 1967 4.5 130 13.7 2.7 7,780 Agriculture / Flood
Cntrl
Phase 2
Lach Buoi Nghê An/Nghi Lô c
Cả 1964 4.5 130 18.2 3.6 10,919 Agriculture / Flood
Cntrl
Phase 2
Sub 3 Triệu
Thượng 1
Reservoir
Quảng
Trị/Trieu
Phong
Thach
Hãn
1979 5 666.4 11.5 3.6
5000
Agriculture / Flood
Cntrl
Phase 2
Environmental and Social Management Framework (ESMF) Viet Nam Natural Hazards Management Project (Vn-Haz/WB5)
45
Triệu
Thượng 2
Reservoir
Quảng
Trị//Trieu
Phong
Thach
Hãn
1989 5 547 10.7 3.5 Agriculture / Flood
Cntrl
Phase 2
Sub 4 Phước Môn
Reservoir
Quảng Trị Thach
Hãn
1980 5 282 8.4 0.85 1435 Agriculture / fishing
/Flood Cntrl
Phase 2
Sub 5 Khe Tan
Reservoir
Quang Nam
/ Dai Loc
Vu Gia-
Thu Bon
1985 6 1700 22.40 108.5 25000 Agriculture / Flood
Cntrl / Drought Mgt
Phase 2
Sub 6 Chan Son
Reservoir
Quang Nam
/ Dai Loc
Vu Gia-
Thu Bon
1982 5 170 8 0.85 6974 Agriculture / Flood
Cntrl / Drought Mgt
Phase 2
Sub 7 Hòa Trung
Reservoir
Da Nang/
Hoa Vang
Vu Gia
– Thu
Bồn
1983 5 870 14 11.69 100000 Agriculture / Flood
Control
Phase 2
Sub 8 Trước Đông
Reservoir
Da Nang/
Hoa Vang
Vu Gia
– Thu
Bồn
1985 4 200 10 2.3 18000 Agriculture / Flood
Control
Phase 2
Trường Loan
Reservoir
Da Nang/
Hoa Vang
Vu Gia
– Thu
Bồn
1981 4 120 7 0.45 8000 Agriculture / Flood
Control
Phase 2
Hốc Khế
Reservoir
Da Nang/
Hoa Vang
Vu Gia
– Thu
Bồn
1982 4 90 8 1.1 15000 Agriculture / Flood
Control
Phase 2
Hố Cau
Reservoir
Da Nang/
Hoa Vang
Vu Gia
– Thu
Bồn
1983 4 190 10 1.0 10000 Agriculture / Flood
Control
Phase 2
Sub 9 Đồng Tréo
Reservoir
Da Nang/
Hoa Vang
Vu Gia
– Thu
Bồn
1985 4 410 7 0.8
7000 Agriculture / Flood
Control
Phase 2
Hồ Thung
Reservoir
Da Nang/
Hoa Vang
Vu Gia
– Thu
Bồn
1977 4 90 10 0.3 6500 Agriculture / Flood
Control
Phase 2
Environmental and Social Management Framework (ESMF) Viet Nam Natural Hazards Management Project (Vn-Haz/WB5)
46
Table A1.7: List of the activities to be implemented under Component 3
No Component / Sub-component / Activity
Sub C 3.1 Capacity strengthening for CBDRM at commune level
A Commune Resilient Planning
1 Commune risk assessment preparation
2 Commune annual flood and storm control plan (CAFSCP) Improvement
3 Integration of safety plan into Socio Economic Dev. Plan
4 Commune Resilient Planning
B Commune Institution Strengthening
1 Facilitation skill
2 CBDRM, risk assessment and safety plan
3 Exchange visits
4 M&E training
5 Network of CFSC
6 CPC/CF follow-up training
Sub C 3.2 CBDRM Investments
C CBDRM Non-structural Investment
1 Public evacuation drills
2 IEC material development
3 Public awareness
4 School education and evacuation drills
5 Loud speaker system
6 Safe house design training
7 Mass organization training (first aid, evacuation support, others)
8 Equipment for emergency response
D CBDRM structural measure investment
1
Small scale structures (Multi-purpose shelter, feeder road, pumps, drainage
dredging, ,…)
Environmental and Social Management Framework (ESMF) Viet Nam Natural Hazards Management Project (Vn-Haz/WB5)
47
Annex 2: Standard Environmental Code of Practices (ECOP) for the Subprojects
Table of content
I. Introduction
II. Relevant World Bank’s Safeguard Policies and Government’s Regulations
III. Responsibilities
IV. General Provisions
4.1 Contract Specific Environmental Plan (CSEP)
4.2 Non-compliance and Incident Reporting Procedure
4.3 Coordination with Government Authorities and the Public
4.4 Community Relations
4.5 Mitigation Objective
4.6 Implementation of “Chance Find” Procedures
4.7. Prohibitions
V. Management of Construction
5.1 Management of Construction Sites and Activities
5.2 Management of Environmental Quality
5.3 Management of Work Camp
5.4 Management of Stockpiles, Quarries, and Borrow pits.
5.5 Management of Dredging
5.6 Monitoring of Potential Impacts
Environmental and Social Management Framework (ESMF) Viet Nam Natural Hazards Management Project (Vn-Haz/WB5)
48
I. Introduction
1. Objective. This Environmental Code of Practices (ECOP) was prepared to guide the
planning and implementation of the mitigation measures to be carried out by Contractor during
construction. It sets out standard practices and procedures for managing the potential negative
impacts on local environment and local communities of all civil works to be carried out under
the Project. The ECOP will be included as a separate annex in all bidding and contract
documents and the field engineers and supervisor will be assigned the responsibility to ensure
compliance and reporting. The Contractor will be made aware of and commit to this obligation
and know that cost for implementation of the measures is part of the construction cost.
2. Scope and application. This ECOP will be applied to all the subprojects to be
implemented under Component 4. For the sake of clarity, “construction” in this document
includes all site preparation, demolition of structures, spoil disposal, materials and waste
removal and all related engineering and construction activities.
II. Relevant World Bank’s Safeguard Policies and Government’s Regulations
3. World Bank’s safeguard policies. This ECOP is prepared to satisfy the WB safeguard
requirements under OP4.01 (EA) which requires planning, implementation, and monitoring of
the mitigation measures during construction.
4. GOV’s regulations. There are a number of GoV regulations, standards, code of
practices, etc. related to environmental and safety that are relevant to construction activities and
environmental quality. In addition to the main laws and regulation outlined in the
Environmental and Social Management Framework, the ones related to environmental quality
and safety are listed below (not exhaustive) and have to be closed observed:
Water environment
- QCVN 01:2009/BYT: National technical regulation on drinking water quality
- QCVN 02:2009/BYT: National technical regulation on domestic water quality
- QCVN 08:2008/BTNMT: National technical regulations on surface water quality
- QCVN 09:2008/BTNMT: National technical regulations on groundwater quality
- QCVN 10:2008/BTNMT: National technical regulations on quality of coastal water
- QCVN 11:2008/BTNMT: National technical regulation on industrial wastewater quality.
- QCVN 14:2008/BTNMT: National technical regulations on quality of domestic
wastewater
- QCVN 24:2008/BTNMT: Industrial wastewater – Discharge standards
- TCVN 5502:2003: Supplied water – Requirements for quality
- TCVN 6773:2000: Water quality – Water quality for irrigational purposes
- TCVN 6774:2000: Water quality – Water quality for aquaculture protection
- TCVN 7222:2002: Water quality – Water quality for concentrated domestic water
Soil environment
- QCVN 03:2008/BTNMT – National technical regulation on the allowable limits of
heavy metals in the soils;
Air environment
- QCVN 05:2008: Air quality – Standards for ambient air quality
Environmental and Social Management Framework (ESMF) Viet Nam Natural Hazards Management Project (Vn-Haz/WB5)
49
- QCVN 06:2008: Air quality – Maximum allowable concentration of hazardous
substances in the ambient air.
- QCVN 07:2008: Air quality – Threat hold of hazardous substances in the air.
- TCVN 6438:2001: Road vehicles – Maximum permitted emission limits of exhausted
gases
- TCVN 6438:2001 - Road vehicles - Maximum permitted emission limits of exhaust.
- QCVN 07:2009: National technical regulations for classification of hazardous wastes
Vibration and Noise
- QCVN 27:2010/BTNMT – National technical regulation on Vibration (replace TCVN
6962:2001 - Vibration emitted by construction works and factories - Maximum
permitted levels in the environment of public and residential areas;
- QCVN 26:2010/BTNMT – National technical regulation on Noise (replace TCVN
5948:1999 Acoustics - Noise caused by transportation means when speeding -
Allowable level)
- TCVN 5949:1998 Acoustics - Noise in public and residential areas - Allowable level
Labor Health and Safety
- Decision No.3733/2002/QĐ-BYT issued by Ministry of Healthcare dated on 10/10/2002
about the application of 21 Labor health and safety standards that concerned about
microclimate, noise, vibration, Chemicals – Permitted level in the working environment.
Moreover, regarding planning and design of infrastructure, operation and management of
the water supply systems, and water source option to serve domestic water supply systems
the following standards are used:
- Decision No.628/BXD-CSXD of the Ministry of Construction (MOC) dated 14th
December 1996: Vietnamese Construction Regulations and Standards;
- Design standards No. 20TCN-33-85 for water supply projects;
- Instructions for preparation and approval of town construction planning of MOC in
1998;
- Construction standard TCXD No.66:1991 on Operation of water supply and drainage
systems - Safety requirements;
- Construction standard TCXD No. 76:1979 on Procedures for technical management in
operation of water supply systems; and
- Construction standard TCXD No.233:1999 on criteria used for choosing surface water,
groundwater sources to serve domestic water supply system.
III. Responsibilities
5. The subproject owner (PPMUs) and the contractor are the key entities responsible for
implementation of this ECOP. Key responsibilities of the subproject owners and the contractors
are as follows:
(a) Subproject owner
- General: The subproject owner (PPMUs) on behalf of the Central Project Management
Unit (CPMO) is responsible for ensuring that the ECOP is effectively implemented. The
subproject owner will assign a group of qualified staff to be responsible for preparation
and management of environmental and social safeguard of the subproject throughout its
Environmental and Social Management Framework (ESMF) Viet Nam Natural Hazards Management Project (Vn-Haz/WB5)
50
life, including supervision of contractors. The subproject owner is responsible for
preparing the safeguard reports and submitting to the CPMO.
- For the contract involving dredging, the subproject owners with assistance of the
consultants will prepare a Dredge Materials Disposal Plan (DMDP) during the
preparation of an EMP or detailed design as appropriate.
- During construction, the subproject owners will assign the Construction Supervision
Consultants (CSCs) and/or field engineer to be responsible for monitoring and
supervision of the compliance of the contractors to fulfill the agreed CSEP (see below).
Responsibilities of the CSCs would include the following: (a) monitoring the
contractors’ compliance with the environmental plan, (b) taking remedial actions in the
event of non-compliance and/or adverse impacts occur, (c) investigating complaints,
evaluating and identifying corrective measures; (d) advising to the Contractor on
environment improvement, awareness, proactive pollution prevention measures; (f)
supervising the Contractor’s activities in responding to the complaints; (g) providing
guidance and on-the-job training to field engineers on various aspects to avoid/mitigate
potential negative impacts to local environment and communities during construction.
(b) Contractors
- Contractors have the responsibility of carrying out contracted works through fulfilling
the agreed CESP (Contract Environmental Specification Plan as defined in General
Provisions below). In doing so, the contactors will establish and maintain contact with
the subproject owner and local residents, and keep them informed of construction
matters likely to affect them. This may include regular and frequent distribution of
newsletters and attendance at meetings at the request of the subproject owner with
representatives of local residents groups.
- Contractors will provide information and reporting telephone “Hot Line”, staffed at all
times during working hours. Contact details should be prominently displayed at the sites.
Information on the construction progress, including the projected activities that might
require closure of traffic or may cause safety risk should be timely provided.
- Contractors have the duty to secure appropriate permits and licenses before undertaking
the works or moving heavy equipment. It is the responsibility of the Contractors to
monitor the development and implementation of new environmental legislation and
regulation and to use the appropriate standards prevailing at the time of awarding
contracts. Contractors must comply with all prevailing legislation at the time of
construction, including any requirements under health and safety.
IV. General Provisions
4.1 Contract Specific Environmental Plan (CSEP)
6. Contractors will be required to prepare a CSEP describing how the Contractor intends to
operate construction at works sites as well as other specific measures necessary to avoid and/or
reduce the potential negative impacts as required in the ECOP, especially those related to
management of the construction site, including borrow pits; transportation of construction
materials, especially dredge materials; control of dust, noise, and vibration; solid and liquid
waste management; and public health. Given different scope and nature of civil works, scope
Environmental and Social Management Framework (ESMF) Viet Nam Natural Hazards Management Project (Vn-Haz/WB5)
51
and nature of the CSEP could be differ and all the CSEP will be reviewed and approved by the
PEMC to be assigned by the subproject owner.
4.2 Non-compliance Reporting Procedures
7. Contractors must comply with the CSEP, and must ensure that their Sub-Contractors (if
any) also comply with it. To ensure that necessary action has been undertaken and that steps to
avoid recurrence have been implemented, the CSC/PEMCs and/or Contractors must advise the
subproject owner within 24 hours of any serious incidents of non-compliance with the CSEP
that may have serious consequence. In the event of working practices being deemed dangerous
either by the subproject owners, the local authorities, or the other concerned agencies,
immediate remedial action must be taken by the Contractors. The Contractors must keep records
of any incidents and any ameliorative action taken. The records on non-compliance that could
be practically addressed (not cause serious impacts) should be reported to the subproject owner
on a monthly basis.
8. The Contractor will be responsible for dealing with any reports forwarded by the
subproject owner, Police or other agencies by (following instruction from the subproject owner
representative as appropriate) as soon as practicable, preferably within one hour but always
within 24 hours of receipt by either the Contractor. The CSC/PEMC will monitor and ensure
that the Contractor has taken appropriate action. Where appropriate, approval remedial actions
may require an agreement from the local authorities and/or other GOV agencies. Procedures
should be put in place to ensure, as far as is reasonably practical, that necessary actions can be
undertaken to avoid recurrence and/or serious damage.
4.3 Liaising with Authorities and the Public
9. Prior to the commencement of subproject activities and throughout the construction
duration, the Contractors will work closely with the local authorities and other agencies to
ensure full compliance with GOV regulations and will also provide adequate information on the
Project to the General Public, especially those that may cause public safety, nuisance, and
sensitive areas and the locations of storage and special handling areas.
10. The Contractor will provide information and reporting telephone “Hot Line” staffed at
all times during working hours. Information on this facility shall be prominently displayed on
site hoardings.
4.4 Community Relations
11. Contractors will assign a community-relation personnel, who will be focused on
engaging with the community to provide appropriate information and to be the first line of
response to resolve issues of concern. Contractors will take reasonable steps to engage with
residents of ethnic minority backgrounds and residents with disabilities (or other priority groups
as appropriate), who may be differentially affected by construction impacts.
12. Contractors will ensure that local residents nearby the construction sites will be
informed in advance of works taking place, including the estimated duration. In the case of
work required in response to an emergency, local residents shall be advised as soon as
reasonably practicable that emergency work is taking place. Potentially affected residents will
also be notified of the ‘Hotline’ number, which will operate during working hours. The
Environmental and Social Management Framework (ESMF) Viet Nam Natural Hazards Management Project (Vn-Haz/WB5)
52
“Hotline” will be maintained to handle enquiries regarding construction activities from the
general public as well as to act as a first point of contact and information in the case of any
emergency. All calls will be logged, together with the responses given and the callers' concerns
action and a response provided promptly. The helpline will be widely advertised and displayed
on site signboards.
13. The Contractor respond quickly to emergencies, complaints or other contacts made via
the ‘Hotline’ or any other recognized means and liaise closely with the emergency services,
local authority officers and other agencies (based on established contacts) who may be involved
in incidents or emergency situations.
14. The Contractor will manage the work sites, work camps, and workers in a way that is
acceptable to local residents and will not create any social impacts due to workers. Any
construction workers, office staff, Contractor’s employees, or any other person related to the
Project found violating the “prohibitions” activities listed in Section A2 below may be subject
to disciplinary actions that can range from a simple reprimand to termination of his/her
employment depending on the seriousness of the violation.
4.5 Mitigation Objectives and Special Considerations
15. Main objective of this ECOP is to minimize the potential negative impacts during
construction on local environment, local community, and human and environmental safety and
disturbance. The Contractor is expected to implement the activities in line with the following
approach as much as possible in close consultation with the supervision and/or field engineers
who will be assigned by PPMU to supervise the contract. Key approaches include, but not
limited, to:
- Minimize impacts and restore damages;
- Replanting trees in project areas;
- Control erosion and sedimentation during construction;
- Proper control of suspended solids during dredging;
- Use main roads when possible;
- Heavy traffic restrictions;
- Control (collection, disposal) of wastes (solid and liquid);
- Minimize disturbance to local population; Frequent meetings with local people and
provision of timely and adequate information to the project affected peoples (PAPs)
so that their living and production conditions could be managed;
- Engage and provide labour opportunity for local population;
- Application of proper safety and warning measures in the construction sites,
especially in dredging activities;
- Provision of temporary crossings and bridges during construction of bridges;
Application of proper safety and warning measures;
- Conduct public information campaign and outreach program, including training and
capacity building.
4.6 Implementation of “Chance Find” Procedures
Environmental and Social Management Framework (ESMF) Viet Nam Natural Hazards Management Project (Vn-Haz/WB5)
53
16. If Contractors discovers archeological sites, historical sites, remains and objects,
including graveyards and/or individual graves during excavation or construction, the
Contractors will carry out the following steps:
- Stop the construction activities in the area of the chance find;
- Delineate the discovered site or area;
- Secure the site to prevent any damage or loss of removable objects. In cases of
removable antiquities or sensitive remains, a night guard shall be arranged until the
responsible local authorities or the National Culture Administration take over;
- Notify the supervisory Project Environmental Officer and Project Engineer who in
turn will notify the responsible local authorities and the Culture Department of
Province immediately (within 24 hours or less);
- Responsible local authorities and the Culture Department of Province would be in
charge of protecting and preserving the site before deciding on subsequent
appropriate procedures. This would require a preliminary evaluation of the findings
to be performed by the archeologists of National Culture Administration. The
significance and importance of the findings should be assessed according to the
various criteria relevant to cultural heritage; those include the aesthetic, historic,
scientific or research, social and economic values;
- Decisions on how to handle the finding shall be taken by the responsible authorities
and Culture Department of Province. This could include changes in the layout (such
as when finding an irremovable remain of cultural or archeological importance)
conservation, preservation, restoration and salvage;
- Implementation for the authority decision concerning the management of the finding
shall be communicated in writing by relevant local authorities; and
- Construction work could resume only after permission is given from the responsible
local authorities or Culture Department of Province concerning safeguard of the
heritage.
4.7 Prohibitions
17. The following activities are prohibited on or near the Project sites:
- Cutting of trees for any reason outside the approved construction area; Hunting, fishing,
wildlife capture, or plant collection; Buying of wild animals for food; Having caged wild
animals (especially birds) in camps; Poaching of any description; Explosive and
chemical fishing; Disturbance to anything with architectural or historical value;
- Building of fires; Use of unapproved toxic materials, including lead-based paints,
asbestos, etc.; Use of firearms (except authorized security guards); Use of alcohol by
workers in office hours; Driving in an unsafe manner in local roads;
- Washing cars or machinery in streams or creeks; Maintenance (change of oils and
filters) of cars and equipment outside authorized areas: Creating nuisances and
disturbances in or near communities; Disposing garbage in unauthorized places;
Indiscriminate disposal of rubbish or construction wastes; Littering the site; Spillage of
potential pollutants, such as petroleum products; Collection of firewood; Urinating or
defecating outside the designated facilities; and Burning of wastes and/or cleared
vegetation.
V. Management of Construction
Environmental and Social Management Framework (ESMF) Viet Nam Natural Hazards Management Project (Vn-Haz/WB5)
54
5.1 Management of Construction Sites
18. This section outlines the requirements relating to site management practices that should
be implemented during site operation. These relate to working hours, site layout and appearance
and good housekeeping as well as operations of equipment and vehicles. Monthly
inspection/meeting should be conducted to ensure that these procedures are adhered to. The
Contractor must follow a ‘good housekeeping’ policy at all times. The site should be cleared by
the Contractor on completion of the construction.
19. The Contractor is required to minimize, as far as reasonably practicable, any adverse
environmental impact of their construction activities. All appropriate licenses and consents in
respect of site operations will be timely secured. Key measures are as follows:
(i) General requirements on construction sites. A construction site must satisfy the following
requirements
- Site layout. The overall site layout must be designed and approved under regulations to
suit the construction location, the site’s area, natural and climate conditions in the place
of construction, facilitate the construction and ensure safety for human, machines and
equipments at the construction site and the surrounding areas affected by construction
activities.
- Site arrangement. Supplies and materials are placed neatly according to the approved
overall plan design. Supplies, materials and obstacles are not placed on roads,
emergency exits or fire entrances. Flammable and explosive material warehouses are not
arranged near the place of construction and tents. Waste materials are removed and
discharged in prescribed places. Water drainage systems are regularly cleared to ensure
that the construction ground is always dry.
- Signs. At the construction site there are signs according to Article 74 of the
Construction Law. At the main entrance, a plan of the overall ground of the construction
site and working regulations is displayed. Safety measures and rules are publicized at the
construction site for compliance. At dangerous places at the construction site, such as
trenches and foundation pits, there are fences, warning signs and instructions for
accident prevention. At night, signal lights are turned on.
- Good housekeeping: The Contractor will follow a ‘good housekeeping’ policy at all time
for the workers and the surrounding environment. This will include, but not necessarily
be limited to the following: dust and noise control; waste treatment, keeping the site
clean and tidy. To sites located near residential areas, wastes must be covered and
collected and properly disposed off. Construction and waste materials during
transportation must be properly covered to ensure safety and environmental sanitation.
In case the Contractor does not comply with environmental protection regulations, the
project owner and environmental authorized state agencies will have the power to
suspend the construction operations. Persons responsible for adverse environmental
impacts during the construction will be held responsible and compensate for any
damages caused at his fault.
- Power safety: Motive and lighting power grids at the construction site are separate and
installed with general circuit-breakers and sectioned circuit-breakers for cutting off
power in part or the whole of the construction area. Ensure power safety for workers,
construction machines and equipment at the construction site. Electric equipment are
safely insulated during the construction process. Workers are guided on power safety
techniques and ways to give first aid to persons who get electric shock in power
accident.
Environmental and Social Management Framework (ESMF) Viet Nam Natural Hazards Management Project (Vn-Haz/WB5)
55
- Fire and explosion safety: the Subproject Management Unit needs to set up a
commanding board for fire and explosion prevention and fighting at the construction
site, which has its own working regulations on its specific duties and powers. Fire and
explosion prevention and fighting plans are appraised and approved under regulations.
The contractor organizes a fire and explosion prevention and fighting brigade which has
its own working regulations on its specific duties and tasks. At the construction site,
local fire fighting equipments are arranged. At fire-prone places, inflammable
signboards and fire fighting and alarm equipment are installed to promptly detect fires
and take remedies.
(ii) Requirements during construction. During construction, the following requirements must be
satisfied:
- Working hours: Core working hours will be from 0800 to 1800 on weekdays and 0800
to 1300 on Saturday. Individual site requirements which differ from the above will be
considered on a site by site basis. Noisy operations shall not take place outside these
hours without prior approval from the subproject owner. All construction related traffic
will abide by the agreed hours of working for each site. Any exemption will require an
agreement with the Subproject owner, subproject, and/or local authorities.
- Before starting construction, an approved design of construction measures is required,
including labor safety solutions for workers and construction machines and equipment
for each job, which has explanations about technical and use instructions.
- During construction, the approved design as well as regulations, standards and technical
processes are complied with. Jobs dependent on the quality of previous jobs are
performed only after the previous jobs have been tested to meet quality requirements
under regulations.
- Construction measures and safety solutions are periodically or extraordinarily examined
for modification according to practical conditions at the construction site.
- Organizations and individuals are fully capable in the jobs they perform under
regulations. Operators of construction machines and equipment and performers of jobs
with strict labor safety requirements are trained in labor safety and possess labor safety
cards under regulations.
- Construction machines and equipment with strict labor safety requirements are inspected
by and registered with competent agencies under regulations for operation at the
construction site. During operation, they comply with safety processes and measures. If
construction equipment is operated outside the construction site, the investor approves
safety measures for construction-affected people, machines, equipment and works inside
and outside the construction site. If due to construction conditions, equipment have to be
placed outside the construction site and while not in operation, if they operate outside
the construction site, such is permitted by authorized agencies under local regulations.
- Workers at the construction site are provided with medical checks-up and safety training
and adequate personal safety equipment under the labor law.
- Unexploded Ordnance (UXO): Although the risk is not present in the entire project area,
in some subproject areas such as in Quang Nam and Quang Tri, the Contractor will be
responsible for ensuring UXO safety of the construction site. The response process
needs to be included in emergency procedures. The emergency procedures will be
prepared and carried out if UXO risk is identified at the construction site.
Environmental and Social Management Framework (ESMF) Viet Nam Natural Hazards Management Project (Vn-Haz/WB5)
56
(iii) Clearance and rehabilitation of construction site after completion:
- On completion of the works the Contractor will clear away and remove all materials and
rubbish and temporary works of every kind. The site will be left clean and in a condition
to the satisfaction of the PPMU. Any potentially hazardous defects to the works will be
made good, prior to permanent reinstatement
5.2 Management of Environmental Quality
(a) Water quality
20. The Contractor must take all the efforts to prevent wastes (solid and liquid) discharge
into all rivers and coastal water and to protect surface and groundwater from pollution and other
adverse impacts including changes to water levels, flows and general water quality. Discharge
of engine oil and oily waste from dredgers and construction machines to the rivers will be
strictly prohibited. Engine oil, used oil, and other toxic substances and hazardous wastes must
be properly collected, stored, treated, and/or disposed off. Key measures are as follows:
- Used oil/engine oil: The oil container at the construction site (especially when the site is
located less than 10 meters from the waterways) must be of sufficient strength to ensure
to prevent leakage. The container must be situated within a secondary containment
system (bunded), which will prevent the release of any leaked oil. The Contractor must
make provisions to ensure that all hazardous substances including oil drums or
containers on site are properly labeled and properly stored and that no oil or other
contaminants are allowed to reach water courses or groundwater.
- Wastewater from sites: Whenever possible, the Contractor must minimize the amounts
of wastewater that need to be discharged and find alternative means of disposal. The
Contractor will ensure that any seepage and wastewater arising from the works and
camp sites must be collected and discharged via a settlement tank. The standards for
wastewater treatment prior to discharge must be agreed in advance with the ESA.
Contaminated water or water of an uncertain quality must be discharged into sewers by
tankers or other approved means of disposal.
- Drainage. Water drainage must be designed to avoid stagnant conditions that could
create bad smell and unsanitary condition. The Contractor must agree with the ESA in
advance, details of the methodology to be employed, prior to commencement of the
construction. Particular attention must be given to regular pest control treatment
(particularly rats and flies); removal of sludge and other debris after drainage; reducing
smell nuisance from sludge and algae by measures including deodorizing, hosing down
etc. Safety measures must also be taken to protect both the general public and employees
and to prevent fly-tipping and illegal access during the development works.
- Water quality monitoring: The Contractor must ensure continuous compliance with all
the above conditions under the monitoring of the Subproject Owner and/or field
engineer, including undertaking water quality monitoring at specific sites and are in
compliance with government regulation related to wastewater management and water
quality monitoring.
Environmental and Social Management Framework (ESMF) Viet Nam Natural Hazards Management Project (Vn-Haz/WB5)
57
(b) Dust, noise, vibration
21. The Contractor must take all the efforts to control dust, noise, and vibration levels from
the site, as far as is reasonably practicable. Excessive noise/vibration generation activities must
be in accordance with GOV standards. For critical areas, the Contractor many be required to
conduct noise measurement in close consultation with the local residents and establish
appropriate measures to control and manage noise level. Measures for reducing dust and other
air pollution, noise, and vibration are provided as follows:
- Inform the residents: Prior to commencement of work at any site, the Contractor will be
required to inform the local authority and residents regarding the construction plan and
potential noise and vibration that may occur from the construction activities, including
measures to reduce noise and vibration.
- Dust control: The Contractor will ensue that no burning of waste materials on site;
adequate water supply is available on site; dry sweeping of large areas is not allowed;
Cover all trucks carrying loose or potentially dusty materials (soil, mud, etc.) to and
from construction site; Water or sprinkle the construction areas periodically, especially
at site located near residential area; avoid overloaded of trucks; routinely clean public
roads and access routes; Ensure vehicles working on site have exhausts positioned such
that the risk of re-suspension of ground dust is minimized (exhausts should preferably
point upwards), where reasonably practicable; Control driving speed on un-surfaced haul
routes and work areas; Ensure bulk cement and other fine powder materials are delivered
in enclosed tankers and stored in silos with suitable emission control systems to prevent
escape of material and overfilling during delivery; Mix large quantities of cement, grouts
and other similar materials in designated areas; Store materials with the potential to
produce dust away from site boundaries where reasonably practicable; Minimize the
amount of excavated material held on site; Sheet, seal or damp down unavoidable
stockpiles of excavated material held on site, where required; Seal or re-vegetate
completed earthworks as soon as reasonably practicable after completion.
- Care must be undertaken during the transportation of dredge spoil to and from the
construction site; the spoil must be covered at all time. Fly-tipping will not be permitted.
Loads must only be deposited at designated sites. The Contractor will be responsible for
all the trucks delivering to, or exiting from, a worksite and will clean up all damage that
may occur to public road and other public facilities. Care should be taken when loading
or unloading vehicles or dismantling scaffolding or moving materials to reduce impact
noise. Loading or unloading bays may have to be housed in suitable acoustic enclosures.
- The installation of sheet piling with a diesel or air driven impact or drop hammer may
not be acceptable on some of the sites. Use of hydraulically operated or vibratory
hammers may be necessary in these circumstances to drive and extract sheet piling,
provided the soil strata are suitable for such equipment. Where practicable, rotary drills
and bursters actuated by hydraulic or electrical power should be used for excavating
hard material. Noisy plant or equipment will be sited as far away as is practicable from
noise sensitive buildings. The use of barriers, (e.g. soil mounds), site huts, acoustic sheds
or partitions to deflect noise away from noise sensitive areas must be employed
wherever practicable.
Environmental and Social Management Framework (ESMF) Viet Nam Natural Hazards Management Project (Vn-Haz/WB5)
58
- The Contractor will be obliged to comply with the vibration levels established by
agreement with the ESA on a site by site basis given due attention to minimize human
exposure (1 Hz to 80 Hz) and protection of damage to nearby structures.
(d) Solid waste control and treatment
1. Solid wastes from subproject construction activities. The subproject construction activities
will generate a big amount of escaped soil and stones, cement bags and other surplus
materials (oily wastes, miscellaneous woods, etc.). Although solid wastes discharged in this
stage are not toxic or dangerous (except for some oily wastes such as oily cloths after
cleansing machines and equipments, etc.), proper measures for waste collection and
treatment are required to avoid contaminating the environment and affecting local
landscape. The Contractor must make a commitment to collect all escaped soil and stones
and transport to designated areas or reuse them for dyke/road construction. Bags and other
solid wastes will be collected for recycling or burning or taken to temporary dumps in the
area (solid wastes disposed at these temporary dumps must be buried or covered in a
sanitary way). In addition, during subproject construction, uncontrolled discharging of solid
wastes into the environment needs to be minimized to reduce impacts to environmental
landscape, transportation and daily activities of local residents, and the environment (water
quality, soil quality and natural habitats).
2. Domestic solid wastes. During subproject construction, the Contractor must carry out
appropriate measures for waste collection and treatment. The domestic wastes will be
collected in plastic or wooden bins with lids placed in convenient places and in worker
canteens. Periodically, at appropriate time, transport those bins to the dumping lot (the
Contractor will select a proper location for the dumping lot, at least 500 m away from
residential areas, 200 m away from work camps and surface water sources, and not in the
prevalent wind direction of the area) to dispose of the wastes, from which the local Urban
Environmental and Construction Company will be hired to carry out proper removal and
treatment. The Contractor must sign a contract with the Urban Environmental and
Construction Company to collect and treat solid wastes generated during the subproject
construction. In case the wastes cannot be transported to the dumping lot (for example, due
to lack of appropriate transport route), wastes must be buried at temporary dumps in the
project area in a sanitary way – a waste layer covered by a layer of soil, and when the dump
is filled, it is covered by a soil layer about 50 cm thick. Temporary dumps must be located at
least 500 m away from residential areas, 200 m away from work camps and surface water
sources, and not in the prevalent wind direction of the area. Upon completion of works,
cover the entire temporary dumps with soil, ensure land and landscape restoration for the
subproject area.
(d) Traffic and Transportation
22. The Contractor will be required to use designated construction traffic routes as directed
by the local authorities and the Police. The number of truck movements, hours of operation and
any truck holding areas will be agreed in advance with the local authority and the Police. Plans
will be required for each site showing the site entrances/exits and the agreed access roads for
use to the nearest main road, and the routes to be used by truck to and from the strategic road
network.
- The Contractor will maintain an up to date log of all drivers that will include a written
undertaking from them to adhere to the local authority’s approved routes for
Environmental and Social Management Framework (ESMF) Viet Nam Natural Hazards Management Project (Vn-Haz/WB5)
59
construction traffic. In the case of non-compliance, the Contractor and/or their sub-
contractor(s) would be in breach of contract, necessitating disciplinary action against
individual drivers.
- The Contractor may be required to provide truck stickers uniquely identifying the group
of construction sites included in each contract, details of which shall be submitted to the
local authority for approval. For identification purposes the Contractor will fix these in a
prominent position on all trucks frequently serving the construction site. The
identification will need to be sufficiently large to be easily read from a distance of 20
meters. Trucks waiting to enter or leave the site must switch off their engines to avoid
unnecessary engine noise and emissions. Restrictions on the size and weight of vehicles
accessing each site may be imposed depending on agreed access routes.
- For construction that interference with a carriageway or footway, the Contractor will
inform the local authorities, responsible agencies, and local residents before
commencing the works and proposed measures to minimize the safety risk and
inconvenience to the public. All necessary consents and licenses must be obtained in
advance. The safety of the public must be ensured. In the case of temporary footways,
reasonable access shall be provided for people in accordance with the following
requirements: (a) Any temporary footways and carriageways will be constructed to the
reasonable requirements of the local authorities and should have uniform surfaces as
much as possible; (b) Clear signing must be provided at all times for pedestrian routes
with the minimum number of changes to all temporary layouts in order to reduce
confusion. Advance warning should, if possible, indicate alternative existing wheelchair-
accessible routes; (c) After completion of the works all materials arising from the works
will be cleared from the highway leaving the same in a clean and tidy condition to the
reasonable requirements of the local authorities; and (d) The Contractor will be
responsible for any damage caused by their activities to the roads and public facilities in
the vicinity of the worksite. Any defects caused by the Contractors must be rectified
immediately if dangerous or otherwise within 24 hours.
- Any street furniture (electrical or non electrical) cannot be removed or relocated by the
Contractor or any of its sub-contractors without written agreement from the responsible
agencies.
(d) Excavation Materials and Demolition Materials
3. Earth excavation must be carefully handled to reduce dust and possible obstruction and
causing nuisance and health impacts to local residents. Excavation that affects public roads
(such as pipeline and bridges) must be properly planned in consultation with local authority
and informed to the residents in advance. All dredged spoils as well as excavation materials
will be reused for dike/road construction and/or land filling at or nearby the work site.
Demolition materials must be properly disposed off. The Contractor must consult ESA on
the final selection of disposal sites and methods.
(f) Protection of natural habitats
4. During the construction stage, if mitigation measures of air, noise, water and soil pollution,
the project will create negative impacts on the growth and development of some animal and
plant species in the area, especially aquatic species. Proposed mitigation measure is to
develop a detailed plan and speed up the construction progress. The Contractor must
observe the national and local regulations and policies related to protected areas/species,
Environmental and Social Management Framework (ESMF) Viet Nam Natural Hazards Management Project (Vn-Haz/WB5)
60
wildlife sanctuaries. No trees in sensitive areas shall be cut without obtaining prior
agreement with the authorities. Strengthen monitoring the contractor’s compliance with
environmental protection commitments. In addition, organize training courses to improve
environmental protection awareness of the staff and local communities.
5.3 Management of Work Camp
23. The Contractor will consult with local authority regarding the location of the worker
camps and will provide appropriate water supply, garbage collection, toilets, mosquito net, and
other health protection measures to all workers. Fishing, wildlife hunting, and other social
disturbance to local societies are prohibited. Training of workers on safety, good hygiene, and
prohibitions activities is required. Detail measures as follow:
(i) During the preconstruction stage:
Contractor will consult with local authority and subproject management unit regarding
the location of the worker camps
Once work camp location is identified, the Contractor will set up temporary
accommodation for all the workers throughout the construction or maintenance period.
In terms of supply and storage of domestic water at the work camp area, the Contractor
will comply with the following requirements: (a) Provide adequate drinking water
supply for the work camps in appropriate tanks/containers. The Contractor will identify
appropriate public water source for drinking in consultation with the local authority; (b)
in case no appropriate source of water is identified, the Contractor will take water from
other sources which will be tested and treated before supplied to the work camps; (c) All
water supply and storage areas must be away from the wastewater storage area, drainage
system or other sources of contamination according to the regulations. Water from
drains or contaminated water must not be used as domestic water at the site.
At all construction sites, facilities for washing and necessary and appropriate tools must
be provided by the Contractor. Bathrooms must be provided separately for male and
female workers. Such facilities must ensure convenience for use and cleaning.
Waste discharges, wastewater must be properly collected and disposed off.
First aid/Emergency aid kit. The first/emergency aid kit must be available at the work
camp area and managed by a responsible person. This person must be trained on
emergency/first aid. Injured or seriously sick people must be taken to the nearest
hospital.
Community relations. The Contractor will ensure that conflicts between the workers and
local population are avoided.
(ii) Construction stage:
Work camps must be kept clean and tidy, unaffected by oil spill and construction wastes.
Any oil spilt or leaked must be cleaned immediately to avoid soil and water
contamination. Some actions to carry out are as follow: (a) avoid oil leakage into surface
water or groundwater; (b) wastewater must not be disposed directly to natural water
areas; (c) solid waste materials are removed and discharged in prescribed places at
frequent intervals; (d) First/Emergency aid supplies and materials and cleaning tools are
regularly provided.
Environmental and Social Management Framework (ESMF) Viet Nam Natural Hazards Management Project (Vn-Haz/WB5)
61
PPMU will monitor the housekeeping of work camp areas and ensure these areas are
kept clean throughout the construction period.
(iii) Construction completion.
During this stage, all work camps and facilities will be cleared away and removed from
the site. The site will be rehabilitated to ensure the operation of the works.
5.4 Management of Stockpiles, Quarries, and Borrow Pits
24. Commercial quarries and borrow pits approved by local environmental agencies should
be used as much as possible. If non-commercial quarries and/or borrow pits are used, in
consultation with the Construction Management Consultant (CSC) and/or field engineers, the
Contractor will comply with the following requirements:
Large-scale borrow pits or stockpiles will need site-specific measures that go beyond
those required in this ECOP.
All locations to be used must be previously identified in the approved construction
specifications. Sensitive sites such as scenic spots, areas of natural habitat, areas near
sensitive receptors, or areas near water should be avoided.
An open ditch shall be built around the stockpile site to intercept wastewater.
Stockpile topsoil when first opening a borrow pit and use it later to restore the area to
near natural conditions.
If needed, disposal sites shall include a retaining wall.
If the need for new sites arises during construction, they must be pre-approved by the
responsible local authorities.
If landowners are affected by use of their areas for stockpiles or borrow pits, they must
be included in the project resettlement plan.
For any stockpile, quarry, or borrow pit sites involved in this project, but not to be used
afterwards. The contractor will prepare and implement a Contract Specific
Environmental Plan (CSEP) in compliance with the ECOP that includes management of
borrow pits and their closure plans.
If access/rescue roads are needed, they must have been considered in the environmental
assessment. The alignment for each of these roads must be clearly determined with its
impacts and mitigation measures.
5.5 Management of Dredging
25. Some of the Component 4 subprojects may involve maintenance dredging of existing
river mounts/coastal area in relation to construction of safe harbor for fishing boats. For these
subprojects, a dredge material disposal plan (DMDP) will be prepared by the project owner
during the preparation of an EMP or detailed design stage as appropriate. The DMDP will
describe the amount of dredge materials and its potential contamination during dredging and
disposal as well as the mitigation measure to be carried out during dredging and disposal
process. The Contractor will be required to strictly follow the DMDP as well as to make all
efforts to avoid and/or minimize potential negative impacts on local use of land, beaches, and/or
Environmental and Social Management Framework (ESMF) Viet Nam Natural Hazards Management Project (Vn-Haz/WB5)
62
water especially impact on local fisheries. Details will be prepared as part of the Contract
Specific Environmental Plan (CSEP) given due attention to address the following issues:
Pollution control during the transport of the dredged materials from the dredging site to
the disposal area;
Potential increase in turbidity and pollution of the water in the areas due to the dredging
and potential impacts on other nearby beneficial uses;
Potential contamination of soil and water source including groundwater nearby the
disposal area; and
Potential misuse of the contaminated dredged materials for public infrastructure and
households.
26. The assessment of dredged materials must be based on quantitative methods based on
sampling and analysis/testing (such a toxicity characteristics leachate procedure-TCLP for
hazardousness), and the determination of the use of the dredged materials should be conducted
in light of these test results, considering the legal requirements for potential end uses.
5.6. Monitoring of Potential Impacts
27. The Contractor will be required to carry out the following monitoring program and a
monitoring plan will be included as part of the CSEP:
IMPACT PARAMETERS EXAMPLE LOCATIONS FREQUENCY
Air emissions
Dust level Vicinity of
clearing works
In windy
conditions
Noise and
vibration
generation
Noise levels to meet
TCVN/QCVN
requirements
In the vicinity of
sensitive receivers
In response to
complaints
Erosion and
sedimentation
Efficiency of erosion
and sediment controls
Erosion and
sediment controls
After heavy rain
events
Surface water
quality
deterioration
TSS, pH, BOD,
salinity, coliform
Upstream and downstream of
dredging and/or construction
works, especially when other
beneficial uses (aquaculture,
water supply sources, etc.)
are located.
Regularly during
construction works
Environmental and Social Management Framework (ESMF) Viet Nam Natural Hazards Management Project (Vn-Haz/WB5)
63
Annex 3: Scope for an EMP Preparation
1. This annex provides technical guidelines for preparing the EMPs to be submitted to
World Bank, including guidelines for consultation and information disclosure. Preparation of a
Dam Safety Report for large dam and a Dam Safety Inspection Report for small dam as required
by DSF and the water quality monitoring are considered as part of the EMP for the subproject.
I. EMP Outline
2. Below provide a sample outline of an EMP for the subprojects to be implemented under
Component 4.
Executive summary
1. Introduction - provide brief but concise information on objective of the EMP and its
connection with the ESMF and the Project
2. Policy, regulations, and institutional frameworks
2.1 GOV’s regulations - provide brief description of GOV regulations related to EIA
and standards applied for the subproject
2.2 WB’s safeguard policy – list WB policy triggered
3. Project description – provide description of the subproject including location maps
showing location in the project area as well as details at the subproject level. This is to
provide reader who is not familiar with the area to understand the issue clearer. For
the subproject involving dam/reservoir safety and/or upgrading/construction of coastal
infrastructure, scope of the new activities should be clearly defined in relations to
existing condition. For the subproject related to dam safety a Dam Safety Report (for
large dam) or a Dam Safety Inspection Report (for small dam) will be prepared
separately.
4. Environmental background – provide key information on the environmental
background of the subproject as well as its connection with the project area, including
maps. Focus should be given to provide clear data on topography, major land use and
water uses, water flow and water quality, and natural hazard and emergency response
in the subproject area. Brief description on socioeconomic condition and ethnic minority
should also be provided. For the subproject involving dam safety, background
information regarding existing dam design, instruments, and performance as well as
potential risk associated with dams breach should be provided in line with the Dam
Safety Report or Dam Safety Inspection Report. For the subproject involving dredging of
the river mouth and/or construction of coastal infrastructure, background information
regarding existing land/water use along the coastline and coastal erosion should be
provided.
5. Potential impacts and mitigation measures – provide results of the safeguard
screening following the criteria in the ESMF, identify potential impacts (positive and
negative) and mitigation measures; the impacts should be described for pre-
construction, construction, and operation phases; using a matrix format could help
understanding connection between the impacts and mitigation better. For the
Environmental and Social Management Framework (ESMF) Viet Nam Natural Hazards Management Project (Vn-Haz/WB5)
64
subproject involving dam safety, the impact assessment should also include risks
associated with dam breach and adequacy of existing instruments and inspection
procedures and/or capacity while the mitigation measures should be proposed in line
with the Dam Safety Report or Dam Safety Inspection Report. For the subproject
involving dredging of the river mouth and/or construction of coastal infrastructure, the
impacts assessment and mitigation measures should also include the impacts on existing
land/water use along the coastline and coastal erosion.
6. Actions to be carried out under the subproject – explain the mitigation measures and
agencies responsible for the implementation during preconstruction, construction, and
operation stages of the subproject. Details on the ECOP, dam safety measures, and/or
water quality monitoring could be provided as an annex if appropriate in line with the
Dam Safety Report or Dam Safety Inspection Report. For the subprojects involving
dredging at the river mouth and/or upgrading/construction of infrastructure along the
coastline a study on the potential impacts on other land/water users and coastal erosion
will be carried out and the required mitigation measures be included as part of the
EMP.
7. Implementation arrangement – explain responsible agencies (including their capacity
to carry out the activities identified in the EMP and the need for training),
implementation schedule, cost estimate, and how the EMP will be integrated into the
subproject, including state explicitly that the ECOP will be included in the bidding
documents of contractors.
8. Consultation and information disclosure – provide summary on consultation activities
and stakeholders on the EMP at subproject level (This can be combined with RAP) and
concerns raised and responses. Locations and dates of EMP to be disclosed should be
provided (see guidelines below).
II. Consultation and Information Disclosure
3. Consultation. The WB requires that for project category B at least one consultation with
the local actors, including the community will be carried out. This consultation should provide
information on the following aspects: a) purposes of the project; b) results of the environmental
evaluation; and c) presentation of the complementary studies required in the case that they
apply. The results should be presented in the EMP report. Consultation through a community
outreach or relations program during implementation is considered a good practice to ensure
that the potential negative impacts and concerns are properly addressed during construction and
operation of a project. Details on consultation can be found in the guideline for consultation in
investment lending (Consultations in Investment Lending: Guidance Note, World Bank March
2010). Extensive consultation with affected population and ethnic minority are required when
the activities involve relocation, land acquisition, and ethnic minority.
4. Information disclosure. Disclosure of safeguard documents is required throughout the
project cycle. All the RAPs, EMDPs, and EMPs will be made available to the public in the local
languages. Disclosure of information in advance of at least 60 days before construction is
considered a good practice.
Environmental and Social Management Framework (ESMF) Viet Nam Natural Hazards Management Project (Vn-Haz/WB5)
65
III. Preparation of a DMDP
5. For the subproject that involves dredging, preparation of a Dredge Materials Disposal
Plan (DMDP) will be required during the preparation of an EMP and/or detailed design. The
DMDP will cover the following aspects:
Identifying water users that may be affected by the dredging, including water quality
monitoring plan that could be used to monitor the potential impacts. Priority should be given
to monitor the areas that are sensitive to change in water quality (high suspended solid (SS),
high BOD or COD, high salinity, etc.) especially where the water is used for recreation
purposes and/or aquaculture production.
Identifying the available land for disposing the dredged materials. The plan should also
identify the possible lands to be appropriated for the disposal of dredged materials. Public
land, land for construction of rural roads, public works, private land, etc. may be used, with
an agreement with the project affected households. It should also meet local plans for land
use. The identified land should be large enough to accommodate the detailed estimated
amount of the dredged materials. The selected disposal land should be located at least 1 km
from any Bird Sanctuary or protected sites, at least 200 m from public works (schools,
administrative offices, and markets), temples and churches, and at least 200 m from
aquaculture farms.
Preparing for a transportation plan. In case, the dredge disposal area is far away from the
dredged sites, the DMDP shall set out a transportation plan including: (a) methods of
transportation (pipeline, barges, hopper barges) and uploading to the disposal area. If trucks
are used, indicate proposed route of the transport from the dredged site to the disposal area,
(b) time of operation, (c) type of vehicles/trucks and proposed measures to reduce the
leakage of the dredged materials from the transport trucks, (d) contractors’ responsibilities
for cleaning the roads and carry out remedial works if necessary, and (e) a communication
plan for the nearby communities including contact number for possible complaints.
Plan for managing the disposal site including: (a) plan for reducing the drainage (refer the
next bullet), (b) construction of the perimeter dykes, (c) construction of sub-containment
area, if applicable, (d) planned thickness of the dredged materials (typically less than 1.5
meters), (e) any measures to protect ground water and soils (e.g., installation of PVC
membrane).
Designing the Draining for Disposal lands. As the dredged materials are in the state of mud
at first and soil particles are suspended for 24 to 48 hours. All drainage water from disposal
land shall be driven to the drains and discharged back to the river. In order to limit the
negative impacts of mud (produced by dredging) on the environment as well as the water
quality of river and coastal areas, the dredged sediment will be transported to a containing
area which is appropriately located and properly design with an adequate size. The dredged
spoil will be pumped to the disposal land and then overflow to a settlement pond, where
turbidity and total suspended solids are settled. After some time, effluent is returned to the
river and coastal water.
A typical design of the dike around each disposal may be as follows: Height: 2m, Footing
width: 5 m, and Surface width: 1m. The plan should set out a basic layout.
Environmental and Social Management Framework (ESMF) Viet Nam Natural Hazards Management Project (Vn-Haz/WB5)
66
Identification of the disturbance on local businesses and transportation. The DMDP shall
carry out an inventory analysis on the possible affected local businesses, access to water,
and transportation (mainly due to the dredging) and provide a plan to compensate the
disturbances of the businesses (through the respective RAPs) and make a plan for
constructing temporary bridges. If access to water is affected for some households by the
disposal of the dredged materials, a plan to provide alternative access to water shall be
included in the DMDP.
Monitoring the Disposed Dredged Materials. A plan for monitoring the dredged materials as
well as water quality of effluent would be required. As stated before, an intensive
monitoring would be required if the dredged materials contains higher content of the heavy
metals and other harmful materials than the national thresholds.
In order to mitigate the issue of turbidity during dredging operation, the DMDP shall set out
dredging equipment and/or techniques suitable to the particular site. On laying dredging
machines on a barge, contractors can use a proper mud–stopping net for enclosing the
dredging site and keeping back mud on land, not to let it goes back to the river and coastal
water. If the disposal site for dredge materials is located far away from the dredger, a
suction dredger should be used to transfer all the mud and soil in water to the disposal sites.
The length of dredging sections should be limited less than 1 km and the dredging should be
done one by one.
IV. Preparation of a study for coastal erosion
6. Given that construction of solid infrastructure along the coast could significantly change
the near shore current and sediment transport pattern, a quick assessment of potential impacts on
coastal erosion in nearby area should be conducted if the subproject involves construction
and/or upgrading of existing structure for the purpose of erosion protection and/or storm
protection. The study will be conducted by a group of qualified consultants.
Environmental and Social Management Framework (ESMF) Viet Nam Natural Hazards Management Project (Vn-Haz/WB5)
67
Annex 4: Simple Environmental Code of Practices (ECOP) for Small Works
1. This ECOP comprises three parts: Prohibitions; “Chance Find” procedures, and Good
environmental and housekeeping practices. It will be applied for the Project activities to be
implemented under Components 1, 2, 3 that are involved civil works. The ECOP will be
included in the bidding document and/or agreement with local communities as appropriate.
Monitoring of the ECOP implementation at the subproject level will be responsible by PPMU
while that at Project level will be responsible by CPMO. Results will be included in the
subproject and/or Project progress reports.
I. General provisions
1. Preconstruction stage
- Design drawings. Prior to commencement of construction, the project owner should
develop design drawings. The design should be based on examination of land boundaries
and the quality of the ground planned for construction or on the construction survey
report, if any, and results of examination of the conditions of adjacent and neighboring
works; complying with construction technical regulations, technical standards and other
relevant laws; and assuring safety for the construction without adversely affecting
adjacent and neighboring works.
- Prior to commencement of construction, the project owner must inform the Commune
and Ward People’s Committees of the place of construction within 7 working days, as
well as adjacent and neighboring project owners.
2. Construction stage
- The construction must guarantee work quality, labor safety and environmental
sanitation; comply with provisions of the construction permit; and does not adversely
affect adjacent and neighboring works. Especially, mitigation measures for noise, dust,
vibration, scraps and wastes, etc. must be strictly complied.
- The project owner may assign each job to each contractor. Agreement between the
project owner and contractors shall be made in written construction contracts, especially
for construction surveyors, work construction designers and builders.
3. Construction completion
- On completion of the works the project owner or the Contractor will clear away and
remove all materials and rubbish and temporary works of every kind. The site will be
left clean and in a condition to the satisfaction of the PPMU
II. Good Environmental and Housekeeping Practices
4. This practice is intended to minimize the potential negative impacts during construction for
small civil works given attention to address the issue related to human and environmental
safety and minimize disturbance of local residents. The Contractor will strictly implement
the following practices as relevant to the activities and locations of works:
DO:
- Limited working hour during the day time, especially in residential areas, and
control driving speed;
- Minimize earth excavation and dispose spoils in designated areas;
Environmental and Social Management Framework (ESMF) Viet Nam Natural Hazards Management Project (Vn-Haz/WB5)
68
- Minimize opening of new borrow pits and ensure leveling and re-vegetation of the
affected areas;
- Minimize traffic congestion, dust and noise generation;
- Proper maintenance of construction equipment and vehicles;
- Provide appropriate safety sign (day and night) and closely inform local residents;
- Avoid spill of used oil and other toxic materials, including safe transportation and
storage;
- Apply good housekeeping in the construction and/or storage sites to ensure safety of
workers and peoples
- Ensure access to clean water and latrines by workers and provide mosquito net.
- Avoid social/cultural conflict between workers and local population.
DO NOT:
- Do not permit rubbish to fall freely from any locations of the project and/or access
by animals (dogs, cats, pigs, etc.). Use appropriate containers.
- Do not throw tools or other materials.
- Do not raise or lower any tool or equipment by its own cable or supply hose.
- Use grounding straps equipped with clamps on containers to prevent static electricity
buildup.
- Do not allow hunting of animals by workers in protected areas.
SPECIAL NOTE ON FLAMMABLE/EXPLOSIVE MATERIALS:
- Store flammable or explosive materials such as gasoline, oil and cleaning agents
apart from other materials.
- Keep flammable and explosive materials in proper containers with contents clearly
marked.
- Dispose of greasy, oily rags and other flammable materials in approved containers.
- Store full barrels in an upright position.
- Store empty barrels separately.
- Post signs prohibiting smoking, open flames and other ignition sources in areas
where flammable and explosive materials are stored or used.
- Store and chain all compressed gas cylinders in an upright position.
- Mark empty cylinders and store them separately from full or partially full cylinders.
- Ventilate all storage areas properly.
- Ensure that all electric fixtures and switches are explosion proof where flammable
materials are stored.
Environmental and Social Management Framework (ESMF) Viet Nam Natural Hazards Management Project (Vn-Haz/WB5)
69
III. Prohibitions
5. The following activities are specifically prohibited:
- Cutting of trees for any reason outside the approved construction area or poaching of
any description; Explosive and chemical fishing;
- Spillage of potential pollutants, such as petroleum products; Burning of wastes
and/or cleared vegetation outside the project area; Indiscriminate disposal of rubbish
or construction wastes or rubble; and
- Disturbance to anything with architectural or historical value; Use of firearms
(except authorized security guards); Use of alcohol by workers in office hours;
Driving in an unsafe manner in local roads; Creating nuisances and disturbances in
or near communities.
IV. “Chance find” Procedures
6. If the Contractor discovers archeological sites, historical sites, remains and objects,
including graveyards and/or individual graves during excavation or construction, the
Contractor will carry out the following steps:
- Stop the construction activities in the area of the chance find;
- Delineate the discovered site or area;
- Secure the site to prevent any damage or loss of removable objects. In cases of
removable antiquities or sensitive remains, a night guard shall be arranged until the
responsible local authorities or the National Culture Administration take over;
- Notify the supervisory Project Environmental Officer and Project Engineer who in
turn will notify the responsible local authorities and the Culture Department of
Province immediately (within 24 hours or less);
- Responsible local authorities and the Culture Department of Province would be in
charge of protecting and preserving the site before deciding on subsequent
appropriate procedures. This would require a preliminary evaluation of the findings
to be performed by the archaeologists of National Culture Administration. The
significance and importance of the findings should be assessed according to the
various criteria relevant to cultural heritage; those include the aesthetic, historic,
scientific or research, social and economic values;
- Decisions on how to handle the finding shall be taken by the responsible authorities
and Culture Department of Province. This could include changes in the layout (such
as when finding an irremovable remain of cultural or archaeological importance)
conservation, preservation, restoration and salvage;
- Implementation for the authority decision concerning the management of the finding
shall be communicated in writing by relevant local authorities; and
- Construction work could resume only after permission is given from the responsible local
authorities or Culture Department of Province concerning safeguard of the heritage.
Environmental and Social Management Framework (ESMF) Viet Nam Natural Hazards Management Project (Vn-Haz/WB5)
70
Annex 5. Safeguard Screening and Key Impacts of Component 4 Subprojects
A5.1 Key Impacts of the First Year Subprojects
1. Tables A5.1-5.2 summarize results of the safeguard screening and impacts assessment of
the first year subprojects. The subproject specific EMPs have been prepared and will be
submitted to WB for public disclosure and clearance. The safeguard screening and identification
of key impacts for the follow-on subprojects will be carried out during Project implementation.
A5.2 Key Impacts of the Follow-on Year Subprojects
2. Table A5.3 summarizes results of preliminary safeguard screening and impacts
assessment of potential subprojects for the follow-on years. The screening and assessment are
done based on investment items of the subproject and information provided by the province.
They could be changed during EMPs preparation.
Environmental and Social Management Framework (ESMF) Viet Nam Natural Hazards Management Project (Vn-Haz/WB5)
71
Table A5.1: Results of Safeguard Screening for the First Year Component 4 Subprojects
No. Subproject name Investment Items
Type of
works River
basins
Potential negative
impacts per the
screening criteria
indicated in Table 5.1
Safeguard
document
prepared
GOV EIA
requireme
nt
I. Thanh Hoa
1 Maintain, upgrade and
treat the key parts of the
left dyke of Cau Chay
river (section from K0-
K42), Yen Dinh district
Upgrade 42 km dyke site;
Renew structures on the site;
build more rescue roads
Dyke/
road
Ma River (1), (3), (4), (5), (8) RAP, EMP EIA
II. Nghe An
2 Upgrade dyke site of
Lương Yen Khai Line, widen, stabilize the surface
2.87 Km
Dyke/
road
Ca River (1), (4), (5), (8) RAP, EMP EIA
3 Bridge combining with
overflow connecting
rescued roads, Nghi Loc
and Vinh city
65m bridge combining with
overflow and 1 Km road and a
drain sluice with B=7.5 m
Dyke/
road
Ca River (1), (5) RAP,EMP
III. Ha Tinh
4
Upgrade dyke site Phuc
Long Nhuong, Cam
Xuyen district
Upgrade dyke site of 11.41 km;
Renew 21 drainage sluices
crossing the dyke; build 12 road
sites combining with dyke
rescue with the total length of
8.974 km
Dyke/
road
Ha Vang-
Rac River (1), (3), (4), (5), (8) RAP, EMP EIA
VII. Quang Nam
5 Repair, upgrade Thach Main dam, overflow, intake Dam Thu Bon (1), (4), (5), (6), (7), RAP, EMP EIA
Environmental and Social Management Framework (ESMF) Viet Nam Natural Hazards Management Project (Vn-Haz/WB5)
72
Ban reservoir, Duy
Xuyen district gate, management house and
road River (8)
IX. Binh Dinh
6
Upgrade anti-erosion
embankment of Kone
river for safety, An
Nhon and Tuy Phuoc
district
(i) 1.2 km Thang Cong section –
Nhon Phuc commune
(ii) 1.5 km Song Ngheo section
– Nhon Hau commune
(iii) 1.8 km Tam Dan – Tan
Duong section – Nhon An
commune
(iv) 1.3 km embankment in the
downstream of Ba Di bridge –
Phuoc Loc commune
Dyke/
road
Kone River (1), (3), (5) RAP,EMP EIA
*Note: (1) Involve land acquisition and/or resettlement, (2) involve ethnic minority, (3) involve PCR, (4) involve UXO risk; (5) involve civil works;
(6) involve dredging; (7) involve dam safety; (8) likely to involve land/water use conflicts; (9) involve river mouth construction.
Environmental and Social Management Framework (ESMF) Viet Nam Natural Hazards Management Project (Vn-Haz/WB5)
73
Table A5.2: Potential Negative Impacts of the First Year Component 4 Subprojects
Components Physical Biological Socio Others Remarks
Air,
noise,
vibrati
on
Land,
soil,
water
Solid
waste,
Sludge
Forest,
natural
habitat
s
Fish,
aquatic
life
Land
acquisi
tion,
resettle
ment
Indigen
ous
peoples
Physical
cultural
resource
s
Livelih
ood,
comm
unity
disturb
ance
Local
flood,
traffic,
safety
Off-
site
impact
s
Subproject 1: Maintain, upgrade and treat the key parts of the left dyke of Cau Chay river (section from K0-K42), Yen Dinh district (Thanh Hoa) (240 bil. VND);
Scope include: upgrade 42km dyke site; Repair, upgrade and renew structures on the site, including construction of sluices; build more rescue roads
Background/Key issues: [ protect property and life of 130,000 people; protect 10,000 ha agricultural land and ensure the safety for infrastructures; build the rescue
road to boost the socio-economic development for 25 communes in Yen Dinh district] [781 affected HHs, of which 18 HHs lose more than 20% of productive land;
04 HHs have to relocate graves; 43 HHs are in vulnerable group (18 poor HHs, 20 FHHs); [1 million cubic meters will be excavated and dyked; dust and noise in
construction phase]
Pre-const. L L L N L H N L M L L - Ensure effective implementation of
ECOP and consultation with local
residents Construction M M M N L N N L M M M
Operation N N N N N N N N M L N - Ensure effective O/M; Build capacity of
local community with high risks through
Component 3 implementation
Subproject 2: Upgrade dyke site of Luong Yen Khai (Nghe An) (45 bil VND): Scope includes (Line, widen, stabilize the surface of 2.87km) Background/Key issues: [protect life and property for 10.756 inhabitants and maintain production stability for 651.8 ha of agricultural land]; [83 affected HHs, of
which 80 HHs lose their agricultural land, 03 HHs lose adjacent garden to their residential land, affected land is 13,300 m2];[ 186,314.98 m
3 soil will be excavated
and dyked; dust and noise in construction phase]
Environmental and Social Management Framework (ESMF) Viet Nam Natural Hazards Management Project (Vn-Haz/WB5)
74
Pre-const. L L L N L H N L M L L - Ensure effective implementation of
ECOP and consultation with local
residents Construction M M M N L N N L M M M
Operation N N N N N N N N M L N - Ensure effective O/M; Build capacity of
local community with high risks through
Component 3 implementation
Subproject 3: Bridge combining with overflow connecting rescued roads, Nghi Loc and Vinh city (Nghe An) (27 bil. VND);
Scope includes 65m bridge combining with overflow and 1Km road and a drain sluice with B=7.5m
Background/Key issues: [improve the economy and reduce poverty for about 13,709 people in Hung Hoa and Nghi Thai communes by increasing access ability to
the administrative centers, market centers, health care, education and social services, reducing the time and cost for agricultural products transportation];[5
affected HHs, earth fill K95 7,940 m3, mud dredging 687m
3, dust and noise in construction phase ].
Pre-const. L L L N L H N L M L L - Ensure effective implementation of
ECOP and consultation with local
residents Construction M M M N L N N L M M M
Operation N N N N N N N N M L N - Ensure effective O/M; Build capacity of
local community with high risks through
Component 3 implementation
Subproject 4: Upgrade dyke site Phuc Long Nhuong, Cam Xuyen district (Ha Tinh) (180 bil VND); Scope include: upgrade dyke site of 11 km; Renew 21 drainage
sluices crossing the dyke; build 12 road sites combining with dyke rescue with a total length of 8.974 km.
Contract arrangement?
Background/Key issues: [Preventing and reduction of disaster damage by storm, tropical depression, storm surges occur frequently in direct of 19,728
persons/2,471 ha of Thien Cam town, Cam Phuc, Cam Nhuong communes and indirect of 12,450 persons/1,345ha of Cam Xuyen town and Cam Thang commune.];
[335 affected HHs, of which 125 households will lose agricultural land, 119 households will lose house-stage garden, 22 households will lose aqua-cultural land,
and 44 households will lose residential land]; [excavation soil 90,000 m3; dust and noise in construction phase]
Pre-const. L L L N L H N L M L L - Ensure effective implementation of
ECOP and consultation with local
residents Construction M M M N L N N L M M M
Operation N N N N N N N N M L N - Ensure effective O/M; Build capacity of
local community with high risks through
Component 3 implementation
Subproject 5: Repair, upgrade Thạch Ban reservoir, Duy Xuyen district (Quang Nam) (86 bil VND); Scope includes: Main dam, overflow, intake gate,
management house and road
Background/key issues:[ reduce the vulnerability due to the external factors such as drought, floods and erosion, flood control issues will be enhanced, protect more
than 10,000 people in two communes (Duy Phu, Duy Thu), protect infrastructure such as houses of citizens, clinics, post offices, markets, kindergartens, primary
schools, secondary schools, inter-village transportation system and electricity]; [7 affected HHs in Duy Thu commune have temporary acquisition of 2 ha forest
Environmental and Social Management Framework (ESMF) Viet Nam Natural Hazards Management Project (Vn-Haz/WB5)
75
land]; [150,000 m3 of fill-land, 1,748.05 m
3 of stone, 11,271.84 m
3 of sand and gravel are needed for the construction; Air, noise and water pollution]
Pre-const. L L L N L H N L M L L - Ensure effective implementation of
ECOP and consultation with local
residents Construction M M M N L N N L M M M
Operation N N N N N N N N M L N -To ensure effective O/M; Build capacity
of local community with high risks
through Component 3 implementation
Subproject 6: Upgrade anti-erosion embankment of Kone river for safety, An Nhon and Tuy Phuoc district (Binh Dinh) (47 bil. VND); Scope include (i) 1,2 km
Thang Cong section – Nhon Phuc commune; (ii) 1,5km Song Nghẹo section – Nhon Hau commune; (iii) 1,8km Tam Dan – Tan Duong section – Nhon An commune;
(iv) 1,3 km embankment in the downstream of Ba Di bridge – Phuoc Loc commune.
Background, key issues: [Upgrading anti-flood and anti-inundation capacity for all of the dyke belong to Kone river dyke system aim to protect directly human,
infrastructure, land, house and property of 49,183 people (8,197 households) in 3 communes Nhon An, Nhon Hau, Nhon Phuc (An Nhon District) and Phuoc Loc
(Tuy Phuoc District)]; [73 affected HHs in 3 Ward PCs of Binh Dinh province, including: 16 HHs in Phuoc Loc Commune, 13 HHs in Nhon An Commune, 27 HHs
in Nhon Phuc Commune and 17 HHs in Nhon Hau Commune]; [45,092 m3 of excavation land and 66,673 m
3 of fill-land; Dust, noise, water pollution]
Pre-const. L L L N L H N L M L L - Ensure effective implementation of
ECOP and consultation with local
residents Construction M M M N L N N L M M M
Operation N N N N N N N N M L N - Ensure effective O/M; Build capacity of
local community with high risks through
Component 3 implementation
Note: The following criteria are used for the assessment of level of impacts: None (N) –no impact; Low (L) – Small works, minor impacts, localized, reversible,
temporary; Medium (M) –Small works in coastal/sensitive areas, medium scale works with moderate impacts of which most are reversible, reducible and
manageable, localized, temporary; High (H) –Medium scale works in coastal/sensitive area, large scale works with significant impacts (socially and/or
environmentally) of which many are irreversible and require compensation; Both M and H levels need implementation of the mitigation measures, monitoring, and
adequate institutional capacity on safeguard.
Environmental and Social Management Framework (ESMF) Viet Nam Natural Hazards Management Project (Vn-Haz/WB5)
76
Table A5.3: Results of Preliminary Safeguard Screening for potential subprojects for the follow-on years by provinces
No. Name of subproject Investment Items Type of
works
River
basins
Potential negative
impacts per the
screening criteria
indicated in Table 5.1
Safeguard
document
prepared
GOV
EIA
requirem
ent
Total 9 provinces
I. Thanh Hoa
II. Nghe An
1 Repair, Upgrade, ensure safety for
reservoirs Ban Muong, Cho Quan,
Xop Thap
Earthen dam; overflow; intake
gate and management house
Dam - Ca
River
(1), (2), (3), (4), (5),
(7), (8)
RAP
EMDP
EMP/DSR
EIA
2
Rescued road of Hung Nguyen
district (including Hung Lam,
Hung Nhan, Hng Xuan, Hung
Chau)
Line, widen, stabilize the road
surface 23.5 Km
Dyke/
road
Ca
River
(1), (3), (4), (5) RAP
EMP
EIA
3 Embankment protecting Ca River,
acrossing Dinh Son, district Anh
Son. 2 km embankment
Dyke/
road
Ca
River
(1), (3), (5) RAP
EMP
EIA or
EPC
4 Embankment protecting Ca River,
acrossing Linh Son, district Anh
Son. 2 km embankment
Dyke/
road
Ca
River
(1), (3), (4), (5) RAP
EMP
EIA or
EPC
5 Rescued road of Do Luong
district (including Thai Son, Minh
Son communes)
Line, widen, stabilize the road
surface 12 km
Dyke/
road
Ca
River
(1), (3), (4), (5) RAP
EMP
EIA
6 Upgrade dyke Vach Bac, district
Yen Thanh 9km dike
Dyke/
road
Ca
River
EIA
Environmental and Social Management Framework (ESMF) Viet Nam Natural Hazards Management Project (Vn-Haz/WB5)
77
7 Rescued road connecting national
road 46 to Thanh Luong - Nam
Hung.
Line, widen, stabilize the road
surface 11.5 km
Dyke/
road
Ca
River
(1), (3), (4), (5) RAP
EMP
EIA
III. Ha Tinh
8
Dredging, treating jet to Cua Sot
shelter, Loc Ha district
Dredge a jet with 4 km length;
build 300 m embankment, treat
flow; 2 km rescued roads, 1.5 km
embankment protecting harbors
and flood shelters
Coastal
structure
Ca
River
(1), (3), (4), (5), (6), (9) RAP
EMP
EIA
IV. Quang Binh
9 Fishing boat harbor in Nhat Le
river basin Boats anchoring structures; anti-
wave dike
Coastal
structure
Gianh
River
(1), (3), (4), (5), (6), (9) RAP
EMP
EIA
V. Quang Tri
10 Upgrade Trieu Thuong reservoirs
1 and 2 Upgrade main damp, flood
overflow, intake gate under damp
Dam Thach
Han
River
(1), (3), (4), (5), (7), (8) RAP
EMP/DSR
EIA
11 Repair and upgrade Hydraulic
Structures:
Viet Yen – Vinh Phuoc Upgrade sluice and sluice gate
Dam Thach
Han
River
(3), (5) EMP/DSR EIA or
EPC
12 Upgrade Phuoc Mon reservoir,
Hai Le commune Upgrade main dam, flood
overflow, sluice under dam
Dam Thach
Han
River
(3), (4), (5), (7), (8) EMP/DSR
EIA
13 Emergency anti- erosion
embankment for Nai Cuu – Trieu
Dong commune – Trieu Phong
district
Build 1.02 km river embankment
Dyke/
road
Thach
Han
River
(1), (3), (4), (5) RAP
EMP
EIA or
EPC
14 Embankment for Trieu Do
commune – Trieu Phong district Build 2.24 km river embankment
Dyke/
road
Thach
Han
River
(3), (4), (5) EMP
EIA
15 Emergency anti-erosion
embankment for Trieu Tai
commune – Trieu Phong district Build 1km river embankment
Dyke/
road
Thach
Han
River
(1), (3), (4), (5) RAP
EMP
EIA or
EPC
VI. Da Nang
Environmental and Social Management Framework (ESMF) Viet Nam Natural Hazards Management Project (Vn-Haz/WB5)
78
16
Upgrade ensure safety for Hoa
Trung reservoir
(i) Widen main overflow
(ii) Reinforce main dam
(iii) Equipments and management
house
(iv) Upgrade rescued road and
over flood bridge
Dam Vu Gia-
Thu
Bon
(1), (3), (5), (7), (8) RAP
EMP/DSR
EIA
17
Upgrade, widen flood drain for An
Trach weir
(i) Replace 12 old valvet gates by
12 flat valvet gates operating by
electricity
(ii) Widen 2 more drain section
(iii) Reinforce, upgrade
absorption yard
(iv) Equip controlling system
(v) Repair Ha Thanh dam
Dam Vu Gia-
Thu
Bon
(1), (3), (5), (8) RAP
EMP/DSR
EIA
18
Upgrade ensure safety for 4
reservoirs: Truoc Dong, Truong
Loan, Hoc Khe, Ho Cau
(i) Upgrade main dam
(ii) Upgrade & widen main
overflow
(iii) Widen auxiliary overflow
(iv) Repair intake gate
(v) Reinforce rescued &
management roads
Dam Vu Gia-
Thu
Bon
(1), (3), (5), (7), (8) RAP
EMP/DSR
EIA
19
Upgrade ensure safety for 2 small
reservoirs: Dong Treo and Ho
Thung
(i) Upgrade main dam
(ii) Widen, reinforce main
overflow
(iii) Repair auxiliary overflow
(iv) Repair intake gate
Dam Vu Gia-
Thu
Bon
(1), (3), (5), (7), (8) RAP
EMP/DSR
EIA
VII. Quang Nam
20 Repair, upgrade Khe Tan
reservoir, Dai Loc district Main dam, overflow, intake gate,
management house and road
Dam Vu Gia
River
(1), (2), (3), (4), (5),
(7), (8)
RAP
EMDP
EMP/DSR
EIA
Environmental and Social Management Framework (ESMF) Viet Nam Natural Hazards Management Project (Vn-Haz/WB5)
79
21 Build anti-erosion embankment
for Thu Bon river, Phu Da area,
Duy Xuyen district
Embankment’s body and foot
made of concrete slabs, length 1.5
km
Dyke/
road
Thu
Bon
River
(1), (3), (4), (5) RAP
EMP
EIA
22 Repair, upgrade Chan Son
reservoir, Dai Loc district
Main dam, overflow, intake gate,
management house and road,
electricity system
Dam Vu Gia
River
(1), (3), (4), (5), (7), (8) RAP
EMP/DSR
EIA or
EPC
23 Build river embankment for Tan
Binh village, Dien Trung
commune, Dien Ban district
Embankment’s body and foot
made of concrete slabs, length 1.5
km
Dyke/
road
Thu
Bon
River
(1), (3), (4), (5) RAP
EMP
EIA
24 Build anti-landslide embankment
for Bau Sau river, in the down-
stream of Bau Nit weir, Dien Ban
district
Embankment’s body made of
precast concrete, its foot made of
Ferro-concrete M200, length 1
km
Dyke/
road
? (1), (3), (4), (5) RAP
EMP
EIA or
EPC
VIII. Quang Ngai
25
Duc Loi dam Headwork dam
Dam Tra
Khuc–
Tra
Bong
River
(1), (2), (3), (4), (5),
(7), (8)
RAP
EMDP
EMP/DSR
EIA
26
Fishing boat harbor and My A sea
gates (phase 2)
Lengthen 180 m South dike Nam,
160 m North dike Bac to the
level of +6.0 m; Lengthen anti-
sand dike, flood prevention for
more than 120 m, crest level of
+3.2 m. Dredge and widen jet to
60 m. Logistic fishing structure,
shelters for fishermen and
technical structures
Coastal
structure
Tra
Khuc–
Tra
Bong
River
(3), (4), (5), (6), (9) EMP
EIA
IX. Binh Dinh
Environmental and Social Management Framework (ESMF) Viet Nam Natural Hazards Management Project (Vn-Haz/WB5)
80
27
Upgrade, repair overflow bridges
of rescued road Dong Tuy Phuoc
– An Nhon – Phu Cat
Upgrade 8 overflow bridges of
road DT640: Bridge # 15 in
Huynh Mai; Km14+310;
Km14+760; Km15+820;
Km16+620; Km17+080;
Km17+865;
and Bau Sao overflow bridge on
road DT636A
Dyke/
road
Kone
River
(1), (3), (4), (5) RAP
EMP
EIA
X. Ninh Thuan
28 Upgrade dyke at the north of Dinh
river
Upgrade the whole dike site to
protect Phan Rang – Thap Cham
city combining with traffic,
length of 11.1 Km
Dyke/
road
Dinh
River
(1), (2), (3), (5), (8) RAP
EMDP
EMP
EIA
*Note:
- (1) Involve land acquisition and/or resettlement, (2) involve ethnic minority, (3) involve PCR, (4) involve UXO risk; (5) involve civil works; (6) involve
dredging; (7) involve dam safety; (8) likely to involve land/water use conflicts; (9) involve river mouth construction.
- Results of Preliminary Safeguard Screening for potential subprojects for the follow-on years are done based on investment items of the subproject and
raw information provided by the province. They could be changed during EMPs preparation.
Environmental and Social Management Framework (ESMF) Viet Nam Natural Hazards Management Project (Vn-Haz/WB5)
81
Annex 6. Summary of Potential Impacts, Mitigating Measures; Monitoring, and Responsible agencies
Table A6.1. Potential Environmental and Social Impacts, Mitigating Measures; Monitoring, and Responsible agencies
Component 1 2 3 4 5
Key activities Strengthening
DRM institutions,
information
systems and
planning
Strengthening
weather
forecasting
and early
warning
systems
Community-based
disaster risk
management,
including non-
structural and
structural measure
investment (Multi-
purpose shelter,
feeder road, pumps,
drainage dredging,
…) participatory
process
Priority disaster risk mitigation investments
including upgrade existing and/or construct new
for dam, dyke, rescue roads, protection of coastal
erosion/storm surge)
There are 6 subproject in first phase and 28
subprojects in second phase (total 34 projects)
Project management
including safeguard
activities
Positive
impacts
Improve policy
and institutional
capacity at
national/basin
level
Improve
technical
capacity on
forecasting
Improve capacity at
community level
Improve infrastructure services and institutional
capacity at provincial level that contribute to
increase capacity at basin/sub-basin level
Reduction of human losses and property damage
Facilitation for socio-economic development and
improvement in living standards for local people
in the project areas
Raising community awareness and natural
disaster risk management capacity of different
levels
Improvement in quality of living environment
Strengthen safeguard
capacity of project
staff
Negative
impacts
- - Involve small works
that may require land,
involve EM, and
create impacts during
Involve small and medium size works in priority
areas;
Preparation stage: Impacts due to land
The project focus in
high risk areas (more
people, inadequate
infra, or protection of
Environmental and Social Management Framework (ESMF) Viet Nam Natural Hazards Management Project (Vn-Haz/WB5)
82
construction acquisition and resettlement of local people
including ethnic people, grave. The impacts will
be small to medium localized, and temporary,
and can be mitigated
Construction stage:
- Impacts due to civil works could temporary
increase levels of dust and other air pollution,
noise, vibration, water pollution, local traffic
volume, safety risk, and other impacts on local
residents and businesses to be small to moderate
(depending on size and type of works); The
impacts however will be small to moderate,
localized, and temporary, and can be mitigated.
- There are UXO risks during construction but
this risk is considered moderate and could be
mitigated.
Operation stage: Impacts during operation will
be positive however there are risk due to
dams/dyke/structure breach, coastal erosion or
land/water use conflicts
sensitive areas
(culture, habitats,
coastal, etc.); So
background
information should be
adequate to make
appropriate judgment
on level of impacts
and mitigation needs
-- EMP should
provide information
on institutional
arrangement and
capacity to deal with
disaster for each
subproject too
Mitigation The impacts should
be mitigated through
participatory
planning and
application of
standard ECOP for
small works –good
construction practices
Impacts on land acquisition, EM, grave will be
medium and will be mitigated via compensation,
etc. RPF, EMPF, subproject EMDPs and RAPs
are prepared.
Impacts due to civil works could be mitigated
via a standard ECOP for works. UXO risks
could be mitigated through an UXO examination
and clearance (as needed). ESMF and MPs are
prepared.
Impacts during operation could be mitigated via
the preparation of an emergency plan and
strengthen institutional capacity, of which
priority activities should be incorporated into
Environmental and Social Management Framework (ESMF) Viet Nam Natural Hazards Management Project (Vn-Haz/WB5)
83
Components 1 and 3. DSMF will provide
guideline on what should be done; priority
activities will be part of the EMP.
Monitoring Monitor/report on
safeguard
performance during
construction in terms
of land acquisition,
complaints
During construction:
Monitor water quality upstream and downstream
of the area where dyke construction is located
near rivers/water bodies, and/or sluice
construction is located; Air and other monitoring
should be made only when necessary.
The EMP team should
be able to identify
sensitive areas that
need to be monitored,
especially WQ based
on knowledge on the
project sites,
sensitivity of the area,
water users, and
consultation with the
people.
During operation: monitoring safety of
dams/dyke will be necessary and budget/capacity
of staff must be adequate. Monitoring result
should be submitted to WB on an annual basis
after completion of construction and one year
after completion of the project.
Training on
dams/dyke safety
monitoring should be
carried out during
implementation. This
can be part of
Component 1 and 3 or
be part of safeguard
training
Responsible
agencies/entiti
es
Each PPMU
implement and
include progress in
progress report;
CPMO/ESU/CEMC
monitor/report
Each PPMU implement and include progress in
progress report; CSC/field engineers are
responsible for day-to-day
supervision/monitoring/reporting
CPMO/ESU/CEMC monitor/report
Environmental and Social Management Framework (ESMF) Viet Nam Natural Hazards Management Project (Vn-Haz/WB5)
84
REFERENCES
1. Environment Protection Law No.52/2005/QH11 dated November 29th 2005, issued on
December 12th 2005, and became full effect on July 1st 2006.
2. Decree No.29/2011/ND-CP dated April 18th 2011 of the Government guiding the the
assessment of strategic environment, environment impact assessment and environment
protection commitment.
3. Circular No.26/2011/BTNMT dated July 18th 2011 of the Ministry of Natural Resources and
Environment guiding the assessment of strategic environment, environment impact assessment
and environment protection commitment.
4. The World Bank in Viet Nam, 2004, World Bank environment safeguard policies
5. The World Bank in Viet Nam, 2004, World Bank social safeguard policies.
6. Final draft report of Vn-Haz/WB5 Environment Assessment.
7. Final draft report of Vn-Haz/WB5 first year subprojects Environmental Impact Assessment.
8. Final draft report of Vn-Haz/WB5 first year subprojects Environmental Management Plan.
9. Final draft report of Vn-Haz/WB5 Resettlement Action Plan.