soil nailing - where when and why

27
8/13/2019 Soil Nailing - Where When and Why http://slidepdf.com/reader/full/soil-nailing-where-when-and-why 1/27

Upload: chinhow

Post on 04-Jun-2018

261 views

Category:

Documents


7 download

TRANSCRIPT

Page 1: Soil Nailing - Where When and Why

8/13/2019 Soil Nailing - Where When and Why

http://slidepdf.com/reader/full/soil-nailing-where-when-and-why 1/27

Page 2: Soil Nailing - Where When and Why

8/13/2019 Soil Nailing - Where When and Why

http://slidepdf.com/reader/full/soil-nailing-where-when-and-why 2/27

  1

SOIL NAILING: WHERE, WHEN AND WHY – A PRACTICAL GUIDE

Thomas J. Tuozzolo, P.E., M.ASCE1 

ABSTRACT 

Since its development in Europe in the early 1970s, soil nailing has become a widely accepted

method of providing temporary and permanent earth support, underpinning and slope

stabilization on many civil projects in the United States. In the early years, soil nailing was

typically performed only on projects where specialty geotechnical contractors offered it as an

alternate to other, conventional systems. More recently, soil nailing has been specified as the

system of choice due to its overall acceptance and effectiveness. However, although the

theoretical engineering aspects of soil nailing may be well understood, there is a far lesser degree

of understanding, even within the geotechnical community, as to the site conditions – where,

when and why – under which soil nailing should, and should not, be used. The purpose of this

 paper, therefore, is to offer experienced-based guidelines to owners, engineers, designers and

general contractors trying to decide if soil nailing is the right system for their project. Typical

soil nail details, procedures, design, monitoring and testing considerations, and case studies are

 presented as a tool to aid in making those decisions.

INTRODUCTION

Soil nailing is a method of providing temporary earth support and retention during excavation for

new construction. The technique is also used for construction of permanent retaining walls, slope

stabilization, underpinning, and protection of existing cuts (Tuozzolo, 1997).

The soil nailing concept was developed in Europe for the permanent and temporary stabilization

of natural slopes, for renovation of old retaining walls, and for repair of earth walls that had

 prematurely deteriorated. The first recorded application was in France in 1972. Soil nailing was

also used as temporary shoring for basement excavations and as permanent and temporary earth

support for excavations associated with railroads and tunnels (Chassie, 1993).

1 Vice President, Moretrench American Corporation,

100 Stickle Avenue, Rockaway, NJ 07866. Tel: 973.627.2100. [email protected]

Page 3: Soil Nailing - Where When and Why

8/13/2019 Soil Nailing - Where When and Why

http://slidepdf.com/reader/full/soil-nailing-where-when-and-why 3/27

  2

The first recorded use of soil nailing in the United States was in the mid 1970s as a method of

 providing temporary earth support during the construction of a new hospital (Chassie, 1993). The

major use of soil nailing in the United States to date has been for temporary excavation support

and earth retention during construction of buildings and other structures in urban areas.

FUNDAMANTAL CONCEPTS

Soil nailing is an economical, top-down construction technique that increases the overall shear

strength of unsupported soils in situ  through the installation of closely spaced reinforcing bars

(nails) into the soil/rock. Typically, a structural concrete facing (shotcrete) is sprayed against the

excavated earth face to connect the nails and reduce deterioration and sloughing. A common

misconception is that this structural facing is the major element of the soil nail system. In fact,

the nails do the work.

Soil nails are passive elements and, unlike tieback anchors, they are typically not mechanically

 pre-tensioned after installation. Rather, they become forced in tension when the soil they are

supporting deforms laterally as the depth of the excavation increases. Without soil movement,

the nails remain in a passive state. This is a fundamental difference between soil nails and

tieback anchors, and one that is commonly not examined closely enough or considered during

determination of proper use and monitoring.

The movements required to mobilize the nail forces are very small and generally correspond to

the movements that occurs in a braced system (Chassie, 1993). In some cases, specifications

require that the soil nails be tensioned and locked off, as a tieback would. This is not correct.

Some specifications even require production soil nails to have a free, or unbonded, length. This

is also not appropriate. In some cases, a small pre-tensioned load may be applied to limit the

amount of deflection of the soil that is required to mobilize the nail. However, a major post-

tensioning effort defeats the purpose and effectiveness of the nail. 

CONSTRUCTION METHODS

Soil nailing is a specialty geotechnical technique. Owners, specifiers and general contractors

should ensure that the work is designed and constructed only by firms with the requisite

experience.

Page 4: Soil Nailing - Where When and Why

8/13/2019 Soil Nailing - Where When and Why

http://slidepdf.com/reader/full/soil-nailing-where-when-and-why 4/27

  3

Typical Construction Sequencing and Components

•   Excavate in Lifts

The execution of soil nailing consists of making a 1.2 to 1.8 m (4 to 6 ft) vertical cut

extending for a horizontal length to be stabilized and shotcreted the same day. The verticalcut may need to be reduced or other measures may have to be considered if the face

stability of the soils is of concern. Typically, the cut is made to 0.3 to 0.8 m (1 to 2.5 ft)

 below the elevation of the soil nails so that a suitable bench can be established for the

installation of the nails at the proper angle.

Usually, mass excavation is performed on the project with relatively large earth moving

equipment. Smaller equipment may have to be utilized to provide the necessary face

trimming prior to installation of the soil nail wall. It is important that excavation of lifts is

 performed in a controlled manner so that over-excavation of the face, and sloughing of the

soils, does not occur. After the lift has been excavated to the proper elevation, a level

work area, or bench, is constructed in front of the wall to accommodate the drilling

equipment. Depending on the type of equipment used, this bench can be as small as 3 m

(10 ft) or as large as 12 m (40 ft), although 7.5 m (25 ft) is usual.

•   Install Nail

Typically, the next step is to install the soil nails.  It is important to note that the shotcrete

can be applied prior to installing the nails if there is a concern with the standup time of

the soil and the possibility of sloughing of the soil. In the United States, common practice

is to use rotary and rotary/percussion drill rigs for the installation of the nail, although it is

quite common to utilize augers in cohesive soils. In Europe, some contractors utilize

machines to drive the soil nails into the ground (launched nails). Soil nails are typically

installed on a 1.2 to 1.8 m (4 to 6 ft) horizontal and vertical grid pattern, with the drill hole

inclination being 10 to 20 degrees from horizontal. The holes are either cased or uncased,

depending on the type of soil and are, on average, 100 to 200 mm (4 to 8 in) in diameter.

Once the hole is drilled, the nail is installed and the hole is tremie-grouted with either type

I, II, or III Portland cement and water. The water/cement ratio is normally on the order of

0.45 to 0.50. In the United States, it is common to use No. 25 to No. 36 (No. 8 to No 11),

Page 5: Soil Nailing - Where When and Why

8/13/2019 Soil Nailing - Where When and Why

http://slidepdf.com/reader/full/soil-nailing-where-when-and-why 5/27

  4

Grade 400 or 500 (Grade 60 or 75) threaded bar as the nail. The bar is centered in the drill

hole by means of plastic centralizers spaced every 3 m (10 ft) along the length of the bar,

as shown in Figure 1. The length of the bar is based on the design, but a common rule of

thumb is that the length of the first level of nails is typically 0.6 to 1 times the overall cut

height. Soil-to-grout bond values are used in the design to determine the final length of the

nail and the nail spacing.

Figure 1: Typical Temporary Soil Nail Cross-section

•  Place Reinforcing & Drainage

Once the excavation is made and the soil nails are installed, reinforcing material, typically

a welded wire mesh, may need to be placed along the face of the excavation to reinforce

the concrete facing. It is not uncommon, however, to use reinforcing bars for the length of

the wall in lieu of the wire mesh. As an alternate to placing the reinforcing prior to

shotcreting, the reinforcing material can actually be added to the ready-mix concrete at the

 plant. This is known in the industry as fiber-reinforced concrete. Some common types of

reinforcing material are steel or synthetic fibers.

When the bearing plate and nut are installed and the nail becomes loaded as the soil

deforms, this load is transmitted to the shotcrete facing. Because of this, it is important to

ensure that the facing can handle the punching shear induced from the nail load. It may be

necessary to strengthen this area directly behind the bearing plate with reinforcing. A

typical punching shear detail is shown in Figure 2.

1 ft = 0.3048 m

1 in = 25.4 mm

Page 6: Soil Nailing - Where When and Why

8/13/2019 Soil Nailing - Where When and Why

http://slidepdf.com/reader/full/soil-nailing-where-when-and-why 6/27

  5

 

Figure 2: Typical Punching Shear Detail

If drainage behind the soil nail wall is a concern, a prefabricated geotextile drain mat, typically

0.6 m (24 in) wide, can be applied in strips to the excavated earth face of the wall between the

nails prior to applying the shotcrete facing (Figure 3). In most cases, drainage material is notinstalled for temporary soil nail walls unless drainage is a major concern. For permanent walls,

the drainage material is extended from the top of the excavation to the bottom of the excavation

and tied into a drainage collection system at the bottom of the wall. If perched water is

encountered during construction, weep holes and small horizontal relief drainage pipes can be

installed.

Figure 3: Soil Nail Drainage

•  Shotcreting & Installing Bearing Plates

Once the reinforcing and any required drainage medium are placed, the next step is to

apply the shotcrete facing. For most temporary shotcrete walls, this is accomplished by

applying a 75 to 100 mm (3 to 4 in) thick layer of 21 MPa (3000 psi) concrete. In a

temporary application, shotcreting is merely a method of tying the system together,

1 in = 25.4 mm

1 ft = 0.3048 m

Page 7: Soil Nailing - Where When and Why

8/13/2019 Soil Nailing - Where When and Why

http://slidepdf.com/reader/full/soil-nailing-where-when-and-why 7/27

  6

 providing a cover for the soil, and retaining the soil between the nails. The shotcrete can,

however, become more critical if the nail spacing increases. Immediately after the

shotcrete is applied, the soil nail bearing plates are installed on the fresh shotcrete facing

and their nuts are hand-tightened. It is very important to make sure that the bearing plates

and nuts are installed as soon as possible, but definitely before the next cut is made since

this is what provides the lock off of the nail as the soil deforms.

•   Repeat Steps to Final Subgrade

After the shotcrete has been installed and the soil nails have cured for three days, the

 process is repeated in lifts until the predetermined subgrade elevation is reached. Typical

temporary and permanent soil nail details are presented in Figures 4 and 5.

Figure 4: Typical Temporary Soil Nail Detail

Figure 5: Typical Permanent Soil Nail Detail

1 in = 25.4 mm

1 in = 25.4 mm

Gr. 60 = Gr. 400 SI

Gr. 75 = GR. 500 SI

Page 8: Soil Nailing - Where When and Why

8/13/2019 Soil Nailing - Where When and Why

http://slidepdf.com/reader/full/soil-nailing-where-when-and-why 8/27

  7

Permanent Facing

Although soil nailing began as a method of providing temporary earth support, it has evolved as

an economical method of providing a permanent, finished wall. Since soil nailing is a very

flexible system in that there is no need to make 90° corners or straight walls, it is very easy to

 provide a soil nail wall with curves and bends. If the final product calls for such geometry, more

than likely the permanent facing could be shotcrete (Figure 6). Once the temporary shotcrete

wall is constructed, a permanent facing typically involves adding another 100 to 150 mm (4 to 6

in) of shotcrete to the existing 75 to 100 mm (3 to 4 in) of shotcrete. The permanent facing will

 be reinforced and a screed face finish can be provided. In lieu of using shotcrete as the

 permanent facing, there are several other choices. A one-sided concrete wall can be poured

against, and attached to, the soil nail wall, or a variety of concrete block or precast panel systems

can be mechanically attached to provide a wall that will blend into any retaining wall system

(Figure 7).

Figure 6: Permanent Shotcrete or CIP Wall Facing Detail

Figure 7: Segmental Block Facing Detail

1 in = 25.4 mm

Page 9: Soil Nailing - Where When and Why

8/13/2019 Soil Nailing - Where When and Why

http://slidepdf.com/reader/full/soil-nailing-where-when-and-why 9/27

  8

Corrosion Protection

For temporary systems, single-corrosion protection for the soil nails is normally adequate. The

nail is simply a bare bar, with sufficient grout cover achieved by providing centralization of the

nail in the drill hole. For permanent soil nail systems, corrosion protection has to be examined

more closely. In non-aggressive soils, the nail should be provided with an epoxy or galvanized

coating as per standard manufacturer specifications. In more aggressive soils, fully encapsulated

nails are recommended. Typical tieback guidelines are normally followed to determine the

appropriate corrosion protection.

WHERE, WHEN AND WHY

Soil nailing is a very versatile geotechnical construction technique with many advantages over

other types of temporary and permanent retaining walls. Soil nailing can be used on numerous

sites to provide an economical and fast method of temporary earth support, underpinning and

stabilization.  However, there are many factors to be addressed when determining if soil nailing

is the right system for a project, and it is very important to understand the dos and don’ts of soil

nailing before it is recommended. When evaluating where soil nailing is appropriate, the

following guidelines can be used:

The Right Underground Conditions 

As with any geotechnical technique, the underground conditions are normally the paramount

consideration. A good geotechnical exploration and laboratory testing program is essential. As a

minimum, this information should include soil borings, groundwater data, sieve analysis, and

 plasticity testing. Whenever possible, test pits excavated with a backhoe are recommended to

evaluate the stand up time of the soils prior to production work.

Underground Conditions that are Conducive

In general, soil nailing can be used in any soil where a vertical cut can remain stable for at least24 hours. These cuts should be on the order of 1.2 to 1.8 m (4 to 6 ft), which is standard practice

for soil nail lifts. Cuts less than this reduce the economical advantage of soil nailing. Normally

soils that have some binder in them are considered the most favorable, such as:

Page 10: Soil Nailing - Where When and Why

8/13/2019 Soil Nailing - Where When and Why

http://slidepdf.com/reader/full/soil-nailing-where-when-and-why 10/27

  9

1.   Natural cohesive materials, such as silts and low plasticity clays not prone to creep.

2.  Glacial till.

3.  Cemented sand with little gravel.

4.  Find to medium sand with silt to act as a binder.

5.  Weathered rock.

6.  Residual soils.

Underground Conditions that are Not Conducive 

The soil nailing system is not recommended if any of the following conditions are present: 

1.  Urban fills and loose, natural fill material.

2.  Soft, cohesive soils that will not provide a high pullout resistance.

3.  Highly plastic clays, since they are susceptible to excessive creep.4.  Loose, granular soils with N-values lower than 10 to 15.

5.  Soils without any apparent cohesion and with high gravel content.

6.  Expansive clays.

7.  The presence of groundwater. Groundwater presents a problem with maintaining face

stability during the cut between lifts, and must be properly controlled in the

construction of a soil nail wall.

Most Effective Applications

Although soil nailing is a very fast and economical earth retention system, the most cost

advantages are realized in situations where other, more conventional, techniques have

limitations. Soil nailing offers the most advantages during the following applications:

 Difficult Soil Conditions: In some situations, the underground conditions may not be conducive

to driving soldier piles for a conventional, tied-back, soldier pile and lagging wall. The presence

of cobbles and boulders or the presence of rock above subgrade may require the soldier piles to

 be installed with large, costly drilling equipment. In general, this will greatly increase the overall

unit price, thus reducing the cost effectiveness of the system. However, since soil nails are

typically short, small-diameter, drilled-in elements, the cost of installation generally does not

significantly increase under these conditions.

Page 11: Soil Nailing - Where When and Why

8/13/2019 Soil Nailing - Where When and Why

http://slidepdf.com/reader/full/soil-nailing-where-when-and-why 11/27

  10

On-line Systems: On some projects, due to space limitations, the foundation wall for the

 proposed structure needs to be within millimeters of an adjacent structure or property line. Since

most conventional earth retention systems have a general width of 0.3 to 0.6 m (12 to 24 in),

installation would be impossible under these circumstances. Other options, such as concrete

underpinning pits can be very costly, particularly in difficult, dense soils. In the above

situations, soil nailing can provide large savings. Since temporary soil nail systems are normally

75 to 100 mm (3 to 4 in) thick, they will not encroach into the new structure as other systems

would, and since soil nail walls can be designed to withstand surcharge loads, they can be

installed adjacent to existing structures.

 Low Headroom Conditions/Tight Access: On some projects, earth retention may be required in

low headroom conditions or within tight access. One such situation would be the widening of anexisting highway, where the new portion of the highway must be constructed while an existing,

overhead bridge remains active and the overhead bridge girders remain in place. With the

development of compact, low-headroom drilling equipment the soil nailing system can be more

easily installed under these conditions whereas previously a much more expensive system, such

as driving and splicing soldier piles or sheet piling might have been the only option.

Permanent Walls: While soil nailing has become a highly effective system for retaining cuts

during construction of new structures, its use for the economic installation of permanent

retaining walls is still evolving. Since soil nail systems are already designed to withstand

temporary lateral loading, designing the wall to withstand permanent lateral and vertical loading

is a rather simple process and although unit costs will increase, the overall wall cost will still be

less than the cost of installing a new foundation wall. 

Soil nailed walls are much more “flexible” than conventional, rigid walls. Thus, they perform

 better during a seismic event. These structures can conform to deformation of surrounding

ground and can withstand larger total and differential settlements in all directions.

Areas of Concern

In the following situations, soil nailing should be ruled out or additional measures should be

taken:

Page 12: Soil Nailing - Where When and Why

8/13/2019 Soil Nailing - Where When and Why

http://slidepdf.com/reader/full/soil-nailing-where-when-and-why 12/27

  11

 Loose Fill & Sandy Soil Conditions: Since soil nailing is a top-down construction technique, it is

essential that the cut face can stand up long enough to install the nails and the shotcrete facing.

“Pushing the envelope” and installing soil nailing where this is not achievable is not

recommended and can result in face stability failure.

 Below the Water Table:. The presence of flowing groundwater will limit the stand up time of the

cut face and can also cause face stability problems. In addition, if the installation is successful

there is the added consideration of hydrostatic loading on the soil nail wall and additional

drainage requirements.

Outside Temperature: As for any concrete application, and as per the ACI code, the shotcrete

should be applied when the ambient temperature is 4.5° C (40° F) and rising. The construction

of the soil nail wall below such temperatures is only achievable with an imported heating system

and should be a major consideration during evaluation of use of the soil nail system. Temporary

heated enclosures and tents can be constructed to keep the temperature above 4.5° C (40° F), but

this can dramatically increase the overall construction cost of the soil nail wall.

Utility Interferences and Easements: As for tieback construction, a major consideration when

specifying or choosing a system should be the location and proximity of adjacent underground

utilities and adjacent property limits. Existing utilities may cause interference during installation

of the nails, and easements may be required if the nails will extend onto adjacent property.

 Expansive Clays: As stated previously, clays that have the potential for expansion or are

susceptible to creep should be approached cautiously. An additional monitoring and testing

system should be implemented prior to production work to verify the movement of the nails and

the wall during construction.

 Large Surcharge Loads: Soil nail walls can be designed to withstand significant exterior

surcharge loads (traffic, equipment and building surcharges, and so forth). Nevertheless, it is

important that the potential impact of these loads is understood and addressed prior to design

finalization, since they can dramatically impact the overall design and the future performance of

the soil nail system. Large wall deformations can result in significant settlement, and this should

 be considered in the design of the soil nail wall.

Page 13: Soil Nailing - Where When and Why

8/13/2019 Soil Nailing - Where When and Why

http://slidepdf.com/reader/full/soil-nailing-where-when-and-why 13/27

  12

 

DESIGN, MONITORING AND TESTING

Design

The installation of a soil nail wall results in the construction of a composite, coherent mass

similar to that of a mechanically stabilized earth (MSE) wall. Although soil nail walls and MSE

walls  have inherent differences in both construction and performance, they are similar in the

design approach. The reinforced soil mass is separated into two zones, an active zone and a

resistant zone. The active zone, or potential sliding wedge, is close to the face, where the lateral

shear stresses are mobilized, thus increasing the tension force in the nail and increasing the

 pullout force. The resistant zone, or steady zone, is where the nail forces are transferred into the

ground. Ground movement during and   at the completion of construction is restrained by the

frictional bond between the soil and the reinforcing element. Therefore, the most important

design consideration is to ensure that the soil nail interaction is effectively mobilized to restrain

ground movements and to ensure lateral stability with the required factor of safety for the

 particular project (Sakr and Kimmerling, 1995).

In the early years, the most common methods used to design soil nail walls were derived from

classical slip surface limiting equilibrium design methods of slope stability analysis, modified to

incorporate the additional shearing, tensile and pullout resistance provided by the nail

reinforcement crossing the failure surface. These methods of analysis evaluate “internal” factors

of safety along potential failure surfaces throughout the soil mass. The failure surface is

assumed to be either bi-linear, parabolic, circular, or a logarithmic spiral. The most common

methods used were the German Method (Stocker et al., 1979), the Davis Method (Shen et al.,

1981) and the French Method (Schlosser et al., 1983).

In the United States, two other methods have been developed and are commonly used for the

design of soil nail walls. These are the SNAIL method, developed by the California Department

of Transportation (CALTRANS, 1991) and the GoldNail design method developed by Golder

Associates of Redmond, Washington. The SNAIL method uses a bi-linear wedge analysis for

failure planes existing at the toe of the wall and tri-linear forces for failure planes developing

 below and beyond the wall toe. The Golder method can analyze circular failure surfaces. Both

methods consider the tensile resistance of the nails crossing the failure surface. These two

Page 14: Soil Nailing - Where When and Why

8/13/2019 Soil Nailing - Where When and Why

http://slidepdf.com/reader/full/soil-nailing-where-when-and-why 14/27

  13

methods are considered improvements over the other earlier methods in that they consider the

limiting pull-out capacity of the nails and take into account the wall facing attached to the soil

nails as part of the system.

Monitoring

The FHWA’s Manual For Design and Construction Monitoring of Soil Nails (Byrne et al., 1996)

estimates that for a typical, vertical soil nail wall, designed with a reasonable factor of safety, the

 peak wall displacements at the top of the wall tend to vary from 0.1%H (cut height) or less for

weathered rock and very competent and dense soils, to 0.2%H for granular soils, and up to

0.4%H for fine-grained, clay type soils. These displacements are comparable to those

experienced by other types of retaining systems such as tieback walls, which generally average

maximum lateral movements of 0.2%H (Byrne et al., 1996). 

As with any retention system, some type of monitoring should be conducted to determine how

the system is performing or if additional measures need to be taken. The type of monitoring

 program that should be implemented is directly related to the type of system being installed. For

temporary systems, monitoring can be performed by simply conducting daily or weekly

surveying with a typical transit and level to determine the horizontal and vertical movements that

have occurred, and which allows an approximation of the deflection of the system. Typically,

this type of device is accurate to 1.6 mm (0.0625 in).

When permanent soil nail walls or deeper temporary walls are constructed, it is prudent to install

inclinometers in addition to normal survey monitoring to measure lateral deformations. The

 probe is inserted into near-vertical, grooved casing of known orientation. Typically, the grooves

are set perpendicular and parallel to the object in question. Readings are taken at set intervals

while the probe is being extracted. The resultant data is a set of tilt readings at known depths

that can be plotted to show the overall lateral deflection of the casing and subsequent

surroundings.

In addition to monitoring for deflection, there are some circumstances where determination of

the actual stress that the nails are experiencing may be useful and important. Such information

can be obtained by using vibrating wire strain gages, small instruments used to measure strains in

Page 15: Soil Nailing - Where When and Why

8/13/2019 Soil Nailing - Where When and Why

http://slidepdf.com/reader/full/soil-nailing-where-when-and-why 15/27

  14

steel structures such as bridges, piles and tunnel linings (Figure 8). Measurements are developed

 by plucking the internal tensioned wire at its natural resonant frequency. Variations in the

frequency correspond to variations in the strain, which is converted and displayed on a readout

 box. This type of monitoring is costly. Thus, it is typically used only on critical structures and

for research and development.

Figure 8: Strain Gage Installation Plan and Section 

(After FHWA-SA-96-069 Manual for Design and Construction Monitoring of Soil Nails) 

Field Testing 

It is also important to implement a field-testing program to verify design assumptions. Field

testing also verifies that the equipment used on site is providing the assumed specified design

 parameters of drill hole diameters, drill lengths, shotcrete thickness, and so forth.

 Nail Testing

Testing performed on soil nails includes pre-production testing, verification testing and proof

testing. The type of testing can be directly related to the nature of the soil nail wall. For

instance, pre-production testing may be required only on a permanent wall to aid in the final

design. Although the type of testing may differ somewhat, there is always some type of

verification required. Nail testing is performed with a center hole hydraulic jack and power pack pump, similar to that used in tieback testing. As for tieback testing, the load is incrementally

applied as the movement of the nail is determined by using a dial gauge capable of measuring to

the nearest 0.0254 mm (0.001 in).

Page 16: Soil Nailing - Where When and Why

8/13/2019 Soil Nailing - Where When and Why

http://slidepdf.com/reader/full/soil-nailing-where-when-and-why 16/27

  15

•  Pre-production testing is performed on non-production or sacrificial nails. The pre-

 production test helps to determine the ultimate adhesion capacity as it compares to the values

used in the design. It is sometimes not possible to achieve ultimate pullout of the nail.

•  Verification Testing should be performed on at least one nail per row on all projects. The

verification test (pullout test) is performed on a shorter, non-production nail. The verification

nail should have a short unbonded (free) length so that the nail can elongate during testing

and ensure that the load is transferred to the bond zone. The bond zone is purposely made

shorter so that better bond values can be achieved and possibly bond failure will occur so that

the ultimate values are achieved (see Figure 13). The verification test is performed

incrementally, generally to a factor of at least two times the design value. The results

achieved are compared to the design, and changes in nail length or spacing can be made ifrequired.

•  Proof Testing should be performed on production nails. Typically, five percent of the total

number of production nails should be proof tested. These proof tests are not measuring

elongation as a performance test of a tieback would, but merely verifying that the bond is

achieved and that creep is not a concern.

•  Long Term Creep Testing  can be performed in addition to proof testing when creep is a

concern. Fine-grained soils or plastic soils should be creep-tested. Deflection versus log time

results are plotted on a semi-log graph and are compared against the acceptable criteria.

Shotcrete Panel Testing

In order to verify the compressive strength of the in-place shotcrete for permanent wall facings, a

test panel is prepared from which samples can be extracted, rather than extracted from the wall

itself. ACI 506.2-95 Specification for Shotcrete recommends ASTM C 1140-98 Standard

Practice for Preparing and Testing Specimens from Shotcrete Test Panels. Forms are

constructed from either steel or wood having a minimum width and length of 0.6 m (24 in) and a

minimum depth of 90 mm (3.5 in). The panels are prepared using the same reinforcement,

equipment, mix design and shooting orientation (slabs, slopes, vertical, overhead) as the actual

application. Panels are shotcreted either before or during the production phase of the shotcrete

Page 17: Soil Nailing - Where When and Why

8/13/2019 Soil Nailing - Where When and Why

http://slidepdf.com/reader/full/soil-nailing-where-when-and-why 17/27

  16

wall. The panel is then cured in the field or in a moist room until ready for testing. Cores are

drilled from the panel and tested in compression perpendicular to the surface of the panel.

Sawed cubes and beams may also be prepared from the panel and tested either perpendicular or

 parallel to the surface. Testing is done at 7 and 28 days, unless project requirements specify

otherwise.

CASE STUDIES

Robert Wood Johnson Hospital - Cancer Center Addition

New Brunswick, New Jersey

Underpinning

Construction of a Cancer Center addition to the Robert Wood Johnson Hospital, in New

Brunswick, NJ, required excavation to hard rock at up to 7.6 m (25 ft) below existing grade. The

46 m by 61 m (150 ft by 200 ft) excavation site was bounded on two sides by hospital buildings

and on the other two sides by an emergency access road and a busy thoroughfare. Earth retention

and underpinning to protect the integrity of the structures and roadways was an integral part of

the project design.

Conventional Approach

A drilled-in soldier beam and lagging system, in conjunction with conventional concrete

underpinning, is a common and effective approach to this type of work in the northern New

Jersey area. However, evaluation of the subsurface conditions showed a soil profile of 3 m (10 ft)

of residual overburden soil with good standup time, below which weathered rock extended to

 bedrock. These conditions are ideally suited to soil nailing, where underpinning and excavation

support can be achieved in a single operation.

Value Engineered Alternate

For this site, the geotechnical contractor calculated that soil nailing would be as effective as

conventional support systems, yet less expensive and faster to install. Since the new structure had

to be constructed within 100 mm (4 in) of the existing hospital, the soil nail system offered both

an economical method of providing the necessary underpinning and an on-line earth retention

system into which the new foundation wall could be tied. The geotechnical contractor proposed

Page 18: Soil Nailing - Where When and Why

8/13/2019 Soil Nailing - Where When and Why

http://slidepdf.com/reader/full/soil-nailing-where-when-and-why 18/27

  17

this value-engineered, alternative design to the excavation contractor and the construction

manager for the project. After evaluating the constructability of the system, it was decided that

soil nailing would be an innovative and economical solution for the site conditions.

 Design and Installation 

In unobstructed areas of the site, soil nails were installed at 15 degrees below horizontal on a 1.5

m (5 ft) grid pattern. However, a 0.6-m (24-in) diameter sanitary sewer that served the entire

hospital complex ran directly beneath existing foundations where the soil nail system had to be

constructed on-line and act as the form for the new foundation wall (Figure 9). Compromising

this essential utility would effectively shut down all hospital services and lead to very large

consequential damages. The geotechnical contractor investigated the precise location and

elevation of the sewer and adjusted the angle of the nail installation accordingly. In addition, avery loose sand backfill, most likely used during the construction of the utility, was encountered

during the excavation of the upper soil nail lifts. Since this backfill did not exhibit good standup

time, the lifts were reduced to 0.6 m to 1m (2 to 3 ft).

Figure 9: Cross-section Showing Utility and Soil Nail Installation

Three to four tiers of soil nails were installed, depending on the depth at which hard rock had

 been encountered at the time of the geotechnical investigation. For each tier, a vertical lift of 1.2

to 1.5 m (4 to 5 ft) was excavated, extending for a horizontal length that could be stabilized

Elevations in

feet.

1 ft = 0.3048 m

Page 19: Soil Nailing - Where When and Why

8/13/2019 Soil Nailing - Where When and Why

http://slidepdf.com/reader/full/soil-nailing-where-when-and-why 19/27

  18

during the workday. Other than where backfill was encountered,  the cut face exhibited good

stand up time, allowing the soil nails to be installed first across the entire face of the cut. A

geocomposite drainage strip and reinforcing wire mesh was then placed, and a 75-mm (3-in)

thick shotcrete facing was applied to bridge the soil nails and complete the structural

underpinning and retention system. The 1300 m2  (14,000 ft

2) soil nail system was successfully

completed three weeks ahead of schedule, resulting in significant savings.

Route 87 & 287 at Meadow Street

Tarrytown, New York

 Bridge Widening

 pgrading of Route 87/287 from two to four lanes to accommodate increased traffic flow

required the installation of a replacement bridge abutment approximately 1 m (3 ft) in front of

the toe of the embankment supporting the existing west abutment at the Meadow Street overpass.

Since the new abutment foundation would be up to 4.3 m (14 ft) deeper than the existing

abutment foundation, an excavation support system would be required to support the

embankment soils beneath the existing abutment during this work. The geotechnical contractor

was awarded a subcontract by the general contractor for New York State DOT to design and

 build the earth retention system.

Soil Nail Design and Installation 

The embankment soils consisted of silty glacial till with large boulders. Given the presence of

these boulders, coupled with the low headroom working conditions beneath the overpass, the

geotechnical contractor elected to use soil nailing to support the soils.  With the active abutment

 bearing directly on soil rather than deep foundations, the soil nail wall was designed to take into

account the large vertical surcharge of the existing abutment as well as lateral earth pressures

from the embankment behind the abutment.

Three levels of soil nails were installed on a 1.4 m H by 1.5 m V (4.5 ft H by 5.0 ft V) grid to

support the 4.3-m (14-ft) deep, 61-m (200-ft) long embankment (Figure 10). Given the nature of

the embankment fill, the geotechnical contractor chose to first reinforce the cut face with wire

mesh and a 75 to 100-mm (3 to 4 in) thick layer of 20 MPa (4000 psi) shotcrete. After the

shotcrete had cured, the soil nails were drilled and grouted in place. Specialty drilling techniques

U

Page 20: Soil Nailing - Where When and Why

8/13/2019 Soil Nailing - Where When and Why

http://slidepdf.com/reader/full/soil-nailing-where-when-and-why 20/27

  19

were required to penetrate the large boulders during soil nail installation. Sacrificial test nails

were used to verify bond values. The soil nail wall was installed in one mobilization, with no

removal of overhead superstructure required.

Figure 10: Cross-section Showing Installed Soil Nail Wall

University of Medicine & Dentistry

Dental School Expansion

Newark, New Jersey

 Earth Retention

Expansion of the Dental School at the University of Medicine & Dentistry of New Jersey

(UMDNJ) in Newark, NJ, included construction of a five-story, steel structure with a one-story,

 below-grade basement. The site was bounded on one side by the existing Dental School, and on

the opposite side by 12th

 Avenue, a major access road for emergency vehicles en route to the

adjacent University Hospital. Parallel, underground, electric and telephone duct banks, each 1.5

m by 0.6 m (5 ft by 2 ft), ran along 12th

 Avenue. The telephone bank lay nearest the site, 1.5 m

(5 ft) below existing grade and within millimeters of the proposed building.

The proposed structure, approximately 85.4 m by 36.6 m (280 ft by 120 ft) in plan, entailed

excavations to a depth of 8.2 m (27.0 ft) below grade. In order to facilitate these excavations, a

temporary earth retention system was required for approximately 80.8 lm (265 lf) along 12th

 

Avenue and for 38.0 lm (125 lf) along the west side of the site. Also, a permanent retention and

underpinning system was required for 18.3 lm (60 lf) on the south side of the project, along the

Elevations in

feet.

1 ft = 0.3048 m 

Page 21: Soil Nailing - Where When and Why

8/13/2019 Soil Nailing - Where When and Why

http://slidepdf.com/reader/full/soil-nailing-where-when-and-why 21/27

  20

existing, 3-story Dental School, where the new building would be constructed on-line and tied in.

Preliminary excavation support system concepts included driven steel sheeting and soldier beams

and lagging along 12th

 Avenue and the west side, and a permanent, on-line, soil nail wall along

the existing Dental School. However, the proximity of the duct banks along 12 th  Avenue

 precluded the sheeting and soldier beam options since both systems would encroach into the new

 building and would require the structure be moved and redesigned. In addition, the soil borings

encountered rock at or just above the proposed subgrade elevation, which could impede the

driving of soldier piles or steel sheets and likely necessitate a more expensive, drilled-in system.

 Engineered Solution

The pre-construction geotechnical investigation indicated that the subsurface conditions

consisted of 1.2 m to 1.8 m (4 ft to 6 ft) of fill, underlain by natural silts and silty sands

containing varying amounts of gravel, cobbles and boulders. Weathered sandstone bedrock was

encountered at or above the subgrade elevation of the proposed structure. After evaluating the

soil conditions, space limitations and the schedule, the geotechnical contractor offered a system

that entailed a temporary soil nail wall along 12th

 Avenue and the west side of the site, and a

combination of drilled-in minipiles and soil nailing along the existing Dental School. The

minipiles would be drilled through the existing column footings to underpin the building and

transfer the loads below the proposed subgrade. Soil nailing would be used to support and retain

the soil between the existing columns.

12th

 Avenue and West Side

The soil nail wall along 12th

 Avenue and on the west side of the site entailed three to five levels

of soil nails installed at 15 degrees from the horizontal on a 1.5 m (5 ft) grid pattern. A 75-mm

(3-in) thick layer of shotcrete, reinforced with wire mesh, was used to tie the system together and

retain the soils between the nails. Construction began with the excavating contractor making an

initial, sloped precut to locate the top of the telephone duct bank and remove the existing fill

soils which did not exhibit good ‘standup’ time. The precut also allowed the first level of soil

nails to be installed at a 15 degree angle below the duct bank, and did not require any redesign or

relocation of the proposed structure. Once the first level was installed, and the soil nails and

shotcrete had cured, the process was repeated and the remaining lifts were installed until

Page 22: Soil Nailing - Where When and Why

8/13/2019 Soil Nailing - Where When and Why

http://slidepdf.com/reader/full/soil-nailing-where-when-and-why 22/27

  21

subgrade was reached (Figure 11). A view of the soil nail wall along 12th

 Avenue is presented in

Figure 12.

Figure 11: Cross-section Showing Soil Nail Wall Installation 

Figure 12: View of Soil Nail Wall along 12th

 Avenue

The wall was designed to withstand the temporary lateral and traffic surcharge loads. The system

was also designed to withstand the surcharge loads associated with a large crane scheduled to be

 placed on the sidewalk directly behind the soil nail wall, to aid in construction of the new

addition. Since the soil nail wall for this part of the project was installed on-line, the new

foundation wall was constructed using a one-sided form and poured directly against the soil nail

wall. A drainage composite and waterproofing membrane were placed between the soil nail wall

and the new concrete wall. This 935 m2 system (10,000 ft

2) allowed the proposed foundation to

 be built ahead of schedule and without the need for any design modifications.

Elevations in

feet.

1 ft = 0.3048 m

Page 23: Soil Nailing - Where When and Why

8/13/2019 Soil Nailing - Where When and Why

http://slidepdf.com/reader/full/soil-nailing-where-when-and-why 23/27

  22

Soil Nail Instrumentation and Monitoring

In order to evaluate design assumptions and monitor the construction, a comprehensive testing

 program was implemented, consisting of field pullout tests, proof testing, surveying, and strain

monitoring.

Verification Testing: At least one pullout test was performed on each soil nail row (lift) to verify

that adhesion values used in the design program were obtained in the field. The pullout test was

 performed incrementally, generally to a factor of at least two times the design value, on a shorter

sacrificial nail (Figure 13). In addition, a minimum of five percent of the production nails were

 proof tested to 1.33 times the design load to measure the bond and creep values.

Figure 13: Pullout Test Detail 

Survey and Monitoring: Survey monitoring was implemented to measure horizontal and vertical

displacements. The deflection of the wall was generally 0.2% of the cut height, which is within

the range of the anticipated deformation for wall construction in these soils (Byrne, et al., 1996).

Strain Monitoring:  In addition to the normal monitoring, a strain-monitoring program was

developed and implemented for the temporary soil nail wall to compare the in situ parameters of

a multi-tier soil nail earth retention system with that of the original design parameters,

information that would be valuable in the future. Strain gage monitoring is discussed more fully

in the Design, Monitoring and Testing section of this paper.

1 ft = 0.3048 m

1 kip = 4.45 kN

Page 24: Soil Nailing - Where When and Why

8/13/2019 Soil Nailing - Where When and Why

http://slidepdf.com/reader/full/soil-nailing-where-when-and-why 24/27

Page 25: Soil Nailing - Where When and Why

8/13/2019 Soil Nailing - Where When and Why

http://slidepdf.com/reader/full/soil-nailing-where-when-and-why 25/27

  24

 

Figure 15: Composite Stress Plot

Table 1: Summary of Stresses

Stress Behavior 

 All Soil Nails

0.0

5.0

10.0

15.0

20.0

25.0

11/1/02 11/15/02 11/29/02 12/13/02 12/27/02 1/10/03 1/24/03 2/7/03 2/21/03

Date

   S  o   i   l  n  a   i   l   B  a  r   S   t  r  e  s  s

   (   k  s   i   ) B47-15-U

B47-15-L

B47-5-U

B47-5-L

C47-15-U

C47-15-L

C47-5-U

C47-5-L

D24-15-U

D24-15-L

D24-5-U

D24-5-L

Excavation

of "C" lift

Excavation

of "D" lift

Excavation

of "E" lift

Crane set up at top

of wall above gages

Strain Gage Bar Stress Average Stress Theoretical StressNumber (ksi) (ksi) SNAILZwin output

B47-15-U 16.28

B47-15-L 18.99

B47-5-U 16.24

B47-5-L 17.26

C47-15-U 7.93

C47-15-L 7.25

C47-5-U N/A

C47-5-L 14.06

D24-15-U 3.63

D24-15-L N/A

D24-5-U 6.91D24-5-L 6.52

3.63

6.72

15.901

14.053

17.137

16.75

7.59

14.06

17.64 24.287

18.854

20.094 1 ksi = 6.89 MPa

Page 26: Soil Nailing - Where When and Why

8/13/2019 Soil Nailing - Where When and Why

http://slidepdf.com/reader/full/soil-nailing-where-when-and-why 26/27

  25

 Existing Dental School (Understanding the Conditions)

During construction of the permanent soil nail wall along the existing Dental School,

unanticipated conditions were encountered during excavation of the first 1.5-m (5-ft) lift. A

loose, cohesionless fill with poor standup time was encountered directly below the existing first

floor slab. To assess the actual conditions, the geotechnical contractor installed a trial test

section of shotcrete and test nails to determine if soil nailing would still be viable. The shotcrete

did not adhere to the loose fill, causing sloughing of the material and “cave-in” of the test

section. Additionally, the test nails did not achieve the bond values that the design assumed.

Considering all these conditions, the geotechnical contractor recommended the soil nailing

system not be installed and offered a redesign, which consisted of on-line concrete pits, tieback

anchors and treated timber lagging to retain the soil between the columns. As originally

 proposed, minipiles were installed through the column footing to underpin the column footings

and transfer the column loads below the new subgrade elevation. 

SUMMARY

Soil nailing is an accepted technology, the theoretical aspects of which are well understood and

well reported in technical literature. However, research indicates that there are few practical

guidelines available that offer a comprehensive, experience-based insight into the construction

considerations that should be addressed before a soil nail system design is finalized and

implemented. This paper is intended to bridge that void, and is offered as a tool to aid owners,

designers, specifiers and general contractors, as well as those within the engineering community,

in making the informed decisions that result in appropriate and successful applications of this

versatile and economic technology.

ACKNOWLEDGEMENTS

The author extends his thanks and appreciation to the following people whose cooperation and

input has been invaluable, both on the jobsite and in the preparation of this paper: Steven Lacz of

Moretrench Geotec, John J. Peirce, P.E., of Peirce Engineering; and Ken Quazza, P.E. of SESI

Consulting Engineers.

Page 27: Soil Nailing - Where When and Why

8/13/2019 Soil Nailing - Where When and Why

http://slidepdf.com/reader/full/soil-nailing-where-when-and-why 27/27

REFERENCES

Byrne, R.J., Cotton, D., Porterfield, C., Wolschlag, G., and Ueblacker, G. (1996). “Manual for

 Design and Construction Monitoring of Soil Nail Walls.” FHWA-SA-96-069, Federal Highway

Administration, Washington, DC.

Chassie, R.G. (1993). “Soil Nailing Overview” and “Soil Nail Wall Facing Design and Current Developments,” presented at the Tenth Annual International Bridge Conference, Pittsburgh, PA.

Sakr, C. T. and Kimmerling, R. (1995). “Soil Nailing of a Bridge Embankment, Report 2: Design

and Field Performance.” Oregon Department of Transportation Experimental Features Project

OR 89-07

Schlosser, F. (1983). “Analogies et Differences dans le Compartment et le Calcul des Ouvranges

de Soutenement en Terre Armee et par Clouage du Sol.” Proceedings of Annales ITBTP No.

418, Sols et Foundations 184, pp 8-23.

Shen, C.K., Herrman, L.R., Ronstad, K.M., Bang, S., Kim, Y.S., and DeNatale, J.S. (1981). “AnIn Situ Earth Reinforcement Lateral Support System.”  National Science Foundation, Grant No.APR 77-03944, CE Dept., University of California Davis, Report No. 81-03.

Stocker, M.F., Korber, G.W., Gassler, G., and Gudehus, G. (1979). “Soil Nailing.” Proceedings

of the International Conference on Soil Reinforcement 1, Paris, Vol.2, pp 469-474.

Tuozzolo, T.J. (1997). “Stabilizing the Stacks - A hybrid soil nailing system provides permanent

underpinning for a historic college library.” Civil Engineering Magazine, December 1997.

CALTRANS (1991). “A User’s Manual for the SNAIL Program, Version 2.02.” California

Department of Transportation, Division of Technology, Material & Research, Office ofGeotechnical Engineering.

BIBLIOGRAPHY

Elias, V. and Juran, I. (1991). FHWA RD-89-198, “Soil Nailing for Stabilization of Highway

Slopes and Excavations.” Federal Highway Administration, Washington, D. C.

Singla, S. (1999). FHWA-IF-99-026, “ Demonstration Project 103: Design & Construction

 Monitoring of Soil Nail Walls.”  Project Summary Report. Federal Highway Administration,Washington, D. C.