soil specialist report
TRANSCRIPT
SOIL SPECIALIST REPORT
Sagehen Project Tahoe National Forest
Truckee Ranger District
January 16, 2013
Prepared by: Sharon Falvey
East Zone Hydrologist Tahoe National Forest
Sagehen Project Soils Specialist Report January 16, 2013
1
1 INTRODUCTION
This report provides an analysis of the effects of the Sagehen Project on short-term and long-
term soil quality in the project area. The purpose of the report is to introduce existing conditions
based on field observations into the project record and to provide evidence of adequate analysis
of the potential impacts to soil resources from the action alternatives within the project record for
the Sagehen Project Environmental Assessment (EA).
The report describes the soil for the project activity areas, provides an assessment of current soil
conditions within the activity area, analyzes the potential effects that the action alternatives
might have on the soil resource, and specifies mitigation in the form of management
requirements that would minimize adverse effects on soil quality.
The report includes:
the regulatory framework and applicable standards and guidelines used to evaluate soil
condition and the potential impacts of proposed treatments;
a description of the indicator, metrics and methods used to assess the effects of the
project on soil resources;
a description of the affected environment, including a listing of the soils in the project
activity area, a map showing the distribution of soil maximum erosion hazard rating for
the activity area, and an assessment of soil current condition in the activity areas as
affected by past land management activities, and relevant natural processes,
an assessment of the direct, indirect, and cumulative effects of the action alternatives on
the soil resource.
This document cross references additional supporting documents including:
Sagehen Project Environmental Assessment, Standard Management Requirements (SMRs),
Appendix A associated with this proposed action.
2 REGULATORY FRAMEWORK
Management actions must occur in conformance with applicable law, regulation, policy,
guidance, and management direction. This regulatory framework determines the overall
objectives and standards and guidelines applied to project activities and managing the soil
resource.
Specific measures, indicators, and thresholds are established through this regulatory framework.
They are used in assessing soil condition, to evaluate the effects of the proposed project on the
soil resource- what gets looked at, why, and interpretation of what it means to soil quality and
site productivity.
Sagehen Project Soils Specialist Report January 16, 2013
2
2.1 LAW, REGULATION, AND POLICY
2.1.1 National Forest Management Act
The National Forest Management Act of 1976 (NFMA) recognized the fundamental need to
protect, and where appropriate improve, the quality of soil, water, and air resources. With respect
to soil, NFMA requires that the Forest Service manage lands so as not to impair their long-term
productivity. Furthermore, activities must be monitored to ensure that productivity is protected.
This law led to subsequent regulation and policy to execute the law at various levels of
management.
2.1.2 National Soil Management Handbook
The National Soil Management Handbook defines soil productivity and components of soil
productivity, and establishes guidance for measuring soil productivity. Although a new FSM was
approved in 2010, the direction is that the SQS in The Tahoe National Forest LRMP is binding
until Forest Plan revision is completed. With this in mind, the SQS from the preceding National
Soil Management Handbook used to develop the Forest Plan Revision is presented in this
section. This guidance sets the definition for a threshold of areal extent of detrimental effects at
15 percent for a reduction in inherent soil productivity. These values apply to measurable or
observable soil properties or conditions that are sensitive to significant change. The threshold
values, along with areal extent limits, would serve as an early warning signal of reduced soil
productive capacity, where changes to management practices or rehabilitation measures may be
warranted.
Management activities have potential to cause various types and degrees of disturbance. Soil
disturbance is categorized into compaction, displacement, puddling, severe burning, and erosion.
Direction was established that the properties, measures, and thresholds relative to these
disturbance types would be developed at the Regional and Forest levels, known as Soil Quality
Standards (SQSs).
2.1.3 Region 5 Soil Management Handbook Supplement
The Region 5 Soil Management Handbook Supplement establishes Regional objectives for the
Soil Management Program and Regional Soil Quality Analysis Standards (SQAS). These
analysis standards are intended to help guide direction in forest plan development to determine if
ecosystem health and long-term productivity are being maintained.
In the discussion of Soil Quality Standards (FSH2509.18,2.2.1), the handbook states “Prescribe
the kind and amounts of soil cover that would not elevate wildfire risk or severity to the point
that fuel management and soil quality objectives cannot be met. If there is no viable alternative
for providing soil cover without elevating the risk of adverse wildfire effects, prescribe minimum
soil cover needed to avoid detrimental soil loss.”
The soil quality standards are currently being assessed following the hand book direction stating
that “Long-term plots established with Forest Service Research Units will be needed to establish
or validate the correlation between threshold values and significant change.” Results from
current literature provided by these studies are incorporated into this analysis and are used to
inform the significance of these soil property changes.
Sagehen Project Soils Specialist Report January 16, 2013
3
2.2 MANAGEMENT DIRECTION, STANDARDS AND GUIDELINES
The Tahoe National Forest Land and Resource Management Plan (LRMP) (USDA 1990)
established the Forest SQS per the National Soil Management Handbook direction and the R5
Soil Management Handbook direction. The Forest SQS are described within the LRMP as
Standard & Guideline (S&G) #55 presented below. The Regional Forester’s letter (February 5,
2007), specific to soil management, reaffirmed that the standards and guidelines in Forest Land
and Resource Management Plans provide the relevant substantive standards to comply with
NFMA.
2.2.1 Tahoe National Forest Land and Resource Management Plan Standard and
Guideline #55
The Tahoe National Forest LRMP (USDA 1990), as amended by the Sierra Nevada Forest Plan
Amendment Record of Decision, hereafter referred to as SNFPA, (USDA 2004), provides
direction for maintaining long-term soil productivity through standards and guidelines for three
soil characteristics: soil porosity, soil cover, and soil organic matter (LRMP, pages V-36 through
V-38). When the standard and guideline for these three soil characteristics (described below) are
met on at least 85 percent of an activity area, the soil is considered to be in an acceptable
condition, without significant impairment to soil productivity. An activity area is the area where
soil-impacting activity has occurred, or is planned to occur, and includes landings, skid roads and
trails, and temporary roads, but does not include system roads. The LRMP notes that it may be
difficult to achieve this standard and guideline during fire salvage; rehabilitation, or recovery
activities including reforestation of brush fields. It may also be difficult to achieve in areas where
existing plant communities have developed inadequate cover or duff, or where resource
objectives are in direct conflict. In these situations, a soil scientist will work with the project
interdisciplinary team to develop site-specific management prescriptions that approximate this
standard and guideline, and do not result in a significant reduction in soil productivity (LRMP,
page V-36).
Standard for Soil Porosity (LRMP, pg. V-36)
Maintain at least 90 percent of the total soil porosity found under natural conditions, as measured
at 4 to 8 inches below the soil surface over at least 85 percent of the activity area.
Standard for Soil Cover (LRMP, pp. V-36 – V-37)
The soil is considered to be in acceptable condition after a land-disturbing activity when the
effective soil cover on an activity area is (1) the minimum amount shown in the following table,
or (2) the minimum amount prescribed for a specific site by a qualified earth science specialist
after an on-site investigation The minimum effective soil cover prescribed for a specific site can
vary from the values shown in the table due to local differences in slope, micro relief, surface
rock fragments, detachability, and other factors that vary within soil types
When less than 85percent of an activity area is in an acceptable soil condition as defined above,
restoration treatments will be implemented to bring effective soil cover levels up to the minimum
standard. Restoration treatments will be completed prior to any seasonal period of precipitation
Sagehen Project Soils Specialist Report January 16, 2013
4
or runoff. Treatment may include, but is not limited to, mulching with straw or woodchips,
scattering concentrations of slash, or seeding grasses or forbs.
Table 1: Minimum Percent Effective Soil Cove r (ESC) by Slope Group and Soil Group
Slope (percent)
< 35percent 35 to 50 percent > 50percent
Soil Group A
Soil Group B
Soil Group C
Soil Group D
70 percent ESC
50 percent ESC
40 percent ESC
30 percent ESC
80 percent ESC
60 percent ESC
50 percent ESC
40 percent ESC
90 percent ESC
75 percent ESC
65 percent ESC
55 percent ESC
Soil Group A: These soils are highly erodible, have developed from granitic parent material,
have a short timber rotation length, and are at lower elevations on the westside of the Forest.
Included are the Hoda, Holland, Hotaw, and Musick series
Soil Group B: These soils have developed from a variety of parent materials. Their erodability,
geographic location, and climate vary, and they have short to moderate timber rotation lengths.
Included are the Aiken, Boomer, Boomer Variant, Chaix, Cohasset, Delleker, Dubakella, Euer,
Euer Variant, Forbes, Fugawee, Horseshoe, Hotaw Variant, Huysink, Jocal, Jocal Variant, Jorge,
Kinkel Variant, Lorack Variant, Mariposa, McCarthy, Ponto Variant, Putt, Sattley, Sierraville,
Sites, and Trojan series.
Soil Group C: These soils have developed from a variety of parent materials. Their erodability,
geographic location, and climate vary, and they have moderate to long timber rotation lengths.
Included are the Aspen Variant, Bucking Variant, Chaix Variant, Crozier, Haypress, Hurlbut,
Jorge Variant Kyburz, Ledford, Ledford Variant, Neer, Smokey, Tahoma Variant, Tallac, Tinker,
and Zeibright series.
Soil Group D: These soils occur primarily in the true fir zone, have low erodability and have
long timber rotations. Included are the Ahart, Bucking, Ceiio Variant, Lorack, Smokey Variant,
Tahoma, Umpa, Waca, and Windy series.
Guidelines for Soil Organic Matter (LRMP, pp. V-37 – V-38)
(1) Maintain Large Woody Material
The objective of this guideline is to maintain soil productivity and nutrient cycling by
maintaining woody residues in timber harvest units while allowing the merchantable logs to be
removed.
Within the LRMP, large woody material retention is recommended at a rate of 5 of the largest
downed logs/acre. Preference is for large cull logs 20 inches or more in diameter and more than
40 cubic feet in volume. Where possible, logs should be evenly distributed throughout the
activity area and in contact with the soil. Logs should be in a range of decomposition classes as
defined in USDA Handbook 553, page 80 (Thomas 1979), except that at least two logs per acre
should be in class 1 or 2. A total volume of 200 to 800 cubic feet of smaller logs, merchantable
wood, or other woody material may be substituted when sufficient large logs are not available.
Sagehen Project Soils Specialist Report January 16, 2013
5
Hardwood residues, which have a much shorter residence time, should be considered for
retention when conifer residues are absent or in short supply. Large woody material is considered
part of effective soil cover under the Standard for Soil Cover.
The activity area for large woody material guideline does not include roadsides and ridges
designated for fuel reduction in Practice P1: Areas emphasizing fire prevention in developed
areas, areas of concentrated recreation use and during periods of significant activities (USDA
1990).
(2) Maintain Forest Duff
Forest duff helps maintain long-term soil productivity by; (1) providing a source of organic
matter and nutrients, (2) providing habitat for soil micro-organisms, and (3) providing mulch that
conserves soil moisture.
The goal is to maintain a minimum of 20 percent of the undisturbed forest duff evenly distributed
throughout the activity area. Undisturbed duff is duff that has not been displaced or moved, its
natural structure is intact, including a well-decomposed layer at the interface with mineral soil,
the thickness of its well-decomposed layer has not been reduced, and its surface may be charred
by fire, but not consumed.
Undisturbed forest duff has the capacity to absorb soil being displaced and transported by sheet
erosion. Undisturbed forest duff is also a source of organic matter, nutrients, and microbial
habitat.
Forest duff is considered part of effective soil cover under the Standard for Soil Cover. Because
of its special qualities, forest duff may be used to reduce the requirements of the soil cover
standard as follows:
Where more than 20 percent of undisturbed forest duff is maintained, the effective soil cover
required under the soil cover standard may be reduced by 5 percent for each 10 percent of
undisturbed duff over 20 percent. This applies only to Soil Groups B, C, and D in the
Standard for Soil Cover.
2.2.2 Sagehen Project Management Area Direction There is no soil specific management direction related to soils in the project area.
2.3 CURRENT SCIENCE AND MONITORING
Direction exists at virtually all levels to consider past monitoring, new information, and current
science in the evaluation of resource management practices and the decision making framework.
Current science helps inform the relevance of the impact on the soil resource evaluated. As such,
this has become part of the overall framework for evaluating soil impacts, and further informs
the soil effects assessment.
2.3.1 Long-Term Soil Productivity Study
The Long-Term Soil Productivity Study (LTSPS) was borne in direct response to NFMA and the
National Soil Management Handbook to help validate and refine indicators and thresholds used
in the SQAS. This effort was cooperatively undertaken by Forest Service Research and the
National Forest System, and is an ongoing nation-wide experimental study.
Sagehen Project Soils Specialist Report January 16, 2013
6
An extensive world-wide literature review was first conducted looking for real evidence of
productivity declines and causes, beyond anecdotal and confounded studies. Where productivity
declines were well documented, the causal factors commonly reported were compaction and/or
organic matter removal from the site.
An experimental design was developed by Robert Powers and others1 to investigate factors
related to long-term productivity. In brief, the study design involves three levels of compaction
(none, intermediate, and severe) and three levels of organic matter removal (bole only, whole
tree, and whole tree plus all forest floor), in factorial combinations for nine treatments. Sites
were clearcut, treatments applied, and then planted with native conifer species. In addition, plots
were split in half, where competing vegetation was controlled in one half but not the other. Some
sites had additional “mitigation plots” where they were impacted and then rehabilitated by means
such as subsoiling, to test effectiveness of rehab methods. Conclusions from the Ministry of
Forestry indicate landings tilled with a winged subsoiler can be successfully rehabilitated
(Plotnikoff, 1999).
It is important to note with LTSP that “severe compaction” was experimental - approximately
90-95 percent of the area was heavily compacted (everywhere but stumps). Both in terms of
extent and severity this greatly exceeds impacts of typical harvest operations; severity may be
typical of landings. Intermediate compaction would be more typical in severity to well-used skid
trails, though again much more extensive than typical operations (90-95 percent area). In terms
of organic matter removal, vegetation treatment and fuel reduction projects such as the proposed
action would be typified by whole tree plus some forest floor removal.
California has 12 such study plot installations, more than any other Region, established from
1991 to 1998. California installations were purposely placed on a variety of major forest soils, to
investigate relationships on different soil types. Total aboveground productivity has been
measured at 5-year intervals. Results from the recent 5- and 10-year studies, show soil
compaction in sandy soil has resulted in increased productivity due to increases in plant-
available water. Finer textured soil, however, have shown decreased productivity resulting from
compaction and loamy textured soil showed no change. Growth tends to be reduced by
compaction on clayey soil due to loss of aeration from decreased porosity (Powers et.al, 2005).
These studies have shown that effects to soil productivity from compaction vary based on texture
even when standards are exceeded.
Literature by Greacen and Sands (1980) and Gomez et al. (2002) suggests that compaction may
increase water-holding capacity without unduly hampering soil aeration with some coarser
textured soil. Compaction risk is also reduced for soil with large rock fragments and higher rock
content. Moisture content is one of the most important factors influencing soil compaction (Page-
Dumroese et al., 2006). Operations over dry soil minimize the potential for changes in porosity.
2.3.2 Monitoring and Impacts of Ground-Based Thinning:
Findings were reported related to disturbance monitoring following ground based thinning in a
Seral Reserve (no measured existing disturbance) and mixed conifer forest (Iron Canyon late
1 Powers et al.1989.
Sagehen Project Soils Specialist Report January 16, 2013
7
seral reserve) over loam/clay loam soil and within an activity area with residual disturbance from
a previous entry. Disturbance as compaction severity (10 percent reduction in porosity) or extent
(15 percent) was not exceeded in the seral reserve but, results showed pre-existing disturbance
impacts are compounded by additional thinning. Pre-existing disturbance can remain measurable
over decades and thus is an accumulative impact (in areal extent and severity) and can influence
pre-existing disturbance for future harvests (Young 2005).
Data from the Herger Feinstein Quincy Library Group (HFQLG) 2010 monitoring report suggest
there may be direct effects to soil porosity since each entry into an activity area adds a small
amount of compaction; multiple entries needed to complete treatments make the activity areas
susceptible to increased compaction. The results from the HFQLG 2010 monitoring report
showed that somewhere around 9 percent of activity areas changed from meeting the compaction
standard to not meeting the compaction standard. The HFQLG studies made two conclusions 1)
most activity areas that exceed the standard post-treatment start with high compaction extent
nearing the Forest LRMP standard and, 2) there was not a large amount of change between pre-
treatment and post-treatment compaction for most activity areas.
2.3.3 Large Woody Material
Large woody material is described per the LRMP as having a preference toward a 20 inch
diameter and 10 foot long log, when sufficient large logs are not available smaller logs,
merchantable wood, or other woody material may be substituted. Therefore, the definition of
downed wood and applicable science for this indicator would include smaller woody debris, and
larger woody material such as the 1,000 hour fuels.
A study conducted by Spears et al., 2003 determined that woody debris contributes little to soil
biology and nutrient cycling, or that the effect is obscured because all soils have been affected by
woody debris at some time. While this study was conducted in Oregon with soils comparatively
rich in organic matter, it may illustrate the short-term cycling may not be as important to
productivity for soils as previously mentioned. Some suggestions are made that woody material
may be more important in low productivity soils.
Another finding conducted at the Black Mountain Experimental Forest concludes the large wood
retains more soil moisture under brown cubical rot of large wood. Further benefits include three
times more soil Nitrogen (N) mineralized beneath coarse woody debris than other cover types.
Assuming coarse woody debris cover is no more than 1 percent N, gain is 75 grams/acre/year in
mineral soil and is as good or surpassed by other vegetation types when extent is considered.
Large wood does provide habitat for fungi.
A study conducted by Stephens, 2001 shows the variation in fuel loads between a Jeffry pine
stand and an adjacent Upper Montane Stand for fire history plots. The mean fire return interval
for the Jeffry pine and Upper Montane fire plots were 9 and 24.7 years respectively. The study of
fuels including the 1,000 hour fuels was approximately 15 percent of the 1,000 hour fuel found
in the Upper Montane fire plot. This study illustrates that fire frequency and fuelbed
characteristics are linked.
Sagehen Project Soils Specialist Report January 16, 2013
8
2.3.4 Duff and Burn Prescriptions This section takes applicable information directly from (USDAFS, 2012). While this information presents
the components that may affect the amount of duff retained, there was no relationships presented as to the
amount of duff remaining following application of fire.
Duff is generally composed of two distinct layers: an upper fermentation layer of organic
material, including branchwood, cones, and bark in the early stages of decomposition and a lower
humus layer of mostly indistinguishable organic matter. The humus layer, or lower duff, is in an
advanced state of decomposition and is dark brown to black in color.
When using prescribed burn practices the lower duff is primarily consumed by smoldering
combustion. Moisture content is most important, with the probability of sustained smoldering
combustion inversely related to duff moisture content. Studies have shown that lower duff burns
independently of surface fuels below 90 percent moisture content. Conversely, duff rarely burns
above a moisture content of 120 percent. In controlled laboratory burning of lower duff from a
ponderosa pine dry mixed conifer stand in the southern Klamath Mountains, smoldering
combustion was halted at moisture contents exceeding 102 percent moisture content, and was
variable below that threshold. Mineral content is secondarily important through its interaction
with moisture content; higher levels of mineral content in the duff require drier duff in order for
consumption to occur. Higher fuel moistures reduce the potential fire intensity that would heat the
soil. Soil moisture also creates a buffer to soil heating. The depth that heat penetrates the soil is
largely dependent on soil moisture.
2.3.5 Pile Burning
Burning when soils are dry increases the likelihood of elevated soil heating regardless of fuel
type (Frandsen and Ryan, 1986; Hartford and Frandsen, 1992; Valette et al.1994; Campbell et
al., 1995) due to the low heat capacity of dry soils or the lower energy requirement needed to
heat air-filled pores compared with water-filled pores (Jury et al., 1991). Preliminary results of
studies in the Tahoe Basin determined project area piles generally take up less than 15 percent of
the treatment area and the overall effect of pile burning on soil productivity is not extensive. Soil
heating can occur up to a four inch depth when piles contain large bole wood. Large bole wood
included numerous pieces greater than 15 inches in diameter. Bulk density is increased under all
burn piles and infiltration is decreased in large (numerous pieces greater than15 inches) and
mixed burn piles (greater than 15 inches mixed with medium to small sizes) (Hubbert et.al,
2010). While no specifics on pile burning and hydrophobicity were conducted in this study a
study on length of hydrophobic effects suggest a weakening of fire-induced soil hydrophobicity
after 3 months and that fire-induced soil hydrophobicity persists for at least 22 months to a lesser
degree (Huffman et.al, 2001).
2.3.6 Region 5 Best Management Practice Evaluation Process (BMPEP) (Monitoring) (25,
T04, T06)
Best Management Practices (BMPs) have been designed primarily to protect water quality.
Several of the BMPs (F25, T04, T06) protect water quality by preventing erosion. Therefore, the
implementation and effectiveness monitoring results for these BMPs is relevant to protecting soil
productivity.
Prescribed Burning through Regional BMPEP Monitoring (F25)
The Regional BMPEP Monitoring summary occurring from 2003-2007 resulted in 190 sites
across the region monitored for prescribed burning. Data results using two assessment measures
Sagehen Project Soils Specialist Report January 16, 2013
9
show: 1) 83 percent effectiveness, and 5 percent ineffective (the results rate BMPs as successful
or not based on whether individual responses indicate departures) and 2) 100 percent
implementation and 98 percent effectiveness. Based on the record there was one case where the
result was assessed to have adverse effects extending to a stream for a period extending beyond 5
days. So with the exception of 1 site in 190, the BMPEP results show a high rate of protection of
water quality. Furthermore when the BMP is appropriately implemented, protection of water
quality resources was measured at 100 percent (USDA FS PSR, 2009).
Regional BMPEP Monitoring: Landings (T04)
The Regional BMPEP Monitoring summary occurring from 2003-2007 resulted in 277 sites
across the region monitored for protection of water quality. Results from that data set show 1) 90
percent implementation, and 93 percent effective (the results are expressed as rates BMPs as
successful or not based on whether individual responses indicate departures) and 2) 94 percent
implementation and 98 percent effectiveness (USDA FS PSR, 2009).
Timber Sale Erosion Control through Regional BMPEP Monitoring (T06)
The Regional BMPEP Monitoring summary occurring from 2003-2007 resulted in 24 sites
across the region monitored for Erosion Control (TO6). Results from that data set show1) 92
percent effectiveness, and 0 percent ineffective (the results rate BMPs as successful or not based
on whether individual responses indicate departures), and 100 percent implementation and 100
percent effectiveness. Out of 24 sites monitored all the BMPEP results show a high rate of
protection of water quality. Data show that when the BMP is appropriately implemented
protection of water quality resources results (USDA FS PSR, 2009).
2.3.7 Underburning of Masticated Fuels
Treatment of masticated fuels is fairly recent, and prescribed underburning following mastication
is a relatively new activity. Mulch depths of 7.5 centimeters (3 inches) can result in lethal soil
temperatures killing roots and creating biological damage at 10 centimeters (4 inches) (Busse
et.al, 2005). Damaging temperatures can be limited to the surface 2 to 5 centimeters (0.8 inches
to 2 inches) in the mineral soil when soil moisture was high. Soil moisture is the primary
determinant of downward heat transfer during burning of high woody fuel loads. Busse found
that burning, when soil has greater than 20 percent volumetric moisture minimizes lethal root
heating and limits damaging temperatures to the surface 2 to 5 centimeters in the mineral soil
(Busse et. al., 2010). Soil surface damage varies in extent and depth with variation of depth of
masticated fuels above 7.5 centimeters (3 inches). Results indicate that most plant roots will be
unaffected by the burning of masticated woody fuels in moist soils under typical spring burn
conditions in the western United States. Burning heavy fuel loads when soils are moist (greater
than 20 percent volumetric moisture) should limit damaging temperatures to the surface 2 to 5
cm in the mineral soil. On the other hand, prescribed burning when soil moisture is low, may
produce considerable soil heating.
Another study conducted by Knapp (2011), found that little heat from burning masticated fuels
appeared to penetrate deeply into the mineral soil. Litter and the 1-hour woody fuels were most
readily consumed whereas larger wood and duff contained considerable moisture and were less
completely consumed during late spring-early summer burns. It should be noted that when the
Sagehen Project Soils Specialist Report January 16, 2013
10
average duff moisture was above 30 percent, prescribed burning was found to lead to incomplete
consumption.
2.3.8 Aspen Restoration and Soil Organic Matter
Shepperd, 2006 provides various descriptions of the soil/water and nutrient interactions and
states “The cyclic relationship between soil nutrients and the accompanying understory of aspen
stands provide annual leaf litter that enhance the nutrient cycles as the organic matter
decomposes” and concludes, “This process is the foundation for development of soil water
holding capacity of the habitat.”(N.V. DeByle and R.P. Winokur 1985).
3 METHODS
3.1 Indicator, Metrics and Methods
Through direction outlined in the Region 5 Soil Management Handbook Supplement and the
National Soil Management Handbook, Standard and Guideline #55, within the Tahoe National
Forest LRMP was developed. The SNFPA Record of Decision (2004) did not include language
that supersedes this direction; therefore, the LRMP standard and guideline are the indicator and
metrics used to assess the effects of the project on soil resources; and are the means to maintain
ongoing long-term soil productivity. Standard and Guideline #55 identifies one indicator,
“productivity”, and three metrics “soil porosity”, “soil cover”, and “soil organic matter”.
The LRMP direction sets guidelines for soil properties and soil conditions that have been
indicated to maintain productivity. Key soil functions can be maintained when the three metrics
for productivity: 1) soil porosity, 2) soil cover, and 3) soil organic matter are met over an activity
area. Soil disturbance is considered “detrimental” if the thresholds described for these standards
are exceeded. Subsequent impairment of soil functions may be at risk, if standards are not met.
Both severity and extent of detrimental disturbance are important considerations that must be
evaluated together to assess potential adverse impacts on the activity area soil resource. As such,
detrimental disturbance can be allowed on a small portion of an activity area without affecting
productivity. Current science section 2.3.1 Long-Term Soil Productivity Study (LTSPS), further
informs risk to productivity.
Note that the activity area is the scale at which impacts are ultimately assessed, defined as the
area where soil disturbing activities take place, such as a timber harvest unit in a sale area or a
burn area within a prescribed burn project; system roads, trails, and other areas not dedicated to
growing vegetation (other dedicated uses) are not included as part of an activity area.
3.1.1 Standard for Soil Porosity
Maintain at least 90 percent of the total soil porosity found under natural conditions, as measured
at 4 to 8 inches below the soil surface over at least 85 percent of the activity area.
If the standard for porosity is exceeded in severity and extent, information from the LTSPS is
applied and the risk of effects on soil productivity is conducted based on the impacted soil
texture. Based on the LTSPS, reduced productivity from porosity exists only over fine textured
soil.
Sagehen Project Soils Specialist Report January 16, 2013
11
Porosity Methods:
Sampling is conducted using a tile spade where each site is characterized as to whether it is
detrimentally compacted or not. A couple of sites within each activity area with no evidence of
previous mechanical activity are sampled to establish a baseline to represent the undisturbed
condition. Compaction data is collected at each sample point by excavating 8 to12 inches deep
and 4 to 6 inches wide with a soil spade. The soil from 4 to8 inches deep is observed and
manually manipulated to assess whether detrimental compaction exists. Undisturbed soil would
typically offer little resistance to spade penetration. It is usually loose and has a fine granular
structure. Detrimental compaction has moderate to high resistance to spade penetration compared
to the undisturbed sites. It also commonly exhibits platy structure. The tilth and friability of the
soil are noticeably reduced. It may appear blocky or massive as opposed to loose and granular in
the undisturbed site. The project record describes the transect method for collecting data and
contains data sheets used. The summary of each data point along the transect is used to estimate
the extent of detrimental compaction.
3.1.2 Standard for Soil Cover
The guidelines presented above in Section 2.2.1, set the minimum standard for percent effective
soil cover. Additional measures are included in the Sagehen Project Environmental Assessment,
Standard Management Requirements (SMRs), Appendix A. Monitoring further informs success.
Where accelerated onsite erosion is observed additional remedies to control erosion are provided.
Soil Cover Methods:
Soil cover data is collected by observing the soil cover within a one square foot area at the toe
point. The percentage of organic cover (at least ½ inch thick) per the R5 Soil Quality Standards
(SQS) is estimated as to whether it is 50 percent or more cover (yes) or less than 50 percent
cover (no) over the grid area. This is translated into the percentage of plots having 50 percent or
more cover (i.e.: if 75 percent of the plots had over 50 percent cover the activity area is evaluated
as having 75 percent cover). The dominate type of soil cover is also identified and recorded.
Categories include: CO-undisturbed duff and litter (O horizon); C2-rock; C3-vegetation or shrub
canopy less than two feet above the soil surface; C4-bare soil; C5-larger woody debris (logs,
stumps). The project record describes the transect method for collecting data.
3.1.3 Standard for Organic Matter as Large Woody Material and Forest Duff
3.1.3.1 Standard for Large Woody Material Within the LRMP for soils, large woody material retention is recommended at a rate of 5 of the
largest downed logs per acre with a preference for large wood greater than 20 inches diameter
and ten feet long. Other woody material may be substituted when sufficient large logs are not
available with a total volume of 200 to 800 cubic feet per acre of smaller logs, merchantable
wood, or other woody material. The LRMP recognized there would be times when these
standards would not be met particularly for plantations and when providing site preparation for
reforestation. As discussed in the Appendix H (pg. H-5) of the Environmental Impact Statement
(EIS) for the LRMP, the standard for downed wood is based on the application of general
principals and was considered a prudent starting point. Large woody debris requirements were
developed from a position statement for the Siskiyou National Forest (USDA, 1987). However,
Sagehen Project Soils Specialist Report January 16, 2013
12
as this forest is located in the Cascade Range, the ecosystem is not similar to the eastern districts
of the Tahoe National Forest.
Based on current literature, and recent findings on fire return intervals for some of the east side
forests, the guideline of 5 trees per acre may be high for some east side forest types. The primary
objectives in some locations of east side forest types, is to meet fuels reduction needs. As
discussed in Appendix H (pg. H-6) of the EIS for the LRMP, the requirement for large woody
material is waived in areas designated as fuel breaks.
Current science informs this position and is based on more frequent fire return intervals. As
presented by Stephens, 2001, the findings suggest there is a link between fuel bed, species and
fire frequency. For instance there is a decreased presence of 1,000 hour fuels (3 inches or
greater) in Jeffry pine, having a shorter fire return interval than an upper montane forest.
Qualifiers found in the guidelines for Soil Organic Matter of the LRMP recognize the large
woody material does not include roadsides and ridges designated for fuel reduction under
Practice P1 (Areas emphasizing fire prevention in developed areas, areas of concentrated
recreation use and during periods of significant activities).
The minimum standard for large woody material includes the smaller logs, merchantable wood,
or other woody material at a rate of 200 cubic feet to 800 cubic feet per acre and this equates to
approximately 2.3 to 10 tons per acre depending on density.
Information in the direct and indirect effects section applies the standards to Alternative 1 and
Alternative 3 slightly differently based on the proposed actions, site conditions, and these
guidelines. Because the proposed action has an emphasis on downed wood for Martin species the
wildlife criteria was used to develop the proposed action plan and the basis of that criteria is
based on a minimum criteria of downed wood at 5 downed logs, 15 foot diameter and10 feet
long. These lengths were designated a minimum, however: the proposed alternative also
proposed leaving the 5 largest trees. With additional downed wood the basis of the proposed
action with a 15 foot diameter and 10 feet length objective meets the minimum standards for
soils when considering that it includes the largest available downed wood and other woody
material at a rate of 200 cubic feet to 800 cubic feet per acre.
Large Woody Material Methods:
Existing conditions were determined using observations and data were obtained from point data
previously collected by UC Berkley and compiled by Scott Conway, Vegetation Management
Officer. Valiant (2008) provides the following description regarding the design of the UC
Berkeley vegetation plots in the Sagehen Basin and more information on the source data and
methods can be found in the Silviculture Specialist Report for the Sagehen Project(Conway,
2012). The data used include large logs (greater than 15 feet in diameter and greater than10 feet
long).
Post implementation monitoring follows standard Forest Service procedure using the transect
method. At every fifth sample point along the transect a 37-foot radius sample area
(approximates a tenth acre plot) is estimated. The numbers of down logs by decomposition class
Sagehen Project Soils Specialist Report January 16, 2013
13
1-5 that are at least 20 inches in diameter and 10 feet long are recorded. Since the distance
between samples varies based on activity area width, where unit size is small, it may be
necessary to sample every sixth or seventh point instead of every fifth point to make sure that the
1/10th
acre plots are at least 75 feet apart so that they do not overlap. The project record describes
the transect method for collecting data and contains data sheets to be used. When downed logs at
the 20 inch diameter size are not present across the site the data would be collected using the
applicable Photo Series for quantifying forest Residues. See section 6.2.1.3 Organic Matter
Changes from Vegetation Management for more detail on how these standards were applied to
the action alternatives.
3.1.3.2 Standard for Forest Duff
The goal is to maintain a minimum of 20 percent of the undisturbed forest duff evenly distributed
throughout the activity area. Undisturbed duff is duff that has not been displaced or moved, its
natural structure is intact, including a well-decomposed layer at the interface with mineral soil,
the thickness of its well-decomposed layer has not been reduced, and its surface may be charred
by fire, but not consumed. Appendix H of the EIS for the LRMP recognized it may not be
possible to maintain forest duff under plantations until they are mature enough to provide needle
cast.
Forest Duff Methods:
Prior to implementation, transect data determine existing cover components as undisturbed duff
and litter, vegetation that contributes duff, and larger woody debris. These data describe existing
conditions for forest duff.
After implementation, transect data may be collected across an activity area. Disturbed areas,
along a transect, would be identified as categories N-no displacement, D1 –slight disturbance
duff and A horizon in place, D2- disturbance evident duff displaced: D3- duff and part of A
horizon removed or slash and A horizon mixed, D4 A horizon gone. The percent disturbed area
would be assessed with categories D2, D3, and D4 where the recent activities caused the
displaced duff. Percent disturbance would be calculated based on these transect data. The project
record describes the transect method for collecting data.
3.2 SOIL RESOURCE INFORMATION
Soil information for the project area was obtained from two sources: the Tahoe National Forest
Soil Resource Inventory (1994), and field observations of the project area (2004-2011).
3.2.1 Soil Resource Inventory
Soil maximum erosion hazard rating information, by operational activity area, is illustrated in
Soil and Water Resource Map 1. To simplify the soil map unit characteristics, the major soils in
each soil map unit were determined based on the percent present within the soil map unit. Where
soil mapping units included one or two soil families comprising over 30 percent of the map unit
they were included as major soil types for that operational soil activity area.
Sagehen Project Soils Specialist Report January 16, 2013
14
3.2.2 Field Observations
The purposes of field work were to: (1) validate the soil survey mapping, (2) gather information
on site-specific soil properties, (3) assess current soil conditions as affected by past management
activities, (4) determine level of mitigation measures and (5) develop predictions on soil
response to the proposed treatments.
Activity areas were selected to be sampled in order to describe existing conditions. Selection of
activity areas to be sampled is based primarily on risk for exceeding compaction (proposed
action where heavy equipment is used, areas with recent entries, or legacy compaction) and the
frequency with which the soil type occurred within the proposed activity area areas. Soil type,
slope, proposed activities, and past activities were used to refine the sample selections and obtain
representative site conditions. When soils were sampled, surrounding units with similar soils
were observed to determine if the sampling was representative. Where an activity area is
observed to have potential for more compaction, additional transects were made or the unit is
selectively sampled. Dave McComb, Soil Scientist, completed soil sampling. Sites were also
visited by Sharon Falvey, East Zone Hydrologist. Summary information from field data is
available in the project record.
Field observations confirming soil type and general site conditions were completed during
interdisciplinary team meetings. Areas with concerns identified were noted and detailed remedial
actions to address those issues were incorporated into the Standard Management Requirements
(SMRs) in Appendix A of the Sagehen EA.
4 AFFECTED ENVIRONMENT
4.2 SOIL EXISTING CONDITONS
Productivity
4.2.1 Soil Porosity (Compaction)
Field observations of detrimental compaction on proposed units are well below threshold.
Measured transects found 33 percent of the sample areas had no compaction, and areas with
observed compaction from transect measurements ranged from an extent of 3 percent to a high of 8
percent along the transect. Within the general project area detrimental compaction was typically
observed along historic features and older access routes. All of the unit activity areas were visited
and site observations conclude they currently meet the Tahoe LRMP soil porosity standard.
Measured unit results showed no compaction to up to 8 percent detrimental compaction.
4.2.2 Effective Soil Cover (Erosion)
On all proposed activity areas observed there were soil cover quantities sufficient to prevent soil loss due
to erosion. Data from measured activity area transects showed a range of 80 to 97 percent effective soil
cover. No accelerated erosion or sediment movement was observed on any proposed activity areas
surveyed that would indicate a loss in soil productivity. In the general project area outside of activity
areas, some erosion and sediment movement was observed (as sheet flow merging to concentrated
flows) in areas where Wyethia (W. heleniodes) vegetation dominates, and along roads and where road
Sagehen Project Soils Specialist Report January 16, 2013
15
drainages concentrate and discharge downslope of the road particularly where multiple roads converge.
Data from soil transects measuring soil cover can be found in the project record.
4.2.3 Organic Matter
Large Woody Material Large woody material data is assessed for existing conditions by emphasis area. Existing
conditions were determined using observations and the data were obtained from point data
previously collected by UC Berkley. The UC Berkley data use logs greater than 15 feet in
diameter and greater than10 feet long as minimum criteria to estimate large logs per acre. Valiant
(2008) provided the description regarding the design of the UC Berkeley vegetation plots in the
Sagehen Basin and more information on the source data and methods can be found in the
Silviculture Specialist Report for the Sagehen Project(Conway, 2012).
A data summary that included data conversions to comparable units were calculated by Scott
Conway, Vegetation Management Officer for UC Berkley data that overlap proposed action
activity areas. These data were then averaged by emphasis area, first using all data, then by
removing the data from the plantations (46, 87) and natural regeneration areas (76, 98, 99) that
may skew the data in the natural stands. It should be recognized that the observed data have high
variability and therefore, the average obtained would not be likely to be observed over every
acre, but may be more representative of an average at a landscape scale. As can be seen in Table
2 below there are no logs recorded for emphasis area 8. However; downed logs and a total
volume of 200 to 800 cubic feet per acre of smaller logs, merchantable wood, or other woody
material meeting the minimum requirements were observed in the emphasis area and general
activity area during field visits.
Table 2: Large Wood: Existing Conditions
Emphasis Area
Average Logs per acre
(>15 inches diameter and
> 10 feet long
Average Logs per acre (>15 inches diameter
and > 10 feet long removing data from
plantation and regeneration activity area 46,87
and 76, 98, 99 respectively
1 21.6 logs/acre 26 logs/acre
2 12 logs/acre 12 logs/acre
4 10 logs/acre 12 logs/acre
5 5 logs/acre 6.5 logs/acre
6 14 logs/acre 18 logs/acre
7 8.6 logs/acre 10.6 logs/acre
8* 0 logs/acre 0 logs/acre
*Downed logs and a total volume of 200 to 800 cubic feet per acre of smaller logs, merchantable wood, or other
woody material meeting the minimum requirements were observed during field visits to these activity areas.
Forest Duff Transect results representative of the project area showed forest duff varied from 65 percent to
90 percent. Transect data for plantations in proposed activity area 46 have 85 percent duff. The
transect running through the uplands of previously treated areas in activity area 213 showed 65
percent duff. Transects running along the western margin in activity area 213 showed 73 percent
Sagehen Project Soils Specialist Report January 16, 2013
16
duff. Other transects in proposed activity areas such as activity areas 38 and 39 show 90 percent
existing duff.
4.1 GEOLOGY AND SOIL INFORMATION
Geologically, the project area is comprised of Cenezoic Sedimentary and Cenezoic volcanic
rock. The landscape is formed through glacial deposits and tertiary pyroclastic rock and volcanic
mudflow.
The order 3 soil survey information is used to describe activity area soil (USDAFS 1994). There
are nine major soil types within the activity area for the proposed action. See Map 1: Sagehen
Activity Area Soil, available in the project file, presenting the major soil by activity area and
identifying maximum erosion hazard rating. The reason for identifying the major soil is to define
the dominate characteristics found at the activity area level since all map units at the order three
scale result in small areas of other soils contained in the map unit. For this document, the major
soils is a term used to describe the dominate soil in the mapped soil unit (order three soil series)
and any co-dominate soil present at greater than or equal to 30 percent presence within the
mapped soil unit. Where present the co-dominate soil is hyphenated. These soil units were
originally attributed based on their presence in the project area and were further segmented based
on activity area.
Waca Series are formed in residuum and weathered from andesitic mudflow and rhyolitic tuff.
Jorge soils formed from residuum from volcanic flow rock of andesite, basalt and latite.
Fugawee, and Fugawee Altered and Terraced soil is formed in residuum weathered from basic
igneous rocks principally latite and andesite flows. Tahoma series are formed in residuum
weathered from basic volcanic rock. Trojan series are formed in residuum and weathered from
andesitic and basaltic conglomerate and breccia.
Fugawee, Sierraville, Tahoma and Jorge soil are Alfisols. Waca soil is an Inceptisols and Trojan
soil is a Xeroll. Soil textures vary from sandy loam to loam; the Waca soil have 15 to 45 percent
gravel and Fugawee, Tahoma, and Jorge can vary between 3 to 60 percent cobble and stone or
rock fragment. Soils are very deep to moderately deep and mostly well drained with the
exception of wet soil types described below.
Soil survey, monitoring data, and field observations are used to describe the affected soil and
existing conditions in the project area. The internet website Web Soil Survey can be used to view
the soil mapping for the area based on the order three soil mapping conducted for the Tahoe
National Forest (http://websoilsurvey.nrcs.usda.gov/app (USDAFS, 1994). Also, see the project
record for the mapped soil location for unit activity areas and the Maximum Erosion Hazard
Rating (MEHR) associated with those soils on Map 1: Sagehen Project Area Soils Alternative
1,and Map 2: Sagehen Project Area Soils Alternative 3. Maximum Erosion Hazard Rating. The
Order 3 survey data was available by Geographic Information System (GIS) layer built from the
information from the Tahoe National Forest Soil Survey (USDAFS, 1994). The mapped unit soil
symbols associated with the Major Soil in the soil series are presented in the following
paragraphs by alternative. Other available information considered included an Order 2 mapping
of soils was completed by Hanes and Poff (1989) for the Sagehen basin; however, the order three
Sagehen Project Soils Specialist Report January 16, 2013
17
soil survey was utilized as it is the most recent science and basic soil survey information was
available in digital form.
Under Alternative 1 (2,653 treatment acres), the activity areas are comprised of approximately
47 percent Fugawee-Tahoma and altered soil (FTE, FTEA, FTF), 17 percent Fugawee (FVE,
FRE and FME) with a component of altered and terraced Fugawee soil (FRE5 and FRF6) in the
plantations on both the north and south slopes). Additionally, there are approximately18 percent
Jorge (JTE, JTF and JWF) 10 percent Sierraville (SIE), and 7 percent Waca (WAF, WDF and
WEE) soil. There is a minor component of Aquolls/Borolls (1 percent) and less than 1 percent
combined presence of Trojan (TTF) and Tallac (TBE) soil in the proposed activity areas. The
Aquolls/Borolls (AQB) are all located within units proposed for hand pile and pile burning or
under burning only, and these are located primarily near the southern flank of the Sagehen
Creek. There are small inclusions of Cryumbrepts, wet soil and the Aquolls and Borolls
associated with wet springs and meadow areas in other activity areas.
Under Alternative 3 (1,132 treatment acres), the units are comprised of approximately 69.6
percent Fugawee-Tahoma and altered soil (FTE, FTEA,FTF), 16 percent Fugawee (FVE, FRE
and FME) with a component of altered and terraced Fugawee soil (FRE5 and FRF6) in the
plantations on both the north and south slopes). Additionally, there are approximately 11 percent
Jorge (JTE, JTF and JWF), and 1.5 percent Sierraville (SIE). There is a minor component of
Aquolls/Borolls (AQB) (2.2 percent). The Aquolls/Borolls are all located within activity areas
proposed for hand pile and pile burning or under burning only, and these are located primarily
near the southern flank of the Sagehen Creek. There are small inclusions of Cryumbrepts, wet
soil and Aquolls/Borolls also associated with wet springs and meadow areas.
Sagehen Project Soils Specialist Report January 16, 2013
18
5. Alternatives Considered
Three alternatives are being analyzed in detail for the Sagehen Project: the Proposed Action
(Alternative 1), the No Action Alternative (Alternative 2), and the Non-Commercial Funding
Alternative (Alternative 3). The primary difference between alternative 1 and alternative 3,
where area treatments remain the same in the subset of units treated, is in the size of material
removed. Under alternative 3, the suppressed cut, used for hand treatment removes the majority
of trees less than ten inches dbh in the units proposed for treatment. There would be no designed
DCA or ESO. The prescription is focused on removing 12 inch dbh or smaller with occasional
trees of 18 inches dbh removed in the mechanically thinned units. Table 3 summarizes the
treatment acreages; Table 4 displays the road work, and a summary of the restoration activities
under the proposed alternative(s). More detail can be obtained in the Sagehen Project proposed
action and Environmental Assessment.
Table 3. Sagehen Project: summary of proposed treatment acreages by alternative.
Treatment Alternative 1 (acres) Alternative 2 (acres) Alternative 3 (acres)
Mechanical Thin/ Grapple Pile and Burn 635 0 0
Mechanical Thin/ Grapple Pile and Pile
Burn/Underburn
82
Mechanical Thin/ Underburn 496 0 0
Underburn 116 0 84
Mechanical Thin/ Lop & Scatter,
Mastication, Underburn
661 0 661
Hand Thin/ Pile Burn/ Underburn 248 0 248
Mechanical Thin, Lop & Scatter,
Mastication
315 0 45
Hand Thin/ Pile Burn 94 0 94
Aspen Restoration – Mechanical Thin 1 0
Aspen Restoration – Hand Thin, Hand
Pile, burn
5 0 0
Total Treatment Acres 2,653 0 1,132
Table 4. Sagehen Project: summary of proposed road activities by mileages for the alternatives.
Road work Alternative 1 (miles) Alternative 2 (miles) Alternative 3 (miles)
Road construction (temporary with
follow-up decommissioning)
3.8 0 0
Road decommissioning 1 0 0
Road maintenance 22.4 0 7.2
Restoration Actions: Alternative 1 Only
Road 11-5, Action 1: Approximately one mile of this road would be obliterated following its use
for vegetation treatment activities.
Sagehen Project Soils Specialist Report January 16, 2013
19
Road 11-5, Action 2: On the section of the 11-5 road which passes through the bottom end of a
fen (300 feet), the road and its associated culvert system would be removed and full restoration
measures improving the hydrology through the fen will improve approximately three acres of
hydrology surrounding the fen.
6 ENVIRONMENTAL EFFECTS
6.1 BOUNDING OF EFFECTS ANALYSIS
For the soil resource assessment, the analysis area is bounded by the project activity areas (unit
based assessment), where the potential ground disturbing activities are proposed. The effects are
bounded in time with the past and present actions assessed through the existing condition. The
proposed action alternatives for soil resource are the foreseeable future actions which, by
definition, include planned activities that are reasonably foreseeable and have sufficient detail to
be analyzed.
6.2 DIRECT AND INDIRECT EFFECTS
Environmental effects are assessed with the assumption that the management requirements
included in the SMRs are implemented as prescribed. Management requirements provide
measures that aim to prevent adverse effects to the soil resource and to ensure the standards for
soil resources are attained. Some management requirements incorporate mitigation measures to
be conducted in conjunction with operations for treating unavoidable undesired effects.
Direct and indirect effects are determined largely based on literature and past monitoring results
in context with the metrics outlined under section 2.2 Management Directions, and the
Standards and Guidelines above. Standard and Guideline #55 identifies one indicator,
“productivity”, and three metrics “soil porosity”, “soil cover”, and “soil organic matter”.
Professional judgment based on monitoring, and current science informs the direct and indirect
effects on the soil resource from the proposed alternatives.
In this document the direct and indirect effects are presented for three activity categories;
Vegetation Management (silvicultural and fuels prescriptions), Temporary Roads (Alternative
1 only) and Restoration Activities (Alternative 1 only). Each of the three metrics is assessed for
each activity category for the alternatives considered.
The alternatives considered in this analysis include Alternative 1; the Proposed Action,
Alternative 2: the No Action Alternative, and Alternative 3: the Non-Commercial Funding
Alternative. The primary difference between Alternative 1 and Alternative 3 (for the same
treatment activity area) is in the size of material removed. For the purpose of measuring the
metric for porosity, effective cover or organic matter as duff there is no notable change in the
Non-Commercial Funding Alternative as compared with the Proposed Action Alternative. There
would be a difference in downed logs as there would not be added criteria to increase the
minimum requirements for wildlife objectives. This is described further in S&G #55 and is
presented below in section 6.2.1.3.
Sagehen Project Soils Specialist Report January 16, 2013
20
6.2.1 DIRECT AND INDIRECT EFFECTS: VEGETATION MANAGEMENT
6.2.1.1 Soil Porosity: Effects from Vegetation Management
Each entry can result in incremental decreases in soil porosity, but the potential for a decrease in
porosity does not extensively result in detrimental compaction (a decrease of 10 % of natural soil
porosity conditions). Under 2.3.2 Monitoring and Impacts of Ground-Based Thinning
(Current Science and Monitoring) above, each proposed action has a variable potential for
additional decreases in porosity (degree).
Activities that rely on manual (hand thin, hand pile burning, and underburning) treatment only,
are not considered to have the same potential to affect porosity. There is some potential to affect
porosity through changes in bulk density after pile burning where bolewood greater than 15
inches is present in numerous pieces. However, since hand pile materials are generally smaller
with less than 14 inch pieces the majority of piles will not have numerous pieces greater than 15
inches. Therefore; the majority of assessment areas of concern for change in porosity are focused
on activities using mechanical equipment. The potential for compaction can vary based on the
type of equipment. Low ground pressure equipment often used for mastication and grapple piling
can have significantly lower incremental changes in compaction. Differences for the potential
acres of direct and indirect effects to soil porosity between alternatives are presented in Table 5.
Table 6 lists the general effects that may occur as a result of mechanical activities.
Multiple factors result in the potential variability of effects to decreases in soil porosity. This
variability is based on many factors including soil type. Some additionally heavily weighted
influencing factors are soil moisture, equipment used, and operator skill. The greatest control
over limiting the extent of detrimental compaction is obtained through: 1) operating over dry
soils, 2) reuse of exiting skid trials, 3) limited equipment tracking over the general operating area
(fewer than 3 passes of heavy equipment off of main trails), and 4) mitigating impact through
subsoiling in heavy traffic areas. Thus, some of the more critical protection measures that
minimize detrimental compaction in degree and extent include: 1) equipment limitation of
operations and dry soil requirements SMR (3) for uplands and SMR (4) and SMR (5) for
operations within the RCA (this also eliminates operations over areas with an equilibrated water
table at two feet), 2) to prevent cumulative additions of areas of soil deformation, reuse of
existing skid trails SMR (6) and landing systems SMR (10) where ever practical and when other
resource damage can be limited and 3) subsoiling of compacted areas according to SMR (12)
which is designed to mitigate areas of heavy compaction over landings and skid trails.
Comparison of Alternatives for Direct and Indirect to Soil Porosity from Vegetation
Management
A summary of the acres affected that will have a decrease in porosity over portions of the
activity areas are presented in Table 6. Within the activity area higher risk areas are mostly found
over skid trials, landings, and areas of heavy use of equipment tracking. Only a small portion of
these high use areas would be considered detrimentally compacted even though those higher use
areas will typically cover approximately 15 percent of the activity area unit.
Alternative 1: Proposed Action
There would be decreased porosity across mechanical treatment units with a potential for some
of the 2,190 acres to incur some degree of decreased porosity. The highest risk areas for
detrimental compaction are over skid trials, landings and heavily tracked areas. Assuming proper
Sagehen Project Soils Specialist Report January 16, 2013
21
implementation of SMR (3) for uplands and (4) and (5) within the RCA where the equipment
operations meet the operability criteria for dryness, the degree of detrimental compaction
exceeding 10 percent becomes primarily tied to heavily compacted landings and converging skid
trails near the landing. Where low levels of legacy compaction exist, these heavy tracked areas
tend to be below the threshold in extent. With SMR (12), the sub-soiling of some heavy use areas
mitigate compaction by lifting and fracturing the compacted soil. To prevent cumulative
additions of areas of soil deformation, reuse of existing main skid trails SMR (6) and landing
systems SMR (10) are required where ever practical and where other resource damage can be
limited.
Direct and indirect effects results in a potential for some of the mechanical treatment activity
area acres to incur some degree of decreased porosity. However levels of detrimental compaction
in degree or extent are designed to meet S&G#55 with proper implementation of the combination
of SMRs (3), (4), (5), (6), (7), (10), (11) and (12). Even high use areas at greatest risk for
detrimental compaction (estimated to be approximately 15 percent of the activity area or 329
acres) do not typically exceed the threshold in degree over the full extent of the activity area. Of
the 2,190 acres 976 acres in this action alternative activity area use the combination of thinning
and mastication and could potentially have fewer acres exposed to the heavy tracking where
mastication only occurs. Additional small areas of pile burning can increase bulk density but this
preliminary data (Hubbert et.al, 2010) did not provide a range of change that could be related to
the S&G for porosity. With implementation of the SMRs associated with this metric, S&G #55
for porosity would be met for the entries under this action alternative.
Sagehen Project Soils Specialist Report January 16, 2013
22
Table 5: General Potential Effects Related to Porosity for Proposed Activities
Proposed Action Activity Effects
1) Mechanical Thin and Aspen Restoration(Alt 1) Mechanical Thin
The greatest potential for decreases in porosity would occur over skid trails, landings, and heavy use areas of
equipment tracking. Small incremental decreases in soil porosity may occur in the general activity area where
equipment operates. However, areas with less than three passes are not likely to attain the degree or extent
defined as detrimental compaction in a single entry. Landings are typically detrimentally compacted in degree
over some portion of the area and are assessed for compaction following implementation. Landings and skid
trails that converge at the landings are sub-soiled as described in SMR (12) to increase infiltration and mitigate
the extent of compaction found in heavy use areas. See the additional mitigations listed above.
2) Grapple Pile and Pile
Burn;
Grapple piles can have concentrated equipment activities where piles are created that can decrease soil porosity;
however; equipment used are typically low ground pressure equipment so the degree of incremental changes in
porosity are of a low degree and may not attain levels defined as detrimental compaction (10% change in
porosity from natural soils). Similarly, areas with less than three passes are not likely to attain levels defined as
detrimental compaction. Piles are more likely to have bolewood and burn piles may burn hot enough to affect
bulk density but, this information was not related to soil porosity in the related study (Section 2.3.5). See
additional mitigations listed above.
3) Lop & Scatter, Mastication
Where mastication occurs prior to mechanical thinning or is the only mechanical treatment, the potential for
decreases in porosity is reduced because masticated material can cushion activities and minimize soil
compaction. It is impossible to estimate where decreases in porosity may occur in an activity area; however,
potential for decreases in porosity is lower over the general activity than for areas of mechanical thinning
particularly for areas treated exclusively by mastication. Since the mastication equipment is typically low
ground pressure equipment, main access routes are not likely to result in detrimental compaction in extent or
degree.
4) Pile Burning During burning of piles high temperatures and heat duration are mostly limited to the surface and 5 and 10 cm
depths beneath piles containing large bolewood (numerous fuels greater than 15 inches). Repellency at the soil
surface may occur under the large and mixed piles (fuels greater than 15 inches mixed with smaller fuels). Bulk
density increases under pile burn sites and infiltration is reduced on large and mixed pile burns, density but, this
information was not related to soil porosity in the related study (Section 2.3.5). Hand piles tend to be filled with
finer burn materials and thus are not likely to result in detrimental effects, but some increases in bulk density
and reduced infiltration could occur due to soil repellency. Repellency tends to begin to decrease after 3 to 22
months. Larger burn piles with large bole wood associated with thinning and grapple piling are more likely to
result in areas having reduced infiltration due to potential for larger fuels in the piles. (Note: impacts from
landings are combined in the assessment under mechanical thinning and similarly the impacts from grapple pile
burning are assessed under the grapple pile and burn impacts above).
Sagehen Project Soils Specialist Report January 16, 2013
23
Table 6: Comparison of Alternatives
Activity Areas Susceptible to Direct and Indirect Effects to Soil Porosity*
Proposed Action
Treatment
Activity
Alt. 1
(acres)
Activity Areas
Alt 1
Alt. 2
(acres)
Alt. 3
(acres)
Activity Areas
Alt 3
Mechanical
Thin/Grapple Pile
and Pile Burn;
Thin/Grapple Pile
and Pile
Burn/Underburn;
(Table 5 combined
effects of actions 1,
2, and 4).
717
33 (118 acres)
35 (63 acres)
36 (101 acres)
156 (84 acres)
163 (82 acres)
213(268 acres)
0 0 NA
Mechanical Thin;
Aspen
Restoration(Alt 1)
(Table 5 actions
1and 4).
1 85 EA-8 (1
acre)
Mechanical Thin;
Mechanical
Thin/Underburn;
(Table 5 combined
effects of actions 1,
and 4).
496
34 (68 acres)
38 (210 acres)
73 (144 acres)
89 (34 acres)
90 (40 acres)
0 0 NA
Mechanical Thin/
Lop & Scatter,
Mastication and
Mechanical Thin/
Lop & Scatter,
Mastication/
Underburn
(Table 5 combined
effects of actions 1,
3, and 4).
976
46 EA 5,6,7 :
(574 acres)
76 EA 5,6,7
(87 acres)
85 EA 5,6
(63 acres)
87
(207 acres)
99 EA 5, 6
(45 acres)
0 706
46 EA 5,6,7
(574 acres)
76 EA 5,6,7
(87 acres)
99 EA 5, 6
(45 acres)
Total 2,190 0 706
*While these areas are the total activity areas susceptible to decreases in porosity, the actual extent and
degree of decreased porosity that results in detrimental compaction is significantly smaller and
unpredictable. However, detrimental compaction is most likely to occur over some smaller portion of the
heavy use areas that would consist of less than 15% of the activity area.
EA-stands for the subunit emphasis area. More information on the subunit emphasis area can be found in
the Sagehen proposed action.
Sagehen Project Soils Specialist Report January 16, 2013
24
Alternative 2: No Action Alternative.
No detrimental disturbance that would affect existing levels of soil porosity is predicted to occur
from the no action alternative.
Alternative 3: Non -Commercial Funding. There would be decreased porosity across mechanical treatment units with a potential for some
of the 706 acres to incur some degree of decreased porosity. The highest risk areas for
detrimental compaction are over skid trials, landings and heavily tracked areas. Assuming proper
implementation of SMR (3) for uplands and (4) and (5) within the RCA where the equipment
operations meet the operability criteria for dryness, the degree of detrimental compaction
exceeding 10 percent becomes primarily tied to heavily compacted landings and converging skid
trails near the landing. Where low levels of legacy compaction exist, these heavy tracked areas
tend to be below the threshold in extent. With SMR (12), the sub-soiling of some heavy use areas
mitigate compaction by lifting and fracturing the compacted soil. To prevent cumulative
additions of areas of soil deformation, reuse of existing main skid trails SMR (6) and landing
systems SMR (10) are required where ever practical and where other resource damage can be
limited.
Direct and indirect effects results in a potential for some of the mechanical treatment activity
area acres to incur some degree of decreased porosity. However levels of detrimental compaction
in degree or extent are designed to meet S&G#55 with proper implementation of the combination
of SMRs (3), (4), (5), (6), (7), (10), (11) and (12). Even high use areas at greatest risk for
detrimental compaction (estimated to be approximately 15 percent of the activity area or 106
acres) do not typically exceed the threshold in degree over the full extent of the activity area.
Because this action alternative uses the combination of thinning and mastication fewer acres may
be exposed to the heavy tracking where mastication only occurs. Additional small areas of pile
burning can increase bulk density but this preliminary data (Hubbert et.al, 2010) did not provide
a range of change that could be related to the S&G for porosity. With implementation of the
SMRs associated with this metric, S&G #55 for porosity would be met for the entries under this
action alternative.
6.2.1.2 Effective Soil Cover (ESC): Effects from Vegetation Management
Soil cover monitoring results from past actions show that soil productivity is maintained when
minimum effective soil cover standards are met on the East Side Forests (Current Science 2.3.6).
Thus soil erosion is largely prevented. Each proposed action has a variable potential for reducing
existing soil cover to the point where the site may not provide effective erosion control and can
lead to sediment transport. Differences between alternatives are provided in Tables 8A and 8B.
Table 7 lists the general effects that may occur as a result of proposed action activities.
The most effective protection measures that provide for effective soil cover include: The
elements of an erosion control plan as described in SMR (22) which includes provisions for
effective erosion control/ground cover requirements SMR (16) (17), mulching skid trails SMR
(8), erosion prevention SMR (16), timing of erosion control SMR (22), and burn prescription
requirements (18). Other SMRs contained in the Sagehen Project Environmental Assessment,
Standard Management Requirements (SMRs), Appendix A. include additional provisions that
contribute to attaining ESC. With implementation of the SMRs associated with this metric, S&G
#55 for ESC would be met for the entries under this action alternative.
Sagehen Project Soils Specialist Report January 16, 2013
25
Table 7: General Potential Effects Related to Effective Soil Cover (ESC) for Proposed Activities
Proposed Action Activity Direct and Indirect Effects
1) Mechanical Thin
Variable results in depth of cover would occur over the activity area. Areas with increases in slash and needle cast can occur in units due to breakage and other areas would see reductions in cover particularly occurring over skid trails, landings, and in landing burn piles. Monitoring on recent projects shows that generally activity areas would meet minimum SQS for ESC (Current Science and Monitoring 2.3.6 - F25, T04, T06). Risk for areas with reduced ground cover is primarily limited to landings, since needle cast may only be available on the perimeter to re-supply ground cover until re-vegetated. Some landing burn piles do not result in complete combustion and remaining fuels are redistributed as ground cover, or in some cases chips will be scattered across the landing. Management requirements that maintain minimum ESC include SMR (22) erosion control plan, erosion control measures/groundcover requirements SMR (16) and (17), mulching of skid trails SMR (8), erosion prevention SMR (16), timing of erosion control SMR (22).
2) Grapple Pile and Pile Burn
Risk for areas with reduced cover is primarily limited to large burn piles, since needle cast may only be available on the perimeter to re-supply ground cover. With smaller scattered piles, the extent of low ground cover would be less than 15 percent. Some piles do not result in complete combustion and remaining fuels are redistributed as ground cover. Since the burn pile areas tend to be scattered and discontinuous they do not typically result in soil erosion. Monitoring on recent projects shows that generally activity areas would meet SQS for ESC (Current Science and Monitoring 2.3.6, F25, T04, T06). Management requirements that maintain minimum ESC include erosion control measures/ground cover requirements SMR (16) and (17), mulching of skid trails SMR (8), erosion prevention SMR (16), timing of erosion control and erosion control plan SMR (22), and burn prescription requirements SMR (18).
3) Aspen Restoration: Mechanical Thin
Variable reductions in existing soil cover from end lining and skid trails and landings use would occur. A portion of the Aspen Restoration area would be end lined to the road. Monitoring on recent projects shows that generally activity areas would meet SQS for ESC (Current Science and Monitoring 2.3.6 – F25, T04). Management requirements that maintain minimum ESC include erosion control measures/ground cover requirements SMR (16) and (17), mulching of skid trails SMR (8), erosion prevention SMR (16), timing of erosion control and erosion control plan SMR (22).
4) Lop & Scatter, Mastication
Mastication results in redistribution of ladder fuels to ground fuels increasing soil cover over large portions of the activity area. Thus the activity area would likely exceed minimum ESC requirements for both percent soil cover and extent. Risk for developing ineffective soil cover is unlikely.
5) Mastication Underburn
Underburning of masticated units is relatively new. Little underburning of masticated units have occurred on the district. However, the Truckee District fuels officer Linda Ferguson has experience in successful implementation of burning masticated fuels (personal communication, February, 2012). Risk for negative impacts as soil erosion is low. Final disposition of the site would result with areas where existing soil cover would be increased in locations while fuels consumption could decrease to levels of existing cover or reduced cover in some locations. The minimum ESC would be met across the extent of the activity area, and would be exceeded in degree in some locations.
Sagehen Project Soils Specialist Report January 16, 2013
26
Table 7: General Potential Effects Related to Effective Soil Cover (ESC) for Proposed Activities
Proposed Action Activity Direct and Indirect Effects
6) Underburn It is estimated that 60 percent to 80 percent of an activity area would result in surface fire effects through underburning. Heavier fuels may burn hotter and variable reduction in existing cover across the activity area would occur. Monitoring results show that generally activity areas meet minimum ESC (Current Science and Monitoring 2.3.6, F25, T04, T06). Typically areas treated will retain adequate canopy cover that can quickly restore ground cover. Needle cast will improve areas of low soil cover either by the fall season or within a year or so. Monitoring on recent projects shows that generally activity areas would meet SQS for ESC, so no substantive negative impacts from soil erosion are expected (Current Science and Monitoring 2.3.6, F25).
7) Hand Thin/ Pile Burn; Aspen Restoration (Hand Thin, Hand
Pile and Burn)
Variable reductions in existing soil cover would occur. Existing levels of effective soil cover may be reduced under burn piles. The extent would be less than 15 percent of the activity area (Current Science and Monitoring 2.3.4). Some piles do not result in complete combustion and unburned fuels remain as ground cover. Since the burn pile areas tend to be scattered and discontinuous they do not typically result in soil erosion. Typically areas with canopy cover recover with needle cast by the fall season or within a year or so. Monitoring on recent projects shows that generally activity areas would meet SQS for ESC so no negative impacts from soil erosion are expected (Current Science and Monitoring 2.3.6, F25).
Sagehen Project Soils Specialist Report January 16, 2013
27
Table 8 A: Comparison of Alternatives
Maximum Potential Acres Exposed to Variable Decreases in Existing Effective Soil Cover*
Proposed Action Treatment Activity
Alt 1 Acres
Activity Areas Alt 1
Alt 2 Acres
Alt 3 Acres
Activity Areas Alt 3
Mechanical Thin/Grapple Pile and Pile Burn (Table 7 combined effects of actions 1 and 2).
635
33 (118 acres) 35 (64 acres)
36 (101 acres) 156 (84 acres)
213 (268 acres)
0 0
N/A
Mechanical Thin/Grapple Pile and Pile Burn/Underburn (Table 7 combined effects of actions 1, 2, and 6).
82
163 (82 acres)
0 0
N/A
Mechanical Thin/Underburn (Table 7, combined effects of actions 1 and 4).
496
34 (68 acres) 38 (210 acres)
73 (144 acres)
89 (34 acres) 90 ( 40 acres)
0 0
N/A
Aspen Restoration Mechanical Thin (Table 5, effects of action 3).
1
85
0 0
N/A
Underburn (Table 7 effects of action 6).
116
39 (32 acres) 46 EA-4
(47 acres) 47 (33 acres)
76 EA-4 (4 acres)
0 84
46 EA-4 (47 acres)
47 (33 acres) 76 EA-4 (4 acres)
Hand Thin/Pile Burn/Underburn (Table 7, combined effects of action 7 and 6).
248
61 (20 acres) 100 (120 acres) 282 (108 acres)
0 248
61 (20 acres) 100 (120 acres) 282 (108 acres)
Hand Thin/Pile Burn (Aspen Restoration –Alt1) Hand Thin, Hand Pile and Pile Burn (Table 7 effects of action 7).
99
80 (5 acres) 91 (9 acres)
98 (63 acres) 99 EA -1,2,4 (22 acres)
0 94
91 (9 acres) 98 (63 acres) 99 EA -1,2,4 (22 acres)
Sagehen Project Soils Specialist Report January 16, 2013
28
Table 8 A: Comparison of Alternatives
Maximum Potential Acres Exposed to Variable Decreases in Existing Effective Soil Cover*
Proposed Action Treatment Activity
Alt 1 Acres
Activity Areas Alt 1
Alt 2 Acres
Alt 3 Acres
Activity Areas Alt 3
Total 1,677 0 426
EA-stands for the subunit emphasis area. More information on the subunit emphasis area can be found in the Sagehen proposed action.
* While these acres would see a potential change in existing ESC, with implementation of the SMRS minimum ESC is expected to be attained after each action is implemented.
Table 8 B: Comparison of Alternatives
Maximum Potential Acres Exposed to Variable Decreases and Increases in Existing Effective Soil Cover
Mechanical Thin, Lop & Scatter, Mastication (Table
7, combined effects of actions 1, and 4).
315
85 EA – 5,6 (63 acres)
87 (207 acres) 99 EA -5,6, (45 acres)
0 45 99 EA -5,6, (45 acres)
Mechanically Thin, Lop & Scatter, Mastication, Underburn (Table 7, combined effects of actions 1, 4 and 5).
661
46 EA-5,-6,-7 (574 acres)
76 EA – 5,6,7 (87 acres)
0 661
46 EA-5,-6,-7 (574 acres)
76 EA -5,6,7, (87 acres)
Total 976 0 706
EA-stands for the subunit emphasis area. More information on the subunit emphasis area can be found in the Sagehen proposed action.
Implementation of any part of the activity without completion of the whole action can cause variability. In particular, stages of increased ground fuels may be present for some time after thinning in some units(estimated 1-5 years) prior to final implementation of phases of the proposed action such as grapple piling or underburning.
* While these acres would see a potential change in existing ESC, with implementation of the SMRS minimum ESC is expected to be attained after each action is implemented.
Sagehen Project Soils Specialist Report January 16, 2013
29
Comparison of Alternatives for Direct and Indirect Effects to Effective Soil Cover from
Vegetative Management
A summary of the acres potentially affected that could have a decrease in existing soil cover is
presented in Table 8A above. Table 8B displays acres that could potentially have both increases
and/or decreases from the existing soil cover. The minimum ESC would be attained to maintain
productivity after each action is implemented. Because each of these activities within an activity
area may be separated by a few to several years, ground cover commonly accumulates prior to
implementation of the phase of the prescription. Additionally, in cases where grapple piling is
prescribed there are potentially areas of heavy pockets of ground cover that may be present after
thinning and prior to any follow up prescription.
Alternative 1: Proposed Action.
Existing levels of ground cover would have the potential to be reduced over portions of 1,677
activity area acres. Areas with ground cover levels reduced to mineral soil can occur in burn
piles. Areas with scattered burn piles will occur over a portion of 1,060 activity area acres. The
Tahoe Basin determined project area hand piles generally take up less than 15 percent of the
treatment area and we know through experience not all piles would reduce existing cover to bare
mineral soil (Section 2.3.5). Additionally, areas of heavy equipment use can affect ground cover
and usually occur on skid trails, landings and turning zones. This heavy equipment use area is
typically found over approximately 15 percent of the activity area associated with mechanical
thin prescriptions. However, only a small portion of these areas are reduced below effective soil
cover after implementing SMRs. The SMR requirement to meet ESC is to attain the minimum
requirements for erosion control prior to the winter season. There are a potential 2,190
mechanically thinned activity area acres that may incur some mechanical equipment disturbance.
Out of these 2,190 mechanical thin acres, 976 acres are also exposed to variable potentials for
increased ground cover in masticated portions of these units. There would also be areas with
reduced levels of pre-existing ground cover across portions of a potential 1,516 activity area
acres through underburning. It is estimated that 60 percent to 80 percent of an activity area
prescribed for underburning would actually be underburned. Because each entry by type of
action within an activity area may be separated by a few to several years, ground cover
commonly accumulates prior to implementation of the phase of the prescription.
As presented in Current Science and Monitoring 2.3.6 above, the BMPs (F25, T04, T06) were
shown to be effective in protecting water quality by preventing erosion, thus soil cover is shown
to be effective by controlling erosion. This monitoring shows that when the standards are met the
extent of reduced soil cover is commonly adequate to control erosion. Although multiple actions
may result in various degrees of change in existing soil cover, over the sequence of
implementation the SMRs applied after each implementation sequence bring the site back to
minimum standards. ESC requirements are designed to meet or exceed S&G#55. With
implementation of the SMRs associated with this metric, the S&G for ESC will be met for the
entries under this action alternative.
Alternative 2: No Action
There are no actions that will affect effective soil cover.
Sagehen Project Soils Specialist Report January 16, 2013
30
Alternative 3: Non -Commercial Funding. Existing levels of ground cover would have the potential to be reduced over 426 activity area
acres (1,251 fewer acres than Alternative 1). Areas with ground cover levels reduced to mineral
soil can occur in burn piles. Areas with scattered burn piles will occur over a portion of 342
activity area acres (722 fewer acres than Alternative 1). The Tahoe Basin determined that project
area piles generally take up less than 15 percent of the treatment area and not all piles would
reduce cover levels to mineral soil (Section 2.3.5). Other areas of heavy equipment use
(mechanical equipment) can affect ground cover and usually occur on skid trails, landings and
turning zones. This heavy equipment use area is typically found over approximately 15 percent
of the activity area associated with mechanical thin disturbance. However, only a small portion
of these areas are reduced below effective soil cover after implementing SMRs. The SMR
requirement to meet ESC is to attain the minimum requirements for erosion control prior to the
winter season. There are a potential 796 activity area acres that may incur this type of
disturbance (1,484 fewer acres than Alternative 1). The 706 mechanical thin acres will also be
exposed to variable potentials for increased ground cover in masticated portions of these activity
areas. It is estimated that 60 percent to 80 percent of an activity area would undergo under
burning resulting in areas with decreased ground cover across a potential 906 activity area acres
(610 fewer acres than Alternative 1). Some areas of low ground cover may be created through
under burning. There are 661 of these acres that are exposed to variable potentials for decreases
or increases in existing ground cover in the underburned mastication units (942 fewer acres than
Alternative 1).
As presented in Current Science and Monitoring 2.3.6 above, the BMPs (F25, T04, T06) were
shown to be effective in protecting water quality and preventing erosion, thus activity areas
meeting minimum ESC are shown to be effective in controlling erosion. Although multiple
actions may result in various degrees of existing soil cover over the sequence of implementation,
the SMRs applied after each implementation sequence bring the site back to minimum standards.
ESC requirements are designed to meet or exceed S&G#55. With implementation of the SMRs
associated with this metric, the S&G for ESC will be met for the entries under this action
alternative.
6.2.1.3 Organic Matter Changes from Vegetation Management
Forest Duff
Duff would have the potential to be reduced over the activity area acres. Areas with duff levels
reduced to mineral soil can occur in burn piles, or areas of hot underburning. Other areas of
heavy equipment use can affect duff and usually occur on skid trails, landings and turning zones.
For units proposing to be underburned it is estimated that 60 percent to 80 percent of an activity
area would undergo underburning resulting in areas with surface char of duff across those
portions of the activity area. Surface char that is not consumed is not considered disturbed duff.
(3.1.3.2 Standard for Forest Duff). Areas of no silviculture treatments including most Dense
Cover Areas (DCAs) combined with undisturbed areas would result in maintaining at least 20
percent undisturbed duff across the activity area. The general effects on forest duff from
Sagehen Project Soils Specialist Report January 16, 2013
31
vegetation management are included in Table 9 below. The extent of the impact is designed to
meet S&G#55 and productivity would be maintained.
Findings related to underburning of masticated fuels show that when spring and early summer
burns have duff with moisture levels above 30 percent little duff is consumed. For most site
conditions it will be desirable to char the top layer of duff. Similarly, when allowing a backing
fire into fens, meadows or perennial systems such as springs, measures to ensure duff moisture
levels are high enough to minimize impacts of burning peat and other wet system soil organic
matter would be implemented. The ignition plan for burning around fens, springs and hydric
systems will be limited to times when the system is not undergoing lengthy and extreme drought
conditions, but decisions would be based on site specific conditions (SMR 18).
Sagehen Project Soils Specialist Report January 16, 2013
32
Table 9: Direct and Indirect Effects to Forest Duff
Proposed Activity Actions Effects
1) Mechanical Thin and Aspen Restoration(Alt 1) Mechanical Thin
Variable intensities of disturbance would reduce existing duff depth. Areas of heavy equipment use can affect duff and usually occur on skid trails, landings and turning zones. With designed areas of exclusions including DCAs, and with operationally undisturbed areas and resource exclusion areas, units typically exceed the 20 percent undisturbed duff across the activity area. In aspen treatment activity areas as the aspen expand, soil organic matter would improve due to the relatively quick decay process associated with deciduous Aspen leaves. Indirectly soil duff would increase with the increase of Aspen expansion and health (Current Science and Monitoring 2.3.8).
2) Grapple Pile and Pile Burn
Variable intensities of disturbance would reduce existing duff depth. Areas of heavy equipment use can affect duff. Minimizing turning, and maintaining operations off steep slopes reduces duff disturbance (SMR 3). The objective of grapple piling is to pick up larger fuels and allow the finer materials and duff to remain in place. Areas with duff levels reduced to mineral soil can occur in burn piles. Burn pile areas tend to be scattered and discontinuous. With designed areas of exclusions including DCAs, and with operationally undisturbed areas and resource exclusion areas units, maintain the 20 percent undisturbed duff across the activity area.
3) Lop & Scatter, Mastication
Under mastication activities areas of duff typically would be retained below the masticated materials and would result in maintaining more than 20 percent undisturbed duff across the activity area. Additions of masticated material could result in increasing cover that may hide duff or previously disturbed areas.
4) Mastication, Underburn
Variable intensities of disturbance would result. It is estimated that 60 percent to 80 percent of an activity area would
undergo underburning. This results in areas with surface char of duff across portions of the activity area and randomly
smaller areas where the duff may have consumption to bare soil. As described in section 3.1.3.2 above, surface char is not considered disturbed duff unless fully consumed. Additions of masticated material could result in areas increasing cover that may hide duff or previously disturbed areas. The results for underburning of masticated fuels show when spring and early summer burns have duff with moisture levels around 20 percent limits damaging temperatures and little heat penetration occurs to surface soils during late spring and early summer burns. (Current Science and Monitoring 2.3.7). With little heat penetration to duff at the soils surface little affect to existing duff would occur.
5) Underburn It is estimated that 60 percent to 80 percent of a prescribed burn activity area would be affected by prescribed underburning
resulting in a mosaic of areas with surface char of duff and random areas where the duff may be consumed to bare soil. As described in section 3.1.3.2 above, surface char is not considered disturbed duff unless consumed. Based on the monitoring results from prescribed burning through regional BMPEP monitoring (F25), and based on observations per Randy Westmoreland, Tahoe NF East Side Soil and Water Resource Manager; on an activity area basis, undisturbed duff is maintained over more than 20 percent across the activity area (personal communication, 2010).
Sagehen Project Soils Specialist Report January 16, 2013
33
Table 9: Direct and Indirect Effects to Forest Duff
Proposed Activity Actions Effects
6) Hand Thin/ Pile Burn and Aspen Restoration – Hand Thin, Hand Pile and Pile Burn
Areas with duff levels reduced to mineral soil can occur in burn piles. The burn pile areas tend to be scattered and discontinuous; piles generally take up less than 15 percent of the treatment area. With designed areas of exclusions including DCAs, and with operationally undisturbed areas and resource exclusion areas activity areas maintain greater than the 20
percent undisturbed duff across the activity area. While the aspen activity area here will be treated using hand thinning, the
existing soil characteristics are already influenced by a surrounding stand of aspen, so the change in soil duff in this stand would not be as notable as for the mechanically treated aspen activity area. Hand falling large trees may disturb duff where trees are dragged to a skid trail. The measures to repair drag lines are included in SMR (17). These areas are dispersed and infrequent and typically only used in areas near wet features. The activity area would not exceed the standards for forest duff.
Sagehen Project Soils Specialist Report January 16, 2013
34
Table 10: Comparison of Alternatives
Maximum potential acres exposed to variable decreases in existing forest duff*
Proposed Action Treatment Activity
Alt 1 Acres
Activity Areas Alt 1
Alt 2 Acres
Alt 3 Acres
Activity Areas Alt 3
Mechanical Thin/Grapple Pile and Pile Burn (Table 9 combined effects of actions 1 and 2) and Mechanical Thin/Grapple Pile and Pile Burn/Underburn (Table 9 combined effects of actions 1, 2 and 5).
717
33 (118 acres) 35 (64 acres)
36 (101 acres) 156 (84 acres)
213 (268 acres)
0 0 N/A
Mechanical Thin/Underburn (Table 9, combined effects of actions 1 and 4).
496
34 (68 acres) 38 (210 acres)
73 (144 acres)
89 (34 acres) 90 ( 40 acres)
0 0 N/A
Aspen Restoration Mechanical Thin (Table 9, effects of action 3).
1
85
0 0 N/A
Mechanical Thin, Lop & Scatter, Mastication (Table 9, combined effects of actions 1, and 4).
315
85 EA – 5,6 (63 acres)
87 (207 acres) 99 EA -5,6, (45 acres)
0 135 99 EA -5,6, (45 acres)
Mechanically Thin, Lop & Scatter, Mastication, Underburn (Table 9, combined effects of actions 1, 4 and 5).
661
46 EA-5,-6,-7 (574 acres)
76 EA – 5,6,7 (87 acres)
0 574
46 EA-5,-6,-7 (574 acres)
76 EA -5,6,7, (87 acres)
Underburn (Table 9 effects of action 6).
116
39 (32 acres) 46 EA-4
(47 acres) 47 (33 acres)
76 EA-4 (4 acres)
0 80
46 EA-4 (47 acres)
47 (33 acres) 76 EA-4 (4 acres)
Hand Thin/Pile Burn/Underburn (Table 9, combined effects of action 7 and 6).
248
61 (20 acres) 100 (120 acres) 282 (108 acres)
0 247 61 (20 acres)
100 (120 acres) 282 (108 acres)
Sagehen Project Soils Specialist Report January 16, 2013
35
Table 10: Comparison of Alternatives
Maximum potential acres exposed to variable decreases in existing forest duff*
Proposed Action Treatment Activity
Alt 1 Acres
Activity Areas Alt 1
Alt 2 Acres
Alt 3 Acres
Activity Areas Alt 3
Hand Thin/Pile Burn (Aspen Restoration –Alt1) Hand Thin, Hand Pile and Pile Burn (Table 9 effects of action 7).
100
80 (5 acres) 91 (9 acres)
98 (63 acres) 99 EA -1,2,4 (22 acres)
0 94
91 (9 acres) 98 (63 acres) 99 EA -1,2,4 (22 acres)
Total 2,654 0 1,130
EA-stands for the subunit emphasis area. More information on the subunit emphasis area can be found in the Sagehen proposed action.
* While these acres would see a potential change in existing Forest Duff with implementation of the SMRS minimum ESC is expected to be attained.
Comparison of Alternatives for Direct and Indirect Effects to Forest Duff from Vegetation
Management
Reductions in duff would be expected to occur at differing levels across activity areas. The acres of
activity area potentially affected by reduction in duff are presented by alternative in Table 10.
Alternative 1: Proposed Action.
Existing levels of duff would have the potential to be reduced over portions of 2,654 activity area
acres. Areas with duff levels reduced to mineral soil can occur in burn piles. Areas with scattered
burn piles will occur over a portion of 1,066 activity area acres. Other areas of heavy equipment use
can affect duff and usually occur on skid trails, landings and turning zones. This disturbance is
typically found over 15 percent of the activity area associated with mechanical disturbance, but not
all of the area is considered to have affected the duff to mineral soil. There are approximately 2,190
activity area acres that may create disturbed duff from thinning. Of those mechanically thinned
acres there are 975 acres that are exposed to variable potential increases in long-term duff
development and the potential for disturbed duff is decreased where mastication occurs prior to
thinning. It is estimated that 60 percent to 80 percent of an activity area prescribed with
underburning would result in areas with surface char of duff across 1,507 activity area acres. Some
areas of disturbed duff may be created through underburning; however, it is not considered
disturbed duff unless it consumes the duff and exposes the mineral soil. Areas of exclusions due to
operability or inclusion for DCAs combined with the areas meeting the undisturbed duff description
would result in maintaining 20 percent undisturbed duff across the activity areas. Monitoring has
shown adequate levels of duff are maintained after implementing these activities. With
implementation of the SMRs associated with this metric, the S&G for forest duff will be met for the
entries under this action alternative.
Sagehen Project Soils Specialist Report January 16, 2013
36
Alternative 2: No Action
There are no actions that will affect existing forest duff.
Alternative 3: Non -Commercial Funding. Existing levels of duff would have the potential to be reduced over 1,130 activity area acres (1,255
fewer acres than Alternative 1). Areas with duff levels reduced to mineral soil can occur in burn
piles. Areas with scattered burn piles will occur over 344 activity area acres (722 fewer acres than
Alternative 1). Other areas of heavy equipment use (mechanical equipment) can affect duff and
usually occur on skid trails, landings and turning zones. This disturbance is typically found over
approximately 15 percent of the activity area associated with mechanical thinning. There are a
potential 709 activity area acres that may incur this type of disturbance (1,948 fewer acres than
Alternative 1) and these areas are also to be treated by mastication. If mastication occurs prior to
thinning the potential for disturbing existing duff is further reduced.
In areas that are underburned it is estimated that 60 percent to 80 percent of an activity area would
undergo under burning resulting in areas with surface char of duff across a potential 902 activity
area acres (605 fewer acres than Alternative 1). Some areas of disturbed duff may be created
through under burning; however, it is not considered disturbed duff unless it exposes the mineral
soil. Areas of exclusions due to operability or inclusion for DCAs combined with the areas meeting
the undisturbed duff description would result in maintaining 20 percent undisturbed duff across the
activity area. While the various proposed actions have more than one entry that may reduce areas of
existing duff depth, there are few activity as a whole which tend to remove duff to the extent that it
is reduced to mineral soil over a large extent of the activity area, therefore, the proposed action is
expected to meet requirement limits for disturbed duff and result in maintaining 20 percent
undisturbed duff across the activity areas. Monitoring has shown adequate levels of duff are
maintained after implementing these activities. With implementation of the SMRs associated with
this metric, the S&G for forest duff will be met for the entries under this action alternative.
.
Large Woody Material from Fuels Treatment and Vegetation Management
The proposed action alternative, Alternative 1, has based the desired conditions for large woody
material on the desired conditions for wildlife. Thus the criteria for downed wood was created for
each emphasis area, so under the assessment for Alternative 1 the results are presented by emphasis
area.
The emphasis area objective criteria, based on wildlife needs differ slightly from the soils standards
for large downed wood. As described in the methods section above, the wildlife criteria are
designed to retain the largest available logs accepting a minimum 15 inch diameter log that is at
least 10 feet in length. The soil standard relies on a preference for a 20 inch diameter log at least 10
feet in length.
In order to quantify the proposed actions intent in meeting large woody material three categories
were developed; 1) exceeds the large woody material standard, 2) meets the intent for large woody
material in downed logs, and 3) meets the intent for large woody material having adequate smaller
logs, merchantable wood, or other woody material.
Sagehen Project Soils Specialist Report January 16, 2013
37
The criteria for Alternative 1 are based on the following logic:
Meets the large woody material standard in logs: Where the 5 largest logs (at greater than15
inch diameter and 10 feet in length) also meet the standard for 200 cubic feet to 800 cubic feet per
acre, (additional smaller logs, merchantable wood, or other woody material), these 5 logs per acre
will be considered to meet the intent for large woody material.
Exceeds the large woody material standard: Where the objective is in excess of the 5 largest
logs (at greater than 15 inches in diameter and 10 feet in length), the activity area will be considered
to exceed the standard. The target for Emphasis Areas 1 and 2 is to retain 15 to 20 of the largest
logs per acre.
Meets the large woody material standard as other woody material: Where less than 5 logs per
acre (the largest logs greater than 15 inches in diameter and 10 feet in length) are to be retained, the
activity area acres meet large woody material guidelines primarily based on retaining adequate
smaller logs, merchantable wood, or other woody material at a rate of 200 cubic feet to 800 cubic
feet per acre particularly when no large logs are available (this volume equates to approximately 2.3
to 10 tons per acre depending on density).
The objectives by emphasis area were reviewed to see how many acres would exceed large woody
material retention, meet large woody material (based on retaining 5 of the largest pieces at least 15
inches in diameter and 10 feet long), or acres that meet large woody material based on retaining
adequate smaller logs, merchantable wood, or other woody material at a rate of 200 cubic feet to
800 cubic feet per acre when no large logs are available (approximately 2.3 to 10 tons per acre
depending on density).
The criteria for Alternative 3 are based on the following logic:
For Alternative 3 the objective is to meet the S&G #55, so the consideration is limited to 5 downed
logs where large downed wood criteria can be met based on availability, or based on other woody
material. These objectives (based on retaining 5 of the largest pieces at least 20 inches in diameter
and 10 feet long where available, or retention of adequate smaller logs, merchantable wood, or other
woody material at a rate of 200 cubic feet to 800 cubic feet per acre when no large logs are
available (approximately 2.3 to 10 tons per acre depending on density). Much of the area will only
meet the merchantable wood, or other woody material at a rate of 200 cubic feet to 800 cubic feet
per acre when no large logs are available (approximately 2.3 to 10 tons per acre depending on
density) as the larger wood pieces are unavailable over many of the activity areas prescribed under
this alternative.
Sagehen Project Soils Specialist Report January 16, 2013
38
Comparison of Alternatives for Direct and Indirect Effects to Large Woody Material from
Vegetation Management
Alternative 1: Proposed Action
Emphasis Area 1 (Activity Area 33, 35, 38, 61, 98, 99, 100, 156,163 and 213) result in a total of
453 acres where the large woody material objective exceeds the standard with the intention of
averaging 15 downed logs/acre.
Emphasis Areas 2 and 4 (Activity Area 33, 35, 36, 38, 46, 61, 73, 76, 89, 91, 98, 99, 100, 213 and
282) have a total of 276 acres where large woody material exceeds the standards. On 173 acres the
objective is to attain an average of 10 downed logs/acre in Activity Area 33, 35, 36, 38, 46, 73, 76,
89, 99, 100, and 213. On 103 acres the objective is to attain an average of 20 downed logs/acre in
Activity Areas 61, 91, 98, 99, 100, 213, and 282.
Emphasis Area 5 has 1,028 acres (Activity Area 33, 34, 35, 36, 38, 39, 46, 47, 73, 76, 85, 87, 98,
99, 100, 163, and 213) where the objective is to meet the standard for an average of 5 downed
logs/acre.
Emphasis Area 6 and 7 have 890 acres that meet large woody material with adequate tons/acre of
and smaller logs, merchantable wood, or other woody material. The emphasis for these areas for fire
and fuels.(Activity Area 33, 34, 35, 36, 38, 46, 73, 76, 85, 87, 89, 90, 99, 100, 163, 213 and 282).
Emphasis Area 8 has 6 acres where the objective is to meet the large woody material with adequate
tons/acre and smaller logs, merchantable wood, or other woody material. The emphasis is on aspen
restoration. The activities, particularly in activity area 80 where there are 5 acres of hand treatment,
would not result in changing the exiting downed large wood.
In addition to the requirement for downed wood there are requirements for creating short snags in
emphasis areas 1 through 6 subunits with silvicultural prescriptions that include existing DCAs.
These subunits are located outside the Sagehen Project’s plantations. To create short snags,
approximately two live trees per acre of DCA, greater than 15 inches dbh, would be cut at a height
of ten to 20 feet above the ground. White fir would be the preferred cut species. Felled portions of
these cut trees would be retained on site. These proposed activities have the capability of
supplementing downed wood to meet objectives on 725 acres.
Based on the objectives for large downed wood, Alternative 1 would exceed large wood criteria
over 729 acres in emphasis areas 1, 2 and 4. It would meet the large wood criteria over 1,028 acres
in emphasis area 5, and meet the objective for tons per acre through smaller logs, merchantable
wood, or other woody material on 896 acres in emphasis areas 6, 7, and 8. It should be recognized
that these objectives are based on data that have high variability and therefore the average obtained
over an activity area would not be likely to be observed over every acre, but should be expected to
be clumpy and variable based on existing conditions. There would be cases where increases in
downed logs would occur in emphasis areas 1 through 6 through short snag creation in DCAs. Some
existing downed logs would be decreased from areas where grapple piling and fuels objectives are
designed to reduce fuel loading. With implementation of the SMRs associated with this metric, the
S&G for large woody material will be met for the entries under this action alternative.
Sagehen Project Soils Specialist Report January 16, 2013
39
Alternative 2: No Action
There are no actions that will affect existing large woody material.
Alternative 3: Non -Commercial Funding.
Acres that would be treated are less likely to have large changes to the existing downed wood
because the treatment area is limited primarily to plantations that are already low in downed wood
volumes. Hand thinning would not create an extensive effect on large downed wood but, prescribed
underburning in hand thinning units could consume some logs. There are 993 acres that will
undergo underburning and may reduce some existing downed wood. There are 574 activity acres
prescribed for underburning in masticated acres. There are 80 acres that will undergo underburning
only and may reduce some existing large down wood; however, the minimum down wood
objectives would meets the intent for large woody material having adequate smaller logs,
merchantable wood, or other woody material. With the redistribution of fuels from ladder to ground
fuels it is expected these areas will easily meet the objective in masticated and masticated and
underburned treatment areas. With implementation of SMR (39), large wood will be lined to
achieve objectives and 30 % of the activity area that remain unburned would also contribute to
downed wood retention. There are 94 acres of hand pile and pile burn acres that would not be
expected to affect existing pieces of large downed wood and is designed to meet the S&G # 55 for
large wood with areas meeting the large downed wood (through existing pieces) and some of those
areas meeting the objective for tons per acre through smaller logs, merchantable wood, or other
woody material.
Based on the proposed action for Alternative 3 large woody material would not be changed over
1,521 acres as compared to Alternative 1. Acres that would be treated are less likely to have large
changes to the existing downed wood because the treatment area is limited primarily to plantations
that are already low in downed wood volumes. Hand thinning would not affect large downed wood
but, prescribed underburning in hand thinning units could consume some logs. A total of 1,131
acres would meet the objective for large wood primarily by meeting tons per acre through smaller
logs, merchantable wood, or other woody material. With implementation of the SMRs associated
with this metric, the S&G for large woody material will be met for the entries under this action
alternative.
Sagehen Project Soils Specialist Report January 16, 2013
40
6.2.2 DIRECT AND INDIRECT EFFECTS TEMPORARY ROADS
6.2.2.1 Soil Porosity: Effects from Temporary Roads.
There would be detrimental compaction on temporary roads over 3.8 miles on approximately 5.5
acres (with no need for a borrow site) for a period of approximately 5-years until the road is put to
bed. Temporary roads are required to be designed to minimize construction length and width (SMR12) and
also follow the provisions of traffic control wet periods SMR(20). Following use they are sub-soiled,
roadside berms with mineral soil are pulled back in, and drainage is provided to create a hydrologically
neutral state (SMR 21). Sub-soiling lifts and fractures the soil rather than turning the soil, as occurs when
tilling. This results in reduced mixing of the soil maintaining any developed structure of the soil. Most of
these sub-soiled temporary roads start showing signs of some vegetative recovery after 5 years. Provisions
that require decommissioned roads to be sub-soiled are included in SMR (21). Compaction from
temporary roads are assessed for the hydrologic properties in the Water Resource Effects ERA analysis.
6.2.2.2 Effective Soil Cover: Effects from Temporary Roads
There would be 3.8 miles of temporary road built on approximately 5.5 acres (with no need for a
borrow site) having decreased effective soil cover for a period of approximately 5-years until the
road is put to bed. Post operation requirements include pulling the berm where duff and soil was
displaced during construction back onto the road bed. Provisions that require effective soil cover and
mulching as needed to prevent erosion are included in SMR (21)).
6.2.2. 3 Organic Matter: Effects from Temporary Roads.
There would be 3.8 miles of temporary road built on approximately 5.5 acres (with no need for a
borrow site) having decreased duff and large woody material for a period of approximately 5-years
until the road is put to bed. Requirements include pulling the berm where duff and soil was
displaced and adding wood chips or mulch from landings and the adjacent project to supplement
loss of duff. Over the long-term these materials will contribute to future duff development. Roads
are often blocked using available large woody debris over the first 200 feet. Thus, SMR (21) is
included to retain some available large woody material for this purpose. As the temporary roads are
linear features, the adjacent trees are likely to add to downed wood presence across this feature over
the mid-term.
Comparison of Alternatives for Direct and Indirect Effects to Effective Soil Cover, Porosity
and Organic Matter from Temporary Roads
Alternative 1: Proposed Action
Loss of productivity would occur through detrimental compaction (porosity), loss of effective soil
cover, and loss of organic matter from temporary roads on 3.8 miles, over approximately 5.5 acres
until decommissioned. The road compaction is estimated to persist for about 5 years. Following use
they are sub-soiled, and any roadside berms with mineral soil is pulled back, drainage is provided to attain a
hydrologically neutral state (SMR 21). Sub-soiling lifts and fractures the soil rather than turning the soil, as
occurs when tilling. Most of these sub-soiled temporary roads start showing signs of some vegetative
recovery after 3 years. Effective soil cover and mulching requirements along with requirements to provide
drainage and pull berms allow these lands to be entered into productivity within a minimum of 8 years (5
years operation period and 3 years to begin vegetative recovery) but, may not achieve pre-existing
productivity levels for several more years.
Sagehen Project Soils Specialist Report January 16, 2013
41
Alternative 2: No Action
There are no proposed temporary roads under this alternative. Productivity will not be affected from
this action.
Alternative 3: Non - Commercial Funding
There are no proposed temporary roads under this alternative. Productivity will not be affected from
this action.
6.2.3 DIRECT AND INDIRECT EFFECTS SITE-SPECIFIC WATERSHED
RESTORATION
Site Specific Watershed Restoration
Within the proposed action the following two watershed improvements are proposed under
Alternative 1.
Road 11-5, Action 1: Approximately one mile of this road would be obliterated following its use
for vegetation treatment activities.
Road 11-5, Action 2: On the section of the 11-5 road which passes through the bottom end of a fen
the road and its associated culvert system would be removed and full restoration measures
improving the hydrology through the fen will be implemented.
6.2.3.1 Soil Porosity: Effects from Restoration Activities
The action described in the proposed action (Alternative 1) for Road 11-5, Action 1 and Action 2
would result in reduced compaction over 1.3 acres following re-contouring of the road bed. During
the restoration the equipment would be primarily contained within the existing road bed so there
would be little potential for expanding the existing compaction during construction. Any staging
area would occur over previously disturbed landings, or roads and would be restored by reducing
compaction where needed.
6.2.3.2 Effective Soil Cover: Effects from Restoration Activities
The action described above for Road 11-5, Actions 1 and 2 would result in short-term disturbance
and replacement of soil cover over 1.3 acres. As re-contouring of the road bed occurs under
Action1, mulch and large wood from the adjacent activity area would be applied to the re-contoured
landscape. Additional mulch would be applied where needed to control erosion as described under
SMR(22).
Road 11-5; Action 2, would incur a short term disturbance and replacement of soil cover over
approximately a tenth of an acre. Where feasible, adjacent vegetation would be used within the
activity area to acquire small plugs to supplement seeding and mulch (these sources would come
from non-sensitive areas outside of the fen within the activity area as shown on the Sagehen Project
Proposed Action Map 1). The timing of transplanting and provisions for effective soil cover is
nearly immediate in relation to re-configuring the landscape and providing mulch and planting.
Native vegetation would probably begin to re-establish within 1 year because of the inherent
moisture of the site. SMR (21) will be used to ensure soils are stabilized.
Sagehen Project Soils Specialist Report January 16, 2013
42
6.3.3. 3 Organic Matter: Effects from Restoration Activities.
It is estimated that in combination with the aspen treatment (conifer removal), the fen and wetland
soil and organic matter in the area surrounding the fen could be improved over approximately three
acres over the long term. This is based on the processes associated with wet anaerobic sites and
organic matter cycling as described in section 2.3.8 under Current Science and Monitoring.
Comparison of Alternatives for Direct and Indirect Effects to Effective Soil Cover, Porosity
and Organic Matter from Restoration Activities
Alternative 1: Proposed Action
Under the proposed action for Road 11-5 described above, approximately 300 feet of this road
which currently crosses through a fen and aspen stand, would be removed. Restoration actions
would be designed to restore porosity, effective cover and organic matter thus restoring productivity
over these acres in the long-term. It is estimated that in combination with the aspen treatment
(conifer removal), the fen and wetland soil and organic matter in the area surrounding the fen could
be improved over approximately three acres.
Alternative 2: No Action
There is no proposed restoration under this alternative. Productivity will not be affected from this
action.
Alternative 3: Non - Commercial Funding
There is no proposed restoration under this alternative. Productivity will not be affected from this
action.
Sagehen Project Soils Specialist Report January 16, 2013
43
7 CUMULATIVE EFFECTS
Cumulative effects are determined largely based on literature and monitoring results. For the soil
resource cumulative effects is the assessment of the direct and indirect effects of the proposed
action alternatives in context with the existing conditions. Detrimental cumulative effects to the soil
resources use the threshold metrics outlined under section 2.2: Management Directions, and
Standards and Guidelines. To have a potential effect on the indicator; productivity, the threshold in
degree and extent for the metrics (porosity effective soil cover and organic material) would first
need to be exceeded.
The cumulative effects assessment area for the soil resource is bounded in space within the
proposed activity areas, where a potential for soil disturbing activities take place. The analysis is
further bounded in time by the foreseeable future period during which effects of this project could
persist as detectable effects and may be short- term or long-term in nature. Past effects are
accounted for based on the existing conditions or present time, and reasonably foreseeable future
actions are those proposed actions assessed within this document. There are no other future
foreseeable actions in addition to the Sagehen Project within the resource activity area (unit)
boundaries. A larger history is provided in the disturbance layer in the Watershed Resource
Specialist Report. In general, cumulative soil effects are identified to have a potential negative
impact when data shows detrimental soil disturbance could exceed Forest Plan standards and
guidelines in terms of extent, severity and longevity.
Alternative 1: Cumulative Effects Determination Proposed Action.
Vegetation Management
Porosity
Areas with decreased porosity can remain on the landscape over the long-term and with each entry
can incrementally increase the degree and extent of the detrimentally affected area. However, the
proposed action is not predicted to exceed the standard and guideline #55 when BMPs/SMRs are
implemented. As presented in Science and Monitoring 2.3.2 above, the Herger Feinstein Quincy
Library Group studies provide two conclusions regarding detrimental effects from changes in
porosity measured as compaction: 1) most activity areas that exceed the standard post-treatment
start with a high compaction extent nearing the Forest LRMP standard, and 2) there was not a large
amount of change between pre-treatment and post-treatment compaction for most activity areas. For
the Sagehen Project S&G#55 is expected to be attained because: 1) existing levels of compaction
are considered to be moderate to low (well under the 15 percent threshold in extent), and 2) the
potential for incremental changes in degree (up to 10% decrease in porosity) do not necessarily
equate to an increase in extent of area that exceeds the threshold (in degree or extent).
Existing results from sampled activity areas show 33 percent of the activity areas sampled show no
detrimental compaction (10 percent decrease in porosity) and activity areas with detrimental
compaction ranged from a low of 3 percent to a high of 8 percent in extent. In addition, sub-soiling
(as mitigation for decreased porosity) improves infiltration and vegetative growth on these
previously compacted soils. The sub-soiling is typically completed on the heavy use areas (landings,
and skid trails converging at the landings) most likely to exceed the threshold.
Sagehen Project Soils Specialist Report January 16, 2013
44
The potential for a decrease in porosity (degree) can incrementally occur over small portions of the
activity area. Since no activity area is predicted to exceed the threshold in extent, an assessment of
risk to productivity based on texture is unnecessary. The proposed action alternative combined with
existing conditions support a conclusion that the extent of the impact is designed to meet S&G#55
and productivity would be maintained for porosity. There would be a potential for a small
incremental portion of 2,190 acres to decrease porosity (in degree) over the affected activity areas.
Effective Soil Cover
Existing conditions within activity areas have effective soil cover that meet the S&G #55, so no
areas of special concern were identified based on existing condition. Data from measured activity area
transects showed a range of 80 to 97 percent effective soil cover. No accelerated erosion or sediment
movement was observed on any proposed activity areas surveyed that would indicate a loss in soil
productivity.
The proposed action alternative combined with existing conditions support a conclusion that the
extent of the impact is designed to meet S&G#55 and productivity would be maintained for ESC.
There is the potential to reduce existing cover in degree and extent over small portions of activity
areas across 1,677 acres, but ESC would be maintained. Additionally, there would also be periods
of increased ESC during some intermediate steps on some units particularly for thinned areas
designated for grapple piling following thinning. There would also be potential increases in existing
ground cover over 976 acres in mastication units.
Because ground cover accumulates seasonally, the cumulative effect of reduced existing cover is
expected to be short lived. The proposed action alternative maintains productivity through effective
erosion control.
Organic Matter
Forest Duff
Transect results representative of the project area showed forest duff varied from 65 percent to 90
percent. Transect data for plantations in proposed activity area 46 have 85 percent duff. The transect
running through the uplands of previously treated areas in activity area 213 showed 65 percent duff.
Transects running along the western margin in activity area 213 showed 73 percent duff. Other
transects in proposed activity areas such as activity area 38 and 39 show 90 percent existing duff.
There is the potential to reduce existing duff levels in degree and extent over small portions of
activity areas after each entry on 2,654 acres. Of those acres there are 975 acres that are exposed to
variable potential increases in long-term duff development and the potential for disturbed duff is
further decreased where mastication occurs prior to thinning. Contrastingly, existing duff would be
reduced in degree and extent over small portions of activity areas following prescribed burning on
1,507 acres.
Upper layers of organic material, including branchwood, cones, and bark are quickly restored to the
forest floor in the years following implementation. Retention of soils duff in the early stages of
decomposition are added to over the long term through these processes. Undisturbed forest duff and
sites would maintain a minimum of 20 percent of the undisturbed forest duff evenly distributed
Sagehen Project Soils Specialist Report January 16, 2013
45
throughout the activity area; therefore, S&G #55 would be attained and cumulative effects to
productivity are not expected from the proposed actions related to reductions in existing duff.
Large Woody Material
The minimum observed average for activity area logs meet the 5 downed logs/acre criteria
described under existing conditions. The exception was in aspen restoration sites, however; these
areas are small and based on the site visit most have adequate downed wood or adequate attain
requirements for other woody material at a rate of 200 cubic feet to 800 cubic feet per acre in the
area. Additionally, wind fall after treatment in aspen stands is commonly observed (personal
observation) adding to the downed wood component one to three years following treatment. Areas
of heavy fuels will see areas with reduced downed wood within grapple pile units. While
underburning can reduce levels of existing large downed wood in upper decay classes, 993 acres
that will undergo underburning and another 80 acres that will undergo underburning only may
reduce some existing downed wood. However, following underburning the cycling of large downed
wood could be enhanced in some thinned and un-thinned units in areas where conifers are
negatively fire affected. This effect is predicted to be limited and there could be lag time before
snags fall and contribute to the large woody material. Current science suggests woody material may
not be as important to soil productivity as previously thought. Still the proposed action is expected
to enhance large woody material in some low volume areas, and since it is demonstrated that S&G
#55 would be attained for large woody material. No decrease in productivity would be expected
from reduction in large wood under the proposed action.
Temporary Roads
While it is recognized temporary roads disrupt productivity of the soils. The temporary roads may
extend beyond an activity area or serve more than one activity area and; therefore, cannot be tied
specifically to an activity area to assess general changes in productivity. However, loss of
productivity would occur through detrimental compaction (decreased porosity), loss of effective soil
cover, and loss of organic matter from temporary roads on 3.8 miles, over approximately 5.5 acres
until decommissioned. These lands would be re-entered into productivity within about 8 years (5
years operation period and 3 years to begin vegetative recovery) but may not achieve pre-existing
productivity levels for several more years.
Watershed Restoration
There would be approximately 1 mile of road template (approximately 4.5 acres) restored. An
existing road bed will be decommissioned, re-vegetated, and mulched. The restoration will allow
these lands to be available for re-entry into productivity. These lands outside of the restored fen
would be entered into productivity within about 8 years (5 years operation period and 3 years to
begin vegetative recovery) but, may not achieve the potential productivity levels for several more
years.
It is estimated that in combination with the aspen restoration treatment (conducted as conifer
removal), the fen, and wetland soil and organic matter in the area surrounding the fen, could be
improved over approximately three acres over the long term. This improvement is based on the
processes associated with wet anaerobic sites and organic matter cycling as described in section
2.3.8 under Current Science and Monitoring.
Sagehen Project Soils Specialist Report January 16, 2013
46
Alternative 2: Cumulative Effects Determination No Action Alternative.
No detrimental disturbance that would affect productivity is predicted to occur from the no action
alternative. No actions are proposed and existing conditions meet S&G#55. So there would be no
variation in existing trends for cumulative effects to the soil resource in severity or extent for
effective soil cover (erosion control), soil organic matter (forest duff or large woody material) or
porosity that would affect soil productivity or contribute to soil erosion.
Alternative 3: Cumulative Effects Determination Non -Commercial Funding.
Vegetation Management
Porosity
Areas with decreased porosity can remain on the landscape over the long-term and with each entry
can incrementally increase the degree and extent of the detrimentally affected area. However, the
proposed action is not predicted to exceed the standard when BMPs/SMRs are implemented. As
presented in Science and Monitoring 2.3.2 above, the Herger Feinstein Quincy Library Group
studies provide two conclusions regarding detrimental effects from changes in porosity as
compaction: 1) most activity areas that exceed the standard post-treatment start with a high
compaction extent nearing the Forest LRMP standard, and 2) there was not a large amount of
change between pre-treatment and post-treatment compaction for most activity areas. For the
Sagehen Project S&G#55 is expected to be attained because: 1) existing levels of compaction are
considered to be moderate to low (well under the 15 percent threshold in extent), 2) the potential for
incremental changes in degree (up to 10% decrease in porosity) do not necessarily equate to an
increase in extent of area that exceeds the threshold (in degree or extent).
Existing results from sampled activity area show 33 percent of the activity areas sampled show no
detrimental compaction (10 percent decrease in porosity) and activity areas with detrimental
compaction ranged from a low of 3 percent to a high of 8 percent in extent. In addition, sub-soiling
as mitigation for reduced porosity improves infiltration and vegetative growth in compacted soils.
This action is typically completed on the heavy use areas (landings, and skid trails converging at the
landings) most likely to exceed the threshold.
The potential for a decrease in porosity (degree) can incrementally occur over small portions of the
activity areas. Since no activity area is predicted to exceed the threshold in extent, an assessment of
risk to productivity based on texture is unnecessary. The proposed action alternative combined with
existing conditions support a conclusion that the extent of the impact is designed to meet S&G#55
and productivity would be maintained for porosity. There would be a potential for a small
incremental portion of 706 acres to decrease porosity (in degree) over the affected activity areas.
Effective Soil Cover
Existing conditions within activity areas have effective soil cover that meet the S&G #55, so no
areas of special concern were identified based on existing condition. Data from measured activity area
transects showed a range of 80 to 97 percent effective soil cover. No accelerated erosion or sediment
movement was observed on any proposed activity areas surveyed that would indicate a loss in soil
productivity.
Sagehen Project Soils Specialist Report January 16, 2013
47
The proposed action alternative combined with existing conditions support a conclusion that the
extent of the impact to soil resources is designed to meet S&G#55 and productivity would be
maintained for ESC. There is the potential to reduce existing cover in degree and extent over small
portions of activity areas after each entry on 1,195 acres, but ESC would be maintained. Out of the
1,195 acres, there would also be potential increases in existing ground cover over 706 mastication
acres with 661 of those acres exposed to underburning following mastication.
Because ground cover accumulates seasonally, the cumulative effect of reducing the existing cover
is expected to be short lived. The proposed action alternative maintains productivity through
meeting minimum ground cover requirements for effective erosion control.
Organic Matter
Forest Duff
Transect results representative of the project area showed forest duff varied from 65 percent to 90
percent. Transect data for plantations in proposed activity area 46 have 85 percent duff. The transect
running through the uplands of previously treated areas in activity area 213 showed 65 percent duff.
Transects running along the western margin in activity area 213 showed 73 percent duff. Other
transects in proposed activity areas such as activity area 38 and 39 show 90 percent existing duff.
Upper layers of organic material, including branchwood, cones, and bark are quickly restored to the
forest floor in the years following implementation. Retention of soils duff in the early stages of
decomposition are added to in the long term through this process. Undisturbed forest duff and sites
would maintain a minimum of 20 percent of the undisturbed forest duff evenly distributed
throughout the activity area; therefore, S&G #55 would be attained and cumulative effects to
productivity are not expected.
Large Woody Material
The minimum observed average for activity area logs meet the 5 downed logs/acre criteria
described under existing conditions. Areas of heavy fuels will see areas reduce existing downed
wood. Since current science suggests woody material may not be as important to soil productivity
as previously thought, and since the proposed actions are expected to meet minimum requirements
for large woody material and meet S&G #55 under Alternative 3. Cumulative effects to productivity
are not expected from this action alternative.
Summary
Maintained Productivity Area
For activity areas treated and not related to temporary roads or restoration under Alternative 1, and
for all activity areas under Alternative 3 the Standard and Guideline #55 is predicted to be met for
porosity, ESC and organic matter, over proposed activity areas, thus based on the direction for soils
laid out in the LRMP cumulative effects to productivity are not expected from the proposed actions
for fuels reduction and silvicultural vegetative activities.
Loss of Productivity
Sagehen Project Soils Specialist Report January 16, 2013
48
Under Alternative 1 activities associated with temporary roads will reduce productivity over the
mid-term on Loss of productivity would occur through detrimental compaction (decreased
porosity), loss of effective soil cover, and loss of organic matter from temporary roads on 3.8 miles,
over approximately 5.5 acres until decommissioned. These lands would be re-entered into
productivity within about 8 years (5 years operation period and 3 years to begin vegetative
recovery) but may not achieve pre-existing productivity levels for several more years. No
temporary roads are proposed under Alternative 3.
Restored Productivity
Under Alternative 1, there would be approximately 1 mile of road template with approximately 4.5
acres restored. An existing road bed will be decommissioned, re-vegetated, and mulched. The
restoration will allow these lands to be available for re-entry into productivity. These lands outside
of the restored fen would be entered into productivity within about 8 years (5 years operation period
and 3 years to begin vegetative recovery) but, may not achieve the potential productivity levels for
several more years. It is estimated that in combination with the aspen restoration treatment
(conducted as conifer removal), the fen, and wetland soil and organic matter in the area surrounding
the fen, could be improved over approximately three acres over the long term. No restoration
activities are proposed under Alternative 3.
Sagehen Project Soils Specialist Report January 16, 2013
49
6 REFERENCES
British Columbia, Ministry of Forests, December 1989, Developing Timber Harvesting
Prescriptions to Minimize Site Degradation- Interior Sites, Land Management Handbook,
Field Guide Insert.
Busse, M.D., C. Shestak, E. Knapp, G. Fiddler, and K. Hubbert. 2005. Lethal soil heating during
burning of masticated fuels: effects of soil moisture and texture. International Journal of
Wildand Fire. 2005. 14 267-276.www.publish.csiro.au/journals/ijwf.
Busse M, et.al. 2010. Soil Physical Properties Regulate Lethal Heating during Burning of Woody
Residues. Soil Sci. Soc. Am. J. 74:947–955. Published online 4 March 2010
doi:10.2136/sssaj2009.0322 Received 31 Aug. 2009
Campbell, G.S., J.D. Jungbauer, Jr., K.L. Bristow, and R.D. Hungerford. 1995. Soil temperature and
water content beneath a surface fire. Soil Sci. 159:363–374.
Debyle, N.V. 1985c. Wildlife. In: DeByle, N.V.; Winokur, R.P., eds. Aspen: ecology and
management in the western United States. GTR-RM-119. Fort Collins, CO: U.S.
Department of Agriculture, Forest Service, Rocky Mountain Forest and Range Experiment
Station: 135-152.
Frandsen, W.H., and K.C. Ryan. 1986. Soil moisture reduces belowground heat flux and soil
temperatures under a burning fuel pile. Can. J. For. Res. 16:244–248.
Gomez, G.A., Powers, R.F., Singer, M.J., Horwath,W.R., 2002. Soil compaction effects on growth
of young ponderosa pine following litter removal in California’s Sierra Nevada. Soil Sci.
Soc.Am. J. 66, 1334–1343.
Greacen, E.L., Sands, R., 1980. Compaction of forest soils. Areview. Aust. J. Soil Res. 18, 163–
189.
Hanes R. and Poff, R. 1989. Descriptive Legend for the Soil Survey of the Sagehen Area, Tahoe
National Forest Area, California.
Hartford, R.A.; Frandsen, W.H. 1992. When it’s hot, it’s hot … or maybe it’s not (surface flaming
may not portend extensive soil heating). International Journal of Wildland Fire. 2: 139–144.
Hubbert K., M. Busse, S. Overby, C. Shestak. USDA Forest Service, Pacific Southwest Research
Station, USDA Forest Service, Rocky Mountain Research Station.Poster Presentation.
http://www.fs.fed.us/psw/partnerships/tahoescience/r9_pile_burning_effects.shtml
Huffman, E.L. et.al. 2001. Strength and persistence of fire-induced soil hydrophobicity under
ponderosa and lodgepole pine, Colorado Front Range. Hydrol. Process. 15, 2877–2892
(2001) DOI: 10.1002/hyp.379.
Sagehen Project Soils Specialist Report January 16, 2013
50
Jury, W.A., Gardner, W.R., and Gardener, W.H. 1991. Soil Physics. John Wiley and Sons.
Powers, Robert F., David H. Alban, Gregory A. Ruark, Allan E. Tiarks, Charles B. Goudey, Jerry F.
Ragus, Walter E. Russell, 1989. Evaluating Timber Management Impacts on Long-Term
Soil Productivity: A Research and National Forest System Cooperative Study. On file, PSW
Redding.
Powers, Robert F., et.al. 2005. The North American Long-Term Soil Productivity Experiment:
Findings from the first decade of research. Forest Ecology and Management 220 (2005) 31-
50.
Powers, Robert. 2005, Presentation USDA FS Soils Conference, Redding CA. 2005. Unpublished.
Shepperd, Wayne D. et.al. 2006. Ecology, Management, and Restoration of Aspen in the Sierra
Nevada Final Report, Collaborative Work Agreement between USDA, Forest Service Lake
Tahoe Basin Management Unit and USDA, Forest Service, Rocky Mountain Research
Station January 20, 2006.
Spears et.al. 2003. The influence of decomposing logs on soil biology and nutrient cylcling in old
growth mixed coniferous forest in Oregon, U.S.A. Can. J. For. Res. 33: 2193–2201 (2003)
Stephens, S. 2001. Fire history differences in adjacent Jeffry pine and upper montane forests in the
eastern Sierra Nevada. International Journal of Wildland Fire 10, 161-167.
Thomas, Jack W. 1979. Wildlife Habitats in Managed Forests: The Blue Mountains of Oregon and
Washington. USDA Forest Service Ag. Handbook No. 553.
HFQLG, 2011. 2010 HFQLG Soil Monitoring Report, Feburary 2011. Unpublished.
HFQLG, 2008. 2007 HFQLG Soil Monitoring Report, January 2008. Unpublished.
HFQLG, 2006. 2005 HFQLG Soil Monitoring Report, March 2006. Unpublished.
Knapp, E. et al. 2011. Behavior and effects of prescribed fire in masticated fuelbeds. International
Journal of Wildland Fire 20,932-945.
Page-Dumroese D. S., Martin F. Jurgensen, Allan E. Tiarks, Felix Ponder, Jr., Felipe G. Sanchez,
Robert L. Fleming, J. Marty Kranabetter, Robert F. Powers, Douglas M. Stone, John D.
Elioff, and D. Andrew Scott. 2006. Soil physical property changes at the North American
Long-Term Soil Productivity study sites: 1 and 5 years after compaction. Can. J. For. Res.
36: 551–564.
Plotnikoff, M., Schmidt, M., Bulmer, C., and Curran, M. 1999. Forest productivity and soil
conditions on rehabilitated landings: interior British Columbia. Extension Note 40. British
Columbia Ministry of Forests, Research Branch, Victoria, B.C.
USDA Forest Service 1090. Soil erosion hazard rating. Soil and Water Conservation Handbook,
CH.50, R-5 FSH2509.22, R5 Amend. 2. PSW Region, Vallejo, California.
Sagehen Project Soils Specialist Report January 16, 2013
51
USDA Forest Service 1987. Forest position statement Siskiyou National Forest. Forest management
team notes of May 27, 1987. (unpublished report on file at Grants Pass, Oregon).
USDA Forest Service, Tahoe National Forest. 1990. Land and Resource Management Plan. Pacific
Southwest Region, USDA Forest Service. Nevada City, CA.
USDA Forest Service, 1994. Soil Survey, Tahoe National Forest Area California. Pacific Southwest
Region, USDA Forest Service in cooperation with USDA Soil Conservation Service and
Regents of the UC Agricultural Experiment Station.
USDA Forest Service. 1999. Eight Eastside Rivers Wild and Scenic River Study Report and Final
Environmental Impact Statement Record of Decision. Nevada City, CA: U.S. Department of
Agriculture, Forest Service, Pacific Southwest Region, Tahoe National Forest and Lake
Tahoe Basin Management Unit.
USDA Forest Service, 2001, Water Quality Protection on National Forests in the Pacific Southwest
Region: Best Management Practices Evaluation Program, 2003-2007. Pacific Southwest
Region, Vallejo, California.
U.S.D.A. Forest Service (NT&DP) National Technology &Development Program. December 2008.
0877 1807—SDTDC. December 2008.Soil and Water Road-Condition Index Desk
Reference U.S. Department of Transportation Federal Highway Administration.
USDA FS PSWR (United States Deparment of Agriculture Forest Service Pacific Southwest
Region). 2004. Sierra Nevada Forest Plan Amendment Final Environmental Impact
Statement Record of Decision. Region 5, Vallejo, CA.
USDA Forest Service PSWR 2009, Water Quality Protection on National Forests in the Pacific
Southwest Region: Best Management Practices Evaluation Program, 2003-2007. Pacific
Southwest Region, Vallejo, California.
USDA Forest Service, RMRS. 2012. A comprehensive guide to fuel management practices for dry
mixed conifer forests in the northwestern United States. Gen. Tech. Rep. RMRS-GTR-292.
Fort Collins, CO: U.S. Department of Agriculture, Forest Service, Rocky Mountain
Research Station. 331 p.
USDA Forest Service, Tahoe National Forest. 2012. Silviculture Specialist Report. Sagehen Project
Tahoe National Forest. Truckee Ranger District. Unpublished. May 9th, 2012
Valette, J.-C., V. Gomendy, J. Maréchal, C. Houssard, and D. Gillon. 1994. Heat transfer in soil
during very low-intensity experimental fi res: The role of duff and soil moisture content. Int.
J. Wildland Fire 4:225–237.
Valiant, Nicole, UC Berkeley 2008: Sagehen Experimental Forest Past, Present, and Future: An
Evaluation of the Fireshed Assessment Process
Sagehen Project Soils Specialist Report January 16, 2013
52
Weingart, B. 2007. Retional Forester’s Letter to Forest Supervisors: Use of R5 Soil Management
Handbook, R5 Suplement No. 2509, 18-95-1, February 5, 2007.
Young D. 2005, Presentation USDA FS Soils Conference, Redding CA. 2005. Unpublished.
3332
31
6 54
7 8 9
161718
N A T I O N A L
SI E
RR
AV
I LL
ET
RU
CK
EE
S A G E H E N H I L L S
R i v e r
RO
AD
S A G E H E N
S a g e h e n
Spring
GagingStation
Univ of CalifWildlife Exper Sta
7084
7104
6738
BM6210
6518
6708
6502
6688
6424
6650
BM6173
6596
6395
BM6506
BM 6555
BM6681
6986
11-10
89-36
89-34
89-38
89-36
8989-36
260
878-1
89-4007-10
878-2
351
89-36-12
89-36-12-3
89-36-12-3-5
87-34-16
89-35-5
89-34-20
89-36-4-4
89-36-4
89-36-4-6
89-36-10
89-36-8
89-36-4-2
89-40-20-15
89-40-20
89-40-20
89-40-20-10
07-10-50
89-36-4-8
14 13
11 12
12
3536
S I E R R A V I L L E
T R U C K E E
R A N G E R
R A N G E R
D I S T R I C T
D I S T R I C T
S I E R R A C ON E V A D A C O
L A K E
Ind
ep
en
de
nc
e
SecretMeadow
GagingStation
Sa g e h e n
C r e e k
S A G E H E N R O A D
SAGEHEN CG
7122
7214
7357
7188
6839
7416
7078
7080
7696 7722
350-25
350
351
351-10
351
11-2
1111
11-4
11-6
11-6
1111-8
11-10
11-10
11-10
11-10-2
11-6-6
11-6-7
11-6-411-6-6-2
11-6-2
11-5
11-5-2
46
87
213
36
282
10085
163
90
7376
99
34
98
35
80
156
89
6191
33 3839
47
47
|ÿ89
FtE
JtF
FtE
FtF
FrE
JtF
FrE
FrE
FrE5
WaF
JtE
FtE
SiE
SiE
WdF
FtF
JtE
FtE
FtE
JtESiE
FtESiE
SiE
FtF
FtF
FtF
FrE5
JtE
JtE
JtE
JwF
WeE
JtE
JtE
FtF
SiE
SiE
TtF
FvEFvE
FrF6
AQB
FvEFtE
FmE
SiE
AQB
FvE
TtF
FvE
TbE
FvE
FtE
WeE
FtE
WdF
FvE
AQB
AQB
FTEA
USDA Forest ServiceTahoe National Forest
Truckee Ranger District
Sagehen Project
December 14, 2012
Soils Map 1Alternative 1
0 0.5 10.25
Miles
Scale = 1:24,000Data Source: Tahoe National Forest Geospatial Database.Projection: UTM Zone 10, NAD83, GRS 1980.This map is reproduced from geospatial informationprepared by USDA Forest Service. Using GIS productsfor purposes other than those for which they wereintended may yield inaccurate or misleading results. Forest Service reserves the right to correct, update, modify or replace GIS products without notification.
"Legend.
AQBFmEFrEFvEFrE5FrF6FtEFTEAFtF
.
.JtEJtFJwFSiETbETtFWaFWdFWeE
*Reference: USDA Forest Service, 1994. Soil Survey,Tahoe National Forest Area, California. Pacific Southwest Region, USDA Forest Service in cooperation with USDA Soil Conservation Service and Regents of the UC Agricultural Experiment Station.**Tahoe National Forest Erosion Hazard Rating: Soil type WeE is moderate, all other soil types within project units are High.
National ForestNon-National Forest
Unit Boundary & Number98
High Erosion Hazard Rating**
Order III Soils Series*
Moderate Erosion Hazard Rating**
3332
31
6 54
7 8 9
161718
N A T I O N A L
SI E
RR
AV
I LL
ET
RU
CK
EE
S A G E H E N H I L L S
R i v e r
RO
AD
S A G E H E N
S a g e h e n
Spring
GagingStation
Univ of CalifWildlife Exper Sta
7084
7104
6738
BM6210
6518
6708
6502
6688
6424
6650
BM6173
6596
6395
BM6506
BM 6555
BM6681
6986
11-10
89-36
89-34
89-38
89-36
8989-36
260
878-1
89-4007-10
878-2
351
89-36-12
89-36-12-3
89-36-12-3-5
87-34-16
89-35-5
89-34-20
89-36-4-4
89-36-4
89-36-4-6
89-36-10
89-36-8
89-36-4-2
89-40-20-15
89-40-20
89-40-20
89-40-20-10
07-10-50
89-36-4-8
14 13
11 12
12
3536
S I E R R A V I L L E
T R U C K E E
R A N G E R
R A N G E R
D I S T R I C T
D I S T R I C T
S I E R R A C ON E V A D A C O
L A K E
Ind
ep
en
de
nc
e
SecretMeadow
GagingStation
Sa g e h e n
C r e e k
S A G E H E N R O A D
SAGEHEN CG
7122
7214
7357
7188
6839
7416
7078
7080
7696 7722
350-25
350
351
351-10
351
11-2
1111
11-4
11-6
11-6
1111-8
11-10
11-10
11-10
11-10-2
11-6-6
11-6-7
11-6-411-6-6-2
11-6-2
11-5
11-5-2
46
282
10076
9998
6191
47
47
|ÿ89
JtF
FrE
FrE
SiE
FtF FtE
FtE
FtF
FtF
FtF
FrE5
FtF
FvEFvE
FrF6
AQB
FvEFtE
FmE
AQB
FvE
FtE
FtE
AQB
AQB
FTEA
USDA Forest ServiceTahoe National Forest
Truckee Ranger District
Sagehen Project
December 14, 2012
Soils Map 2Alternative 3
0 0.5 10.25
Miles
Scale = 1:24,000Data Source: Tahoe National Forest Geospatial Database.Projection: UTM Zone 10, NAD83, GRS 1980.This map is reproduced from geospatial informationprepared by USDA Forest Service. Using GIS productsfor purposes other than those for which they wereintended may yield inaccurate or misleading results. Forest Service reserves the right to correct, update, modify or replace GIS products without notification.
".
AQBFmEFrEFvEFrE5FrF6FtEFTEAFtFJtFSiE
*Reference: USDA Forest Service, 1994. Soil Survey,Tahoe National Forest Area, California. Pacific Southwest Region, USDA Forest Service in cooperation with USDA Soil Conservation Service and Regents of the UC Agricultural Experiment Station.
**Tahoe National Forest Erosion Hazard Rating: All soil types within Alternative 3 project units are High.
National ForestNon-National Forest
Unit Boundary & Number98
High Erosion Hazard Rating**
Order III Soils Series*Legend