solar farms: design & construction solar farm construction on distribution in the carolinas ¾...
TRANSCRIPT
![Page 1: Solar Farms: design & construction solar farm construction on distribution in the Carolinas ¾ Characteristics – Primary voltage (12 kV, 23 kV, etc.) at the POI/PCC – Range from](https://reader031.vdocuments.net/reader031/viewer/2022020319/5d1aaa2288c993656e8c4778/html5/thumbnails/1.jpg)
Impacts to utility distribution systemsSolar Farms: design & construction
John W. Gajda, P.E.
Duke Energy
Manager, DER Operations Support
![Page 2: Solar Farms: design & construction solar farm construction on distribution in the Carolinas ¾ Characteristics – Primary voltage (12 kV, 23 kV, etc.) at the POI/PCC – Range from](https://reader031.vdocuments.net/reader031/viewer/2022020319/5d1aaa2288c993656e8c4778/html5/thumbnails/2.jpg)
Agenda
– North Carolina’s unique situation, which is coming to a state
near you
– Typical solar farm characteristics
– Recent solar farm experiences, investigations, and solutions
– Where do we go from here?
2
![Page 3: Solar Farms: design & construction solar farm construction on distribution in the Carolinas ¾ Characteristics – Primary voltage (12 kV, 23 kV, etc.) at the POI/PCC – Range from](https://reader031.vdocuments.net/reader031/viewer/2022020319/5d1aaa2288c993656e8c4778/html5/thumbnails/3.jpg)
North Carolina: 2nd in nation in solar capacity additions
3
![Page 4: Solar Farms: design & construction solar farm construction on distribution in the Carolinas ¾ Characteristics – Primary voltage (12 kV, 23 kV, etc.) at the POI/PCC – Range from](https://reader031.vdocuments.net/reader031/viewer/2022020319/5d1aaa2288c993656e8c4778/html5/thumbnails/4.jpg)
Interconnection Queue:Duke & Progress in North Carolina
4
Cancelled Connected Open
UnderConstruction
GrandTotal
DEC 1,019 477 624 149 2,269DEP 5,618 1,126 3,929 631 11,304GrandTotal 6,637 1,604 4,552 780 13,573
As of June 30, 2016, in NC, Duke Energy:• has connected over 1,600 MW of solar
generation• received requests for over 13,000 MW of
interconnections• has 780 MWs of 3rd party projects under
construction• is constructing facilities and system upgrades
approaching $400,000 per project, averaging six months to complete.
Interconnected MWs
Interconnection Cost($ in Millions)
![Page 5: Solar Farms: design & construction solar farm construction on distribution in the Carolinas ¾ Characteristics – Primary voltage (12 kV, 23 kV, etc.) at the POI/PCC – Range from](https://reader031.vdocuments.net/reader031/viewer/2022020319/5d1aaa2288c993656e8c4778/html5/thumbnails/5.jpg)
Typical solar farm construction on distribution in the Carolinas
¾ Characteristics– Primary voltage (12 kV, 23 kV, etc.) at the POI/PCC– Range from 1 MW to 20 MW– In NC, 5 MW is a popular size– 8 acres to over 100 acres– Utility overhead facilities– Solar farm overhead and underground facilities (primary voltage)– Solar farm transformers (pad mount), inverters, panels
5
![Page 6: Solar Farms: design & construction solar farm construction on distribution in the Carolinas ¾ Characteristics – Primary voltage (12 kV, 23 kV, etc.) at the POI/PCC – Range from](https://reader031.vdocuments.net/reader031/viewer/2022020319/5d1aaa2288c993656e8c4778/html5/thumbnails/6.jpg)
6
5 MW solar farmnear Maxton, NC
![Page 7: Solar Farms: design & construction solar farm construction on distribution in the Carolinas ¾ Characteristics – Primary voltage (12 kV, 23 kV, etc.) at the POI/PCC – Range from](https://reader031.vdocuments.net/reader031/viewer/2022020319/5d1aaa2288c993656e8c4778/html5/thumbnails/7.jpg)
7
5 MW solar farmnear Maxton, NC
~2000’
![Page 8: Solar Farms: design & construction solar farm construction on distribution in the Carolinas ¾ Characteristics – Primary voltage (12 kV, 23 kV, etc.) at the POI/PCC – Range from](https://reader031.vdocuments.net/reader031/viewer/2022020319/5d1aaa2288c993656e8c4778/html5/thumbnails/8.jpg)
8
5 MW solar farmnear Maxton, NC
Interconnectionat 22.86 KV
![Page 9: Solar Farms: design & construction solar farm construction on distribution in the Carolinas ¾ Characteristics – Primary voltage (12 kV, 23 kV, etc.) at the POI/PCC – Range from](https://reader031.vdocuments.net/reader031/viewer/2022020319/5d1aaa2288c993656e8c4778/html5/thumbnails/9.jpg)
9
5 MW solar farmnear Maxton, NC
POI/PCC
![Page 10: Solar Farms: design & construction solar farm construction on distribution in the Carolinas ¾ Characteristics – Primary voltage (12 kV, 23 kV, etc.) at the POI/PCC – Range from](https://reader031.vdocuments.net/reader031/viewer/2022020319/5d1aaa2288c993656e8c4778/html5/thumbnails/10.jpg)
10
5 MW solar farmnear Maxton, NC
• 22.86 kV• 12 poles• 360’ utility
OHD• 1500’ solar
farm OHD• Significant
underground cable
![Page 11: Solar Farms: design & construction solar farm construction on distribution in the Carolinas ¾ Characteristics – Primary voltage (12 kV, 23 kV, etc.) at the POI/PCC – Range from](https://reader031.vdocuments.net/reader031/viewer/2022020319/5d1aaa2288c993656e8c4778/html5/thumbnails/11.jpg)
11
Another example:
20 MW solar farmnear Maxton, NC
22.86 kV9 poles
![Page 12: Solar Farms: design & construction solar farm construction on distribution in the Carolinas ¾ Characteristics – Primary voltage (12 kV, 23 kV, etc.) at the POI/PCC – Range from](https://reader031.vdocuments.net/reader031/viewer/2022020319/5d1aaa2288c993656e8c4778/html5/thumbnails/12.jpg)
12
Another example:
20 MW solar farmnear Maxton, NC
22.86 kV9 poles
![Page 13: Solar Farms: design & construction solar farm construction on distribution in the Carolinas ¾ Characteristics – Primary voltage (12 kV, 23 kV, etc.) at the POI/PCC – Range from](https://reader031.vdocuments.net/reader031/viewer/2022020319/5d1aaa2288c993656e8c4778/html5/thumbnails/13.jpg)
Fault event at solar farm causes customer disruption
13
Industrial customer on adjacent feeder suffers multiple process disruptions, twice over several weeks
Caused by fault events at 20 MW solar farm
![Page 14: Solar Farms: design & construction solar farm construction on distribution in the Carolinas ¾ Characteristics – Primary voltage (12 kV, 23 kV, etc.) at the POI/PCC – Range from](https://reader031.vdocuments.net/reader031/viewer/2022020319/5d1aaa2288c993656e8c4778/html5/thumbnails/14.jpg)
14
20 MW solar farmsite inspection, after second occurrence
dip pole “B” (7th pole)
fault evidence
![Page 15: Solar Farms: design & construction solar farm construction on distribution in the Carolinas ¾ Characteristics – Primary voltage (12 kV, 23 kV, etc.) at the POI/PCC – Range from](https://reader031.vdocuments.net/reader031/viewer/2022020319/5d1aaa2288c993656e8c4778/html5/thumbnails/15.jpg)
15
20 MW solar farm, at dip pole “B”:
• C (left) phase fault, developed into phase-to-phase fault
• occurred twice in 15 days
Primary issues identified:• clearances at stress
cones• terminations
![Page 16: Solar Farms: design & construction solar farm construction on distribution in the Carolinas ¾ Characteristics – Primary voltage (12 kV, 23 kV, etc.) at the POI/PCC – Range from](https://reader031.vdocuments.net/reader031/viewer/2022020319/5d1aaa2288c993656e8c4778/html5/thumbnails/16.jpg)
A looming issue?
¾ This experience raised awareness of MV construction at solar farms– Exposure:
• >200 solar farms (≥ 1 MW) in Duke Energy Progress• Average size = 4.4 MW• Total = 926 MW
¾ Duke then initiated “investigative inspections” of 8 sites– results mixed, but not reassuring
16
![Page 17: Solar Farms: design & construction solar farm construction on distribution in the Carolinas ¾ Characteristics – Primary voltage (12 kV, 23 kV, etc.) at the POI/PCC – Range from](https://reader031.vdocuments.net/reader031/viewer/2022020319/5d1aaa2288c993656e8c4778/html5/thumbnails/17.jpg)
17
No lightning arresters on any of the 3 dip poles
![Page 18: Solar Farms: design & construction solar farm construction on distribution in the Carolinas ¾ Characteristics – Primary voltage (12 kV, 23 kV, etc.) at the POI/PCC – Range from](https://reader031.vdocuments.net/reader031/viewer/2022020319/5d1aaa2288c993656e8c4778/html5/thumbnails/18.jpg)
18
At one site, none of the connections were greased
![Page 19: Solar Farms: design & construction solar farm construction on distribution in the Carolinas ¾ Characteristics – Primary voltage (12 kV, 23 kV, etc.) at the POI/PCC – Range from](https://reader031.vdocuments.net/reader031/viewer/2022020319/5d1aaa2288c993656e8c4778/html5/thumbnails/19.jpg)
19
Lockwashers?
![Page 20: Solar Farms: design & construction solar farm construction on distribution in the Carolinas ¾ Characteristics – Primary voltage (12 kV, 23 kV, etc.) at the POI/PCC – Range from](https://reader031.vdocuments.net/reader031/viewer/2022020319/5d1aaa2288c993656e8c4778/html5/thumbnails/20.jpg)
20
Terminator installed incorrectly.
![Page 21: Solar Farms: design & construction solar farm construction on distribution in the Carolinas ¾ Characteristics – Primary voltage (12 kV, 23 kV, etc.) at the POI/PCC – Range from](https://reader031.vdocuments.net/reader031/viewer/2022020319/5d1aaa2288c993656e8c4778/html5/thumbnails/21.jpg)
21
Reverse dip through wetlands. No arrester protection for terminations.
Messenger wire for fiber is not bonded at all 3 poles (possible induced voltage).
![Page 22: Solar Farms: design & construction solar farm construction on distribution in the Carolinas ¾ Characteristics – Primary voltage (12 kV, 23 kV, etc.) at the POI/PCC – Range from](https://reader031.vdocuments.net/reader031/viewer/2022020319/5d1aaa2288c993656e8c4778/html5/thumbnails/22.jpg)
22
Underground primary cable neutral bonded to very small wire. Weak link.
![Page 23: Solar Farms: design & construction solar farm construction on distribution in the Carolinas ¾ Characteristics – Primary voltage (12 kV, 23 kV, etc.) at the POI/PCC – Range from](https://reader031.vdocuments.net/reader031/viewer/2022020319/5d1aaa2288c993656e8c4778/html5/thumbnails/23.jpg)
23
Switch is grounded with separate ground.Pole ground and switch ground should be commonly bonded.
![Page 24: Solar Farms: design & construction solar farm construction on distribution in the Carolinas ¾ Characteristics – Primary voltage (12 kV, 23 kV, etc.) at the POI/PCC – Range from](https://reader031.vdocuments.net/reader031/viewer/2022020319/5d1aaa2288c993656e8c4778/html5/thumbnails/24.jpg)
24
Metal base of switch extends half way over deadend insulator.
Extension link needed.
![Page 25: Solar Farms: design & construction solar farm construction on distribution in the Carolinas ¾ Characteristics – Primary voltage (12 kV, 23 kV, etc.) at the POI/PCC – Range from](https://reader031.vdocuments.net/reader031/viewer/2022020319/5d1aaa2288c993656e8c4778/html5/thumbnails/25.jpg)
25
12.7kV MCOV rating on arrester
(system here is22.86 kV/13.2 kV)
![Page 26: Solar Farms: design & construction solar farm construction on distribution in the Carolinas ¾ Characteristics – Primary voltage (12 kV, 23 kV, etc.) at the POI/PCC – Range from](https://reader031.vdocuments.net/reader031/viewer/2022020319/5d1aaa2288c993656e8c4778/html5/thumbnails/26.jpg)
26
Deadend caps installed with no arresters.
Flat to flat connections ungreased.
![Page 27: Solar Farms: design & construction solar farm construction on distribution in the Carolinas ¾ Characteristics – Primary voltage (12 kV, 23 kV, etc.) at the POI/PCC – Range from](https://reader031.vdocuments.net/reader031/viewer/2022020319/5d1aaa2288c993656e8c4778/html5/thumbnails/27.jpg)
27
H0 bushing ground strap installed, but no connection to ground bus in transformer.
![Page 28: Solar Farms: design & construction solar farm construction on distribution in the Carolinas ¾ Characteristics – Primary voltage (12 kV, 23 kV, etc.) at the POI/PCC – Range from](https://reader031.vdocuments.net/reader031/viewer/2022020319/5d1aaa2288c993656e8c4778/html5/thumbnails/28.jpg)
28
Only 1 crimp on every connector.
Manufacture requires 4 compressions.
![Page 29: Solar Farms: design & construction solar farm construction on distribution in the Carolinas ¾ Characteristics – Primary voltage (12 kV, 23 kV, etc.) at the POI/PCC – Range from](https://reader031.vdocuments.net/reader031/viewer/2022020319/5d1aaa2288c993656e8c4778/html5/thumbnails/29.jpg)
Solar farm construction quality:solutions
¾ Solar farm MV facilities are an “extension” of the utility distribution system– need “compatibility”
¾ Require consideration of utility’s construction specifications as “minimum” requirements in Interconnection Agreement
¾ Inspection & Commissioning program– 3-4 weeks before startup, inspection
& “punchlist”– “final inspection” at time of
interconnection commissioning– Soon to include inverter inspection
29
![Page 30: Solar Farms: design & construction solar farm construction on distribution in the Carolinas ¾ Characteristics – Primary voltage (12 kV, 23 kV, etc.) at the POI/PCC – Range from](https://reader031.vdocuments.net/reader031/viewer/2022020319/5d1aaa2288c993656e8c4778/html5/thumbnails/30.jpg)
Wait, inverter inspections too?In 2015, Duke asked Advanced Energy (not the inverter mfr) to inspect 41 PV sites.
30
# sites compliant
% sites compliant
Documentation: inverter type and number matches interconnection request 19 46%
Documentation: transformer type and number matches interconnection request 14 34%
Sites compliant with the interconnection protection settings specified in the Interconnection Agreement 40 98%
Sites compliant with the interconnection protection settings specified in the Interconnection Agreement 9 22%
Sites which do not have a possible open phase detection issue, based on inverter manufacturer’s documentation 23 56%
Sites meeting NEC-required AC ground fault protection or fault detection (NEC 230.95, 250.21b) 16 39%
![Page 31: Solar Farms: design & construction solar farm construction on distribution in the Carolinas ¾ Characteristics – Primary voltage (12 kV, 23 kV, etc.) at the POI/PCC – Range from](https://reader031.vdocuments.net/reader031/viewer/2022020319/5d1aaa2288c993656e8c4778/html5/thumbnails/31.jpg)
31
• One site has 830 kVA transformers, each with two secondary windings rated for 415 kVA each
• At one of the transformers, an 830 kVA inverter is wired to one of the two 415 kVA secondary windings, overloading the transformer
Yet there’s more…
![Page 32: Solar Farms: design & construction solar farm construction on distribution in the Carolinas ¾ Characteristics – Primary voltage (12 kV, 23 kV, etc.) at the POI/PCC – Range from](https://reader031.vdocuments.net/reader031/viewer/2022020319/5d1aaa2288c993656e8c4778/html5/thumbnails/32.jpg)
32
At one site, improperly rated 600 V insulated wire is used on 690 V inverter AC output circuits
Yet there’s more…
![Page 33: Solar Farms: design & construction solar farm construction on distribution in the Carolinas ¾ Characteristics – Primary voltage (12 kV, 23 kV, etc.) at the POI/PCC – Range from](https://reader031.vdocuments.net/reader031/viewer/2022020319/5d1aaa2288c993656e8c4778/html5/thumbnails/33.jpg)
Where do we go from here?
¾ Duke Energy is working with Advanced Energy (Raleigh NC), Dominion, and other NC utilities to raise the bar– Underway: development of a North Carolina model inspection and commissioning
standard for utility-scale solar farms
¾ Duke Energy building a robust inspection & commissioning program– periodic inspection requirements also being developed
33
![Page 34: Solar Farms: design & construction solar farm construction on distribution in the Carolinas ¾ Characteristics – Primary voltage (12 kV, 23 kV, etc.) at the POI/PCC – Range from](https://reader031.vdocuments.net/reader031/viewer/2022020319/5d1aaa2288c993656e8c4778/html5/thumbnails/34.jpg)
Contact information
John W. Gajda, P.E.Manager, DER Operations SupportDuke Energy411 Fayetteville Street, NC16Raleigh, NC 27601T: 919-546-4697
34