Some implementations of the control systems Control system for water deaeration, beer filtration and distribution to packaging line, Nigerian Breweries, Heineken group, Ota, Nigeria. For Corosys Proc 2 Siemens S7-300 PLC's, 2 Siemens MP377 operator panels, about 500 I/O. I've made all system, electrical supervision, comissioning. Piotr Nieoczym Page 1

Upload: piotr-nieoczym

Post on 14-Aug-2015

33 views

Category:

Documents


0 download

TRANSCRIPT

Some implementations of the control systems

Control system for water deaeration, beer filtration and distribution to

packaging line, Nigerian Breweries, Heineken group, Ota, Nigeria.

For Corosys Proc• 2 Siemens S7-300 PLC's,

• 2 Siemens MP377 operator panels,

• about 500 I/O.

I've made all system, electrical supervision, comissioning.

Piotr Nieoczym Page 1

Brewhouse control system, Nigerian Breweries, Heineken group, Ota,

Nigeria.• 3 x S7-400 PLC's,

• 2 x Siemens MP377 operator panels,

• about 2500 I/O.

I made part of the PLC programming, electrial works co-supervision, commissioning.

Piotr Nieoczym Page 2

Control system for medical waste incinerator

• PLC - S7 300,

• about 300 I/O,

• Operator stadion - ASIX.

All design and commissioning have been made by me.

Piotr Nieoczym Page 3

Control system for pneumatic transport of copper sulphate, Copper Smelter in

Głogów

• Schneider Quantum PLC,

• Magelis – operator panel, about. 300 I/O.

All design and commissioning have been made by me.

Piotr Nieoczym Page 4

Installation of ovens gas cleaning anode, copper smelter in Legnica• 2 xSiemens S7-400 PLCs,

• 2 x Siemens MP-270 panels,

• 2 x operator stations Wonderware Intouch SCADA,

• about. 1500 I/O.

I made the SCADA system, comissioning.

Piotr Nieoczym Page 5

Installation of gas purification in Mahhindra Ugine Steel Company Ltd, Jagdish

Nagar, India• Schneider Electric Premium PLC,

• Operator stadion based on ASIX,

• about 500 I/O.

I made SCADA system, comissioning.

Piotr Nieoczym Page 6

Control system for washing machine factory building Amica Wronki SA• 17 x S7-300 PLCs,

• 2 x opeator stations Wonderware Intouch SCADA,

• about 6500 I/O.

I made SCADA system and a part of PLC software, comissioning.

Piotr Nieoczym Page 7

Recovery of rhenium from acid slurry, Ecoren SA in Glogow• Schneider Electric Premium PLC

• 3 operator stations Wonderware InTouch,

• about 400 I/O.

I made SCADA system and part of PLC program, comissioning.

Piotr Nieoczym Page 8

Piotr Nieoczym Page 9

Installation for the production of zinc oxide and the installation of flue

gas from rotary kilns (wet), Boleslaw Recycling in Bukowno

• 7 x S7-400 PLCs,

• 1x Redundant WinCC server

• 8 x operator stations Siemens WinCC 6.0 SCADA,

• about 5000 I/O.

I made SCADA system and part of PLC program, comissioning.

Piotr Nieoczym Page 10

Piotr Nieoczym Page 11

Dust extraction system for ZRP kolumn Stack gases Hindistan Zinc ltd.

Chanderia Led Zinc Smelter India.

• Alarn Bradley RsLogix 500 PLC,

• 2 operator stations Rsview 32 SCADA,

• about 600 I/O.

I made SCADA system, comissioning.

Piotr Nieoczym Page 12

Control System for ash removing and sorbent feed in a 460 MW power

plant in Bedzin• 8 x S7-300 PLCs,

• 6 x operator panels MP 270

• 2 x oparator stations Asix SCADA,

• about 3000 I/O.

I made SCADA system and PLC programs for all PLC’s, comissioning.

Piotr Nieoczym Page 13

Flue gas desulphurisation (dry scrubing) for copper smelter „Głogów” • 11 x PLC controllers Schneider Electric Quantum,

• about 5000 I/O,

• 10 x operator panels - PanelMate 3000,

• 2 x operator stations MonitorPro SCADA.

I’ve made most of PLC’s programs and all applications for operator panels, commissioning.

Piotr Nieoczym Page 14